Big Thunder Wind Park

Size: px
Start display at page:

Download "Big Thunder Wind Park"

Transcription

1 Big Thunder Wind Park Frequently Asked Questions Prepared for: Horizon Wind Inc. Prepared by: M.K. Ince and Associates April 14, 2011

2 FREQUENTLY ASKED QUESTIONS Project Details and Description 1. Where is a map showing the project area? Where is a map showing the project turbines, roads and electrical taplines? The Site Plan, appended to the Design and Operations Report, is a high resolution map showing the project area and all turbine locations, roads, electrical lines and other equipment. Smaller maps are included in many other reports. The Project Description Report has two maps which show the original study area, turbine locations, access roads, electrical taplines and switching stations that constitute the project. 2. How much area will be cleared for the project? The amount of land cleared to facilitate the construction and operation of the turbines and associated infrastructure will be kept to an absolute minimum. The property proposed for the wind farm spans almost 8,000 hectares; the total cleared area for all turbines, roads, substations, electrical lines, and laydown areas will be around hectares. An area of approximately 70 m by 70 m will be cleared around the base of each turbine to be used for turbine assembly and equipment laydown areas. The turbine tower base will have a diameter of 7.5 m; hence the area occupied by the base itself will be 44 m 2 approximately (See Environmental Screening Report Section 2.4.4). Staging areas will also be cleared in two locations; these are shown in the Site Plan included in Appendix B of the Design and Operations Report. These staging areas will be approximately 30 m by 60 m. Access roads approximately 6 metres wide will be cleared, though roads will be wider than 6 metres at corners and bends. For the overhead electrical tapline, which will connect the project to the electrical distribution grid, a right of way approximately 12 metres in width will be cleared. For more information on land clearing, its effects and proposed mitigation measures please see Section of the Environmental Screening Report. Section 2.4 of the Project Description Report details the project location and includes the various maps. 3. Describe the electrical lines that will carry electricity generated by the wind turbines? What voltage will these lines carry? What type of poles will they be mounted on? Within the project area where the turbines are located, internal electrical taplines (overhead cables) will collect the electricity produced by the turbines and carry it to the switching stations. These electrical collector lines will be mounted on guyed wooden poles. Overhead lines will then connect the turbines to the electricity grid in Neebing and Thunder Bay. These interconnection taplines will be low voltage (25 kv) and will be constructed in two stages. The tapline routes will be within existing electrical line rightof-ways and will be placed on existing hydro poles for the majority of line length. For the remaining line length auger holes will be drilled using a truck-mounted auger and the hydro poles will be installed using a crane. M.K. Ince and Associates 1

3 Phase 1 of the electrical tapline will extend 600 m north from the wind park area to connect to the existing electricity grid within the Municipality of Neebing at Loch Lomond Road. Phase 2 taplines will follow existing electrical poles and existing hydro corridors through the City of Thunder Bay, crossing the Kaministiquia River underground. The total length of the electrical tapline will be approximately 16 km. Line voltages will be 25 kv, equal that of the local distribution lines. Details on electrical facilities and interconnections can be found in Sections Section 2.4.5, and of the Environmental Screening Report. The tapline route is illustrated in Figure 2-2 of the Environmental Screening Report as well as the Site Plan appended to the Design and Operations Report. 4. What make and model of turbine is being used? The model of turbine to be installed is the Enercon E82, with a nameplate capacity of 2.0 MW per turbine. These turbines will have a tower height of 98 m and blade length of 41 meters. The maximum height of the wind turbines will be 139 m. For more details please see Section of the Project Description Report which describes in detail the wind turbine technology to be utilized for this project. Table 2-1 in Section gives the wind turbine specifications. The Wind Turbine Specifications Report provides additional technical details related to the Enercon E82 turbine model. 5. Why are you changing the nameplate capacity and turbine model for the project? Horizon Wind is increasing the nameplate capacity for each turbine from 1.5MW to 2MW. This will not increase the height of the turbines. The increase of the nameplate capacity will permit Horizon Wind to build the first 16.5MW with only 8 turbines instead of the proposed 11. In other words, Horizon will be able to build a given amount of MW with fewer turbines. The model of turbine is Enercon E-82, with a 2.0 MW capacity, with a maximum height of 139 metres. 6. What is happening with the City litigation? What will happen to the 4 turbines currently under dispute? Legal representatives for Horizon Wind and the City of Thunder Bay have been working through a process to achieve a positive resolution for both parties. The goal was to find a win-win situation for both parties. On Monday, April 11 the City ratified a vote allowing the project to advance. Two of the four turbines will remain as part of the proposed Big Thunder Wind Park project. Horizon Wind Inc. and the City of Thunder Bay have reached a compromise regarding the other two turbines. The compromise involves finding alternative locations for the remaining two turbines. Project Proponents and Timeline 7. Who are the proponents of the Big Thunder Wind Park? What history/experience does this company have with wind energy projects? M.K. Ince and Associates 2

4 The proponent of the Project is Horizon Wind Inc., as general partner of Horizon Wind LP, of which Horizon Legacy is a parent company. Horizon Wind LP is 100% Canadian owned, and is privately owned by the Zwig Family. Horizon has over 50 years of experience in the development, construction, financing, management, and operation of major infrastructure projects in Canada, including wind energy projects. Horizon, through its subsidiaries, completed the construction, financing, and commissioning of two wind projects in the 6MW Maryvale Windfarm in Antigonish, Nova Scotia, and the 4.5MW Uilk Windfarm in Pipestone, Minnesota. Additionally, Horizon is developing a 50 MW wind farm in the Rimouski region of Quebec, as well as projects in other regions of Ontario and Northern United States. Please note that Horizon Wind LP should not be confused with Horizon Wind Energy in the U.S. There is no relationship between these two companies. 8. When was this project first proposed? At what point were the public engaged? What was the timeline of this project in terms of public consultation? On May 4 th 2006, a letter was sent to the City of Thunder Bay proposing to develop a wind farm on Big Thunder. On February 22 nd 2008, a Notice of Commencement of Environmental Screening was published in the Thunder Bay Source Newspaper. Since that time there have been 6 public meetings, and continuous information transfer between stakeholders, and the proponents and the authors of the Renewable Energy Application (REA) reports. 9. Why was this particular area chosen (over any others in Ontario) for this project? What criteria are met by this area? The location of the wind turbines is based on constraints such as proximity to environmental features (sensitive areas), wind resource (wind speeds), accessibility, and proximity to electrical lines. These have all informed the placement of the wind turbines, and the initial placement of the wind turbines has been changed in light of input from the public and by factoring in these constraints. 10. What is the lifetime of the project? What will happen at the end of the project s life? The anticipated life of the project is 25 years. At the end of the useful life of the wind turbines, typically 25 years, the old wind turbines will be either refurbished or decommissioned. New foundations and turbines could potentially be installed at this time. Any expansion of the Wind Park (addition of turbines) within these 25 years, or extension of the life of the project would be subject to the Renewable Energy Application or the relevant legislative process in place at the time. 11. How much has the project been altered since it was first proposed? A number of changes have been made since the project was first proposed. Turbines locations have changed to increase distance between the wind farm and local residences, and more recently, a change in turbine model has occurred which will allow for the construction of fewer turbines to meet the contractual obligations of Horizon Wind Inc. under their Feed-in-Tariff contract. Additional studies and commitments have also been made by Horizon Wind to provide a better understanding of the impacts of the development and offset those impacts where they occur. 12. What authorisations/permits are necessary for this project to proceed? M.K. Ince and Associates 3

