UPGRADING FOR TOTAL NITROGEN REMOVAL WITH A POROUS MEDIA IFAS SYSTEM

Size: px
Start display at page:

Download "UPGRADING FOR TOTAL NITROGEN REMOVAL WITH A POROUS MEDIA IFAS SYSTEM"

Transcription

1 UPGRADING FOR TOTAL NITROGEN REMOVAL WITH A POROUS MEDIA IFAS SYSTEM T. Masterson, J. Federico, G. Hedman, S. Duerr BETA Group, Inc. 6 Blackstone Valley Place Lincoln, Rhode Island ABSTRACT The Westerly, Rhode Island wastewater treatment facility (WWTF) is an activated sludge plant with a monthly design average daily flow of 3.3 million gallons per day (MGD). Construction and commissioning of an integrated fixed-film activated sludge (IFAS) process completed in September 2003, upgraded the biological process at the facility from carbonaceous BOD 5 removal only, to include total nitrogen removal. The IFAS system met the treatment performance criteria soon after commissioning and startup and has performed well to date with total effluent nitrogen concentrations averaging approximately 5 mg/l. INTRODUCTION The modifications were completed to comply with revisions of the facility s discharge permit issued by the State of Rhode Island Department of Environmental Management (RIDEM). The revised discharge permit includes seasonal limits for ammonia and total nitrogen, in addition to the previous discharge permit limits for BOD 5, total suspended solids, fecal coliform and total residual chlorine. A summary of the current permit limits that the process modifications were designed to achieve is below: Table 1 Discharge Permit Limit Summary Parameter BOD 5 TSS Total Nitrogen Ammonia Fecal Coliform Total Residual Chlorine Discharge Limit (Average Monthly) 30 mg/l 30 mg/l 15 mg/l, June - October 5.5 mg/l, June October 30.9 mg/l, November May 200 MPN 65 µg/l Prior to the construction of the process modifications, the facility consisted of a manual influent bar rack, grit removal, primary clarification, mechanical aeration, secondary clarification, and sodium hypochlorite disinfection. Improvements were made to the preliminary treatment, primary treatment and disinfection processes as part of the overall facility improvements as well as to the biological treatment and secondary clarification processes. The focus of this paper will be on the improvements made to the biological treatment process to achieve total nitrogen

2 removal. This paper will present the construction sequence issues addressed in order to construct the improvements while maintaining compliance with the facility s previous discharge permit, discuss the installation and commissioning of an IFAS System in the existing aeration basins for total nitrogen removal, and present process performance data that confirms the process capability of the system. KEYWORDS Integrated fixed-film, IFAS, total nitrogen removal, porous support media CONSTRUCTION SEQUENCE The primary focus of the upgrade of the biological treatment system at the facility was the modification of aeration basins to accommodate the IFAS system while the facility maintained compliance with its discharge permit limits of 30 mg/l for BOD 5 and TSS. The aeration tanks are two tanks in parallel with each tank divided into 3 cells. Each cell is approximately 34 feet square with a side water depth of 14 feet. Aeration was provided by mechanical surface aerator equipment that was beyond its useful operating life and had difficulty maintaining adequate dissolved oxygen (DO) for BOD 5 oxidation. Two centrifugal blowers and aeration piping, part of the permanent process improvements, were installed while the surface aeration equipment remained in service. Temporary coarse bubble diffusers were installed in each aeration tank to supplement the function of the mechanical aeration equipment. The dissolved oxygen (DO) concentrations in the aeration tanks improved quickly and the periods of low DO and the related process upsets were eliminated. Interim permit discharge limits for BOD 5 and TSS were negotiated with RIDEM for the construction period that would have allowed less restrictive discharge concentrations for both BOD 5 and TSS without violation. The construction sequence was coordinated such that supplemental coarse bubble aeration and the construction of a third secondary clarifier allowed the aeration tanks to be taken out of service one at a time for completion of the IFAS system upgrade work. One of the two aeration tanks was in service at all times along with three secondary clarifiers during construction of the IFAS improvements. As a result, the facility maintained compliance with its BOD 5 and TSS permit limits of 30 mg/l for BOD 5 and TSS during construction. The porous support media was not introduced into the reactors until the mechanical process improvements to both aeration tank s were complete. The anoxic zones were operated as aerobic zones (with temporary coarse bubble aeration) during the period prior to the introduction of the porous media in order to maximize the aerobic HRT in the system for BOD 5 removal. The mechanical aeration equipment was decommissioned as each aeration tank was removed from service. Septage receiving was suspended during the construction to reduce the pollutant loads on the biological treatment process while one aeration tank was out of service.

3 IFAS SYSTEM The IFAS system installed in each aeration tank is a LINPOR -CN System supplied by Mixing & Mass Transfer Technologies (m 2 t). The LINPOR -CN System operates with a suspended porous support media, in combination with a freely suspended biomass. This combination results in total mixed liquor biomass concentrations in the aerobic biological reactor that are substantially higher than conventional activated sludge systems. The higher total effective biomass concentration allows higher reactor volumetric pollutant loadings at biomass loadings similar to a conventional air activated sludge process. The porous support media is sponge-like, 15 millimeter polyurethane cubes. Structural and process equipment modifications were made to the two existing aeration tanks in order to provide a nitrogen removal configuration. The upstream cell of each aeration tank was converted to a baffled anoxic zone with submersible mixers. A single fiberglass reinforced plastic baffle and support structure was installed in each anoxic zone to minimize flow shortcircuiting and improve mixer performance. Each anoxic zone is mixed by two, stainless steel submersible mixers.

4

5 The other two cells of each aeration tank were converted to the aerobic LINPOR -CN reactors. The reinforced concrete wall separating the second and third cells was demolished to provide single aerobic reactors 34 feet wide by approximately 70 feet long. Steel beams were installed in the removed wall s former location for supporting the tank exterior walls. These beams were installed above the liquid level to allow free surface flow. Tubular membrane-type fine pore air diffuser grids were installed in the aerobic reactors. The diffusers were designed in a tapered configuration with the highest diffuser densities being installed at the feed (highest demand) end of the reactors. Photo 1 Tubular Membrane Diffusers The porous support media is retained in the aerobic reactors by a perforated, stainless steel screen installed at the effluent weirs. The media retention screen prevents media overflow to the final clarifiers. The screen extends the full depth of each reactor and has circular perforations 8 millimeters in diameter spaced at 11 millimeters on center. Media retained by the screen is kept from impinging on the screen by a coarse-bubble air knife installed at the base of the screens. This air knife provides air scouring of the screen and maintains free passage of the mixed liquor through the screen to secondary clarification. Uniform support media distribution is maintained in the aerobic reactors by recycling the media within the reactors with air-lift pumps. Air for this service is supplied by the process aeration blowers. No dedicated air supply source is required. The air-lift pumps return media which migrates from the feed end to the effluent end of the plug-flow aerobic reactors.

