Alignment of CPM Scheduling and Short Interval Planning
|
|
- Austen O’Brien’
- 6 years ago
- Views:
Transcription
1 Alignment of CPM Scheduling and Short Interval Planning Scott Kelly, Walt Disney Imagineering Jeff Betts, Whiting-Turner Contracting Co. Don Rote, Building Point Pacific Steven Solloway, Whiting-Turner Contracting Co. OCTOBER 18, 2017 C A P T U R E A N D L E V E R A G E T H E L E A N A D V A N T A G E
2 Evolution of Planning Over a Career Elementary School Modernization- 2 Week Look Ahead 02/04/03 Mobilization Dur Start complete Move on Temp Const Office Trailers Temp Const Office - Furniture Temp Const Office - Equipment Temp Const Office - Phone Temp Const Office - Power Temp Const Office - DSL Fencing at Bld. C & Cov'd Walk Fencing at Onsite Laydown Area Subcontractor Safety Orientation / Planning Meeting Building C Phase 1 Safe / Disconnect Elec, Gas, HVAC, Plumbing, Alarm Electrical Demo Plumbing Demo & Cut-N-Cap HVAC Demo & Cut-N-Cap Phase 1 Soft Demo Phase 1 Hard Demo Layout Mech Roof Op.s to identify dimensions for ordering of pre-fab curb Pending Response to RFI Elec/HVAC/Plumbing/Framer Coord Mt Electrical Rough HVAC Rough Phase 3 Work Utility Markout for New HC Ramp Barricade Work Area at New HC Ramp Demo for New Ramp Layout & Ecavate Footings New Ramp Footing Templates Footing Reinforcing 2
3 Planning Successes and Lessons Learned Community College Theater and Art Center Four-building summer sprint ($8M) CPM required by Specifications (+) Pull planning new but rapidly embraced (+) Daily coordination accomplished by pull planning Five rows of planning boards (-) Difficulty developing TIA without CPM 3
4 Planning Successes and Lessons Learned Power Plant Multi Year Risk Project ($BBs) (+)Required robust Critical & Near Critical Path Analyses (+) Evaluation of Required Schedule Contingencies (+) Establishing In Field Need Dates for Long Lead Equipment (+) Resource analysis of critical craft labor (-) Limited insight into near term discrete activities and / or constraints (-) Limited communication & buy-in of near term plans & activities 4
5 Planning Successes and Lessons Learned Last Planner System Field-use look-ahead Simple spreadsheet The REAL schedule CPM Schedule Office use contractual tool CPM software The billing schedule 5
6 6
7 Important Questions and How to Answer Them What is the longest path to operation of the Gamma Ray? What constraints are there to getting the plasma vault dried in by net Friday? What is the late date to order the cyborg s holoprojector? What is the turnover date of Lieutenant Raffi s transport shuttle landing pad? What day will humanoid robot s chest plate be welded to his rib supports? Will we delay completion of the Space Sasquatch s village if we only mobilize one rope bridge crew? How many crews will be working in the Little Green Men s palace on second shift this weekend? Are there any impacts to the pour date of the Warlocks s hut foundation if we need to remove and replace the tree branch elements? 7
8 Important Questions and How to Answer Them What is the longest path to operation of the Gamma Ray? What constraints are there to getting the plasma vault dried in by net Friday? What is the late date to order the cyborg s holoprojector? What is the turnover date of Lieutenant Raffi s transport shuttle landing pad? What day will humanoid robot s chest plate be welded to his rib supports? Will we delay completion of the Space Sasquatch s village if we only mobilize one rope bridge crew? How many crews will be working in the Little Green Men s palace on second shift this weekend? Are there any impacts to the pour date of the Warlocks s hut foundation if we need to remove and replace the tree branch elements? Some questions are best answered by the short interval plan 8
