1 ADDENDUM #1 February 6, 2015 RFP WOLFTRAP CREEK STREAM RESTORATION ******ATTENTION BIDDERS****** (To be completed and returned with bid response) A request was made that the Stormwater Local Assistance (SLAF) grant package and the supporting documentation be made available to interested firms. Those documents are attached to this Addendum. ALL OTHER TERMS, CONDITIONS, AND SPECIFICATIONS SHALL REMAIN THE SAME. A copy of this signed addendum must accompany your response as an acknowledgment of its receipt: NAME AND ADDRESS OF FIRM: PHONE #: NAME OF AUTHORIZED REPRESENTATIVE: Please Print SIGNATURE: DATE: Page 1

2

3

4

5

6 Wolftrap Creek/Difficult Run - Stream Restoration Grant Application Stormwater Local Assistance Fund 2014 Town of Vienna Grant Application for a Stream Restoration Project to the 2014 Stormwater Local Assistance Fund

7 Contents A: Background... 2 B: Environmental Benefit... 4 C: Statement of Need... 5 Condition of the Stream Sections... 5 TP (Total Phosphorus)... 6 Stream Restoration Description... 7 Maintenance... 7 D: Grant Application Summary... 8 I. POLLUTION REDUCTION... 8 II. COST EFFECTIVENESS... 8 III. IMPAIRED WATER BODIES... 8 IV. FISCAL STRESS... 8 V. READINESS TO PROCEED... 9 VI. PHASE II (SMALL) MS E: Closing... 9 Figure 1 Location Map and Extents of Proposed Project... 4 Figure 2 - Section ' eroded bank... 5 Figure 3 - Stream Condition Types... 5 Figure 4 Sinuosity Example... 5 Figure 5 Difficult Run Channel Evolution Model Map... 5 Figure 6 Difficult Run Sub Watershed Modeling Results... 6 Page 1 of 13

8 A: Background: The Town of Vienna is located approximately 15 miles west of Washington D.C. and is called home by approximately 16,000 residents. With a geographic area of slightly over 4 square miles the Town is one of a handful of incorporated areas within Fairfax County. The Town was primarily developed during the 1950s and 60s without the environmental benefits of Stormwater Management and Water Quality Treatment. Further subdivision development in the 1980 s throughout the Town of Vienna increased impervious areas, enclosed tributaries, straightened streams, removed riparian buffers and steepened stream banks to allow more homes to be built. Recently the Town has experienced a redevelopment boom leading to a further increase in impervious surfaces and a further burden on the receiving water courses. Predictably the receiving streams and channels have experienced incision, erosion and widening in response to the increase in water quantity as a result of 50 plus years of development. Within Vienna s four plus square miles is the watershed for the Wolftrap Creek section of the Difficult Run watershed and subject of this application. The Wolftrap Creek section this proposed project will impact is an unassessed portion categorized as a 3A in the Virginia 2012 Impaired Waters 303(d) category list. However other assessed section are listed as type 5 (the most severe impairments). Additionally the Wolftrap Creek flows to the Potomac and the Potomac is under a TDML. Still, this section shares many of the same issues of assessed sections. Additionally, this section is just upstream of a previous restoration project on Wolftrap. The issues affecting this section are the same as the downstream section previous restored, the previously restored section is described as follows from a Fairfax SlideShare presentation: Before restoration, the stream and the natural habitat were degraded. Poor water quality and loss of the natural habitat are hallmarks of a poor environment Uncontrolled stormwater runoff flowed through the stream and eroded the banks exposing tree roots. Trees were falling which created a safety hazard. Sediment was deposited in the streambed by stormwater runoff. Some aquatic animals raise their young in streambeds. Sediment covers the streambed and kills aquatic animals living there. Undercut stream banks, unbalanced sediment transport and fallen trees, demonstrate the before appearance of the area. (County, 2013) 1 Municipal maintenance funds are only available for occasional dredging of sediment but not for corrective action to prevent the erosion and to naturally stabilize the stream. Stream bank armoring and dredging have been used for years as the standard repair method by Vienna stream maintenance crews. Funding is tight; therefore, problems are not addressed preventatively, but only in reactive mode. This project will show local staff and residents the practical aspects of correcting the problem of stream bank erosion before sediment must be dredged from the stream. As it ages, the stabilization of the problem area will demonstrate how carefully preparing for natural restoration is cheaper in the long run with the elimination of costly dredging. This project will extend closer to the ultimate headwaters and additional 1 From :Wolftrap Stream Restoration in Wildwood Park, Vienna, Virginia, slideshow Page 2 of 13

9 action on this stream will help maintain the previously restored downstream section by reducing the sediment load. In 2013 additional regulation in response to the continuing challenges faced by the Chesapeake Bay went into effect and the Town of Vienna, as a MS4 permitee, will experience additional requirements relating to the water quality in its streams. The town has executed a cooperative agreement with Fairfax County to share responsibility for implementing a joint Chesapeake Bay TDML Action Plan. As a function of these requirements and the cooperative agreement with the Fairfax County the amount of Phosphorus, Nitrogen and Total Suspended Solids will need to be reduced. Vienna, in conjunction with working with the Fairfax County, has a role and responsibility in meeting these requirements. Formal correspondence with Fairfax County has indicated available construction funding for the restoration to constitute the matching funds required for the grant, (Appendix C, Letter from Fairfax County). This application also makes multiple references to Fairfax s Difficult Run Watershed Management Plan. This plan describes the needs and requirements for the future of the watershed, and a path to meeting the requirements of the coming regulations. Page 3 of 13

10 B: Environmental Benefit The primary aim and quantified requirement in meeting the grant application standards is establishing the amount of Total Prosperous to be removed as a result of the proposed project. This project proposes to stabilize approximately 1,020 feet of stream bank within the borders of the town of Vienna, see figure 1. The section for restoration is in the Wolftrap Creek in the Difficult Run watershed just upstream from a previously restored section of stream. This section is located entirely on Town property and is close to the headwater of the stream. As a result of being situated in the headwaters, all downstream sections will benefit from stabilization and restoration that takes place in the upper reaches. The erosion of stream banks causes suspended solids, which may be laden with phosphorus, to be suspended in runoff. Additionally, the restoration of stream banks provides a means of pretreatment for runoff and removal of phosphorus prior to reaching the stream. As outlined in the grant application a credit of lbs per linear foot of restored stream is credited for stream restoration projects. Figure 1 Location Map and Extents of Proposed Project o Approximately 1,020 linear feet of restored Stream: At lbs/ft = lbs of removed Phosphorus Phosphorus amounts were tabulated utilizing the grant application credited rate of lbs/ft, methodology for calculating total phosphorus reduction, Attachment A of the Stormwater Local Assistance Fund grant application. Page 4 of 13

