Unemployment Compensation Project Independent Verification and Validation Monthly Assessment Report Summary. period ending 29 October 2010

Size: px
Start display at page:

Download "Unemployment Compensation Project Independent Verification and Validation Monthly Assessment Report Summary. period ending 29 October 2010"

Transcription

1 Unemployment Compensation Project Independent Verification and Validation Monthly Assessment Report Summary period ending 29 October 2010

2 Topics for discussion General IV&V overview Overall risk state and trending Key indicators Key findings and risk areas Recommendations Upcoming IV&V activities Open deficiencies and implications Summary of changes Page 2

3 General IV&V overview The project office (PMO) is in the process of mobilizing the PMO for UC3 including the development of a PMO mobilization schedule, project charter, project plan, and schedule for UC3. The PMO has begun onboarding key stakeholders and training them on the project procedures documented in the project plan (PMP). The UC3 Project Team and the IV&V Team are working together to avoid any deficiencies in the UC3 project processes, controls and execution. Page 3

4 Overall risk state and trending Program Functionality Technical architecture Risk state of UC Project Resource T1 T4 Functional requirements T7 P3 Operations support High-level system architecture Requirements mapping Technology Cost Risk adjusted financials T2 T5 T8 P2 P6 Non-functional requirements Legacy integration Stabilization Governance Performance Risk T3 T6 T9 P1 P5 P9 B1 Business objectives and value alignment Cost, benefit and risk B4 B7 Compliance and regulatory Time P4 Quality P8 B2 B5 Business process Benefits tracking Investment governance and approval B8 As of 29 October 2010 Change P7 Organization design B3 Communication B6 Reporting and value monitoring B9 Business CMMI gap of risks with trending T3 Technology P1 T5 P4 T7 T8 T1 T2 T4 T6 T9 P2 P5 P3 Program Maturity complexity match P6 P7 B7 B9 B6 B5 B8 Difference between target and current CMMI rating P8 B4 P9 B1 B2 B3 Business Indicates that the area being assessed has critical issues that will result in significant risk to the project most likely resulting in either the inability to achieve the outcomes, inability to meet the projected schedule, or a significant cost over-run. Requires immediate action. Indicates that the area being assessed has issues that need to be resolved; inefficiencies exist. Current process/method can be used with refinement. Indicates that the area being assessed did not have significant issues to report. Continued monitoring should be performed. Indicates that the area being assessed has incomplete information available for a conclusive finding or is not applicable. Page 4

5 Key indicators Indicator Value Comment Is the project approach sound? Yes Critical deficiencies with the UC project previously identified by the IV&V Team have been addressed. Is the project on time? Is the project on budget? Is there scope variance (scope creep)? What are the project s future risks? Are the project s risks increasing or decreasing? Are there new or emerging technological solutions that will affect the project s technology assumptions? Yes Yes No N/A Decreasing Unknown The work being completed as part of the UC2 project is within the scope of the project as defined in the UC modernization project phase 2 RFQ. The UC3 Project Team and the IV&V Team are working together to avoid any deficiencies in the UC3 project processes, controls and execution. Page 5

6 Key findings and risk areas The governance structure does not contain a decision framework in sufficient detail to properly govern the project. As a result, it is not clear how risks and issues are escalated through the governance tiers, as well as who is responsible for making decisions. Program processes, controls, and disciplines are not in place and not properly institutionalized within the UC project. This has resulted in incomplete project planning, inadequate integrated master schedules, lack of appropriate performance, resource, and overall poor program visibility. Page 6

7 Recommendations Governance Program Business Technology Area Recommendations Define decision frameworks for each level of governance with attendant priorities and decision rights. Outline expectations, accountability and authority for each governance tier. Establish and communicate priorities for decision criteria to ensure decisions are aligned to the project s objectives. Define success based upon the realization of business benefits and develop metrics to measure the level of success. Develop an integrated master schedule that allows for the roll-up of activities, work effort, resources and costs. Develop a risk strategy and decision framework. Map the risk events in the risk register with plan activities and analyze through simulation to determine risk hotspots, overall cost and schedule risk exposure, and cost benefit analysis of alternate mitigation scenarios. Implement objective-based performance metrics (e.g., earned value ) to the project master schedule to more accurately track remaining effort and performance to date. Build the capability within the project governance structure to integrate risk, change control and planning processes including an associated risk decision framework. None None Page 7

8 Upcoming IV&V activities Conduct deliverable assessment on the UC3 project materials. Includes project charter, project plan, project schedule and supporting documents and information. Schedule and conduct interviews with key stakeholders as part of the baseline assessment. Eighteen (18) interviews to be conducted weeks of 8 and 15 November Conduct baseline assessment and prepare Baseline Assessment Report (BAR). Page 8