9 Important Questions and How to Answer Them What is the longest path to operation of the Gamma Ray? What constraints are there to getting the plasma vault dried in by net Friday? What is the late date to order the cyborg s holoprojector? What is the turnover date of Lieutenant Raffi s transport shuttle landing pad? What day will humanoid robot s chest plate be welded to his rib supports? Will we delay completion of the Space Sasquatch s village if we only mobilize one rope bridge crew? How many crews will be working in the Little Green Men s palace on second shift this weekend? Are there any impacts to the pour date of the Warlocks s hut foundation if we need to remove and replace the tree branch elements? and some by the Critical Path Method schedule. 9
10 Strengths and Weaknesses of the Systems CRITICAL PATH METHOD SCHEDULING (CPM) LAST PLANNER SYSTEM (LPS) PROS CONS Logic Driven PROS CONS Logic Driven Lacks Details Big Picture Daily Detail Lacks Logic Big Picture Not Collaborative Critical Path Group Effort Micro View Critical Path Accountability Daily Detail Ownership Highly Detailed Group Effort Ownership 10
11 Creating the Integrated Process Big Hairy Audacious Goals Defining the ideal Setting ground rules Communicating to the larger team 11
12 The Integrated Process Defined Development using both tools First pass (CPM) Trade informed (CPM) Phase planned (short interval) CPM Pull planned (short interval) Actualized (both) Refinement and addition of detail LPS Stickies Sandbo schedule Active schedule Current published Schedule Development Over Time Initial Schedule Trade Partner Input Pull Planned 12
13 Weekly Meeting Cycle Monday Tuesday Wednesday Thursday Friday Daily Check-in Daily Check-in Phase Plan Daily Check-in Daily Check-in Weekly 6- week Plan Daily Check-in CPM & WWP Sync 13
14 Integration with Other Processes 14
15 Challenges Change! Integration of Varied Stakeholder Eperience Software limitations Compleity of Project 15
16 Successes Current Construction PPC: 82 Communication to a diverse audience Transparency and trust Early warning system Smaller project staff Integration of many disciplines in schedule Smooth integration of phase plans into CPM Happy customer! 16
17 Looking Forward 17
18 In the spirit of continuous improvement, we would like to remind you to complete this session s survey in the Congress app! We look forward to receiving your feedback.
Best Practices for Collaborative Pull Planning of Complex Renovation Work in Manufacturing
Best Practices for Collaborative Pull Planning of Complex Renovation Work in Manufacturing Samir Emdanat, Ghafari Associates Branden Brickles, General Motors Tim Buckley, Barton Malow Thursday Oct 19 th,
More informationMIS 2101/2901 EXAM 1 REVIEW SESSION. Michelle Purnama Diamond Peer
MIS 2101/2901 EXAM 1 REVIEW SESSION Michelle Purnama Diamond Peer michelle.purnama@temple.edu EXAM FORMAT 25 Multiple Choice Questions First 5 from assigned readings Next 10 from assigned videos & lectures
More informationGETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams
GETTING STARTED WITH LEAN CONSTRUCTION A guide for project teams HOW TO USE THIS DOCUMENT Outlined in this guide are foundational steps for helping project teams improve the predictability and profitability
More informationIntroduction to the Last Planner System
Introduction to the Last Planner System Dick Bayer October 3, 2016 1 Agenda: Welcome, overview and introductions Current Practice Last Planner System (LPS) as a series of countermeasures Establishing milestones
More informationEstimating and Scheduling
Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques
More informationCourse 1 Project Management and Planning in Facilities Connect
Course 1 Project Management and Planning in Facilities Connect PM MODULE HOME SCREEN (COMPANY FOCUS) In today s course, we will explore the following: Facilities Connect Overview Project Management / Planning
More informationEffective Management of the Last Planner System Using vplanner
Effective Management of the Last Planner System Using vplanner Effective Management of the Last Planner System Using vplanner 2018 LCI Congress Webinar Series Samir Emdanat Director of Product Development
More informationOconomowoc Area School District Facility Construction Update July 27, 2018