6 Photo 2 Air-Lift Pump Inlet and Media Retention Screen The air-lift pumps discharge the media and mixed liquor above the water surface through a stainless steel pipeline that is perforated to allow mixed liquor to drain back into the reactor. The discharge is also equipped with a flat plate fixed across the opening to cause excess biomass to be separated from the support media and reenter the tank as suspended, rather than fixed, biomass. This action controls the amount of fixed biomass in the system. The flowrate of the media recycle is controlled manually by operating a butterfly valve on the air drop legs to the media air-lift hoods. Photo 3 - Air-Lift Pump Media Recycle Discharge

7 Nitrified mixed liquor is pumped from the end of the aerobic reactor to the anoxic zone by submersible, mixer-type, axial pumps. There is one nitrate recycle pump in each aerobic reactor and each delivers approximately 735 gpm. The pumps are installed downstream of the media retention screen and do not contact the support media. The flowrate of these pumps is controlled by variable frequency electric drives that operate based on a manually programmed speed setpoint. The pumps are interlocked with a point level sensor installed in each reactor. The nitrate recycle pumps will shut down based on a high level in the reactors. This condition may result from high flows or the unlikely blinding of the media retention screen. Process air is supplied to the IFAS system by two, multi-stage, centrifugal air blowers. Two blowers are installed with one duty unit and one backup as 100 percent redundancy. The system operates under average design load conditions with one blower in operation at approximately 4,300 scfm and 7.2 psig. The output of the blowers is controlled by variable frequency electric drives that operate in automatic control by a programmable logic controller (PLC) based dissolved oxygen (DO) control system. The blowers are protected locally by a vibration and surge alarm system that will report trouble to the system s main PLC and send alarms to operators via local telemetry and dialer systems. Photo 4 Centrifugal Blowers and Vibration/Surge Panel Each aerobic reactor has two DO sensors and analyzers that report DO and temperature information to the control system PLC. The output of the blowers and the modulation of airflow control valves at the reactors are controlled automatically by this system. The output of process air to the reactors is adjusted automatically as the system loads vary with time. The DO control setpoints in the system are approximately 2.0 mg/l.

8 Photo 5 DO and ph Sensors and Analyzers

9

10 IFAS SYSTEM PERFORMANCE AND DISCUSSION The LINPOR - CN IFAS system was initially commissioned in July 2003 and began to demonstrate nitrification, total nitrogen removal and steady process operation within 4 weeks. Table 2 presents performance data for the initial period of operation showing compliance with the requirements of the current discharge permit limits soon after startup. This data was collected during the system performance test conducted in September and October 2003 as required by the construction contract. Influent flows during this performance test period averaged approximately 2.5 mgd. Table 2 - LINPOR Performance Test Data Influent 9/22/03 9/23/03 9/24/03 9/25/03 BOD 5 (mg/l) Ammonia (mg/l) TKN (mg/l) Effluent BOD 5 (mg/l) 19 7 <3 <3 Ammonia (mg/l) Nitrite (mg/l) <0.01 <0.01 <0.01 * Nitrate (mg/l) * TKN (mg/l) * Total N (mg/l) * Influent 9/26/03 9/27/03 9/28/03 10/1/03 BOD 5 (mg/l) Ammonia (mg/l) TKN (mg/l) Effluent BOD 5 (mg/l) 30 < Ammonia (mg/l) Nitrite (mg/l) <0.01 <0.01 <0.01 <0.01 Nitrate (mg/l) TKN (mg/l) Total N (mg/l)

11 Influent 10/2/03 10/3/03 10/8/03 10/9/03 BOD 5 (mg/l) Ammonia (mg/l) TKN (mg/l) Effluent BOD 5 (mg/l) 6 <3 <3 3 Ammonia (mg/l) Nitrite (mg/l) <0.01 * <0.01 <0.01 Nitrate (mg/l) 2.8 * TKN (mg/l) 3.2 * Total N (mg/l) 6 * Influent 10/15/03 10/16/03 10/22/03 10/23/03 BOD 5 (mg/l) Ammonia (mg/l) * * TKN (mg/l) * * Effluent BOD 5 (mg/l) 4 < Ammonia (mg/l) Nitrite (mg/l) <0.01 <0.01 <0.01 <0.01 Nitrate (mg/l) TKN (mg/l) Total N (mg/l) * - Indicates Parameter not Analyzed Additional system operating and performance data is presented in Table 3. This group of data shows consistent total nitrogen removal performance through the cold weather months. This full-scale data validates the cold-weather data collected during the system piloting in 2002.

12 Table 3 - IFAS System Performance and Operating Data Summary Oct. '03 Nov. '03 Dec. '03 Jan. '04 Feb. '04 Mar. '04 Apr. '04 Plant Influent Flow (Q) mgd BOD5 mg/l TSS mg/l Ammonia (1) mg/l TKN (1) mg/l Temperature (Avg.) C Temperature (Min.) C Plant Effluent BOD5 mg/l TSS mg/l Ammonia mg/l TKN mg/l TN mg/l Reactors RAS Flow mgd Nitrate Recycle (NR) Flow mgd Aerobic HRT (Q) hrs Aerobic HRT (Q+RAS+NR) hrs Anoxic HRT (Q) hrs Anoxic HRT (Q+RAS+NR) hrs MLSS free mg/l MLSS fixed mg/l SVI ml/g WAS lbs/day Effluent Suspended Solids lbs/day SRT - free biomass days SRT - free + fixed biomass days (1) Influent ammonia and TKN values from Nov. '03 through April '04 are estimates based on historical ratios to BOD5. Some process upsets were encountered during this time where excessive foaming was experienced. This foaming was attributed to fats, oils and grease introduced through septage addition at the facility headworks. Process modifications were subsequently made at the facility headworks to control the flow of septage. The foaming has subsided to this date as a result. The system has also shown excellent performance during wet weather events and the resulting high flows. Wash-out of the fixed biomass cannot occur in the system due to the media retention

13 screens and therefore the impact of the high flows to the process was shown to be negligible. This was shown in April 2004 when record wet weather caused the influent flowrate to the system to rise above the design peak hour flow of the facility. The system maintained compliance with the pollutant discharge limits even though the nitrate recycle pumps had shut down briefly due to high water elevations in the aerobic reactors. The system did not require reseeding or excessive return sludge pumping to restore the loss of biomass since the fixed biomass of approximately 10,000 mg/l was maintained in the reactors. It is noteworthy that the system provides nitrogen removal to below 5 mg/l with nitrate recycle rates significantly less than the literature values of 2 to 4 times the reactor influent rates (2Q to 4Q). This system operates at a fixed nitrate recycle rate of 2.12 mgd total (1.06 mgd per reactor). This equates to a nitrate recycle rate of approximately 1Q, or less than half of the rate and pumping energy requirements of some conventional nitrogen removal systems such as a typical Modified Ludzack-Ettinger (MLE) process. This reduction in the nitrate recycle rate is due to simultaneous nitrification and denitrification that occurs in the aerobic reactors. The simultaneous reactions are possible since the interior of the support media cubes can act as small anoxic environments where nitrate in the aerobic reactor is denitrified without being recycled to the anoxic zone by the nitrate recycle pumps. Photo 6 - LINPOR Aerobic Reactor Prior to IFAS Media Addition

14 Photo 7 - Sponge Media Addition to Aerobic Zone and Wetting with RAS Photo 8 - Media Recycle Discharge During Media Wetting at Startup

15 WEFTEC 2004 Photo 9 IFAS Media on Surface Prior to Assimilation with Mixed Liquor Photo 10 - LINPOR Aerobic Reactor Following IFAS Media Addition Copyright 2004 Water Environment Federation. All Rights Reserved.