9 Open deficiencies and implications No. Areas Deficiency Implications D1 P1: Governance The decision framework is not defined in sufficient detail to properly govern the project. Limited capacity to facilitate timely decision making and forecast typical challenges (risks and issues) that could face the program. Inability to deliver a desirable solution that represents the anticipated outcome for the business units. Misalignment in project operational decisions to the intended project objectives. D2 P2: Cost P3: Resource P4: Time P5: Performance The project schedule is not an integrated master schedule (IMS) and does not contain all elements required to make it useful for managing the project. Unable to establish true visibility and determine forecasting capability to schedule and cost performance in achieving project expectations. Unable to determine the true cost performance and probabilistic cash flow. D3 P5: Performance There is no performance measurement baseline (PMB) against which program performance can be measured. Inability to ascertain and analytically support a point of view for current and forecasted project performance. The lack of performance metrics impacts the ability to effectively manage timelines and resources. D7 P1: Governance P9: Risk Management The governance structure and associated decision framework is not defined in sufficient detail to properly manage risks and issues. Inadequate handling of risks (identification, mitigation and resolution) and limited dealing with issues that evolve from risks. Page 9

10 Summary of changes Item Deficiencies addressed New deficiencies identified Risk ratings Capability maturity model integrated (CMMI) ratings Interviews conducted Artifacts received Description Open deficiencies identified in the last report have not been addressed. No new deficiencies identified since the last report. No risk ratings changed since the last report. No CMMI rating changes since the last report. No interviews conducted since the last report. Artifacts received include budget and status reports. Page 10

Unemployment Compensation Project Independent Verification and Validation Monthly Assessment Report Summary. period ending 30 September 2010

Unemployment Compensation Project Independent Verification and Validation Monthly Assessment Report Summary. period ending 30 September 2010 Unemployment Compensation Project Independent Verification and Validation Monthly Assessment Report Summary period ending 30 September 2010 General All critical deficiencies with the UC project identified

More information

Florida PALM Quarterly Project Oversight Report: Comprehensive Review For April - June 2015

Florida PALM Quarterly Project Oversight Report: Comprehensive Review For April - June 2015 Department of Financial Services Florida Planning, Accounting, and Ledger Management (PALM) For Period: April June 2015 Project Description Quarter Ending: 6/30/2015 Agency Name: Department of Financial

More information

Monthly IV&V Assessment Report (December 1 31, 2015)

Monthly IV&V Assessment Report (December 1 31, 2015) Monthly IV&V Assessment Report (December 1 31, 2015) Department of Financial Services Date: 01/13/2016 Version 1.0 Table of Contents Department of Financial Services Executive Summary... 4 Project... 4

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting and Ledger Management (PALM) Project April 2016 Date: 5/11/2016 Version 1.0 Table of Contents Executive Summary...

More information

Part Work plan and IV&V methodology

Part Work plan and IV&V methodology Part 3 4.4.3 Work plan IV&V methodology EY s IV&V methodology is an explicit risk quantitative process that proactively identifies the interrelationship of factors conditions that could impede the success

More information

Title: Project Director Location: Tallahassee, FL Clearance: none required

Title: Project Director Location: Tallahassee, FL Clearance: none required Title: Project Director Location: Tallahassee, FL Clearance: none required Position Overview: The Project Director (PD) shall define, establish, and direct the planning and operations of the Project Management

More information

Project Charter. A. General Information

Project Charter. A. General Information A. General Information Project Title: Brief Project Description: Prepared By: Date: Version: B. Project Objective: Explain the specific objectives of the project. For example: What value does this project

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting, and Ledger Management (PALM) Project February 2018 Date: 3/12/2018 Version 1.0 Table of Contents Executive

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting and Ledger Management (PALM) Project February 2016 Date: 3/10/2016 Version 1.0 Table of Contents Executive

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting and Ledger Management (PALM) Project September 2016 Date: 10/12/2016 Version 1.0 Table of Contents Executive

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting, and Ledger Management (PALM) Project October 2017 Date: 11/13/2017 Version 1.0 Table of Contents Executive

More information

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes

More information

1.0 PART THREE: Work Plan and IV&V Methodology

1.0 PART THREE: Work Plan and IV&V Methodology 1.0 PART THREE: Work Plan and IV&V Methodology 1.1 Multi-Faceted IV&V Methodology Large, complex projects demand attentive and experienced IV&V and project management support to meet expectations. Monitoring