5 The Big Thunder Wind Park project requires permits from Federal, Provincial, and Municipal levels of government. These are listed in Section 1.3 of the Project Description Report. 13. What is the status of the REA application? The Renewable Energy Approval process is underway, in April 2011 the REA reports will be release to the public and we will invite the population to comment on it and give their input. The REA reports will be posted on our website in April 2011, public consultation will start again with a Notice of Open House to be issued in April Also, mail & notices, Aboriginal notices will be send to everyone registered to our mailing list. 14. How have the questions/requests/comments from the public been dealt with since the project was first brought to the attention of the public? s, letters and phone calls received from the public were logged and all concerns were tabulated up until August 24 th Questionnaires were distributed during Public Meetings and collected and compiled after meetings concluded. While not all concerns can be fully resolved for all stakeholders, Horizon took all reasonable measures to respond to the concerns raised during stakeholder consultations. The consultation period will be extended in April 2011 to get further input from members of the public on the proposed development. All comments received will be logged and the summarized in the Public Consultation Report which will be submitted to the Ministry of Environment along with the Final REA application. 15. Why are you having this open house? Where do I send my comments and concerns now? The MOE is committed to maintaining an open dialogue with the public and Ontario s electricity stakeholders in the implementation of renewable energy projects under the REA process. Horizon is responsible to meet the community to share their intentions, to give the community the opportunity to make comments and get their support. The public commenting period will re-open in April Questions and comments can be submitted online, by , mail, or by attending our next open houses to be held on May 17 th and 18 th. Contact details for each are noted below. Furthermore comments can also be submitted after the Final REA Application has been made through the MOE consultation process. info@bigthunderwindpower.ca Online Feedback: Mailing address: Nhung Nguyen, Horizon Wind 2300 Yonge St. Suite 801, P.O. Box 2300 Toronto, ON. M4P 1E4 Project Impacts 16. How will the turbines affect the view shed from the various vantage points in Thunder Bay? M.K. Ince and Associates 4

6 The Big Thunder Wind Park will be visible from many vantage points around the project area depending on weather conditions. The Visual Impact Assessment Report provides a map showing where and how many turbines will be visible in areas around the project area. Also included in the report are photo-realistic renderings of what the turbines will look like from various viewpoints around the project area. Further information on the visual impacts of the Big Thunder Wind Park can be found in Section of the Environmental Screening Report. 17. Will the turbines be lit? For safety reasons, seven of the eighteen wind turbines will be lit. Lighting will be used only as required by Transport Canada for air navigation and safety purposes. These lights will warn pilots in low-flying aircraft to avoid the turbine blades. White lights will be used during the daytime and red flashing lights during nighttime. The minimum number of flashes per minute and the briefest flash duration permissible by Transport Canada will be used to minimize light pollution and impacts to bird populations. Section of the Environmental Screening Report outlines turbine lighting procedures. A list of wind turbines which are lit are given in Table 3-2 of the Design and Operations Report. 18. Are there any possible health effects? a) Shadow Flicker - How will it affect humans? - Can it affect epilepsy sufferers? - How has shadow flicker been modelled for this project? - How accurate/conservative are the model predictions? Shadow Flicker (SF) occurs when the blades from a wind turbine pass between an observer and the sun. As a wind turbine rotates, the shadow cast by the blades can cause a flicker for an observer, which is considered an annoyance by some people. One important aspect to the impact of shadow flicker is its frequency; the number of times per second a turbine blade crosses between an observer and the sun. Research indicates that frequencies between 2.5 and 20 Hz (cycles per second) cause annoyance and can even trigger epileptic problems for a certain portion of the population [Burton, Sharpe, Jenkins, Bossanyi, Wind Energy Handbook. West Sussex: John Wiley & Sons Ltd, 2001]. Shadow Flicker was modelled for the Big Thunder Wind Park, using conservative modelling assumptions, and no home was found to experience shadow flicker for more than 19 hours and 4 minutes total per year. The model was created based on site-specific information, geographical and topographical data, solar angles for Thunder Bay, and historical sunshine statistics from Environment Canada's Thunder Bay weather station. The Shadow Flicker Report contains information on shadow flickerhow it was modelled and a map showing the extent of shadow flicker. The map shows the modelled amounts of shadow flicker in the nearby area which recreational users could expect. Conservative modelling assumptions were made which included clear skies every day, constant turbine rotation, and a bare ground (no trees or obstructions). Given these assumptions, the actual amount of flicker that a person would experience will be less than that modelled (especially if they are hiking in tree covered paths). M.K. Ince and Associates 5

7 b) Noise - What sound levels will the turbines emit? - Does the model take into account cliffs and rock faces along the Nor Westers? - Is there a health risk from the sound that the turbines will emit? - What about low frequency sound and infrasound? - How accurate/conservative are the model predictions? When modeled according to the ISO method Acoustics Attenuation of Sound During Propagation Outdoors, all noise levels at points of reception in the vicinity of the Big Thunder Wind Park are predicted to be within the most restrictive MOE noise level limit of 40 dba (equivalent to the sound level inside a quiet room). Figure 6-1 in the Noise Impact Assessment Report shows noise isolines, valid for all wind speeds, indicated on a map along with all receptors and wind turbines. Please note that the noise modelling was undertaken for worst-case conditions; for example no shielding or damping from vegetation or buildings was included, worst-case meteorological conditions were assumed, and ground porosity was underestimated. Section 3.3 of the Noise Impact Assessment Report lists these assumptions resulting in conservative modelling of noise impacts. The noise model does not take into account the cliffs and rock faces along the Nor Westers, as these are not expected to influence noise effects. Exposed rock cliffs are located north of the wind park area, between turbines and noise receptors. Due to the relative orientation of wind turbines, cliffs and noise receptors, no amplification or echo effects are expected. For echoes to be produced, noise sources and receptors must be on the same side of a cliff to allow sound waves to bounce back from cliff faces. As the cliff faces are located between wind turbines and noise receptors, and are oriented to face noise receptors, these effects are not expected. A Noise Impact Assessment Report was produced although it was not required as part of the Renewable Energy Approvals process for this project, since the minimum separation distance between any Big Thunder turbine and point of reception exceeds 850 m (O. Reg. 359/09 Section 55). The noise impacts of the project are also discussed in Section of the Environmental Screening Report Please refer to the noise impact assessment report for details of the noise modelling carried out, and the residences for which noise impacts were modeled. With regards to infrasound, or low frequency sound that cannot be detected by the human ear, available scientific evidence to date does not demonstrate a direct causal link between wind turbine noise and adverse health effects. The report Infrasound from Wind Turbines- Fact, Fiction or Deception was published as a Special Issue for Canadian Acoustics, and is written by a noise and vibration consultant Goeff Leventhall from the United Kingdom, it can be found at this link: WT-CanAcoustics2.pdf For more information on this and other health concerns, please see Section of the Environmental Screening Report. c) Is there a health risk from Power Frequency Electric and Magnetic Fields emanating from the power lines? Based on currently-available information, electro-magnetic fields and interference are not considered a serious health concern. The level of EMF (low frequency magnetic field) from the switching stations and turbines at the Wind Park are negligible for public health compared to daily exposure levels. EMF M.K. Ince and Associates 6

