BPA Wind Voltage Control Requirements
|
|
- Clare McCoy
- 5 years ago
- Views:
Transcription
1 BPA Wind Voltage Control Requirements PJM Conference Dmitry Kosterev Bonneville Power Administration
2 Many of BPA Paths are Stability-Limited Cross-Cascades North Montana - Northwest Cross-Cascades South Wind Pacific HVDC Intertie California Oregon Intertie Slide 2
3 Pre-2007 Projects Wind generation amount was below 500 MW Wind power plants were not required to contribute to voltage control Required to operate at unity power factor Size switched reactive to compensate for reactive power losses Many operational challenges were observed Slide 3
4 Customer Impacts Voltage versus Power for a Wind Farm (Actual Operating Data) Voltage Voltage (Per Unit) 1 Wind Farm Voltage Customer Voltage Power Power (Per Unit of Full Output) Excessive LTC operations Slide 4
5 Voltage (per unit) Power (MW) MW WPP Connected to 115-kV Voltages Time (min) Wind Total Power kV bus 34.5-kV bus Time (min) Wind Total Reactive Power 0 These are actual recordings Project did not have dynamic reactive capabilities Several oscillatory events were observed with all lines in service The power output was curtailed STATCOM with voltage controller was installed Reactive (MVAR) Time (min) Slide 5
6 Wind power ramp Voltage (kv) Voltage Early plants do not have STATCOMs and use only shunt caps Power (MW) Reactive (MVAR) Time (min) Active Power Time (min) Reactive Power Time (min) Operate mainly in power factor mode As POI voltage declines WPP draws larger amount of reactive power Slide 6
7 Wind Ramp PV-Curve for same wind ramp 243 PV Plot - Voltage versus Wind Total 242 Voltage (kv) The edge All lines in service Power (MW) Slide 7
8 Modeling (Lesson Learned) Wind Power Plant models were unable to predict the observed the stability issues ahead of time Model tuning was required to match in principle the disturbance recordings with reality Static powerflow snapshots were often found inadequate, there was a need for a time-sequence simulation of power ramps
9 Modeling BPA made a major effort on improving powerflow models for WPPs based on WECC Guidelines for WPP Powerflow Modeling BPA is participating in DOE-NREL-UWIG project on dynamic model validation BPA requires all new projects connecting at 230-kV level to install Phasor Measurement Units (PMUs) / extended DFRs at POIs BPA is working with the WPP owners on retrofitting the existing WPPs with PMUs Slide 9
10 2006 Study BPA conducted a large-scale study to determine the impact of 3,000 MW of wind on system macro stability The study concluded that the wind power plants need to provide voltage Major voltage stability, transient stability, and undampened oscillations were observed should wind operate in power factor mode, resulting in intertie derating Slide 10
11 Voltage Control Requirements BPA requires wind power plants to provide voltage control and reactive power to support the grid just like other large generation projects How much reactive is needed: Dynamic reactive sized to provide continuous +/ power factor at 34.5-kV bus Switched shunts to compensate for reactive power losses between WTGs and Point Of Interconnection, high switching duty Slide 11
12 100 MW Type 2 with STATCOM W 1.0 pf Three 10 MVAR switched shunts capacitors to compensate for steady-state reactive losses, high switching duty (can be on BPA high side) +/- 16 MVAR STATCOM +/-32 MVAR 2-second overload capability W Slide 12
13 100 MW Type 3 or 4 Wind Generator Example W W Two 9 MVAR switched shunts capacitors to compensate for steady-state reactive losses, high switching duty (can be on BPA HV bus for several plants) +/ pf (+/- 33 MVAR) continuously controllable Reactive power deliverability Slide 13
14 Voltage Control Requirements How to control reactive resources: Operate in continuous (no dead-band!) voltage control mode, control POI voltage to BPA schedule with reactive droop Switching shunts to maximize the availability of dynamic capabilities at the plant Slide 14
15 POI Voltage Voltage Control Mode High Side Voltage Control Power Factor / VAR Control HSVC with a Droop (5.8% on plant MW base) Power Plant POI Reactive Power 15 Slide 15
16 Observed Challenges Reactive power deliverability Collector system voltage raise prevents WPP from delivering VARs to POI Shunt capacitor availability Long discharge time Reactive power coordination among several WPPs in the same wind hub Slide 16
17 250.0 Jones Canyon 230-kV Voltage B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Leaning Juniper #2B V-Q kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : Leaning Juniper #2B MW MW kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ :00 Leaning Juniper #2B MVAR MVAR /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : M VAR Slide 17
18 250.0 Jones Canyon 230-kV Voltage B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Leaning Juniper #1 V-Q kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : Leaning Juniper #1 MW MW kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ :00 Leaning Juniper #1 MVAR MVAR /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : M VAR Slide 18
