BPA Wind Voltage Control Requirements

Size: px
Start display at page:

Download "BPA Wind Voltage Control Requirements"

Transcription

1 BPA Wind Voltage Control Requirements PJM Conference Dmitry Kosterev Bonneville Power Administration

2 Many of BPA Paths are Stability-Limited Cross-Cascades North Montana - Northwest Cross-Cascades South Wind Pacific HVDC Intertie California Oregon Intertie Slide 2

3 Pre-2007 Projects Wind generation amount was below 500 MW Wind power plants were not required to contribute to voltage control Required to operate at unity power factor Size switched reactive to compensate for reactive power losses Many operational challenges were observed Slide 3

4 Customer Impacts Voltage versus Power for a Wind Farm (Actual Operating Data) Voltage Voltage (Per Unit) 1 Wind Farm Voltage Customer Voltage Power Power (Per Unit of Full Output) Excessive LTC operations Slide 4

5 Voltage (per unit) Power (MW) MW WPP Connected to 115-kV Voltages Time (min) Wind Total Power kV bus 34.5-kV bus Time (min) Wind Total Reactive Power 0 These are actual recordings Project did not have dynamic reactive capabilities Several oscillatory events were observed with all lines in service The power output was curtailed STATCOM with voltage controller was installed Reactive (MVAR) Time (min) Slide 5

6 Wind power ramp Voltage (kv) Voltage Early plants do not have STATCOMs and use only shunt caps Power (MW) Reactive (MVAR) Time (min) Active Power Time (min) Reactive Power Time (min) Operate mainly in power factor mode As POI voltage declines WPP draws larger amount of reactive power Slide 6

7 Wind Ramp PV-Curve for same wind ramp 243 PV Plot - Voltage versus Wind Total 242 Voltage (kv) The edge All lines in service Power (MW) Slide 7

8 Modeling (Lesson Learned) Wind Power Plant models were unable to predict the observed the stability issues ahead of time Model tuning was required to match in principle the disturbance recordings with reality Static powerflow snapshots were often found inadequate, there was a need for a time-sequence simulation of power ramps

9 Modeling BPA made a major effort on improving powerflow models for WPPs based on WECC Guidelines for WPP Powerflow Modeling BPA is participating in DOE-NREL-UWIG project on dynamic model validation BPA requires all new projects connecting at 230-kV level to install Phasor Measurement Units (PMUs) / extended DFRs at POIs BPA is working with the WPP owners on retrofitting the existing WPPs with PMUs Slide 9

10 2006 Study BPA conducted a large-scale study to determine the impact of 3,000 MW of wind on system macro stability The study concluded that the wind power plants need to provide voltage Major voltage stability, transient stability, and undampened oscillations were observed should wind operate in power factor mode, resulting in intertie derating Slide 10

11 Voltage Control Requirements BPA requires wind power plants to provide voltage control and reactive power to support the grid just like other large generation projects How much reactive is needed: Dynamic reactive sized to provide continuous +/ power factor at 34.5-kV bus Switched shunts to compensate for reactive power losses between WTGs and Point Of Interconnection, high switching duty Slide 11

12 100 MW Type 2 with STATCOM W 1.0 pf Three 10 MVAR switched shunts capacitors to compensate for steady-state reactive losses, high switching duty (can be on BPA high side) +/- 16 MVAR STATCOM +/-32 MVAR 2-second overload capability W Slide 12

13 100 MW Type 3 or 4 Wind Generator Example W W Two 9 MVAR switched shunts capacitors to compensate for steady-state reactive losses, high switching duty (can be on BPA HV bus for several plants) +/ pf (+/- 33 MVAR) continuously controllable Reactive power deliverability Slide 13

14 Voltage Control Requirements How to control reactive resources: Operate in continuous (no dead-band!) voltage control mode, control POI voltage to BPA schedule with reactive droop Switching shunts to maximize the availability of dynamic capabilities at the plant Slide 14

15 POI Voltage Voltage Control Mode High Side Voltage Control Power Factor / VAR Control HSVC with a Droop (5.8% on plant MW base) Power Plant POI Reactive Power 15 Slide 15

16 Observed Challenges Reactive power deliverability Collector system voltage raise prevents WPP from delivering VARs to POI Shunt capacitor availability Long discharge time Reactive power coordination among several WPPs in the same wind hub Slide 16

