1 Scoping Framework: Scoping Projects for Easier Cost Estimating Darrin DeReus, Ph.D. Air Force Cost Support Project Manager Senior Cost Analyst 25 July 2014
2 Purpose Show a current project Discuss the current requirements Discuss the current scope Discuss the impacts of scope on cost estimating Scope Cost Estimate Budget Execution
3 Agenda Current Requirements Scope Guidance Where are we now?
4 Current Requirements Purpose: Enable warfighters to exploit full spectrum of missions capabilities within LVC environments Minimize mission risk Improve AF readiness at lower costs How: Perform analytical comparisons of suitability, risk and life cycle costs of material solutions Focus is to close or mitigate an attainable portion of the capability gaps Specific Gaps: Representation, Security, and Interoperability Air Force Responsibility: Lead AoA, drafting study plan, conducting analysis, and deliver final report
5 Current Defined Scope Alternatives focused on operational training and architecture integration for Space and Missile Defense Focused on Modeling and Simulation Environment All other environments: Capabilities of the interconnecting transport system will be analyzed Using detailed, operational scenarios for analysis
6 Scope (cont) Identify: Where joint and interagency efforts can be leveraged Considering availability, cost to integrate, military utility, etc Non-material approaches Doctrine, organization, training, leadership and education policy and facilities (DOTLPF) for each alternative Current fiscal realities rule out a complete redesign of a new space and missile defense architecture and is omitted from this effort.
7 Alternative Descriptions Alt I Baseline Utilize existing software, hardware, systems, and networks with current sustainment practices Alt II Modified Baseline Modify current software, hardware, systems, and networks with operationally relevant technology that could migrate into an enterprise-wide application Alt III Emerging Technology Adapt emerging technology and opportunities to the LVC architectures and environments as an enterprise to share LVC capabilities throughout LVC communities
8 Alt I Baseline Our Focus Utilize existing software, hardware, systems, and networks with current sustainment practices Alt II Modified Baseline Modify current software, hardware, systems, and networks with operationally relevant technology that could migrate into an enterprise-wide application Alt III Emerging Technology Adapt emerging technology and opportunities to the LVC architectures and environments as an enterprise to share LVC capabilities throughout LVC communities
9 Scoping Plan Collect Requirements Define Scope Create WBS Verify Scope Control Scope
10 Scoping Plan Collect Requirements Define Scope Create WBS Verify Scope Control Scope
11 Key Questions Guidance At a minimum: To what extent does each alternative address scalability, interoperability, integration, and latency to meet operational requirements? To what extent does each alternative address the capability gaps and at what cost and risk including informational assurance and security? What is the military utility (operational benefit) of each alternative? What is the cost-effectiveness of each alternative?
12 Threats and Scenarios Scenarios and use cases will be used Operational, Space and Missile Defense environment training requirements will come from experts Study team will develop two scenarios that collectively exercise the full range of mission tasks to train realistically on space assets Apply assets to train in the detection; tracking and assignment of target, and render outcomes that are quantifiable in terms of their derived measures.
13 Effectiveness Analysis Will improvements in air and space combat readiness be realized through increases in information and simulation fidelity? If so, how much, and at what cost? Will findings contribute/comply with the mandatory Training Key Performance Parameters for current and future weapon systems? Will these efforts translate to legacy weapon systems at affordable/appropriate times? Will modifications to increase information and simulation fidelity present new/additional Information Assurance risk? Identify them and recommend potential mitigation options.