19 250.0 Jones Canyon 230-kV Voltage B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Rattle Snake V-Q kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : Rattle Snake MW MW 60.0 kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ :00 Rattle Snake MVAR MVAR /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : M VAR Slide 19
20 Wind Hub Generation Situational Awareness Slide 20
21 BPA Activities in Progress Voltage control Working with WPP operators on implementing a droop control Coordination of reactive resources in a wind hub Modeling and Monitoring Projects to install and integrate WPP PMUs DOE-UWIG Wind Modeling Project Situational Awareness SCADA alarming, PI applications for voltage control monitoring Dynamic transfers WECC VGS Planning Guideline Slide 21
Collaborative Approach for Wind Power Plant Model Data and Validation
Collaborative Approach for Wind Power Plant Model Data and Validation Dmitry Kosterev, Steve Yang and Gordon Kawaley, BPA WECC MVWG October 5, 2017 1 Regulatory Landscape NERC MOD-032 Data for Power System
More informationWhat makes a Wind Plant Grid Friendly?
Stable Renewable Plant Voltage and Reactive Power Control NERC ERSTF June 11-12, 2014 Sebastian Achilles Nicholas Miller Einar Larsen Jason MacDowell GE Energy Consulting 1 / Topics Features of modern
More informationDaniel Feltes Phone: Fax:
Coordination of Controls of Renewable Power Plants to Meet Steady State and Dynamic Response Requirements for Voltage Control and Reactive Power Supply Dinemayer Silva Phone: 518-395-5169 Fax: 518-346-2777
More informationDECISIONS on operating transfer limits and transmission
1144 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 2, MAY 2004 Hydro Turbine-Governor Model Validation in Pacific Northwest Dmitry Kosterev Abstract This paper presents an approach for generator model
More informationBriefing on using renewables to integrate renewables
Briefing on using renewables to integrate renewables Clyde Loutan, Sr. Advisor, Renewable Energy Integration Board of Governors Meeting General Session December 14-15, 2016 Can variable energy resources
More informationGenerator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report
Generator Interconnection Affected System Impact Study Plains & Eastern Clean Line Final Report May 19, 2015 MISO 2985 Ames Crossing Eagan Minnesota - 55121 http://www.misoenergy.org Midcontinent Independent
More informationHydro-Quebec s experience with HYPERSIM Real-time Power System Simulator
Hydro-Quebec s experience with HYPERSIM Real-time Power System Simulator Christian Larose, Power System Simulation, Hydro-Québec (CANADA) June 26, 2013 Presentation overview > Application of Hypersim at
More informationHarnessing Renewables in Power System Restoration
Harnessing Renewables in Power System Restoration Dr. Wei Sun, and Amir Golshani Assistant Professor, EECS Dept. University of Central Florida (South Dakota State University) Panel: Cascading Failures:
More informationConsortium for Electric Reliability Technology Solutions (CERTS)
Consortium for Electric Reliability Technology Solutions (CERTS) CERTS-CAISO Meeting Phasor Applications for Monitoring, Alarming & Control February 17 th, 2006 Joe Eto, Jim Dyer, Manu Parashar OUTLINE
More informationCalifornia Independent System Operator Corporation Fifth Replacement Tariff
Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing
More informationCalifornia Independent System Operator Corporation Fifth Replacement Tariff
Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing
More informationWWSIS - 3: Western Frequency Response and Transient Stability Study
WWSIS - 3: Western Frequency Response and Transient Stability Study GE Energy Nicholas W. Miller (PM) Miaolei Shao Slobodan Pajic Rob D Aquila NREL Kara Clark (PM) NERC ERSTF Briefing Atlanta December
More informationCOLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN
COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN January 11, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503) 943-4940 8338 NE Alderwood Road, Suite
More informationCalifornia Independent System Operator Renewable Integration Study
California Independent System Operator Renewable Integration Study Clyde Loutan Proposed Transmission Plan for Integration of Renewables Transmission System Analysis - Overview Joint Study between the
More informationReliability Guideline
Reliability Guideline Power Plant Model Verification for Inverter-Based Resources June 2018 NERC Report Title Report Date I Table of Contents Preface... iv Preamble... v Executive Summary... vi Introduction...1
More informationGOLDEN VALLEY ELECTRIC ASSOCIATION
October 13, 2008 GOLDEN VALLEY ELECTRIC ASSOCIATION Eva Creek Wind Farm-Limited Study Doubly Fed Asynchronous Generators Power Flow, Reactive Compensation, Transient Stability Revision 0 PROJECT NUMBER:
More informationReliability Guideline
Reliability Guideline Power Plant Model Verification for Inverter-Based Resources September 2018 NERC Report Title Report Date I Table of Contents Preface... iv Preamble... v Executive Summary... vi Introduction...