17 250.0 Jones Canyon 230-kV Voltage B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Leaning Juniper #2B V-Q kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : Leaning Juniper #2B MW MW kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ :00 Leaning Juniper #2B MVAR MVAR /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : M VAR Slide 17

18 250.0 Jones Canyon 230-kV Voltage B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Leaning Juniper #1 V-Q kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : Leaning Juniper #1 MW MW kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ :00 Leaning Juniper #1 MVAR MVAR /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : M VAR Slide 18

19 250.0 Jones Canyon 230-kV Voltage B O N N E V I L L E P O W E R A D M I N I S T R A T I O N Rattle Snake V-Q kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : Rattle Snake MW MW 60.0 kv /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ :00 Rattle Snake MVAR MVAR /27/ :00 12/28/2011 0:45 12/28/2011 4:30 12/28/2011 8:15 12/28/ : M VAR Slide 19

20 Wind Hub Generation Situational Awareness Slide 20

21 BPA Activities in Progress Voltage control Working with WPP operators on implementing a droop control Coordination of reactive resources in a wind hub Modeling and Monitoring Projects to install and integrate WPP PMUs DOE-UWIG Wind Modeling Project Situational Awareness SCADA alarming, PI applications for voltage control monitoring Dynamic transfers WECC VGS Planning Guideline Slide 21

Collaborative Approach for Wind Power Plant Model Data and Validation

Collaborative Approach for Wind Power Plant Model Data and Validation Collaborative Approach for Wind Power Plant Model Data and Validation Dmitry Kosterev, Steve Yang and Gordon Kawaley, BPA WECC MVWG October 5, 2017 1 Regulatory Landscape NERC MOD-032 Data for Power System

More information

What makes a Wind Plant Grid Friendly?

What makes a Wind Plant Grid Friendly? Stable Renewable Plant Voltage and Reactive Power Control NERC ERSTF June 11-12, 2014 Sebastian Achilles Nicholas Miller Einar Larsen Jason MacDowell GE Energy Consulting 1 / Topics Features of modern

More information

Daniel Feltes Phone: Fax:

Daniel Feltes Phone: Fax: Coordination of Controls of Renewable Power Plants to Meet Steady State and Dynamic Response Requirements for Voltage Control and Reactive Power Supply Dinemayer Silva Phone: 518-395-5169 Fax: 518-346-2777

More information

DECISIONS on operating transfer limits and transmission

DECISIONS on operating transfer limits and transmission 1144 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 19, NO. 2, MAY 2004 Hydro Turbine-Governor Model Validation in Pacific Northwest Dmitry Kosterev Abstract This paper presents an approach for generator model

More information

Briefing on using renewables to integrate renewables

Briefing on using renewables to integrate renewables Briefing on using renewables to integrate renewables Clyde Loutan, Sr. Advisor, Renewable Energy Integration Board of Governors Meeting General Session December 14-15, 2016 Can variable energy resources

More information

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report Generator Interconnection Affected System Impact Study Plains & Eastern Clean Line Final Report May 19, 2015 MISO 2985 Ames Crossing Eagan Minnesota - 55121 http://www.misoenergy.org Midcontinent Independent

More information

Hydro-Quebec s experience with HYPERSIM Real-time Power System Simulator

Hydro-Quebec s experience with HYPERSIM Real-time Power System Simulator Hydro-Quebec s experience with HYPERSIM Real-time Power System Simulator Christian Larose, Power System Simulation, Hydro-Québec (CANADA) June 26, 2013 Presentation overview > Application of Hypersim at

More information

Harnessing Renewables in Power System Restoration

Harnessing Renewables in Power System Restoration Harnessing Renewables in Power System Restoration Dr. Wei Sun, and Amir Golshani Assistant Professor, EECS Dept. University of Central Florida (South Dakota State University) Panel: Cascading Failures:

More information

Consortium for Electric Reliability Technology Solutions (CERTS)

Consortium for Electric Reliability Technology Solutions (CERTS) Consortium for Electric Reliability Technology Solutions (CERTS) CERTS-CAISO Meeting Phasor Applications for Monitoring, Alarming & Control February 17 th, 2006 Joe Eto, Jim Dyer, Manu Parashar OUTLINE

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

WWSIS - 3: Western Frequency Response and Transient Stability Study

WWSIS - 3: Western Frequency Response and Transient Stability Study WWSIS - 3: Western Frequency Response and Transient Stability Study GE Energy Nicholas W. Miller (PM) Miaolei Shao Slobodan Pajic Rob D Aquila NREL Kara Clark (PM) NERC ERSTF Briefing Atlanta December