11 C: Statement of Need Condition of the Stream Sections The current condition of the stream sections have been evaluated onsite and photographed as shown to the right, additional photographs are included in Appendix A. In addition to the site visits and photographs taken, the Fairfax County Watershed Plan for the Difficult Run was reviewed for insight into the phosphorus loads arising from the drainage areas. Figure 2 to the right shows the degree of incision and erosion along the banks. While walking the stream several areas of 3 to 4 high eroded banks are clearly visible. In many of these areas existing trees have been undermined and overturned. Figure 4 to the right shows the degree of sinuosity in the stream, again a common sight along this stream. As the stream turns there is too much volume and velocity for the existing soils resulting in erosion and loss of available water quality storage treatment in fringe flood plains. The condition of the stream appears to be a Type III as described by figure 3 below and indicated in figure 5 of the Fairfax Difficult Run Watershed Management Plan Chapter 2 Watershed Condtion report. Stream Restoration Grant Proposal Figure 2 - Section ' eroded bank Figure 4 Sinuosity Example. Figure 3 - Stream Condition Types Figure 5 Difficult Run Channel Evolution Model Map Page 5 of 13

12 TP (Total Phosphorus) In reviewing the Difficult Run watershed management plan, as produced by Fairfax County, several items reference the condition of the streams in the Wolftrap Creek portion of the watershed. From chapter 2 of the report: Table 2.17 shows results of the hydrologic and water quality modeling, normalized by area, so that the sub watersheds and be compared directly. There is a correlation between the amount of development and the hydrologic results. Old courthouse Spring Branch has the highest level of imperviousness and the highest runoff volume. Snakeden branch, Wolftrap Creek, Colvin Run and Piney Branch also show high runoff volume and high levels of imperviousness. The same five sub watersheds also have the highest peak flows. Old Courthouse Spring Branch also shows up with the highest levels of TSS, TN and TP from runoff. Wolftrap Creek, Colvin Run and Snakenden branch also have high levels of these pollutants. Figure 6 Difficult Run Sub Watershed Modeling Results As seen above in the table and quote the Phosphorus load in the Wolftrap Creek watershed is considered very high. This very high rating for phosphorus further supports the need for stream mitigation. A map of the drainage areas is included in Appendix G. Page 6 of 13

13 The streams condition assessment indicates a significant need for restoration and stabilization. In conjunction with the watershed s plan finding that the Wolftrap Creek is inundated with high levels of total phosphorus and the significant drainage area to these stream sections this project represents a prime opportunity to achieve the Total Phosphorus reduction goal of the SLAF grant. Stream Restoration Description The goal of stream restoration is to return the stream to a stable state in which it; neither significantly erodes or fills with sediment, is connected to its floodplain and has an improved habitat condition. In so doing a connection to the floodplain is created, reducing total phosphorus discharge, as well as preventing further erosion and bound total phosphorus discharge to the stream. For incised urban channels, such as this one, there are several options available depending on the severity of the section and the extent of adjacent land. The most extensive restoration portions may move the stream itself, creating a new channel on a new alignment at the original floodplain elevation. Other sections could involve adjusting the cross-section, reducing bank slopes, or creating a new floodplain bench within an over-widened channel. For portions with restricted availability of adjacent land where there is no room to increase meander width, the restoration design will use grade controls to flatten the slope of the stream and dissipate stream energy. In the small sections where it is infeasible to recreate a natural channel less extensive restoration approaches will be undertaken. Such measures include armoring stream banks with rock or bioengineering materials to prevent further erosion and grading to lay back over-steepened banks to create a more stable cross-section. Maintenance Provisions for the long-term maintenance responsibility of the restored stream, including an inspection and maintenance schedule, will be included in the project. Project documents will indicate the specific maintenance requirements for the project as well as the duration and ongoing requirements and responsibilities. The project falls within public land owned by the Town. Page 7 of 13

14 D: Grant Application Summary I. POLLUTION REDUCTION Points will be based on the calculated reduction of total phosphorous (TP) as a result of the proposed project. The established methodology for calculating the TP reduction is outlined in Attachment A. Approximately 1,020 linear feet of restored Stream: At lbs/ft = lbs of removed Phosphorus The project proposes a total of 1,020 linear feet of stream restoration with a total of lbs of removed Phosphorus. II. COST EFFECTIVENESS Points will be based on the projected cost of the project divided by the calculated amount of TP reduction. Project Cost as included on the Grant Application = $890,000 Total Phosphorus Removed = lbs Cost Effectiveness Ratio = $12,471/lb III. IMPAIRED WATER BODIES Points will be based on the location and impact of the proposed project in relation to priority water bodies in the state.. Note: These categories (a b) are additive. a. Project is directly related to the requirements of the Chesapeake Bay TMDL 60 pts. b. Project is directly related to requirements of a local impaired stream TMDL 40 pts. or Project is directly related to a local impaired stream without a TMDL 20 pts. The project is not directly in a TDML plan, the project does however flow to Difficult Run, which has some TDMLs, and then flows onto the Potomac and the Chesapeake Bay both of which have TDMLs. IV. FISCAL STRESS 50 of the points for county and city applicants will be based on the latest available Commission on Local Government composite fiscal stress index. Town applicants will be assigned the points of the surrounding county. Any applicant with a project serving more than one jurisdiction (such as public service authorities or towns located in two counties) will be assigned a weighted average from the component scores. An additional 25 points will be awarded to applicants that have established a dedicated local funding/revenue mechanism for stormwater capital projects The Town of Vienna has a dedicated local funding/revenue mechanism. The Stormwater Tax is collected via Fairfax County and portions thereof are then passed onto Vienna for use in implementing The Town of Vienna s responsibilities. Page 8 of 13

