The building contract a tool to minimise disputes and enhance productivity

Size: px
Start display at page:

Download "The building contract a tool to minimise disputes and enhance productivity"

Transcription

1 Page 1 of Pages The building contract a tool to minimise disputes and enhance productivity INTRODUCTION Most Standard Building Contracts include a number of clauses to deal with a variety of situations the employer and the contractor may encounter during the execution of a building project. Where a situation occurs that may cause delay and/or additional expense standard contracts generally include a procedure to follow including time bars to encourage the speedy resolution of such events. Not solving potential problems promptly often results in an acrimonious situation later in the life of a contract, usually with broken relationships, delayed projects and other consequential damages that could have been avoided if all parties worked together and followed simple, defined procedures POTENTIAL PROBLEMS THAT MAY BECOME DISPUTES There are many successful building and construction projects but also a not insignificant number where things go wrong including:- 1 Poor project definition 2 Inadequate exploration of appropriate design options 3 Poor final design not the optimum solution 4 Flawed procurement processes 5 Personality clashes and competence issues 6 Poor governance of the project 7 Delays on site 8 Cost overruns, payment delays Many of these issues have their origin in decision making early in the project life cycle:- 1 Has the need for the project been established in terms of business strategy, current and future technology, market conditions etc? 2 Is the location critical suitable greenfield or brown field sites? 3 Has the project been properly defined in terms of space requirements, appropriate materials, construction and operational skills > specification of services, utilities, finishes and maintenance and other operational criteria for its economic lifespan? 4 Is the use of new materials and/or novel construction techniques proposed? 5 What statutory requirements are applicable? 6 Do international or other quality standards apply? 7 Must particular performance dates be achieved? 8 How is the project financed? (not necessarily with all funding in the bank but available to suit project cash flow) 9 How is the project designed in house team, external consultants, combination of both? 10 How is the project executed traditional execution using an employer provided design (where the employer has control over the outcome) or s design + build type solution where the outcome to a large extent is determined by the contractor s experience and resources?

2 Page 2 of Pages 11 Hence - What forms of contract are appropriate? An experienced project manager, or team of project managers with different skills, may be the only person(s) to see a project through all its phases and be able to ensure that critical decisions are reviewed and made timeously by corporate management and/or by statutory and other authorities Where this has not been done the construction team may my have to resolve issues in a hurry on site. This is likely to be a compromise solution probably involving delays and likely to attract addition costs = crisis management! At this stage the employer may be in an uncomfortable situation vis-à-vis his customers and is now looking for explanations - if not someone to blame who can be made to pay for the late delivery? DISPUTE AVOIDANCE OPTIONS The employer organisation must be able to deal with projects in a professional manner 1 Has a project been hierarchy developed of persons with appropriate skills to make decisions without having to refer to a board meeting in two months time? 2 Where professional consultants are appointed be critical of their competence. It is not unusual that a well known firm is appointed but the executant with that firm may have limited experience and or competence As the employer - insist on a reports in a format that can easily be audited in terms of the original performance criteria and appropriate standards - and ensure that the consultant has adequate Professional Indemnity Insurance! 3 As the employer in consultation with the professional team ensure that sufficient time been allowed to explore alternatives to find the optimum solution for the project at hand? 4 Has sufficient time been allowed to realistically design and document a project? 5 Has sufficient time been allowed for the statutory and other approval processes? 6 Is the money available not necessarily the full amount on day one, but to suit the project cash flow? 7 Has a project administration system been developed to file and retrieve information? 8 Has quality management system appropriate for the project been designed? 9 Does the company have an appropriate Health and Safety policy and plan for the project? 10 Has a project review process been created to audit, monitor, and if necessary, make changes? 11 Who has the authority to implement such actions quickly? * In essence this is a risk management exercise in the employer organisation The project execution team would like to be reassured that the employer is part of the team and can be called upon to resolve potential issues before they become problems PROCUREMENT It is not unusual that employer organisations have a (series of) policies dealing with the acquisition of goods and services but, to quote from a CIDB document The Preferential Procurement Policy Framework (Act 5 of 2000) requires that building tenders are awarded in accordance with a system that is fair, equitable, transparent, competitive and cost effective. (SANS 294 Construction Procurement Processes, Methods and Procedures)

3 Page 3 of Pages Where in this definition is competence of the various contractors mentioned? 1 Have the tender documents been properly compiled to enable realistic pricing? 2 Can the complexity and the method of construction be gauged by the contractor + subcontractors? 3 Is there sufficient time to price a tender realistically? 4 Are specified materials / construction equipment / skills readily available? 5 From the contractor s experience what has been left out that may develop into a dispute later? (employer expecting 5 star finishes from a 2 star specification?) * The contractor must assess his risk in tendering and hence execution of the project based on the available information poor information results in unreliable pricing and becomes the employer s risk to proceed CONTRACT EXECUTION Assume the employer (and his agents) have followed the various procedures described to initiate the project, complied with the procurement processes and have decided to award the building tender:- The contractor 1 Has carefully read and understood the tender documents the Bill of Quantities, the drawings provided and any other documents to check: 2 Checked if there any contradictions between the various documents? 3 Checked if any items are hidden in the Preliminaries or other Bills that may vary the standard conditions of contract and other rights the contractor may have? 4 Has insisted that an original unaltered form of standard building contract is provided for signature by the employer + the contractor before the start of the works and a copy provided to the contractor? 5 Checked if securities must be provided between the parties? 6 Checked who is responsible for (specified) insurances provided before the start of the works? 7 Checked if applicable statutory approvals been obtained to allow the work to commence on the intended dates? 8 Checked if there are other reasons to prevent access to the site / execution of the works? 9 Agrees to provide the same/back to back contractual documentation to subcontractors relevant to their specialisation 10 Confirmed that all relevant documentation is available? 11 Confirmed that key responsibilities and relevant persons have been identified by both parties? Assuming these criteria are met construction can begin! If not then the contractor may have a claim for additional time before the project has started, this may be the employer s risk? THINGS THAT CAN and DO GO WRONG Delays 1 Insufficient information 2 Late information 3 Incorrect information 4 Non availability of specified products 5 Non compliance with statutory requirements