More information

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN

COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN COLUMBIAGRID 2018 SYSTEM ASSESSMENT DRAFT STUDY PLAN January 11, 2018 ColumbiaGrid 8338 NE Alderwood Road, Suite 140 Portland, OR 97220 www.columbiagrid.org (503) 943-4940 8338 NE Alderwood Road, Suite

More information

California Independent System Operator Renewable Integration Study

California Independent System Operator Renewable Integration Study California Independent System Operator Renewable Integration Study Clyde Loutan Proposed Transmission Plan for Integration of Renewables Transmission System Analysis - Overview Joint Study between the

More information

Reliability Guideline

Reliability Guideline Reliability Guideline Power Plant Model Verification for Inverter-Based Resources June 2018 NERC Report Title Report Date I Table of Contents Preface... iv Preamble... v Executive Summary... vi Introduction...1

More information

GOLDEN VALLEY ELECTRIC ASSOCIATION

GOLDEN VALLEY ELECTRIC ASSOCIATION October 13, 2008 GOLDEN VALLEY ELECTRIC ASSOCIATION Eva Creek Wind Farm-Limited Study Doubly Fed Asynchronous Generators Power Flow, Reactive Compensation, Transient Stability Revision 0 PROJECT NUMBER:

More information

Reliability Guideline

Reliability Guideline Reliability Guideline Power Plant Model Verification for Inverter-Based Resources September 2018 NERC Report Title Report Date I Table of Contents Preface... iv Preamble... v Executive Summary... vi Introduction...

More information

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL

Case Metrics 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality Metrics FINAL Case s 2015 Summer Base Case Quality Assessment Phase I Powerflow and Dynamics Case Quality s FINAL Introduction Powerflow and dynamics cases are the foundation of virtually all power system studies. Calculations

More information

Critical Load Serving Capability by Microgrid using 100% Renewable Energy

Critical Load Serving Capability by Microgrid using 100% Renewable Energy 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Critical Load Serving Capability by Microgrid using 100% Renewable Energy P. PENKEY,

More information

Improving Reliability Through Better Models

Improving Reliability Through Better Models Improving Reliability Through Better Models By Philip Overholt, Dmitry Kosterev, Joseph Eto, Steve Yang, and Bernard Lesieutre The Office of Electricity Delivery and Energy Reliability of the U.S. Department

More information

Big Data Analysis. ipcgrid 30 March 16. Gordon Matthews, P.E. Bonneville Power Administration Technology Innovation

Big Data Analysis. ipcgrid 30 March 16. Gordon Matthews, P.E. Bonneville Power Administration Technology Innovation Big Data Analysis ipcgrid 30 March 16 Gordon Matthews, P.E. Bonneville Power Administration Technology Innovation BPA Overview Bonneville Power Administration (BPA) is a Federal Power Marketing Agency

More information

2012 Grid of the Future Symposium. Modeling and Simulation of Advanced Reactive Compensation Systems in Renewable Energy Applications

2012 Grid of the Future Symposium. Modeling and Simulation of Advanced Reactive Compensation Systems in Renewable Energy Applications , rue d Artois, F78 PARIS CIGRE US National Committee http : //www.cigre.org Grid of the Future Symposium Modeling and Simulation of Advanced Reactive Compensation Systems in Renewable Energy Applications

More information

Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study

Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study 2018-2019 Transmission Planning Process Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study Ebrahim Rahimi Lead Regional Transmission

More information

Technical considerations for integration of distributed renewables on the grid

Technical considerations for integration of distributed renewables on the grid Technical considerations for integration of distributed renewables on the grid A paper by Dr Charlotte Higgins, Dr Bunmi Adefajo & Kumbuyani Chisoro Kumbuyani Chisoro Manager Southern Africa TNEI Services

More information

Western Wind & Solar Integration Studies

Western Wind & Solar Integration Studies Western Wind & Solar Integration Studies Kara Clark, Greg Brinkman, NREL Nick Miller, Miaolei Shao, Slobodan Pajic, Rob D Aquila, Bruno Leonardi, GE 3/22/17 NREL is a national laboratory of the U.S. Department

More information

Technical and economical analysis of the wind turbines interconnection with the windfarm substation

Technical and economical analysis of the wind turbines interconnection with the windfarm substation Technical and economical analysis of the wind turbines interconnection with the windfarm substation NICOLAE COROIU Faculty of Electrical Engineering and Industrial Management University of Oradea Oradea,