16 Photo 11 - LINPOR Aerobic Reactor with Completely Assimilated Media CONCLUSIONS This project has shown that existing conventional activated sludge facilities can be retrofitted for total nitrogen removal without the costly construction of additional reactor tankage. Although additional influent hydraulic capacity was not required as part of this upgrade design, the Westerly, Rhode Island facility was converted from carbonaceous removal only to nitrification/denitrification within the existing tankage by the incorporation of the LINPOR - CN IFAS process. The LINPOR - CN IFAS system has shown that effluent ammonia and total nitrogen concentrations below the discharge limits can be consistently met even in wet and winter weather. The system has proven to require no more attention than the conventional activated sludge process previously operated at the facility, and has been relatively simple to troubleshoot and adjust. The operations staff also report that since the system was placed in service, a significant improvement in the sludge volume index (SVI) values has occurred, thereby allowing more consistent solids removal and processing at the facility.

17 ACKNOWLEDGMENTS The authors extend their deep appreciation to the following groups for their contributions to this project and to this paper: The Town of Westerly, Rhode Island Engineering Department Facility Owner Aquarion Operating Services Facility Operator BETA Group, Inc. Consulting Engineer Hart Engineering Corporation Constructor and Construction Manager Mixing & Mass Transfer Technologies (m 2 t) LINPOR System Engineer and Supplier REFERENCES Water Environment Federation (1992) Design of Municipal Wastewater Treatment Plants, Manual of Practice No. 8; Alexandria, Virginia. U.S. Environmental Protection Agency (1993) Nitrogen Control; EPA/625/R-93/010; Washington, D.C. Sedlak, Richard I. Phosphorus and Nitrogen Removal from Municipal Wastewater. New York: Lewis Publishers, 1991.

Altoona Westerly Wastewater Treatment Facility BNR Conversion with Wet Weather Accommodation

Altoona Westerly Wastewater Treatment Facility BNR Conversion with Wet Weather Accommodation Pennsylvania Water Environment Federation PennTEC Annual Technical Conference June 4, 2013 Altoona Westerly Wastewater Treatment Facility BNR Conversion with Wet Weather Accommodation Presented by: Jim

More information

COMPARISON OF SBR AND CONTINUOUS FLOW ACTIVATED SLUDGE FOR NUTRIENT REMOVAL

COMPARISON OF SBR AND CONTINUOUS FLOW ACTIVATED SLUDGE FOR NUTRIENT REMOVAL COMPARISON OF SBR AND CONTINUOUS FLOW ACTIVATED SLUDGE FOR NUTRIENT REMOVAL Alvin C. Firmin CDM Jefferson Mill, 670 North Commercial Street Suite 201 Manchester, New Hampshire 03101 ABSTRACT Sequencing

More information

CLR Process. Vertical Loop Configuration

CLR Process. Vertical Loop Configuration CLR Process Vertical Loop Configuration Vertical Configuration System Flexibility Parallel Operation Raw wastewater and return activated sludge are introduced at a single point in each standard CLR basin.

More information

Global Leaders in Biological Wastewater Treatment

Global Leaders in Biological Wastewater Treatment Global Leaders in Biological Wastewater Treatment OVERVIEW OF ANOXKALDNES AnoxKaldnes is a global provider of leading-edge biological processes for wastewater treatment. The head-office is in Sweden. There

More information

Palmer Wastewater Treatment Plant Environmental Impacts. A summary of the impacts of this treatment alternative are listed below:

Palmer Wastewater Treatment Plant Environmental Impacts. A summary of the impacts of this treatment alternative are listed below: 6.1.3 Environmental Impacts A summary of the impacts of this treatment alternative are listed below: 1. The Matanuska River will receive treated effluent as it currently does. 2. Effluent quality would

More information

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W Facility Overview The recently upgraded and expanded Henry N. Wochholz Regional Water Reclamation Facility (WRWRF) treats domestic wastewater generated from the Yucaipa-Calimesa service area. The WRWRF

More information

We Know Water. AnoxKaldnes. Moving Bed Biofilm Reactor (MBBR) Integrated Fixed-Film Activated Sludge (IFAS) and ANITA Mox Deammonification

We Know Water. AnoxKaldnes. Moving Bed Biofilm Reactor (MBBR) Integrated Fixed-Film Activated Sludge (IFAS) and ANITA Mox Deammonification We Know Water AnoxKaldnes Moving Bed Biofilm Reactor (MBBR) Integrated Fixed-Film Activated Sludge (IFAS) and ANITA Mox Deammonification WATER TECHNOLOGIES AnoxKaldnes MBBR and Hybas Processes AnoxKaldnes

More information

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND Brett T. Messner, PE, Tetra Tech, Inc., 201 E Pine St, Suite 1000, Orlando, FL 32801 Brett.Messner@tetratech.com, Ph: 239-851-1225 Fred

More information

- 1 - Retrofitting IFAS Systems In Existing Activated Sludge Plants. by Glenn Thesing

- 1 - Retrofitting IFAS Systems In Existing Activated Sludge Plants. by Glenn Thesing - 1 - Retrofitting IFAS Systems In Existing Activated Sludge Plants by Glenn Thesing Through retrofitting IFAS systems, communities can upgrade and expand wastewater treatment without the expense and complication

More information

AquaPASS. Aqua MixAir System. Phase Separator. System Features and Advantages. Anaerobic. Staged Aeration. Pre-Anoxic.

AquaPASS. Aqua MixAir System. Phase Separator. System Features and Advantages. Anaerobic. Staged Aeration. Pre-Anoxic. PHASED ACTIVATED SLUDGE SYSTEM PHASED ACTIVATED SLUDGE SYSTEM Aqua-Aerobic Systems has led the industry in time-managed, biological technology since 1984. In 2004, Aqua-Aerobic applied its expertise in

More information

Assuming 100 gallons per capita per day, and 3 people per REU, design flows for the development are proposed to be:

Assuming 100 gallons per capita per day, and 3 people per REU, design flows for the development are proposed to be: Andelina Farms Wastewater Treatment Plant Preliminary Basis of Design May 2018 Andelina Farms is a proposed Planned Unit Development in Saline Township located along US-12 just west of the City of Saline.

More information

We Know Water. AnoxKaldnes. Moving Bed Biofilm Reactor (MBBR) Integrated Fixed-Film Activated Sludge (IFAS) and ANITA Mox Deammonification

We Know Water. AnoxKaldnes. Moving Bed Biofilm Reactor (MBBR) Integrated Fixed-Film Activated Sludge (IFAS) and ANITA Mox Deammonification APPENDIX C.2 IFAS We Know Water AnoxKaldnes Moving Bed Biofilm Reactor (MBBR) Integrated Fixed-Film Activated Sludge (IFAS) and ANITA Mox Deammonification WATER TECHNOLOGIES AnoxKaldnes MBBR and Hybas

More information

TWO YEARS OF BIOLOGICAL PHOSPHORUS REMOVAL WITH AN ADVANCED MSBR SYSTEM AT THE SHENZHEN YANTIAN WASTEWATER TREATMENT PLANT

TWO YEARS OF BIOLOGICAL PHOSPHORUS REMOVAL WITH AN ADVANCED MSBR SYSTEM AT THE SHENZHEN YANTIAN WASTEWATER TREATMENT PLANT TWO YEARS OF BIOLOGICAL PHOSPHORUS REMOVAL WITH AN ADVANCED MSBR SYSTEM AT THE SHENZHEN YANTIAN WASTEWATER TREATMENT PLANT Chester Yang, Ph.D., Gaowei Gu, Baowei Li, Hongyuan Li, Wanshen Lu, Lloyd Johnson,