8 from overhead electrical taplines will be similar in levels to those experienced by existing overhead distribution lines in the neighbouring community. ELF (low frequency electric field) fields vary in strength according to the voltage of the device in question the higher the voltage, the stronger the field. ELF will be generated by the distribution lines, switching stations, transformers and generators at the Big Thunder Wind Park. The strength of these fields decreases quickly with distance. No significant ELF fields are expected to occur at ground level beneath the turbines. Transformers will step-up voltage from the turbines to 25 kv for interconnection to the existing electrical distribution grid at that voltage. There will be low-voltage (25 kv) overhead electrical taplines used in this project. Both the electric and magnetic fields for the 25 kv overhead cables are expected to be of a magnitude similar to those from the existing electrical distribution lines in the neighbouring community. Section of the Environmental Screening Report gives more details on the potential effects of electro-magnetic radiation on public health. 19. What is ice throw? Is it a risk to safety? During certain conditions ice can build up on wind turbine rotor blades, in a similar way to how ice can build up on stationary structures such as transmission towers, communications towers and buildings. At times, ice can fall from the blades to the ground. From a stationary turbine, ice falls directly downward, and thus presents a similar hazard to ice falling from communication towers or transmission lines. From a rotating turbine, blade ice can be thrown and can present a hazard to people in the vicinity of the turbines. Ice throw only presents a hazard during the specific number of days per year that the weather conditions lend themselves to ice accretion on the turbine blades. A recent study, Recommendations for Risk Assessment of Ice Throw and Blade Failure in Ontario (Garrad Hassan Canada, 2007) found that for an average Ontario site, the risk of a fixed dwelling situated 250 m from a turbine struck by ice fragments is equivalent to 1 event in 300 years. The risk to an individual being struck in the vicinity of the dwelling is equivalent to 1 event in 500,000 years. Considering that all turbines in the Big Thunder Wind Park will be over 4 times this distance (over 1.1 km) away from existing dwellings, and the nearest vacant lot is 1075 m from the nearest turbine, the probability of injury due to ice thrown is extremely small. Turbines will be equipped with sensors to detect ice buildup and cease operation if ice accretion occurs. Additionally, signs warning of the potential for ice fall or ice throw during the winter months will be posted along public trails within the vicinity of the wind turbines. Signs will also be posted along access roads to warn the public of the potential danger of falling ice. For more details on the potential effects of ice throw and mitigation measures see Section of the Environmental Screening Report. 20. Is it possible to predict the effects of the wind park at a particular residence? Noise impacts have been modelled for all homes or points of reception (receptors) within 2000 metres of a wind turbine belonging to the project; please see the Noise Impact Assessment Report for details. Additional receptors that lie more than 2000 m away from the turbines were also included as well as five additional receptors at the Loch Lomond ski area. Photo images depicting proposed turbines from the Big Thunder Wind Park as viewed from several vantage points in Neebing and Thunder Bay were created by Cartographics M.K. Ince and Associates 7

9 of Guelph, Ontario, based on geo-referenced on-site photos. These photo images can also be found in the Visual Impact Assessment Report produced by Cartographics. The Shadow Flicker Report also contains computer generated images of the view at different orientations from 5 representative receptors in the project area. 21. Is the project expected to affect property values? If property values drop upon construction/operation of the wind park, will property owners be reimbursed? The Big Thunder Wind Park is not expected to have a negative effect on the values of properties in the surrounding area. In a study performed by Lawrence Berkley National Laboratory, the potential impact to property values of 24 different wind farms in nine US States was examined. No conclusive evidence to impacts on property prices was found using a variety of statistical models. The study covered sales of nearly 7,500 single family homes within 10 km of each wind farm and was unable to find any consistent, measureable, and statistically significant effect on home sale prices based on either view of the wind farms or distance from the wind farms. Section of the Environmental Screening Report discusses the potential effects of the project on property values in the surrounding area. In the six detailed studies quoted, no statistically significant link was found for changes to property values following construction of a wind farm. One of these studies carried out by the Canadian Wind Energy Association pertains to Municipality of Chatham-Kent in Southern Ontario. Wind farms in this municipality were not found to have a statistically significant negative effect on property values. Despite the evidence that wind farms have no statistically measurable effect on home prices, Horizon cannot guarantee property values within the viewshed of the Big Thunder Wind Farm. 22. Will electricity rates in the City of Thunder Bay and Municipality of Neebing be affected? Individual developers have no control over electricity rates; this is in the hands of Ontario Power Authority. 23. How will the local economy benefit from the project? Will there be any jobs created? If so, what type of jobs and will they be permanent? The project is expected to inject $15 million into the local economy; this figure pertains to the estimated construction cost to be spent locally on labour and equipment but does not include the turbines themselves. The injection of $15 million into the Ontario economy will lead to an increase in employment. Horizon expects 30 jobs to be created directly during construction of the Big Thunder Wind Park, and three permanent jobs during operation of the wind park. Lease payments for use of the land on which the project is located will provide consistent income for the City of Thunder Bay. In addition, property taxes from the project will also provide consistent income to the Municipality of Neebing for the lifetime of the project. Please see Section of the Environmental Screening Report for more details on the socio-economic impacts of the project. 24. Will the project affect tourism in the area? Wind turbines are still relatively new to Thunder Bay District and thus there is a potential for the Big Thunder Wind Park to attract local tourists. It is not, however, expected to M.K. Ince and Associates 8

10 draw tourists from elsewhere in the province. It is also possible that some tourists who visit nearby natural areas may be deterred by the adjacent development of the wind park. The perceived effect of turbines on the landscape is highly subjective. While some people may consider turbines to be a detriment to the landscape, others may find them attractive and interesting. Section of the Environmental Screening Report discusses the potential effects of the project on tourism in the local area and possible mitigation strategies. 25. Will there be any blasting of rock during the construction of the project? What are the potential effects of blasting? Blasting may occur at individual turbine sites during construction. Any required blasting will be scheduled to minimize noise effects during non-daylight hours. Following best practices, Horizon will assess and monitor the condition of wells and structures within 150m of the blasting location. 26. How will the wildlife be affected? (a) Birds Section of the Environmental Screening Report discusses the species of birds that may be affected by the project, and the methods used to survey and monitor their populations through four seasons. Details of the Big Thunder Avian Study are included in the Avian Impact Assessment Report in Appendix D of the Environmental Screening Report. Also included in Appendix E is a review of historical bird observations for the project area. Section of the Environmental Screening Report discusses the potential effects on birds and mitigation measures. The most significant risk factor to avian species associated with the Big Thunder Wind Park relates to the high density of Peregrine Falcon nesting sites in the region surrounding the project. Though no Peregrine Falcon nest sites exist within 1km of any proposed wind turbine, the Ontario Ministry of Natural Resources and Horizon Wind Inc. are consulting on studies of Peregrine Falcon usage of the area where the Big Thunder Wind Park is proposed. The Peregrine Falcon is protected under the Endangered Species Act (ESA). Consultation with the Ontario Ministry of Natural Resources Thunder Bay District Office is ongoing to determine whether a Section 17 permit under the Endangered Species Act may be required for the project due to the high concentration of Peregrine Falcons nesting near the project area. This is discussed in detail in Section of the Environmental Screening Report and in the Natural Heritage Records Review Report. More details and mitigation measures can also be found in Sections and of the Environmental Screening Report, and the Avian Impact Assessment Report in Appendix E of the Environmental Screening Report. (b) Bats Section of the Environmental Screening Report gives details of bat species that may be affected by the project and how bat populations and activities at the site were monitored. Section of the Environmental Screening Report discusses potential effects of the project on bats and mitigation measures. (c) Plants M.K. Ince and Associates 9