More information

California ISO Preparing California for a Greener and Smarter Grid

California ISO Preparing California for a Greener and Smarter Grid California ISO Preparing California for a Greener and Smarter Grid Presented by Jim McIntosh Director Operations Executive Advisor California ISO Agenda CAISO Overview Current & Future Challenges Renewables

More information

Utility Tools and Design Modifications to Mitigate the Impact of PV on the Distribution System

Utility Tools and Design Modifications to Mitigate the Impact of PV on the Distribution System Utility Tools and Design Modifications to Mitigate the Impact of PV on the Distribution System? IEA-Task 14/SEPA High Penetration PV Workshop Dec. 1, 2010 Overview Service Territory & PV Activity PV System

More information

July 5, SUBJECT: MT Renewable Action Plan (BPA and Montana Partnership)

July 5, SUBJECT: MT Renewable Action Plan (BPA and Montana Partnership) James Yost Chair Idaho W. Bill Booth Idaho Guy Norman Washington Tom Karier Washington Jennifer Anders Vice Chair Montana Tim Baker Montana Ted Ferrioli Oregon Richard Devlin Oregon July 5, 2018 MEMORANDUM

More information

Connection Study Requirements

Connection Study Requirements Document Release Released: September 20, 2010 The Customer shall comply with all the applicable requirements in this document when performing connection studies to produce the engineering study report.

More information

Centralia Power Plant Closure Study. Initial Study Results DRAFT. March 17, 2011

Centralia Power Plant Closure Study. Initial Study Results DRAFT. March 17, 2011 Centralia Power Plant Closure Study Initial Study Results DRAFT March 17, 2011 Conditions Studied 5 and 10-year Winter and Summer Peak 5-year Light Autumn High Transfers to and from British Columbia Additional

More information

Analysis of Three Recent Blackouts

Analysis of Three Recent Blackouts Analysis of Three Recent Blackouts San Diego Gas & Electric -09/08/2011 Indian Northern Grid 07/30/2012 Indian Northern & Eastern Grids 07/31/2012 Bharat Bhargava Advanced Power System Technologies, Inc.

More information

ISSN Vol.07,Issue.16, November-2015, Pages:

ISSN Vol.07,Issue.16, November-2015, Pages: ISSN 2348 2370 Vol.07,Issue.16, November-2015, Pages:3181-3185 www.ijatir.org Improvement of Power Quality in A Grid Connected Induction Generator Based Wind Farm using Static Compensator K. YOSHMA 1,

More information

A. RECOMMENDATIONS ON PROPOSED RELIABILITY PROJECTS

A. RECOMMENDATIONS ON PROPOSED RELIABILITY PROJECTS Public Advocates Office California Public Utilities Commission 505 Van Ness Avenue San Francisco, California 94102 Tel: 415-703-1584 www.publicadvocates.cpuc.ca.gov COMMENTS OF THE PUBLIC ADVOCATES OFFICE

More information

DRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan -

DRAFT Work in Progress CAISO Integration of Renewable Resources Program (IRRP) - High-Level Program Plan - CAISO 2008-2013 Integration of Renewable Resources Program (IRRP) - High-Level Program Plan - Purpose The purpose of this document is to provide an initial high-level scoping and program plan for the CAISO

More information

Renewable Integration in India

Renewable Integration in India Nihar S Raj Business Head Power Consulting ABB India Limited Renewable Integration in India Agenda Introduction & Plans Duck Curve Challenges with Renewable Integration Grid Impact Studies Demand Management

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

Criteria. C~/v~ ~ ~ ~ G! " A1A "~"" T"""g"'~10N COr'P""''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria

Criteria. C~/v~ ~ ~ ~ G!  A1A ~ Tg'~10N COr'P''~ P LG -C R-0001-V T~c~e: Transmission System Planning Criteria A1A "~"" T"""g"'~10N COr'P""''~ Criteria Department: Document No: System Planning and Strategic Projects P LG -C R-0001-V 19.2 T~c~e: Transmission System Planning Criteria issue gate: Previous Date: February

More information

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA For Compliance with NERC Reliability Standard: TPL-001-4 1/10/2017 Version: 4.2 Table of Contents 1 Revision and Approval History... 2 1.1 Revision

More information

FINAL PROJECT REPORT WECC WIND GENERATOR DEVELOPMENT

FINAL PROJECT REPORT WECC WIND GENERATOR DEVELOPMENT FINAL PROJECT REPORT WECC WIND GENERATOR DEVELOPMENT Appendix III WIND POWER PLANT EQUIVALENCING Prepared for CIEE By: National Renewable Energy Laboratory A CIEE Report - i - Acknowledgments This work