14 Cost Analysis Life Cycle Cost Estimates (LCCEs) will be expressed in Base Year (BY) 2014 and Then Year (TY) dollars Will include uncertainty and risk analysis LCCEs will include RDT&E, procurement, operations and support, and disposal costs Will also include the integration costs necessary to achieve the desired capability for each system included in the study Manpower cost estimates should include government civilian, military, and contactor personnel AoA team will work with the Air Force Cost Analysis Agency and coordinate the LCCE with the OSD Cost Assessment Group
15 Sensitivity and Risk Analysis The AoA will conduct sensitivity analyses to identify variables that may change the relative cost-effectiveness among the alternatives. Report shall identify the variables, assess their impact, and document underlying assumptions Report shall conduct sensitivity analysis on any applicable minimum value in the IA-ASLVCE AoA that appears to be significantly influencing the design and/or cost of any of the alternatives Report will identify the risks (i.e., programmatic, operational, technical) associated with the various alternatives
16 Sufficiency AoA will be judged for sufficiency by OSD CAPE To be determined sufficient, the AoA must provide quantitative assessments of: Cost, effectiveness, and risk for each alternative as specified in this guidance AoA must highlight capability advantages as well as disadvantages, consider joint operational plans, and discuss key variables and sensitivity to changes in them Programmatic, operational, and technical risks of each alternative will be identified Sufficiency will be determined within 60 days after the completed AoA report is delivered to the Director.
17 Items to Address Enablers Logistics, Intelligence, Human Systems Integration, and Communications Impacts of the above on cost, risk and effectiveness for each alternative Key study questions sufficiently to inform decision makers Appropriate operational performance parameters Include threshold/objective values Alternatives capabilities to mitigate gaps Performance, cost and risk drivers Trade-space explored Trade-offs between performance, cost and risk Sensitivity analysis results Affordability constraints identified at MDD
18 Where are we? Scope - Gaps Remain Must understand the following: Capability gaps and any identified prioritization Mission areas and tasks Operational concepts and environment Threats and Scenarios Measures and standards Approaches and alternative concepts, including baseline Maturity of the technologies Operational risk Timeframes Ground rules, constraints and assumptions Science and Technology (S&T) activities, and DOTLPF-P Change Recommendations
19 Key Overarching Questions How well does each alternative close the capability gaps? How does each alternative compare to the baseline? What are all the enabling capabilities? What are the risks? What is the life cycle cost estimate for each alternative? What are the significant performance parameters? What are the trade-offs between effectiveness, cost, risk and schedule for each alternative?
20 Additional Analysis Requirements Identify Ground Rules, Constraints and Assumptions (GRC&A) Define Alternative Concepts Identify Stakeholders Determine level of effort Determine level of support (Gov t and Contractor support)
21 Effectiveness Analysis Mission Task Attributes Several Joint Capability Areas (JCA s) Measures Levels of Analysis Engineering, Engagement, Mission/Battle, Theater/Campaign Study Risk
22 Cost Analysis Total cost to the Federal Government Annual breakdown of costs Trade-offs/Cost As an Independent Variable (CAIV) Cost drivers for all alternatives Cost of enablers and operational support for capability LCCE for each alternative Projected costs for each decision expected for each alternative Uncertainty and risks associated with each cost estimate
23 Cost Considerations Sunk Costs Prior and those expected prior to implementation of chosen alternative R&D Costs Investment Costs O&S Costs Disposal Costs Baseline Extension Costs Life Cycle Time Frame Pre-fielding Costs
24 Way Ahead IMS for program and AoA WBS for baseline and alternatives as they are defined Scope Alt I (Baseline) & Alt II (Modified) Establish ground rules and assumptions Data collection plan Phasing/timeline plan Start data collection and create cost methodologies Establish Cost/Benefit/Capability Gap assessment methodology Coordinate with AFLCMC and AFCAA continuously Currently developing Rough Order of Magnitude (ROM) for budget submission For???