11 With regards to flora that may be affected by the project, sugar maple trees, though not a rare species, is a species of interest to the local community and concern was raised over potential clearing activities. If any sugar maple trees need to be cleared during construction, an equal number of sugar maple trees will be replanted by Horizon nearby. Squaretop Mountain is an International Biological Program (IBP) site and an Area of Natural and Scientific Interest (ANSI) located in the northwest corner of the large project study area. Square Top Mountain covers 260 hectares and includes the largest sugar maple forest in Northwestern Ontario. All proposed infrastructure and construction or operation activities for the Big Thunder Wind Park are at least 2 km away from the nearest boundary of the Squaretop Mountain ANSI, therefore no disturbance to this area will occur. 27. Will the Loch Lomond ski area be affected? Wind turbines will be visible to skiers at Loch Lomond ski area, however the ski trails will remain accessible and their topography preserved. Please see Section of the Environmental Screening Report for more details. 28. Will there be any effects on TV/radio reception? The tower and blades of wind turbines can affect communication signals in certain situations. Generally FM (frequency modulated) signals are much more immune to this electromagnetic interference than AM (amplitude modulated) radio frequency (RF) signals. The effects of electromagnetic interference on FM signals have been simulated in a laboratory environment; the interference manifests as a hissing sound superimposed on the FM signal. Research conducted by Sengupta and Senior (1994) and Chignell (1986) concluded that the effects of wind turbine electromagnetic interference on FM reception is negligible, except within a few tens of metres from a wind turbine. Horizon will investigate any issues to communication signals that may arise. Project Rationale 29. Why build a wind farm at this location in North Western Ontario when there is a surplus of hydro power that is also green? Is another green energy source necessary? Individual developers have no control over transmission lines and provincial electricity supply and rates; this is determined by Ontario Power Authority. That said, the Big Thunder Wind Park project is necessary to help fill the gap between the current demand for power and the increasing demand in the next 25 years, as determined by Ontario Power Authority. Over the next 25 years many power plants may reach the end of their design life (this will also include wind farms) and will need to be either recommissioned or shut down. At that time more energy will be needed from clean sources to replace current power generation. The Ontario Ministry of Energy and Infrastructure state on their website: Today, Ontario s peak capacity is between 26,000 megawatts (MW) and 28,000 MW. Peak demand for electricity is expected to rise to 29,000 MW within 10 years and to 33,677 MW by To meet that demand, we need to refurbish, rebuild or replace almost 80 per cent of our installed generating capacity of more than 30,000 MW between now and 2025, as well as adding some new supply What this means is that 24,000 MW (80 per cent of 30,000) of electricity in Ontario needs to be replaced. The capacity of the proposed Big Thunder Wind Park is 27MW, which is a small contribution, but it has taken over 3 years to develop. M.K. Ince and Associates 10

12 Ontario is attempting to be the first jurisdiction in North America to eliminate its dependence on coal but it must be replaced by something else. Through the new Green Energy Act, Ontario has chosen to pursue a renewable-energy policy, recognizing that renewable energy will fuel the world's future economy and Ontario is planning to achieve a 10% target of its power from wind. 30. What are the advantages and disadvantages of this project? The project advantages and disadvantages are listed in Section 11 of the Environmental Screening Report. M.K. Ince and Associates 11

Welcome To The Public Open House For The Wainfleet Wind Energy Project August 24, 2010

Welcome To The Public Open House For The Wainfleet Wind Energy Project August 24, 2010 Welcome To The Public Open House For The Wainfleet Wind Energy Project August 24, 2010 Objectives of Open House: Introduce Wainfleet Wind Energy Inc. and IPC Energy. Present an overview of Wainfleet Wind

More information

Project siting. Lanfine. Wind resource assessment. Wind Power Project

Project siting. Lanfine. Wind resource assessment. Wind Power Project Project siting Wind resource assessment This assessment determines how much electrical energy can be extracted from the wind Meteorological towers are installed on site to measure wind speed and direction

More information

Big Thunder Wind Park

Big Thunder Wind Park Big Thunder Wind Park Big Thunder Wind Park is an eighteen turbine, twenty-seven megawatt project. The wind park has a price tag of 75-million dollars, and out of the total price, 15-million dollars will

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest What s Inside? Answers to On: NextBridge Infrastructure and the East-West Tie Project Electricity in Northern Ontario Land issues Routing Project approval process Health

More information

14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER

14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER Knockskae Wind Farm Environmental Statement Volume 2 Main Report 14-1 14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER 14.1 Introduction 14.1.1 This Chapter has been prepared by. It identifies and

More information

Big Thunder Wind Park

Big Thunder Wind Park Construction Plan Report DRAFT Prepared by: M.K. Ince and Associates Ltd. May 18, 2010 TABLE OF CONTENTS BIG THUNDER WIND PARK... 1 1 PROJECT OVERVIEW... 1 1.1 PROJECT SCHEDULE... 2 2 CONSTRUCTION ACTIVITIES...

More information

Additional information relevant to Section 8 is presented in Appendix E in Volume 2 of 3 of the EIS.

Additional information relevant to Section 8 is presented in Appendix E in Volume 2 of 3 of the EIS. 8. SHADOW FLICKER Additional information relevant to Section 8 is presented in Appendix E in Volume 2 of 3 of the EIS. 8.1 RECEIVING ENVIRONMENT Wind turbines, as with trees or any other tall structure,

More information

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017

OPEN HOUSE PROJECT OVERVIEW OPEN HOUSE NOVEMBER 16, :00-8:00 PM FALL 2017 FALL 2017 PROJECT OVERVIEW EDF EN Canada is proposing to develop, construct, and operate the Cypress Wind Power Project with 243.6 megawatts (MW) of generating capacity. The Project is south of Dunmore,

More information

We are here to:

We are here to: Welcome! We are here to: Provide an overview and update of the proposed wind energy project Introduce the Project team Review the wind project development process Answer your questions NextEra Energy Resources

More information

Theme Comment Response. All neighbours should be entitled to revenue sharing, not just those who have signed an option agreement with Suncor.

Theme Comment Response. All neighbours should be entitled to revenue sharing, not just those who have signed an option agreement with Suncor. The following table summarizes the comments provided during and after the October 3 rd, 2012 Public Meeting for the Suncor Energy Adelaide Wind Project (the Project) via the questionnaire and email. The

More information

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April 28 2016 Renewable Energy Systems (RES) In Canada for more than 12 years Family-owned company

More information

South Canoe Wind Project: Environmental Fact Sheet

South Canoe Wind Project: Environmental Fact Sheet South Canoe Wind Project: Environmental Fact Sheet Background The South Canoe Wind Project received Environmental Approval with Conditions on July 13th, 2012. South Canoe is a 102 MW wind energy project

More information

Whynotts Community Wind

Whynotts Community Wind Whynotts Community Wind Project Benefits Investing in Local Communities Local Community Education Once constructed, the project will fund The Whynotts Community Renewable Education Program. This program

More information

Pteragen Canada Inc.

