CONSISTENCY BETWEEN CUHP AND RATIONAL METHODS James C.Y. Guo, PhD, P.E., and Ben Urbonas, P.E., D.WRD 08/04/2008
|
|
- Egbert Goodman
- 6 years ago
- Views:
Transcription
1 CONSISTENCY BETWEEN CUHP AND RATIONAL METHODS James C.Y. Guo, PhD, P.E., and Ben Urbonas, P.E., D.WRD 08/04/2008 When estimating runoff for a storm event it is assumed that the storm runoff occurs from the entire tributary area. The surface retention volume in the tributary area plays an important role when making such estimates. For a small urban watershed, the surface retention volume is considered negligible and the peak runoff rate is considered to vary linearly with the size of the tributary area. This fact is well portrayed in the Rational method. On the other hand, the rainfall-runoff process in larger watersheds is more complicated and the significance of depression and surface storage volumes is fully considered. As a result, more descriptive computational techniques are used to estimate stormwater runoff from larger watersheds, such as the unit-graph method recommended by the Urban Drainage and Flood Control District. In addition, when conducting a master drainage study, the watershed is divided into small and large subwatersheds. As a result, it is very important that both the Rational and the unit-graph methods be calibrated for the region to have a consistent basis for flood flow predictions for the ranges in watershed areas where the used of these two methods overlap. The 2005 Colorado Unit Hydrograph Procedure (CUHP2005) is an urban stormwater runoff prediction method derived and calibrated using data from the metropolitan Denver region and Colorado high plains. This report presents a study that modifies the calculation procedures for both CUHP2005 and Rational methods to improve consistency among the peak runoff flow predictions from small tributary areas (smaller than approximately 100 acres). A set of hypothetic square watersheds were tested for several empirical functions derived to calculate the time parameters used in CUHP2005 and Rational methods. The test tributary areas ranged from 10 to 1000 acres. The major effort was to focus on the flow-area relationship smaller than 160 acres. It is proposed that the peaking coefficient (C p ) and time to peak coefficient (C t ) used in CUHP2005 be modified to provide a smooth transition for tributary areas from 10 to 160 acres. Secondly, the calculation protocol for the time of concentration (T c ) used in the Rational method be also modified to recognize the slow overland sheet flows that occur in watersheds with little or no urbanization and the much more rapid sheet flows that occur in highly paved areas. With the proposed revisions, all test watersheds were found to produce a smooth relationship between peak flows and for the test range of tributary areas. Of course, it is recommended that this procedure be further verified using observed rainfall-runoff data and randomly shaped watersheds as well. REVISIONS TO CUHP2005 CUHP2005 is a synthetic unit-graph method that is sensitive to unit-graph peaking coefficient, peaking parameter, time to peak coefficient, and catchment area. As recommended in 2001 USDCM, the time to peak for the unit-graph is calculated as: 1
2 0.48 LLcs t p CT (1) S in which, t op = time to peak of the unit hydrograph from midpoint of unit rainfall in hours, L = length along the drainage way path from study point to the most upstream limits of the catchment in miles, L ace = length along the flow path from study point to a point along it adjacent to the centroid of the catchment in miles, S = length weighted average slope of catchment along the flow path to upstream limits of the catchment in feet per foot, and C T = coefficient reflecting time to peak as depicted in Figure 1. Figure 1 Variation of C T as Function of Imperviousness As shown in Figure 1, the more development in the catchment, the faster the runoff. In addition to the watershed imperviousness, the time to peak is also inversely varied with respect to the tributary area. In fact, the empirical formula in Figure 1 was calibrated for watersheds greater than 90 acres (USDCM, 2001) and shall be considered as the limiting value that is suitable for large watersheds. For smaller watersheds, it is suggested that the time to peak coefficient be revised as follows: 0.31 Ct CT (0.65A ) applicable to areas up to cutoff size (2) Ct C T applicable to area>cutoff in size (3) in which, A = tributary area in square mile, C T = limiting time to peak coefficient in Figure 1 as published in 2001 USDCM. As illustrated in Figure 2, the variable, C t, 2
3 decreases with respect to tributary area and then converges to its limiting value of C T at the cutoff size. Figure 2 Variation of Time to Peak Coefficient for Specified Imperviousness Table 1 summarizes the results from the investigation of the cutoff sizes for watershed imperviousness ratios of 5, 40, and 80%. For these three cases, the cutoff size is found to be 160 acres. It implies that the empirical equation for C T in Figure 1 was applicable to watersheds greater than 160 acres. For tributary areas less than 160 acres, the time of peak coefficient must be decayed as a function of watershed area. Table 1. Convergence of C t and C T functions Area Imp = 5% Imp = 40% Imp = 80% acre C t C t -C T C t C t -C T C t C t -C T