25 Recommendation Follow your PM training Scope, Estimate, Budget, Execute, Monitor Understand your project/program Creating a cost estimate prior to understanding scope will flex your change management process experience Great ways to help scope the unknown? Request for Information (RFI) Outside help? (Industry Day) Attend professional conferences (stay current on trends) 25
26 Questions? Darrin L. DeReus, Ph.D. Air Force Cost Support Project Manager
Analysis of Alternatives from a Cost Estimating Perspective. Kirby Hom and Kenny Ragland
Analysis of Alternatives from a Cost Estimating Perspective Kirby Hom and Kenny Ragland Office of the Deputy Assistant Secretary of the Army Cost and Economics March 30, 2015 Background In May of 2009,
More informationImproving Weapon System Investment Decisions A Knowledge-based Approach to Weapon System Acquisitions Could Improve Outcomes
Improving Weapon System Investment Decisions A Knowledge-based Approach to Weapon System Acquisitions Could Improve Outcomes Travis Masters Senior Defense Analyst U.S. Government Accountability Office
More informationTOPIC DESCRIPTION SUPPLEMENT for the SYSTEMS ENGINEERING SURVEY DESCRIPTION
1 2 Objectives of Systems Engineering 3 4 5 6 7 8 DoD Policies, Regulations, & Guidance on Systems Engineering Roles of Systems Engineering in an Acquisition Program Who performs on an Acquisition Program
More informationDoD Template for Application of TLCSM and PBL In the Weapon System Life Cycle
DoD Template for Application of TLCSM and PBL In the Weapon System Life Cycle The purpose of this template is to provide program managers, their staff, and logistics participants in the acquisition process
More informationDownload the document titled DOD for information regarding key program documentation and reports.
Page 1 of 12 Program Execution Summary EVM data from the Contract Performance Report (CPR) is often required in the documentation of service program reviews. For example, the Selected Acquisition Report
More informationIntermediate Systems Acquisition Course. Lesson 2.1 Analysis of Alternatives. Analysis of Alternatives (AoA)
Analysis of Alternatives (AoA) The Analysis of Alternatives (AoA) is an important element in the acquisition process. It provides a systematic approach to determine the optimal way to fill a gap in mission
More informationDLA Perspective: Model-Based Enterprise
DEFENSE LOGISTICS AGENCY AMERICA S COMBAT LOGISTICS SUPPORT AGENCY WARFIGHTER-FOCUSED, GLOBALLY RESPONSIVE, FISCALLY RESPONSIBLE SUPPLY CHAIN LEADERSHIP DLA Perspective: Model-Based Enterprise James Jobe
More informationUNCLASSIFIED FY Note FY15 increases for Soldier sensory performance, training effectiveness and Soldier system architecture research.
Exhibit R-2, RDT&E Budget Item Justification: PB 2015 Army Date: March 2014 2040: Research, Development, Test & Evaluation, Army / BA 2: Applied Research COST ($ in Millions) Prior Years FY 2013 FY 2014
More informationThe AF Vision for Capability Development
The AF Vision for Capability Development From Concept to T&E: An MS&A Infrastructure Transformation 8 Mar 2017 Dave Panson MS&A Lead AF Strategic Development Planning & Experimentation 1 Air Force Capability
More informationBusiness Case Analysis. Mr. Ken East, C.P.L.