Pteragen Canada Inc. Decision 2013-171 May 7, 2013 The Alberta Utilities Commission Decision 2013-171: Application No. 1608907 Proceeding ID No. 2181 May 7, 2013 Published by The Alberta Utilities Commission Fifth Avenue Place,

More information

Mohawk College Hamilton, ON. Project Description Report. Fennell Campus Wind Project

Mohawk College Hamilton, ON. Project Description Report. Fennell Campus Wind Project Mohawk College Hamilton, ON Fennell Campus Wind Project H336493-0000-07-124-0001 Rev. C September 24, 2010 Project Report Mohawk College Fennell Campus Wind Project September 24, 2010 Table of Contents

More information

Interim Results: Health and Safety Impacts from Large Scale Wind Turbines

Interim Results: Health and Safety Impacts from Large Scale Wind Turbines Interim Results: Health and Safety Impacts from Large Scale Wind Turbines Submitted by Janis Rod and Wendy Heiger Bernays Presented at the Special PAC Meeting (1pm, ) Scope of our work Objectives Provide

More information

ROCKY MOUNTAIN LAND USE INSTITUTE 17 th Annual Conference University of Denver Sturm College of Law March 6 7, 2008

ROCKY MOUNTAIN LAND USE INSTITUTE 17 th Annual Conference University of Denver Sturm College of Law March 6 7, 2008 ROCKY MOUNTAIN LAND USE INSTITUTE 17 th Annual Conference University of Denver Sturm College of Law March 6 7, 2008 LOCAL GOVERNMENT ZONING/REGULATORY ISSUES FOR WIND FARMS RAYMOND YOUNG Lidstone Young

More information

Welcome. Welcome to our Open House for the. Kent Hills Wind Farm Expansion

Welcome. Welcome to our Open House for the. Kent Hills Wind Farm Expansion Welcome Welcome to our Open House for the Kent Hills Wind Farm Expansion Please visit our displays providing information on this proposed expansion to New Brunswick s first wind farm. We have staff available

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest THANK YOU for attending this Open House We want to hear from you www.nextbridge.ca Purpose of the Open House We are here to provide you

More information

APPENDIX M COMMUNITY ENGAGEMENT

APPENDIX M COMMUNITY ENGAGEMENT APPENDIX M COMMUNITY ENGAGEMENT Project Benefits Millbrook Community Wind The Future is Green Provincial Energy Independence This project will be one of many steps to fulfill Nova Scotia s goal of 40%

More information

TABLE OF CONTENTS PAGE SECTION

TABLE OF CONTENTS PAGE SECTION TABLE OF CONTENTS SECTION PAGE 1.0 EXECUTIVE SUMMARY... 1 1.1 Project Description... 1 1.2 Project Applicant... 1 1.3 Summary of Project Purpose and Need... 2 1.4 Summary of Proposed Alternative... 2 1.5

More information

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #4

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #4 Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #4 Prepared for: Windlectric Inc. 2845 Bristol Circle Oakville ON L9H 7H7 Prepared by: Stantec Consulting Ltd.

More information

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT

Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT HIBERNIAN WIND POWER LIMITED Tullynahaw Wind Energy Project County Roscommon ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY September 2003 Report P04E311A-R2 Stephen Court, 18/21 St. Stephen's Green,

More information

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES SECTION 1601 Wind Energy Installation In any zoning district, a conditional use permit or building permit may be granted to allow a wind energy conversion

More information

Rumster Wind Energy Project

Rumster Wind Energy Project Rumster Wind Energy Project Report OSE3525 Appendix D Noise and Shadow Flicker Assessment Orkney Sustainable Energy Limited 6 North End Road Stromness Orkney KW16 3AG Telephone 01856850054 Facsimile 01856851199

More information

Section 11.01: Zoning Ordinance Subdivision 9.4: Utility and Communication Uses. 96 Chapter 11: Planning and Development

Section 11.01: Zoning Ordinance Subdivision 9.4: Utility and Communication Uses. 96 Chapter 11: Planning and Development 9.4 Utility and Communication Uses A. Wind Energy Conversion Systems (WECS) 1. Intent. The intent of this Subdivision is to promote safe, effective and efficient use of alternative energy sources and systems

More information

Environmental Impact Assessment

Environmental Impact Assessment The Project Hoben International Ltd proposes to develop a single 500kW wind turbine at their Manystones Lane site near Brassington. The turbine will be located approximately 350m to the south east of the

More information

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report Prepared for: Windlectric Inc. 2845 Bristol Circle Oakville ON L9H 7H7 Prepared by: Stantec Consulting Ltd.

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 2010-461 Oldman 2 Wind Farm Project September 24, 2010 ALBERTA UTILITIES COMMISSION Decision 2010-461: Oldman 2 Wind Farm Project Application No. 1605398 Proceeding ID. 293 September 24, 2010

More information

Appendix K Shadow Flicker Study

Appendix K Shadow Flicker Study Appendix K Shadow Flicker Study Shadow Flicker Assessment- Honeywood Final Report Submitted to: Geilectric 1850, Panama Street, Suite 501 Brossard (Québec) Canada J4W 3C6 Classification: Reference: Honeywood_ShadowFlickering

More information

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #3

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #3 Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #3 Prepared for: Windlectric Inc. 354 Davis Road, Oakville, ON L6J 2X1 Prepared by: Stantec Consulting Ltd.

More information

Welcome to our Open House!

Welcome to our Open House! Welcome to our Open House! Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If

More information

Noise Impact Assessment

Noise Impact Assessment APPENDIX C Noise Impact Assessment CBCL Limited Appendices NOISE IMPACT ASSESSMENT PUGWASH WIND FARM, NOVA SCOTIA Client Pugwash Wind Farm Inc. Contact Charles Demond Document No Issue B Status Classification

More information

Garvagh Glebe Wind Energy Project County Leitrim

Garvagh Glebe Wind Energy Project County Leitrim HIBERNIAN WIND POWER LIMITED & COILLTE Garvagh Glebe Wind Energy Project County Leitrim ENVIRONMENTAL IMPACT STATEMENT NON-TECHNICAL SUMMARY March 2003 Report P04J004 R3 Stephen Court, 18/21 St. Stephen's

More information

WILSON TOWNSHIP ZONING ORDINANCE AMENDMENT: WIND ENERGY

WILSON TOWNSHIP ZONING ORDINANCE AMENDMENT: WIND ENERGY WILSON TOWNSHIP ZONING ORDINANCE AMENDMENT: WIND ENERGY (ADD TO ARTICLE 2) WIND ENERGY DEFINITIONS: Ambient: Ambient is defined as the sound pressure level exceeded ninety (90) percent of the time. Anemometer:

More information

AMHERST ISLAND WIND ENERGY PROJECT PROPERTY LINE SETBACK ASSESSMENT REPORT. File No April Prepared for:

AMHERST ISLAND WIND ENERGY PROJECT PROPERTY LINE SETBACK ASSESSMENT REPORT. File No April Prepared for: PROPERTY LINE SETBACK ASSESSMENT REPORT File No. 160960595 April 2013 Prepared for: Windlectric Inc. 2845 Bristol Circle Oakville ON L6H 7H7 Prepared by: Stantec Consulting Ltd. Suite 1 70 Southgate Drive

More information

REPORT REF: SFAUSVICXXMOR.1 SHADOW FLICKER AND BLADE GLINT REPORT

REPORT REF: SFAUSVICXXMOR.1 SHADOW FLICKER AND BLADE GLINT REPORT REPORT REF: SFAUSVICXXMOR.1 SHADOW FLICKER AND BLADE GLINT REPORT MORTLAKE SOUTH WIND FARM SITE VICTORIA (AUSTRALIA) March 2016 Contents 1 Executive Summary... 3 2 Mortlake Site... 5 2.1 Site Location...