More informationCase Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL
Case s 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality s FINAL Introduction Powerflow and dynamics cases are the foundation of virtually all power system studies. Calculations
More informationCritical Load Serving Capability by Microgrid using 100% Renewable Energy
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Critical Load Serving Capability by Microgrid using 100% Renewable Energy P. PENKEY,
More informationImproving Reliability Through Better Models
Improving Reliability Through Better Models By Philip Overholt, Dmitry Kosterev, Joseph Eto, Steve Yang, and Bernard Lesieutre The Office of Electricity Delivery and Energy Reliability of the U.S. Department
More informationBig Data Analysis. ipcgrid 30 March 16. Gordon Matthews, P.E. Bonneville Power Administration Technology Innovation
Big Data Analysis ipcgrid 30 March 16 Gordon Matthews, P.E. Bonneville Power Administration Technology Innovation BPA Overview Bonneville Power Administration (BPA) is a Federal Power Marketing Agency
More information2012 Grid of the Future Symposium. Modeling and Simulation of Advanced Reactive Compensation Systems in Renewable Energy Applications
, rue d Artois, F78 PARIS CIGRE US National Committee http : //www.cigre.org Grid of the Future Symposium Modeling and Simulation of Advanced Reactive Compensation Systems in Renewable Energy Applications
More informationIncreased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study
2018-2019 Transmission Planning Process Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study Ebrahim Rahimi Lead Regional Transmission
More informationTechnical considerations for integration of distributed renewables on the grid
Technical considerations for integration of distributed renewables on the grid A paper by Dr Charlotte Higgins, Dr Bunmi Adefajo & Kumbuyani Chisoro Kumbuyani Chisoro Manager Southern Africa TNEI Services
More informationWestern Wind & Solar Integration Studies
Western Wind & Solar Integration Studies Kara Clark, Greg Brinkman, NREL Nick Miller, Miaolei Shao, Slobodan Pajic, Rob D Aquila, Bruno Leonardi, GE 3/22/17 NREL is a national laboratory of the U.S. Department
More informationTechnical and economical analysis of the wind turbines interconnection with the windfarm substation
Technical and economical analysis of the wind turbines interconnection with the windfarm substation NICOLAE COROIU Faculty of Electrical Engineering and Industrial Management University of Oradea Oradea,
More informationCalifornia ISO Preparing California for a Greener and Smarter Grid
California ISO Preparing California for a Greener and Smarter Grid Presented by Jim McIntosh Director Operations Executive Advisor California ISO Agenda CAISO Overview Current & Future Challenges Renewables
More informationUtility Tools and Design Modifications to Mitigate the Impact of PV on the Distribution System
Utility Tools and Design Modifications to Mitigate the Impact of PV on the Distribution System? IEA-Task 14/SEPA High Penetration PV Workshop Dec. 1, 2010 Overview Service Territory & PV Activity PV System
More informationJuly 5, SUBJECT: MT Renewable Action Plan (BPA and Montana Partnership)
James Yost Chair Idaho W. Bill Booth Idaho Guy Norman Washington Tom Karier Washington Jennifer Anders Vice Chair Montana Tim Baker Montana Ted Ferrioli Oregon Richard Devlin Oregon July 5, 2018 MEMORANDUM
More informationConnection Study Requirements
Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.