More information

Transmission Expansion Advisory Committee. October 11, 2012

Transmission Expansion Advisory Committee. October 11, 2012 Transmission Expansion Advisory Committee October 11, 2012 Issues Tracking Issues Tracking Open Issues None New Issues 3 2012 RTEP - Renewable Portfolio Standards Scenarios Progress Update Scenario #1

More information

Wind Farm Performance on the Grid: Perception and Reality

Wind Farm Performance on the Grid: Perception and Reality Wind Farm Performance on the Grid: Perception and Reality WindVAR and LVRT Data and Graphs provided by Nicholas W. Miller GE Energy, Energy Consulting 1 GE Energy Wind Energy Grid Performance: A Perception

More information

Research Co-design Activity

Research Co-design Activity Research Co-design Activity A. Purpose of Co-design: The ultimate goals of this co-design activity are to: Directly involve all members of a group to make decisions together that would affect their daily

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

PowerWatch Operating A Wind Farm as a Balancing Authority. Manager, Operational Analytics

PowerWatch Operating A Wind Farm as a Balancing Authority. Manager, Operational Analytics PowerWatch Operating A Wind Farm as a Balancing Authority Presented by Devon Yates Manager, Operational Analytics NaturEner overview NaturEner S.A. - Solar 29 PV MW under operation 81 PV MW in late-stage

More information

Power Quality and Voltage Stability of Power Systems with a large share of Distributed Energy Resources

Power Quality and Voltage Stability of Power Systems with a large share of Distributed Energy Resources University of Texas at Tyler Scholar Works at UT Tyler Electrical Engineering Theses Electrical Engineering Spring 4-30-2012 Power Quality and Voltage Stability of Power Systems with a large share of Distributed

More information

Model Validation on Wind Turbine Generators Using the 2 nd Generation Wind Turbine Generator Models

Model Validation on Wind Turbine Generators Using the 2 nd Generation Wind Turbine Generator Models Model Validation on Wind Turbine Generators Using the 2 nd Generation Wind Turbine Generator Models Pouyan Pourbeik ppourbeik@epri.com WECC REMTF Workshop Salt Lake City, UT 6/17/14 OVERVIEW Standards/Policies:

More information

Phasor measurement units gain credibility through improved test and calibration standards

Phasor measurement units gain credibility through improved test and calibration standards Phasor measurement units gain credibility through improved test and calibration standards Smart grid; PMU calibration position 1 The North American interconnection, or electric transmission grid, is a

More information

Standards de planification du NERC

Standards de planification du NERC Demande R-3498-2002 Standards de planification du NERC PREUVE EN CHEF DE TRANSÉNERGIE Original : 2002-11-27 HQT-4, Document 2 (en liasse) NERC PLANNING STANDARDS North American Electric Reliability Council

More information

Grid Interconnection Issues for Wind Generation

Grid Interconnection Issues for Wind Generation Grid Interconnection Issues for Wind Generation NRECA APPA - DOE Teleconference December 8, 2005 By Thomas A. Wind, PE Wind Utility Consulting Jefferson, Iowa Topics I Will Cover What are the key technical

More information

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators

More information

Impact of Power Management Strategies on Micro-Grid Dynamic Performance

Impact of Power Management Strategies on Micro-Grid Dynamic Performance University of Toronto Department of Electrical and Computer Engineering Impact of Power Management Strategies on Micro-Grid Dynamic Performance Reza Iravani Center for Applied Power Electronics (CAPE)

More information

Voltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998

Voltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998 Western Electricity Coordinating Council Voltage Stability Criteria, Undervoltage Load Shedding Strategy, and Reactive Power Reserve Monitoring Methodology May 1998 VOLTAGE STABILITY CRITERIA, UNDERVOLTAGE

More information

Power Quality

Power Quality DEP2016.12.21.01EN Power Quality www.nidec-industrial.com over 7 GVAr power installed > 75 projects across the globe Our expertise spans a wide range of industries including: Metals/mining Renewable Energy

More information

SESSION 3: Grid Integration Studies for Planning Secure and Reliable System Operations with Expected Shares of Variable Renewables

