Risk analysis of parametric cost estimates within a concurrent engineering environment

Size: px
Start display at page:

Download "Risk analysis of parametric cost estimates within a concurrent engineering environment"

Transcription

1 Risk analysis of parametric cost estimates within a concurrent engineering environment Rajkumar Roy, Sara Forsberg, Sara Kelvesjo, Christopher Rush Department of Enterprise Integration, SIMS, Cranfield University, Cranfield, Bedford, MK43 OAL, United Kingdom. Tel: 44 (0) r.roy@cranfield.ac.uk or c.rush@cranfield.ac.uk Abstract In industries where project time scales are long and the investment capital required is high, it is essential to minimise the risk involved with the development of a new product. Aerospace manufacturers are an excellent example of this kind of industry. Parametric estimating is a method used for predicting cost based on historical relationships between cost and one or more predictor variables. This method is commonly used during the conceptual stages of design where potential risk is at its highest. There is an increasing trend within parametric cost estimating to combine parametric analysis with statistical risk analysis methods. All cost estimates have a degree of uncertainty associated with them. The objective of a cost risk analysis is to predict the amount of uncertainties involved during the estimate of future projects. This paper presents the results of a risk analysis study conducted on a recently developed set of cost estimating relationships (CERs). The first case study considers the risks involved within a parametric cost estimate. This particular cost risk methodology can be used when only conceptual information is available. The main risk involved is related to the independent variable and its probability of change during the design process. The second case study provides the estimator with a possible range of costs for designing a part. This method can be used when there is little information available concerning a part. 1. Introduction Within the aerospace industry, where project time scales are long and the capital required is very high, it is essential to minimise the risks involved, especially during the early stages of a project s lifecycle. The objective of a cost risk analysis is to predict the amount of uncertainties involved in the cost estimate of future projects. There will always be uncertainties, i.e. risks, involved in a project. If these uncertainties can be identified and quantified, effort can be made to successfully deal with the impact of them occurring. Risk analysis is a very broad term, meaning the study of any situation, which is controlled in one way or another by uncertainty. The outcome of a risk analysis study may help to make extreme yes or no decisions, but it can also show all solutions between these extremes. By looking at the uncertain variables within a situation, a risk analysis can show which ones have the most effect on the solution, and pinpoint where most effort should be targeted. The risk analysis makes sure that uncertainty within the variable can be accounted for before committing the project. Therefore, the outcome of the analysis can be used as a decision tool for the designer, that is, if the designer understands the risks involved with certain cost drivers, he can choose a different approach to lower the risk. Thus, when using risk assessment and risk analysis it ensures that the consequences of risks to a programme cost and schedule are understood and taken account of for the commercial bid on programme price and duration [1]. This paper begins by highlighting the need for cost risk reduction initiatives within a concurrent engineering environment. It then examines different aspects of parametric costing and risk analysis with respect to their use for cost risk analysis. Section four describes the first of two risk assessment methodologies that can be used with a parametric cost estimate. Section five demonstrates how to use this methodology by applying it to a recently produced cost estimating relationship (CER). Section six describes the second risk analysis methodology and section seven demonstrates its practical application. The results of both methodologies are based on a CER that was previously developed within a European aerospace company [2, 3, 4]. In summary, the risk analysis methods examine whether the independent variables, or cost drivers, included in the CER change as the product matures through the design process. The results demonstrate how changes affect the accuracy of the cost estimate. The paper concludes the main findings of this research in section eight.

2 2. Aerospace concurrent engineering environment The company sponsoring this research embraces a concurrent engineering philosophy. Figure 1 illustrates a typical structure of an integrated project team by a family tree type representation. The tree illustrates the team members operating within the Technical and Engineering activities on the project under scrutiny [4]. Structural Mat Test Technical Task Leader Mech. Design Elec. Design Structural Tests Project IPT Manager Prod. Plan. Engineering Task Leader Assembly Detail Electrical N.C. Prog. Support Group Tool Design Tool Manf. Figure 1. Typical representation of IPT members Figure 2 represents a diagrammatic form of the IPT environment. The company recognised that new cost estimating relationships were required to reflect the activities of their concurrent engineering environment. The CER used for the risk assessment in this paper was developed around the activities within phase D. The reasons behind this were that data was available for the study within this area [13]. A, B & C D E IPT Technical Activities: 1. Mech. Design 2. Structure & Mass 3. Electrical Design 4. General Systems 5. Avionics Systems 6. Airworthiness 7. Structural Test 8. Material Test Engineering Activities: 1. Tool Design 2. Tool Manufacture 3. NC Programme 4. Electrical 5. Detailed 6. Assembly 7. Production Plan. Cradle to Grave Phases Tech. activities activities 1 st Article Production Service Figure 2. Diagram of Project IPD Environment 2.1. Risk analysis within a concurrent engineering environment The developed CER was designed for use during the early stages of design to predict the future effort of a new product development. The design of a new product goes through many phases. From the concept stage a SET (simultaneous engineering team) produces a project plan. From this plan initial schemes are produced until a mature concept is ready. The designs then pass through a freeze gate to prevent any further changes. Components are then separated from the Scheme and modelled on CATIA. These models then pass through a freeze gate before going on to the 2D stage (see Figure 3). Use CER in year 1 Concept Specs. Past Cases S. E. T. Project Plan Initial Schemes Initial Schemes To predict Initial Concept Phase CER 3D Freeze Concept Freeze Mature Concept 3D model Figure 3: Design activities Accumulated Engineering activities over a period of Years A B C D E, F, G F O C U S 2D Detail Activity Eng Freeze 2D Freeze 1 st Article An optimised concurrent engineering environment provides an opportunity to substantially reduce the total risk of a project. Because, integrated product teams (IPTs) containing members of various skilled disciplines, enable a simultaneous contribution to an early product development and definition. Therefore, within a fully integrated product development (IPD) cycle, multidisciplinary teams working together reduce the likelihood of product failure by avoiding costly alterations later in the design process. However, up to 70-80% of a product cost is committed during the concept phase of product development [5, 6, 7, 8]. Making a poor decision at this stage can be extremely costly. This is because product modifications and process alterations are more expensive the later they occur in the development cycle. Since the developed CER is intended to predict the cost of a product 20 years henceforth the sponsoring company wanted to understand the level of risk involved with the CER result. The remainder of this paper describes the process developed for this purpose.

3 3. Related research The following discussion captures different aspects of parametric costing and risk analysis within the conceptual stages of project development. This section provides fundamental knowledge concerning the tools and techniques currently used within the area of costing and risk analysis Parametric costing Parametric cost estimating (PCE) is a technique commonly used to estimate the cost of future systems. It provides a technique for predicting cost based on historical relationships between cost and one or more predictor variables i.e. cost estimating relationships (CERs). The method uses a statistical approach, and is commonly used during the conceptual design stages [9]. Mileham et al. [8] state that there is a growing need within the concurrent engineering environment to provide the designer with a simple, accurate method of estimating product costs during the conceptual stage of design. Their developed methodology is based on the basic information available to the designer during the conceptual design stage, and a set of data converters, which are used to calculate the values of cost-driving parameters. Parametric estimating can be used throughout the product life cycle. Both industry and Government accept the techniques. Many authors commend its usefulness [5, 6, 8, 10]. However, PCE does have its limitations, for example, CERs are sometimes too simplistic to forecast costs. If ill considered a CER could provide a completely misleading result. A broad outline of the CER development process is described below CER development process CERs can range from simple rules of thumb to complex relationships involving multiple variables. The principal function of CERs is to provide equations or graphs that summarise historical cost or resource data in a manner that will allow the equations or graphs to be used to estimate a future cost [5]. A general methodology for developing CERs includes activities such as data collection, testing a CERs logic, statistical analysis, CER significance tests and validation. Figure 4 illustrates this sequential process. The collection of data is often a very critical and timeconsuming activity. Typically more effort is devoted to assembling a quality database than to any other task in the CER development process. It is often said that the estimate is only as good as the data input to the cost model; therefore it is essential to collect accurate data. Data Collection Testing of a CERs logic Statistical Analysis Figure 4. A general process of developing CERs After a database is developed the first step is to hypothesise and then test the mathematical form of the CER. The analyst must determine and test a proposed CER, in order to determine its logic. The work involves discussions with engineers to identify potential cost driving variables, scrutiny of the technical and cost proposals, and identification of cost relationships. Only with an understanding of estimating requirements can an analyst attempt to hypothesise a forecasting model necessary to develop a CER. In order to test and validate a CER statistical analysis is used. Multiple regression is the most common method used to test hypotheses [11]. Although widely accepted PCE is primarily based on statistical assumptions concerning the cost driver relationships to cost, and therefore, estimators should not completely rely upon statistical analysis techniques. Hypotheses, common sense and engineering knowledge should come first, and then the relationship should be tested with statistical analysis. Because of the identified limitations within PCE and CERs there is an increasing trend with parametric cost estimators to combine the statistical techniques of parametric analysis with statistical risk analysis methods. Parametric estimating offers the cost analyst the advantage of being able to quantify the risk. This helps to restore confidence within the results and improves decision-making Risk Analysis Testing of the CERs Significance Validation of the CER Edmonds [1] discusses the advantages of using risk management within the aerospace industry. Stating that the use of risk assessment and risk analysis ensures that the consequences of risks to programme cost and schedule are understood provided they are taken account of during the commercial bid of a programmes price, and duration. A cost risk analysis generates a range of costs for a project, and assigns a probability level to each cost value within the range. The introduction of risk assessment and risk analysis ensures that the goals of the producer and consumer

4 materialise and that they both benefit. It provides confidence concerning the final product and identifies actions needed to keep cost and schedule on target. There are five key steps to follow in the risk management process [12]. Figure 5 illustrates this process more clearly. Identify Assess Feedback Analyse Reduce One of the most important benefits of using risk assessment is to generate a distribution/range of costs i.e. to move away from single point estimating, since a range of costs are much easier to estimate than a single cost [13]. Furthermore, once a risk analysis has been conducted the analyst can consider ways to reduce the risk e.g. by avoidance, deflection or contingency and then plan accordingly to control the reduction process. Statistical theories are well established and there are many software packages available to perform such calculations. However, for risk assessment the situation is very different and software is not so readily available. One computer model that can, and is used for the risk analysis of cost estimating is named SAM [14] (Stochastic Aggregation Model). SAM is a Monte Carlo simulation program designed to help the cost analyst quantify the uncertainty associated with a parametric cost estimate. The areas of cost risk that SAM evaluates are: cost estimating relationships (CER); independent variable uncertainty; complexity factor uncertainty, and; CER statistical uncertainty. Control Figure 5: Risk Management Process Crossland et al. [15] recognised that in the early stages of a design project, it was necessary to evaluate the design to determine its feasibility in order to focus attention with particular areas of the design. They developed a tool-set called RiTo (RIsk TOol) to fulfil this purpose. RiTo, is an objective-oriented risk modelling tool that was developed to support the development of design from the earliest stage by building models for risk assessment. By combining risk analysis with the normal pricing process, the estimator gets a direct measure of the risk at the same time the estimate is formed, and therefore can allow for a contingency value to be quantified. This contingency provides a better understanding of the correlation between items, which can have large combined effect on the overall distribution [16]. The remainder of this paper discusses two different approaches to the cost risk analysis process. Each approach is tested on case studies in order to validate their applicability. 4. Cost risk methodology one 4.1. Identification The first step in handling risks is identification. This is readily available from the results of the cost estimating relationship. The risk consists of the independent variables; included in the CERs (see below), and their probability of changing throughout the process. The independent variables, also called cost drivers, are selected through statistical analysis and form the basis of the CER. Y = C 0 + C 1 (Mass) + C 2 (Surface related) Where: Y = The dependent variable, time; C 0 = The constant; C 1 = The constant multiplied with the value of mass, and; C 2 = The constant multiplied with the surface related. Because the independent variables are prone to change as the product matures through the design process the accuracy of the cost estimate is affected. The higher the probability of the change occurring, and its impact, the less accurate the cost estimate will be Assessment Having identified possible sources of risk, included in the cost estimate, the analyst then needs to calculate their impact on the cost. This is the risk assessment. The risk can be defined as: Risk = p * c, Where: p is the probability of the event occurring, and; c is the impact of the risk on the estimate. This means that both the probability of the risk occurring, and the impacts are assessed. The quantification of the cost risks can be made through a probability distribution. One way of representing this is through a triangular distribution. To achieve this the minimum, most likely, and maximum cost are required, see Figure 6 below.

5 5. Case Study One Minimum Most Likely Maximum Figure 6: Triangular distribution The values of the impact are then taken from the coefficient of the independent variable of the CER and multiplied with the values gathered from the risk assessment. As discussed earlier one of the most important benefits of using risk assessment is to generate a distribution of costs, and move away from single point estimating Analysis After the risk assessment is performed, the analysis can be carried through. This is completed using simulation, such as Monte Carlo or Latin Hypercube. The outcome of the risk analysis provides the estimator with a range of costs, instead of a single one, from the CERs. In this way, it can be assumed that the cost will not exceed a specific value, with a certain probability; normally an 85 % probability is used. This is presented using a cumulative probability curve, the S curve, see Figure 7. % Cumulative Probability A case study was conducted where the risks involved from a parametric cost estimate were considered The estimate, a Cost Estimating Relationship (CER), was developed to capture the design time of producing a specific part [2, 3, 4]. This cost risk analysis methodology can be used during the conceptual design stage when there is limited information and uncertainty concerning the independent variable. That is, there is a probability of the independent variable values changing during the design process Identification In this study, the risk incorporates the independent variables from the CER i.e. mass and surface related. The value of these independent variables can change during the design process, therefore, they are considered as risks Assessment With the assistance of expert opinions an assessment of the risks, included from the CER, were conducted. The identification and evaluation of the two independent variables are illustrated in Table 1. Mass risk Surface related risk Description Risk An increase in the mass (within the time span that the estimate covers). Risk A change of the product whether it is surface related or not. Probability 50% 0% MIN 5% of the mass - Most Likely 20% of the mass - MAX 50% of the mass - Table 1: The identification and assessment of the different risks involved in the cost estimate Figure 7: A cumulative probability curve 4.4. Mitigation Time If the risk involved is shown to be very high, a mitigation plan should be made. The mitigation plan should include discussion with experts concerning the area under consideration and estimators who have experience in risk management. According to the experts, the surface related variable did not have any probability of changing during the design process. This meant that the variable was no longer considered as a risk, and it was therefore excluded from further analysis. The percentages of the likely changes of the mass figure were gathered from the experts. The independent variable, mass, and the impact, c, were then distributed using the triangular distribution. Since there was a large range within the mass of the parts that the CER was based upon, the impacts were grouped into five different weight categories. The averages of these weight categories were then multiplied with the risk percentages and the coefficient of the CER, see example below. This sum was then used as the impact of the risk described in a triangular distribution.

6 (min % of change in mass, most likely % of change in mass, max % of change in mass) *(average weight of the specific category) *(coefficient of the variable from the CER) = Triangular distribution (impact) of the cost estimate. Worked example: (5%, 20%, 50%)*(800 gram)*0.05 = (2 hours, 8 hours, 20 hours) The probability of the risk occurring can be shown in a discrete distribution. This type of distribution is used when there is a known amount of outcomes, i.e. the risk will occur or not. Discrete ({0,1}, 50%, 50%}) The probability of the risk occurring and the impact of the risk are then multiplied to compute the actual risk. This is achieved by multiplying the discrete distribution and the triangular distribution together Analysis During the identification and evaluation of the risks a tool named PREDICT! was used to perform the analysis. This tool is generic and not specifically designed for cost risk analysis. The analysis was made using a Monte Carlo simulation Results The output produced from the analysis is illustrated using a cumulative probability curve. This plot shows that there is a probability of 80 % that the extra design time, if mass increase during the design process, will not exceed 10 hours. See Figure 8 below: % 6. Risk analysis methodology two To predict the range of a CER, when limited information is available about the product i.e. a new concept/idea, another cost risk analysis is required. This provides the analyst with a technique that can predict the maximum outcome of the cost estimate, with a specific probability Identification As previously mentioned, the risks involved that can cause changes within the CER range, are the independent variables. These independent variables are readily available from the CER since they form the basis of the estimate Assessment The probability distributions of the independent variables are also readily available from the data that was used for the development of the CER. These data can be distributed as a triangular distribution with a minimum, most likely and maximum value and used for the assessment of the probability, see Figure 6 above Analysis To perform the risk analysis, a software package can be used. The input data is taken from the identification and evaluation of the risks, or the independent variables included within the estimate. Because probability distribution data are readily available from CERs, parametric costing is sometimes combined with cost risk analysis techniques involving Monte Carlo simulation. The simulation performs several thousand iterations to form a frequency distribution of cost [5] Results The outcome of this type of cost risk analysis is a range of costs for the total CER. This type of analysis is used when there is only a limited amount of information available. The analyst can say to a specific probability, that the cost of a particular type of part, used for the cost estimate, will have a certain cost range. This can be extremely useful for early estimates, when little or no information about a part is available. Figure 8: Cumulative probability curve Time 7. Case Study Two The same CER, used within case study one, was used for this case study. This cost risk analysis provides a range

7 of total costs, to a certain probability, for designing a specific part Identification The CER used two independent variables, mass and surface related that could cause changes within the CERs range. From the data set used for the CER development, the variation of the independent variables, mass and surface related, were identified Assessment The range of mass, which was readily available from the data set, was assessed for the analysis. A minimum, most likely and maximum weight was captured. The other independent variable, surface related had only two possible outcomes, surface related or not Analysis An analysis was conducted on the independent variable mass. A triangular distribution, which included the impact mass had on the CER, was used in the simulation tool PREDICT Result The impact that mass had on the CER is illustrated in the graph, Figure 9. The graph illustrates with an 80% certainty the impact mass has on the CER will not exceed 67 hours. % Total time = C0 + [C1 (mass)+maximum added time if the weight change] + C2 (surface related) Thus, the total time will not exceed 213 hours, with the probability 80%. This is the absolute maximum value that the estimate can be. The second independent variable is chosen to find the maximum impact of the total cost. 8. Discussion and Conclusions This paper has presented two different methodologies for risk analysis of CERs within a concurrent engineering environment. The risk identification and assessment is very much dependent on the environment. When conceptual information is available and a cost estimate is completed using a CER, a risk analysis like the one used in case study one, will provide the analyst with the extra amount of time the design process will take if the independent variable changes, within a certain probability. In some cases when the conceptual information is not totally defined a risk analysis can be very useful for the estimator. The analysis will indicate the upper and lower boundary of cost that a part will obtain as it is being designed. These case studies are based on a CER that was developed for a specific type of part; a small sample size was used for the CER development. Therefore, the results from these case studies can only be used for the same type of part. Nevertheless, the results indicate the possibility of using the two approaches as predictive tools for quantifying the risks involved when using CERs within a concurrent engineering environment. Acknowledgements The authors would like to thank Ian Taylor of BAE SYSTEMS who helped to develop and supervise this research with Cranfield University. Figure 9: Cumulative probability plot Time This result is then summarised with the outcome from the CER. The maximum occurring time is added to the independent variable mass: References [1] EDMONDS, R. J. A case study illustrating the risk assessment and risk analysis process at the bid phase of a project. British Aerospace Defence Limited, Dynamics division. Ch. 2. [2] ROY R., BENDALL D., TAYLOR J. P., JONES P., MADARIAGA A. P., CROSSLAND J., HAMEL J., TAYLOR I. Development of airframe engineering

8 CERs for military aerostructures. MSc group project, Cranfield University, UK, [3] ROY R., BENDALL D., TAYLOR J.P., JONES P., MADARIAGA A. P., CROSSLAND J., HAMEL J., TAYLOR I. M. Development of airframe engineering CERs for military aerostructures. Second World Manufacturing Congress (WMC'99), Durham (UK), 27-30th Sep., [4] ROY R., BENDALL D., TAYLOR J.P., JONES P., MADARIAGA A. P., CROSSLAND J., HAMEL J., TAYLOR I. M. Identifying and capturing the qualitative cost drivers within a concurrent engineering environment. Advances in Concurrent Engineering, Chawdhry, P.K., Ghodous, P., Vandorpe, D. (Eds), Technomic Publishing Co. Inc., Pennsylvania (USA), pp , [5] STEWART, R., WYSKIDSA, R., JOHANNES, J., Cost Estimator's Reference Manual, 2nd ed., Wiley Interscience, [6] DEPARTMENT OF DEFENCE. Parametric Estimating Handbook, 2nd Ed., DoD, [7] TAYLOR, I. M. Cost engineering-a feature based approach. In: 85th Meeting of the AGARD Structures and Material Panel, Aalborg, Denmark, October 13-14, 14:1-9, [8] MILEHAM, R. A., CURRIE, C. G., MILES, A. W., BRADFORD, D. T. A parametric approach to cost estimating at the conceptual stage of design. Journal of Engineering Design, 4 (2): pp , [9] RUSH, C. & ROY, R. Analysis of cost estimating processes used within a concurrent engineering environment throughout a product life cycle. Proceedings, 7 th International Conference on Concurrent Engineering, University Lyon 1, France, July th, [10] PUGH, P. Working top-down: cost estimating before development begins. Journal of Aerospace Engineering, Part G, Vol. 206, pp , [11] NORUSIS, M.J. SPSS 8.0 A guide to data analysis. Prentece-Hall, Inc, New Jersey, 1998 [12] TURNER, R: J. The handbook of project-based management. McGraw-Hill International (UK) Limited, [13] FORSBERG, S., KELVESJÖ, P. S. CER development for airframe engineering. Masters Thesis, Cranfield University, UK, [14] HAMAKER, J. W. SAM user Manual. Huntsville, AL, Cited in: Stewart, R. D., Wyskida, R. M., Johannes, J. D. (ed). Cost estimator s reference manual, ch 8, [15] CROSSLAND, R., SIMS WILLIAMS, J. H., MCMAHON, C. A. An object - oriented design model incorporating uncertainty for early risk assessment. In: International Computers in Engineering Conference, Boston, MA, [16] HULL, K. AEPS/ETG, Ministry of Defence, Procurement Executive. Risk analysis techniques in defence procurement. (unpublished), 1991.

Available online at ScienceDirect. Procedia CIRP 28 (2015 ) rd CIRP Global Web Conference

Available online at  ScienceDirect. Procedia CIRP 28 (2015 ) rd CIRP Global Web Conference Available online at www.sciencedirect.com ScienceDirect Procedia CIRP 28 (2015 ) 179 184 3rd CIRP Global Web Conference Quantifying risk mitigation strategies for manufacturing and service delivery J.

More information

Models in Engineering Glossary

Models in Engineering Glossary Models in Engineering Glossary Anchoring bias is the tendency to use an initial piece of information to make subsequent judgments. Once an anchor is set, there is a bias toward interpreting other information

More information

In any particular situation, dealing with environmental risk involves two steps:

In any particular situation, dealing with environmental risk involves two steps: Presented by: Gargi Bhatt 04/27/2005 ENVIRONMENTAL RISK ASSESSMENT Introduction: The field of Environmental statistics is one of the rapid growths at the moment. Environmental decision making is prevalent

More information

A DESIGN PROCESS MODELING APPROACH INCORPORATING NONLINEAR ELEMENTS

A DESIGN PROCESS MODELING APPROACH INCORPORATING NONLINEAR ELEMENTS Proceedings of 1998 DETC: ASME Design Theory and Methodology Conference September 13-16, 1998, Atlanta DETC98-5663 A DESIGN PROCESS MODELING APPROACH INCORPORATING NONLINEAR ELEMENTS Johan Andersson Department

More information

Uncertainty in transport models. IDA workshop 7th May 2014

Uncertainty in transport models. IDA workshop 7th May 2014 Uncertainty in transport models IDA workshop 7th May 2014 Presentation outline Rationale Uncertainty in transport models How uncertainty is quantified Case study General comments 2 DTU Transport, Technical

More information

Project Controls Expo

Project Controls Expo Project Controls Expo 09/10 Nov London 2011 What is Cost Engineering and Cost Estimating Carl Dalton Director Polaris Consulting Speaker Profile Carl Dalton Carl is a Fellow of the Association of Cost

More information

Distinguish between different types of numerical data and different data collection processes.

Distinguish between different types of numerical data and different data collection processes. Level: Diploma in Business Learning Outcomes 1.1 1.3 Distinguish between different types of numerical data and different data collection processes. Introduce the course by defining statistics and explaining

More information

Introduction to Cost Estimation - Part I

Introduction to Cost Estimation - Part I Introduction to Cost Estimation - Part I Best Practice Checklists Best Practice 1: Estimate Purpose and Scope The estimate s purpose is clearly defined The estimate s scope is clearly defined The level

More information

BAE Systems Insyte Software Estimation

BAE Systems Insyte Software Estimation BAE Systems Software Estimation Steve Webb BAE Systems Estimating Focus Group Chairman Engineering Estimation & Measurement Manager 22 April 2008 1 Background BAE Systems Estimating Focus Group covers

More information

INDUSTRY SURVEY REVIEW OF OBSOLESCENCE MANAGEMENT STRATEGIES IN PERFORMANCE BASED CONTRACTS

INDUSTRY SURVEY REVIEW OF OBSOLESCENCE MANAGEMENT STRATEGIES IN PERFORMANCE BASED CONTRACTS Proceedings of the 11 th International Conference on Manufacturing Research (ICMR2013), Cranfield University, UK, 19th 20th September 2013, pp 467-472 INDUSTRY SURVEY REVIEW OF OBSOLESCENCE MANAGEMENT

More information

Probabilistic well cost and time modelling. See the unforeseen

Probabilistic well cost and time modelling. See the unforeseen Probabilistic well cost and time modelling See the unforeseen P1 is designed to generate time and cost estimates along with the risk profile of a well. The software is applicable for all different types

More information

RISK Realistic and Practical Project Risk Quantification (without CPM)

RISK Realistic and Practical Project Risk Quantification (without CPM) RISK.2515 Realistic and Practical Project Risk Quantification (without CPM) John K. Hollmann, PE CCP CEP DRMP FAACE Hon. Life Abstract From 2007 to 2013, the AACE International Decision and Risk Management

More information

Incorporating DSM Uncertainty and Flexibility into Integrated Resource Planning

Incorporating DSM Uncertainty and Flexibility into Integrated Resource Planning Incorporating DSM Uncertainty and Flexibility into Integrated Resource Planning Eric W. Hildebrandt, RCG/Hagler, Bailly, Inc. Robert M. Wirtshafter, University of Pennsylvania This paper presents an approach

More information

Macro-parametrics and the applications of multicolinearity and Bayesian to enhance early cost modelling

Macro-parametrics and the applications of multicolinearity and Bayesian to enhance early cost modelling 9 th to 12 th June 2015 Macro-parametrics and the applications of multicolinearity and Bayesian to enhance early cost modelling Dale Shermon, QinetiQ Fellow / Head of Profession - Cost 1 and Dr Catherine

More information

Identification Selection Definition Execution. Schedule.

Identification Selection Definition Execution. Schedule. SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification

More information

1 Introduction to Life Cycle Assessment

1 Introduction to Life Cycle Assessment Introduction to Life Cycle Assessment 1 Introduction to Life Cycle Assessment This section of the handbook introduces the concept of Life Cycle Assessment (LCA). Videos 2, 3 and 4 of the GaBi Paper Clip

More information

Programme & Project Planning and Execution

Programme & Project Planning and Execution Portfolio, LEADING THE WAY IN PROJECTS Programme & Project Planning and Execution Caravel Group - Project Management with a total focus on value THE SPECIALIST FOR LARGE COMPLEX MULTI-DISCIPLINED PROJECTS

More information

Economic aspects of the delineation of well head protection areas under conditions of uncertainty

Economic aspects of the delineation of well head protection areas under conditions of uncertainty Economic aspects of the delineation of well head protection areas under conditions of uncertainty N. Theodossiou * and D. Latinopoulos Division of Hydraulics and Environmental Engineering, Department of

More information

Tassc:Estimator technical briefing

Tassc:Estimator technical briefing Tassc:Estimator technical briefing Gillian Adens Tassc Limited www.tassc-solutions.com First Published: November 2002 Last Updated: April 2004 Tassc:Estimator arrives ready loaded with metric data to assist

More information

Getting Started with OptQuest

Getting Started with OptQuest Getting Started with OptQuest What OptQuest does Futura Apartments model example Portfolio Allocation model example Defining decision variables in Crystal Ball Running OptQuest Specifying decision variable

More information

PRE-READING 4 TYPES OF MODEL STRUCTURES

PRE-READING 4 TYPES OF MODEL STRUCTURES LEARNING OBJECTIVES Types of Model Structures PRE-READING 4 TYPES OF MODEL STRUCTURES Appreciate the different structural characteristics that may be incorporated within financial models. Recognise how

More information

A simulation-based risk analysis technique to determine critical assets in a logistics plan

A simulation-based risk analysis technique to determine critical assets in a logistics plan 19th International Congress on Modelling and Simulation, Perth, Australia, 12 16 December 2011 http://mssanz.org.au/modsim2011 A simulation-based risk analysis technique to determine critical assets in

More information

ENGINEERS AUSTRALIA ACCREDITATION BOARD ACCREDITATION MANAGEMENT SYSTEM EDUCATION PROGRAMS AT THE LEVEL OF PROFESSIONAL ENGINEER

ENGINEERS AUSTRALIA ACCREDITATION BOARD ACCREDITATION MANAGEMENT SYSTEM EDUCATION PROGRAMS AT THE LEVEL OF PROFESSIONAL ENGINEER ENGINEERS AUSTRALIA ACCREDITATION BOARD ACCREDITATION MANAGEMENT SYSTEM EDUCATION PROGRAMS AT THE LEVEL OF PROFESSIONAL ENGINEER Document No. Title P05PE Australian Engineering Stage 1 Competency Standards

More information

Risk Assessment Techniques

Risk Assessment Techniques This article was downloaded by: [Stephen N. Luko] On: 27 May 2014, At: 08:21 Publisher: Taylor & Francis Informa Ltd Registered in England and Wales Registered Number: 1072954 Registered office: Mortimer

More information

March Contents. Shrinkage Incentive Methodology Statement Review. UK Gas Transmission

March Contents. Shrinkage Incentive Methodology Statement Review. UK Gas Transmission March 2016 Contents ef Shrinkage Incentive Methodology Statement Review UK Gas Transmission 6 Contents 1 Executive Summary... 3 2 Background... 5 2.1 Introduction... 5 2.2 Overview of NTS Shrinkage...

More information

DMSMS Lifetime Buy Characterization Via Data Mining of Historical Buys

DMSMS Lifetime Buy Characterization Via Data Mining of Historical Buys P. Sandborn, V. Prabhakar, and D. Feng, "DMSMS Lifetime Buy Characterization Via Data Mining of Historical Buys," Proceedings DMSMS Conference, Orlando, FL, November 2007. DMSMS Lifetime Buy Characterization

More information

Issues in Strategic Decision Modelling

Issues in Strategic Decision Modelling Issues in Strategic Decision Modelling Paula Jennings BDO Stoy Hayward 8 Baker Street LONDON W1U 3LL ABSTRACT Models are invaluable tools for strategic planning. Models help key decision makers develop

More information

A Parametric Approach to Project Cost Risk Analysis

A Parametric Approach to Project Cost Risk Analysis A Parametric Approach to Project Cost Risk Analysis By Evin Stump Senior Systems Engineer Galorath Incorporated Preface Risk arises when the assignment of the probability of an event is statistically possible

More information

The challenge of forecasting the cost of complex military, aerospace and weapons projects

The challenge of forecasting the cost of complex military, aerospace and weapons projects The challenge of forecasting the cost of complex military, aerospace and weapons projects Dale Shermon, QinetiQ Fellow / Head of Profession - Cost 1 1 QinetiQ Bristol, Building 240, The Close, Bristol

More information

ASSESSING THE TRADEOFF BETWEEN COST AND AVAILABILITY USING SIMULATION

ASSESSING THE TRADEOFF BETWEEN COST AND AVAILABILITY USING SIMULATION 2017 NDIA GROUND VEHICLE SYSTEMS ENGINEERING AND TECHNOLOGY SYMPOSIUM SYSTEMS ENGINEERING (SE) TECHNICAL SESSION AUGUST 8-10, 2017 NOVI, MICHIGAN ASSESSING THE TRADEOFF BETWEEN COST AND AVAILABILITY USING

More information

Cycle Time Forecasting. Fast #NoEstimate Forecasting

Cycle Time Forecasting. Fast #NoEstimate Forecasting Cycle Time Forecasting Fast #NoEstimate Forecasting 15 th August 2013 Forecasts are attempts to answer questions about future events $1,234,000 Staff 2 Commercial in confidence We estimated every task

More information

Risk Mitigation: Some Good News after the Cost / Schedule Risk Analysis Results

Risk Mitigation: Some Good News after the Cost / Schedule Risk Analysis Results Risk Mitigation: Some Good News after the Cost / Schedule Risk Analysis Results David T. Hulett, Ph.D. Hulett & Associates, LLC ICEAA Professional Development and Training Workshop San Diego, CA June 9-12,

More information

The 7 th International Scientific Conference DEFENSE RESOURCES MANAGEMENT IN THE 21st CENTURY Braşov, November 15 th 2012

The 7 th International Scientific Conference DEFENSE RESOURCES MANAGEMENT IN THE 21st CENTURY Braşov, November 15 th 2012 The 7 th International Scientific Conference DEFENSE RESOURCES MANAGEMENT IN THE 21st CENTURY Braşov, November 15 th 2012 Tudorel SLAVULETE Logistics Directorate/Romanian General STAFF Abstract Top managers

More information

The Mathematics of Material Quality Control

The Mathematics of Material Quality Control The Mathematics of Material Quality Control Scenario You are working in a materials testing laboratory with specific responsibility for testing and monitoring the strength of concrete specimens as they

More information

CHAPTER 2 BACKGROUND INFORMATION AND THEORITICAL FOUNDATION

CHAPTER 2 BACKGROUND INFORMATION AND THEORITICAL FOUNDATION CHAPTER 2 BACKGROUND INFORMATION AND THEORITICAL FOUNDATION Recently, the demand of electricity is increasing quite fast, where it can be seen from the Waktu Beban Puncak (WBP) that is high. The difference

More information

PERCEPTION AND MANAGEMENT OF RISK IN HYDROPOWER PROJECTS

PERCEPTION AND MANAGEMENT OF RISK IN HYDROPOWER PROJECTS International Conference on Hydropower for Sustainable Development Feb 05-07, 2015, Dehradun PERCEPTION AND MANAGEMENT OF RISK IN HYDROPOWER PROJECTS G.P. Patel Managing Director UJVN Limited gppatel@ujvnl.com

More information

Project Risk Management

Project Risk Management Hujambo (Swahili) Project Management Process Groups Initiating Planning Executing Monitoring & Controlling Closing Project 4. Integration Management 5. Scope Knowledge Areas 6. Time 7. Cost 8. Quality

More information

ANALYSIS OF PARAMETRIC AND DATABASE DRIVEN COST ESTIMATES IN THE TRANSIT INDUSTRY

ANALYSIS OF PARAMETRIC AND DATABASE DRIVEN COST ESTIMATES IN THE TRANSIT INDUSTRY ANALYSIS OF PARAMETRIC AND DATABASE DRIVEN COST ESTIMATES IN THE TRANSIT INDUSTRY L. Brian Ehrler Project Management Oversight Cost and Risk Manager Burns Engineering, Inc. 4925 Greenville Ave Dallas,

More information

SYSTEMATIC APPROACH FOR DECOMMISSIONING PLANNING AND ESTIMATING

SYSTEMATIC APPROACH FOR DECOMMISSIONING PLANNING AND ESTIMATING ABSTRACT SYSTEMATIC APPROACH FOR DECOMMISSIONING PLANNING AND ESTIMATING A. Scott Dam, P. E. JUPITER Corporation 2730 University Boulevard West, Suite 900 Wheaton, MD 20702 Nuclear facility decommissioning,

More information

Techniques and Simulation Models in Risk Management

Techniques and Simulation Models in Risk Management Techniques and Simulation Models in Risk Management Mirela GHEORGHE 1 ABSTRACT In the present paper, the scientific approach of the research starts from the theoretical framework of the simulation concept

More information

Cost of Software Obsolescence Resolution

Cost of Software Obsolescence Resolution Cost of Software Obsolescence Resolution S Rajagopal- QinetiQ Fellow Estimating Manager- Cyber, Information and Training 13 th June 2018 ICEAA Professional Development & Training Workshop QINETIQ/EMEA/EO/PUB170141

More information

EST Accuracy of FEL 2 Estimates in Process Plants

EST Accuracy of FEL 2 Estimates in Process Plants EST.2215 Accuracy of FEL 2 Estimates in Process Plants Melissa C. Matthews Abstract Estimators use a variety of practices to determine the cost of capital projects at the end of the select stage when only

More information

Value Stream Analysis of Manufacturing Engineering New Product Introduction Processes

Value Stream Analysis of Manufacturing Engineering New Product Introduction Processes Value Stream Analysis of Manufacturing Engineering New Product Introduction Processes Malachy Maginness a,, Essam Shehab b,1 and Chris Beadle c a, b Decision Engineering Centre, Manufacturing Department,

More information

A Comprehensive Evaluation of Regression Uncertainty and the Effect of Sample Size on the AHRI-540 Method of Compressor Performance Representation

A Comprehensive Evaluation of Regression Uncertainty and the Effect of Sample Size on the AHRI-540 Method of Compressor Performance Representation Purdue University Purdue e-pubs International Compressor Engineering Conference School of Mechanical Engineering 2016 A Comprehensive Evaluation of Regression Uncertainty and the Effect of Sample Size

More information

Project Planning & Management. Lecture 11 Project Risk Management

Project Planning & Management. Lecture 11 Project Risk Management Lecture 11 Project Risk Management The Importance of Project Risk Management PMBOK definition of Project Risk An uncertain event or condition that, if it occurs, has a positive or negative effect on the

More information

HOT Logistic Support Analysis

HOT Logistic Support Analysis HOT Logistic Support Analysis C Taljaard R&M Technologies CC Mobile: +27 (0)82 4523254 Copyright 2013 by C Taljaard. Published and used by INCOSE SA with permission Abstract: The logistic support analysis,

More information

Need for Affordability Analysis in Systems Engineering

Need for Affordability Analysis in Systems Engineering Need for Affordability Analysis in Systems Engineering 24 June 2009 Mark Schankman Associate Technical Fellow Affordability Strategic Projects & Analysis Boeing Research & Technology 314-232-6279 mark.s.schankman@boeing.com

More information

Review: Simple schedule risk modelling with Safran Risk

Review: Simple schedule risk modelling with Safran Risk Creating value from uncertainty Broadleaf Capital International Pty Ltd ABN 24 054 021 117 www.broadleaf.com.au Review: Simple schedule risk modelling with Safran Risk With a view to exploring alternative

More information

EVALUATING CAPACITY AND EXPANSION OPPORTUNITIES AT TANK FARM: A DECISION SUPPORT SYSTEM USING DISCRETE EVENT SIMULATION

EVALUATING CAPACITY AND EXPANSION OPPORTUNITIES AT TANK FARM: A DECISION SUPPORT SYSTEM USING DISCRETE EVENT SIMULATION Proceedings of the 2009 Winter Simulation Conference M. D. Rossetti, R. R. Hill, B. Johansson, A. Dunkin and R. G. Ingalls, eds. EVALUATING CAPACITY AND EXPANSION OPPORTUNITIES AT TANK FARM: A DECISION

More information

Arke Ltd. MOSAIC (Modular Open System Architectures Integrated Cost model)

Arke Ltd. MOSAIC (Modular Open System Architectures Integrated Cost model) Arke Ltd MOSAIC (Modular Open System Architectures Integrated Cost model) Open Systems: Background Open Systems: Wider Viewpoint OSA Framework and MOSAIC Introduction MOSAIC usage context MOSAIC Walkthrough

More information

Identify Risks. 3. Emergent Identification: There should be provision to identify risks at any time during the project.

Identify Risks. 3. Emergent Identification: There should be provision to identify risks at any time during the project. Purpose and Objectives of the Identify Risks Process The purpose of the Identify Risks process is to identify all the knowable risks to project objectives to the maximum extent possible. This is an iterative

More information

US climate change impacts from the PAGE2002 integrated assessment model used in the Stern report

US climate change impacts from the PAGE2002 integrated assessment model used in the Stern report Page 1 of 54 16 November 27 US climate change impacts from the PAGE22 integrated assessment model used in the Stern report Chris Hope & Stephan Alberth Judge Business School, University of Cambridge, UK

More information

Predicting Over Target Baselines (OTBs) 1

Predicting Over Target Baselines (OTBs) 1 2010, Issue 4 The Magazine of the Project Management Institute s College of Performance Management Predicting Over Target Baselines (OTBs) 1 By Kristine Thickstun, MBA, MS, and Dr. Edward D. White Stick

More information

A cost capability maturity analysis of the US and European costing communities

A cost capability maturity analysis of the US and European costing communities A cost capability maturity analysis of the US and European costing communities by Mark Gilmour and Dale Shermon, QinetiQ mwgilmour@qinetiq.com dshermon@qinetiq.com Abstract - High quality cost estimating

More information

Simulation of fruit pallet movement in the port of Durban: A case study

Simulation of fruit pallet movement in the port of Durban: A case study Volume 21 (1), pp. 63 75 http://www.orssa.org.za ORiON ISSN 0529-191-X c 2005 Simulation of fruit pallet movement in the port of Durban: A case study J Bekker M Mostert FE van Dyk Received: 1 February

More information

Topic title/heading. Definition

Topic title/heading. Definition Topic title/heading 3.5.2 Risk techniques Definition No more than a few sentences required approximately 30 words. It should be succinct, and wherever possible, independent of the level of project/programme/portfolio

More information

DETERMINING A DYNAMIC MAINTENANCE THRESHOLD USING MAINTENANCE OPTIONS

DETERMINING A DYNAMIC MAINTENANCE THRESHOLD USING MAINTENANCE OPTIONS DETERMINING A DYNAMIC MAINTENANCE THRESHOLD USING MAINTENANCE OPTIONS Gilbert Haddad a, Peter Sandborn a, and Michael Pecht a,b a Center for Advanced Life Cycle Engineering (CALCE), University of Maryland,

More information

Introduction to Project Management

Introduction to Project Management Introduction to Project Management 600-101 INTRODUCTION Enterprise Consultants International, Ltd. Enterprise Consultants International, Ltd. INTRODUCTION Large projects in the oil and gas industry create

More information

Use of ISO measurement uncertainty guidelines to determine uncertainties in noise & vibration predictions and design risks

Use of ISO measurement uncertainty guidelines to determine uncertainties in noise & vibration predictions and design risks Use of ISO measurement uncertainty guidelines to determine uncertainties in noise & vibration predictions and design risks P. Karantonis, C. Weber Renzo Tonin & Associates, Surry Hills, NSW, Australia

More information

Risk Management User Guide

Risk Management User Guide Risk Management User Guide Version 17 December 2017 Contents About This Guide... 5 Risk Overview... 5 Creating Projects for Risk Management... 5 Project Templates Overview... 5 Add a Project Template...

More information

Introduction to Business Research 3

Introduction to Business Research 3 Synopsis Introduction to Business Research 3 1. Orientation By the time the candidate has completed this module, he or she should understand: what has to be submitted for the viva voce examination; what

More information

Decision Making Delays with Regard to IT Investments

Decision Making Delays with Regard to IT Investments Available online at www.sciencedirect.com Procedia - Social and Behavioral Sciences 40 ( 2012 ) 258 263 2012 International Conference of Asia Pacific Business Innovation and Technology Management Decision

More information

TAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH

TAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH TAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH Chris Rolison CEO, Comply Serve Limited The Collaborative Systems Engineering Approach Collaboration A system

More information

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A

Deltek Acumen 7/15/16. Learning Objectives. Introduction to Project Risk Analysis. Planning, Risk, Acceleration. The 5 steps. Worked examples Q&A Deltek Acumen Planning, Risk, Acceleration Tom Polen Director, Solution Architecture Learning Objectives The 5 steps 1. Capturing uncertainty: calibrating the schedule 2. Identifying risk events: accounting

More information

Advantages and Disadvantages of. Independent Tests. Advantages. Disadvantages

Advantages and Disadvantages of. Independent Tests. Advantages. Disadvantages 8.0 Test Management Outline 8.1 Test organisation 8.2 Test planning and estimation 8.3 Test program monitoring and control 8.4 Configuration management 8.5 Risk and testing 8.6 Summary Independent Testing

More information

AGENCY FOR STATE TECHNOLOGY

AGENCY FOR STATE TECHNOLOGY AGENCY FOR STATE TECHNOLOGY PROJECT RISK & COMPLEXITY ASSESSMENT TOOL Risk & Complexity Assessment Model for State Information Technology Projects Purpose: In order to determine the level of risk associated

More information

Lean Aerospace Initiative Annual Symposium

Lean Aerospace Initiative Annual Symposium Lean Aerospace Initiative Annual Symposium Improving Avionics Affordability Through Product Development Jeremy Tondreault MIT System Design and Management Program 01 jeremy.p.tondreault@baesystems.com

More information

North European Functional Airspace Block Avinor, Norway EANS, Estonia Finavia, Finland LGS, Latvia. NEFAB Project SAFETY CASE REPORT. Version 3.

North European Functional Airspace Block Avinor, Norway EANS, Estonia Finavia, Finland LGS, Latvia. NEFAB Project SAFETY CASE REPORT. Version 3. NEFAB Project SAFETY CASE REPORT Version 3.01 Page 1 of 40 Revision history Version Date Description Approved 3.0 3.01 14/12/2011 Page 2 of 40 TABLE OF CONTENTS 1. INTRODUCTION... 4 1.1. AIM... 4 1.2.

More information

TIMEBOXING PLANNING: BUFFERED MOSCOW RULES

TIMEBOXING PLANNING: BUFFERED MOSCOW RULES TIMEBOXING PLANNING: BUFFERED MOSCOW RULES EDUARDO MIRANDA, INSTITUTE FOR SOFTWARE RESEARCH, CARNEGIE MELLON UNIVERSITY, SEPTEMBER 2011 ABSTRACT Time boxing is a management technique which prioritizes

More information

Managing Volatility. Risk in mining investment decisions. Managing Volatility

Managing Volatility. Risk in mining investment decisions. Managing Volatility Managing Volatility Risk in mining investment decisions Managing Volatility Previous page Contents page Next page Contents Managing volatility risk in mining investment decisions Introduction 2 Can your

More information

Masters in Business Statistics (MBS) /2015. Department of Mathematics Faculty of Engineering University of Moratuwa Moratuwa. Web:

Masters in Business Statistics (MBS) /2015. Department of Mathematics Faculty of Engineering University of Moratuwa Moratuwa. Web: Masters in Business Statistics (MBS) - 2014/2015 Department of Mathematics Faculty of Engineering University of Moratuwa Moratuwa Web: www.mrt.ac.lk Course Coordinator: Prof. T S G Peiris Prof. in Applied

More information

GEOTHERMAL RESOURCE ASSESSMENT CASE EXAMPLE, OLKARIA I

GEOTHERMAL RESOURCE ASSESSMENT CASE EXAMPLE, OLKARIA I Presented at Short Course II on Surface Exploration for Geothermal Resources, organized by UNU-GTP and KenGen, at Lake Naivasha, Kenya, 2-17 November, 2007. GEOTHERMAL TRAINING PROGRAMME Kenya Electricity

More information

Benefits of Integrating Schedule

Benefits of Integrating Schedule Benefits of Integrating Schedule and Cost Risk Analysis Rafael Hartke Oil and Energy Industry Consultant About me... Rafael Hartke Education B.Sc., M.Sc. in Mechanical Engineering MBA in Finance, Investment

More information

Using PHM to Meet Availability-Based Contracting Requirements

Using PHM to Meet Availability-Based Contracting Requirements Using PHM to Meet Availability-Based Contracting Requirements Taoufik Jazouli and Peter Sandborn CALCE Center for Advanced Life Cycle Engineering Department of Mechanical Engineering University of Maryland,

More information

When Information Flow in Project Organizations Becomes Turbulent: Toward an Organizational "Reynolds Number"

When Information Flow in Project Organizations Becomes Turbulent: Toward an Organizational Reynolds Number S U R J When Information Flow in Project Organizations Becomes Turbulent: Toward an Organizational "Reynolds Number" Michael Fyall When managers try to develop complex products with many interdependent

More information

Revision confidence limits for recent data on trend levels, trend growth rates and seasonally adjusted levels

Revision confidence limits for recent data on trend levels, trend growth rates and seasonally adjusted levels W O R K I N G P A P E R S A N D S T U D I E S ISSN 1725-4825 Revision confidence limits for recent data on trend levels, trend growth rates and seasonally adjusted levels Conference on seasonality, seasonal

More information

Introduction to Analytics Tools Data Models Problem solving with analytics

Introduction to Analytics Tools Data Models Problem solving with analytics Introduction to Analytics Tools Data Models Problem solving with analytics Analytics is the use of: data, information technology, statistical analysis, quantitative methods, and mathematical or computer-based

More information

Yield Frontier Analysis of Forest Inventory

Yield Frontier Analysis of Forest Inventory Yield Frontier Analysis of Forest Inventory S.A. Mitchell & K. Kim Department of Engineering Science University of Auckland New Zealand s.mitchell@auckland.ac.nz Abstract Standing inventory analysis allows

More information

Design of Experiments for Processes Reliability Management

Design of Experiments for Processes Reliability Management 10 th International Symposium Topical Problems in the Field of Electrical and Power Engineering Pärnu, Estonia, January 10-15, 2011 Design of Experiments for Processes Reliability Management Marina Pribytkova,

More information

Simulation Analytics

Simulation Analytics Simulation Analytics Powerful Techniques for Generating Additional Insights Mark Peco, CBIP mark.peco@gmail.com Objectives Basic capabilities of computer simulation Categories of simulation techniques

More information

Agile Software Development Cost Risk for Information Technology Programs

Agile Software Development Cost Risk for Information Technology Programs Agile Software Development Cost Risk for Information Technology Programs Today s Presenter John McCrillis John McCrillis has been working hardware and software cost estimating for 18 years as an operations

More information

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol The following presentation was given at: SCAF Workshop Integrated Cost and Schedule Risk Analysis Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol Released for distribution by the Author www.scaf.org.uk/library

More information

F a i r f i e l d, Ohio and Dennis J. C a r r. Fernald Environmental R e s t o r a t i o n Management Corporation with

F a i r f i e l d, Ohio and Dennis J. C a r r. Fernald Environmental R e s t o r a t i o n Management Corporation with COST ESTIMATING FOR CERCLA REMEDIAL ALTERNATIVES A UNIT COST METHODOLOGY Richard W B r e t t i n PARSONS Environmental R e m e d i a l A c t i o n P r o j e c t F a i r f i e l d, Ohio 45014 and Dennis

More information

TAGUCHI APPROACH TO DESIGN OPTIMIZATION FOR QUALITY AND COST: AN OVERVIEW. Resit Unal. Edwin B. Dean

TAGUCHI APPROACH TO DESIGN OPTIMIZATION FOR QUALITY AND COST: AN OVERVIEW. Resit Unal. Edwin B. Dean TAGUCHI APPROACH TO DESIGN OPTIMIZATION FOR QUALITY AND COST: AN OVERVIEW Resit Unal Edwin B. Dean INTRODUCTION Calibrations to existing cost of doing business in space indicate that to establish human

More information

PLANNING FOR PRODUCTION

PLANNING FOR PRODUCTION PLANNING FOR PRODUCTION Forecasting Forecasting is the first major activity in the planning, involving careful study of past data and present scenario to estimate the occurence, timing or magnitude of

More information

Principles of Verification, Validation, Quality Assurance, and Certification of M&S Applications

Principles of Verification, Validation, Quality Assurance, and Certification of M&S Applications Introduction to Modeling and Simulation Principles of Verification, Validation, Quality Assurance, and Certification of M&S Applications OSMAN BALCI Professor Copyright Osman Balci Department of Computer

More information

Methodology for risk management in systems development

Methodology for risk management in systems development Methodology for risk management in systems development Vrassidas LEOPOULOS Mechanical Engineer Dpt National Technical University of Athens Iroon Polytechniou 9 GREECE Konstantinos KIRYTOPOULOS Mechanical

More information

Reliability Engineering & Asset Management (REAM) IMechE Accredited CPD Courses

Reliability Engineering & Asset Management (REAM) IMechE Accredited CPD Courses Reliability Engineering & Asset Management (REAM) IMechE Accredited CPD Courses Prof Jyoti Sinha CEng, FIMechE Programme Director, REAM Head Dynamics Laboratory The University of Manchester has been delivering

More information

Presented at the 2008 SCEA-ISPA Joint Annual Conference and Training Workshop -

Presented at the 2008 SCEA-ISPA Joint Annual Conference and Training Workshop - DEVELOPMENT AND PRODUCTION COST EQUATIONS DERIVED FROM PRICE-H TO ENABLE RAPID AIRCRAFT (MDO) TRADE STUDIES 2008 Society Cost Estimating Analysis (SCEA) Conference W. Thomas Harwick, Engineering Specialist

More information

Cost Engineering Health Check - a limited survey. Prepared by QinetiQ. For Society for Cost Analysis and Forecasting (SCAF)

Cost Engineering Health Check - a limited survey. Prepared by QinetiQ. For Society for Cost Analysis and Forecasting (SCAF) Cost Engineering Health Check - a limited survey Prepared by QinetiQ For Society for Cost Analysis and Forecasting (SCAF) QINETIQ/TIS/S&AS/IP1203326 ver. 1.0 10th December 2012 Copyright QinetiQ 2012 Page

More information

Probabilistic approach for predicting life cycle costs and performance of buildings and civil infrastructure

Probabilistic approach for predicting life cycle costs and performance of buildings and civil infrastructure Probabilistic approach for predicting life cycle costs and performance of buildings and civil infrastructure Phil BAMFORTH Principal Consultant Taylor Woodrow Leighton Buzzard, UK Phil.bamforth@uk.taylorwood

More information

A Genetic Algorithm Applying Single Point Crossover and Uniform Mutation to Minimize Uncertainty in Production Cost

A Genetic Algorithm Applying Single Point Crossover and Uniform Mutation to Minimize Uncertainty in Production Cost World Applied Sciences Journal 23 (8): 1013-1017, 2013 ISSN 1818-4952 IDOSI Publications, 2013 DOI: 10.5829/idosi.wasj.2013.23.08.956 A Genetic Algorithm Applying Single Point Crossover and Uniform Mutation

More information

PROJECT TIME MANAGEMENT

PROJECT TIME MANAGEMENT PROJECT TIME MANAGEMENT ESTIMATE ACTIVITY DURATION PLANNING MONITORING & CONTROLLING 6.1 Plan Schedule Mgt 6.7 Control Schedule 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources

More information

TenStep Project Management Process Summary

TenStep Project Management Process Summary TenStep Project Management Process Summary Project management refers to the definition and planning, and then the subsequent management, control, and conclusion of a project. It is important to recognize

More information

Why Does It Cost How Much? Edwin B. Dean * NASA Langley Research Center Hampton VA

Why Does It Cost How Much? Edwin B. Dean * NASA Langley Research Center Hampton VA Why Does It Cost How Much? Edwin B. Dean * NASA Langley Research Center Hampton VA Abstract There is great concern for the competitiveness of the aerospace industry today. This paper examines the concept

More information

91 محرم الصفحة. Industrial Engineering Standards. Professional Engineer Exam Ι

91 محرم الصفحة. Industrial Engineering Standards. Professional Engineer Exam Ι Industrial Engineering Standards 1 الصفحة Introduction Engineering standards are the set of knowledge, abilities, and professional attributes necessary to practice the engineering profession [3-5]. Every

More information

Reliance on and Reliability of the Engineer s Estimate in Heavy Civil Projects

Reliance on and Reliability of the Engineer s Estimate in Heavy Civil Projects Construction Economics and Building Vol. 17, No. 2 June 2017 VIEWPOINT Reliance on and Reliability of the Engineer s Estimate in Heavy Civil Projects George Okere School of Design and Construction, Washington

More information

Selection and Deployment of a Standard COTS Monte Carlo Software Tool November 18, 2009

Selection and Deployment of a Standard COTS Monte Carlo Software Tool November 18, 2009 Selection and Deployment of a Standard COTS Monte Carlo Software Tool November 18, 2009 Presenter: Fred Oleson (Systems Engineering) Contributors: Carole Doan, Debra Buswell BAE Systems, USCS: 1 Agenda

More information

THE TRUE VALUE OF PROJECT RISK ANALYSIS

THE TRUE VALUE OF PROJECT RISK ANALYSIS THE TRUE VALUE OF PROJECT RISK ANALYSIS Dr. Dan Patterson, PMP Chief Design Officer, PLANNING & SCHEDULING Introduction Much has been written in recent years about the benefits of conducting a project

More information

Minimising Material Waste by Utilising BIM and Set-based Design in the Structural Design of Reinforced Concrete Slabs

Minimising Material Waste by Utilising BIM and Set-based Design in the Structural Design of Reinforced Concrete Slabs Minimising Material Waste by Utilising BIM and Set-based Design in the Structural Design of Reinforced Concrete Slabs Abstract Considering the significant amount of material wasted in the construction

More information