More information

ISACA Systems Implementation Assurance February 2009

ISACA Systems Implementation Assurance February 2009 ISACA Pressures Today Pressure to increase realization of value from IT spending Pressure to deliver on IT projects at a time when resources/budgets are constrained Pressure from risk of technology-based

More information

Metric systems for executive overview

Metric systems for executive overview Metric systems for executive overview Martin Woznica & Jesse Crowley Presenter Title October 24 th, 2012 Copyright 2011 Raytheon Company. All rights reserved. Customer Success Is Our Mission is a registered

More information

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Introduction How to Read an Activity Description Objective: Provides the overall objective of the activity :

More information

Using your EAC as a GPS 6 Characteristics of a Good EAC. Kim Koster, Senior Director IPM

Using your EAC as a GPS 6 Characteristics of a Good EAC. Kim Koster, Senior Director IPM Using your EAC as a GPS 6 Characteristics of a Good EAC Kim Koster, Senior Director IPM Top Ten Reasons Projects Fail BAD plans and inadequate planning processes Proposal not adequate Lack of scope comprehension

More information

CMMI Project Management Refresher Training

CMMI Project Management Refresher Training CMMI Project Management Refresher Training Classifica(on 2: Foxhole Technology Employees Only RMD 032 Project Management Refresher Training Course September 21, 2017 Version 1.0 The Process Approach The

More information

This resource is associated with the following paper: Assessing the maturity of software testing services using CMMI-SVC: an industrial case study

This resource is associated with the following paper: Assessing the maturity of software testing services using CMMI-SVC: an industrial case study RESOURCE: MATURITY LEVELS OF THE CUSTOMIZED CMMI-SVC FOR TESTING SERVICES AND THEIR PROCESS AREAS This resource is associated with the following paper: Assessing the maturity of software testing services

More information

Be Able to React to Change Quickly! Integrated Business Planning Overview

Be Able to React to Change Quickly! Integrated Business Planning Overview Be Able to React to Change Quickly! Integrated Business Planning Overview John Mervis Value Chain Planning Oracle Confidential Internal/Restricted/Highly Restricted Safe Harbor Statement The following

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

OE PROJECT CHARTER PROJECT NAME: PREPARED BY: PROJECT CHARTER VERSION HISTORY VERSION DATE

OE PROJECT CHARTER PROJECT NAME: PREPARED BY: PROJECT CHARTER VERSION HISTORY VERSION DATE PROJECT : PREPARED BY: Josh Blatt DATE (MM/DD/YYYY): 1/9/2012 Institutional Data Council Project Manager PROJECT CHARTER VERSION HISTORY VERSION DATE COMMENTS (DRAFT, SIGNED, REVISED CURRENT STATUS) (MM/DD/YYYY)

More information

Can t Afford the Cost of Failure? Try Process-Based Risk Management

Can t Afford the Cost of Failure? Try Process-Based Risk Management Can t Afford the Cost of Failure? Try Process-Based Risk Management A Stakeholder Management Case Study of the Washington State Health Benefit Exchange Healthplanfinder Project Paul S. Royer, PMP Agenda

More information

AGENCY FOR STATE TECHNOLOGY

AGENCY FOR STATE TECHNOLOGY AGENCY FOR STATE TECHNOLOGY PROJECT RISK & COMPLEXITY ASSESSMENT TOOL Risk & Complexity Assessment Model for State Information Technology Projects Purpose: In order to determine the level of risk associated

More information

MITA 01 MITA SS A: Achievable Strategies for the MITA Roadmap and Enterprise Maturity Overview of MMIS Procurement Strategy Process

MITA 01 MITA SS A: Achievable Strategies for the MITA Roadmap and Enterprise Maturity Overview of MMIS Procurement Strategy Process MITA 01 MITA SS A: Achievable Strategies for the MITA Roadmap and Enterprise Maturity Overview of MMIS Procurement Process Presented September 10, 2013] At the Medicaid Enterprise Systems Conference Charleston,

More information

<Project Name> Charter

<Project Name> Charter < NOTE: Remove the italicized, bracketed guidance before routing for approvals. > General Information 1. Project Number: 2. Project Name: 3. Executive : 4. Business : 5. IT : 6. Project Manager/Lead: Executive

More information

Overview: Status Reports/Dashboards provide program leadership and governance with updates on program progress, and strategic program risks/issues.