Oconomowoc Area School District Facility Construction Update July 27, 2018 IXONIA ELEMENTARY SCHOOL The exterior of Ixonia Elementary School looks more complete every day! Concrete work for the exterior
More informationLessons Learned in Agile Enterprise Deployments
Lessons Learned in Agile Enterprise Deployments Michael Rudy Aras Managing Consultant Agenda Aras Consulting delivers a range of services for global enterprise customers This presentation will offer Lessons
More informationOconomowoc Area School District Facility Construction Update June 29, 2018
Oconomowoc Area School District Facility Construction Update June 29, 2018 IXONIA ELEMENTARY SCHOOL Finishing touches and final cleaning has begun inside the new addition at Ixonia Elementary, and major
More informationWeek 5 Project Work Plan
Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304
More informationTHE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION
THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION Dr. Dan Patterson, PMP Chief Design Officer, PLANNING & SCHEDULING Introduction Twenty-five years ago, I was taught that project management was built
More informationMonday to Friday, 1:00 PM to 2:00 PM. Monday-Wednesday-Thursday 8:10 AM to 11:00 AM Tuesday 8:10 AM -12:00 PM
California Polytechnic State University, San Luis Obispo College of Architecture & Environmental Design Construction Management Department CM 214, Residential Construction Management Sections 01 & 02,
More informationTHE LAST 100 FEET >> BIM IN THE FIELD TULALIP RESORT HOTEL 2009 AIA TAP BIM AWARDS
THE LAST 100 FEET >> BIM IN THE FIELD TULALIP RESORT HOTEL 2009 AIA TAP BIM AWARDS TULALIP RESORT HOTEL >> TABLE OF CONTENTS Architect Statement Descriptive Data Contractor Statement Owner Statement Introduction
More informationTHE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION
THE IMPORTANCE OF PLANNING DURING PROJECT EXECUTION A BASIS White Paper by Dr. Dan Patterson, PMP Introduction Twenty-five years ago, I was taught that project management was built upon the premise of
More informationEvanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201
Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October
More informationProject Controls for Optimal Execution
Project Controls for Optimal Execution Scheduling Techniques to Optimize Execution Tony Bolstad, Senior Project Controls Manager, Scheduling & Information Services, Inc. www.1sis.com Agenda Scheduling
More informationTurner is implementing an improved Production Planning System as well as other Innovations on the Great Wolf Lodge Project.
EXHIBIT N - Lean Production Planning System and Innovation Turner is implementing an improved Production Planning System as well as other Innovations on the Great Wolf Lodge Project. Production Planning
More informationCounty of Santa Cruz
County of Santa Cruz County Administrative Office 701 Ocean Street, Suite 520, Santa Cruz, CA 95060-4073 Phone:(831) 454-2100 Fax:(831) 454-3420 TDD/TTY: call 711 Carlos J. Palacios, County Administrative
More informationLincoln Village Community Park Par Course Project Cordova Recreation & Park District Addendum #1 Issued on Friday January 12, 2018
Lincoln Village Community Park Par Course Project Cordova Recreation & Park District Addendum #1 Issued on Friday January 12, 2018 1. CHANGE: The existing concrete mowbands at each entrance to the par
More informationGas Operational Forum. 27 March :30AM Radisson Blu Hotel, 130 Tottenham Court Road, London
Gas Operational Forum 27 March 2018 09:30AM Radisson Blu Hotel, 130 Tottenham Court Road, London Health & Safety Brief No fire alarm testing is planned for today. In the case of an alarm, please follow
More informationCollaborative Design and Scoping. CH2M s practice of Target Value Design
Collaborative Design and Scoping CH2M s practice of Target Value Design Agenda Purpose of the Collaborative Design and Scoping Process How does the CDS relate to Target Value Delivery? CDS outcome: the
More informationCivil Engineering and Architecture TEKS/LINKS Student Objectives One Credit