4 Page 4 of Pages 6 Changes initiated by the professional team 7 Changes initiated by the employer 8 Poor workmanship 9 Poor performance 10 Poor relationship with subcontractors 11 Interference by the employer Payment 1 Inadequate / late / incorrect information generally cause delays that cause additional expense 2 Any delays generally attract cost as additional preliminaries charges and/or material and labour charges 3 Late payments traditionally result in delayed payments to others in the project team who may be prevented from performing their tasks due to an inadequate cash flow MANAGEMENT OF DELAYS 1 Proper contract administration 2 Promptly and competently dealing with claims as they occur 3 Employer to involve a dispute avoidance board throughout the project MAINTENANCE AND OPERATIONS 1 The employer must be provided with all as built documentation, product warranties and operating manuals in an agreed format before occupation of the building 2 Where warranties extend beyond the final completion date (air conditioning, lifts, landscaping, etc) how are these dealt with? HOW DOES THE BUILDING CONTRACT ASSIST IN DISPUTE AVOIDANCE? All standard building and construction contracts include procedures in individual clauses to deal with items that may become a dispute if not resolved timeously including but not limited to 1. Provision of information to the contractor 2. Delays to the project for various reasons 3. Additional costs 4. Appointment of subcontractors 5. Performance by subcontractors 6. Performance by the principal contractor 7. Changes instructed by the employer 8. Changes for statutory compliance 9. Late or non payment by the employer 10. Late or non issue of payment certificates by the contract administrator (also completion certificates) 11. professional contract administration is a serious and time consuming responsibility!

5 Page 5 of Pages The contract administrator (the principal agent, the engineer, the project manager) must fulfill their duties described in the various standard contracts as well as coordinating the obligations and the rights of the contractor and the employer. Simplistically Either party must give notice of becoming aware of a potential problem (usually within a defined time period) The contract administrator must act on such information to hopefully resolve the issues raised Where an identified problem is not resolved generally a further notice is required before the contractor (and possibly the employer) can invoke the suspension or termination clauses Similarly the dispute resolution clauses may be invoked Following the procedures is critical to ensure a project is brought to conclusion within the agreed construction period 1. It is crucial that the contract administrator, as well as the parties to the contract promptly communicate in writing and keep records of relevant information (site photos, delivery notes, etc) to create an auditable information trail should events need to be proved in a dispute scenario 2. Keeping minutes of all meetings in an agreed format and the prompt issue of such minutes and the approval of minutes, or the noting of corrections are equally crucial should they be required as evidence later 3. The parties must resolve contractual claims as they occur whilst the facts pertaining to the scenario and persons involved may be contacted to find an appropriate solution. Leaving this to the end of the contract creates uncertainty, and will most likely become a dispute as either party may offer a myriad of excuses that he/she did not see / know / agree IN SHORT Keep accurate records in a format that can easily be accessed - Agree communication procedures and stick to them! Speedily deal with all notifications of any potential problem and find a solution by consensus Uwe Putlitz, CEO JBCC

ICES Core Cost Engineering Competencies

ICES Core Cost Engineering Competencies CM CORE 1 Cost Engineering Commercial Management Core Competency Cost Engineering Specialism COMPETENCIES AND ASSESSMENT Financial and commercial processes in civil engineering January 2015 Technical Member

More information

Estimating specialism core competencies

Estimating specialism core competencies CORE ESTIMATING COMPETENCIES 2015 The estimating competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off to a specific

More information

ICES Core Cost Engineering Competencies

ICES Core Cost Engineering Competencies COST ENGINEERING CORE COMPETENCIES 2018 The quantity surveying competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off

More information

Conception Design Construction Operation.

Conception Design Construction Operation. 4 Development Process and Procurement 4.1 The development process by which the project moves from the earliest ideas to the final completion of the facilities and their use can be considered as having

More information

Member level the optimum standard is given against each activity statement

Member level the optimum standard is given against each activity statement QUANTITY SURVEYING CORE COMPETENCIES 2018 The quantity surveying competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off

More information

SCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE

SCOPE OF WORK FOR PROFESSIONAL SERVICES: HET POSTHUYS ELECTRICAL UPGRADE ANNEXURE A T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 SCOPE OF WORK FOR

More information

Commercial Planning Core Competencies PLANNING CORE COMPETENCIES 2018

Commercial Planning Core Competencies PLANNING CORE COMPETENCIES 2018 PLANNING CORE COMPETENCIES 2018 The competencies are split into core and specialist competencies. OPTIMUM STANDARDS Each of the activities under the competencies must be signed-off to a specific standard,

More information

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee COAA EPCM CONTRACT PHILOSOPHY COAA EPCM Contract Committee 1. Introduction The COAA EPCM Contract Committee, consisting of owner, contractor and affiliate members, has developed a standard form EPCM Contract