SESSION 3: Grid Integration Studies for Planning Secure and Reliable System Operations with Expected Shares of Variable Renewables SESSION 3: Grid Integration Studies for Planning Secure and Reliable System Operations with Expected Shares of Variable Renewables Presenter: Eduard Muljadi National Renewable Energy Laboratory 15013 Denver

More information

Coordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function

Coordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function Coordination of Multiple Voltage Controllers of Adjacent Wind Plants Connected to João Câmara II with Droop Function Mariana B. Pereira 1, Sebastian A. Achilles 2, Nath Venkit 2 Energy Consulting General

More information

EAPP interconnection readiness workshop

EAPP interconnection readiness workshop 1 EAPP interconnection readiness workshop Self-Assessment for EAPP/IC -Compliance Rwandan-Grid Gap Analysis & Proposed mitigations GENERATION, TRANSMISSION & DISTRIBUTION 01 st October, 2018 INTRODUCTION

More information

Dynamic Response of Large Wind Power Plant Affected by Diverse Conditions at Individual Turbines

Dynamic Response of Large Wind Power Plant Affected by Diverse Conditions at Individual Turbines Dynamic Response of Large Wind Power Plant Affected by Diverse Conditions at Individual Turbines Marcelo A. Elizondo Pacific Northwest National Laboratory Seattle, Washington USA Marcelo.Elizondo@pnnl.gov

More information

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar

California ISO Energy Imbalance Market Operations Overview. June 10, 2014 Webinar California ISO Energy Imbalance Market Operations Overview June 10, 2014 Webinar Objectives 1. EIM Overview 2. CAISO s process in mitigating Unscheduled Flow (USF) 3. WebSAS tool: how dynamic and pseudo

More information

Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012

Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012 Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012 1 Presentation Overview Joint Working Group The Issue Structure of the Report Wind Plant Configuration Wind Turbine Generators

More information

CENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE

CENTRE FOR WIND ENERGY TECHNOLOGY CHENNAI INDIAN WIND GRID CODE CHENNAI INDIAN WIND GRID CODE Rajesh Katyal Unit Chief, R&D Centre for Wind Energy Technology OVERVIEW NEED FOR INDIAN WIND GRID CODE Wind energy constitutes 6% of the installed capacity in the power scenario

More information

Peak West-wide System Model Validation Activities

Peak West-wide System Model Validation Activities Peak West-wide System Model Validation Activities 10/24/2016 Brett Wangen Hongming Zhang Gareth Lim Purpose of This Discussion Provide West-wide System Model (WSM) overview Give insight into ongoing model

More information

Comparative Analysis between IG and DFIG for Wind Energy Conversion Systems using STATCOM

Comparative Analysis between IG and DFIG for Wind Energy Conversion Systems using STATCOM International Journal of Energy and Power Engineering 2014; 3(6-2): 21-26 Published online November 27, 2014 (http://www.sciencepublishinggroup.com/j/ijepe) doi: 10.11648/j.ijepe.s.2014030602.14 ISSN:

More information

Online Security Analysis of Power Grids with High Wind Penetration. By Ivan M. Dudurych, Alan Rogers, Robbie Aherne, Lei Wang, Fred Howell, and Xi Lin

Online Security Analysis of Power Grids with High Wind Penetration. By Ivan M. Dudurych, Alan Rogers, Robbie Aherne, Lei Wang, Fred Howell, and Xi Lin Safety in Numbers Digital Object Identifi er 10.1109/MPE.2011.2178283 Date of publication: 22 February 2012 62 IEEE power & energy magazine 1540-7977/12/$31.00 2012 IEEE march/april 2012 By Ivan M. Dudurych,

More information

Regulation and Frequency Response Service Capability of Modern Wind Power Plants

Regulation and Frequency Response Service Capability of Modern Wind Power Plants 1 Regulation and Frequency Response Service Capability of Modern Wind Power Plants Germán Claudio Tarnowski, Philip Carne Kjær, Søren Dalsgaard, Anders Nyborg Technology R&D, Vestas Wind Systems A/S, Denmark

More information

MOD Steady-State and Dynamic System Model Validation

MOD Steady-State and Dynamic System Model Validation MOD-033-1 Steady-State and Dynamic System Model Validation A. Introduction 1. Title: Steady-State and Dynamic System Model Validation 2. Number: MOD-033-1 3. Purpose: To establish consistent validation

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Using PMU data for model validation of wind power plants. Pouyan Pourbeik, EPRI or 7/30/14 IEEE PES GM, July 2014