Business Case Analysis Mr. Ken East, C.P.L. Ken.East@LogSec.com Performance-Based Logistics A strategy for weapon system product support that provides (vs. employs the purchase of) support as an integrated
More informationINFORMATION ASSURANCE DIRECTORATE
National Security Agency/Central Security Service INFORMATION ASSURANCE DIRECTORATE CGS Portfolio Management Portfolio Management is the process of analyzing, selecting, controlling, and evaluating needs
More informationRequest for Solutions: High Energy Laser (HEL) Flexible Prototype. 11 December 2018
Request for Solutions: High Energy Laser (HEL) Flexible Prototype 11 December 2018 1.0 Purpose The Air Force Life Cycle Management Center (AFLCMC) seeks a prototype groundbased Laser Weapon System (LWS)
More informationStatement of Work For PMA-205 TRAINING SYSTEMS Training Ranges Integrated Product Team. 9 July 2009
Statement of Work For PMA-205 TRAINING SYSTEMS Training Ranges Integrated Product Team 9 July 2009 Statement of Work For PMA-205 Training Systems Training Ranges Integrated Product Team 1.0 Background
More informationUNCLASSIFIED. FY 2016 Base FY 2016 OCO
Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Air Force Date: February 2015 3600: Research, Development, Test & Evaluation, Air Force / BA 6: RDT&E COST ($ in Millions) Prior Years FY 2014 FY 2015
More informationM3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan
M3 Playbook Guidance Phase 1: Readiness This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration
More informationDATA ITEM DESCRIPTION
DATA ITEM DESCRIPTION Title: HUMAN SYSTEMS INTEGRATION PROGRAM PLAN Number: Approval Date: 20070404 AMSC Number: N7716 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility:
More informationActionable enterprise architecture management
Enterprise architecture White paper June 2009 Actionable enterprise architecture management Jim Amsden, solution architect, Rational software, IBM Software Group Andrew Jensen, senior product marketing
More informationAn Enhanced Analysis of Alternatives (AoA)
An Enhanced Analysis of Alternatives (AoA) A Mission-Oriented, Evaluation-Based Framework for Defense Test & Evaluation Highlighting Emerging Roles for Systems Engineering in Defense Decision Making Abstract
More informationIntermediate Systems Acquisition Course. Lesson 3.15 Full Rate Production ADE-3. Supporting ADE-3
Supporting ADE-3 At the end of the Obtain Phase, the program office prepares for Acquisition Decision Event 3 (ADE-3). ADE-3 is the production decision to advance to the Produce/Deploy/Support/Dispose
More informationPerformance Assessments and Root Cause Analyses
APPROVED FOR PUBLIC RELEASE DISTRIBUTION UNLIMITED: 15-S-1951, 15 JUL 2015. 0 Performance Assessments and Root Cause Analyses August 13, 2015 Mr. Gary Bliss Director, PARCA gary.r.bliss.civ@mail.mil 571-256-0646
More informationCost Estimating Documentation Guide
Cost Estimating Documentation Guide Prepared by Deputy Assistant Secretary of the Navy (Cost & Economics) Naval Center for Cost Analysis Purpose: Provide Naval Center for Cost Analysis (NCCA) policy on
More informationAn Enhanced Analysis of Alternatives (AoA)
An Enhanced Analysis of Alternatives (AoA) A Mission-Oriented, Evaluation-Based Framework for Defense Test Evaluation NDIA March 2-5. 2009 Vince Roske Institute for Defense Analyses vroske@ida.org 703
More informationOperational Requirements Document (ORD)
Operational Requirements Document (ORD) A. Purpose This Appendix sets the requirements and establishes procedures for preparation of an Operational Requirements Document (ORD). It also prescribes procedures
More informationEXPRESS PROGRAMMATIC STATEMENT OF WORK TABLE OF CONTENTS
EXPRESS PROGRAMMATIC STATEMENT OF WORK TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 SCOPE 3.0 PROGRAMMATIC FUNCTIONAL SPECIALTY AREAS 3.1. PS1 RESOURCE MANAGEMENT SUPPORT 3.2. PS2 COST ESTIMATING/ANALYSIS 3.3.
More informationProgram Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
More informationIntegrated Baseline Review (IBR) Refocusing on Achievability August 24, 2017
Integrated Baseline Review (IBR) Refocusing on Achievability August 24, 2017 1 What is an IBR? The Review A Government program manager led review to ensure the Contractor's baseline plan has: Adequate
More informationCOMPLIANCE WITH THIS PUBLICATION IS MANDATORY
BY ORDER OF THE COMMANDER EDWARDS AIR FORCE BASE EDWARDS AIR FORCE BASE INSTRUCTION 99-100 14 SEPTEMBER 2017 Test and Evaluation TEST PROJECT MANAGEMENT COMPLIANCE WITH THIS PUBLICATION IS MANDATORY ACCESSIBILITY:
More informationBAE SYSTEMS North America Innovating for a Safer World 2003 Interoperability & Systems Integration Conference Industry Views
BAE SYSTEMS North America Innovating for a Safer World 2003 Interoperability & Systems Integration Conference Industry Views Bob Stow North America Group VP Engineering, Technology, & Program Management
More informationPurpose.