More information

2015 HDR, Inc., all rights reserved.

2015 HDR, Inc., all rights reserved. 2015 HDR, Inc., all rights reserved. Hastings Utilities Water Pollution Control Facility Improvements Brian Bakke, HDR ASCE Environmental Conference 4/6/2017 Review Existing Facilities Need for the Project

More information

NITROGEN REMOVAL GRANT WEAVER, PE & WWTP OPERATOR PRESIDENT THE WATER PLANET COMPANY. Create Optimal Habitats

NITROGEN REMOVAL GRANT WEAVER, PE & WWTP OPERATOR PRESIDENT THE WATER PLANET COMPANY.   Create Optimal Habitats NITROGEN REMOVAL Create Optimal Habitats Recognize the Importance of People Skills Full-scale Experimentation GRANT WEAVER, PE & WWTP OPERATOR Regulatory Support Utility Support PRESIDENT THE WATER PLANET

More information

IFAS Nutrient Removal Enhancement Retrofit of an Existing Contact / Stabilization Treatment Process at Neptune Beach, FL

IFAS Nutrient Removal Enhancement Retrofit of an Existing Contact / Stabilization Treatment Process at Neptune Beach, FL IFAS Nutrient Removal Enhancement Retrofit of an Existing Contact / Stabilization Treatment Process at Neptune Beach, FL John E. Olson, P.E. 1* ; Todd A. Schwingle, P.E. 1* ; Mark F. Greenwood 2* ; Amy

More information

NEW CLOTH MEDIA FILTER SYSTEM REPLACES 4 MGD TRAVELING BRIDGE FILTERS WITH 12 MGD CAPACITY IN EXISTING TANKAGE

NEW CLOTH MEDIA FILTER SYSTEM REPLACES 4 MGD TRAVELING BRIDGE FILTERS WITH 12 MGD CAPACITY IN EXISTING TANKAGE NEW CLOTH MEDIA FILTER SYSTEM REPLACES 4 MGD TRAVELING BRIDGE FILTERS WITH 12 MGD CAPACITY IN EXISTING TANKAGE Keith C. Dayton Department of Utilities Stafford County, Virginia P. O. Box 339 Stafford,

More information

BIOSPHERE MOVING BED BIOLOGICAL SYSTEMS

BIOSPHERE MOVING BED BIOLOGICAL SYSTEMS REACTION TANKS BIOSPHERE MOVING BED BIOLOGICAL SYSTEMS PROVEN FIXED-FILM TECHNOLOGY IDEAL FOR BNR UPGRADES AND CAPACITY EXPANSIONS. SAME FOOTPRINT, BETTER TREATMENT AT NEPTUNE BEACH, FL WWTP Without adding

More information

North Side WRP Master Plan Research and Development Department 2006 Seminar Series October 27, 2006 Metropolitan Water Reclamation District of

North Side WRP Master Plan Research and Development Department 2006 Seminar Series October 27, 2006 Metropolitan Water Reclamation District of North Side WRP Master Plan Research and Development Department 2006 Seminar Series October 27, 2006 Metropolitan Water Reclamation District of Greater Chicago Today s Goals Discuss project background Provide

More information

We Know Water. AnoxKaldnes. Moving Bed Biofilm Reactor (MBBR) Integrated Fixed-Film Activated Sludge (IFAS) and ANITA Mox Deammonification

We Know Water. AnoxKaldnes. Moving Bed Biofilm Reactor (MBBR) Integrated Fixed-Film Activated Sludge (IFAS) and ANITA Mox Deammonification We Know Water AnoxKaldnes Moving Bed Biofilm Reactor (MBBR) Integrated Fixed-Film Activated Sludge (IFAS) and ANITA Mox Deammonification WATER TECHNOLOGIES AnoxKaldnes MBBR and Hybas Processes AnoxKaldnes

More information

Presentation Outline

Presentation Outline Presentation Outline Nitrification/denitrification refresher Treatment technologies available for nitrification and BNR/ENR What is the problem? BNR/ENR VPDES permitting Causes of reduced BNR performance

More information

WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES

WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES WASTEWATER TREATMENT PLANT MASTER PLAN 6. BUSINESS CASE EVALUATION OF ALTERNATIVES A range of potential ammonia limits were identified for alternatives evaluation, as discussed in Section 2.2.5. This chapter

More information

AnoxKaldnes. Moving Bed Biofilm Reactor (MBBR) and Integrated Fixed-Film Activated Sludge (IFAS)

AnoxKaldnes. Moving Bed Biofilm Reactor (MBBR) and Integrated Fixed-Film Activated Sludge (IFAS) AnoxKaldnes Moving Bed Biofilm Reactor (MBBR) and Integrated Fixed-Film Activated Sludge (IFAS) AnoxKaldnes MBBR and Hybas Processes AnoxKaldnes is the global leader in MBBR and IFAS technologies. Kruger,

More information

Full Scale Testing to Demonstrate Anaerobic Selector Effect for Low Strength Wastewater

Full Scale Testing to Demonstrate Anaerobic Selector Effect for Low Strength Wastewater OWEA State Conference June 20, 2012 Full Scale Testing to Demonstrate Anaerobic Selector Effect for Low Strength Wastewater Presenters Bill Donohue NEORSD Bob Hrusovsky MWH Don Esping BC Easterly Plant

More information

SIMPLE and FLEXIBLE ENERGY SAVINGS And PERFORMANCE ENHANCEMENT for OXIDATION DITCH UPGRADES

SIMPLE and FLEXIBLE ENERGY SAVINGS And PERFORMANCE ENHANCEMENT for OXIDATION DITCH UPGRADES SIMPLE and FLEXIBLE ENERGY SAVINGS And PERFORMANCE ENHANCEMENT for OXIDATION DITCH UPGRADES Oxidation ditches are very popular wastewater treatment processes for small to medium sized municipalities that

More information

Soggy in Snohomish - Biofilm Media Improves Wet-Weather Lagoon Nitrification

Soggy in Snohomish - Biofilm Media Improves Wet-Weather Lagoon Nitrification Soggy in Snohomish - Biofilm Media Improves Wet-Weather Lagoon Nitrification Chuck McCall 1*, Erin Gallimore 1, Tom Giese 2, Steve Schuller 3, Karen Allen 3, Duane Leach 3 1 Entex Technologies Inc., Chapel

More information

Module 17: The Activated Sludge Process - Part III Answer Key

Module 17: The Activated Sludge Process - Part III Answer Key Module 17: The Activated Sludge Process - Part III Answer Key What other differences can you see between Complete Mix and Step Aeration? One of the features that make Complete Mix Aeration different from

More information

SECTION 8.0 NEWPCC SECOND PRIORITY CONTROL ALTERNATIVES

SECTION 8.0 NEWPCC SECOND PRIORITY CONTROL ALTERNATIVES SECTION 8.0 NEWPCC SECOND PRIORITY CONTROL ALTERNATIVES 8.1 PREAMBLE Table 8.1 below indicates the target ammonia concentrations for the Best Practicable and the Second Priority Levels of Control for the

More information

AMMONIA REMOVAL USING MLE PROCESS EXPERIENCES AT BALLARAT NORTH. David Reyne. Central Highlands Water Authority

AMMONIA REMOVAL USING MLE PROCESS EXPERIENCES AT BALLARAT NORTH. David Reyne. Central Highlands Water Authority AMMONIA REMOVAL USING MLE PROCESS EXPERIENCES AT BALLARAT NORTH Paper Presented by : David Reyne Author: David Reyne, Plant Operator Wastewater Treatment, Central Highlands Water Authority 65 th Annual