First Six Weeks History of Civil Architect CEA 1.1(A) The student will connect modern structural and architectural designs to historical architectural and civil engineering achievements. CEA 1.1(B) The
More informationSECTION NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10
SECTION 01 32 17.05 20 NETWORK ANALYSIS SCHEDULES (NAS) FOR DESIGN-BUILD 8/10 PART 1 GENERAL 1.1 DESCRIPTION The Contractor is responsible for scheduling all design, procurement and construction. A single
More informationLessons Learned Impacting Bridget Malinowski and John Stevens
Lessons Learned Impacting 2015 Bridget Malinowski and John Stevens Agenda Review lessons learned Maintain the schedule Potential change orders Agency coordination Claims process Design and construction
More informationMONTHLY PROGRESS REPORT
Report Date: Prepared By: Prepared For: MONTHLY PROGRESS REPORT 04 SEPTEMBER REPORT LISTING Project Description 1 S OUTHBOROUGH, MASSACHUSETTS Project Information 1 Payment Status 2 Damages / Claims 2
More informationFull Time Job Title: Tile Setter Job Number: 3303 Hours/Days: Monday-Friday Salary: $20.00/hr Location:
Full Time Job Title: Tile Setter Job Number: 3303 Hours/Days: Monday-Friday Salary: $20.00/hr Los Angeles, CA Skills Be able to square a room for tile layout. Need to be able to tile shower walls, counter
More informationMitch Miorelli Walt Disney Imagineering Bill Minnielli Hubbard Construction Carl Ross Clear on Black Chris Dierks DPR Construction
STARTING UP AN ILPD PROJECT Mitch Miorelli Walt Disney Imagineering Bill Minnielli Hubbard Construction Carl Ross Clear on Black Chris Dierks DPR Construction As to Disney artwork/properties: Disney Lean
More informationCVEN 4087/4434. Construction Engineering Project Plan Assignment. Spring Context
CVEN 4087/4434 Construction Engineering Project Plan Assignment Spring 2008 Context The preconstruction phase is arguably one of the most important phases of construction on any project. Pre-planning before
More informationCORNERCUBE. Lean Construction and Lean Project Delivery: Implications for Cost and Schedule CORNERCUBE. Optimizing Project Outcomes
Optimizing Project Outcomes Lean Construction and Lean Project Delivery: Implications for Cost and Schedule What s Happening On LPD Projects Cost Improvement Opportunity Cost LPD Time Improvement Opportunity
More informationConstruction Engineering: Reinvigorating the Discipline
Construction Engineering: Reinvigorating the Discipline Lean Construction Institute Gregory A. Howell, P.E. A brief history of project management An activity centered operating system develops based on
More informationNOTICE OF MEETING TUESDAY, MAY 9, 2017 Immediately following the 6:00 pm Special Meeting
NOTICE OF MEETING TUESDAY, MAY 9, 2017 Immediately following the 6:00 pm Special Meeting I. CALL TO ORDER Park District of Highland Park Board of Park Commissioners West Ridge Center 636 Ridge Rd. Highland
More informationValue of Failure! Students Course! Module 4: Preventing Failure!
Value of Failure Students Course Content 1. Project Management 2. Basics of risk management Project: The black box of project management Project Idea Project Management Completion / Operation Project management
More informationA Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E.
A Guide to the Last Planner for Construction Foremen and Supervisors Gregory A. Howell, P.E. Last Planners prepare assignments for people who do work. Last Planners can be found throughout construction
More informationCherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12
SCOPE SUMMARY: DIVISION: 0 - LEGAL DOCUMENTS Complete; DIVISION: 1 - GENERAL REQUIREMENTS As Applicable; SECTION: - ATTACHED SKETCH Complete; Geotechnical Engineering Report as prepared by Building and
More informationI-70 over SR 121 Bridge Slide Construction and Engineering
I-70 over SR 121 Bridge Slide Construction and Engineering March 6, 2018 Kevin Gorak, American Structurepoint Pete Jerrell, Walsh Construction Project Overview Project Location I-70 in Richmond, IN Project
More informationSECTION CONSTRUCTION OPERATIONS AND SITE UTILIZATION PLAN