SCARS Overview Lt Col Jeff Zdenek AFLCMC/WNS (937) 656-8043 Jeffrey.zdenek@us.af.mil 8 May 18 Disclaimer: The information provided herein represents the Government s best understanding of the procurement
More informationCost and Software Data Reporting (CSDR) Post Award Meeting Procedures
Cost and Software Data Reporting (CSDR) Post Award Meeting Procedures Defense Cost and Resource Center (DCARC) 11/14/2018 This document provides an overview of the CSDR Post Award Meeting procedures. Table
More informationArdmore Seaport-e Contract Team Capabilities
Ardmore Seaport-e Contract Team Capabilities COMPANY NAME 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 3.12 3.13 3.14 3.15 3.16 3.17 3.18 3.19 3.20 3.21 3.22 ARDMORE CONSULTING GROUP SURVICE TWINTRON
More informationBased on historical data, a large percentage of U.S. military systems struggle to
A Reliability Approach to Risk Assessment and Analysis of Alternatives (Based on a Ground-Vehicle Example) Shawn P. Brady Based on historical data, a large percentage of U.S. military systems struggle
More informationa GAO GAO DEFENSE MANAGEMENT Tools for Measuring and Managing Defense Agency Performance Could Be Strengthened
GAO United States Government Accountability Office Report to the Committee on Armed Services, U.S. Senate September 2004 DEFENSE MANAGEMENT Tools for Measuring and Managing Defense Agency Performance Could
More informationThe 7 th International Scientific Conference DEFENSE RESOURCES MANAGEMENT IN THE 21st CENTURY Braşov, November 15 th 2012
The 7 th International Scientific Conference DEFENSE RESOURCES MANAGEMENT IN THE 21st CENTURY Braşov, November 15 th 2012 Tudorel SLAVULETE Logistics Directorate/Romanian General STAFF Abstract Top managers
More informationSoftware Maintenance, Sustaining Engineering, and Operational Support
Software Maintenance, Sustaining Engineering, and Operational Support Estimating Software Maintenance Costs for U.S. Army Weapons Systems Office of the Deputy Assistant Secretary of the Army for Cost and
More informationModernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management
Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Introduction How to Read an Activity Description Objective: Provides the overall objective of the activity :
More informationMethodology for Selecting the Preferred Networked Computer System Solution for Dynamic Continuous Defense Missions
Methodology for Selecting the Preferred Networked Computer Solution for Dynamic Continuous Defense Missions San Diego Dr. Glenn S. Tolentino Command & Control and Enterprise Engineering Department SPAWAR
More informationAffordability Engineering for Better Alternative Selection and Risk Reduction
Affordability Engineering for Better Alternative Selection and Risk Reduction Bob Koury, Senior Solutions Architect Marlena McWilliams, Cost Analyst ICEAA June 2014 - Denver 2013 PRICE Systems, LLC All
More informationAffordability Engineering for Better Alternative Selection and Risk Reduction
Affordability Engineering for Better Alternative Selection and Risk Reduction Bob Koury, Senior Solutions Architect Marlena McWilliams, Cost Analyst ICEAA June 2014 - Denver 2013 PRICE Systems, LLC All
More informationDI-MGMT-XXXXX (Technical Data DID) April 13, 2017
DRAFT DATA ITEM DESCRIPTION DRAFT Title: Technical Data Report (DRAFT) Number: DI-MGMT-XXXXX Approval Date: DRAFT AMSC Number: XXXX Limitation: DTIC Applicable: No GIDEP Applicable: No Preparing Activity:
More information..._ I Page lof 13 ~ LOG200 Intermediate Acquisition Logistics lesson 2.6- Evaluate Product Support Capabilities- Metrics. Welcome to Metrics
lesson 2.6- Evaluate Product Support Capabilities- Metrics RESOURCES I PRIMT I HELP Welcome to Metrics This lesson addresses the development of system sustainment metrics that will be used in the evaluation
More informationPart I of this article, published in the May-June 2009 issue of Defense AT&L magazine,
L I F E C Y C L E L O G I S T I C S Focusing Sustainment Logistics Toward Capabilities Development: Part II Charles Borsch Part I of this article, published in the May-June 2009 issue of Defense AT&L magazine,
More informationNumber: DI-HFAC-81743A Approval Date: Office of Primary Responsibility: AS/AIR 4.6 Applicable Forms: N/A
DATA ITEM DESCRIPTION Title: HUMAN SYSTEMS INTEGRATION PROGRAM PLAN Number: Approval Date: 20110421 AMSC Number: N9190 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility:
More informationSECTION C - DESCRIPTION / SPECIFICATIONS / STATEMENT OF WORK
SECTION C - DESCRIPTION / SPECIFICATIONS / STATEMENT OF WORK C.1. OBJECTIVE The objective of OASIS is to provide Government agencies with total integrated solutions for a multitude of professional service
More informationECONOMIC BENEFITS ANALYSIS
www.caskllc.com The Other-Side of Cost ECONOMIC BENEFITS ANALYSIS By: Paul Gvoth 2013 Cask LLC. All rights reserved. The Cask name and logo are registered trademarks. All content contained in this document
More informationBest practices for highly effective test design; Part 1 Beginners guide to mapping the T&E strategy
Best practices for highly effective test design; Part 1 Beginners guide to mapping the T&E strategy Luis A. Cortes, PE The goal of the STAT T&E COE is to assist in developing rigorous, defensible test
More informationCapabilities-Based Assessment (CBA) Handbook
Capabilities-Based Assessment (CBA) Handbook A Practical Guide to the Capabilities-Based Assessment 10 March 2014 Office of Aerospace Studies Air Force Materiel Command (AFMC) OAS/A5 1655 1st Street SE
More informationUNCLASSIFIED. FY 2016 Base FY 2016 OCO. Work in this project is performed by the U.S. Army Research Laboratory (ARL), Aberdeen Proving Ground, MD.
Exhibit R-2, RDT&E Budget Item Justification: PB 2016 Army Date: February 2015 2040: Research, Development, Test & Evaluation, Army / BA 2: Applied Research COST ($ in Millions) Prior Years FY 2014 FY
More informationRisk Management Using Spiral Model for Information Technology
Risk Management Using Spiral Model for Information Technology Rajendra Ganpatrao Sabale, Dr. A.R Dani Student of Ph.D., Singhania University, Pacheri Bari, Dist. Jhunjhunu( Rajasthan), India International
More informationIntermediate Systems Acquisition Course. Lesson 2.11 Program Approval ADE-2. Program Approval ADE-2
Program Approval ADE-2 At the end of the Analyze/Select Phase, the program office prepares for the next major acquisition decision event, Acquisition Decision Event 2A (ADE-2A). ADE-2A approves the program
More informationDOD INSTRUCTION BUSINESS SYSTEMS REQUIREMENTS AND ACQUISITION
DOD INSTRUCTION 5000.75 BUSINESS SYSTEMS REQUIREMENTS AND ACQUISITION Originating Component: Office of the Under Secretary of Defense for Acquisition and Sustainment Effective: February 2, 2017 Change
More informationSystems Characterization: An Approach to Modernizing Disparate Legacy Systems
Systems Characterization: An Approach to Modernizing Disparate Legacy Systems Jane Orsulak Julie Kent April 30, 2015 Copyright 2015 Raytheon Company. All rights reserved. Customer Success Is Our Mission