More information

The following biological nutrient removal processes were evaluated in detail in the 2016 Liquid Processing Facilities Plan:

The following biological nutrient removal processes were evaluated in detail in the 2016 Liquid Processing Facilities Plan: Nitrite Shunt Pilot Project Purpose: The purpose of this project is to full scale pilot test the nitrite shunt biological nutrient removal process to confirm process design criteria, impacts to sludge

More information

Nutrient Removal Optimization at the Fairview WWTP

Nutrient Removal Optimization at the Fairview WWTP Alyssa Mayer, PE Principal Engineer Nutrient Removal Optimization at the Fairview WWTP Mark Strahota, PE Associate Presentation Overview Project Background Process Model Development BNR Design Considerations

More information

Appendix D JWPCP Background and NDN

Appendix D JWPCP Background and NDN Appendix D JWPCP Background and NDN JWPCP Background JWPCP Water Quality Primary Clarifiers HPO Reactors Final Clarifiers Unit Influent Primary Effluent Secondary Effluent BOD mg/l 460 240

More information

Upgrade of an Oxidation Ditch Using Bio-Mass Carriers

Upgrade of an Oxidation Ditch Using Bio-Mass Carriers Upgrade of an Oxidation Ditch Using Bio-Mass Carriers Nir Assulin and Yigal Master Aqwise - Wise Water Technologies Ltd. The Problem Oxidation ditches (OD) are very popular wastewater treatment processes

More information

COLD WEATHER NITRIFICATION OF LAGOON EFFLUENT USING A MOVING BED BIOFILM REACTOR (MBBR) TREATMENT PROCESS

COLD WEATHER NITRIFICATION OF LAGOON EFFLUENT USING A MOVING BED BIOFILM REACTOR (MBBR) TREATMENT PROCESS ABSTRACT COLD WEATHER NITRIFICATION OF LAGOON EFFLUENT USING A MOVING BED BIOFILM REACTOR (MBBR) TREATMENT PROCESS Mr. Flemming G. Wessman 1 and Mr. Chandler H. Johnson 1 AnoxKaldnes, Inc., 58 Weybosset

More information

Integrated Fixed Film Activated Sludge (IFAS) System for Additional Nitrification at the Coldwater WWTP

Integrated Fixed Film Activated Sludge (IFAS) System for Additional Nitrification at the Coldwater WWTP Fishbeck, Thompson, Carr & Huber, Inc. Integrated Fixed Film Activated Sludge (IFAS) System for Additional Nitrification at the Coldwater WWTP Jim Flamming, P.E., Senior Process Engineer, FTC&H Dave Woodman,

More information

City of Elk River Wastewater Treatment Facility Improvements. Achieving Wastewater Treatment Goals

City of Elk River Wastewater Treatment Facility Improvements. Achieving Wastewater Treatment Goals City of Elk River Wastewater Treatment Facility Improvements Achieving Wastewater Treatment Goals By Tejpal Bala, P.E. Bolton & Menk, Inc. The City of Elk River received a new NPDES permit and the existing

More information

COMPARISON STUDY BETWEEN INTEGRATED FIXED FILM ACTIVATED SLUDGE (IFAS), MEMBRANE BIOREACTOR (MBR) AND CONVENTIONAL ACTIVATED SLUDGE (AS) PROCESSES

COMPARISON STUDY BETWEEN INTEGRATED FIXED FILM ACTIVATED SLUDGE (IFAS), MEMBRANE BIOREACTOR (MBR) AND CONVENTIONAL ACTIVATED SLUDGE (AS) PROCESSES Sixteenth International Water Technology Conference, IWTC 16 2012, Istanbul, Turkey 1 COMPARISON STUDY BETWEEN INTEGRATED FIXED FILM ACTIVATED SLUDGE (IFAS), MEMBRANE BIOREACTOR (MBR) AND CONVENTIONAL

More information

At the Mercy of the Process Impacts of Nitrogen Removal Performance on WWTP Disinfection

At the Mercy of the Process Impacts of Nitrogen Removal Performance on WWTP Disinfection OBG PRESENTS: At the Mercy of the Process Impacts of Nitrogen Removal Performance on WWTP Disinfection Ned Talbot, PE Tri-Association Conference 2018 8/30/18 9:00-9:30AM AGENDA Overview of Plant Processes

More information

ENHANCING THE PERFORMANCE OF OXIDATION DITCHES. Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis

ENHANCING THE PERFORMANCE OF OXIDATION DITCHES. Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis ENHANCING THE PERFORMANCE OF OXIDATION DITCHES Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis ABSTRACT Oxidation ditches are very popular wastewater treatment

More information

Watertown Wastewater Facility Plan. August 11, 2015

Watertown Wastewater Facility Plan. August 11, 2015 Watertown Wastewater Facility Plan August 11, 2015 Watertown Wastewater Wastewater Treatment Facility History Comprehensive Planning Wastewater Concerns Capacity Condition Permitting Requirements Watertown

More information

Compact Waste Water Treatment MBR /MBBR Technology

Compact Waste Water Treatment MBR /MBBR Technology Compact Waste Water Treatment MBR /MBBR Technology 1 Minimal Operation and Maintenance Costs and use of Chemicals 2 Recycle and Reuse water for Irrigation and Recreation 3 Save Water, Energy, Money and

More information

Technical Memorandum No. 1

Technical Memorandum No. 1 To: From: Steve McGowan, P.E., BCEE Project Manager, Malcolm Pirnie, Inc. Eric Wang, P.E. Project Engineer, Malcolm Pirnie, Inc. Date: Subject: August 11, 28 (Final) Madison MSD Project No. 84251 Malcolm

More information

NEWEA 2015 Annual Conference Session 16

NEWEA 2015 Annual Conference Session 16 NEWEA 2015 Annual Conference Session 16 Meeting North Attleborough, MA s 0.1 mg/l Phosphorus Limit with Bio-P and Cloth Media Filters January 27, 2015 Sue Guswa, P.E., Tighe & Bond Merrill Hastings, Town

More information

Water Resources Director: Chris Graybeal

Water Resources Director: Chris Graybeal Water Resources Director: Chris Graybeal Our Mission To promote and protect the environment, preserve natural resources, and ensure the health and safety of our customers. Granite Falls Wastewater Treatment

More information

Upgrading Lagoons to Remove Ammonia, Nitrogen, and Phosphorus *nutrient removal in cold-climate lagoon systems

Upgrading Lagoons to Remove Ammonia, Nitrogen, and Phosphorus *nutrient removal in cold-climate lagoon systems Upgrading Lagoons to Remove Ammonia, Nitrogen, and Phosphorus *nutrient removal in cold-climate lagoon systems October 7, 2015 3:15 4:00pm Session M Room Tamboti / Aloes-wood Treatment Processes Aerated

More information

Emerging Issues in the Water/Wastewater Industry. Austin s Full-Scale Step-BNR Demonstration

Emerging Issues in the Water/Wastewater Industry. Austin s Full-Scale Step-BNR Demonstration Summer Seminar Emerging Issues in the Water/Wastewater Industry Austin s Full-Scale Step-BNR Demonstration Rajendra P. Bhattarai, P.E., DEE Austin Water Utility, City of Austin 625 East 10 th Street, Suite

More information

Energy Reduction and Nutrient Removal in WWTPs Using Feed- Forward Process Control