More information

Chapter 2 Parties to the Contract

Chapter 2 Parties to the Contract Chapter 2 Parties to the Contract 2.1 Introduction Construction work may include building of a new structure, additions, alterations, expansion, replacement, dismantling, erection, commissioning, rehabilitation,

More information

ANNEXURE A SCOPE OF WORK FOR PROFESSIONAL SERVICES: RESTORATION OF NON PAREILLE BUILDINGS. Principal Agent and Professional Architectural Services

ANNEXURE A SCOPE OF WORK FOR PROFESSIONAL SERVICES: RESTORATION OF NON PAREILLE BUILDINGS. Principal Agent and Professional Architectural Services T: +27 21 462 4502 F: +27 21 462 4509 E: info@sahra.org.za South African Heritage Resources Agency - Head Office 111 Harrington Street Cape Town P.O. Box 4637 Cape Town 8001 ANNEXURE A SCOPE OF WORK FOR

More information

Maintenance for Building Services

Maintenance for Building Services A BSRIA Guide www.bsria.co.uk Maintenance for Building Services How to acquire maintenance services contracts By Jo Harris BG 3/2008 BG 3-2008 (Maintenance contracts) cover 6.p653 06/06/2008, 09:26 ACKNOWLEDGEMENTS

More information

How Construction Contracts Cause Litigation. By: Robert C. Epstein, Esq. 1

How Construction Contracts Cause Litigation. By: Robert C. Epstein, Esq. 1 How Construction Contracts Cause Litigation By: Robert C. Epstein, Esq. 1 We live in a litigious society, and construction contributes its fair share of disputes. Conflicts, disputes and claims seem to

More information

FIDIC Contracts. Training Course in English language. May, 25-26, Two days course on:

FIDIC Contracts. Training Course in English language. May, 25-26, Two days course on: FIDIC Contracts Training Course in English language May, 25-26, 2018 Two days course on: FIDIC Module 4 - FIDIC Contracts Management and Administration FIDIC 99 EDITIONS ESSENTIALS FOR WORKING IN INTERNATIONAL

More information

SAFETY, HEALTH & WELFARE AT WORK (CONSTRUCTION) REGULATIONS Briefing Note 1 for Clients, Designers and Project Supervisor Design Process

SAFETY, HEALTH & WELFARE AT WORK (CONSTRUCTION) REGULATIONS Briefing Note 1 for Clients, Designers and Project Supervisor Design Process SAFETY, HEALTH & WELFARE AT WORK (CONSTRUCTION) REGULATIONS 2006 1. Introduction Briefing Note 1 for Clients, Designers and Project Supervisor Design Process ISSUED NOVEMBER 2006 BY ACEI, EI, RIAI and

More information

From Uncertainty to Certainty; How Clients can Improve their Experience of the Construction Process

From Uncertainty to Certainty; How Clients can Improve their Experience of the Construction Process From Uncertainty to Certainty; How Clients can Improve their Experience of the Construction Process www.provelio.com Summary This paper is an independent project manager s critique of two projects. One

More information

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell:

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell: CONSTRUCTION MANAGEMENT By GREEN PLANET SERVICES Lesley Padayachee Cell: 084 525 4720 Lesley.gpes@gmail.com 5 th FEBRUARY 2013 CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process

More information

Federation of Master Builders (FMB)

Federation of Master Builders (FMB) FOR INTERNAL USE ONLY Federation of Master Builders (FMB) Our members are expected to adhere to the FMB Code of Practice, a copy of which is attached. We can, if appropriate, refer the Member s conduct

More information

COMMUNITY LIVING BRANT POLICY AND PROCEDURE MANUAL

COMMUNITY LIVING BRANT POLICY AND PROCEDURE MANUAL PAGE 1 of 7 FILE UNDER SECTION: 4 EFFECTIVE DATE: January 2012 REVISION DATE: APPROVAL DATE: January 2012 POLICY: This Policy includes the requirements that are set out in the Broader Public Sector (BPS)

More information

FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20

FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20 FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20 PATRIZIA PALMITESSA-SAVRIC BSc Arch Eng MArch Arch.BW RIBA MAAB FCIArb FAArb FBIArb Head Contracts & Dispute Resolution GINDER PALMITESSA PTY LTD T: +267

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical

Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical Learn best practices with regard to contract administration and management; Identify the various phases of contract administration; Gain practical experience in how to organize the contract administration

More information

Connoisseur Solutions Project Procurement Management

Connoisseur Solutions Project Procurement Management Project Procurement Management Project Procurement Management Processes necessary to purchase or acquire products, services or results needed from outside the project team. Procurement Management Processes

More information

Inform Practice Note #7

Inform Practice Note #7 Inform Practice Note #7 May 2007 (Version 1 - May 2007) Subcontracting Arrangements cidb s Inform Practice notes provide guidance and clarity in achieving client objectives in construction procurement

More information

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1.