More information

WHO ARE WE? Willow Ridge Wind Project

WHO ARE WE? Willow Ridge Wind Project Willow Ridge WELCOME This is the Second Public Open House for the, where project staff are available to answer any questions and recieve input from attendees.this process is being undertaken as part of

More information

Wind Energy in Alberta: Sustainable Communities, Sustainable Environment > Communities, neighbours and wind energy facilities page 1

Wind Energy in Alberta: Sustainable Communities, Sustainable Environment > Communities, neighbours and wind energy facilities page 1 Workshop Discussion Paper Wind Energy in Alberta: Sustainable Communities, Sustainable Environment Communities, neighbours and wind energy facilities Summary Wind energy s nature as a safe and healthy

More information

Suncor Energy Adelaide Wind Power Project March 20, 2012 Public Meeting Comment Response Table

Suncor Energy Adelaide Wind Power Project March 20, 2012 Public Meeting Comment Response Table Suncor received a total of five written comments from the March 20, 2012 Public Meeting for the Suncor Energy Adelaide Wind Project (the Project). The following table provides an example of some of the

More information

EXCERPT FROM EMMET COUNTY ZONING ORDINANCE. A. Definitions For purposes of this section, the following definitions shall apply:

EXCERPT FROM EMMET COUNTY ZONING ORDINANCE. A. Definitions For purposes of this section, the following definitions shall apply: EXCERPT FROM EMMET COUNTY ZONING ORDINANCE SECTION 2102-16 WIND ENERGY SYSTEMS (WES S) 16. WIND ENERGY SYSTEMS (WES S) A. Definitions For purposes of this section, the following definitions shall apply:

More information

Coal Closure In Ontario

Coal Closure In Ontario MINISTRY OF ENERGY Coal Closure In Ontario August 2015 Purpose Ontario has experience in phasing out coal-fired electricity generation. This deck provides insight into Ontario s experience through a thorough

More information

Black Oak Getty Wind Farm

Black Oak Getty Wind Farm Noise Technical Report Black Oak Getty Wind Farm Stearns County, Minnesota January 19, 2016 Prepared for: Black Oak Wind, LLC Prepared by: HDR Engineering, Inc. 701 Xenia Avenue South, Suite 600 Minneapolis,

More information

EXECUTIVE SUMMARY. Supplemental Environmental Impact Statement Jericho Rise Wind Farm

EXECUTIVE SUMMARY. Supplemental Environmental Impact Statement Jericho Rise Wind Farm EXECUTIVE SUMMARY This (SEIS) has been prepared for the proposed Jericho Rise Wind Farm (the Project). LLC (the Applicant), a wholly owned subsidiary of EDP Renewables (EDPR), is proposing to construct

More information

Canadian Wind Energy Association Position on Setbacks for Large-Scale Wind Turbines in Rural Areas (MOE Class 3) in Ontario

Canadian Wind Energy Association Position on Setbacks for Large-Scale Wind Turbines in Rural Areas (MOE Class 3) in Ontario Canadian Wind Energy Association Position on Setbacks for Large-Scale Wind Turbines in Rural Areas (MOE Class 3) in Ontario September 28, 2007 i Table of Contents 1. Executive Summary...1 2. Introduction...2

More information

Willow Ridge Wind Project Frequently Asked Questions. Popular Questions Who is the developer of the proposed project?

Willow Ridge Wind Project Frequently Asked Questions. Popular Questions Who is the developer of the proposed project? Willow Ridge Wind Project Frequently Asked Questions Popular Questions Who is the developer of the proposed project? Algonquin Power Co./ Liberty Power Co. is the company proposing the project and, if

More information

1.0 INTRODUCTION 1.1 SUMMARY OF SEQRA PROCESS

1.0 INTRODUCTION 1.1 SUMMARY OF SEQRA PROCESS 1.0 INTRODUCTION This is prepared for the Jericho Rise Wind Farm (hereafter, the Project ) pursuant to the New York State Environmental Quality Review Act (SEQRA) and its implementing regulations, 6 NYCRR

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on March

More information

1. Description of and Rationale for Proposed Change

1. Description of and Rationale for Proposed Change Suite 500, 4342 Queen Street Niagara Falls, Ontario, Canada L2E 7J7 Tel. 905 374 5200 Fax: 905 374 1157 www.hatch.ca Nick Colella 2 St. Clair Avenue West Floor 12A Toronto, ON M4V 1L5 Dear Mr. Colella:

More information

Prepared for: Prepared by:

Prepared for: Prepared by: File No. 160960710 Prepared for: Suncor Energy Products Inc. 150 6 th Avenue SW Calgary AB T2P 3E3 Prepared by: Stantec Consulting Ltd. Suite 1-70 Southgate Drive Guelph ON N1G 4P5 Executive Summary Suncor

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22296-D01-2017 Hays Solar Power Plant June 7, 2017 Alberta Utilities Commission Decision 22296-D01-2017 Hays Solar Power Plant Proceeding 22296 Application 22296-A001 June 7, 2017 Published by

More information

Grand Valley Wind Farms Phase 3 Wind Project Wind Turbine Specification Report

Grand Valley Wind Farms Phase 3 Wind Project Wind Turbine Specification Report Grand Valley Wind Farms Phase 3 Wind Project Wind Turbine Specification Report Prepared for: Grand Valley 2 Limited Partnership 222 3rd Avenue Southwest, Suite 900 Livingston Place, South Tower Calgary

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on June

More information

PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL

PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL ENVIRONMENTAL IMPACT ASSESSMENT PROCESS PROPOSED WAAIHOEK WIND ENERGY FACILITY UTRECHT KWA-ZULU NATAL BACKGROUND INFORMATION DOCUMENT April 2014 (2 nd Edition) Project developer: South Africa Mainstream

More information

William Cundiff. From: Sent: To: Cc: Subject: Attachments: Bill, Steve, Bob,

William Cundiff. From: Sent: To: Cc: Subject: Attachments: Bill, Steve, Bob, William Cundiff From: Sent: To: Cc: Subject: Attachments: neexpansion@aol.com Tuesday, September 28, 2010 12:10 PM wcundiff@douglasma.org szisk@douglasma.org; pbrown@brown-brown-pc.com; info@americanprowind.com;

More information

SUNCOR ENERGY CEDAR POINT WIND POWER PROJECT DESIGN AND OPERATIONS REPORT. Attachment D. Property Line Setback Assessment

SUNCOR ENERGY CEDAR POINT WIND POWER PROJECT DESIGN AND OPERATIONS REPORT. Attachment D. Property Line Setback Assessment SUNCOR ENERGY CEDAR POINT WIND POWER PROJECT DESIGN AND OPERATIONS REPORT Attachment D Property Line Setback Assessment SUNCOR ENERGY CEDAR POINT WIND POWER PROJECT PROPERTY LINE SETBACK ASSESSMENT REPORT

More information

Renewable Energy Services Ltd.

Renewable Energy Services Ltd. Decision 1976-D01-2018 McLaughlin Wind Power Plant and Substation February 23, 2018 Alberta Utilities Commission Decision 1976-D01-2018 McLaughlin Wind Power Plant and Substation Proceeding 1976 Applications

More information

DIGBY WIND POWER PROJECT ENVIRONMENTAL ASSESSMENT Appendices APPENDIX F NOISE IMPACT STUDY

DIGBY WIND POWER PROJECT ENVIRONMENTAL ASSESSMENT Appendices APPENDIX F NOISE IMPACT STUDY DIGBY WIND POWER PROJECT ENVIRONMENTAL ASSESSMENT Appendices APPENDIX F NOISE IMPACT STUDY Sound Impact Assessment Digby Wind Power Project SKYPOWER CORP. Project No. 1030972. EXECUTIVE SUMMARY Project

More information

Summit Repower Siting Process - Update to August 23, 2016 and November 10, 2016 reports.

Summit Repower Siting Process - Update to August 23, 2016 and November 10, 2016 reports. Summit Repower Siting Process - Update to August 23, 2016 and November 10, 2016 reports. June 29, 2017 Introduction This document addresses the siting work outstanding as of the November 10 th, 2016 siting

More information

Summary of Proposed Changes to the Technical Guide to Renewable Energy Approvals

Summary of Proposed Changes to the Technical Guide to Renewable Energy Approvals Summary of Proposed Changes to the Technical Guide to Renewable Energy Approvals Purpose The Ministry of the Environment and Climate Change (MOECC) is proposing a number of revisions and updates to the

More information

Photomontages SECTION 10

Photomontages SECTION 10 Photomontages SECTION 10 10.1 Photomontages Photomontages have been prepared by Truescape Visual Communication to illustrate the likely location of the Collector Wind Farm turbines following construction.

More information

TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Initiative

TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Initiative REGION OF WATERLOO TRANSPORTATION AND ENVIRONMENTAL SERVICES Rapid Transit Initiative TO: Chair Jim Wideman and Members of the Planning and Works Committee DATE: FILE CODE: D10-20/RT SUBJECT: PROPOSED

More information

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018

Decision D The City of Calgary. Bonnybrook Cogeneration Expansion Project. May 17, 2018 Decision 22711-D01-2018 Bonnybrook Cogeneration Expansion Project May 17, 2018 Alberta Utilities Commission Decision 22711-D01-2018 Bonnybrook Cogeneration Expansion Project Proceeding 22711 Application

More information

Burnt Hill Wind Development

Burnt Hill Wind Development Report OSE3581 Appendix D Noise and Shadow Flicker Assessment Environmental Health Studies: Noise and Shadow Flicker Assessment 1 Summary results 1.1 Wind turbines can create two types of environmental

More information

NIAGARA REGION WIND FARM PROJECT

NIAGARA REGION WIND FARM PROJECT NIAGARA REGION WIND FARM PROJECT Community Liaison Committee Meeting 4 February 7, 2017 AGENDA Introductions & Meeting Structure Outline Review of Minutes CLC Meeting #3 Project Update Topics of Community

More information

C&B Alberta Solar Development ULC

C&B Alberta Solar Development ULC Decision 22781-D01-2017 Newell Solar Power Plant November 15, 2017 Alberta Utilities Commission Decision 22781-D01-2017 Newell Solar Power Plant Proceeding 22781 Application 22781-A001 November 15, 2017

More information

Ironstone Quarry Wind Energy Project Environmental Statement

Ironstone Quarry Wind Energy Project Environmental Statement Ironstone Quarry Wind Energy Project Environmental Statement Non Technical Summary April 2011 Introduction Waste Recycling Group (WRG) Ltd is seeking permission to construct and operate a four turbine

More information

Welcome. to the Community Meeting for the Niagara Region Wind Project. Thank you for coming!

Welcome. to the Community Meeting for the Niagara Region Wind Project. Thank you for coming! Welcome to the Community Meeting for the Niagara Region Wind Project Thank you for coming! In early September we will host the first Public Open House under We are happy to share information about this

More information

March 20, Mr. Corey Juhl Juhl Energy Development Inc th Street SE Pipestone, MN 56164

March 20, Mr. Corey Juhl Juhl Energy Development Inc th Street SE Pipestone, MN 56164 March 20, 2018 Mr. Corey Juhl Juhl Energy Development Inc. 1502 17 th Street SE Pipestone, MN 56164 Re: Acoustic and Shadow Flicker Studies Davison County Wind, LLC Dear Corey: Tech Environmental, Inc.

More information

Seven Generations Energy Ltd.

Seven Generations Energy Ltd. Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant January 17, 2018 Alberta Utilities Commission Decision 22976-D01-2018 Power Plant Exemption at Gold Creek Gas Plant Proceeding 22976

More information

Additional information relevant to Section 7 is presented in Appendix D in Volume 2 of 3 of the EIS.

Additional information relevant to Section 7 is presented in Appendix D in Volume 2 of 3 of the EIS. 7. NOISE & VIBRATION Additional information relevant to Section 7 is presented in Appendix D in Volume 2 of 3 of the EIS. 7.1 RECEIVING ENVIRONMENT 7.1.1 Monitoring Continuous noise monitoring was undertaken

More information

NIAGARA REGION WIND FARM PROJECT

NIAGARA REGION WIND FARM PROJECT NIAGARA REGION WIND FARM PROJECT Community Liaison Committee Meeting 4 February 7, 2017 AGENDA Introductions & Meeting Structure Outline Review of Minutes CLC Meeting #3 Project Update Topics of Community

More information

Technical Bulletin Six Required Setbacks for Wind Turbines

Technical Bulletin Six Required Setbacks for Wind Turbines Renewable Energy Approvals Technical Bulletin Six Required Setbacks for Wind Turbines as part of an application under O.Reg.359/09 Draft document posted for public comment on the Environmental Registry

More information

Appendix T BIWF Shadow Flicker Analysis

Appendix T BIWF Shadow Flicker Analysis Appendix T BIWF Shadow Flicker Analysis Shadow Flicker Impact Analysis for the Block Island Wind Farm Prepared for Deepwater Wind Block Island, LLC Prepared by 160 Federal Street Boston, MA 02110 May 2012

More information

Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet

Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet Project Description Canadian Niagara Power Inc. ( CNP ) proposes to replace two existing lattice steel towers (Queen Street

More information

methods consist of: activities of The physical the Project surveying; stockpiling; grading; piling and turbine delivery; distribution line; operation

methods consist of: activities of The physical the Project surveying; stockpiling; grading; piling and turbine delivery; distribution line; operation 3.0 SCOPE OF THE ASSESSMENT The following section provides the scope of the Project and its assessment as well as the used for the environmental assessment. methods 3.1 Scope of the Project and Assessment

More information

Wind Power Regulatory Process Review

Wind Power Regulatory Process Review Wind Power Regulatory Process Review Stakeholder Consultation Summary of Discussion September 28, 2012 The Alberta Utilities Commission Wind Power Regulatory Process Review Stakeholder Consultation Summary

More information

Town of Rensselaerville LOCAL LAW NO. 2 OF THE YEAR 2009

Town of Rensselaerville LOCAL LAW NO. 2 OF THE YEAR 2009 LOCAL LAW FILING NEW YORK STATE DEPARTMENT OF STATE 41 State Street, Albany NY 12231 Town of Rensselaerville LOCAL LAW NO. 2 OF THE YEAR 2009 A Local Law entitled Non-Commercial Wind Power Facilities Law

More information

APPENDIX R SHADOW FLICKER REPORT

APPENDIX R SHADOW FLICKER REPORT APPENDIX R SHADOW FLICKER REPORT Shadow Flicker Study Palo Alto Wind Energy Project - Palo Alto County, Iowa Prepared for: Palo Alto Wind Energy LLC One South Wacker Drive Suite 1800 Chicago, Illinois

More information

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5 CONTENTS 2. PROJECT DESCRIPTION 2-2 2.1 NEED FOR THE PROJECT 2 2 2.2 ABOUT THE PROPONENT 2 4 2.3 SITE SELECTION 2 4 2.4 OVERVIEW OF THE PROJECT 2 5 Figure 2.1: Provisional wind profile for the Jeffrey

More information

SOUTH BRANCH WIND FARM DECOMMISSIONING REPORT

SOUTH BRANCH WIND FARM DECOMMISSIONING REPORT SOUTH BRANCH WIND FARM DECOMMISSIONING REPORT Report 7 of 9 March 26, 2012 South Branch Windfarm Inc. 226 ½ James Street North, Unit A Hamilton, Ontario L8R 2L3 Tel: 905-528-1747 Fax: 866-203-6516 Email:

More information

Technical Requirements for for Wind Power Projects. James Murphy Manager, Project Development Ontario Sustainable Energy Association

Technical Requirements for for Wind Power Projects. James Murphy Manager, Project Development Ontario Sustainable Energy Association Technical Requirements for for Wind Power Projects James Murphy Manager, Project Development Ontario Sustainable Energy Association Technical Requirements Overview Acquiring Land Rights Wind Resource Assessment(s)

More information

AMHERST ISLAND WIND ENERGY PROJECT CONSULTATION REPORT. Appendix C. Project Notices

AMHERST ISLAND WIND ENERGY PROJECT CONSULTATION REPORT. Appendix C. Project Notices AMHERST ISLAND WIND ENERGY PROJECT CONSULTATION REPORT Appendix C Project Notices AMHERST ISLAND WIND ENERGY PROJECT CONSULTATION REPORT Appendix C1 Notice of Proposal to Engage in a Renewable Energy Project

More information

Wind power... can compete with other power generation options at good sites.

Wind power... can compete with other power generation options at good sites. Debunking the myths The Myth: Wind power is expensive The Facts: Wind power... can compete with other power generation options at good sites. Wind cannot compete with the cost of producing electricity

More information

Ohio Power Siting Board. Staff Investigation Report and Recommendation

Ohio Power Siting Board. Staff Investigation Report and Recommendation Ohio Power Siting Board Staff Investigation Report and Recommendation Case No.: 11-1995-EL-BGA Project: Amendment to Blue Creek Wind Farm Certificate of Environmental Compatibility and Public Need Applicant:

More information

Belle River Wind Project

Belle River Wind Project Belle River Wind Project Community Liaison Committee Meeting #3 May 25, 2017 MEETING SUMMARY Minutes prepared by: AECOM www.belleriverwind.com Page 1 of 11 Belle River Wind Project Community Liaison Committee

More information

COMMUNITY FUND AND INVOLVEMENT

COMMUNITY FUND AND INVOLVEMENT ENNER WIND POWER ANUARY 2018 NEWSLETTER INTRODUCTION enner Wind Limited Partnership (WLP), a subsidiary of Potentia Renewables Inc. (PRI), would like to thank you for your continued support and interest

More information

Please sign in at the front desk and provide your contact information if you would like to receive project updates.

Please sign in at the front desk and provide your contact information if you would like to receive project updates. Community Meeting Please sign in at the front desk and provide your contact information if you would like to receive project updates. We invite you to walk around and look at the displays. If you have

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 12 th June 2017 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: A/2014/0558/F Full Application

More information

Canadian Solar Developers Ltd.

Canadian Solar Developers Ltd. Canadian Solar Developers Ltd. Type of Document Draft Report Project Name Proposed Ground Mount Solar Facility L.P #5 8338 Scotchmere Drive, Strathroy, ON OPA FIT Program: FIT-FL67GB5 Project Number V00002250-00

More information

Strong Breeze Wind Project

Strong Breeze Wind Project IESO LRP 1 RFP Date: July 2, 2015 Qualified Applicant: Invenergy LLC 120 Front Street East, Suite 201 Toronto, ON M5A 4L9 Registered Proponent: Strong Breeze Wind Power Partnership Email: strongbreezeinfo@invenergyllc.com

More information

Source of Activity Sound Level in A-Weighted Decibels (dba) Qualitative Reference Carrier deck jet operation 140

Source of Activity Sound Level in A-Weighted Decibels (dba) Qualitative Reference Carrier deck jet operation 140 10.2. Sound Emission Wind turbine sound can be of mechanical or aerodynamic origin. Mechanical sounds are produced by components in the nacelle, such as the gear box, while aerodynamic sounds are produced

More information

Article 57 WIND GENERATION AND WIRELESS COMMUNICATION TOWERS

Article 57 WIND GENERATION AND WIRELESS COMMUNICATION TOWERS Article 57 WIND GENERATION AND WIRELESS COMMUNICATION TOWERS SECTION 57.010, PURPOSE: The purpose of this article is to establish wind generation and wireless communication tower (Hereafter referred to

More information

Derry City and Strabane District Council Planning Committee Report

Derry City and Strabane District Council Planning Committee Report Derry City and Strabane District Council Planning Committee Report COMMITTEE DATE: 4 th July 2018 APPLICATION No: APPLICATION TYPE: PROPOSAL: LOCATION: APPLICANT: AGENT: A/2014/0558/F Full Application

More information

Environmental Assessment 10 Megawatt Wind Power Project, Lingan Addendum

Environmental Assessment 10 Megawatt Wind Power Project, Lingan Addendum July 12, 2006 NOVA SCOTIA ENVIRONMENT AND LABOUR P. O. Box 697 Halifax, Nova Scotia B3J 2T8 ATTENTION: The Honourable Mark Parent, Minister Environmental Assessment 10 Megawatt Wind Power Project, Lingan

More information

Scorecard - Toronto Hydro-Electric System Limited

Scorecard - Toronto Hydro-Electric System Limited Scorecard - Toronto Hydro-Electric System Limited 9/23/2015 Performance Outcomes Performance Categories Measures 2010 2011 2012 2013 2014 Trend Industry Distributor Target Customer Focus Services are provided

More information

Chapter 750 WIND POWER GENERATION FACILITIES

Chapter 750 WIND POWER GENERATION FACILITIES Chapter 750 WIND POWER GENERATION FACILITIES 750.01 Purpose 750.02 Definitions 750.03 Designated Areas 750.04 Permitted Uses 750.05 Conditional Uses 750.06 Construction Standards 750.07 Application Requirements

More information

Decommissioning Report East Durham Wind Energy Centre

Decommissioning Report East Durham Wind Energy Centre NextEra Energy Canada, ULC East Durham Wind Energy Centre Prepared by: GENIVAR Inc. 500 600 Cochrane Drive 905-475-7270 tel Markham, ON, Canada L3R 5K3 905-475-5994 fax www.genivar.com Project Number:

More information

Oldman 2 Wind Farm Limited

Oldman 2 Wind Farm Limited Decision 22706-D01-2017 Spring 2017 Comprehensive Sound Survey at Receptors R and S August 25, 2017 Alberta Utilities Commission Decision 22706-D01-2017 Proceeding 22706 Application 22706-A001 August 25,

More information

Appendix G Noise Analysis Report

Appendix G Noise Analysis Report Appendix G Noise Analysis Report ENVIRONMENTAL NOISE IMPACT ASSESSMENT McLEANS MOUTAIN WIND FARM MANITOULIN ISLAND, ONTARIO PREPARED FOR: Northland Power Inc. 30 ST CLAIR AVE W, Toronto, ON M4V 3A1 PREPARED

More information