15 V. READINESS TO PROCEED Because it is important that grant recipients proceed quickly with their proposed projects, applicants that can proceed immediately with their proposed projects, or demonstrate an advanced state of readiness, will be given the highest points under this category. Design has been submitted, reviewed, and approved 40 pts. Design submitted / under review 35 pts. Reasonable assurance design will be completed / submitted within 4 months 30 pts. Project identified in current year Capital Improvement Plan or annual budget 20 pts. Project included in Stormwater or Watershed Management Plan 10 pts. Additional 10 points will be awarded if land necessary for the project has already been acquired. The proposed project is in the beginning stages of coordination. Fairfax County has committed to providing the local matching funds for this project (see letter of commitment from Fairfax County in Appendix C. The project will be administered by the Town. Upon notice of award of the grant, the Town will immediately acquire a design engineer and begin the project. It can be expected that an engineer could be under contract within three months of the notice a grant award. No acquisition of property is required for this project. The land for the project is already owned by the Town of Vienna. VI. PHASE II (SMALL) MS4 Applicants that are regulated under the General Permit for the Discharge of Stormwater from Small Municipal Separate Storm Sewer Systems will receive 25 points. The Town of Vienna is regulated under a General Permit for the Discharge of Stormwater from Small Municipal Separate Storm Sewer systems. E: Closing In closing the Town of Vienna appreciates the opportunity to apply for grant match funds for a critical and sorely needed Stormwater management project that will benefit the State, Fairfax County, the Chesapeake Bay and Town while meeting our MS4 responsibilities. Page 9 of 13

16 Appendix A Additional Site Photographs Stream Restoration Grant Proposal Page 10 of 13

17 Appendix B - Letter from Fairfax County Page 11 of 13

18 Appendix C Project Location Map Page 12 of 13

19 Appendix D Drainage Area Map Map Source: *Edited to reflect new project Page 13 of 13

COTTONWOOD CREEK RECLAMATION PHASE I & II

COTTONWOOD CREEK RECLAMATION PHASE I & II COTTONWOOD CREEK RECLAMATION PHASE I & II COTTONWOOD CREEK RECLAMATION Stream Stabilization Approach to Urban Runoff Quality Cherry Creek Basin Water Quality Authority The Problem The Cherry Creek Reservoir

More information

Primer introduction to watershed management Plan Process highlight the major steps of plan development Project types look at some examples of common

Primer introduction to watershed management Plan Process highlight the major steps of plan development Project types look at some examples of common 1 Primer introduction to watershed management Plan Process highlight the major steps of plan development Project types look at some examples of common projects Plan Organization how to read the plan Next

More information

Stream Restoration in the Urban Environment Concepts and Considerations

Stream Restoration in the Urban Environment Concepts and Considerations Stream Restoration in the Urban Environment Concepts and Considerations The Restoration of Our Rivers; October 5, 2012 Matthew A. Van Eps, PE & Sandi J. Formica: Watershed Conservation Resource Center

More information

Integrated Watershed Restoration in Urban Areas

Integrated Watershed Restoration in Urban Areas Integrated Watershed Restoration in Urban Areas Jarrod Karl, Hazen and Sawyer SESWA 2016 Annual Conference Presentation Outline Urban Watershed Challenges Tools for Addressing Impairments Ways of Achieving

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW

COON CREEK WATERSHED DISTRICT PERMIT REVIEW 16-054 Woodland Creek Wetland Banking Restoration Project, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 11 FILE NUMBER: 16-054 ITEM: Woodland Creek

More information

BMP 5.4.2: Protect /Conserve/Enhance Riparian Areas

BMP 5.4.2: Protect /Conserve/Enhance Riparian Areas BMP 5.4.2: Protect /Conserve/Enhance Riparian Areas The Executive Council of the Chesapeake Bay Program defines a Riparian Forest Buffer as "an area of trees, usually accompanied by shrubs and other vegetation,

More information

Appendix B Stormwater Site Plan Submittal Requirements Checklist

Appendix B Stormwater Site Plan Submittal Requirements Checklist Stormwater Site Plan Submittal Requirements Checklist The Submittal Requirements Checklist is intended to aid the design engineer in preparing a Stormwater Site Plan. All items included in the following

More information

Meeting the Chesapeake Bay TMDL

Meeting the Chesapeake Bay TMDL Meeting the Chesapeake Bay TMDL Local Stormwater Perspective Presented by Rob Hopper, PE Developed with Mike Morgan, PE September 14, 2015 Chesapeake Bay TMDL Local Stormwater Perspective Virginia Stormwater

More information

Division of Watershed Stewardship Drainage Program

Division of Watershed Stewardship Drainage Program Not Your Father s Tax Ditch Enhancing Delaware s Drainage Network Through the Use of Natural Channel Design Techniques Division of Watershed Stewardship Drainage Program Presented at the National Conference

More information

Watershed master planning, City of Griffin, Georgia, USA

Watershed master planning, City of Griffin, Georgia, USA Water Resources Management VII 3 Watershed master planning, City of Griffin, Georgia, USA J. K. Kaplan & B. J. Watson Tetra Tech, Water Resources Group, Atlanta, Georgia, USA Abstract Tetra Tech has assisted

More information

Old Mill School Stream Restoration

Old Mill School Stream Restoration Project Overview This conceptual plan restores and stabilizes two consecutive reaches of a highly incised and unstable stream and reconnects them with the floodplain. The restoration reaches are part of

More information

APPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports

APPENDIX H Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports APPENDIX H H.1 Guidance for Preparing and Reviewing CEQA Initial Studies Step 1: Consider the Project Characteristics as Provided by the Project Applicant Review the project application and draft plan

More information

FREQUENTLY ASKED QUESTIONS: URBAN STREAM RESTORATION BMP. David Wood Chesapeake Stormwater Network. Lisa Fraley-McNeal Center for Watershed Protection

FREQUENTLY ASKED QUESTIONS: URBAN STREAM RESTORATION BMP. David Wood Chesapeake Stormwater Network. Lisa Fraley-McNeal Center for Watershed Protection FREQUENTLY ASKED QUESTIONS: David Wood Chesapeake Stormwater Network URBAN STREAM RESTORATION BMP Lisa Fraley-McNeal Center for Watershed Protection Bill Stack Center for Watershed Protection FREQUENTLY

More information

Joint Pollutant Reduction Plan

Joint Pollutant Reduction Plan Paxton Creek Watershed TMDL, Chesapeake Bay PRP, Wildwood Lake PRP, and UNT to Spring Creek PRP August 23, 2017 2018 PAG 13 Regulation NPDES (National Pollutant Discharge Elimination System) Individual

More information

STORM WATER MANAGEMENT STANDARDS DRAFT

STORM WATER MANAGEMENT STANDARDS DRAFT STORM WATER MANAGEMENT STANDARDS 1. Storm Water Management Plans (SWMP) - All development activity that is required to have a permit for land disturbing shall have an approved Storm Water Management Plan

More information

Water Quality Ecosystem Services in the Urban Environment

Water Quality Ecosystem Services in the Urban Environment Water Quality Ecosystem Services in the Urban Environment Dianna Hogan and JV Loperfido ACES 2010 December 7, 2010 U.S. Department of the Interior U.S. Geological Survey Water Quality Ecosystem Services