PROBUILD GUIDE SUBCONTRACTOR QUALITY MANAGEMENT. Section Two Project Specific Quality Management Plans. Version No 1. PROBUILD SUBCONTRACTOR QUALITY MANAGEMENT GUIDE Section Two Project Specific Quality Management Plans Version No 1. PREFACE This document has been developed to assist subcontractors to meet Probuild s

More information

TECHNICAL MEMBER COMPETENCIES QUANTITY SURVEYING

TECHNICAL MEMBER COMPETENCIES QUANTITY SURVEYING Formulation of a cost estimate through to submission of a tender document to a client, including co-ordination with planning, procurement, surveying and management. To exhibit knowledge of all civil engineering

More information

- Details of the item to be procured and whether it is for works, services or goods;

- Details of the item to be procured and whether it is for works, services or goods; Procurement Policy 1. INTRODUCTION The policy is designed to ensure we comply with the relevant legislation, regulations and guidance which regulate our procurement activities. We will ensure our procurement

More information

CIPS POSITIONS ON PRACTICE PURCHASING & SUPPLY MANAGEMENT: INCENTIVISATION

CIPS POSITIONS ON PRACTICE PURCHASING & SUPPLY MANAGEMENT: INCENTIVISATION CIPS POSITIONS ON PRACTICE PURCHASING & SUPPLY MANAGEMENT: INCENTIVISATION INTRODUCTION The CIPS' practice documents are written as a statement in time. They are a collection of views on good practice

More information

PROCUREMENT CODE OF CONDUCT

PROCUREMENT CODE OF CONDUCT PROCUREMENT CODE OF CONDUCT 1 PROCUREMENT CODE OF CONDUCT Sabah Electricity Sdn Bhd (SESB) believes that all supplier/contractor relationships should be based on principles of good governance such as integrity,

More information

Procurement Policy. Prepared By. Nick Ronan, Development Director. Date of Last Review November Date of Current Review March 2016

Procurement Policy. Prepared By. Nick Ronan, Development Director. Date of Last Review November Date of Current Review March 2016 Procurement Policy Prepared By Nick Ronan, Development Director Date of Last Review November 2012 Date of Current Review March 2016 Date of Next Review March 2019 Reviewed By Board 1. INTRODUCTION 1.1

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,

More information

Retail Contracts Scheme Benchmarks

Retail Contracts Scheme Benchmarks Retail Contracts Scheme s 1 - Clear supply commencement 1.1. The gas supply arrangements must state when the supply of gas is to commence, either by stating a specific commencement date or the circumstances

More information

GREATER SHEPPARTON CITY COUNCIL and GOULBURN VALLEY REGIONAL COLLABORATIVE ALLIANCE

GREATER SHEPPARTON CITY COUNCIL and GOULBURN VALLEY REGIONAL COLLABORATIVE ALLIANCE GREATER SHEPPARTON CITY COUNCIL and GOULBURN VALLEY REGIONAL COLLABORATIVE ALLIANCE Policy Number 13.POL1 Version 3.0 Adopted February 2013 Last Reviewed July 2016 Business Unit: Responsible Officer: Approved

More information

NAPRANUM ABORIGINAL SHIRE COUNCIL. POLICY STATEMENT. Procurement Policy. Authority in respect of this Policy is hereby delegated to CEO

NAPRANUM ABORIGINAL SHIRE COUNCIL. POLICY STATEMENT. Procurement Policy. Authority in respect of this Policy is hereby delegated to CEO NAPRANUM ABORIGINAL SHIRE COUNCIL POLICY STATEMENT Procurement Policy AUTHORITY: DELEGATION: NAPRANUM ABORIGINAL SHIRE COUNCIL. Authority in respect of this Policy is hereby delegated to CEO PURPOSE This

More information

AUSTRALIAN ETHICAL GOVERNANCE FRAMEWORK. Version 3.0

AUSTRALIAN ETHICAL GOVERNANCE FRAMEWORK. Version 3.0 AUSTRALIAN ETHICAL GOVERNANCE FRAMEWORK Document Owner Document Author Approver Chief Risk Officer Chief Risk Officer Board of AES Version 3.0 Date Approved 21 November 2018 AES Next Review Date 21 November

More information

THE ROLE OF A BRIDGE INSPECTOR

THE ROLE OF A BRIDGE INSPECTOR C.1 The Role of a Bridge Inspector - General The Contractor is responsible for constructing the bridge in full accordance with the Plans and Specifications. The Bridge Inspector s role is that of ensuring

More information

Regulations Supervisory Board

Regulations Supervisory Board Regulations Supervisory Board November 1, 2017 Regulations Supervisory Board BE Semiconductor Industries N.V. Purpose These Regulations have been established by the Supervisory Board on November 1, 2017

More information

Audit and Risk Management Committee Charter

Audit and Risk Management Committee Charter Audit and Risk Management Committee Charter Qube Holdings Limited ACN 149 723 053 Audit and Risk Management Committee Charter (revised June 2018 ) Page 1 of 8 1. Introduction 1.1 Objectives The objectives

More information

PROCUREMENT STRATEGY &

PROCUREMENT STRATEGY & THENUE HOUSING ASSOCIATION PROCUREMENT STRATEGY 2016-17 & 2017-18 1. BACKGROUND Under the terms of the Procurement Reform (Scotland) Act 2014 a contracting authority which is likely to spend in excess

More information

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification Structure 4 Centre requirements 6 Support for candidates 6 Links to National Standards / NOS

More information

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification

Level 7 NVQ Diploma in Construction Senior Management. Qualification Specification Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification Structure 4 Centre requirements 6 Support for candidates 6 Links to National Standards / NOS

More information

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE THE UNIVERSITY of EDINBURGH Estates & Buildings ESTATE DEVELOPMENT ISSUE/REVISION JK 1 LAST MODIFIED 12 October 2011 DATE PRINTED RIBA stages JK JK 1 START OF MAIN CONTRACT WORKS 1. DEFINITION The Main

More information

Level 7 NVQ Diploma in Construction Site Management. Qualification Specification

Level 7 NVQ Diploma in Construction Site Management. Qualification Specification Level 7 NVQ Diploma in Construction Site Management Qualification Specification ProQual 2016 Contents Page Introduction 3 Qualification profile 3 Qualification Structure 4 Centre requirements 6 Support

More information

PROCUREMENT POLICY. Policy Owner. Procurement Advisor Department

PROCUREMENT POLICY. Policy Owner. Procurement Advisor Department PROCUREMENT POLICY Policy Owner Procurement Advisor Department Governance & Corporate Performance Creation Date 23/04/2012 Revision Date 19/06/2017 TABLE OF CONTENTS PURPOSE... 1 SCOPE... 1 DEFINITIONS...