Overview: Status Reports/Dashboards provide program leadership and governance with updates on program progress, and strategic program risks/issues. M3 Playbook Guidance Phase 4: Migration This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration

More information

IPM Systems Engineering EV Practitioners Forum August 25, 2017

IPM Systems Engineering EV Practitioners Forum August 25, 2017 IPM Systems Engineering EV Practitioners Forum August 25, 2017 Gordon M. Kranz gmkranz@eipm-llc.com gordon.kranz@agileforgovernment.com 8/22/17 Ó 2016 Enlightened Integrated Program Management, LLC All

More information

Audit of Information Management. Internal Audit Report

Audit of Information Management. Internal Audit Report Audit of Information Management Internal Audit Report October 2011 Table of Contents EXECUTIVE SUMMARY 2 1.0 INTRODUCTION...... 6 1.1 BACKGROUND... 6 1.2 RISK ASSESSMENT...... 7 1.3 AUDIT OBJECTIVES AND

More information

PART THREE - WORK PLAN AND IV&V METHODOLOGY WORK PLAN. FL IT IV&V Work Plan

PART THREE - WORK PLAN AND IV&V METHODOLOGY WORK PLAN. FL IT IV&V Work Plan WORK PLAN FL IT IV&V Work Plan PART THREE - WORK PLAN AND IV&V METHODOLOGY ID Task Name Duration 1 FL IT IV&V Project Work Plan 261 days 2 DDI / SI Contract Award 0 days 3 Project Initiation and Planning

More information

Executive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 July 27, 2016

Executive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 July 27, 2016 Executive Steering Committee Meeting Department of Revenue Building 2, Room 1250 Roll Call and Opening Remarks Facilitator: Robert (Budd) Kneip, Chair Review of June 2016 Meeting Minutes Facilitator: Robert

More information

Project Connect. December 12, 2012

Project Connect. December 12, 2012 Project Connect December 12, 2012 Introduction Meeting Minutes Approval Project Status Report IV&V Update by Ernst & Young Other Business Public Comments Review of Actions from Meeting Scheduling of Next

More information

How to Drive Business Value with Capacity Management

How to Drive Business Value with Capacity Management How to Drive Business Value with Capacity Management 18 July 2017 Your Presenter Jim Smith The Building Blocks Executive Buy-in Benefits realization Assessment Roles and responsibilities Strategy Toolset

More information

Work Plan and IV&V Methodology

Work Plan and IV&V Methodology Work Plan and IV&V Methodology ISG Public Sector has been helping public sector organizations acquire and implement (from a project oversight and organizational change management perspective) new, enterprise-wide

More information

Financial and Cash Management Task Force

Financial and Cash Management Task Force Financial and Cash Management Task Force Recommended Enterprise Project Governance 12/1/08 1.1 It is important to address the proper structure for governing projects that will be implementing enterprise

More information

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan M3 Playbook Guidance Phase 1: Readiness This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration

More information

Independent Verification and Validation (IV&V)

Independent Verification and Validation (IV&V) Independent Verification and Validation (IV&V) 12 th Annual NDIA CMMI Conference November 2012 - Denver, CO The MITRE Corporation The author s affiliation with The MITRE Corporation is provided for identification

More information

Preparing your organization for a Human Resource Outsourcing implementation

Preparing your organization for a Human Resource Outsourcing implementation IBM Global Technology Services Thought Leadership White Paper April 2013 Preparing your organization for a Human Resource Outsourcing implementation How to collaborate for a more successful transition

More information

PD Re-engineering Program Charter

PD Re-engineering Program Charter PD Re-engineering Program Charter Version:.0 Date: May 0, 0 Page Table of Contents INTRODUCTION... PROGRAM PURPOSE... PROGRAM OBJECTIVES... PROGRAM SCOPE DEFINITIONS... PD Re-engineering Program Scope

More information

Efficiency First Program

Efficiency First Program Efficiency First Program Short-Term Impact; Long-Term Results Presented to: Discussion Points About AOTMP Your Telecom Environment The Efficiency First Framework Our Approach The Efficiency First Program

More information

The Key Project Processes That Drive Project Outcomes. Copyright of Dr. E.L. Owens, Jr. April 20,

The Key Project Processes That Drive Project Outcomes. Copyright of Dr. E.L. Owens, Jr. April 20, The Key Project Processes That Drive Project Outcomes 1 Data 2 Sample Statistics Data 3 Sample Statistics Data 4 Sample Statistics Data 5 Data Sample Statistics 6 PMDP Project Management Description Processes

More information

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B 1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework

More information

Oilpocalypse Now: Weathering the Storm with Integrated Project Management Samarth Jain Andrew Lavinsky

Oilpocalypse Now: Weathering the Storm with Integrated Project Management Samarth Jain Andrew Lavinsky Oilpocalypse Now: Weathering the Storm with Integrated Project Management Samarth Jain Andrew Lavinsky June 2, 2015 Devon Energy Center Oklahoma City, Oklahoma, USA Welcome 3 Agenda Business Context Importance