4 In this study, an investigation on the unit-graph peaking coefficient, C p, was also conducted. Among various empirical formulas recommended in 2001 USDCM, the following equation was selected for testing: C 0.15 p PCT A applicable to tributary area of any size. (4) in which, C p = unit hydrograph peaking coefficient and P = peaking parameter. The equation for variable, P, is published in 2001 USDCM as: Figure 3 Unit-graph Peak Coefficient Varied with Imperviousness Revisions to Rational Method The Rational method is simple for use, but difficult to fully understand. For small watersheds the most sensitive parameter in the Rational method is the time of concentration, T c, of the watershed. The time of concentration is composed of overland flow and channel flow times as: T c T T (5) o f In which T o = overland flow time, and T f = channel flow time. The empirical formulas recommended for T f and T o are: 4
5 T T o f 0.33 o 0.5 o 0.395(1.1 C) L (6) S L f (7) 60K S f In which, T o = overland flow time in minutes, L o = overland flow length in feet, S o = overland flow slope in ft/ft, L f = channel flow length in feet, K = conveyance coefficient, S f = channel slope in ft/ft, and C = design event s runoff coefficient (i.e., not the runoff coefficient for the 5-yr event, C 5 ), in 2001 USDCM. For smaller watersheds, the time of concentration is typically dominated by the overland flow time. The length of sheet flow depends on the watershed development, namely it s imperviousness. The common practice of a constant 300 feet as the maximal overland flow length was fount to be not appropriate when addressing the overland flow characteristics of urbanized watersheds. In this study, the maximal allowable overland flow length was set to vary with the watershed imperviousness and watersheds with imperviousness less than and equal to 20% were considered to be rural in drainage nature. Therefore, Denver s regional formula for maximum T c was found to be only applicable to watersheds with imperviousness less than 20% as expressed by the following relationships: T c Min T T, T ) (8) ( o f R Lo L f T R 10 Applicable to Imp>20% (9) 180 In which T R = regional time of concentration in minutes. Table 2 Calculation Protocols for Time of Concentration Imperviousness Max Overland Flow Channel Flow Check with Regional T R Percentage Length in feet Conveyance K No No Yes Yes Yes 5
6 TEST ON CONSISTENCY BETWEEN CUHP2005 AND RATIONAL METHODS In this study, the test cases were selected to cover a wide range of engineering practice. All test watersheds are hypothetical, symmetric squares with a diagonal waterway. The tributary area varies from 10 through 1000 acres. Numerous computer runs were made using watershed area imperviousness ratios that varied from 5 to 80% and waterway slopes from 0.5 to 2.0%. For all test cases, Equations 1 and 2 provide a smooth transition from 10 to 160 acres. As shown in Figures 4 through 8, reasonable agreement can be achieved between the revised CUHP2005 and the Rational method up to areas less than 90 acres. PeakFlow in cfs yr Event for Imp= 5% S=0.5% Area in acres CUHP05 Revised CUHP Rational Figure 4 Comparison of Predicted 5-yr Peak Flows for Imp=5% and S=0.5% 6
7 PeakFlow in cfs yr Event Imp= 20% CUHP05 Revised CUHP Rational Area in acres Figure 5 Comparison of Predicted 100-yr Peak Flows for Imp=20% and S=2% yr Event for Imp= 40% S=2% PeakFlow in cfs CUHP05 Revised CUHP Rational Area in acres Figure 6 Comparison of Predicted 100-yr Peak Flows for Imp=40% and S=2% 7
8 PeakFlow in cfs 5-yr Event for Imp= 60% S=0.5% CUHP05 Revised CUHP Rational Area in acres Figure 7 Comparison of Predicted 5-yr Peak Flows for Imp=60% and S=0.5% 1,600 1, yr Event for Imp=80% and S=2% PeakFlow in cfs 1,200 1, CUHP Revised CUHP Area in acres Rational Figure 8 Comparison of Predicted 100-yr Peak Flows for Imp=80% and S=2% In this study, it was observed that the regional formula, namely Equation 9 for T R, dominates the time of concentration for a watershed with a slope of 0.5%. On the other 8
9 hand for a watershed with a slope of 2%, the calculated T c in Equation 5 is dominated by the recommended overland flow lengths shown in Table 2 (i.e, the tested range). TEST ON LEVEL OF WATERSHED MODELING DETAILS A large watershed is often divided into smaller sub-areas for numerical simulations and as a practical matter in master planning and other hydrology studies. It has been observed that the level of watershed discretization can cause an artificial increase in the peak runoff predicted at the outfall point. Often the smaller the subareas, the higher the cumulative peak runoff is at the downstream limits. In this study, the revised procedure to CUHP2005 was further tested for the level of watershed modeling discretization. The test square watershed has a total area of 300 acres on a slope of 2.0% and imperviousness of 40%. Four cases were developed for testing. They are: Case 1. The watershed is divided into six sub areas of 50 acres (six small basins) Case 2. The watershed is divided into three sub areas of 100 acres (a small + a large basin) Case 3. The watershed is divided into twp subareas: 200- and 100-acre (mixed sizes) Case 4. The watershed is modeled as a 300-acre single tributary area (a large basin) All sub-areas are modeled as a square with a diagonal waterway on a 2.0% slope. Between sub-areas, the channel was defaulted to be a 5-ft trapezoidal channel of 500-ft in length. The predicted peak outflows at the