Using PMU data for model validation of wind power plants. Pouyan Pourbeik, EPRI or 7/30/14 IEEE PES GM, July 2014 1 Using PMU data for model validation of wind power plants Pouyan Pourbeik, EPRI ppourbeik@epri.com or pouyan@ieee.org 7/30/14 IEEE PES GM, July 2014 MODEL VALIDATION REQUIREMENTS IN THE USA 2 Standards/Policies:

More information

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Addressing System Restoration Issues for the ISO New England System Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Key Power System and Market Facts (2014) 6.5 million households

More information

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection 7th Solar Integration Workshop, 24-25 October 2017, Berlin, Germany Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection Baheej

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

Next Generation EMS Control Center

Next Generation EMS Control Center Next Generation EMS Control Center JST-NSF-DFG-RCN Workshop on Distributed Energy Management Systems Washington DC April 20th, 2015 Jay Giri Director, Power Systems Technology & Strategic Initiatives Redmond,

More information

NERC PLANNING STANDARDS

NERC PLANNING STANDARDS NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation

More information

Transmission Planning Process. Study Scope for

Transmission Planning Process. Study Scope for 2018-2019 Transmission Planning Process Study Scope for Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study May 23, 2018 Final

More information

Operating Procedure PURPOSE... 2

Operating Procedure PURPOSE... 2 No. 3100 Table of Contents PURPOSE... 2 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 3 2.1. Background... 3 2.2. Scope/ Applicability... 3 3. PROCEDURE DETAIL... 4 3.1. Acceptable System Performance

More information

Mitigating Extraordinary Events using Wide Area Monitoring Applications

Mitigating Extraordinary Events using Wide Area Monitoring Applications 2, rue d Artois, F-75008 PARIS 53 RECIFE 20 http : //www.cigre.org Mitigating Extraordinary Events using Wide Area Monitoring Applications E. JOHANSSON, K. UHLEN, G. KJØLLE Norwegian University of Science

More information

Transmission Planning Process. Study Scope for

Transmission Planning Process. Study Scope for 2018-2019 Transmission Planning Process Study Scope for Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study April 12, 2018 DRAFT

More information

Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs

Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs RE integration workshop, Chennai January 23, 2018 Zakir H Rather, IIT Bombay Email: zakir.rather@iitb.ac.in Wind

More information

Page 1 of 5 Version 1

Page 1 of 5 Version 1 GREATER BAY AREA BLACKSTART TECHNICAL VARIABLES and CRITERIA Geographic Area of Consideration Upon the loss of AC to the Greater Bay Area (GBA), the potential blackstart resource must support the restoration

More information

Grid Connection and Power Quality Optimization of Wind Power Plants

Grid Connection and Power Quality Optimization of Wind Power Plants Grid Connection and Power Quality Optimization of Wind Power Plants Fikri Baris UZUNLAR 1, Onder GULER 2, Ozcan KALENDERLI 3 1, 2 Istanbul Technical University, Energy Institute, Istanbul, Turkey barisuzunlar@hotmail.com,

More information

CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL

CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL VOLUME NO. III Page No. 655 CALIFORNIA INDEPENDENT SYSTEM OPERATOR ANCILLARY SERVICES REQUIREMENTS PROTOCOL VOLUME NO. III Page No. 656 ANCILLARY SERVICES REQUIREMENTS PROTOCOL Table of Contents ASRP 1

More information

Steady State Power System Security Analysis with PowerWorld Simulator

Steady State Power System Security Analysis with PowerWorld Simulator Steady State Power System Security Analysis with PowerWorld Simulator S8: Security Analysis for a Generator Interconnection Study 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com

More information

April and May 2018 Fault Induced Solar Photovoltaic Resource Interruption Disturbances Report

April and May 2018 Fault Induced Solar Photovoltaic Resource Interruption Disturbances Report April and May 2018 Fault Induced Solar Photovoltaic Resource Interruption Disturbances Report Southern California Events: April 20, 2018 and May 11, 2018 Joint NERC and WECC Staff Report January 2019 NERC

More information

Post SAR July day Formal Comment Period with Parallel Ballot July 2013

Post SAR July day Formal Comment Period with Parallel Ballot July 2013 Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard becomes effective. Development Steps Completed

More information

Capacity and Location Effects of Wind Turbine Energy Systems on Power Systems Stability

Capacity and Location Effects of Wind Turbine Energy Systems on Power Systems Stability International Journal on Power Engineering and Energy (IJPEE) Vol. (4) No. () ISSN Print (234 738) and Online (234 73X) January 23 Capacity and Location Effects of Wind Turbine Energy Systems on Power