More information

Information Services Group Public Sector

Information Services Group Public Sector IV&V Assessment Report - Deliverable IVV2.2 Presented by: Information Services Group Public Sector December 12, 2018 2018 Information Services Group, Inc. All Rights Reserved Copyright 2018, Information

More information

Executive Steering Committee Meeting. Department of Revenue Building 1 August 9, 2017

Executive Steering Committee Meeting. Department of Revenue Building 1 August 9, 2017 Executive Steering Committee Meeting Department of Revenue Building 1 Roll Call and Opening Remarks Facilitator: Robert (Budd) Kneip, Chair Review of June 20, 2017 Meeting Minutes Facilitator: Melissa

More information

Project Management Assessment. Apply an In-Depth Approach to Project Management to Achieve Systematic Success

Project Management Assessment. Apply an In-Depth Approach to Project Management to Achieve Systematic Success Management Assessment Apply an In-Depth Approach to Management to Achieve Systematic Success Your Journey Starts Here. Understand Your PM Strengths & Weaknesses Evaluate Performance and Required Next Steps

More information

Why PMOs Fail: Is Your Organization at Risk?

Why PMOs Fail: Is Your Organization at Risk? Why PMOs Fail: Is Your Organization at Risk? June 10, 2010 Presented by Phil Kyle Infinitive 2010 1 Agenda» Defining Our Terms» How PMOs Create Tangible Value» What Are the Common PMO Pitfalls?» Assessing

More information

DEPARTMENT OF REVENUE BUILDING 2 SEPTEMBER 26, 2018

DEPARTMENT OF REVENUE BUILDING 2 SEPTEMBER 26, 2018 DEPARTMENT OF REVENUE BUILDING 2 SEPTEMBER 26, 2018 3 FACILITATOR: RYAN WEST 4 FACILITATOR: MELISSA TURNER 5 FACILITATORS: MELISSA TURNER, CAROLYN HICKS, PAUL LAVERY, RACHAEL LIEBLICK, ANGIE ROBERTSON

More information

Yvette Soliz Rivers PMP, CQA, MBA. PROGRAM MANAGEMENT AND IV&V CONSULTANT

Yvette Soliz Rivers PMP, CQA, MBA. PROGRAM MANAGEMENT AND IV&V CONSULTANT Enlightening program performance. Yvette Soliz Rivers PMP, CQA, MBA PROGRAM MANAGEMENT AND IV&V CONSULTANT 703-498-1319 yrivers@luzent.com SUMMARY. Ms. Rivers is an accomplished management consultant recognized

More information

Project Management Advisory Board Deep Dive Study of Program Management

Project Management Advisory Board Deep Dive Study of Program Management Project Management Advisory Board Deep Dive Study of Program Management Purpose The purpose of this study is twofold: 1. Understand how Saint Louis companies are managing programs 2. Study the maturity

More information

PMP TRAINING COURSE CONTENT

PMP TRAINING COURSE CONTENT PMP TRAINING COURSE CONTENT SECTION1: INTRODUCTION PMI, PMP AND PMBOK What is PMI, PMP, and PMBOK? What do I get out of PMP? How do I get certified? Exam qualifications and PM experience Guidelines to

More information

Guten Tag. (good day)

Guten Tag. (good day) Guten Tag (good day) 4.5 Perform Integrated Change Control How a person may percieve change: paideiagroup.com 4.5 Perform Integrated Change Control Consider what change is: Crossing unknown territory Departing

More information

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Introduction How to Read an Activity Description Objective: Provides the overall objective of the activity :

More information

Project+ Examination Blueprint Version June 1, 2003

Project+ Examination Blueprint Version June 1, 2003 Introduction The Project + examination is designed for business professionals involved with projects with a technology component. The examination is designed for candidates possessing at least 12 months

More information

HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018

HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018 HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018 3 FACILITATOR: MELISSA TURNER 4 FACILITATOR: MELISSA TURNER 5 FACILITATORS: DAYMON JENSEN, RACHAEL LIEBLICK, MELISSA TURNER Budget FY

More information

Enterprise Risk Management

Enterprise Risk Management Enterprise Risk Management A Roadmap For Implementation June 12, 2018 Presented by: Speaker Name Marianne Turnbull CohnReznick LLP 4 Becker Farm Road Roseland, NJ 07068 P: 973-228-3500 E:marianne.turnbull@cohnreznick.com