More informationCentralia Power Plant Closure Study. Initial Study Results DRAFT. March 17, 2011
Centralia Power Plant Closure Study Initial Study Results DRAFT March 17, 2011 Conditions Studied 5 and 10-year Winter and Summer Peak 5-year Light Autumn High Transfers to and from British Columbia Additional
More informationAnalysis of Three Recent Blackouts
Analysis of Three Recent Blackouts San Diego Gas & Electric -09/08/2011 Indian Northern Grid 07/30/2012 Indian Northern & Eastern Grids 07/31/2012 Bharat Bhargava Advanced Power System Technologies, Inc.
More informationISSN Vol.07,Issue.16, November-2015, Pages:
ISSN 2348 2370 Vol.07,Issue.16, November-2015, Pages:3181-3185 www.ijatir.org Improvement of Power Quality in A Grid Connected Induction Generator Based Wind Farm using Static Compensator K. YOSHMA 1,
More informationA. RECOMMENDATIONS ON PROPOSED RELIABILITY PROJECTS
Public Advocates Office California Public Utilities Commission 505 Van Ness Avenue San Francisco, California 94102 Tel: 415-703-1584 www.publicadvocates.cpuc.ca.gov COMMENTS OF THE PUBLIC ADVOCATES OFFICE
More informationDRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan -
CAISO 2008-2013 Integration of Renewable Resources Program (IRRP) - High-Level Program Plan - Purpose The purpose of this document is to provide an initial high-level scoping and program plan for the CAISO
More informationRenewable Integration in India
Nihar S Raj Business Head Power Consulting ABB India Limited Renewable Integration in India Agenda Introduction & Plans Duck Curve Challenges with Renewable Integration Grid Impact Studies Demand Management
More informationRochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017
Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2
More informationCriteria. C~/v~ ~ ~ ~ G! " A1A "~"" T"""g"'~10N COr'P""''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria
A1A "~"" T"""g"'~10N COr'P""''~ Criteria Department: Document No: System Planning and Strategic Projects P LG -C R-0001-V 19.2 T~c~e: Transmission System Planning Criteria issue gate: Previous Date: February
More informationTRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA
TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision
More informationFINAL PROJECT REPORT WECC WIND GENERATOR DEVELOPMENT
FINAL PROJECT REPORT WECC WIND GENERATOR DEVELOPMENT Appendix III WIND POWER PLANT EQUIVALENCING Prepared for CIEE By: National Renewable Energy Laboratory A CIEE Report - i - Acknowledgments This work
More informationTransmission Expansion Advisory Committee. October 11, 2012
Transmission Expansion Advisory Committee October 11, 2012 Issues Tracking Issues Tracking Open Issues None New Issues 3 2012 RTEP - Renewable Portfolio Standards Scenarios Progress Update Scenario #1
More informationWind Farm Performance on the Grid: Perception and Reality
Wind Farm Performance on the Grid: Perception and Reality WindVAR and LVRT Data and Graphs provided by Nicholas W. Miller GE Energy, Energy Consulting 1 GE Energy Wind Energy Grid Performance: A Perception
More informationResearch Co-design Activity
Research Co-design Activity A. Purpose of Co-design: The ultimate goals of this co-design activity are to: Directly involve all members of a group to make decisions together that would affect their daily
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service
More informationPowerWatch Operating A Wind Farm as a Balancing Authority. Manager, Operational Analytics
PowerWatch Operating A Wind Farm as a Balancing Authority Presented by Devon Yates Manager, Operational Analytics NaturEner overview NaturEner S.A. - Solar 29 PV MW under operation 81 PV MW in late-stage
More informationPower Quality and Voltage Stability of Power Systems with a large share of Distributed Energy Resources
University of Texas at Tyler Scholar Works at UT Tyler Electrical Engineering Theses Electrical Engineering Spring 4-30-2012 Power Quality and Voltage Stability of Power Systems with a large share of Distributed
More informationModel Validation on Wind Turbine Generators Using the 2 nd Generation Wind Turbine Generator Models
Model Validation on Wind Turbine Generators Using the 2 nd Generation Wind Turbine Generator Models Pouyan Pourbeik ppourbeik@epri.com WECC REMTF Workshop Salt Lake City, UT 6/17/14 OVERVIEW Standards/Policies:
More informationPhasor measurement units gain credibility through improved test and calibration standards
Phasor measurement units gain credibility through improved test and calibration standards Smart grid; PMU calibration position 1 The North American interconnection, or electric transmission grid, is a
More informationStandards de planification du NERC
Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council
More informationGrid Interconnection Issues for Wind Generation