More information

URBAN STREAM RESTORATION BMP

URBAN STREAM RESTORATION BMP FREQUENTLY ASKED QUESTIONS: URBAN STREAM RESTORATION BMP OVERVIEW In May of 2013, the Water Quality Goal Implementation Team (WQGIT) approved the Final Recommendations of the Expert Panel to Define Removal

More information

STREAM AND BUFFER AREA PROTECTION/RESTORATION

STREAM AND BUFFER AREA PROTECTION/RESTORATION STREAM AND BUFFER AREA PROTECTION/RESTORATION AMENDMENT OPTIONS TO STRENGTHEN POLICY IN HEADWATERS AREAS DRAFT SUBSEQUENT TO THE JANUARY 25, 2007 MEETING OF THE PLANNING COMMISSION ENVIRONMENT COMMITTEE

More information

City of Daphne, Alabama Water Quality Monitoring Plan For Phase II MS4

City of Daphne, Alabama Water Quality Monitoring Plan For Phase II MS4 City of Daphne, Alabama Water Quality Monitoring Plan For Phase II MS4 2016-2021 Permit # ALR 040039, Expiration Date: September 30, 2021 I. Introduction This document presents the City of Daphne s Stormwater

More information

Municipal Stormwater Management Planning

Municipal Stormwater Management Planning Municipal Stormwater Management Planning Christopher C. Obropta, Ph.D., P.E. Water Resources Extension Specialist with Rutgers Cooperative Extension Assistant Professor with Department of Environmental

More information

J. Sargeant Reynolds Community College. Chesapeake Bay TMDL Action Plan

J. Sargeant Reynolds Community College. Chesapeake Bay TMDL Action Plan J. Sargeant Reynolds Community College Prepared for: J. Sargeant Reynolds Community College Parham Road Campus Facilities Management & Planning 1651 E. Parham Road Richmond, VA 23228 June 30, 2015 Revised

More information

POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS

POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS POLICY FOR NATURAL RESOURCE MANAGEMENT AREAS I. POLICY STATEMENT Auburn University's (the University's) "Policy for Natural Resource Management Areas" implements the Campus Master Plan Land Use Element

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432 PAN 16-112, Westwood Middle School, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: August 22, 2016 AGENDA NUMBER: 10 FILE NUMBER: 16-112 ITEM: Westwood Middle School RECOMMENDATION:

More information

Go Green, Save Money: Lowering Flood Insurance Rates in Virginia with Stormwater Management. Kristen Clark VCPC Alumna, Spring 2014

Go Green, Save Money: Lowering Flood Insurance Rates in Virginia with Stormwater Management. Kristen Clark VCPC Alumna, Spring 2014 Go Green, Save Money: Lowering Flood Insurance Rates in Virginia with Stormwater Management Kristen Clark VCPC Alumna, Spring 2014 Rising Waters, Rising Rates Coastal Communities in Virginia are confronted

More information

APPENDIX N Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports

APPENDIX N Guidance for Preparing/Reviewing CEQA Initial Studies and Environmental Impact Reports APPENDIX N N.1 Guidance for Preparing and Reviewing CEQA Initial Studies Step 1: Consider the Project Characteristics as Provided by the Project Applicant Review the project application and draft plan

More information

Quantifying the Benefits of Stream Restoration

Quantifying the Benefits of Stream Restoration Quantifying the Benefits of Stream Restoration 10 th Annual GAFM Technical Conference, March 2016 Jarrod Karl, Hazen and Sawyer Presentation Outline Benefits of Stream Restoration The Watershed Approach

More information

ARLINGTON COUNTY, VIRGINIA

ARLINGTON COUNTY, VIRGINIA ARLINGTON COUNTY, VIRGINIA County Board Agenda Item Meeting of April 21, 2007 DATE: April 20, 2007 SUBJECT: Approve the Award of a Contract to Sagres Construction Corp. for the construction of Phase I

More information

Paxton Creek Watershed TMDL Strategy

Paxton Creek Watershed TMDL Strategy Paxton Creek Watershed TMDL Strategy Public Review Meetings: November 17, 2015 November 18, 2015 December 10, 2015 Paxton Creek Watershed Cooperative Progressive approach to achieving water quality improvements.

More information

Stream and Watershed Restoration Design and Quantitative Benefits. Kelly Gutshall, RLA and Mike LaSala

Stream and Watershed Restoration Design and Quantitative Benefits. Kelly Gutshall, RLA and Mike LaSala Stream and Watershed Restoration Design and Quantitative Benefits Kelly Gutshall, RLA and Mike LaSala Suquehanna Greenway River Towns Workshop September 30, 2013 Benefit Stacking Single Function Multiple

More information

Municipal Separate Storm Sewer System (MS4) Permit and Program Ordinance Update. City of Fairmont March, 2018

Municipal Separate Storm Sewer System (MS4) Permit and Program Ordinance Update. City of Fairmont March, 2018 Municipal Separate Storm Sewer System (MS4) Permit and Program Ordinance Update City of Fairmont March, 2018 What is a MS4 Program? A program developed by the EPA to help manage stormwater within cities

More information

Council of Governments

Council of Governments Metropolitan Washington Council of Governments Anne Arundel County Draft Phase II Watershed Implementation Plan January 18, 2011 Chesapeake Bay TMDL Pollutants of Concern Nitrogen Phosphorus Sediment 2

More information

TOWN OF SMYRNA Water Quality Buffer Zone Policy

TOWN OF SMYRNA Water Quality Buffer Zone Policy TOWN OF SMYRNA Water Quality Buffer Zone Policy Section I - Description A water quality buffer zone (a.k.a. a riparian zone) is a strip of undisturbed native (indigenous) vegetation, either original or

More information

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit)

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit) CHESAPEAKE BAY TMDL ACTION PLAN (2013 2018 MS4 General Permit) Piedmont Virginia Community College A Plan for Achieving a 5% Reduction of Existing Loads June 30, 2015 Main Campus This plan satisfies the

More information

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc.

ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975. Source: Hey and Associates, Inc. ILLINOIS URBAN MANUAL PRACTICE STANDARD TEMPORARY STREAM CROSSING (no.) CODE 975 Source: Hey and Associates, Inc. DEFINITION A bridge or culvert crossing installed across a stream or watercourse for short-term

More information

D Olive Watershed. Path Toward Restoration

D Olive Watershed. Path Toward Restoration D Olive Watershed Path Toward Restoration Water is the most critical resource issues of our lifetime and our children s lifetime. The health of our waters is the principal measure of how we live on the

More information

STAFF REPORT FOR POLICY PLAN AMENDMENT S10-CW-1CP

STAFF REPORT FOR POLICY PLAN AMENDMENT S10-CW-1CP STAFF REPORT FOR POLICY PLAN AMENDMENT S10-CW-1CP EXECUTIVE SUMMARY This Plan Amendment would serve to clarify policy guidance regarding circumstances under which proposals for disturbances to Environmental

More information

MARION COUNTY COMPREHENSIVE PLAN 2035

MARION COUNTY COMPREHENSIVE PLAN 2035 GOALS, OBJECTIVES AND POLICIES GOAL 1: To provide adequate stormwater management, afford reasonable protection from flooding, and protect the quality of surface water and groundwater in Marion County.

More information

STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS. By Marcus Rubenstein, CPESC

STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS. By Marcus Rubenstein, CPESC STREAM RESTORATION PURPOSE, PRACTICE, AND METHODS By Marcus Rubenstein, CPESC WHAT IS STREAM RESTORATION? The return of a stream s lost natural functions, usually resulting from watershed alterations,

More information

Chesapeake Bay Action Plan

Chesapeake Bay Action Plan 2016 Chesapeake Bay Action Plan Dale Chestnut JMU Facilities Engineering & Construction 3/23/2016 Chesapeake Bay Action Plan Harrisonburg, Virginia 2016 Update Submitted to satisfy the terms of the General

More information

Appendix E : Guidelines for Riparian Buffer Areas

Appendix E : Guidelines for Riparian Buffer Areas Appendix E : Guidelines for Riparian Buffer Areas This document should be read in conjunction with the CRCA Planning Policy. 1.0 PURPOSE The purpose of this document is to summarize the recommendations

More information

4.4.6 Underground Detention

4.4.6 Underground Detention 4.4.6 Underground Detention Limited Application Water Quality BMP Description: Detention storage located in underground pipe systems or vaults designed to provide water quantity control through detention

More information

Chesapeake Bay TMDL Action Plan and MS4 Program Update. Presentation to the Herndon Town Council. May 5, 2015

Chesapeake Bay TMDL Action Plan and MS4 Program Update. Presentation to the Herndon Town Council. May 5, 2015 Chesapeake Bay TMDL Action Plan and MS4 Program Update Presentation to the Herndon Town Council May 5, 2015 Overview Quick Background Meeting the Chesapeake Bay Restoration Requirements Draft Chesapeake

More information

City of Madison: 2017 Capital Budget Capital Improvement Plan

City of Madison: 2017 Capital Budget Capital Improvement Plan City of Madison: 2017 Capital Budget Capital Improvement Plan Agency: Stormwater Utility Project Summary Backyard Drainage Problems 25,000 25,000 25,000 25,000 25,000 25,000 CIPP Lining Storm Sewer 100,000

More information

Wood Canyon Emergent Wetland Project. City of Aliso Viejo 12 Journey, Suite 100 Aliso Viejo, CA 92656

Wood Canyon Emergent Wetland Project. City of Aliso Viejo 12 Journey, Suite 100 Aliso Viejo, CA 92656 Wood Canyon Emergent Wetland Project City of Aliso Viejo 12 Journey, Suite 100 Aliso Viejo, CA 92656 Introduction Wood Canyon is located within Aliso and Wood Canyon Regional Park in southwest Orange County,

More information

DEVELOPING A WATERSHED IMPROVEMENT PLAN TO MEET MULTIPLE COMMUNITY OBJECTIVES IN GAINESVILLE AND HALL COUNTY, GEORGIA

DEVELOPING A WATERSHED IMPROVEMENT PLAN TO MEET MULTIPLE COMMUNITY OBJECTIVES IN GAINESVILLE AND HALL COUNTY, GEORGIA DEVELOPING A WATERSHED IMPROVEMENT PLAN TO MEET MULTIPLE COMMUNITY OBJECTIVES IN GAINESVILLE AND HALL COUNTY, GEORGIA Chrissy, Thom 1, David Dockery 2, Kevin McInturff 3, Betsy Massie 1, and Lauren Murphy

More information

Stormwater Management Tools: Real-Life Solutions for a Resilient Community Riparian Corridor Protection

Stormwater Management Tools: Real-Life Solutions for a Resilient Community Riparian Corridor Protection Stormwater Management Tools: Real-Life Solutions for a Resilient Community Riparian Corridor Protection Montgomery County Planning Commission October 24, 2013 Eric Jarrell, Assistant Section Chief, Community

More information

Overview of Stormwater Management in Virginia. Stuart McKenzie, NNPDC Environmental Planner

Overview of Stormwater Management in Virginia. Stuart McKenzie, NNPDC Environmental Planner Overview of Stormwater Management in Virginia Stuart McKenzie, NNPDC Environmental Planner Background In the 1950 s into the 1960 s stormwater management was not required by the State or Federal Government

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW Mississippi Dr Coon Rapids, MN SQ FT Residence on 0.64 Acre Lot

COON CREEK WATERSHED DISTRICT PERMIT REVIEW Mississippi Dr Coon Rapids, MN SQ FT Residence on 0.64 Acre Lot 17-082 Van Sloun Residence, Page 1 of 5 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: May 8, 2017 AGENDA NUMBER: 17 FILE NUMBER: 17-082 ITEM: Van Sloun Residence RECOMMENDATION: Approve with

More information

CHAPTER 1 INTRODUCTION. Stream processes are strongly related to the physical conditions of the

CHAPTER 1 INTRODUCTION. Stream processes are strongly related to the physical conditions of the 1 CHAPTER 1 INTRODUCTION Stream processes are strongly related to the physical conditions of the watershed from which they flow. Alterations to physical conditions of a watershed manifest themselves through

More information

RESOLUTION Perennial Stream Reclassification Procedures ADOPTED AUGUST 23, 2005

RESOLUTION Perennial Stream Reclassification Procedures ADOPTED AUGUST 23, 2005 Rebecca Cate, Chair Denise Rodgers, Vice Chair Anne Pastorkovich, Secretary Karen Hunt, Treasurer RESOLUTION Perennial Stream Reclassification Procedures ADOPTED AUGUST 23, 2005 Background Water sampling

More information

FieldDoc.org User Guide For 2017 NFWF Chesapeake Bay Stewardship Fund Applicants. Background 2. Step 1: Register for a FieldDoc account 3