outfall point for this 300-acre watershed are tabulated in Table 3. Cases Table 3 Tests on Level of Watershed Discretization CUHP2005- now Q in cfs CUHP2005- revised Q in cfs Comments Six Areas of 50 acres six small basins Three Areas of 100 acres a small + a large basin Two Areas of 200 and 100 acres mixed sizes Single Area of 300 acres a large basin As shown in Table 3, the revised CUHP2005 procedure can significantly improve the consistency among various levels of watershed modeling discretization. The difference among all cases is within 10% when using the revised CUHP2005. CONCLUSION Watersheds are classified into small and large watersheds. Using the basis of watershed s response to rainfall, the demarcation between small and large urban watersheds is specified in the USDCM as 160 acres. However, based on the testing during this investigation a more appropriate demarcation between small and large watersheds was found to be approximately 90 acres. 9
10 The existing gap between the CUHP2005 for large watersheds and the Rational method for small watersheds has created serious inconsistency in many master drainage and engineering studies. This study presents sufficient numerical tests on the new equations that are proposed to revise the time parameters used in the CUHP2005 protocol to limit such discrepancies. Similarly, it is also proposed that the procedure for calculating the overland flow time in the Rational method be modified to reflect the watershed development condition. Based on the tests and analyses, it is recommended that (1) Equations 2, 3, and 4 be adopted to revise the computer model: CUHP2005, (2) the demarcation between large and smaller watersheds be set at 160 acres when calculating C t and C T in the revised CUHP2005, (3) the peaking parameter be calculated using Equation 5 for all watersheds, (4) Table 2 be adopted to revise the Rational method outlined in 2001 USDCM (5) the revised Rational method be used for watersheds smaller than 90 acres In addition, it was discovered that the USDCM and the CUHP User Manual has typographical errors in the figure represented in this report as Figure 3. The exponent for the peaking factor P shown on that figure needs to be chanced to be 0.15 and not In addition, the coefficient b for Equation 1 in that figure should be changed from to as are reflected in the equations incorporated in the CUHP2005 model. CUHP2005 had been calibrated before. With the proposed revisions, the new version of CUHP2005 must be further tested using real watersheds of various sizes, especially below 160 acres in size. It is necessary to verify the new CUHP2005 results by comparing with available stream gage data and/or previous master planning studies to test its efficacy and impact on hydrology calculations. 10
Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall
6.0 Introduction This chapter summarizes methodology for determining rainfall and runoff information for the design of stormwater management facilities in the City. The methodology is based on the procedures
More informationHYDROLOGIC MODELING CONSISTENCY AND SENSITIVITY TO WATERSHED SIZE
HYDROLOGIC MODELING CONSISTENCY AND SENSITIVITY TO WATERSHED SIZE by James C.Y. Guo. Professor, Civil Engineering, U. Of Colorado at Denver, James.Guo@cudenver.edu.. And Eric Hsu, Project Engineer, Parson
More informationTable of Contents. Overview... 1
Chapter 3 Chapter 3 Table of Contents Overview... 1 Rainfall... 2 3-2-1 Rainfall Depths and Intensities... 2 3-2-2 Design Storm Distribution for Colorado Urban Hydrograph Procedure (CUHP)... 5 3-2-3 Temporal
More informationTECHNICAL MEMORANDUM. SUBJECT: Determination of watershed historic peak flow rates as the basis for detention basin design
TECHNICAL MEMORANDUM FROM: Ken MacKenzie and Ryan Taylor SUBJECT: Determination of watershed historic peak flow rates as the basis for detention basin design DATE: June 7, 2012 The purpose of this memorandum
More informationSection 600 Runoff Table of Contents
Section 600 Runoff Table of Contents 601 INTRODUCTION...600-1 602 RATIONAL METHOD...600-1 602.1 Rational Method Formula...600-2 602.2 Time of Concentration...600-2 602.3 Intensity...600-4 602.4 Runoff
More informationDRAINAGE CRITERIA MANUAL (V. 1) RUNOFF
Section CONTENTS Page RO- 1.0 OVERVIEW... 1 2.0 RATIONAL METHOD... 3 2.1 Rational Formula... 3 2.2 Assumptions... 4 2.3 Limitations... 4 2.4 Time of Concentration... 5 2.4.1 Initial Flow Time... 5 2.4.2
More information6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff
October 2003, Revised February 2005 Chapter 6.0, Runoff Page 1 6.1 Introduction 6.0 Runoff The timing, peak rates of discharge, and volume of stormwater runoff are the primary considerations in the design
More informationAPPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY)
APPENDIX IV. APPROVED METHODS FOR QUANTIFYING HYDROLOGIC CONDITIONS OF CONCERN (NORTH ORANGE COUNTY) Hydromodification design criteria for the North Orange County permit area are based on the 2- yr, 24-hr
More informationChapter 3 Calculating the WQCV and Volume Reduction
Contents 1.0 Introduction... 1 2.0 Hydrologic Basis of the WQCV... 1 2.1 Development of the WQCV... 1 2.2 Optimizing the Capture Volume... 3 2.3 Attenuation of the WQCV (BMP Drain Time)... 4 2.4 Excess
More informationEFFECT OF RAINGAGE DENSITY ON RUNOFF SIMULATION MODELING by ABSTRACT