Energy Reduction and Nutrient Removal in WWTPs Using Feed- Forward Process Control Energy Reduction and Nutrient Removal in WWTPs Using Feed- Forward Process Control Tilo Stahl, Ph.D. 1 *, George Lee 1, Matthew Gray 1, P.E, Steven Kestel 1 1 BioChem Technology, Inc., King of Prussia,

More information

Review of WEFTEC 2016 Challenge & Overview of 2017 Event. Malcolm Fabiyi, PhD, MBA Spencer Snowling, PhD. P.Eng

Review of WEFTEC 2016 Challenge & Overview of 2017 Event. Malcolm Fabiyi, PhD, MBA Spencer Snowling, PhD. P.Eng Review of WEFTEC 2016 Challenge & Overview of 2017 Event Malcolm Fabiyi, PhD, MBA Spencer Snowling, PhD. P.Eng Agenda Review 2016 Challenge Provide overview of updates to 2017 event Frequency WEFTEC Scores

More information

2015 Spring Conference

2015 Spring Conference 2015 Spring Conference Meeting Strict Summer Permit Requirements on Day One: Start-up of the Western Wake Regional Water Reclamation Facility Chris White, PE April 13, 2015 Acknowledgements Town of Cary

More information

Upgrade of the Marathon Louisiana Refining Division s Wastewater Treatment Plant to a State-of-the-Art Nitrification-Denitrification Facility

Upgrade of the Marathon Louisiana Refining Division s Wastewater Treatment Plant to a State-of-the-Art Nitrification-Denitrification Facility Upgrade of the Marathon Louisiana Refining Division s Wastewater Treatment Plant to a State-of-the-Art Nitrification-Denitrification Facility Presented to Air & Waste Management Association Louisiana Section

More information

TWO YEAR CASE STUDY OF INTEGRATED FIXED FILM ACTIVATED SLUDGE (IFAS) AT BROOMFIELD, CO WWTP West 124th Street Broomfield, CO 80020

TWO YEAR CASE STUDY OF INTEGRATED FIXED FILM ACTIVATED SLUDGE (IFAS) AT BROOMFIELD, CO WWTP West 124th Street Broomfield, CO 80020 ABSTRACT TWO YEAR CASE STUDY OF INTEGRATED FIXED FILM ACTIVATED SLUDGE (IFAS) AT BROOMFIELD, CO WWTP Mr. Ken Rutt 1, Jim Seda 1 and Mr. Chandler H. Johnson 2 1 City & County of Broomfield 2985 West 124th

More information

SECTION 2.0 WASTEWATER TREATMENT PLANT AND DISPOSAL SYSTEM DESCRIPTION

SECTION 2.0 WASTEWATER TREATMENT PLANT AND DISPOSAL SYSTEM DESCRIPTION SECTION 2.0 WASTEWATER TREATMENT PLANT AND DISPOSAL SYSTEM DESCRIPTION Analytical Environmental Services 2-1 Jamul Indian Village Wastewater Treatment Plant Analytical Environmental Services 2-2 Jamul

More information

Ditches for Energy Efficiency and Improved Nitrogen Removal

Ditches for Energy Efficiency and Improved Nitrogen Removal Upgrade of the Big Gulch WWTP Oxidation Ditches for Energy Efficiency and Improved Nitrogen Removal Thomas G. Authors: Thomas E. Coleman, dtec Systems Bridges, Mukilteo Water & Wastewater District Bend,

More information

Town of Robbinsville Constructs Cheoah River BNR Wastewater Treatment Facility to Meet New Nitrogen and Phosphorus Permit Limits

Town of Robbinsville Constructs Cheoah River BNR Wastewater Treatment Facility to Meet New Nitrogen and Phosphorus Permit Limits Town of Robbinsville Constructs Cheoah River BNR Wastewater Treatment Facility to Meet New Nitrogen and Phosphorus Permit Limits NORTH CAROLINA AWWA-WEA SPRING CONFERENCE ASHEVILLE, NORTH CAROLINA APRIL

More information

American Water College 2010

American Water College 2010 Vocabulary Activated Sludge (Part 1) Activated Sludge Sludge particles produced in raw or settled wastewater (primary effluent) by the growth of organisms (including zoogleal bacteria) in aeration tanks

More information

Design, Construction and Startup of the First Enhanced Nutrient Removal Plant in Maryland Funded by the Chesapeake Bay Restoration Fund

Design, Construction and Startup of the First Enhanced Nutrient Removal Plant in Maryland Funded by the Chesapeake Bay Restoration Fund Design, Construction and Startup of the First Enhanced Nutrient Removal Plant in Maryland Funded by the Chesapeake Bay Restoration Fund Rip Copithorn, Jeff Sturdevant, Vince Maillard GHD Clients People

More information

MUNICIPALITY OF WEST ELGIN WEST LORNE WASTEWATER TREATMENT PLANT

MUNICIPALITY OF WEST ELGIN WEST LORNE WASTEWATER TREATMENT PLANT MUNICIPALITY OF WEST ELGIN WEST LORNE WASTEWATER TREATMENT PLANT 214 ANNUAL REPORT uary 1 to ember 31, 214 Environmental Compliance Approval # 3-442-9-938 Prepared by: Table of Contents Section 1: Overview...

More information

Demonstration of IFAS Technology for Cold Temperature Nitrification in Lagoon WWTFs at Clare and Ludington, Michigan

Demonstration of IFAS Technology for Cold Temperature Nitrification in Lagoon WWTFs at Clare and Ludington, Michigan Demonstration of IFAS Technology for Cold Temperature Nitrification in Lagoon WWTFs at Clare and Ludington, Michigan Jason Borchert 1, Sarah Hubbell 2*, Heidi Rupp 2 1 Gourdie Fraser, Inc., Traverse City,

More information

Efficient Design Configurations for Biological Nutrient Removal

Efficient Design Configurations for Biological Nutrient Removal Efficient Design Configurations for Biological Nutrient Removal A Case Study: Upper Blackstone Water Pollution Abatement District Jane E. Madden, P.E., BCEE August 30, 2017 UBWPAD Wastewater Treatment

More information

CORPORATION THE EXPERIENCED LEADER IN SEQUENCING BATCH REACTOR TECHNOLOGY

CORPORATION THE EXPERIENCED LEADER IN SEQUENCING BATCH REACTOR TECHNOLOGY ISAM SEQUENCING BATCH REACTOR PROCESS TRUST FLUIDYNE S EXPERIENCE The Fluidyne ISAM Sequencing Batch Reactor (SBR) system incorporates the latest and most innovative technology and over two decades of

More information

AMPC Wastewater Management Fact Sheet Series Page 1

AMPC Wastewater Management Fact Sheet Series Page 1 Nitrogen removal Nitrogen present in meat processing wastewater are termed a nutrient, since they are essential elements for life. They largely derive from proteins dissolved into wastewater from meat

More information

AMPC Wastewater Management Fact Sheet Series Page 1

AMPC Wastewater Management Fact Sheet Series Page 1 Nitrogen removal Nitrogen present in meat processing wastewater are termed a nutrient, since they are essential elements for life. They largely derive from proteins dissolved into wastewater from meat