More informationLife Cycle Cost Estimating for System of Systems
Life Cycle Cost Estimating for System of Systems Kishore Gagrani Product Manager PRICE Systems Manmeet Grover Principal Systems Engineer Whole Life Engineering Directorate Raytheon Missile Defense Center
More informationEnterprise Risk Management Discussion American Gas Association Risk Management Committee Meeting
Enterprise Risk Management Discussion American Gas Association Risk Management Committee Meeting July 17, 2017 Objectives Provide perspective on the evolution of Enterprise Risk Management (ERM) New 2017
More informationModernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management
Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Introduction How to Read an Activity Description Objective: Provides the overall objective of the activity :
More informationBest Practices for the Architecture, Design, and Modernization of Defense Models and Simulations
1 Best Practices for the Architecture, Design, and Modernization of Defense Models and Simulations Dr. Katherine L. Morse, JHU/APL Brian Miller, US Army CERDEC NVESD Michael Heaphy, OSD(AT&L)/DMSCO Outline
More informationMDA Small Business Conference
MDA Small Business Conference Missile Defense Agency Engineering and Support Services (MiDAESS) Update 27 May 2010 Distribution Statement A: Approved for public release; distribution is unlimited Kyle
More informationSystems Engineering Challenges for an Army Life Cycle Software Engineering Center
Systems Engineering Challenges for an Army Life Cycle Software Engineering Center NDIA 8th Annual CMMI Technology Conference Denver, CO 17-20 November 2008 Dr. William A. Craig, Kerry M. Kennedy, Arthur
More informationCOMPLIANCE WITH THIS PUBLICATION IS MANDATORY
BY ORDER OF THE COMMANDER AIR FORCE RESEARCH LABORATORY AIR FORCE RESEARCH LABORATORY INSTRUCTION 33-401 13 MARCH 2014 Communications and Information ENTERPRISE BUSINESS INFORMATION TECHNOLOGY REQUIREMENTS
More informationDepartment of Defense MANUAL
Department of Defense MANUAL NUMBER 4151.22-M June 30, 2011 Incorporating Change 1, August 31, 2018 USD(A&S) SUBJECT: Reliability Centered Maintenance (RCM) References: (a) DoD Directive 5134.01, Under
More informationPassit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2
Passit4Sure.OG0-093.221Questions Number: OG0-093 Passing Score: 800 Time Limit: 120 min File Version: 7.1 TOGAF 9 Combined Part 1 and Part 2 One of the great thing about pass4sure is that is saves our
More informationISA 201 Intermediate Information System Acquisition
ISA 201 Intermediate Information System Acquisition Lesson 4 Learning Objectives Today we will learn to: Given the decision to develop a DoD IT/SW system, select the appropriate acquisition strategies
More informationCloud Computing Starter Kit: Cost and Business Case Considerations
Approved for Public Release; Distribution Unlimited. 13 1421 Cloud Computing Starter Kit: Cost and Business Case Considerations March 2013 Raj Agrawal Jennifer Manring Main Points 2 Clouds enable new means
More informationCourse Title: Progressive Concepts in Program Management Course #: 6894 Duration: 4 days Delivery Method: Instructor-led live classroom
Course Title: Progressive Concepts in Program Management Course #: 6894 Duration: 4 days Delivery Method: Instructor-led live classroom 1. What business or organizational need does this course address?