FieldDoc.org User Guide For 2017 NFWF Chesapeake Bay Stewardship Fund Applicants. Background 2. Step 1: Register for a FieldDoc account 3 FieldDoc.org User Guide For 2017 NFWF Chesapeake Bay Stewardship Fund Applicants Table of Contents (click to go to page) Background 2 Step 1: Register for a FieldDoc account 3 Step 2: Create the Project

More information

BUREAU OF CLEAN WATER

BUREAU OF CLEAN WATER COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF CLEAN WATER NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) STORMWATER DISCHARGES FROM SMALL MUNICIPAL SEPARATE STORM

More information

COON CREEK WATERSHED DISTRICT PERMIT REVIEW th Lane NE East Bethel, MN 55005

COON CREEK WATERSHED DISTRICT PERMIT REVIEW th Lane NE East Bethel, MN 55005 18-115 South Terrace Cove, Page 1 of 6 COON CREEK WATERSHED DISTRICT PERMIT REVIEW MEETING DATE: July 23, 2018 AGENDA NUMBER: 8 FILE NUMBER: 18-115 ITEM: South Terrace Cove RECOMMENDATION: Approve with

More information

APPENDIX A. Nutrient Trading Criteria Specific for the Chesapeake Bay Watershed

APPENDIX A. Nutrient Trading Criteria Specific for the Chesapeake Bay Watershed Purpose: APPENDIX A Nutrient Trading Criteria Specific for the Chesapeake Bay Watershed The purpose of Appendix A is to provide additional program specific information regarding the use and incorporation

More information

PA Municipal Separate Storm Sewer System (MS4) TMDL Plan

PA Municipal Separate Storm Sewer System (MS4) TMDL Plan PA Municipal Separate Storm Sewer System (MS4) TMDL Plan Instructor: Bryan Seipp, Watershed Manager- CWP Lee Epstein, Director, Lands Program- CBF 1 To Adjust How the Slides Appear on Your Screen To make

More information

Watershed Hydrology: Go with the flow. Greg Jennings, PhD, PE

Watershed Hydrology: Go with the flow. Greg Jennings, PhD, PE Watershed Hydrology: Go with the flow Greg Jennings, PhD, PE jenningsenv@gmail.com Streams What are your CHALLENGES? Hydrology too much water Pollutants upstream and on-site Vegetation wrong plants, wrong

More information

LOCATION AND DESIGN DIVISION

LOCATION AND DESIGN DIVISION VIRGINIA DEPARTMENT OF TRANSPORTATION LOCATION AND DESIGN DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: Virginia Stormwater Management Program SPECIFIC SUBJECT: Application of the

More information

Stream Restoration Verification Guidance

Stream Restoration Verification Guidance Stream Restoration Verification Guidance Version: Final, February 6 th, 2014 The guidance is revised to incorporate comments provided by the Chesapeake Bay Program Verification Review Panel (CBP Water

More information

CAT BRANCH W16O016 & W16O017 OUTFALL RETROFITS FINAL DESIGN REPORT

CAT BRANCH W16O016 & W16O017 OUTFALL RETROFITS FINAL DESIGN REPORT Prepared for: Anne Arundel County Department of Public Works CAT BRANCH W16O016 & W16O017 OUTFALL RETROFITS FINAL DESIGN REPORT APRIL 2018 CONTRACT #: B552301 Prepared by: Consultants & Designers, Inc.

More information

Post-Development Stormwater Runoff Performance Standards

Post-Development Stormwater Runoff Performance Standards Post-Development Stormwater Runoff Performance Standards December 9, 2014 Topics Why performance standards? What practices/requirements are in effect in other States? The Workgroup s preliminary and final

More information

September 15, 2014 Winston Salem, VA Stormwater Capital Improvement Planning for Total Maximum Daily Load Compliance

September 15, 2014 Winston Salem, VA Stormwater Capital Improvement Planning for Total Maximum Daily Load Compliance September 15, 2014 Winston Salem, VA Stormwater Capital Improvement Planning for Total Maximum Daily Load Compliance An Approach to Compliance with Stormwater MS4 Permits and TMDLs Outline TMDL Requirements

More information

Project Summary

Project Summary Stormwater Utility Capital Improvement Plan Project Summary 2017 2018 2019 2020 2021 2022 Backyard Drainage Problems 25,000 25,000 25,000 25,000 25,000 25,000 CIPP Lining Storm Sewer 100,000 100,000 100,000

More information

Appendix X: Non-Point Source Pollution

Appendix X: Non-Point Source Pollution Appendix X: Non-Point Source Pollution Sources Nonpoint source of pollution, unlike pollution from industrial and sewage treatment plants, comes from many different sources. Nonpoint source pollution is

More information

The Storm Water Quality Benefits of Flood Buyouts. City of Birmingham Edwin Revell, CFM March 10, 2011 ASCE Alabama Section Winter Meeting

The Storm Water Quality Benefits of Flood Buyouts. City of Birmingham Edwin Revell, CFM March 10, 2011 ASCE Alabama Section Winter Meeting The Storm Water Quality Benefits of Flood Buyouts City of Birmingham Edwin Revell, CFM March 10, 2011 ASCE Alabama Section Winter Meeting Outline Floodplain Mgmt & Storm Water Mgmt MS4 NPDES Permit Requirements

More information

Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates VNH File No.

Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates VNH File No. Municipal Stormwater Management Plan Prepared For The Borough of Cape May Point By Van Note-Harvey Associates 2005 VNH File No. 35317-210-21 Table of Contents Introduction... 3 Goals... 3 Storm water Discussion...

More information

WELCOME. Eastern Subwatersheds Stormwater Management Retrofit Study. Online Information Session #2 June 15 to July 13, 2018

WELCOME. Eastern Subwatersheds Stormwater Management Retrofit Study. Online Information Session #2 June 15 to July 13, 2018 WELCOME Eastern Subwatersheds Stormwater Management Retrofit Study Online Information Session #2 June 15 to July 13, 2018 1 Eastern Subwatersheds Stormwater Management Retrofit Study This study is one

More information

Department of Environmental Conservation. Fiscal Year 2015 Performance Outcomes and Measures

Department of Environmental Conservation. Fiscal Year 2015 Performance Outcomes and Measures Department of Environmental Conservation Fiscal Year 2015 Performance Outcomes and Measures Department of Environmental Conservation Fiscal Year 2015 Performance Outcomes and Measures Department of Environmental

More information

Gwinnett County Dept. of Water Resources Watershed Improvement Program. Russell Manley, CFM, Gwinnett County DWR Kevin Middlebrooks, CH2M