SECTION 01 14 11 CONSTRUCTION OPERATIONS PART 1 - GENERAL 1.1 SUMMARY A. The Construction Operations Plan provides a coordinated construction environment to ensure an orderly, secure and safe operation
More informationThe Faster Road to Innovation Why Workopolis Went Agile
The Faster Road to Innovation Why Workopolis Went Agile What I m Covering Today Why did we transition to Agile? What we wanted to Achieve Highlights of How We Did It What we Achieved What we Learned Technology
More informationLearning Objectives In this class, you will:
CS11526 Production Planning and Lean Construction Explained: A Hands-on Simulation Michael Moran Autodesk Todd Elkins Autodesk Nathan Wood DPR Learning Objectives In this class, you will: 1. Learn the
More informationWeek 5 Project Work Plan
Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304
More informationCollege Action Project Worksheet for CAP Projects August 7, 2015 Update for CAP
College Action Project Worksheet for CAP Projects August 7, 2015 Update for 2015-16 CAP CAP #2.1.2: Increase the use of labor market information (LMI) and forecasting in GRCC Planning Processes Tie current
More informationSanitary Sewer Backup Prevention Procedures
Sanitary Sewer Backup Prevention Procedures Contractor Responsibilities: 1. Fill out daily sanitary sewer backup prevention forms that certify that the sewer system is watertight, free of debris and that
More informationCONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/01/2017 to 10/07/2017
AECOM Field Office 3550 Water Street, NW Under the Key Bridge North Abutment REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN WASHINGTON, DC. DC Contract No.:
More informationA Framework for Schedule Design Planning for Schedule Development
A Framework for Schedule Design Planning for Schedule Development Chris Carson, PSP Corporate Director of Project Controls Patrick Kelly, PSP Project Controls Manager Chris.Carson@alphacorporation.com
More informationWeek 5 Project Work Plan
Week 5 Project Work Plan 457.307 Construction Planning and Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304 호 Project
More informationEnhanced Resource Planning
Enhanced Resource Planning With a few resource planning enhancements can get you better schedule models. Just some schedule adjustments you are to do manually when not available within your resource planning
More information3/6/2014 HOSPITALITY AND RESTAURANT MANAGEMENT CHAPTER LEARNING OBJECTIVES CHAPTER LEARNING OBJECTIVES. Leaders Facilitate the Planning Process
HOSPITALITY AND RESTAURANT MANAGEMENT Leaders Facilitate the Planning Process OH 2-2 CHAPTER LEARNING OBJECTIVES Explain basic principles of planning, with an emphasis on how employees can assist, and
More informationGovernment with Microsoft
with Microsoft 1 Initiative Planning Conduct virtual town halls 6 Reach consensus in record time 8 Boost productivity in the field 10 Track files with ease 12 Government with Microsoft Site Scoping Execution
More informationCAMPUS LIFE RETREAT. Strategic Planning Student Health Services. Mary Knudtson, DNSc, NP, FAAN Executive Director
CAMPUS LIFE RETREAT Strategic Planning Student Health Services Mary Knudtson, DNSc, NP, FAAN Executive Director Strategic Planning Strategic planning is an organization s process of defining its strategy,
More informationhttp://www.myvplanner.com Effective Management of Production Planning Information Using vplanner LCI Congress Exhibit Hall Webinar Series Samir Emdanat Peter Ghafari Director of Product Development semdanat@ghafari.com
More informationDesign-Build Surgical Center Program Management
Design-Build Surgical Center Program Management Chris Carson, PSP Alpha Corporation Norfolk, Virginia Mission Provide Construction Managers and Owner Stakeholders with Real Time Information Relating to
More informationToronto Centre-CGAP Regional Course on Supervision of Microfinance Institutions March 2013, Kigali Hosted by Central Bank of Rwanda
Toronto Centre-CGAP Regional Course on Supervision of Microfinance Institutions 17-22 March 2013, Kigali Hosted by Central Bank of Rwanda 1 Toronto Centre-CGAP Regional Course on Supervision of Microfinance