More information

EPICOR, INCORPORATED QUALITY ASSURANCE MANUAL

EPICOR, INCORPORATED QUALITY ASSURANCE MANUAL EPICOR, INCORPORATED QUALITY ASSURANCE MANUAL Revision: 6 Date 05/18/09 EPICOR, INCORPORATED 1414 E. Linden Avenue P.O. Box 1608 Linden, NJ. 07036-0006 Tel. 1-908-925-0800 Fax 1-908-925-7795 Table of Contents:

More information

Code of Conduct for Members of The Federation of Master Builders Limited

Code of Conduct for Members of The Federation of Master Builders Limited Code of Conduct for Members of The Federation of Master Builders Limited Code of Conduct for Members Members of the Federation of Master Builders (FMB) agree to comply with the requirements of the Code

More information

How do FIDIC contracts work

How do FIDIC contracts work How do FIDIC contracts work Zoltán Záhonyi (MSc civil engineer, postgraduate in law) FIDIC Contracts Committee member FIDIC Accredited Trainer Z&Partners Consulting Engineers Ltd. Leading Partner, managing

More information

ECI: Two-Stage Contracts

ECI: Two-Stage Contracts ECI: Two-Stage Contracts Client and Contractor Considerations Michael Creedon Special Counsel ECI in Infrastructure and Major Projects Summit 2010 Sydney, 17 June 2010 Sessions Outline Introduction /

More information

Public Procurement Challenges - Modern Slavery Act March 2018

Public Procurement Challenges - Modern Slavery Act March 2018 Challenges - Modern Slavery Act 2015 15 March 2018 Introduction High volume of procurement challenges in UK o 11% of cases in Technology & Construction Court in London are procurement challenges. o Numerous

More information

SENIOR PROJECT MANAGER

SENIOR PROJECT MANAGER POSITION Reports To; Direct Reports; Key Relationships; SENIOR PROJECT MANAGER Regional Construction Manager Site Managers, other staff allocated to assigned projects Project Directors, Clients, Consultants,

More information

CONTROL OF WORK 1.02 AUTHORITY AND DUTIES OF THE ENGINEER S AUTHORIZED REPRESENTATIVE

CONTROL OF WORK 1.02 AUTHORITY AND DUTIES OF THE ENGINEER S AUTHORIZED REPRESENTATIVE 1.01 AUTHORITY OF THE ENGINEER CONTROL OF WORK A. The work included in the contract is to be done to the complete satisfaction of the Engineer, and the decision of the Engineer as to the true construction

More information

CONTENTS. Quality Policy Statement. Managing Invitations to Tender. Rev 9

CONTENTS. Quality Policy Statement. Managing Invitations to Tender. Rev 9 QUALITY PLAN CONTENTS Section 1 Section 2 Section 3 Section 4 Section 5 Quality Policy Statement Quality System Managing Invitations to Tender Design and Drawings Contract Management Section 1 Quality

More information

ROLES AND RESPONSIBILITIES

ROLES AND RESPONSIBILITIES Audio Sessions Session 2 ROLES AND RESPONSIBILITIES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org

More information

Readiness for service. Gate. Great state. Great opportunity.

Readiness for service. Gate. Great state. Great opportunity. Readiness for service Gate 4 Great state. Great opportunity. The State of Queensland (Queensland Treasury and Trade) 2013. First published by the Queensland Government, Department of Infrastructure and

More information

Blue List. Green List. Civil Engineering Commercial Training Courses

Blue List. Green List. Civil Engineering Commercial Training Courses Blue List Green List Civil Engineering Commercial Training Courses From SURCO, the information business of the Chartered Institution of CIVIL ENGINEERING SURVEYORS SURCO Limited Chartered Institution of

More information

Building and renovating

Building and renovating Building and renovating Last updated: 20 November 2017 Summary This factsheet contains information about: the laws in Victoria on building and renovating the Victorian Building Authority owner-builders

More information

Application of FIDIC CC for EU- Funded Projects in Bulgaria

Application of FIDIC CC for EU- Funded Projects in Bulgaria Application of FIDIC CC for EU- Funded Projects in Bulgaria Assen Antov Transport Engineer Advisor to the Minister of Regional Development and Public Works EFCA Annual Conference 2016, 02 04 June 2016,

More information

IIBAT- Supplier Payment Policy Dated :Tuesday, 01 January 2013

IIBAT- Supplier Payment Policy Dated :Tuesday, 01 January 2013 IIBAT- Supplier Payment Policy Dated :Tuesday, 01 January 2013 Please Note:- This policy should be read along with IIBAT- Supplier Ethics Policy dated 11.01.2012. Why IIBAT should pay its invoices on time?

More information

The Construction (Design and Management) Regulations 2015 sets out the duties of Designers and Contractors.