Grid Interconnection Issues for Wind Generation NRECA APPA - DOE Teleconference December 8, 2005 By Thomas A. Wind, PE Wind Utility Consulting Jefferson, Iowa Topics I Will Cover What are the key technical
More informationLesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System
Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators
More informationImpact of Power Management Strategies on Micro-Grid Dynamic Performance
University of Toronto Department of Electrical and Computer Engineering Impact of Power Management Strategies on Micro-Grid Dynamic Performance Reza Iravani Center for Applied Power Electronics (CAPE)
More informationVoltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998
Western Electricity Coordinating Council Voltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998 VOLTAGE STABILITY CRITERIA, UNDERVOLTAGE
More informationPower Quality
DEP2016.12.21.01EN Power Quality www.nidec-industrial.com over 7 GVAr power installed > 75 projects across the globe Our expertise spans a wide range of industries including: Metals/mining Renewable Energy
More informationSESSION 3: Grid Integration Studies for Planning Secure and Reliable System Operations with Expected Shares of Variable Renewables
SESSION 3: Grid Integration Studies for Planning Secure and Reliable System Operations with Expected Shares of Variable Renewables Presenter: Eduard Muljadi National Renewable Energy Laboratory 15013 Denver
More informationCoordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function
Coordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function Mariana B. Pereira 1, Sebastian A. Achilles 2, Nath Venkit 2 Energy Consulting General
More informationEAPP interconnection readiness workshop
1 EAPP interconnection readiness workshop Self-Assessment for EAPP/IC -Compliance Rwandan-Grid Gap Analysis & Proposed mitigations GENERATION, TRANSMISSION & DISTRIBUTION 01 st October, 2018 INTRODUCTION
More informationDynamic Response of Large Wind Power Plant Affected by Diverse Conditions at Individual Turbines
Dynamic Response of Large Wind Power Plant Affected by Diverse Conditions at Individual Turbines Marcelo A. Elizondo Pacific Northwest National Laboratory Seattle, Washington USA Marcelo.Elizondo@pnnl.gov
More informationCalifornia ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar
California ISO Energy Imbalance Market Operations Overview June 10, 2014 Webinar Objectives 1. EIM Overview 2. CAISO s process in mitigating Unscheduled Flow (USF) 3. WebSAS tool: how dynamic and pseudo
More informationFault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012
Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012 1 Presentation Overview Joint Working Group The Issue Structure of the Report Wind Plant Configuration Wind Turbine Generators
More informationCENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE
CHENNAI INDIAN WIND GRID CODE Rajesh Katyal Unit Chief, R&D Centre for Wind Energy Technology OVERVIEW NEED FOR INDIAN WIND GRID CODE Wind energy constitutes 6% of the installed capacity in the power scenario
More informationPeak West-wide System Model Validation Activities
Peak West-wide System Model Validation Activities 10/24/2016 Brett Wangen Hongming Zhang Gareth Lim Purpose of This Discussion Provide West-wide System Model (WSM) overview Give insight into ongoing model
More informationComparative Analysis between IG and DFIG for Wind Energy Conversion Systems using STATCOM
International Journal of Energy and Power Engineering 2014; 3(6-2): 21-26 Published online November 27, 2014 (http://www.sciencepublishinggroup.com/j/ijepe) doi: 10.11648/j.ijepe.s.2014030602.14 ISSN:
More informationOnline Security Analysis of Power Grids with High Wind Penetration. By Ivan M. Dudurych, Alan Rogers, Robbie Aherne, Lei Wang, Fred Howell, and Xi Lin
Safety in Numbers Digital Object Identifi er 10.1109/MPE.2011.2178283 Date of publication: 22 February 2012 62 IEEE power & energy magazine 1540-7977/12/$31.00 2012 IEEE march/april 2012 By Ivan M. Dudurych,
More informationRegulation and Frequency Response Service Capability of Modern Wind Power Plants
1 Regulation and Frequency Response Service Capability of Modern Wind Power Plants Germán Claudio Tarnowski, Philip Carne Kjær, Søren Dalsgaard, Anders Nyborg Technology R&D, Vestas Wind Systems A/S, Denmark
More informationMOD Steady-State and Dynamic System Model Validation
MOD-033-1 Steady-State and Dynamic System Model Validation A. Introduction 1. Title: Steady-State and Dynamic System Model Validation 2. Number: MOD-033-1 3. Purpose: To establish consistent validation
More informationStandard MH-TPL Transmission System Planning Performance Requirements
A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...