More informationContractor Safety Performance -
Contractor Safety Performance - Maximizing Your Influence Insert then choose Picture select your picture. Right click your picture and Send to back. Copyright 2018 by ERM Worldwide Group Limited and/or
More informationTABLE OF CONTENTS. Student Handout 1: Career Pre-Assessment Student Handout 2: Volunteering, Internships, and Job Shadowing
TABLE OF CONTENTS Lesson 1: The Path to Success (Career and Job Opportunities)... 3 Student Handout 1: Career Pre-Assessment Student Handout 2: Volunteering, Internships, and Job Shadowing Lesson 2: Bread
More informationTHE EXPERIENCE MGMT SUMMIT MARKET RESEARCH
THE EXPERIENCE MGMT SUMMIT MARKET RESEARCH MARKET RESEARCH AT QUALTRICS X4 SUMMIT SLC UTAH MARCH 6-9 2018 WHAT IS THE X4 SUMMIT? The 5th annual Qualtrics X4 Summit is the largest gathering of Qualtrics
More informationDilley ISD 2013 Bond Program Project Update Report June 14, 2016
Dilley ISD 2013 Bond Program Project Update Report June 14, 2016 Professional Services Contracts o Program Management - TASB/SE: Executed 5/5/13 Work on-going construction phase o Architect BWA: Executed
More informationPLANNING. Ahmed Elyamany, PhD
PLANNING Ahmed Elyamany, PhD Lecture Topics Benefits of Planning Use of Project Plan Problems with Day-to-Day Planning Problems Caused By Not Planning Definition of Activity Activity durations Sequencing
More informationWeek 5 Project Work Plan
Week 5 Project Work Plan 457.657 Civil and Environmental Project Management Department of Civil and Environmental Engineering Seoul National University Prof. Seokho Chi shchi@snu.ac.kr 건설환경공학부 35 동 304
More informationINBOUND SALES PLAYBOOK. Your Comprehensive Plan for Turning Prospects Into Happy Customers
INBOUND SALES PLAYBOOK Your Comprehensive Plan for Turning Prospects Into Happy Customers SO, YOUR BUSINESS WANTS TO GO INBOUND WITH ITS SALES PROCESS? Way to go! You re already on the right track to getting
More informationManagement / Supervision Full Time
Full Time Job Title: Associate District Manager Job Number: 3599 (ADM) Hours/Days: Monday-Friday Salary: $DOE Approximate Location: Los Angeles, CA Requirements: Skills Requirements: Recent college graduate,
More informationThe Effects of Comparative 4D Models on Schedule Development and Controls. Abstract
The Effects of Comparative 4D Models on Schedule Development and Controls Kevin Coyne, P.E. Managing Engineer, Exponent, Inc. Abstract In this paper the argument is made that the use of comparative 4D
More informationThe Essential Product Owner Partnering with the Team
The Essential Product Owner Partnering with the Team Bob Galen President & Principal Consultant RGCG, LLC bob@rgalen.com Introduction Bob Galen Somewhere north of 30 years experience Various lifecycles
More informationTransforming Planning and Scheduling at BP Whiting
Transforming Planning and Scheduling at BP Whiting How NetPoint is Improving Schedule Quality and Engaging Stakeholders in New Ways Tuesday January 21, 2014 By Kaveh Dabiran, LEED AP 1 Case Study CLIENT
More informationRole Type Pay Band Location Duration Reports to: Seoul, Korea 1 year (renewable thereafter)
Role Title Customer Management Assistant (CMA) Role Information Role Type Pay Band Location Duration Reports to: Sales and Customer Management J Seoul, Korea 1 year (renewable thereafter) Branch Manager
More information1.0 PART THREE: Work Plan and IV&V Methodology
1.0 PART THREE: Work Plan and IV&V Methodology 1.1 Multi-Faceted IV&V Methodology Large, complex projects demand attentive and experienced IV&V and project management support to meet expectations. Monitoring
More information2019 BUSINESS FORECASTING AND ANALYTICS FORUM MARCH 25-26, 2019 SAN FRANCISCO, CA
2019 BUSINESS FORECASTING AND ANALYTICS FORUM MARCH 25-26, 2019 SAN FRANCISCO, CA DAY 1 - MONDAY, MARCH 25 TH, 2019 7:45am Registration and Breakfast 8:15am Welcome and Opening Comments 8:30am Opening
More informationAWP: The Silver Bullet for Solving Productivity Problems on Projects?