EFFECT OF RAINGAGE DENSITY ON RUNOFF SIMULATION MODELING by Ben Urbonas, P.E., D.WRE 1, Michael Paul Jansekok 2, James C.Y. Guo, PhD, P.E. 3 ABSTRACT Rainfall and runoff data for a 3.08 square mile urban
More informationRainfall, Runoff and Peak Flows: Calibration of Hydrologic Design Methods for the Kansas City Area
Rainfall, Runoff and Peak Flows: Calibration of Hydrologic Design Methods for the Kansas City Area Bruce McEnroe, Bryan Young, Ricardo Gamarra and Ryan Pohl Department of Civil, Environmental, and Architectural
More informationHydrologic Study Report for Single Lot Detention Basin Analysis
Hydrologic Study Report for Single Lot Detention Basin Analysis Prepared for: City of Vista, California August 18, 2006 Tory R. Walker, R.C.E. 45005 President W.O. 116-01 01/23/2007 Table of Contents Page
More informationIBS Site Drainage: Senior Design Project
IBS Site Drainage: Senior Design Project Len Wright, Ph.D., PE Lecturer, CEAE Wright.Len@gmail.com September 11, 2008 mwsw204i1.ppt/1 OUTLINE Motivation for Stormwater Management Quantity (both onsite,
More informationSummary of Detention Pond Calculation Canyon Estates American Canyon, California
July 15, 2015 Bellecci & Associates, Inc Summary of Detention Pond Calculation Canyon Estates American Canyon, California 1. Methodology: Method: Unit Hydrograph Software: Bentley Pond Pack Version 8i
More informationAppendix G Preliminary Hydrology Study
Appendix G Preliminary Hydrology Study Preliminary Hydrology Study VESTING TTM 72608 Long Beach, CA Prepared for: The Long Beach Project, LLC 888 San Clemente, Suite 100 New Port Beach, CA May 28, 2014
More informationHYDROLOGIC CONSIDERATIONS. 22 nd Annual Nonpoint Source Pollution Conference Saratoga Springs, NY
LOW IMPACT DEVELOPMENT HYDROLOGIC CONSIDERATIONS 22 nd Annual Nonpoint Source Pollution Conference Saratoga Springs, NY May 18, 2011 PRESENTATION AGENDA Introduction Definitions Discuss Impacts to Hydrologic
More informationHYDROLOGY REPORT HEACOCK & CACTUS CHANNELS MORENO VALLEY, CALIFORNIA NOVEMBER 2005 REVISED APRIL 2006 REVISED AUGUST 2006
HYDROLOGY REPORT HEACOCK & CACTUS CHANNELS MORENO VALLEY, CALIFORNIA NOVEMBER 2005 REVISED APRIL 2006 REVISED AUGUST 2006 RIVERSIDE COUNTY FLOOD CONTROL AND WATER CONSERVATION DISTRICT TABLE OF CONTENTS
More informationCity of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017
City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017 Phasing of Meetings April Meeting May Meeting October Review of Tax Day Storm Event and Immediate Actions Taken By City Review of Coordination
More informationGwinnett County Stormwater System Assessment Program
Gwinnett County Stormwater System Assessment Program Jonathan Semerjian, PE Dept. of Water Resources Stormwater Management Sam Fleming, PE Dewberry Presentation Overview Project Background Drivers Enhanced
More informationCLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT HYDROLOGIC CRITERIA AND DRAINAGE DESIGN MANUAL
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT HYDROLOGIC CRITERIA AND DRAINAGE DESIGN MANUAL SECTION 600 STORM RUNOFF TABLE OF CONTENTS 601 INTRODUCTION 603 601.1 - Basin Characteristics 603 602 TIME OF
More informationHydrology Study. Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated)
Hydrology Study Ascension Heights Subdivision Ascension Drive at Bel Aire Road San Mateo, California (Unincorporated) Prepared for San Mateo Real Estate & Construction March 9, 21 Rev. 1 11-8-211 Rev.
More informationActivity Calculating Property Drainage
Page 1 of 5 Activity 2.3.11 Calculating Property Drainage Introduction When a property is developed, it is important to understand that changes to watershed characteristics (i.e., land use, slope, soil
More informationHydrology Study. For Bella Terrazza Portion of Lot 1, Block 39, Subdivision of S Tract, Rancho El Cajon El Cajon, CA 92021
Hydrology Study For Bella Terrazza Portion of Lot 1, Block 39, Subdivision of S Tract, Rancho El Cajon El Cajon, CA 92021 Prepared for Daryl Priest - Priest Development Corporation 124 West Main Street,
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT BARRY ASH POND ALABAMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment or any
More informationiswm TM Technical Manual Hydrology:
: 1.0 2.0 Downstream Assessment 3.0 Streambank Protection 4.0 Water Balance 5.0 Rainfall Tables 6.0 Hydrologic Soils Data Table of Contents 1.0... HO-1 1.1 Estimating Runoff... HO-1 1.1.1 Introduction
More informationOverview of NRCS (SCS) TR-20 By Dr. R.M. Ragan
Overview of NRCS (SCS) TR-20 By Dr. R.M. Ragan TR-20 is a computer program for the simulation of runoff occurring from a single storm event. The program develops flood hydrographs from runoff and routes
More informationRunoff Hydrographs. The Unit Hydrograph Approach
Runoff Hydrographs The Unit Hydrograph Approach Announcements HW#6 assigned Storm Water Hydrographs Graphically represent runoff rates vs. time Peak runoff rates Volume of runoff Measured hydrographs are
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT BOWEN ASH POND 1 (AP-1) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationHydrologic Calibration:
Hydrologic Calibration: UPDATE OF EFFECTIVE HYDROLOGY FOR MARYS CREEK October 2010 Agenda Background Hydrologic model Calibrated rainfall Hydrologic calibration 100 year discharges, Existing Conditions
More information1. Stream Network. The most common approach to quantitatively describing stream networks was postulated by Strahler (1952).