Gwinnett County Dept. of Water Resources Watershed Improvement Program. Russell Manley, CFM, Gwinnett County DWR Kevin Middlebrooks, CH2M Gwinnett County Dept. of Water Resources Watershed Improvement Program Russell Manley, CFM, Gwinnett County DWR Kevin Middlebrooks, CH2M Gwinnett County: Population: 859,000 Area: 437 sq. miles 2,000 miles

More information

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit)

CHESAPEAKE BAY TMDL ACTION PLAN ( MS4 General Permit) CHESAPEAKE BAY TMDL ACTION PLAN (2013 2018 MS4 General Permit) Central Virginia Community College A Plan for Achieving a 5% Reduction of Existing Loads June 30, 2015 Main Campus This plan satisfies the

More information

Section 3: Stormwater Problems

Section 3: Stormwater Problems Section 3: Stormwater Problems The Wissahickon Creek Watershed has undergone major development and urbanization. Much of the watershed area was developed as a part of the inner ring suburbs of Philadelphia

More information

The Chesapeake Bay TMDL

The Chesapeake Bay TMDL The Chesapeake Bay TMDL December 29, 2010 EPA Update on Implementation Progress County Engineers Association of Maryland Fall Conference 2015 Jon M. Capacasa, Water Division Director US EPA Region III

More information

TOWN OF BERKLEY ARTICLE 32 STORM WATER BYLAW

TOWN OF BERKLEY ARTICLE 32 STORM WATER BYLAW TOWN OF BERKLEY ARTICLE 32 STORM WATER BYLAW Land development projects and other land use conversions, and their associated changes to land cover, permanently alter the hydrologic response of local watersheds

More information

Lake Elmo, MN Code of Ordinances STORM WATER AND EROSION AND SEDIMENT CONTROL

Lake Elmo, MN Code of Ordinances STORM WATER AND EROSION AND SEDIMENT CONTROL Lake Elmo, MN Code of Ordinances STORM WATER AND EROSION AND SEDIMENT CONTROL 150.270 STATUTORY AUTHORIZATION. This subchapter is adopted pursuant to the authorization and policies contained in M.S. Chs.

More information

Will County Site Development Permit Submittal Checklist TAB 1 PROJECT OVERVIEW

Will County Site Development Permit Submittal Checklist TAB 1 PROJECT OVERVIEW Applicant: Reviewer: Permit No.: The following tables contain a checklist of the requirements before a review for a Site Development Permit submittal will be accepted. Not all requirements pertain to every

More information

FieldDoc.org User Guide - for 2018 NFWF Chesapeake Bay Stewardship Fund Applicants -

FieldDoc.org User Guide - for 2018 NFWF Chesapeake Bay Stewardship Fund Applicants - FieldDoc.org User Guide - for 2018 NFWF Chesapeake Bay Stewardship Fund Applicants - Table of Contents (click to go to page) Background 2 Step 1: Register for a FieldDoc account 3 Step 2: Create the Project

More information

South St. Vrain / Hall Meadows Restoration Planning August 20, 2015

South St. Vrain / Hall Meadows Restoration Planning August 20, 2015 South St. Vrain / Hall Meadows Restoration Planning August 20, 2015 Agenda Introductions Purpose & Goals of Meeting Planning Area Master Plan Restoration Planning: Cost Estimates, Grants, Scope, Timeline

More information

VILLAGE OF BELLAIRE WATER QUALITY ACTION PLAN

VILLAGE OF BELLAIRE WATER QUALITY ACTION PLAN VILLAGE OF BELLAIRE WATER QUALITY ACTION PLAN Elk-River-Chain-of-Lakes Gaps Analysis Project The Watershed Center Grand Traverse Bay Tip of the Mitt Watershed Council Michigan Department of Natural Resources

More information

4. Present Activities and Roles

4. Present Activities and Roles 4. Present Activities and Roles The present missions, authorities, activities and roles of the various agencies involved with flood protection, floodplain management and flood-damage reduction are identified

More information

Virginia State University MS-4 Permit: VAR Chesapeake Bay TMDL Action Plan

Virginia State University MS-4 Permit: VAR Chesapeake Bay TMDL Action Plan Virginia State University MS-4 Permit: VAR040119 Chesapeake Bay TMDL Action Plan Prepared for Virginia State University Capital Outlay & Facilities Management PO Box 9414 Virginia State University, VA

More information

Flood Mitigation Plan

Flood Mitigation Plan City of Huntsville, Alabama Flood Mitigation Plan 2001 Prepared by Flood Mitigation Planning Committee June 1, 2001 City of Huntsville, Alabama Flood Mitigation Plan Executive Summary 1973 1999 Prepared

More information

iswm TM Criteria Manual City Date here December 2009 Revised 1/2015 Revised 1/14/15

iswm TM Criteria Manual City Date here December 2009 Revised 1/2015 Revised 1/14/15 City Date here December 2009 December 2009 i Revised 1/14/15 Overview of the iswm Program The iswm Program for Construction and Development is a cooperative initiative that assists municipalities and counties

More information

IMPROVING OUTCOMES FOR STREAM ALTERATION PROJECTS

IMPROVING OUTCOMES FOR STREAM ALTERATION PROJECTS IMPROVING OUTCOMES FOR STREAM ALTERATION PROJECTS Bethany Matousek Inland Lakes and Streams Program Coordinator Wetlands, Lakes and Streams Unit DEQ Water Resources Division MatousekB@Michigan.gov 517-243-6421

More information

Municipal Separate Storm Sewer Systems (MS4) Implementation. Craig Carson Montgomery County Department of Environmental Protection

Municipal Separate Storm Sewer Systems (MS4) Implementation. Craig Carson Montgomery County Department of Environmental Protection Montgomery County Maryland Municipal Separate Storm Sewer Systems (MS4) Implementation Craig Carson Montgomery County Department of Environmental Protection Montgomery County, Maryland 500 sq. miles 970,000

More information

DC STORMWATER PLAN CONSOLIDATED TOTAL MAXIMUM DAILY LOAD (TDML) IMPLEMENTATION PLAN

DC STORMWATER PLAN CONSOLIDATED TOTAL MAXIMUM DAILY LOAD (TDML) IMPLEMENTATION PLAN DC STORMWATER PLAN CONSOLIDATED TOTAL MAXIMUM DAILY LOAD (TDML) IMPLEMENTATION PLAN CONTENTS Introduction 1 The Challenge 5 The Solution 7 Tracking Progress 11 What can you do? 15 INTRODUCTION The DC Stormwater