AWP: The Silver Bullet for Solving Productivity Problems on Projects? Jim Rammell, Wood Group Mustang Panel Discussion AWP Conference 2014 October 7-8 Houston, TX Introductions Wayne Crew, Director, CII
More informationKaysville Parks and Recreation Department Request For Bids Pioneer Park Phase I RFB 10-17
The total construction s shall be broken down into the categories indicated below to provide the Owner with a comparable analysis of each proposal submitted and a method for determining value engineering
More informationP6 Version 8.2 to 8.4 EPPM Web Power Sample Point Slide Show
THIS SLIDE REQUIRES NEW PICTURE Welcome to the Eastwood Harris Pty Ltd Primavera P6 Version 8.4 EPPM Web Tool 2 day training course Enterprise Portfolio Project Management Page 2 Administration Evacuation
More informationManaging Work Across the Enterprise
Managing Work Across the Enterprise Leveraging ArcGIS Online for Service Ticket & Work Order Management A Case Study for How a City Has Enhanced Efficiency and Increased Productivity to Serve Citizens
More informationEmergency Management Maps
ArcGIS for Emergency Management Emergency Management Maps JESS NEUNER ArcGIS for Emergency Management A solution to support the EM Mission Series of useful maps and apps focused on emergency management
More information12/10/2012. Disney Marketing ROI Case Study DMA Conference. Defining A Marketing ROI Solution. Presentation Agenda
Disney Marketing ROI Case Study DMA Conference Presented by Disney & SAS October 2012 Defining A Marketing ROI Solution Reach the right audience Maximize Return on investment for marketing spend Through
More informationConstruction Update. April 2016
Construction Update April 2016 Western Zone Gridlines 1 to 10 Central Zone Gridlines 10 to 20 Eastern Zone Gridlines 20 to 35 Project Overview 1. Recent Activity 2. Upcoming Activity 3. Safety & Labor
More informationACCENTURE & SAP SUCCESS FACTORS INVESTIGATE CAPABILITIES WORKBOOK. Imagine where we will go together...
ACCENTURE & SAP SUCCESS FACTORS INVESTIGATE CAPABILITIES WORKBOOK Imagine where we will go together... Imagine where we will go together... AGENDA TUESDAY APRIL 19TH 12:00 PM Lunch (outside Ali Conference
More informationExam Code: Number: Passing Score: 800 Time Limit: 120 min File Version: 35.4.
Exam Code:74-343 Number: 74-343 Passing Score: 800 Time Limit: 120 min File Version: 35.4 http://www.gratisexam.com/ Exam Code:74-343 Exam Name:Managing Projects with Microsoft Project 2013 Testinside
More informationImplementing Budget Solutions for Schools: Construction Cost and Scheduling Benefits of Using Wood
Disclaimer: This presentation was developed by a third party and is not funded by WoodWorks or the Softwood Lumber Board. Modern School Construction in the Pacific Northwest: Achieving Performance and
More informationMATERIAL VISIBILITY. for Owners/Operators: The Importance of A CASE STUDY
The Importance of MATERIAL VISIBILITY for Owners/Operators: A CASE STUDY Canadian Oil Sands Refinery project owner gains unprecedented material visibility across multiple contractors INTRODUCTION ABOUT
More informationTHE ENTRELEADER S GUIDE TO DELEGATION
THE ENTRELEADER S GUIDE TO DELEGATION Your business can t grow unless you learn to trust others to help you win. And that starts with delegating to your team. The only problem? Most small-business owners
More informationCycle Through the Success of Ortho NorthEast s Instant Access Clinic
May 16-18, 2018 Caesar s Palace Las Vegas, Nevada Cycle Through the Success of Ortho NorthEast s Instant Access Clinic Kylie Mills, Manager of Scheduling and Phone Triage Krista Bennett, Manager of Clinical
More information8 WAYS WORKFORCE PLANNING CAN INCREASE YOUR PROFITS
8 WAYS WORKFORCE PLANNING CAN INCREASE YOUR PROFITS TABLE OF CONTENTS Introduction...3 1. Determine Your Current Headcount...4 2. Forecast Attrition...5 3. Forecast Workforce Demand...6 4. Perform a Workforce
More informationMicro Service Architecture
Micro Service Architecture A software developer s view on the Cloud Tobias Abarbanell CTO, Frontiers Media 16-Jun-2016 Micro Service Architecture - Tobias Abarbanell 1 What are Micro services? Micro service
More informationNew Main Hospital, Site Park, and Underground Garage Construction Progress Update #16
New Main Hospital, Site Park, and Underground Garage Construction Progress Update #16 Date: March 1, 2010 From: Gary Claar Engineering Services 355-1660 Gary.Claar@NationwideChildrens.org More and more
More informationLong-term Memory Review PROFICIENCY PRACTICE: MONDAY REVIEW