The Construction (Design and Management) Regulations 2015 sets out the duties of Designers and Contractors. TEMPORARY WORKS AND DESIGN PROCEDURE. Legislation The Working at Height Regulations 2005, require Strength and Stability calculations for any arrangement of scaffolding that is not covered by a recognised

More information

CONSTRUCTION MANAGER

CONSTRUCTION MANAGER The South African Council for the Project and Construction Management Professions CONSTRUCTION MANAGER IDENTIFICATION OF WORK AND SCOPE OF SERVICES FOR CONSTRUCTION MANAGERS REGISTERED IN TERMS OF THE

More information

Complaints and Grievance Policy (SRM-PLC-003 Rev 0)

Complaints and Grievance Policy (SRM-PLC-003 Rev 0) Complaints and Grievance Policy (SRM-PLC-003 Rev 0) Page 1 of 7 Table of Contents Document Control 3 1. Purpose 4 2. Scope 4 3. References 4 4. Definition 4 5. Introduction 4 6. Policy 5 7. Internal Procedure

More information

FORM OF APPOINTMENT AS CONSULTANT (CDM CO-ORDINATOR) (FOAC

FORM OF APPOINTMENT AS CONSULTANT (CDM CO-ORDINATOR) (FOAC Form of Appointment Shaping and sharing best practice in construction health and safety risk management FORM OF APPOINTMENT AS CONSULTANT (CDM CO-ORDINATOR) (FOAC 2011) Under the Construction (Design and

More information

Educational Use Only S A M P L E S A M P L E

Educational Use Only S A M P L E S A M P L E CONSENSUSDOCS 240 STANDARD FORM OF AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER This document was developed through a collaborative effort of entities representing a wide cross-section of the construction

More information

COMMERCIAL MANAGEMENT COMPETENCIES Estimating

COMMERCIAL MANAGEMENT COMPETENCIES Estimating Formulation of a cost estimate through to submission of a tender document to a client, including co-ordination with planning, procurement, surveying and management. To exhibit knowledge of all civil engineering

More information

CONTRACTOR PERFORMANCE EVALUATION SYSTEM

CONTRACTOR PERFORMANCE EVALUATION SYSTEM Introduction Request for Statements of Qualifications and Proposals ( RFQ/RFP ) C18-23 CONTRACTOR PERFORMANCE EVALUATION SYSTEM The evaluation is prepared by the Project Manager approved by a Senior Director

More information

CONSTRUCTION PROCUREMENT

CONSTRUCTION PROCUREMENT CONSTRUCTION PROCUREMENT [reflections on processes and lessons from the provincial IDMS] Gysbert Cronje 072 500 2257 Grysbert.Cronje@treasury.gov.za klcronje@gmail.com 8 October 2014 Locating Construction

More information

NZS 3916:2013. Conditions of contract for building and civil engineering Design and construct NZS 3916:2013. New Zealand Standard

NZS 3916:2013. Conditions of contract for building and civil engineering Design and construct NZS 3916:2013. New Zealand Standard New Zealand Standard Conditions of contract for building and civil engineering Design and construct Superseding (in part) NZS 3910:2003 NZS 3916:2013 COMMITTEE REPRESENTATION This Standard was prepared

More information

Course List 2008 Civil Engineering Commercial Training

Course List 2008 Civil Engineering Commercial Training Course List 2008 Civil Engineering Commercial Training From SURCO, the trading company of the Institution of CIVIL ENGINEERING SURVEYORS SURCO Limited Institution of CIVIL ENGINEERING SURVEYORS Dominion

More information

POLICY DOCUMENT. Contracts Management Policy (Version 3.0) BM>SMC>Board

POLICY DOCUMENT. Contracts Management Policy (Version 3.0) BM>SMC>Board POLICY DOCUMENT Contracts Management Policy 2018 (Version 3.0) BM>SMC>Board Policy Review Schedule Date first Approved: Last Approved by the Board: January 2017 Date of Next Review: January 2018 Policy

More information

ARTICLE I Scope and Objective. ARTICLE II Principles of Co-operation

ARTICLE I Scope and Objective. ARTICLE II Principles of Co-operation AGREEMENT BETWEEN THE GOVERNMENT OF THE REPUBLIC OF FINLAND AND THE GOVERNMENT OF THE FEDERAL DEMOCMTIC REPUBLIC OF ETHIOPIA ON THE CO-OPEMTION IN TECHNICAL SUPPORT FOR ENHANCING EQUITYAND INCLUSION IN

More information

FIDIC Workshops. Amman, Jordan January :00 am 05:00 pm. Engineers Training Center is a FIDIC Accredited Training Supplier

FIDIC Workshops. Amman, Jordan January :00 am 05:00 pm. Engineers Training Center is a FIDIC Accredited Training Supplier FIDIC Workshops Amman, Jordan 26-29 January 2014 09:00 am 05:00 pm Engineers Training Center is a FIDIC Accredited Training Supplier About these workshops These special two-day events have been designed

More information

Unit 3: Traditional Project Delivery Using IT Applications

Unit 3: Traditional Project Delivery Using IT Applications Unit 3: Traditional Project Delivery Using IT Applications 3.1 Construction Project Process Flow i. In a typical construction project, the major key to its success hinges on how well the project process

More information

The Heath Family (NW) Multi Academy Trust Sickness Absence Policy. Date amended: 11th October Date reviewed (policy in force from):