More information

PROJECT SCHEDULING & CONTROL

PROJECT SCHEDULING & CONTROL PROJECT SCHEDULING & CONTROL Project Project Management PM Knowledge Areas Time Management 1 Project What is a PROJECT? Definition used by PMI: A temporary endeavor undertaken to create a unique product,

More information

Ensuring Project Success with QA/QC and IV&V

Ensuring Project Success with QA/QC and IV&V Ensuring Project Success with QA/QC and IV&V Presented September 10, 2013 At the Medicaid Enterprise Systems Conference Charleston, South Carolina By Colleen May About CSG Government Solutions Government

More information

Executive Steering Committee Medicaid Eligibility System

Executive Steering Committee Medicaid Eligibility System Project June 7, 2013-1- Project Federal Regulations and CMS Enterprise Life Cycle Gate Reviews -2- Purpose The ELC Reviews (gate reviews) will be used by the Centers for Medicare and Medicaid Services

More information

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration Knowledge Areas According to the PMBOK edition 5 Chapter 4 - Integration 4.1 - Develop Project Charter Process Project statement of work Expert Judgment Project charter Business case Facilitation techniques

More information

Speed to Value in Portfolio Management

Speed to Value in Portfolio Management Speed to Value in Portfolio Management Presentation Objectives Attendees will learn about: Creating an environment where IT becomes viewed as a strategy enabler and value driver for the organization Ensuring

More information

MODERNIZE PORTFOLIO & PROJECT MANAGEMENT. Erika K. Kemp, PMP MPPM Project Director

MODERNIZE PORTFOLIO & PROJECT MANAGEMENT. Erika K. Kemp, PMP MPPM Project Director MODERNIZE PORTFOLIO & PROJECT MANAGEMENT Erika K. Kemp, PMP MPPM Project Director 1 MPPM Business Case Vision of the Future State System capabilities Organizational capabilities Process design Decision

More information

I - PROJECT STATUS OVERVIEW

I - PROJECT STATUS OVERVIEW Project Sponsor: Denise Arnold Project Manager: Naru Nayak Status Report : 10/1/2015 12/31/2015 Project R&C Category: Pre-Charter Phase - 3 Initiation/Planning Phase To Be Assessed Start : July 01, 2015

More information

CNS Digital Transformation - Merging Two Legacy ERPs Into Single ERP Solution On SAP HANA

CNS Digital Transformation - Merging Two Legacy ERPs Into Single ERP Solution On SAP HANA CNS Digital Transformation - Merging Two Legacy ERPs Into Single ERP Solution On SAP HANA v Michael P. Muir Michael.Muir@cns.doe.gov Director, Business Applications UNCLASSIFIED This document has been

More information

Quality Management_200_Quality Product Review Procedure

Quality Management_200_Quality Product Review Procedure Quality Management_200_Quality Product Review Procedure Last Updated: 05/15/2017 Audience: CWDS Service Teams, PMO Frequency: As needed After reading this procedure, the audience will be able to understand

More information

Audit of Human Resources Planning

Audit of Human Resources Planning Health Canada Santé Canada Final Audit Report Audit of Human Resources Planning March 2012 Table of Contents Executive summary... i 1. Introduction... 1 1.1 Background... 1 1.2 Audit objective... 2 1.3

More information

7. Model based software architecture

7. Model based software architecture UNIT - III Model based software architectures: A Management perspective and technical perspective. Work Flows of the process: Software process workflows, Iteration workflows. Check Points of The process

More information

Project Planning and Management (PPM) V2.0. WBS Dictionary

Project Planning and Management (PPM) V2.0. WBS Dictionary Project Planning and Management (PPM) V2.0 WBS Dictionary Software as a Service (SaaS) Version 1.0 August 2014 1 Table of Contents PPM V2.0 Work Breakdown Structure (WBS) Dictionary 1 Project Type: Software

More information

Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017

Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Background Deloitte s Scope Conduct a review of the City s project planning, design, delivery and

More information

2015 Project Execution Training December 1, 2015

2015 Project Execution Training December 1, 2015 2015 Project Execution Training December 1, 2015 Project Management Office Overview Vision Statement The University of Lethbridge IT PMO Will: Enable Project Teams to be successful through providing a

More information

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide processlabs CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide CMMI-DEV V1.3 Process Areas Alphabetically by Process Area Acronym processlabs CAR - Causal Analysis and Resolution...