1. Stream Network The most common approach to quantitatively describing stream networks was postulated by Strahler (1952). First Order Streams streams with no tributaries. Second Order Streams begin at
More informationHYDROLOGY STUDY PREPARED FOR: MARKHAM PERRIS LLC 302 WEST FIFTH STREET, SUITE 103 SAN PEDRO, CA (310) FOR THE PROJECT:
HYDROLOGY STUDY PREPARED FOR: MARKHAM PERRIS LLC 302 WEST FIFTH STREET, SUITE 103 SAN PEDRO, CA 90731 (310) 241-2992 FOR THE PROJECT: PERRIS VALLEY COMMERCE CENTER BUILDING PERRIS, CALIFORNIA PROJECT NUMBER:
More informationInflow Design Flood Control System Plan
Inflow Design Flood Control System Plan For Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Cherokee Station - CCR Surface Impoundments Public Service Company of Colorado Denver, Colorado
More informationChapter 12 Storage. Contents. Overview... 1
Chapter 12 Storage Contents Overview... 1 Implementation of Regional, Sub-regional, and On-site Detention Facilities... 2 Regional Detention... 2 Subregional Detention... 5 Onsite Detention... 6 Detention
More informationI(n)Kn. A Qp = (PRF) --- (8) tp Where A is the watershed area in square miles and PRF is the unit hydrograph peak rate factor.
AN ALTERNATE APPROACH FOR ESTIMATING SCS UNIT HYDROGRAPH PEAK RATE FACTORS (PRFS) IN SOUTHWEST FLORIDA Himat Solanki Southwest Florida Water Management District 115 Corporation Way, Venice, Florida 34292
More informationConstructed Wetland Pond T-8
Constructed Wetland Pond T-8 Description A constructed wetlands pond is a shallow retention pond designed to permit the growth of wetland plants such as rushes, willows, and cattails. Constructed wetlands
More information10.0 Storm Sewer Systems
October 2003 Chapter 10.0, Storm Sewer Systems Page 1 10.0 Storm Sewer Systems 10.1 Introduction A storm sewer system consists of a system of inlets, pipes, manholes, junctions, cleanouts, outlets, and
More informationConstructed Wetland Channel T-9
Description A constructed wetland channel is a conveyance BMP that is built, in part, to enhance stormwater quality. Constructed wetland channels use dense vegetation to slow down runoff and allow time
More information5/11/2007. WinTR-55 for Plan Reviews Small Watershed Hydrology Overview
WinTR-55 for Plan Reviews Small Watershed Hydrology Overview 1 Overview Course Outline Historical Background Program Description Model Capabilities and Limitations This is the Overview portion of the training.
More informationCulvert Sizing procedures for the 100-Year Peak Flow
CULVERT SIZING PROCEDURES FOR THE 100-YEAR PEAK FLOW 343 APPENDIX A: Culvert Sizing procedures for the 100-Year Peak Flow A. INTRODUCTION Several methods have been developed for estimating the peak flood
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT GREENE COUNTY ASH POND ALABMA POWER COMPANY Section 257.82 of EPA s regulations requires the owner or operator of an existing or new CCR surface impoundment
More informationThe Texas A&M University and U.S. Bureau of Reclamation Hydrologic Modeling Inventory (HMI) Questionnaire
The Texas A&M University and U.S. Bureau of Reclamation Hydrologic Modeling Inventory (HMI) Questionnaire May 4, 2010 Name of Model, Date, Version Number Dynamic Watershed Simulation Model (DWSM) 2002
More informationPART 3 - STANDARDS FOR SEWERAGE FACILITIES DESIGN OF STORM SEWERS
PART 3 - STANDARDS FOR SEWERAGE FACILITIES 3.3 - DESIGN OF STORM SEWERS 3.301 Design of Storm Sewers A. General Information B. Investigations and Surveys C. Special Projects 3.302 Design Criteria for Storm
More informationUrban Drainage Introduction. A.Ramachandra Rao. C.B. Burke. T.T. Burke, Jr.
32 Urban Drainage A.Ramachandra Rao Purdue University C.B. Burke Christopher B. Burke Engineering, Ltd. T.T. Burke, Jr. Christopher B. Burke Engineering, Ltd. 32.1 Introduction 32.2 The Rational Method
More informationJacobi, Toombs, and Lanz, Inc.
Area 5: Blackiston Mill Road at Dead Man's Hollow Flooding Assessment Jacobi, Toombs, and Lanz, Inc. This document summarizes an assessment of drainage and flooding concerns and provides recommendations
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND B (AP-B ) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationSoftware Applications for Runoff Hydrological Assessment
Bulletin UASVM Horticulture, 67(2)/2010 Print ISSN 1843-5254; Electronic ISSN 1843-5394 Software Applications for Runoff Hydrological Assessment Severin CAZANESCU 1), Sorin CIMPEANU 1), Oana GUI 2), Dana
More informationSTORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW
SUBCHAPTER 8 STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW 7:45-8.1 Purpose and scope of review Except for those projects expressly exempted by this chapter or waived by the Commission, the Commission
More informationAppendix B. Storm Drain System Data
MENIFEE VALLEY CAMPUS MASTER PLAN FINAL EIR MT. SAN JACINTO COMMUNITY COLLEGE DISTRICT Appendix Appendix B. Storm Drain System Data June 2017 MENIFEE VALLEY CAMPUS MASTER PLAN FINAL EIR MT. SAN JACINTO
More informationDrop Height For Channel Erosion Control
Drop Height For Channel Erosion Control James C.Y. Guo, Professor and Director Department of Civil Engineering, U. of Colorado at Denver, Denver, Colorado 8017 E-mail: James.Guo@cudenver.edu Introduction
More informationTable of Contents. 5-5 Release Rates Year Allowable Release Rate WQCV Release Rate EURV Release Rate...