More information

75 th STREET WASTEWATER TREATMENT PLANT UPGRADES PROJECT

75 th STREET WASTEWATER TREATMENT PLANT UPGRADES PROJECT 75 th STREET WASTEWATER TREATMENT PLANT UPGRADES PROJECT Basis of Design Memorandum Design Memo No.: DM-7 (REVISED) Date: February 2005 Project/Task: 124487.001.420 Subject: Prepared by: Reviewed by: Hydraulic

More information

General Information on Nitrogen

General Information on Nitrogen General Information on Nitrogen What is nitrogen? Nitrogen was discovered in 1772 by Daniel Rutherford in Scotland Nitrogen gas makes up nearly 80% of the air we breathe Nitrogen gas is not toxic Nitrogen

More information

operation of continuous and batch reactors. Contrary to what happens in the batch reactor, the substrate (BOD) of the wastewater in the continuous rea

operation of continuous and batch reactors. Contrary to what happens in the batch reactor, the substrate (BOD) of the wastewater in the continuous rea The Effect of Ammonia Loading on the Nitrification Kinetic of Aerobic Baffled Continuous Biological Reactor S.R.M. Kutty, M.H. Isa and L.C. Leong Abstract - The purpose of this study is to determine the

More information

Hybrid Sequencing Batch Reactors (SBR) Offer an Efficient Wastewater Treatment

Hybrid Sequencing Batch Reactors (SBR) Offer an Efficient Wastewater Treatment Hybrid Sequencing Batch Reactors (SBR) Offer an Efficient Wastewater Treatment CONTRIBUTING WRITERS Michael Lahlou, E.I.T. and James Matthews, P.E. Batch processes are not a new or innovative wastewater

More information

Nutrient Removal Enhancement Using Process Automation at Holly Hill

Nutrient Removal Enhancement Using Process Automation at Holly Hill F W R J Nutrient Removal Enhancement Using Process Automation at Holly Hill Brad T. Blais, Kevin A. Lee, John E. Olson, and David W. Dubey The City of Holly Hill, located on the Atlantic Coast just north

More information

Choices to Address Filamentous Growth

Choices to Address Filamentous Growth Michigan Water Environment Association Process Seminar November 12, 2015 Choices to Address Filamentous Growth Richard Beardslee City of Battle Creek Nathan Cassity Donohue & Associates Outline Battle

More information

Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment

Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment OWEA 2013 Annual Conference June 19, 2013 Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment Jeff Lamson, Superintendent, WPCC Robert Hrusovsky,

More information

MEMBRANE AERATED BIOFILM REACTOR

MEMBRANE AERATED BIOFILM REACTOR MEMBRANE AERATED BIOFILM REACTOR MAY 2018 WHITE PAPER UDI TIROSH Fluence Corporation, All Rights Reserved 2018 MEMBRANE AERATED BIOFILM REACTOR: TECHNOLOGY OVERVIEW Introduction The Fluence Membrane Aerated

More information

Secondary Treatment Process Control

Secondary Treatment Process Control SARBS One-Day Training Seminar Phoenix Club, Anaheim Secondary Treatment Process Control Graham Juby June 5, 2013 Objectives Provide an understanding of nitrogen removal process interactions to support

More information

Aqua MSBR MODIFIED SEQUENCING BATCH REACTOR

Aqua MSBR MODIFIED SEQUENCING BATCH REACTOR MODIFIED SEQUENCING BATCH REACTOR MODIFIED SEQUENCING BATCH REACTOR For over three decades, Aqua-Aerobic Systems has led the industry in sequencing batch reactor technology with performance proven and

More information

Stonecrest Estates Sewage Treatment Plant 2017 Annual Report

Stonecrest Estates Sewage Treatment Plant 2017 Annual Report 2017 Stonecrest Estates Sewage Treatment Plant 2017 Annual Report The Corporation of the City of Quinte West 0 Contents Table of Figures... 1 Executive Summary... 3 Summary and Interpretation of Monitoring

More information

ENHANCED BIOLOGICAL PHOSPHORUS REMOVAL WITHIN MEMBRANE BIOREACTORS. 255 Consumers Road Toronto, ON, Canada, M2J 5B6

ENHANCED BIOLOGICAL PHOSPHORUS REMOVAL WITHIN MEMBRANE BIOREACTORS. 255 Consumers Road Toronto, ON, Canada, M2J 5B6 ENHANCED BIOLOGICAL PHOSPHORUS REMOVAL WITHIN MEMBRANE BIOREACTORS G. Crawford 1,2, G. Daigger 1, and Z. Erdal 1 1 CH2M HILL 2 CH2M HILL 255 Consumers Road Toronto, ON, Canada, M2J 5B6 ABSTRACT Several

More information

Brightwater: The Design Challenges of a 39 mgd (150 MLD) Membrane Bioreactor

Brightwater: The Design Challenges of a 39 mgd (150 MLD) Membrane Bioreactor Brightwater: The Design Challenges of a 39 mgd (150 MLD) Membrane Bioreactor J. Komorita 1, P. Burke 2, B. Youker 2, and G. Crawford 2 1 King County, 2 CH2M HILL ABSTRACT Many Membrane Bioreactor (MBR)

More information

We Know Water. NEOSEP Membrane Bioreactor (MBR) WATER TECHNOLOGIES

We Know Water. NEOSEP Membrane Bioreactor (MBR) WATER TECHNOLOGIES We Know Water NEOSEP Membrane Bioreactor (MBR) WATER TECHNOLOGIES Veolia s NEOSEP MBR NEOSEP combines the best attributes of hollow fiber and flat sheet membranes with the use of hybrid FibrePlate membranes

More information

CORPORATION THE EXPERIENCED LEADER IN SEQUENCING BATCH REACTOR TECHNOLOGY

CORPORATION THE EXPERIENCED LEADER IN SEQUENCING BATCH REACTOR TECHNOLOGY ISAM SEQUENCING BATCH REACTOR PROCESS TRUST FLUIDYNE S EXPERIENCE The Fluidyne ISAM Sequencing Batch Reactor (SBR) system incorporates the latest and most innovative technology and over three decades of

More information

Membrane Bioreactor and High Flow Biological Treatment System for the Cox Creek WRF

Membrane Bioreactor and High Flow Biological Treatment System for the Cox Creek WRF Membrane Bioreactor and High Flow Biological Treatment System for the Cox Creek WRF Thor Young, GHD With Contributions from Vince Maillard, Rip Copithorn, Kristi Perri, and Jeff Sturdevant, GHD Dimitrios

More information

Operation and Control of Multiple BNR Processes in One WWTP

Operation and Control of Multiple BNR Processes in One WWTP Operation and Control of Multiple BNR Processes in One WWTP CENTRAL PLANT Williamsport Sanitary Authority s Chesapeake Bay and CSO Compliance Program Presented by: Phil Anderson 1 June 24, 2015 Purpose

More information

WASTEWATER DEPARTMENT. Bentonville Wastewater Treatment Plant Facts:

WASTEWATER DEPARTMENT. Bentonville Wastewater Treatment Plant Facts: Mission: The mission of the Bentonville Wastewater Treatment Utility and staff is to protect public health and the environment through the effective treatment of wastewater. Effective wastewater treatment

More information

City of Andover, Kansas Energy Assessment-Wastewater Treatment Plant

City of Andover, Kansas Energy Assessment-Wastewater Treatment Plant City of Andover, Kansas Energy Assessment-Wastewater Treatment Plant April 7, 2014 Prepared by Jerry Blain, P.E., Project Associate Environmental Finance Center Funding for this Energy Assessment was provided

More information

NUTRIENT REMOVAL PROCESSES IN WASTEWATER TREATMENT. We re Glad You re Here!