More information

The 10-Day Advanced Project Economics & Performance Management for Oil & Gas Professionals

The 10-Day Advanced Project Economics & Performance Management for Oil & Gas Professionals The 10-Day Advanced Project Economics & Performance Management for Oil & Gas Professionals 23 Jul - 03 Aug 2018, London The 10-Day Advanced Project Economics & Performance Management for Oil & Gas Professionals

More information

Programme Manager - Strategic Initiatives

Programme Manager - Strategic Initiatives Programme Manager - Strategic Initiatives Location: [Global] Category: Project Management *Position location to be determined by home country of successful candidate in a jurisdiction (country of US state)

More information

APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS

APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS Shared denotes whether a Contractor Resource may be responsible for that in addition to another identified. Contractor Required

More information

Services Description. Transformation and Plan Services. Business Transformation and Plan Services

Services Description. Transformation and Plan Services. Business Transformation and Plan Services Services Description Business ation and Plan Services Business ation and Plan Services SAP Business ation and Plan Services provides consulting and prototyping services to facilitate Licensee innovation

More information

Project Steering Committee. Executive Leadership Team Assets leadership team Superintendents team Business Analyst/PMO

Project Steering Committee. Executive Leadership Team Assets leadership team Superintendents team Business Analyst/PMO POSITION DESCRIPTION Position Title: Projects Manager Location: Newcastle Primary Purpose of the Position The primary purpose of this position is to provide a full project life cycle approach to the management

More information

Program managers (PMs)

Program managers (PMs) BEST PRACTICES Integrating Systems Engineering with Earned Value Management Program managers (PMs) expect their supplier s earned value management system (EVMS) to accurately report the program s integrated

More information

Appendix. Process Inputs and Outputs

Appendix. Process Inputs and Outputs 3601cA.fm Page 493 Wednesday, October 26, 2005 12:47 AM Appendix A Process and Throughout this book, PMP: Management Professional Study Guide, 3rd Edition, I ve discussed the inputs and outputs to the

More information

Work Plan and IV&V Methodology

Work Plan and IV&V Methodology Work Plan and IV&V Methodology Technology initiatives and programs should engage with an IV&V process at the project planning phase in order to receive an unbiased, impartial view into the project planning,

More information

REPORT 2014/014. Audit of the implementation of the Murex system in the Investment Management Division of the United Nations Joint Staff Pension Fund

REPORT 2014/014. Audit of the implementation of the Murex system in the Investment Management Division of the United Nations Joint Staff Pension Fund INTERNAL AUDIT DIVISION REPORT 2014/014 Audit of the implementation of the Murex system in the Investment Management Division of the United Nations Joint Staff Pension Fund Overall results relating to

More information

A Practical Approach to Business Intelligence Strategies

A Practical Approach to Business Intelligence Strategies A Practical Approach to Business Intelligence Strategies Creating Connections and Exploring Possibilities Zanné van Wyk University of Newcastle BI Maturity & Performance Stages BI Roadmap Maturity Phase

More information

Attachment B Project Specifications

Attachment B Project Specifications TABLE OF CONTENTS INTRODUCTION... 4 SOFTWARE... 4 PROJECT FACILITIES AND OFFICE EQUIPMENT... 5 PROJECT STAFFING... 6 IMPLEMENTATION CONSIDERATIONS... 6 5.1 Project Phases... 7 5.2 Project Stages... 7 5.3

More information

S&OP as a Profit- Focused Decision Engine October 19 th 2014 Alex Harbell

S&OP as a Profit- Focused Decision Engine October 19 th 2014 Alex Harbell S&OP as a Profit- Focused Decision Engine October 19 th 2014 Alex Harbell Abstract Following mergers companies are often challenged to integrate and harmonize disparate S&OP processes. Building a single

More information

Certified Outsourcing Professional (COP) Exam Study Guide

Certified Outsourcing Professional (COP) Exam Study Guide Certified Outsourcing Professional (COP) Exam Study Guide DEVELOPED BY THE INTERNATIONAL ASSOCIATION OF OUTSOURCING PROFESSIONALS (IAOP) PART OF THE COP PROGRAM 2011 The Certified Outsourcing Professional

More information

Risk Management in BPA / BPI Projects

Risk Management in BPA / BPI Projects Abstract Risk Management in BPA / BPI Projects Chandra Sekhar Ramaraju and Venugopal Juturu Before embarking on the business process assessment and improvement (BPA & BPI) projects that might lead to multiple

More information

Before Launching your Incentive Compensation Management (ICM) Solution:

Before Launching your Incentive Compensation Management (ICM) Solution: Incent Perform Grow Before Launching your Incentive Compensation Management (ICM) Solution: KEY STEPS TO PREPARING FOR ACTIVATION ? The ICM Solution is Selected Now What? Companies spend a significant