PROFICIENCY PRACTICE: MONDAY REVIEW 1) When solving a word problem, the first thing to do is the known information 2) When a problem requires more than one step, one strategy is to organize the known information
More informationProduct Planning Report. Product planning insights from the world s leading companies
2017 Product Planning Report Product planning insights from the world s leading companies What s inside 1 Report Highlights...3 2 Planning & Prioritizing...7 3 Crafting the Plan...11 4 Communicating the
More informationQR Network System Rules
QR Network System Rules Capricornia Coal Chain Date: 31/08/2011 QR Network Capricornia System Rules - 1 - QR Network Capricornia System Rules - 2 - Contact Details For more information on this document,
More information39 Years of Learning the Hard Way. Mark A Etrheim, Mastercraft Homes Inc
39 Years of Learning the Hard Way Mark A Etrheim, Mastercraft Homes Inc Clear and compelling marketing Finding good customers Well designed homes Accurate estimating system Best carpenters to frame Highly
More informationSAMPLE WORK PLAN. 2. Execute subcontractor agreements and gather forms and documentation required from each sub
SAMPLE WORK PLAN You have just been awarded a $500,000 construction contract as a prime bidder. You will perform 60% of the work in-house (including your suppliers) and 40% will be performed by 3 different
More informationDilley ISD 2013 Bond Program Project Update Report March 11, 2015
Dilley ISD 2013 Bond Program Project Update Report March 11, 2015 Professional Services Contracts o Program Management - TASB/SE: Executed 5/5/13 Work on-going o Architect BWA: Executed 2/20/13 Work on-going
More informationIdentification Selection Definition Execution. Schedule.
SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification
More informationBenny s Campus Store. CCNY Campus Spirit Store operates five days a week. The hours of operation are:
Benny s Campus Store 1.00 HOURS OF OPERATION CCNY Campus Spirit Store operates five days a week. The hours of operation are: Monday, Wednesday, Thursday 9:00 am - 5:00 pm When School is in Session Tuesday
More informationWhite Paper January Budgeting: Beyond spreadsheets
White Paper January 2010 Budgeting: Beyond spreadsheets 2 Contents 3 Business problems 3 Business drivers 3 The solution Break the logjam Modeling built for business change Fewer process headaches, more
More informationPrinciples of Planning for IT Projects
Principles of Planning for IT Projects Introduction Building Timings Exercises Meals & refreshments Mobile Phones Part 1 Setting the Scene 1. Course Objectives 2. Where projects come from 3. What is a
More informationA Guide To Your First 30 Days Leading A Business Turnaround
Nebes Consulting LLC William Nebes III, Founder & President bill@nebesconsulting.com (m) +1-603-305-7450 https://nebesconsulting.com @billnebes A Guide To Your First 30 Days Leading A Business Turnaround
More informationSurvey of State Park Managers
Survey of State Park Managers In August 1999, the Legislative Auditor s Office conducted a survey of state park managers. We asked park managers about the use of volunteers, state park budget and capital
More informationReading Utility Meters
Reading Utility Meters Summary: Students observe and interpret daily and weekly patterns of energy consumption by reading utility meters. Objectives Students will be able to read and interpret information
More informationReliable Decisions in Design
Reliable Decisions in Design Paz Arroyo, Lean Project Andy Springer, Jones Lang LaSalle David Long, Lean Project Daniel Kim, Arup Thursday, October 19 th 2017 Presentation Contents Reliable Design Decisions
More informationRobertson Family Farm
Robertson Family Farm Adventures in Blueberry Farming Who are we? James and Sandy purchased the property in February 2013. Matthew and Samantha moved to the farm in June of 2013, and we began our season
More informationOrganizational Change Through Metrics
Organizational Change Through Metrics Speaker: Allen Hurst and Heather Rainey Company: Improving Enterprises Website: www.improvingenterprises.com Welcome to the PMI Houston Conference & Expo 2015 Please
More informationArcGIS for Local Government: An Overview SCOTT OPPMANN
ArcGIS for Local Government: An Overview SCOTT OPPMANN Agenda Introduction Why? Solution Offering What s Next Your Feedback Using ArcGIS to understand and mitigate challenges Housing Forecasting Urban
More informationthe Field Company Describe basic Autodesk options analysis,
BIM for Contractors: Takin It to the Field David Epps Holder Construction Company Rachel Stalzer Holder Construction Company Class ID: CR2694-P Class Descriptio on Many builders who are implementing BIM
More information