More information

City of Charlottesville Water Resources Protection Program

City of Charlottesville Water Resources Protection Program City of Charlottesville Water Resources Protection Program Stormwater Utility Fee Credits Manual Your guide to reducing stormwater utility fees and protecting our City s water resources. City of Charlottesville,

More information

Estimated Fiscal Impacts on Selected Municipal Separate Storm Sewer System Permittees

Estimated Fiscal Impacts on Selected Municipal Separate Storm Sewer System Permittees Waters of the United States Regulations Proposed by the US EPA and US ACOE Estimated Fiscal Impacts on Selected Municipal Separate Storm Sewer System Permittees Prepared for: August 29, 2014 Prepared by

More information

Final TMDL Implementation Plan. Prepared for Minnesota Pollution Control Agency

Final TMDL Implementation Plan. Prepared for Minnesota Pollution Control Agency Wirth Lake Final TMDL Implementation Plan Prepared for Minnesota Pollution Control Agency September 2010 4700 West 77 th Street Minneapolis, MN 55435-4803 Phone: (952) 832-2600 Fax: (952) 832-2601 wq-iw11-03c

More information

MS4 Permits. Understanding MS4 Permits (Municipal Separate Storm Sewer System) P508-17

MS4 Permits. Understanding MS4 Permits (Municipal Separate Storm Sewer System) P508-17 Understanding (Municipal Separate Storm Sewer System) P508-17 1 Edward R. Umbrell, P.E. Mr. Umbrell obtained his civil engineering degree from The University of Maryland and has over 20 years of design

More information

UMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist

UMD Storm Water Program Construction Requirements. Greg Archer, MBA Environmental Compliance Specialist UMD Storm Water Program Construction Requirements Greg Archer, MBA Environmental Compliance Specialist Phase 2 Regulatory Overview Dec. 1999 EPA issues Phase 2 Federal Register Municipalities (MS4) from

More information

Chesapeake Bay Preservation Area Regulations. 9 VAC Development criteria for Resource Protection Areas.

Chesapeake Bay Preservation Area Regulations. 9 VAC Development criteria for Resource Protection Areas. Chesapeake Bay Preservation Area Regulations 9 VAC 10-20-130. Development criteria for Resource Protection Areas. In addition to the general performance criteria set forth in 9 VAC 10-20-120, the criteria

More information

Regional Stormwater Management Plan for Troy Brook, Morris County, New Jersey

Regional Stormwater Management Plan for Troy Brook, Morris County, New Jersey Regional Stormwater Management Plan for Troy Brook, Morris County, New Jersey Executive Summary Troy Brook is in the Whippany River watershed, which has the first TMDL in the State of New Jersey, for fecal

More information

KANKAKEE COUNTY PLANNING DEPARTMENT APPLICATION FOR CLASS I & II GRADING AND DRAINAGE/STOMRWATER PERMIT APPLICATION

KANKAKEE COUNTY PLANNING DEPARTMENT APPLICATION FOR CLASS I & II GRADING AND DRAINAGE/STOMRWATER PERMIT APPLICATION KANKAKEE COUNTY PLANNING DEPARTMENT APPLICATION FOR CLASS I & II GRADING AND DRAINAGE/STOMRWATER PERMIT APPLICATION Michael J. Van Mill, AICP Planning Director 189 East Court Street Kankakee, IL 60901

More information

LITTLE SHADES CREEK RESTORATION PROJECT CWA Section 319(h) Nonpoint Source Implementation Grant Project Workplan #17 ADEM Contract #C

LITTLE SHADES CREEK RESTORATION PROJECT CWA Section 319(h) Nonpoint Source Implementation Grant Project Workplan #17 ADEM Contract #C LITTLE SHADES CREEK RESTORATION PROJECT CWA Section 319(h) Nonpoint Source Implementation Grant Project Workplan #17 ADEM Contract #C90593066 PARTNERS Alabama Department of Environmental Management Cawaco

More information

Pollution Reduction Plan For Municipal Separate Storm Sewer System

Pollution Reduction Plan For Municipal Separate Storm Sewer System Pollution Reduction Plan For Municipal Separate Storm Sewer System West Chester University of Pennsylvania September 2017 Table of Contents Purpose and Scope Permit Requirements Pollution Reduction Conclusion

More information

RIPARIAN CORRIDOR STUDY FINAL PARLEYS CREEK MANAGEMENT PLAN TABLE OF CONTENTS

RIPARIAN CORRIDOR STUDY FINAL PARLEYS CREEK MANAGEMENT PLAN TABLE OF CONTENTS TABLE OF CONTENTS 1.0 INTRODUCTION... 1-1 Riparian Corridor Study and Management Plan Goals... 1-1 Study Area... 1-2 Importance and Functions of Riparian Corridors... 1-2 Habitat for Mammals, Birds, and

More information

Stormwater Utility. Frequently Asked Questions. January 2019 CITY OF NORTH RIDGEVILLE Avon Belden Road North Ridgeville, Ohio 44039

Stormwater Utility. Frequently Asked Questions. January 2019 CITY OF NORTH RIDGEVILLE Avon Belden Road North Ridgeville, Ohio 44039 Stormwater Utility Frequently Asked Questions January 2019 CITY OF NORTH RIDGEVILLE 7307 Avon Belden Road North Ridgeville, Ohio 44039 General Stormwater Information/Education 1. What is stormwater runoff?

More information

Wetlands. DuPage County Stormwater Ordinance Update- Wetlands and Buffers. Is a Stormwater Permit Required? 7/13/2012

Wetlands. DuPage County Stormwater Ordinance Update- Wetlands and Buffers. Is a Stormwater Permit Required? 7/13/2012 DuPage County Stormwater Ordinance Update- Wetlands and Buffers PRESENTED BY: MARY BETH FALSEY WETLAND SPECIALIST Wetlands Section 15-18.A.1.a: If a Stormwater Administrator has the expertise, he/she can

More information

Adjusted Flood Prone Acres

Adjusted Flood Prone Acres Adjusted Flood Prone Acres The flood prone area is defined as the area adjacent to the stream that is innundated or saturated when the elevation of the water is at twice the maximum depth at bankfull stage

More information

Mill Creek Restoration in Lower Merion Township. PH (610) ; FAX (610) ;

Mill Creek Restoration in Lower Merion Township. PH (610) ; FAX (610) ; Mill Creek Restoration in Lower Merion Township Vincent L. Sortman 1 and Robert M. Lambert 2 1 Biohabitats, Inc., 15 W. Aylesbury Road, Timonium, MD 21093; PH (410) 337-3659; FAX (410) 583-5678; email: