ANALYSIS OF PARAMETRIC AND DATABASE DRIVEN COST ESTIMATES IN THE TRANSIT INDUSTRY

Size: px
Start display at page:

Download "ANALYSIS OF PARAMETRIC AND DATABASE DRIVEN COST ESTIMATES IN THE TRANSIT INDUSTRY"

Transcription

1 ANALYSIS OF PARAMETRIC AND DATABASE DRIVEN COST ESTIMATES IN THE TRANSIT INDUSTRY L. Brian Ehrler Project Management Oversight Cost and Risk Manager Burns Engineering, Inc Greenville Ave Dallas, TX 75206

2 ABSTRACT Most major transit projects require some form of grant, either Federal or State, to be financially viable for a city. For those cities considering a transit project there are billions of dollars available each year from the US Department of Transportation. 1 However, to qualify for these dollars the transit agency for the city, must demonstrate that the proposed transit project is cost effective. This qualification requires transit agencies to prepare a cost estimate during the conceptual phase of the project. Because of limited budgets in the early phases of these projects, the transit agencies generally rely on parametric and/or unit cost database cost estimating methodologies. For the transit agencies this is an advantage because a cost estimate can be produced efficiently with minimal cost. For the Federal Transit Administration s Consultant the review and analysis of parametric and unit cost database estimates can sometimes be a challenge. The review and corroboration process for these early phase estimates relies on a number of mechanical tests, mathematical skills, and expert opinions to insure the proposed cost for the project is accurate, comprehensive, and traceable. This paper explores the FTA consultant s challenges of working with the limited output from the transit agency s proprietary cost database and/or parametric systems. Additionally, this paper will demonstrate a number of the consultant s means, methods, and outputs through case study examples. 1 The US Department of Transportation issues grants to cities and municipalities, each year, for public transit initiatives. The FY 2011 President s Budget indicates $1.822 billion will be available this year for transit projects. Pageii

3 Pageiii

4 INTRODUCTION Most major transit projects require some form of grant, either Federal or State, to be financially viable for a city. For those cities considering a transit project there are billions of dollars available each year from the US Department of Transportation. However, to qualify for these dollars the city s transit agency must demonstrate that the proposed transit project is cost effective. Once a transit agency requests a grant the Federal Transit Administration begins the project review process. This process generally involves Project Management Oversight Contractor to perform the technical aspects of the project review. BACKGROUND FEDERAL TRANSIT ADMINISTRATION (FTA) PROJECT COST REVIEW The U.S. Congress and the Federal Transit Administration (FTA) enacting good stewardship require that a Grantee cost estimate for a proposed project is reliable. This reliability measurement is achieved through a thorough evaluation of the project scope, project schedule and project cost estimate, at various points in the proposed project s development (Federal Transit Administration, 2009). The FTA developed means and methods, commonly referred to as the Oversight Procedures, to determine cost estimate reliability. The objectives of the oversight procedures are three fold: Determine the consistency of the project cost estimate information Understand the cost estimate characteristics Confirm that the estimate adequately reflects the overall project scope These objectives are achieved by the FTA through the use of contracted technical consultants, commonly known as a Project Management Oversight Contractor (PMOC) (Federal Transit Administration, 2009). FTA TRANSIT PROJECT DEVELOPMENT PROCESS The FTA charges the PMOC to perform periodic reviews of selected projects at each major milestones, (1) Start of Preliminary Engineering, (3) Start of Final Design, and (3) Full Funding Grant Agreement application, and (4) Start of Construction. The results of these reviews are used by FTA in its decision making process to determine the grant funding eligibility for the project (see Figure 1). Page1

5 Figure 1 FTA New Starts Project Process (Federal Transit Administration, 2003) At each milestone the PMOC is responsible for analyzing the project cost estimate and reporting findings back to the FTA regarding: Page2

6 Soundness of the Grantee s cost estimating methods and processes compared with proven professional quantity surveying and cost estimating practices for projects of this scale; Congruence of the project cost estimate with the project scope and schedule, i.e. do these three elements fully reflect each other Figure 2; Reliability of the estimate for procurements, contract bids, and contract closeout, i.e. will the project budget prove to be adequate at these milestone events. Figure 2 Modified Triple Constraint Scope, Cost, Schedule relationship The constraints between the project cost to the scope and schedule (sometimes referred to as the Triple Constraint) is an important concept for any cost reviewer to understand (Project Management Institute, 2008). The traditional concept of the Triple Constraint indicated that changes to any of the three elements affected the other two. Logically this does not always bear out, as one could, in theory, pay too much for a material element which increases the cost, but does not change the schedule or change the scope. In most cases a change in either scope of schedule will change the cost, but the converse is not always true. The concept of the Scope Schedule Cost and the Scope Cost linkages are the basis for the FTA review process. DATA INPUTS Page3

7 FTA project grantees are required to develop and submit several documents to communicate the characteristics of proposed projects. The project cost estimate information is conveyed primarily by 3 documents: Standard Cost Category (SCC) Workbook Cost Estimate Data for SCC costs Basis of Estimate Report / Memo These cost estimate documents are compared, by the PMOC, with other project documents such as design reports, specifications and drawings to determine the accuracy and precision of the project costs. STANDARD COST CATEGORY WORKBOOK The FTA provides a structured format for grantees to submit project cost data known as the Standard Cost Category (SCC) workbook. The SCC format was implemented by FTA in 2005 to provide a consistent format for reporting estimated project costs (Federal Transit Administration, 2010b). The SCC format is a basic cost element structure (CES) comprised of ten primary cost categories, which are divided into additional sub categories (see Figure 3). Guideway and Track Elements Stations, Stops, Terminals Support Facilities Sitework and Special Conditions Systems Right of Way (ROW) Vehicles Professional Services Contingency Project Finance Cost Page4

8 Figure 3 SCC Workbook (Federal Transit Administration, 2010b). This reporting format has its limitations; however it provides a level of consistency in the cost estimating data submitted to FTA. BASIS OF ESTIMATE The FTA suggests that grantees provide a written basis of estimate (BOE), additionally FTA provides a suggested format for this information (See: Appendix C: Grantee s Memo Regarding Cost Estimating Methods). The FTA basis of estimate suggestions misses the mark as the suggestions do not require the level of detail needed to analyze the project cost estimate. The BOE document should be a thorough detailed document that communicates the inner working of the cost estimate to such a degree that a third party could recreate the costs. Many experienced grantees go beyond the FTA Cost Basis Memo suggestions and provide supplemental information or formal BOE report outlining the cost estimate details. These grantees understand that providing detailed basis documents communicates information to the PMOC to draw conclusions from and leaves little room for assumptions and misinterpretations. Page5

9 MEANS AND METHODS The means and methods for determining the validity of a cost estimate and providing data to FTA so an informed decision can be made regarding the project are comprised of several discrete steps outlined in Figure 4 below. Figure 4 PMOC Estimate Validation Process Map ESTIMATE CLASSIFICATION The project cost estimate is classified by the PMOC to determine the type of estimate (parametric, unit cost database, analogous, bottom up, etc.) and the means and methods used to calculate the costs. The PMOC analyzes the project cost submittals, such as, SCC workbook, cost basis, and cost estimating methodology, to determine the type of the cost estimation techniques employed. Many cost estimates developed in the early stages of transit projects are submitted for review, characterized as parametric estimates (i.e. developed using parametric methodologies), by the project grantee. However, during the initial classification of the estimate data, the cost estimates are determined to originate from analogous methodologies. Page6

10 The result of the classification process yields the estimating methodologies used as one or a combination of the following: (1) Parametric, (2) Unit Cost Database, (3) Analogous, and (4) Bottom Up. The information gained from the estimate classification is used by the PMOC to determine the most effective review method and in the development of a sampling plan for the cost estimate elements. MECHANICAL CORRECTNESS The submitted cost estimates are subjected to several mechanical tests to determine the level of accuracy. The mechanical check is a basic mathematical review of the dollar figures presented to determine: Mathematical correctness in extended costs (e.g. 4 units at $100 each is totaled to $400). All dollar values are correctly transferred from estimate basis documents to FTA Standard Cost Categories. Electronic cost estimate basis document and SCC workbook are formulaically correct. The mechanical correctness check tests the most basic of cost estimation skills, where one would expect to find few if any errors. However, transit project estimates are generally complex and compiled from the work of several estimators of differing disciplines, which increases the opportunity for simple errors to occur. RECONCILIATION OF COST DATA During the mechanical correctness check the PMOC will reconcile the SCC workbook and the cost estimate basis data to insure traceability. This reconciliation exercise is important as the FTA recognizes the SCC workbook as the official project cost submittal. Thus the SCC workbook should accurately represent all of the expected costs to complete the project. ESTIMATE CHARACTERIZATION Once the type of estimate has been determined the estimate is divided into levels [FTA s terminology] and the individual costs are characterized by sub type. This characterization process allows the PMOC to determine the degree of cost estimating effort expended by the grantee and the level of detail in the cost estimate basis. The FTA method uses a series of levels which, in essence, creates a matrix of cost sources based on the SCC workbook. Vertical elements of the matrix are the traced source of the cost such as design drawings, specifications, project schedule, and contingency. The horizontal elements of Page7

11 the matrix characterize the cost estimate line item calculation methods such as, bottom up unit cost, cost database, cost estimating relationship (CER), and allowances. Table 1 Primary characterization matrix (cost by source document) Drawings / Specifications Design Report Schedule (escalation) Contingencies TOTAL Bottom Up Unit Cost Unit Cost Database CER Allowance TOTAL The estimate characterization matrix elements are purposely sequenced in a specific order both horizontally and vertically. This ordering facilitates a cursory risk rating for the estimated aggregate costs. The area of highest risk is on the lower right, the area of lowest risk is on the upper left. Table 2 Primary characterization matrix (cost by source document) Drawings / Specifications Bottom Up Unit Cost Lowest Risk Unit Cost Database CER Allowance Design Report Schedule (escalation) Contingencies Highest Risk Complex estimates are sometimes re characterized into a secondary format which indicates the source of costs by type. This secondary characterization is most often used when comparing a contractor s cost estimate to an established project budget. Page8

12 Table 3 Secondary characterization matrix (cost by type) Direct Costs Indirect Costs Contingencies Escalation Inflation Markups (OH+P) TOTAL Bottom Up Unit Cost Unit Cost Database CER Allowance TOTAL Hybrid characterizations of project cost estimates are also common, as estimate submittals, may have complex detailed sections for near term activities, and sparsely detailed sections for long term activities. EXAMPLE CHARACTERIZATION The sample data is from a project in the later phases of alternative analysis, where very few drawings existed and the estimate data was formulated from a unit cost database. Table 4 Sample Estimate Characterization Name Bottom Up Unit Cost CER Allowance TOTAL Unit Cost Database Utility Relocation (UTL) $6,041,200 $26,100,606 $32,141,806 Drawings / Specifications Design Report / EIS $19,178,412 $19,178,412 Indirect Costs $6,922,194 $6,922,194 Contingencies $6,041,200 $6,041,200 Street Construction (STR) $35,139,373 $8,806,709 $10,035,747 $53,981,828 Drawings / Specifications Design Report / EIS $26,096,306 $7,453,062 $33,549,367 Indirect Costs $9,043,067 $2,582,685 $11,625,752 Contingencies $8,806,709 $8,806,709 Track Grade Construction (GRD) $30,586,940 $6,058,377 $490,264 $37,135,581 Drawings / Specifications Design Report / EIS $22,715,435 $364,095 $23,079,530 Indirect Costs $7,871,505 $126,169 $7,997,674 Contingencies $6,058,377 $6,058,377 As individual characterized cost components this data is of limited use beyond cost traceability. When the data is aggregated into a summary table the level of estimating effort becomes apparent. Page9

13 Name Bottom Up Unit Cost CER Allowance TOTAL Unit Cost Database Totals $0 $65,726,313 $20,906,286 $36,626,617 $123,259,215 Drawings / Specifications $0 $0 $0 $0 $0 Design Report / EIS $0 $48,811,741 $0 $26,995,569 $75,807,309 Indirect Costs $0 $16,914,572 $0 $9,631,048 $26,545,620 Contingencies $0 $0 $20,906,286 $0 $20,906,286 The aggregate data indicates: Estimate composition: Unit Cost Database 53.3% Cost Estimating Relationship 17.0% Allowances 29.7% Sources of cost elements: Drawings / Specs 0.0% Design Report 61.5% Indirect Costs 21.5% Contingencies 17.0% Overall the data from the example indicates that the cost estimate was Primarily based on the design report documents; drawings and specifications were not used in calculating the cost; indirect costs were accounted for the contingencies total less than 20% of the cost half of the estimated costs by dollars were derived from a database The characterization of the cost estimate line items is helpful in determining the level of estimating effort performed and the most effective review methods for the PMOC to employ. For example, when the project in the example was reviewed, the primary analysis focused on the validity of the unit cost database and the cost estimator s methodologies for applying these costs. Alternately, if the characterization indicated the majority of the costs were from a definitive cost estimate, the PMOC would focus on the unit cost basis and pricing development. SAMPLING PLAN The PMOC has to develop an approach to reviewing the project cost data, which takes into account the volume of cost data for the project. For example if a project has a 30,000 line item estimate with several hundred cost sources the PMOC may propose sampling 1% of the cost line items for review. The PMOC uses expert judgment to select an optimum sampling method that allows for sufficient cost review. The PMOC proposes an approach to reviewing the project Page10

14 cost estimate that, regardless of the level of development of the estimate, will provide FTA with reliable findings and recommendations (Federal Transit Administration, 2009). The PMOC develops this plan from the cost estimate classification and characterization data. The plan includes a description of the level of sampling of the estimate line items, and identifies the sources of costs to be reviewed including third parties, market forces, sequencing options, etc. This plan is then communicated to FTA as part of the PMOC reporting procedures and becomes a basis for the PMOC cost review. PROJECT COST REVIEW The FTA process for validating project cost estimates involves a number of common tasks; regardless of cost estimate type (Parametric, Analogous, Bottom up, etc.). Correspondence between the Cost Estimate and Scope Comparison to Industry Standard Costs Comparison of costs to FTA Database CORRESPONDENCE WITH SCOPE REVIEW The project cost estimate is only as valid as the level of congruence to the scope of the project. Projects in the early phases of development may have a limited description of the project scope. However, the cost estimator must insure that each project element is accounted for with an accurate cost. The cost estimate data needs to be sampled and then cross checked with drawings and specifications. Additionally the PMOC needs to review the scope described in the design reports to insure a cost exists for each project scope element. COMPARISON OF COST TO INDUSTRY STANDARDS The sampled costs from the project cost estimate are reviewed against industry standard costs to determine the overall dollar value accuracy. While there are many sources for industry standard costs the most popular sources of information for FTA reviews are: Engineering News Record (ENR) o ENR publishes both a Construction Cost Index with a complete history of the 20 city national average. This index provides both material and labor components (Engineering News Record, 2011). Bureau of Labor and Statistics (BLS) o Bureau of Labor and Statistics gathers more than 9,000 Producer Price Indexes (PPI) for individual products and groups of products are released each month. Page11

15 PPIs are available for the products of virtually every industry in the mining and manufacturing sectors of the U.S. economy (Bureau of Labor Statistics, 2011). RSMeans o RSMeans models and databases for uniform construction design and corporatewide construction budgeting. Cost modeling accuracy is within 93 percent of actual cost and useful for third party validation, negotiating contractor's bids and monitoring as built costs (RS Means, 2011). Using these type of data sources the PMOC reviews the cost (based on the sampling plan) to insure the project unit costs are within an acceptable range for the level of design. Costs that are outside the acceptable range are noted and any potential cost differential is calculated. The aggregate potential cost differential is extrapolated statistically based on the sample size and population for reporting purposes. FTA S PROJECT COST DATABASE The FTA developed a cost database for use in (1) performing cost analysis based on historic costs, and (2) developing order of magnitude cost estimates in the conceptual project phase. Capital Cost Database is a Microsoft Access database of as built costs for 35, federallyfunded, Light Rail and Heavy Rail projects. The projects costs are tracked in FTA s Standard Cost Categories (SCC) and the project costs have been validated by the project sponsors (Federal Transit Administration, 2010a). The PMOC uses the cost database to assess and evaluate the project cost estimate, specifically identifying variances in unit costs and quantities from database average costs for similar projects. Note: the cost database outputs are in the SCC CES format, thus the comparisons are only made to aggregate costs in the project SCC workbook (Federal Transit Administration, 2009). REVIEW OF PARAMETRIC ESTIMATES Reviewing / validating a parametric estimate, according to ISPA (2008), is based on review of three distinct areas Policies and Procedures which control the estimate development Data Collection and Analysis methods for collecting data Means and Methods methods used to develop costs FTA ACCOMMODATIONS FOR PARAMETRIC ESTIMATES Page12

16 The FTA recognizes that parametric and unit cost database estimates are widely used for early phase estimates. When the Oversight Procedures (OP) were developed for the 2009 PMOC Services Contract accommodations were formally made for the basic review of parametric cost estimates. However, no accommodations were made for unit cost database or analogous methodology estimates, which are more common than the parametric methodology estimates in the transit industry. FTA OPERATING PROCEDURE 33 REVIEW OF PARAMETRIC ESTIMATES The PMOC is directed by FTA in the Operating Procedure to review the parametric estimate of project cost and make the following determinations (Federal Transit Administration, 2009): Identifies the key input drivers and explains the relative impact on the estimate; [That the estimate] Adequately provides and supports the data and inputs used in calibration; Demonstrates that the [parametric cost] model utilizes historical costs that are calibrated to current conditions within a reasonable degree of accuracy; [The estimate basis] Explains any adjustments to the model or to the key inputs, and provides adequate rationale for such adjustments; Demonstrates that the calibrated [parametric cost] model produces reliable estimates in comparison to some other benchmark (e.g., actual costs, comparative estimates). The PMOC performs its evaluation through the use of the International Society of Parametric Analysts (ISPA) parametric estimating checklists (International Society of Parametric Analysts [ISPA], 2008). A questionnaire based on an adaptation of this checklist is found in Appendix B. Using the checklists as a guideline the PMOC can determine, through workshops and written correspondence, the methods employed by the grantee s project cost estimator. The information gained from the questionnaire is used in conjunction with other cost estimate findings to substantiate the means and methods employed by the grantees. This information helps the PMOC justify the grantee s processes for developing cost estimates and, by extension, justify a level of confidence or lack therein of the grantees costs. This process can be subjective and relies on the PMOC s professional judgment and experience to produce findings. The PMOC has to guard against introducing biases during this process to achieve valid results. SPECIAL CONSIDERATIONS WORKING WITH LIMITED DATA Page13

17 In some cases the grantee has a very limited database of costs that the estimators are working from. When cost databases are assembled from a limited price pool (e.g. using only a few projects) the statistical margin of error is increased. Having an exhaustive accurate database is the foundation for an accurate parametric or unit cost database estimate (International Society of Parametric Analysts [ISPA], 2008). The importance of population size and number of samples is sometimes misunderstood and a group of 3 to 5 projects are used by a grantee to form a database of costs. This leads to a substantial margin of error when parametric methodologies are applied. In cases such as this the PMOC will recommend the grantee produce a cost estimate by other means such as analogous or bottom up estimating methods. PROPRIETARY DATA Cost estimators are sometimes very protective of their data. A cost estimator that has gathered 15 years worth of data into a unit cost database or parametric cost system, treats the data as if it is their baby and guards the data carefully. During the estimate validation process this becomes an issue as the PMOC needs to validate certain cost figures and the development of those cost figures, which requires in depth analysis. This situation can be problematic for the PMOC, however if the database review process is done in a workshop setting the protective grantee cost estimators are fairly receptive. For example the PMOC may hold an onsite workshop which allows the grantee to demonstrate the data validity of the database without having to transmit details of the data to the PMOC. This alleviates much of the stress and anxiety for the owner of the proprietary cost data as the data remains secure. Page14

18 CONCLUSION The FTA has evolved its cost estimating review process in recent years to include the recognition of parametric estimating techniques. While analysis of parametric estimates is not a new concept for federal projects, recognition of parametric techniques and review methods have not been universal within the federal agencies. The FTA made several proactive efforts to formalize its cost review process and will likely continue this trend. Page15

19 APPENDIX A: ACRONYMS BLS BOE CER CES DOT ENR FAA FTA ISPA OP PMOC PPI ROW SCC WBS Bureau of Labor and Statistics Basis of Estimate Cost Estimating Relationship Cost Element Structure Department of Transportation Engineering News Record Federal Aviation Administration Federal Transit Administration International Society of Parametric Analysts Operating Procedure Project Management Oversight Contractor Producer Price Index Right of Way Standard Cost Category Work Breakdown Structure Page16

20 APPENDIX B: ADAPTATION OF THE ISPA ESTIMATE CHECKLIST General Policies and Procedures Assessment Criteria Yes No Does the Grantee have adequate estimating policies and procedures that address proper implementation of parametric techniques? Do the established policies and procedures contain guidance for: Appropriate use of parametric techniques? Performing internal reviews to assess compliance with estimating policies and procedures, as well as consistency in estimating practices? Complying with relevant Government procurement laws and regulations? Data collection and Analysis Assessment Criteria Yes No Has the Grantee established a process for collecting and analyzing relevant cost and non cost (e.g., technical information) data on a periodic basis? Does the Grantee use a consistent format (e.g., work breakdown structure) for collecting cost and non cost data? Is data accumulated in a manner consistent with the Grantee s estimating practices? Does the Grantee identify and examine any data anomalies? Special Considerations Related to Cost Estimating Relationships (CERs) Assessment Criteria Yes No Does the Grantee demonstrate the ability to establish valid CERs that are reliable and credible predictors of cost? Page17

21 Assessment Criteria Yes No Does the Grantee s procedures for implementing valid CERs include: Ensuring data relationships are logical? Various alternatives (i.e., cost drivers) are considered Cost drivers selected are good predictors of cost Ensuring databases are credible? Data are current, accurate, and complete Data are appropriately analyzed and normalized Any adjustments are logical, reasonable, and verifiable Demonstration that the data relationships are strong? Analytical tests are used to evaluate strengths Evidence that non quantitative information was also considered? Materiality of cost being estimated Quality of alternate estimating techniques Does the Grantee maintain documentation that includes mathematical formulas; independent and dependent variables; statistical analysis results (or other analytical test results if appropriate); and other data used to demonstrate the CERs validity? Are updating policies and procedures established that contain guidance related to: Identifying significant data outside the normal update schedule for analysis, to determine if an out of period update is needed? Identifying and incorporating savings associated with new ways of doing business (e.g., technology changes, single process initiatives, software process improvements)? Are monitoring processes established to ensure CERs remain reliable predictors? Are procedures in place to ensure that CERs are used appropriately in proposals? When Forward Pricing Rate Agreements (FPRAs) are established do they contain definitions of all variables; tracking requirements; and appropriate applications for the CERs? Page18

22 APPENDIX C: GRANTEE S MEMO REGARDING COST ESTIMATING METHODS The PMOC shall review the Grantee s memo or report regarding its cost estimating approach. The memo should be developed by the Grantee as part of its alternatives analysis work and updated with each subsequent estimating effort. The memo or report outline should be as follows: Introduction to the project Estimating Methodology Describe the general approach to defining and quantifying the project capital cost estimate; Sources of Cost Data Define the nature and sources for cost data used in the preparation of the estimate; Cost Estimating Assumptions Allocated Contingency Unallocated Contingency Estimating Procedures If multiple parties are estimating parts of the project, this memo should help to ensure consistency of approach. i) Bottom Up and Top Down Approaches (e.g. at Entry to PE, it could be reasonable to use Bottom Up estimating approach for Guideway, Stations, Support Facilities; and Top Down estimating approach for Sitework, Systems, ROW Land Existing Improvements, Vehicles) Facilities (Guideway, Stations, Support Facilities) Costing Procedures for typical vs. nontypical components Organization and Management of Cost Data (by segment elements; project wide elements) Estimate Limitations Describe perceived or known uncertainties, as well as unknowns that could lead to changes in the estimate due to changes in project scope and design standards, incorrect unit cost or quantity assumptions, and unforeseen problems in implementation. Tracking Costs Describe how capital costs in the SCC format will be tracked through construction, revenue operations, etc. (e.g. provision in Division 1 requiring contractor to submit SCC update with monthly pay application). FTA requires that costs be tracked in the SCC format through construction, revenue operations and through two years post revenue operations to document contract closeout and the after point for the Before and After Study. Page19

23 REFERENCES Bureau of Labor Statistics. (2011). Producer Price Index. Retrieved March 9, 2011, from Engineering News Record. (2011). Construction Cost Index. Retrieved March 9, 2011, from Federal Transit Administration. (2003). Project & Construction Management Guidelines. Washington, D.C. : U.S. Department of Transportation. Federal Transit Administration. (2009). Project Management Oversight Procedure 33 Capital Cost Estimate Review. Washington, D.C.: U.S. Department of Transportation. Federal Transit Administration. (2010a). Capitol Cost Database. Retrieved March 11, 2011, from Federal Transit Administration. (2010b, June 10). Standard Cost Categories (SCC) for Capital Projects. Retrieved March 2, 2011, from International Society of Parametric Analysts [ISPA]. (2008). Parametric Estimating Handbook (4th ed.). Vienna, VA: International Society of Parametric Analysts. Project Management Institute. (2008). A Guide to The Project Management Body of Knowledge (4th ed.). Newtown Square, PA: Project Management Institute. RS Means. (2011). Predictive Cost Models. Retrieved March 9, 2011, from Page20

Oversight Procedure 34 -Project Schedule Review. Competent scheduling is necessary for sound project planning and control of costs and risks.

Oversight Procedure 34 -Project Schedule Review. Competent scheduling is necessary for sound project planning and control of costs and risks. U.S. DOT Federal Transit Administration TPM-20 Office of Engineering Project Management Oversight Oversight Procedure 34 -Project Schedule Review 1.0 PURPOSE The purpose of this Oversight Procedure is

More information

Appendix B. Technical Memoranda and Reports

Appendix B. Technical Memoranda and Reports Cotton Belt Corridor Regional Rail Project Draft Environmental Impact Statement Appendix B Technical Memoranda and Reports Technical memoranda and reports were prepared as independent documents to support

More information

Capital Cost Estimating Methodology Technical Memorandum

Capital Cost Estimating Methodology Technical Memorandum Memo Date: November 7, 2018 Project: To: From: DART Cotton Belt Regional Rail Project DFW International Airport to Shiloh Road Chad Edwards, DART Assistant Vice President Capital Planning John Hoppie,

More information

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Integration Management: processes & activities needed to properly coordinate all aspects of the project to meet stakeholder

More information

Introduction to Cost Estimation - Part I

Introduction to Cost Estimation - Part I Introduction to Cost Estimation - Part I Best Practice Checklists Best Practice 1: Estimate Purpose and Scope The estimate s purpose is clearly defined The estimate s scope is clearly defined The level

More information

Compiled by Rajan Humagai

Compiled by Rajan Humagai Compiled by Rajan Humagai www.pavementengineering.com.au Project Processes Inputs, Tools & Techniques and Outputs. (Based on PMBOK 5 th Edition) 1. Project Integration 1. Develop 1. Project Statement Of

More information

1.0 BASIS OF ESTIMATE (BOE) HOW TO

1.0 BASIS OF ESTIMATE (BOE) HOW TO 1.0 BASIS OF ESTIMATE (BOE) HOW TO 1.1 Definition A Basis of Estimate (BOE) is a document that identifies the logic, data, methodology and calculations used to estimate the resources required to perform

More information

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter 1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business Case Contract Enterprise environmental factors Project charter Expert judgement 26/02/2013 18:22:56 1 2

More information

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th www.pmlead.net PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not

More information

Cost Estimating Manual for WSDOT Projects

Cost Estimating Manual for WSDOT Projects Cost Estimating Manual for WSDOT Projects Cost Estimating Manual for WSDOT Projects Page ii Foreword Each project is unique. To accurately develop an estimate of the construction costs for a project, an

More information

City of Oxnard. Public Works Integrated Master Plan

City of Oxnard. Public Works Integrated Master Plan City of Oxnard This document is released for the purpose of information exchange review and planning only under the authority of Hugh Steve McDonald, December 2015, State of California, PE No. 44074 and

More information

Successful Project Management. Third Edition

Successful Project Management. Third Edition Successful Project Management Third Edition Successful Project Management Third Edition Larry Richman Some material in this course has been adapted from Project Management Step-by-Step, by Larry Richman.

More information

Appendix. Process Inputs and Outputs

Appendix. Process Inputs and Outputs 3601cA.fm Page 493 Wednesday, October 26, 2005 12:47 AM Appendix A Process and Throughout this book, PMP: Management Professional Study Guide, 3rd Edition, I ve discussed the inputs and outputs to the

More information

BASIS OF ESTIMATE AS APPLIED FOR THE SOFTWARE SERVICES INDUSTRIES TCM Framework: 7.3 Cost Estimating and Budgeting

BASIS OF ESTIMATE AS APPLIED FOR THE SOFTWARE SERVICES INDUSTRIES TCM Framework: 7.3 Cost Estimating and Budgeting AACE International Recommended Practice No. 74R-13 BASIS OF ESTIMATE AS APPLIED FOR THE SOFTWARE SERVICES INDUSTRIES TCM Framework: 7.3 Cost Estimating and Budgeting Rev. Note: As AACE International Recommended

More information

Project Execution Plan For

Project Execution Plan For Project Execution Plan For [Insert Name Here] Project Document Revision History Revision Date Project Manager Project Sponsor Page 1 of 24 About This Project Execution Plan Template: This template is intended

More information

Project Controls Expo

Project Controls Expo Project Controls Expo 09/10 Nov London 2011 What is Cost Engineering and Cost Estimating Carl Dalton Director Polaris Consulting Speaker Profile Carl Dalton Carl is a Fellow of the Association of Cost

More information

Implementing the North American Industry Classification System: The Canadian Experience

Implementing the North American Industry Classification System: The Canadian Experience Implementing the North American Industry Classification System: The Canadian Experience Prepared by: Michel Girard Andreas Trau Senior Classification Director Analyst Input-Output Division System of National

More information

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration Knowledge Areas According to the PMBOK edition 5 Chapter 4 - Integration 4.1 - Develop Project Charter Process Project statement of work Expert Judgment Project charter Business case Facilitation techniques

More information

Successful Project Management. Second Edition

Successful Project Management. Second Edition Successful Project Management Second Edition Successful Project Management Second Edition Larry Richman Material in this course has been adapted from Project Management Step-by-Step, by Larry Richman.

More information

TOPIC DESCRIPTION SUPPLEMENT for the SYSTEMS ENGINEERING SURVEY DESCRIPTION

TOPIC DESCRIPTION SUPPLEMENT for the SYSTEMS ENGINEERING SURVEY DESCRIPTION 1 2 Objectives of Systems Engineering 3 4 5 6 7 8 DoD Policies, Regulations, & Guidance on Systems Engineering Roles of Systems Engineering in an Acquisition Program Who performs on an Acquisition Program

More information

Integration Knowledge Area

Integration Knowledge Area Integration Knowledge Area Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational

More information

Initiation Group Process. Planning Group Process

Initiation Group Process. Planning Group Process Initiation Group Process Develop Project Charter Project statement of work Expert judgment Project charter Business case Contract (if third party project) EEF: government/industry standards, organizational

More information

MORS Introduction to Cost Estimation (Part I)

MORS Introduction to Cost Estimation (Part I) MORS Introduction to Cost Estimation (Part I) Mr. Huu M. Hoang Slide 1 Disclosure Form Slide 2 Module Four Module #(s) Items covered Presenter Start Stop One (1) Overview and Background (1) Define Estimate

More information

Project Management Framework

Project Management Framework Project Management Framework What s Project? - Why Project? What s Project Management? - Why Project Management? What s Project Management Professionals? - Why Project Management Professionals? Project

More information

DEPARTMENT OF DEFENSE STANDARD PRACTICE

DEPARTMENT OF DEFENSE STANDARD PRACTICE NOT MEASUREMENT SENSITIVE 5 April 2012 SUPERSEDING 28 January 2008 DEPARTMENT OF DEFENSE STANDARD PRACTICE DOCUMENTATION OF VERIFICATION, VALIDATION, AND ACCREDITATION (VV&A) FOR MODELS AND SIMULATIONS

More information

PROJECT EXECUTION PLANNING FOR COST AND SCHEDULE MANAGERS

PROJECT EXECUTION PLANNING FOR COST AND SCHEDULE MANAGERS PROJECT EXECUTION PLANNING FOR COST AND SCHEDULE MANAGERS ALLEN C. HAMILTON PMP CCE Project Management Associates LLC 3 Totten Way, Suite 110 Morris Plains, New Jersey 07950 USA Telephone: +1 973 984-1853

More information

FUSRAP COST TO COMPLETE. Kate Peterson U.S. Army Corps of Engineers HTRW CX, Omaha District Omaha, NE 68144

FUSRAP COST TO COMPLETE. Kate Peterson U.S. Army Corps of Engineers HTRW CX, Omaha District Omaha, NE 68144 FUSRAP COST TO COMPLETE Kate Peterson U.S. Army Corps of Engineers HTRW CX, Omaha District Omaha, NE 68144 Rick Osborn U.S. Army Corps of Engineers HTRW CX, Omaha District Omaha, NE 68144 ABSTRACT The

More information

CAPITAL INVESTMENT SYSTEMS MAKING THE RIGHT INVESTMENT DECISIONS

CAPITAL INVESTMENT SYSTEMS MAKING THE RIGHT INVESTMENT DECISIONS INTRODUCTION CAPITAL INVESTMENT SYSTEMS MAKING THE RIGHT INVESTMENT DECISIONS Neil Cusworth Managing Director Enthalpy Pty Ltd Investment decisions to develop or acquire new capital assets should be made

More information

PT 03 - Linear Regression

PT 03 - Linear Regression Parametric Cost Estimating Training Track For The Parametric Estimating Handbook Chapter 8 (PT 11) Other Parametric Applications Presenter: David Eck 1 Contents Objective Overview Tailoring Applications

More information

Project Time Management

Project Time Management Project Time Management Project Time Management Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management The process of establishing

More information

Constructing a Price-to-Win 2011 ISPA/SCEA Conference, Albuquerque, NM Frank R. Flett, Senior Vice President MCR Technologies, LLC

Constructing a Price-to-Win 2011 ISPA/SCEA Conference, Albuquerque, NM Frank R. Flett, Senior Vice President MCR Technologies, LLC Constructing a Price-to-Win 2011 ISPA/SCEA Conference, Albuquerque, NM presented by: Frank R. Flett, Senior Vice President MCR Technologies, LLC fflett@mcri.com Agenda Introduction Competitive Assessment

More information

CASE STUDY GOVERNMENT. Metropolitan Council. Managing Project Risks through the Establishment of Effective Project Controls. e-builder.

CASE STUDY GOVERNMENT. Metropolitan Council. Managing Project Risks through the Establishment of Effective Project Controls. e-builder. CASE STUDY e-builder.net Patrick Watz, AECOM s Project Manager By having those processes structured it has helped us streamline things, and give us visibility into where a process is. ABSTRACT This paper

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,

More information

IAASB CAG Public Session (March 2018) CONFORMING AND CONSEQUENTIAL AMENDMENTS ARISING FROM DRAFT PROPOSED ISA 540 (REVISED) 1

IAASB CAG Public Session (March 2018) CONFORMING AND CONSEQUENTIAL AMENDMENTS ARISING FROM DRAFT PROPOSED ISA 540 (REVISED) 1 Agenda Item B.4 CONFORMING AND CONSEQUENTIAL AMENDMENTS ARISING FROM DRAFT PROPOSED ISA 540 (REVISED) 1 ISA 200, Overall Objectives of the Independent Auditor and the Conduct of an Audit in Accordance

More information

Price Analysis and Reasonable Pricing. government contracting

Price Analysis and Reasonable Pricing. government contracting Price Analysis and Reasonable Pricing 1 Bill Walter, CPA Managing Director DHG GovCon Advisory Bill.Walter@dhgllp.com 1410 Spring Hill Road, Suite 500 Tysons, VA 22102 (703) 970.0509 Steve Masiello Partner

More information

INTERNAL AUDIT REPORT. National Transit Database R December 19, 2018

INTERNAL AUDIT REPORT. National Transit Database R December 19, 2018 INTERNAL AUDIT REPORT National Transit Database R-18-09 December 19, 2018 Executive Summary Introduction In conjunction with the Board of Trustees Audit Committee, Internal Audit (IA) developed a risk-based

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

GAO Best Practices Guides

GAO Best Practices Guides GAO Best Practices Guides Karen Richey 2017 EVMP Forum August 24 th & 25 th 1 Learning Objectives Become familiar with various GAO best practices guides used to develop audit findings Introduction to Cost

More information

The Impact of Dedicated Estimators on Project Success. Robert J. Henderson, III Program Office Supervisor Project Estimating April 22, 2016

The Impact of Dedicated Estimators on Project Success. Robert J. Henderson, III Program Office Supervisor Project Estimating April 22, 2016 The Impact of Dedicated Estimators on Project Success Robert J. Henderson, III Program Office Supervisor Project Estimating April 22, 2016 Learning Objectives 1. The role of cost estimators 2. Expectations

More information

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012 5.3.1 Define Scope: Inputs PMBOK Guide Fifth Edition 5.3.1.1 Scope Management Plan Described in Section 5.1.3.1.The scope management plan is a component of the project management plan that establishes

More information

PMP Exam Preparation Course Project Scope Management

PMP Exam Preparation Course Project Scope Management Project Scope Management 1 Product Scope Product scope The features and functions that are to be included in your products or service or result of the project. Completion is measured against the product

More information

The Project Confidence Book. Eight best practices for driving project confidence

The Project Confidence Book. Eight best practices for driving project confidence The Project Confidence Book Eight best practices for driving project confidence With $57 trillion in spend expected by 2030, the capital project industries remain challenged to deliver projects on time

More information

Capacity Building Workshop NCHRP Report 574 and Beyond: Where were We, Where are We, and Where are We Going?

Capacity Building Workshop NCHRP Report 574 and Beyond: Where were We, Where are We, and Where are We Going? Capacity Building Workshop NCHRP Report 574 and Beyond: Where were We, Where are We, and Where are We Going? Stuart Anderson, PhD, PE Texas A&M University Minneapolis, Minnesota August 11, 2010 Outline

More information

Costing: The Final Frontier. FMI Costing Workshop 2018

Costing: The Final Frontier. FMI Costing Workshop 2018 Costing: The Final Frontier FMI Costing Workshop 2018 Please silence your phone but don t turn it off. Financial Officer Competencies Negotiation and Persuasion Using information provided in a cost estimate

More information

Centerwide System Level Procedure

Centerwide System Level Procedure 5.ARC.0004.1 1 of 17 REVISION HISTORY REV Description of Change Author Effective Date 0 Initial Release D. Tweten 7/17/98 1 Clarifications based on 7/98 DNV Audit and 6/98 Internal Audit (see DCR 98-028).

More information

Chapter 6 Field Work Standards for Performance Audits

Chapter 6 Field Work Standards for Performance Audits Chapter 6 Field Work Standards for Performance Audits Introduction 6.01 This chapter contains field work requirements and guidance for performance audits conducted in accordance with generally accepted

More information

EST Accuracy of FEL 2 Estimates in Process Plants

EST Accuracy of FEL 2 Estimates in Process Plants EST.2215 Accuracy of FEL 2 Estimates in Process Plants Melissa C. Matthews Abstract Estimators use a variety of practices to determine the cost of capital projects at the end of the select stage when only

More information

IAASB Main Agenda (September 2004) Page Agenda Item PROPOSED REVISED INTERNATIONAL STANDARD ON AUDITING 540

IAASB Main Agenda (September 2004) Page Agenda Item PROPOSED REVISED INTERNATIONAL STANDARD ON AUDITING 540 IAASB Main Agenda (September 2004) Page 2004 1651 Agenda Item 4-A PROPOSED REVISED INTERNATIONAL STANDARD ON AUDITING 540 AUDITING ACCOUNTING ESTIMATES AND RELATED DISCLOSURES (EXCLUDING THOSE INVOLVING

More information

Course ID October 2015 COURSE OUTLINE. Business Administration 210 Foundations of Project Management

Course ID October 2015 COURSE OUTLINE. Business Administration 210 Foundations of Project Management Page 1 of 5 Degree Applicable Glendale Community College Course ID 010247 October 2015 I. Catalog Statement COURSE OUTLINE Business Administration 210 Foundations of Project Management BUSAD 210 covers

More information

Project Management Session 6.2. Project Initiation Phase Integration Management

Project Management Session 6.2. Project Initiation Phase Integration Management Project Management Session 6.2 Project Initiation Phase Integration Management 1 Project Phases & Knowledge Areas 1. Integration 2. Scope Management 3. Time Management 4. Cost Management 5. Quality Management

More information

State of Florida Department of Children and Families. Evaluation Manual

State of Florida Department of Children and Families. Evaluation Manual State of Florida Department of Children and Families ITN# - SNR1819RS002 Adult Education Services for Refugees and Entrants in Broward County Evaluation Manual Evaluator Name: Vendor Name: Date of Reply

More information

Internal Audit. Audit of Procurement and Contracting

Internal Audit. Audit of Procurement and Contracting Internal Audit Audit of Procurement and Contracting June 2011 Table of Contents EXECUTIVE SUMMARY...5 1. INTRODUCTION...8 1.1 BACKGROUND...8 1.2 OBJECTIVES...9 1.3 SCOPE...9 1.4 METHODOLOGY AND APPROACH...9

More information

State of Florida Department of Children and Families. Evaluation Manual

State of Florida Department of Children and Families. Evaluation Manual State of Florida Department of Children and Families ITN# - SNR1819RS001 Adult Education Services for Refugees and Entrants in Miami-Dade County Evaluation Manual Evaluator Name: Vendor Name: Date of Reply

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

Appendix K. Clean Water Nashville Overflow Abatement Program GUIDANCE FOR DESIGN ESTIMATING. Version 2.0

Appendix K. Clean Water Nashville Overflow Abatement Program GUIDANCE FOR DESIGN ESTIMATING. Version 2.0 Appendix K Clean Water Nashville Overflow Abatement Program GUIDANCE FOR DESIGN ESTIMATING Version 2.0 April 2014 Table of Contents Section 1 Estimating Introduction... 1 1.1 Exception to Designer OPCCs...

More information

Guidance Note: Corporate Governance - Board of Directors. January Ce document est aussi disponible en français.

Guidance Note: Corporate Governance - Board of Directors. January Ce document est aussi disponible en français. Guidance Note: Corporate Governance - Board of Directors January 2018 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance - Board of Directors (the Guidance

More information

Scope Management. 2. Meetings 2. Requirements Management Plan 3. EEF 4.OPA

Scope Management. 2. Meetings 2. Requirements Management Plan 3. EEF 4.OPA Scope Management 5.1 Plan Scope Management: The process of creating scope management plan that documents how project scope will be defined, validated and controlled # Requirement: Condition or capability

More information

Section I - Introduction

Section I - Introduction Section I - Introduction A. Purpose The purpose of this document is to present information to Professional Services Firms that will allow them to design projects, prepare construction documents and provide

More information

The Cost of Organizational Structures and Interfaces

The Cost of Organizational Structures and Interfaces The Cost of Organizational Structures and Interfaces prepared for Ground System Architectures Workshop by Darryl W. Webb Business and Operations Analysis Subdivision Systems Engineering Division The Aerospace

More information

APPENDIX I: COSTING DETAIL APPENDIX I COSTING DETAIL

APPENDIX I: COSTING DETAIL APPENDIX I COSTING DETAIL APPENDIX I: COSTING DETAIL APPENDIX I COSTING DETAIL Draft January 2013 CAPITAL COSTING (LPA) March 2013 As part of the analysis of the alternatives, planning-level capital costing was completed on each

More information

Hong Kong Deposit Protection Board

Hong Kong Deposit Protection Board Hong Kong Deposit Protection Board Independent Assessment Program and Self-Declaration for Compliance with the Guideline on Information Required for Determining and Paying Compensation ( Program Guide

More information

Ambulance Contract Billing Report October 12, 2016 KEY CONTROL FINDING RECOMMENDATION STATUS The City should:

Ambulance Contract Billing Report October 12, 2016 KEY CONTROL FINDING RECOMMENDATION STATUS The City should: Ambulance Contract Billing Report October 12, 2016 The City should: General Recordkeeping Inconsistencies exist in the basic recordkeeping related to ambulance calls. Continue with the implementation of

More information

Information for Contractors Regarding Public Works Projects

Information for Contractors Regarding Public Works Projects Information for Contractors Regarding Public Works Projects Table of Contents INTRODUCTION...2 WHAT IS CUPCCAA?...2 BENEFITS OF CUPCCAA...2 TRADITIONAL BIDDING VS. MCC IMPLEMENTED CUPCCAA...3 ADOPTION

More information

International Association of Certified Practicing Engineers

International Association of Certified Practicing Engineers www.iacpe.com Knowledge, Certification, Networking Page: 1 71 IACPE No 19, Jalan Bilal Mahmood 80100 Johor Bahru Malaysia The International is providing the introduction to the Training Module for your

More information

Project Management Professional (PMP) Exam Prep Course 00 PMP Application & Exam

Project Management Professional (PMP) Exam Prep Course 00 PMP Application & Exam Project Management Professional (PMP) Exam Prep Course 00 PMP Application & Exam Slide 1 Application & Exam Types of Questions PM Basics Ten Knowledge Areas Professional Responsibility Practice Exams Slide

More information

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are:

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are: Introduction Scope Management involves the management of techniques that make sure that the project comprises a Processes included in Scope Management are: 1. Collect Requirements In this process, project

More information

General Session 2 Procurement Update. #AirportsTechnical

General Session 2 Procurement Update. #AirportsTechnical General Session 2 Procurement Update #AirportsTechnical Procurement Update Moderator: Jeff Kirby, Parish & Partners Mike Rottinghaus, FAA, Office of Airport Planning and Programming Jim Harris, Coffman

More information

JOB SUMMARY: THE SUCCESSFUL CANDIDATE MUST COMPLETE THE ONLINE APPLICATION; SUBMIT A RESUME AND COVER LETTER DESCRIBING QUALIFICATIONS.

JOB SUMMARY: THE SUCCESSFUL CANDIDATE MUST COMPLETE THE ONLINE APPLICATION; SUBMIT A RESUME AND COVER LETTER DESCRIBING QUALIFICATIONS. SALARY: $23.69 - $31.69 Hourly Currently accepting applications for: Housing Management Analyst Tukwila, WA OPENING DATE: 05/05/14 CLOSING DATE: 05/19/14 04:30 PM JOB SUMMARY: THE SUCCESSFUL CANDIDATE

More information

This presentation will briefly discuss the three methods of estimating; analytical, analogous and parametric before studying parametric cost and

This presentation will briefly discuss the three methods of estimating; analytical, analogous and parametric before studying parametric cost and Abstract This presentation will briefly discuss the three methods of estimating; analytical, analogous and parametric before studying parametric cost and schedule estimating in more depth. It will consider

More information

Case Study. Effort = (Size X Complexity) Productivity. A Case for Software Estimation

Case Study. Effort = (Size X Complexity) Productivity. A Case for Software Estimation Case Study A Case for Software Estimation A recent search of the World Wide Web identified over 2100 sites that describe over 5000 reasons that software projects fail, ranging from the poor use of technology

More information

PgMP Exam Prep Training - 4 Days

PgMP Exam Prep Training - 4 Days PgMP Exam Prep Training - 4 Days Course Length: 4 Days Course ID: PgMP Credits: 21 PDUs Course Duration: 3 or 4 days (Live in person or online class) Course Level: Advanced Day workshop- PgMP Boot Camp

More information

DEPARTMENT OF DEFENSE Defense Contract Management Agency ANNEX. Technical Support to Indirect Costs (TSI)

DEPARTMENT OF DEFENSE Defense Contract Management Agency ANNEX. Technical Support to Indirect Costs (TSI) DEPARTMENT OF DEFENSE Defense Contract Management Agency ANNEX Technical Support to Indirect Costs (TSI) Engineering and Analysis Technical Directorate DCMA-ANX 213-02 OPR: DCMA-EA DCMA-TD Summary of Changes:

More information

PROJECT MANAGEMENT PLAN

PROJECT MANAGEMENT PLAN PROJECT MANAGEMENT PLAN AS A TOOL TO DEVELOP EFFECTIVE COMMUNICATION TO MANAGE STAKEHOLDERS AND THE DESIGN TEAM Adelaide Airport plaza Event: Design and Development of Stations and Terminals Conference

More information

RISK Realistic and Practical Project Risk Quantification (without CPM)

RISK Realistic and Practical Project Risk Quantification (without CPM) RISK.2515 Realistic and Practical Project Risk Quantification (without CPM) John K. Hollmann, PE CCP CEP DRMP FAACE Hon. Life Abstract From 2007 to 2013, the AACE International Decision and Risk Management

More information

MORS Introduction to Cost Estimation (Part I)

MORS Introduction to Cost Estimation (Part I) MORS Introduction to Cost Estimation (Part I) Mr. Huu M. Hoang Slide 1 Disclosure Form Slide 2 Learning Objectives of Module Two 1. Understand how to define a program using the various documents and other

More information

BSAI Crab Rationalization EDR Audits

BSAI Crab Rationalization EDR Audits BSAI Crab Rationalization EDR Audits Report Prepared for Pacific States Marine Fisheries Commission 2014 Calendar Year Data January 2016 CPAs AND BUSINESS CONSULTANTS T ABLE OF C ONTENTS Introduction...

More information

International Diploma in Project Management. (Level 4) Course Structure & Contents

International Diploma in Project Management. (Level 4) Course Structure & Contents Brentwood Open Learning College (Level 4) Page 1 Unit 1 Overview of Project Management The unit 1 covers the following topics: What is A Project? What is Project Management? Project Constraints Tools and

More information

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Introduction Context Agenda Introduction to Methodologies What is a Methodology? Benefits of an Effective Methodology Methodology

More information

MORS Introduction to Cost Estimation (Part I)

MORS Introduction to Cost Estimation (Part I) MORS Introduction to Cost Estimation (Part I) Mr. Huu M. Hoang Slide 1 Disclosure Form Slide 2 Module Three Module #(s) Items covered Presenter Start Stop One (1) Overview and Background (1) Define Estimate

More information

PRECISE INDUSTRIES INC. Quality Manual

PRECISE INDUSTRIES INC. Quality Manual PRECISE INDUSTRIES INC Revision N Issued July 5, 2017 Conforms to AS9100 Rev. D and ISO 9001:2015 Copyright Year2017 [PRECISE INDUSTRIES INC]; all rights reserved. This document may contain proprietary

More information

PMP Exam Preparation Workshop. Chapter # 5 Project Scope Management

PMP Exam Preparation Workshop. Chapter # 5 Project Scope Management PMP Exam Preparation Workshop Chapter # 5 Copyright PMI SOC 2013 1 Learning Objectives By the end of this session you will understand: How scope management processes relate to the process groups Project

More information

Best Practices for an Owner Estimating Organization. Larry R. Dysert, CCC Conquest Consulting Group

Best Practices for an Owner Estimating Organization. Larry R. Dysert, CCC Conquest Consulting Group Best Practices for an Owner Estimating Organization Larry R. Dysert, CCC Conquest Consulting Group Establish an Estimate Classification System Promotes consistency and understanding of the terminology

More information

SYSTEMATIC APPROACH FOR DECOMMISSIONING PLANNING AND ESTIMATING

SYSTEMATIC APPROACH FOR DECOMMISSIONING PLANNING AND ESTIMATING ABSTRACT SYSTEMATIC APPROACH FOR DECOMMISSIONING PLANNING AND ESTIMATING A. Scott Dam, P. E. JUPITER Corporation 2730 University Boulevard West, Suite 900 Wheaton, MD 20702 Nuclear facility decommissioning,

More information

Cost Estimating Documentation Guide

Cost Estimating Documentation Guide Cost Estimating Documentation Guide Prepared by Deputy Assistant Secretary of the Navy (Cost & Economics) Naval Center for Cost Analysis Purpose: Provide Naval Center for Cost Analysis (NCCA) policy on

More information

Public Private Partnership. PPP Policy Overview. Policy and Planning Division Ministry of Economic Affairs

Public Private Partnership. PPP Policy Overview. Policy and Planning Division Ministry of Economic Affairs Public Private Partnership PPP Policy Overview Policy and Planning Division Ministry of Economic Affairs Delivery of Public Services Outsourcing: short-term contracts and parts of public service PPPs:

More information

BSAI Crab Rationalization EDR Audits

BSAI Crab Rationalization EDR Audits BSAI Crab Rationalization EDR Audits Report Prepared for Pacific States Marine Fisheries Commission 2013 Calendar Year Data January 2015 CPAs AND BUSINESS CONSULTANTS TABLE OF CONTENTS Introduction...

More information

Quality Management Systems in Engineering Practice. Shane R. Beabes, P.E.

Quality Management Systems in Engineering Practice. Shane R. Beabes, P.E. Quality Management Systems in Engineering Practice Shane R. Beabes, P.E. ASQ Northern Virginia Section 11 May 2016 Agenda 1. Quality Management System 2. Quality 3. Client Requirements 4. Quality Assurance

More information

Table of Contents Local Agency Guidelines Section B August 2011

Table of Contents Local Agency Guidelines Section B August 2011 Table of Contents SECTION B NON-CERTIFIED AGENCY 2 Chapter 10 Design Approval... 2 A. OVERVIEW... 2 B. DESIGN ACCEPTANCE PACKAGE (30 PERCENT)... 2 1. Traffic Data... 3 2. Right of Way... 3 3. Horizontal-

More information

Cost Estimating Guideline February, 2017

Cost Estimating Guideline February, 2017 Cost Estimating Guideline February, 2017 Procedures are subject to change without notice. Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Section 1 -

More information

ENGINEERING AND CONSTRUCTION BULLETIN. Expires: 4 Mar Aug No Issuing Office: CECW-CE Issued: 4 Mar Aug 2017, Rev 1

ENGINEERING AND CONSTRUCTION BULLETIN. Expires: 4 Mar Aug No Issuing Office: CECW-CE Issued: 4 Mar Aug 2017, Rev 1 ENGINEERING AND CONSTRUCTION BULLETIN No. 2015-7 Issuing Office: CECW-CE Issued: 4 Mar 2015 30 Aug 2017, Rev 1 Expires: 4 Mar 2017 30 Aug 2019 1. Applicability: Directive and Guidance 2. References: a.

More information

Conduct a job evaluation

Conduct a job evaluation Work Essentials Home > Help and How-to > Work Essentials > Human Resources Conduct a job evaluation Applies to: Microsoft Office InfoPath 2003, Word 2003 By Susan M. Heathfield Your employees want fair

More information

DESIGNING AND IMPLEMENTING A LIFE-CYCLE COST MODEL FOR FIRST-OF- A-KIND BUILDING DECOMMISSIONING

DESIGNING AND IMPLEMENTING A LIFE-CYCLE COST MODEL FOR FIRST-OF- A-KIND BUILDING DECOMMISSIONING DESIGNING AND IMPLEMENTING A LIFE-CYCLE COST MODEL FOR FIRST-OF- A-KIND BUILDING DECOMMISSIONING Jeffrey Stevens Robert Williamson Allen Schubert Kaiser Hill, L.L.C. R. F. Shangraw, Jr. Project Performance

More information

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility RFP Components CLIENT: TradePort International Corporation, Operators of John C. Munro

More information

73R-13: Basis of Estimate

73R-13: Basis of Estimate 73R-13: Basis of Estimate As Applied for the Software Services Industries Slides are used with permission from Nesma, All rights reserved. Acknowledgements For transforming AACEi 34R-05: Basis of Estimate

More information

Connoisseur Solutions Project Scope Management

Connoisseur Solutions Project Scope Management Project Scope Management Project Scope Management Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete

More information

GENERALIZED SYSTEM OF PREFERENCES TECHNICAL INFORMATION FOR PRE-ASSESSMENT SURVEY (TIPS)

GENERALIZED SYSTEM OF PREFERENCES TECHNICAL INFORMATION FOR PRE-ASSESSMENT SURVEY (TIPS) GENERALIZED SYSTEM OF PREFERENCES TECHNICAL INFORMATION FOR PRE-ASSESSMENT SURVEY (TIPS) TABLE OF CONTENTS PART 1 BACKGROUND...2 PART 2 GENERALIZED SYSTEM OF PREFERENCES GUIDANCE...2 2.1 EXAMPLES OF RED

More information

Work Plan and IV&V Methodology

Work Plan and IV&V Methodology Work Plan and IV&V Methodology Technology initiatives and programs should engage with an IV&V process at the project planning phase in order to receive an unbiased, impartial view into the project planning,

More information

CHAPTER 3: DESIGN. TN Higher Education Designers Manual October 2018 Page 1 of 12

CHAPTER 3: DESIGN. TN Higher Education Designers Manual October 2018 Page 1 of 12 3.01 GENERAL A. Design the project to meet the authorized scope, budget, and schedule. B. Upon initiation of the project, arrange to review with the Owner the service and administrative requirements as

More information

COMMERCIAL HVAC SYSTEMS System Selection

COMMERCIAL HVAC SYSTEMS System Selection COMMERCIAL HVAC SYSTEMS System Selection Technical Development Program Technical Development Programs (TDP) are modules of technical training on HVAC theory, system design, equipment selection and application

More information

2009 Annual Report to DRCOG on FasTracks. Appendix C: Cost Estimating Methodologies

2009 Annual Report to DRCOG on FasTracks. Appendix C: Cost Estimating Methodologies Appendix C: Cost Estimating Methodologies Page left intentionally blank Top Down Estimating Procedure for the RTD-FasTracks Program 1. Top Down or parametric estimates are used on the FasTracks program

More information