Chapter 5 Table of Contents 5-1 Introduction... 1 5-1-1 Stormwater Quality Considerations... 1 5-1-2 Stormwater Volume Considerations... 2 5-1-3 Downstream Impacts... 2 5-2 Requirements... 2 5-2-1 General
More informationChapter H. Introduction to Surface Water Hydrology and Drainage for Engineering Purposes
Chapter H. Introduction to Surface Water Hydrology and Drainage for Engineering Purposes As seen in Figure H.1, hydrology is a complex science that deals with the movement of water between various stages
More informationCity of Oakland. Public Works Agency Standards STORM DRAINAGE DESIGN GUIDELINES. Engineering Design & ROW Management Division
City of Oakland PUBLIC WORKS AGENCY 250 FRANK H. OGAWA PLAZA 4 TH FLOOR OAKLAND, CALIFORNIA 94612 (510) 238-3437 FAX (510) 238-7227 TTD (510) 238-3254 Public Works Agency Standards STORM DRAINAGE DESIGN
More informationCHAPTER 3 STORMWATER HYDROLOGY. Table of Contents SECTION 3.1 METHODS FOR ESTIMATING STORMWATER RUNOFF
CHAPTER 3 STORMWATER HYDROLOGY Table of Contents SECTION 3.1 METHODS FOR ESTIMATING STORMWATER RUNOFF 3.1.1 Introduction to Hydrologic Methods...3.1-1 3.1.2 Symbols and Definitions...3.1-3 3.1.3 Rainfall
More informationPre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015
Pre-Treatment Bioretention Cells Bioswales IOWA STORMWATER MANAGEMENT MANUAL DECEMBER 16, 2015 Urban Runoff Background How we got here What Problem?? Provenance of the Problem Unified Sizing Criteria What
More informationFort Leonard Wood, Missouri. September 2013
Fort Leonard Wood, Missouri September 2013 1 Presenters Shannon Kelly, Physical Scientist Clean Water Act Program Manager Directorate of Public Works Environmental Division Environmental Compliance Branch
More informationCokato Lake (86-263) Wright County. Hydrologic Investigation
Cokato Lake (86-263) Wright County Hydrologic Investigation April 14, 2005 Cokato Lake (86-263) Wright County Hydrologic Investigation April 14, 2005 Problem Statement In recent years, heavy rainfall has
More informationInflow Design Flood Control System Plan
Inflow Design Flood Control System Plan For Compliance with the Coal Combustion Residuals Rule (40 CFR Part 257) Valmont Station - CCR Surface Impoundments Public Service Company of Colorado Denver, Colorado
More informationRhode Island Stormwater Design and Installations Standards Manual
Rhode Island Stormwater Design and Installations Standards Manual Public Workshop Required Management Volume Calculations and Redevelopment Considerations March 22, 2011 Presentation Outline Recap of How
More informationStream Reaches and Hydrologic Units
Chapter United States 6 Department of Agriculture Natural Resources Conservation Service Chapter 6 Stream Reaches and Hydrologic Units Rain clouds Cloud formation Precipitation Surface runoff Evaporation
More informationStormwater Management Studies PDS Engineering Services Division ES Policy # 3-01
Stormwater Management Studies PDS Engineering Services Division Revised Date: 2/28/08 INTRODUCTION The City of Overland Park requires submission of a stormwater management study as part of the development
More informationIstokpoga Marsh Watershed Improvement District (IMWID) Minor Impoundment Project. May 23, 2012
STORMWATER INFORMATION AND CALCULATIONS FOR ENVIRONMENTAL RESOURCE PERMIT Istokpoga Marsh Watershed Improvement District (IMWID) Minor Impoundment Project Prepared by Chastain-Skillman, Inc. Prepared for
More informationCity Plaza Residential (TPM ) Preliminary Hydrology Report
Hydrology Study City Plaza Residential (TPM 2016-127) Preliminary Hydrology Report Orange, Orange County, California Prepared For: Greenlaw Partners 18301 Von Karman Avenue, Suite 250 Irvine, CA 92612
More informationGrass Channel STORMWATER MANAGEMENT SUITABILITY KEY CONSIDERATIONS
4.0 Structural Stormwater Control Description: Vegetated open channels designed to filter stormwater runoff and meet velocity targets for the water quality design storm and the Streambank Protection storm
More informationPreliminary Drainage Analysis
Preliminary Drainage Analysis Tanimura and Antle Employee Housing Town of Spreckels County of Monterey, California LIB150205 May 29, 2015 Prepared For: Tanimura and Antle Produce Prepared By: 9699 Blue
More informationMunicipal Stormwater Management Planning
Municipal Stormwater Management Planning Christopher C. Obropta, Ph.D., P.E. Water Resources Extension Specialist with Rutgers Cooperative Extension Assistant Professor with Department of Environmental
More informationDIVISION 5 STORM DRAINAGE CRITERIA
DIVISION 5 STORM DRAINAGE CRITERIA Section 5.01 GENERAL The following storm drainage design criteria shall apply to all storm drainage designs in the City. Additional design criteria are specified in the
More informationSunset Circle Vegetated Swale and Infiltration Basin System Monitoring Report: Rainy Seasons and
Sunset Circle Vegetated Swale and Infiltration asin System Monitoring Report: Rainy Seasons 2012-13 and 2013-14 bstract Site Summary Project Features Sunset Circle Vegetated swales and infiltration basins
More informationCLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT HYDROLOGIC CRITERIA AND DRAINAGE DESIGN MANUAL SECTION 200 DRAINAGE PLANNING AND SUBMITTAL
CLARK COUNTY REGIONAL FLOOD CONTROL DISTRICT HYDROLOGIC CRITERIA AND DRAINAGE DESIGN MANUAL SECTION 200 DRAINAGE PLANNING AND SUBMITTAL TABLE OF CONTENTS 201 SUBMITTAL AND REVIEW PROCESS 201 202 DRAINAGE
More informationHYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR
HYDROLOGIC-HYDRAULIC STUDY ISABELLA OCEAN RESIDENCES ISLA VERDE, CAROLINA, PR 1 INTRODUCTION 1.1 Project Description and Location Isabella Ocean Residences is a residential development to be constructed
More informationPRELIMINARY DRAINAGE REPORT NEWCASTLE FIRE STATION OLD STATE HIGHWAY
PRELIMINARY DRAINAGE REPORT FOR THE NEWCASTLE FIRE STATION OLD STATE HIGHWAY PREPARED FOR THE NEWCASTLE FIRE PROTECTION DISTRICT JULY 2014 BY ROSEVILLE DESIGN GROUP, INC. ROSEVILLE DESIGN GROUP, Inc Established
More informationTHE CROSSROADS IN WINCHESTER 4. DRAINAGE PLAN. 4. Drainage Plan. a. Drainage Plan Description
THE CROSSROADS IN WINCHESTER 4. DRAINAGE PLAN 4. Drainage Plan a. Drainage Plan Description The Specific Plan area drains naturally into two separate watersheds: approximately 6 percent of the Specific
More informationPeak discharge computation
Ia/P 4 Peak Dischage Method Graphical Peak Discharge Method This chapter presents the Graphical Peak Discharge method for computing peak discharge from rural and urban areas. The Graphical method was developed
More informationRunoff Processes. Daene C. McKinney
CE 374 K Hydrology Runoff Processes Daene C. McKinney Watershed Watershed Area draining to a stream Streamflow generated by water entering surface channels Affected by Physical, vegetative, and climatic
More informationSizing Calculations and Design Considerations for LID Treatment Measures
SCVURPPP C.3 Workshop December 18, 2012 Sizing Calculations and Design Considerations for LID Treatment Measures Jill Bicknell, P.E., EOA, Inc. Santa Clara Valley Urban Runoff Pollution Prevention Program
More informationGreen Infrastructure Flood Reduction Computations
Green Infrastructure Flood Reduction Computations Stephen Sands, PE, CFM ssands@hazenandsawyer.com March 24, 2016 Water JAM 2010 Discussion Topics Siting success Watershed-wide computations Individual
More informationCOON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432
PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:
More informationAPPENDIX G HYDRAULIC GRADE LINE
Storm Drainage 13-G-1 APPENDIX G HYDRAULIC GRADE LINE 1.0 Introduction The hydraulic grade line is used to aid the designer in determining the acceptability of a proposed or evaluation of an existing storm
More informationRainfall Depth in inches. Figure 1 Rainfall Depth Distribution in the Denver Area, Colorado
This report was prepared for the Urban Drainage and Flood Control District in 1994 and a somewhat modified version was Published in ASCE J. of Water Resources Planning and Management, Vol 122, No. 1, January
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT YATES ASH POND 3 (AP-3) GEORGIA POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationChapter 6 Hydrology TABLE OF CONTENTS CHAPTER 6 - HYDROLOGY
Chapter 6 Hydrology TABLE OF CONTENTS CHAPTER 6 - HYDROLOGY... 6-1 6.1 Introduction... 6-1 6.1.1 Objective... 6-1 6.1.2 Definition... 6-1 6.1.3 Factors Affecting Floods... 6-1 6.1.4 Sources of Information...
More informationUSER S MANUAL. Water Quality Capture Optimization and Statistics Model (WQ-COSM) v2.0. October 2012 Edition
USER S MANUAL Water Quality Capture Optimization and Statistics Model (WQ-COSM) v2.0 October 2012 Edition Copyright of this manual and the software it describes, October 1, 2012 by Urban Watersheds Research
More informationINFILTRATION BASIN DESIGN AND OVERFLOW RISK
Guo, James C.Y. and Urbonas, Ben. (2002). Runoff Capture and Delivery Curves for Storm Water Quality Control Designs, ASCE J. of Water Resources Planning and Management, Vol 128, Vo. 3, May/June. Guo,
More information3.0 Planning and Submittal Requirements
October 2003, Revised February 2005 Chapter 3.0, Planning and Submittal Requirements Page 1 3.0 Planning and Submittal Requirements 3.1 Drainage Studies and Drawings The City of Greenwood Village (Village)
More informationTECHNICAL BULLETIN. Synthetic Turf Athletic Field Drainage Design Assistance
TECHNICAL BULLETIN Synthetic Turf Athletic Field Drainage Design Assistance The SportsEdge HQ geocomposite strip drain products are engineered specifically for use in synthetic turf athletic field base
More informationPRELIMINARY HYDROLOGY STUDY
PRELIMINARY HYDROLOGY STUDY FOR Tentative Tract Map West Side of Loma Alta Drive City of Oceanside, CA Prepared For: EMERALD HILLS LLC 4272 Dogwood Avenue Seal Beach, CA 90740 Contact: Mr. Jimmy Chen Ph:
More informationINFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY
INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN 40 C.F.R. PART 257.82 PLANT DANIEL ASH POND B MISSISSIPPI POWER COMPANY EPA s Disposal of Coal Combustion Residuals from Electric Utilities Final Rule (40 C.F.R.