The Heath Family (NW) Multi Academy Trust Sickness Absence Policy. Date amended: 11th October Date reviewed (policy in force from): Date completed: 1 st September 2015 Date amended: 11th October 2018 Date reviewed (policy in force from): 15 th November 2018 Custodian title & e-mail address Craig Parkinson, Chief Operating Officer,

More information

Design Team Procedures Practice Note 1, February DESIGN TEAM PROCEDURES PRACTICE NOTE 1 (Revision 2)

Design Team Procedures Practice Note 1, February DESIGN TEAM PROCEDURES PRACTICE NOTE 1 (Revision 2) DESIGN TEAM PROCEDURES PRACTICE NOTE 1 (Revision 2) CHANGES TO STAGE 2b, STAGE 3 & STAGE 4 ARISING FROM AMENDMENTS TO THE PUBLIC WORKS CONTRACTS 1. Introduction 1.1 Changes to Public Works Contracts (a)

More information

City of Virginia Beach Consultant Performance Evaluation. Section I General Project Information Must be completed in its entirety.

City of Virginia Beach Consultant Performance Evaluation. Section I General Project Information Must be completed in its entirety. City of Virginia Beach Consultant Performance Evaluation Section I General Project Information Must be completed in its entirety. Name of Firm: Name of Prime: Prime Phone: Name of Project Manager: Project

More information

Circular No. 10/2013/TT-BXD of July 25, 2013, on construction quality management THE MINISTRY OF CONSTRUCTION

Circular No. 10/2013/TT-BXD of July 25, 2013, on construction quality management THE MINISTRY OF CONSTRUCTION THE MINISTRY OF CONSTRUCTION Circular No. 10/2013/TT-BXD of July 25, 2013, on construction quality management Pursuant to the Government s Decree No. 63/2012/ND-CP of August 31, 2012, defining the functions,

More information

FURTHER QUALIFICATION FOR ENTREPRENEURS 2012

FURTHER QUALIFICATION FOR ENTREPRENEURS 2012 Qualification Requirements for competence-based qualification FURTHER QUALIFICATION FOR ENTREPRENEURS 2012 Regulation 53/011/2012 Publications 2015:1 Finnish National Board of Education and authors Publications

More information

Procurement. Equalities in Procurement Policy. Policy Review Period/Expiry. November 2014

Procurement. Equalities in Procurement Policy. Policy Review Period/Expiry. November 2014 Procurement Equalities in Procurement Policy Policy Manager Andy Hay Policy Group Procurement Policy Established November 2013 Policy Review Period/Expiry November 2014 Last Updated November 2013 Aims

More information

RYDE TOWN COUNCIL QUOTATION DOCUMENTATION TOWN MAP AND EVENTS POSTER

RYDE TOWN COUNCIL QUOTATION DOCUMENTATION TOWN MAP AND EVENTS POSTER RYDE TOWN COUNCIL QUOTATION DOCUMENTATION TOWN MAP AND EVENTS POSTER November 2017 Ryde Town Council Town Map and Events Quotation Documentation November 2017 Page 1 RYDE TOWN COUNCIL TOWN MAP AND EVENTS

More information

Casework Technical Support (Social Welfare - Project Management)

Casework Technical Support (Social Welfare - Project Management) Casework Technical Support (Social Welfare - Project Management) Request for Tenders for Services to MABS NATIONAL DEVELOPMENT The latest date for receipt of tenders is 09 June 2017 Commercial House Westend

More information

Level 6 NVQ Diploma in Construction Site Management (Construction)

Level 6 NVQ Diploma in Construction Site Management (Construction) Level 6 NVQ Diploma in Construction Site Management (Construction) Qualification Specification ProQual 2017 Contents Page Introduction 3 Qualification profile 3 Qualification structure 4 Centre requirements

More information

1 July Guideline for Municipal Competency Levels: Head of Supply Chain and Supply Chain Senior Managers

1 July Guideline for Municipal Competency Levels: Head of Supply Chain and Supply Chain Senior Managers 1 July 2007 Guideline for Municipal Competency Levels: Head of Supply Chain and Supply Chain Senior Managers Municipal Regulations on Minimum Competency Levels issued in terms of the Local Government:

More information

Bosch Car Service Consumer Code of Practice. Your guide to the standards and practices of the Bosch Car Service network

Bosch Car Service Consumer Code of Practice. Your guide to the standards and practices of the Bosch Car Service network Bosch Car Service Consumer Code of Practice Your guide to the standards and practices of the Bosch Car Service network Contents Welcome to Bosch Car Service 4 Our commitment to 100% happy customers 5 What

More information

Quality, Health Safety & Environment Code: 2013

Quality, Health Safety & Environment Code: 2013 Price: AUD 35 Quality, Health Safety & Environment Code Quality, Health Safety & Environment Code: 2013 Published by: TQCS International Pty Ltd Head Office: 117A Tapleys Hill Road HENDON SA 5014 AUSTRALIA

More information

CIPS Exam Report for Learner Community:

CIPS Exam Report for Learner Community: CIPS Exam Report for Learner Community: Qualification: Diploma in Procurement and Supply Unit: D2: Business Needs in Procurement and Supply Exam series: November 2016 Question 1 Learning Outcome 1 Q1(a)

More information

MG ALBA PROCUREMENT POLICY AND SCHEME OF TENDERING

MG ALBA PROCUREMENT POLICY AND SCHEME OF TENDERING MG ALBA PROCUREMENT POLICY AND SCHEME OF TENDERING 1 PROCUREMENT POLICY 1 Purpose and Compliance 1.1 The purpose of this Procurement Policy and Scheme of Tendering is to set clear rules for the procurement