More information

California Independent System Operator (CAISO) Challenges and Solutions

California Independent System Operator (CAISO) Challenges and Solutions California Independent System Operator (CAISO) Challenges and Solutions Presented by Jim Hiebert EMS Power Technology Engineer Lead California ISO by the numbers 65,225 MW of power plant capacity 50,270

More information

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES Effective Date: September 11, 2017 Revision History Date Version Description June 6, 1998 0.0 Initial LGEE document

More information

Great Basin Transmission ITP Submission to California ISO. May 2018

Great Basin Transmission ITP Submission to California ISO. May 2018 Great Basin Transmission ITP Submission to California ISO May 2018 LS Power Power generation and transmission company formed in 1990 39,000+ MW Power generation development, construction or operations

More information

IVGTF 1-7: Performance of Distributed Variable Resources During and After System Disturbance

IVGTF 1-7: Performance of Distributed Variable Resources During and After System Disturbance IVGTF 1-7: Performance of Distributed Variable Resources During and After System Disturbance John Moura, NERC Planning Committee Meeting December 10-11, 2013 Background This task was one of 12 recommendations

More information

Comparative Analysis of Wind Energy Conversion System using DFIG and IG

Comparative Analysis of Wind Energy Conversion System using DFIG and IG 1 Comparative Analysis of Wind Energy Conversion System using DFIG and IG Haroon Ashfaq 1, Surendra Kumar Tripathi 2 Assistant Professor 1, Associate Professor 2 Department of Electrical Engineering Jamia

More information

ReliabilityFirst Regional Criteria 1. Verification and Data Reporting of Generator Gross and Net Reactive Power Capability

ReliabilityFirst Regional Criteria 1. Verification and Data Reporting of Generator Gross and Net Reactive Power Capability ReliabilityFirst Regional Criteria 1 Verification and Data Reporting of Generator Gross and Net Reactive Power Capability 1 A ReliabilityFirst Board of Directors approved good utility practice document

More information

Integrating High Levels of Variable Renewable Energy Sources

Integrating High Levels of Variable Renewable Energy Sources Integrating High Levels of Variable Renewable Energy Sources Erik Ela EPRI Grid Ops and Planning eela@epri.com NYISO Environmental Advisory Council Troy, NY May 6, 2016 EPRI Grid Operations & Planning

More information

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013

NORTHERN TIER TRANSMISSION GROUP (NTTG) BIENNIAL TRANSMISSION PLAN. DRAFT SUMMARY REPORT - January 2013 NORTHERN TIER TRANSMISSION GROUP (NTTG) 2012-2013 BIENNIAL TRANSMISSION PLAN DRAFT SUMMARY REPORT - January 2013 Executive Summary: This report summarizes the findings of power flow studies to determine:

More information

Analysis of Central East Voltage for Hydro-Quebec Transfers Above 1200 MW Summer 2001

Analysis of Central East Voltage for Hydro-Quebec Transfers Above 1200 MW Summer 2001 Approved by the Operating Committee - July 2001 Analysis of Central East Voltage for Summer 2001 June 6, 2001 Prepared by NYISO Operations Engineering Analysis of Central East Voltage for Summer 2001

More information

LS Power. Southwest Intertie Project (SWIP) North. NTTG Stakeholder Meeting April 12, Bringing Energy Forward

LS Power. Southwest Intertie Project (SWIP) North. NTTG Stakeholder Meeting April 12, Bringing Energy Forward LS Power Southwest Intertie Project (SWIP) North NTTG Stakeholder Meeting April 12, 2016 LS Power LS Power is a power generation and transmission group Power Generation Transmission Acquisition Over 32,000

More information

2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS

2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2012 Grid of the Future Symposium METHODOLOGY OF COMPUTING SIMULTANEOUS VARIABLE TRANSFER LIMITS ON MULTIPLE PATHS RAMU

More information

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403 AMERICAN ELECFRIC POWER BOUNDLESS F.1'ERGY" American Electric Power 8500 Smiths Mill Road New Albany, OH 43054 www.aep.com April 26, 2017 PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination

More information

TSOs, taking into account the following: Whereas

TSOs, taking into account the following: Whereas All TSOs proposal for a common grid model methodology in accordance with Articles 67(1) and 70(1) of Commission Regulation (EU) 2017/1485 of 02 August 2017 establishing a guideline on electricity transmission

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information