NUTRIENT REMOVAL PROCESSES IN WASTEWATER TREATMENT. We re Glad You re Here! NUTRIENT REMOVAL PROCESSES IN WASTEWATER TREATMENT We re Glad You re Here! Please, put your cell phones on vibrate during sessions and, take calls to the hallway NUTRIENT REMOVAL PROCESSES IN WASTEWATER

More information

Planning for the Future Battle Creek s Approach to Upgrading its Secondary Treatment Processes

Planning for the Future Battle Creek s Approach to Upgrading its Secondary Treatment Processes Planning for the Future Battle Creek s Approach to Upgrading its Secondary Treatment Processes Michigan Water Environment Association Annual Conference June 21, 2016 Richard Beardslee, City of Battle Creek

More information

ISAM SBR with Blower Assisted Jet Aeration Design Calculations For Lyons, CO WWTP Upgrade

ISAM SBR with Blower Assisted Jet Aeration Design Calculations For Lyons, CO WWTP Upgrade ISAM SBR with Blower Assisted Jet Aeration Design Calculations For Lyons, CO WWTP Upgrade May. 28, 2013 A. Site Conditions 1. Site elevation = 5,322 ft MSL 2. Average barometric pressure = 12.07 psia 3.

More information

membrane bioreactor performance compared to conventional wastewater treatment

membrane bioreactor performance compared to conventional wastewater treatment Water Technologies & Solutions technical paper membrane bioreactor performance compared to conventional wastewater treatment Authors: Thomas C. Schwartz and Brent R. Herring, Woodard and Curran Incorporated

More information

PILOT SCALE TESTS OF A UNIQUE APPROACH FOR BNR UPGRADE OF A SHORT SRT HIGH PURITY OXYGEN SYSTEM AT PIMA COUNTY, AZ

PILOT SCALE TESTS OF A UNIQUE APPROACH FOR BNR UPGRADE OF A SHORT SRT HIGH PURITY OXYGEN SYSTEM AT PIMA COUNTY, AZ PILOT SCALE TESTS OF A UNIQUE APPROACH FOR BNR UPGRADE OF A SHORT SRT HIGH PURITY OXYGEN SYSTEM AT PIMA COUNTY, AZ ABSTRACT Ron Riska,: Pima County Wastewater Management Division Joseph A. Husband, P.E.,

More information

A SIMPLE SOLUTION TO BIG SNAIL PROBLEMS - A CASE STUDY AT VSFCD S RYDER STREET WASTEWATER TREATMENT PLANT

A SIMPLE SOLUTION TO BIG SNAIL PROBLEMS - A CASE STUDY AT VSFCD S RYDER STREET WASTEWATER TREATMENT PLANT A SIMPLE SOLUTION TO BIG SNAIL PROBLEMS - A CASE STUDY AT VSFCD S RYDER STREET WASTEWATER TREATMENT PLANT Timothy R. Tekippe, P.E.,* Robert J. Hoffman, P.E.,* Ronald J. Matheson,** Barry Pomeroy** *Carollo

More information

Aeration University Advanced Concepts in Energy Efficiency

Aeration University Advanced Concepts in Energy Efficiency Aeration University Advanced Concepts in Energy Efficiency Wisconsin Wastewater Operators Association 47 th Annual Conference October 23, 2013 Presented by Phil Korth Aeration and Energy Wastewater Treatment

More information

Water Technologies. The AGAR Process: Make Your Plant Bigger Without Making it Bigger

Water Technologies. The AGAR Process: Make Your Plant Bigger Without Making it Bigger Water Technologies The AGAR Process: Make Your Plant Bigger Without Making it Bigger Enhanced Wastewater Treatment The unique, patented AGAR (Attached Growth Airlift Reactor) process from Siemens is the

More information

CSR Process Simulations Can Help Municipalities Meet Stringent Nutrient Removal Requirements

CSR Process Simulations Can Help Municipalities Meet Stringent Nutrient Removal Requirements CSR Process Simulations Can Help Municipalities Meet Stringent Nutrient Removal Requirements Continuous Flow Sequencing Reactor (CSR) Basin with Moving Bridge, Submerged Diffusers, and Stationary Diffusers

More information

From manual to automatic at Spring Creek

From manual to automatic at Spring Creek When upgrading its water resource recovery facility on Spring Creek, the Springfield (Ill.) Metro Sanitary District designed with operations in mind. By bringing together operators and designers, the district

More information

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010 Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP by: William Leaf Adrienne Menniti Bruce Johnson CH2M HILL, Inc. Clint Dolsby Tracy Crane City of Meridian October 26, 21

More information

WWTF Capacity Assessment Project

WWTF Capacity Assessment Project Wastewater Treatment Facility Evaluation The Richland WWTF was constructed in 1985 to provide primary and secondary treatment for the City's wastewater. Section 3 includes a general description of the

More information

WWTP Side Stream Treatment of Nutrients Considerations for City of Raleigh s Bioenergy Recovery Project. Erika L. Bailey, PE, City of Raleigh

WWTP Side Stream Treatment of Nutrients Considerations for City of Raleigh s Bioenergy Recovery Project. Erika L. Bailey, PE, City of Raleigh WWTP Side Stream Treatment of Nutrients Considerations for City of Raleigh s Bioenergy Recovery Project Erika L. Bailey, PE, City of Raleigh LNBA / NRCA 2017 Wastewater Treatment Plant Operators Training

More information

Wastewater Facility Plan City of Marshall, Minnesota

Wastewater Facility Plan City of Marshall, Minnesota Wastewater Facility Plan City of Marshall, Minnesota Public Hearing March 14, 2017 Bolton & Menk, Inc. Project No. T22.108560 Glossary of General Terms & Abbreviations MPCA - Minnesota Pollution Control

More information

DEVELOPMENT OF THE. Ken Mikkelson, Ph.D. Ed Lang Lloyd Johnson, P.E. Aqua Aerobic Systems, Inc.

DEVELOPMENT OF THE. Ken Mikkelson, Ph.D. Ed Lang Lloyd Johnson, P.E. Aqua Aerobic Systems, Inc. DEVELOPMENT OF THE AquaMB PROCESS Ken Mikkelson, Ph.D. Ed Lang Lloyd Johnson, P.E. Aqua Aerobic Systems, Inc. Aqua-Aerobic Systems, Inc. 6306 N. Alpine Road Rockford, IL 61111 Copyright 2003 Aqua-Aerobic

More information

RE ENGINEERING O&M PRACTICES TO GET NITROGEN & PHOSPHORUS REMOVAL WITHOUT FACILITY UPGRADES

RE ENGINEERING O&M PRACTICES TO GET NITROGEN & PHOSPHORUS REMOVAL WITHOUT FACILITY UPGRADES RE ENGINEERING O&M PRACTICES TO GET NITROGEN & PHOSPHORUS REMOVAL WITHOUT FACILITY UPGRADES GRANT WEAVER, PE & WASTEWATER OPERATOR WISCONSIN WASTEWATER OPERATORS ASSOCIATION WISCONSIN DELLS, WI OCTOBER

More information

Waste Water Treatment Plant Overview and Tour

Waste Water Treatment Plant Overview and Tour Waste Water Treatment Plant Overview and Tour Outline Definitions Chronology BNR Process Description Plant Performance Site Photos Definitions SWPCC: Summerside Water Pollution Control Centre Activated

More information