More information

FLORIDA DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL

FLORIDA DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL PAM STEWART Commissioner MIKE BLACKBURN Inspector General FLORIDA DEPARTMENT OF EDUCATION OFFICE OF INSPECTOR GENERAL MEMORANDUM To: From: Pam Stewart, Commissioner Mike Blackburn, Inspector General Date:

More information

Project Management Process Groups. PMP Study Group Based on the PMBOK Guide 4 th Edition

Project Management Process Groups. PMP Study Group Based on the PMBOK Guide 4 th Edition Project Management Process Groups PMP Study Group Based on the PMBOK Guide 4 th Edition Introduction PM Process Groups In order for a project to be successful, the project team must: Select appropriate

More information

The Importance of Internal Audit and the Role of Governance for Family Businesses in Transformational Stage. George Stoyanov, Grant Thornton

The Importance of Internal Audit and the Role of Governance for Family Businesses in Transformational Stage. George Stoyanov, Grant Thornton The Importance of Internal Audit and the Role of Governance for Family Businesses in Transformational Stage George Stoyanov, Grant Thornton Transformational Stages Role of Governance Role of Internal Audit

More information

DORNERWORKS QUALITY SYSTEM

DORNERWORKS QUALITY SYSTEM DORNERWORKS QUALITY SYSTEM ALIGNMENT WITH CMMI INTRODUCTION Since its beginning, DornerWorks has had quality as one of our main goals. We have delivered solutions for over a dozen aircraft, including several

More information

Motorist Modernization Phase I Citation Processing. January 11, 2018

Motorist Modernization Phase I Citation Processing. January 11, 2018 Motorist Modernization Phase I Citation Processing January 11, 2018 Motorist Modernization Timeline 2 LEGISLATIVE FUNDING PHASE I Funding Received Funding received of $9.8M for Fiscal Year 17/18. Funding

More information

ITBraindumps. Latest IT Braindumps study guide

ITBraindumps.   Latest IT Braindumps study guide ITBraindumps http://www.itbraindumps.com Latest IT Braindumps study guide Exam : PK0-004 Title : CompTIA Project+ Exam Vendor : CompTIA Version : DEMO Get Latest & Valid PK0-004 Exam's Question and Answers

More information

Service Strategy Quick Reference Guide

Service Strategy Quick Reference Guide Service Strategy Quick Reference Guide To enable service providers to think and act in a strategic manner to achieve strategic goals or objectives through the use of strategic assets Value Creation through

More information

7/26/2016 ARETE-ZOE, LLC 1

7/26/2016 ARETE-ZOE, LLC 1 Registered address: 1334 E Chandler Blvd 5 A-19, Phoenix 85048 Arizona, USA T: +1-480-409-0778 Skype: arete-zoe veronikav@arete-zoe.com Website SlideShare 7/26/2016 ARETE-ZOE, LLC 1 RISK MANAGEMENT PROCESS

More information

Project Management: Instructor Guide Module 4 PLAN IMPLEMENTATION

Project Management: Instructor Guide Module 4 PLAN IMPLEMENTATION 200 Project Management: Instructor Guide Module 4 PLAN IMPLEMENTATION Bridges Social Development Project Management Training Program www.canadabridges.com 10/09/2009 PROJECT MANAGEMENT TRAINING PROGRAM

More information

REPORT TO THE BOARD OF GOVERNORS

REPORT TO THE BOARD OF GOVERNORS REPORT TO THE BOARD OF GOVERNORS SUBJECT INTEGRATED RENEWAL PROGRAM FINANCE/HR/STUDENT MEETING DATE JUNE 14, 2018 APPROVED FOR SUBMISSION Forwarded to the Board of Governors on the Recommendation of the

More information

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Introduction 3 Updated date: 7/2/216 Version 1. How to Read an Activity Description Objective: Provides the

More information

NYSITS. Overview of Project Management

NYSITS. Overview of Project Management NYSITS Overview of Management SMART objectives SPECIFIC MEASURABLE ACHIEVABLE REALISTIC TIME-SPECIFIC Initiation WBS Network Diagram Gantt Chart Kick-off Meeting Introduction Objectives Planning Risks

More information

EX0-114_Wins_Exam. Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0

EX0-114_Wins_Exam.   Number: Passing Score: 800 Time Limit: 120 min File Version: 1.0 EX0-114_Wins_Exam Number: 000-000 Passing Score: 800 Time Limit: 120 min File Version: 1.0 http://www.gratisexam.com/ 20000 IT Service Management Foundation Bridge based on ISO/IEC Total Questions: 78

More information

USDA Shared Services Journey

USDA Shared Services Journey USDA Shared Services Journey USDA was named as an SAP Federal Financial Shared Services Provider in May 2014, able to offer financial system services within the federal government. This was in response

More information