More information

The Hashemite Kingdom of Jordan Jordan Institution for Standards & Metrology. Jordanian Quality Mark

The Hashemite Kingdom of Jordan Jordan Institution for Standards & Metrology. Jordanian Quality Mark The Hashemite Kingdom of Jordan Jordan Institution for Standards & Metrology Jordanian Quality Mark Amman in February, 1997 1 Abstract Article (18) of the Law of Standards & Metrology; law no. (15) for

More information

CORPORATE QUALITY MANUAL

CORPORATE QUALITY MANUAL Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of the ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance

More information

SUB-CONTRACTING Charges Supply Chain Fees and POLICY

SUB-CONTRACTING Charges Supply Chain Fees and POLICY SUB-CONTRACTING Charges Supply Chain Fees and POLICY POLICY VERSION NUMBER 1 MEMBER OF STAFF RESPONSIBLE FOR POLICY Head of Apprenticeships & Employer Engagement RECORD OF REVISIONS TO POLICY DATE DETAILS

More information

AWE LIMITED ACN

AWE LIMITED ACN AWE LIMITED ACN 077 897 440 AUDIT AND GOVERNANCE COMMITTEE CHARTER Page No. 1. Introduction 2 2. Objectives of the Committee 2 3. Authority of the Committee 3 4. Committee Responsibilities 3 5. Committee

More information

EYNSFORD PARISH COUNCIL

EYNSFORD PARISH COUNCIL EYNSFORD PARISH COUNCIL FINANCIAL REGULATIONS These Financial Regulations were adopted by the Council at its Meeting held on 20 September 2007, last amended on 20 th July 2017. 1. GENERAL 1.1 These financial

More information

Chapter 8 Project Monitoring and Control It s important to have a schedule, but it s more important to use it

Chapter 8 Project Monitoring and Control It s important to have a schedule, but it s more important to use it Chapter 8 Project Monitoring and Control It s important to have a schedule, but it s more important to use it Header1 Project control can be reduced to two basic components: Monitoring and control Construction

More information

TasNetworks Policy. Procurement Policy. Version Number 1 June Overview of this Policy. Tasmanian Networks Pty Ltd (ACN )

TasNetworks Policy. Procurement Policy. Version Number 1 June Overview of this Policy. Tasmanian Networks Pty Ltd (ACN ) TasNetworks Policy Procurement Policy Version Number 1 June 2014 Overview of this Policy The purpose of this policy is to establish TasNetworks policy position in relation to procurement of goods and services

More information

COSCSMO15 SQA Unit Code H99L 04 Control projects in construction management

COSCSMO15 SQA Unit Code H99L 04 Control projects in construction management Overview This unit is about controlling projects. You will identify quality standards and pass them to the project team. You will set up systems for recording the quality of work against these standards,

More information

Quality Assurance Policy and Procedures

Quality Assurance Policy and Procedures 650 Montana Ave, Suite A Las Cruces, NM 88001 (575) 522-0430 www.rmgovernmentservices.com Quality Assurance Policy and Procedures PURPOSE. The purpose of this policy is to outline the quality assurance

More information

1913 Lausanne, Switzerland

1913 Lausanne, Switzerland FIDIC What is FIDIC? An international federation of consulting engineers, founded in 1913 with its headquarters located in Lausanne, Switzerland, whose objective is to promote the common interests of the

More information

CDM 2015 Regulations Frequently Asked Questions (FAQ s) (Last updated January 2016)

CDM 2015 Regulations Frequently Asked Questions (FAQ s) (Last updated January 2016) Document title ICE Health & Safety Expert Panel: CDM 2015 Regulations Frequently Asked Questions (FAQ s) (Last updated January 2016) Introduction The following questions and answers have been put together

More information

TORONTO MUNICIPAL CODE CHAPTER 67, FAIR WAGE SCHEDULE A, FAIR WAGE POLICY SCHEDULE A FAIR WAGE POLICY

TORONTO MUNICIPAL CODE CHAPTER 67, FAIR WAGE SCHEDULE A, FAIR WAGE POLICY SCHEDULE A FAIR WAGE POLICY SCHEDULE A FAIR WAGE POLICY 67-A1. Definitions. 67-A2. City of Toronto Council references. 67-A3. Purpose and history of Fair Wage Policy. 67-A4. Intent of Fair Wage Policy. 67-A5. Application. 67-A6.

More information

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015

Code of Practice. for Inspecting and Certifying Buildings and Works. Building Control Regulations 1997 to 2015 for Inspecting and Certifying Buildings and Works Building Control Regulations 1997 to 2015 September, 2016 Table of Contents 1. Introduction 1 1.1 Status and Purpose of Code 1 1.2 Overview of Code 1

More information

Annual Compliance Statement 2017 and Board of Directors / Governing Body and Corporate Governance Requirements

Annual Compliance Statement 2017 and Board of Directors / Governing Body and Corporate Governance Requirements Health Service Executive Annual Compliance Statement 2017 and Board of Directors / Governing Body and Corporate Governance Requirements Section 39 Providers Name of Provider: XXX March 2018 1 Contents

More information

Code of Conduct (COCON) Chapter 4. Specific guidance on individual conduct rules

Code of Conduct (COCON) Chapter 4. Specific guidance on individual conduct rules Code of Conduct (COCON) Chapter Specific guidance on .2 Specific guidance on senior manager conduct rules.2.1 SC1: You must take reasonable steps to ensure that the business of the firm for which you are

More information