More informationAPPENDIX F HYDROLOGY REPORT
APPENDIX F HYDROLOGY REPORT UCSD LONG RANGE DEVELOPMENT PLAN HYDROLOGY STUDY MAY 2004 PREPARED FOR: UNIVERSITY OF CALIFORNIA, SAN DIEGO 10280 NORTH TORREY PINES ROAD, SUITE 340 LA JOLLA, CA 92093-0965
More informationRed Barn R.V. and Boat Storage Weld County, Colorado. Final Drainage Report
Red Barn R.V. and Boat Storage Weld County, Colorado Final Drainage Report Prepared for Kevin Moore Project No. 1318-001 February 27, 2017 Prepared By: KETTERLING, BUTHERUS AND NORTON ENGINEERS, LLC. 820
More informationModel Results Operation and Maintenance (O& M) Results Cost-Benefit Analysis Results Conclusions
BMP Performance and Outline Background Model Results Operation and Maintenance (O& M) Results Results Conclusions Melissa Baker, Water Resource Technician Capitol Region Watershed District, St. Paul, MN
More informationChapter 4. Drainage Report and Construction Drawing Submittal Requirements
4.0 Introduction The requirements presented in this section shall be used to aid the design engineer or applicant in the preparation of drainage reports, drainage studies, and construction drawings for
More informationRE: Final Drainage Letter: Northwest Aurora Alley Improvements 2016
April 12, 2016 Mr. Craig Perl, P.E. Senior Engineer City of Aurora Public Works Department 15151 E. Alameda Parkway Aurora, CO 80012 RE: Final Drainage Letter: Northwest Aurora Alley Improvements 2016
More informationEngineering Bulletin 11-02
ENGINEERING, SURVEYING & PERMIT SERVICES DEPARTMENT CHARLES LACKEY, P.E., DIRECTOR 2700 M STREET, SUITE 570 BAKERSFIELD, CA 93301-2370 Phone: (661) 862-8603 Fax: (661) 862-5149 E-mail: esps@co.kern.ca.us
More informationNRCS Hydrology methodology review Minnesota NRCS recommendation MnDOT recommendation Using Atlas 14 with HydroCAD
Dec, 2015 NRCS Hydrology methodology review Minnesota NRCS recommendation MnDOT recommendation Using Atlas 14 with HydroCAD NRCS - Natural Resource Conservation Service (formerly known as SCS Soil Conservation
More informationVillage of Winnetka Flood Risk Reduction Assessment. Christopher B. Burke Engineering, Ltd. (CBBEL) October 11, 2011
Village of Winnetka Flood Risk Reduction Assessment October 11, 2011 Christopher B. Burke Engineering, Ltd. (CBBEL) Thomas T. Burke, Jr., PhD, PE David Buckley, PE, CFM Introduction The September 2008
More informationCORBIN AND NORDHOFF IV. ENVIRONMENTAL IMPACT ANALYSIS ENV EIR F. HYDROLOGY
F. HYDROLOGY ENVIRONMENTAL SETTING Project Site The Project Site is located at 19601 Nordhoff Street in the Chatsworth area of the City of Los Angeles, California, within the Chatsworth - Porter Ranch
More informationTechnical Memorandum Mine Plan of Operations Stormwater Assessment
Tucson Office 3031 West Ina Road Tucson, AZ 85741 Tel 520.297.7723 Fax 520.297.7724 www.tetratech.com Technical Memorandum Mine Plan of Operations Stormwater Assessment To: Kathy Arnold From: David R.
More informationSAN GORGONIO PASS CAMPUS - PHASE I
SAN GORGONIO PASS CAMPUS - PHASE I Banning, CA DRAINAGE STUDY June 16, 2010 Reference 106-195 PREPARED BY: Encompass Associates, Inc. 5699 Cousins Place Rancho Cucamonga, CA 91737 909-684-0093 Fax-909-586-6979
More informationProject Drainage Report
Design Manual Chapter 2 - Stormwater 2A - General Information 2A-4 Project Drainage Report A. Purpose The purpose of the project drainage report is to identify and propose specific solutions to stormwater
More informationHYDROLOGY STUDY LA MIRADA BOULEVARD La Mirada, California
HYDROLOGY STUDY 12000 LA MIRADA BOULEVARD La Mirada, California TTM 73119 Prepared for: The Olson Company 3010 Old Ranch Parkway, Suite 100 Seal Beach, CA 90740 Contact: Mr. Aaron Orenstein (562) 370-9531
More informationAppendix VI: Illustrative example
Central Valley Hydrology Study (CVHS) Appendix VI: Illustrative example November 5, 2009 US Army Corps of Engineers, Sacramento District Prepared by: David Ford Consulting Engineers, Inc. Table of contents
More information