More informationUsing PMU data for model validation of wind power plants. Pouyan Pourbeik, EPRI or 7/30/14 IEEE PES GM, July 2014
1 Using PMU data for model validation of wind power plants Pouyan Pourbeik, EPRI ppourbeik@epri.com or pouyan@ieee.org 7/30/14 IEEE PES GM, July 2014 MODEL VALIDATION REQUIREMENTS IN THE USA 2 Standards/Policies:
More informationAddressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015
Addressing System Restoration Issues for the ISO New England System Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Key Power System and Market Facts (2014) 6.5 million households
More informationInvestigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection
7th Solar Integration Workshop, 24-25 October 2017, Berlin, Germany Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection Baheej
More information1.3 Planning Assumptions and Model Development
Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission
More informationNext Generation EMS Control Center
Next Generation EMS Control Center JST-NSF-DFG-RCN Workshop on Distributed Energy Management Systems Washington DC April 20th, 2015 Jay Giri Director, Power Systems Technology & Strategic Initiatives Redmond,
More informationNERC PLANNING STANDARDS
NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation
More informationTransmission Planning Process. Study Scope for
2018-2019 Transmission Planning Process Study Scope for Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study May 23, 2018 Final
More informationOperating Procedure PURPOSE... 2
No. 3100 Table of Contents PURPOSE... 2 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1. Background... 3 2.2. Scope/ Applicability... 3 3. PROCEDURE DETAIL... 4 3.1. Acceptable System Performance
More informationMitigating Extraordinary Events using Wide Area Monitoring Applications
2, rue d Artois, F-75008 PARIS 53 RECIFE 20 http : //www.cigre.org Mitigating Extraordinary Events using Wide Area Monitoring Applications E. JOHANSSON, K. UHLEN, G. KJØLLE Norwegian University of Science
More informationTransmission Planning Process. Study Scope for
2018-2019 Transmission Planning Process Study Scope for Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study April 12, 2018 DRAFT
More informationDynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs
Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs RE integration workshop, Chennai January 23, 2018 Zakir H Rather, IIT Bombay Email: zakir.rather@iitb.ac.in Wind
More informationPage 1 of 5 Version 1
GREATER BAY AREA BLACKSTART TECHNICAL VARIABLES and CRITERIA Geographic Area of Consideration Upon the loss of AC to the Greater Bay Area (GBA), the potential blackstart resource must support the restoration
More informationGrid Connection and Power Quality Optimization of Wind Power Plants
Grid Connection and Power Quality Optimization of Wind Power Plants Fikri Baris UZUNLAR 1, Onder GULER 2, Ozcan KALENDERLI 3 1, 2 Istanbul Technical University, Energy Institute, Istanbul, Turkey barisuzunlar@hotmail.com,
More informationCALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL
VOLUME NO. III Page No. 655 CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL VOLUME NO. III Page No. 656 ANCILLARY SERVICES REQUIREMENTS PROTOCOL Table of Contents ASRP 1
More informationSteady State Power System Security Analysis with PowerWorld Simulator
Steady State Power System Security Analysis with PowerWorld Simulator S8: Security Analysis for a Generator Interconnection Study 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com
More informationApril and May 2018 Fault Induced Solar Photovoltaic Resource Interruption Disturbances Report
April and May 2018 Fault Induced Solar Photovoltaic Resource Interruption Disturbances Report Southern California Events: April 20, 2018 and May 11, 2018 Joint NERC and WECC Staff Report January 2019 NERC
More informationPost SAR July day Formal Comment Period with Parallel Ballot July 2013
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed
More informationCapacity and Location Effects of Wind Turbine Energy Systems on Power Systems Stability
International Journal on Power Engineering and Energy (IJPEE) Vol. (4) No. () ISSN Print (234 738) and Online (234 73X) January 23 Capacity and Location Effects of Wind Turbine Energy Systems on Power
More informationCalifornia Independent System Operator (CAISO) Challenges and Solutions
California Independent System Operator (CAISO) Challenges and Solutions Presented by Jim Hiebert EMS Power Technology Engineer Lead California ISO by the numbers 65,225 MW of power plant capacity 50,270
More informationPlanning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES
Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Effective Date: September 11, 2017 Revision History Date Version Description June 6, 1998 0.0 Initial LGEE document
More informationGreat Basin Transmission ITP Submission to California ISO. May 2018
Great Basin Transmission ITP Submission to California ISO May 2018 LS Power Power generation and transmission company formed in 1990 39,000+ MW Power generation development, construction or operations
More informationIVGTF 1-7: Performance of Distributed Variable Resources During and After System Disturbance
IVGTF 1-7: Performance of Distributed Variable Resources During and After System Disturbance John Moura, NERC Planning Committee Meeting December 10-11, 2013 Background This task was one of 12 recommendations
More informationComparative Analysis of Wind Energy Conversion System using DFIG and IG
1 Comparative Analysis of Wind Energy Conversion System using DFIG and IG Haroon Ashfaq 1, Surendra Kumar Tripathi 2 Assistant Professor 1, Associate Professor 2 Department of Electrical Engineering Jamia
More informationReliabilityFirst Regional Criteria 1. Verification and Data Reporting of Generator Gross and Net Reactive Power Capability
ReliabilityFirst Regional Criteria 1 Verification and Data Reporting of Generator Gross and Net Reactive Power Capability 1 A ReliabilityFirst Board of Directors approved good utility practice document
More informationIntegrating High Levels of Variable Renewable Energy Sources
Integrating High Levels of Variable Renewable Energy Sources Erik Ela EPRI Grid Ops and Planning eela@epri.com NYISO Environmental Advisory Council Troy, NY May 6, 2016 EPRI Grid Operations & Planning
More informationNORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013
NORTHERN TIER TRANSMISSION GROUP (NTTG) 2012-2013 BIENNIAL TRANSMISSION PLAN DRAFT SUMMARY REPORT - January 2013 Executive Summary: This report summarizes the findings of power flow studies to determine:
More informationAnalysis of Central East Voltage for Hydro-Quebec Transfers Above 1200 MW Summer 2001
Approved by the Operating Committee - July 2001 Analysis of Central East Voltage for Summer 2001 June 6, 2001 Prepared by NYISO Operations Engineering Analysis of Central East Voltage for Summer 2001
More informationLS Power. Southwest Intertie Project (SWIP) North. NTTG Stakeholder Meeting April 12, Bringing Energy Forward
LS Power Southwest Intertie Project (SWIP) North NTTG Stakeholder Meeting April 12, 2016 LS Power LS Power is a power generation and transmission group Power Generation Transmission Acquisition Over 32,000
More information2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS
21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS RAMU
More informationApril 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403
AMERICAN ELECFRIC POWER BOUNDLESS F.1'ERGY" American Electric Power 8500 Smiths Mill Road New Albany, OH 43054 www.aep.com April 26, 2017 PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination
More informationTSOs, taking into account the following: Whereas
All TSOs proposal for a common grid model methodology in accordance with Articles 67(1) and 70(1) of Commission Regulation (EU) 2017/1485 of 02 August 2017 establishing a guideline on electricity transmission
More informationStandard Development Timeline
Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).
More information