More informationBiometrics Enterprise Architecture Systems Engineering Management Plan (BMEA SEMP)
Biometrics Enterprise Architecture Systems Engineering Management Plan (BMEA SEMP) Version 1.0 Prepared by: Date: November 24, 2009 Revision History Purpose Revision Date Level 11/17/2009 First Draft 1.0
More informationS&T/IR&D to Support Development Planning. NDIA 16 th Annual Systems Engineering Conference 30 October John Lohse NDIA DPWG Chair (520)
NDIA Development Planning Working Group Update: Improving the Integration of Government and Industry S&T/IR&D to Support Development Planning NDIA 16 th Annual Systems Engineering Conference 30 October
More informationINTEGRATION of PROJECT MANAGEMENT and SYSTEMS ENGINEERING
Copyright 2018 by Yves Theriault. Permission granted to INCOSE to publish and use. INTEGRATION of PROJECT MANAGEMENT and SYSTEMS ENGINEERING San Diego INCOSE Mini-Conference December 1, 2018 John Wood,
More informationContinual Process Improvement (CPI) In Public-Private Partnerships (PPP)
Continual Process Improvement (CPI) In Public-Private Partnerships (PPP) Expanding Scope of PPP December 4th, 2017 Ms. Misty Goss (Ogden Air Logistics Complex Mr. Mike Phillips (Software Engineering Institute)
More informationRISK MANAGEMENT GUIDE FOR DOD ACQUISITION
RISK MANAGEMENT GUIDE FOR DOD ACQUISITION Sixth Edition (Version 1.0) August, 2006 Department of Defense Preface The Department of Defense (DoD) recognizes that risk management is critical to acquisition
More informationReliability, Availability, and Maintainability
Army Regulation 702 19 Product Assurance Reliability, Availability, and Maintainability UNCLASSIFIED Headquarters Department of the Army Washington, DC 22 May 2018 SUMMARY of CHANGE AR 702 19 Reliability,
More informationNGB-J6/CIO CNGBI DISTRIBUTION: A 13 August 2012 NATIONAL GUARD BUREAU (NGB) JOINT INFORMATION TECHNOLOGY PORTFOLIO MANAGEMENT
CHIEF NATIONAL GUARD BUREAU INSTRUCTION NGB-J6/CIO CNGBI 6000.01 DISTRIBUTION: A NATIONAL GUARD BUREAU (NGB) JOINT INFORMATION TECHNOLOGY PORTFOLIO MANAGEMENT Reference(s): See Enclosure C. 1. Purpose.
More informationTHE FORGOTTEN COSTS AND UNCERTAINTY ANALYSIS WITHIN THE DOD ACQUISITION ENVIRONMENT
THE FORGOTTEN COSTS AND UNCERTAINTY ANALYSIS WITHIN THE DOD ACQUISITION ENVIRONMENT Roberto Perez & Elizabeth Evans ICEAA Conference 2013 www.caskllc.com Introduction» Objective» Assist in developing reliable
More informationINTRODUCTION TO PARTS MANAGEMENT
INTRODUCTION TO PARTS MANAGEMENT Parts Standardization and Management Committee LMI Approved for Public Release COURSE INFORMATION Defense Acquisition University Continuous Learning Register Browse CLL
More informationAn Approach to Human Capital Strategy Implementation Planning
An Approach to Human Capital Strategy Implementation Planning Business Benefits and Technical White Paper Bradford D. Blevins May 2006 / New York, NY 1 1 Background As the CNO states in his 2005 Guidance:
More informationthe sensor revolution
the sensor revolution HOW ENTERPRISE SENSOR INTEGRATION (ESI) IS ENABLING THE INTERNET OF THINGS OVERVIEW There s a lot of buzz surrounding the Internet of Things (IoT) a world in which everything is smart
More informationWORKSHOP 84 STREAMLINING COMPLIANCE THROUGH GRC INTEGRATING A-123 UPDATES AND MORE!
WORKSHOP 84 STREAMLINING COMPLIANCE THROUGH GRC INTEGRATING A-123 UPDATES AND MORE! BOB THORSON ACCENTURE Bob Thorson is a Senior Manager in Accenture Federal Service s Defense Practice, specializing in
More informationSOFTWARE DEVELOPMENT STANDARD
SFTWARE DEVELPMENT STANDARD Mar. 23, 2016 Japan Aerospace Exploration Agency The official version of this standard is written in Japanese. This English version is issued for convenience of English speakers.
More informationSelected Acquisition Report (SAR)
Selected Acquisition Report (SAR) RCS: DD-A&T(Q&A)823-474 F-22 Increment 3.2B Modernization (F-22 Inc 3.2B Mod) As of FY 2016 President's Budget Defense Acquisition Management Information Retrieval (DAMIR)
More informationDOD MANUAL , VOLUME 12 DOD SUPPLY CHAIN MATERIEL MANAGEMENT PROCEDURES: SALES AND OPERATIONS PLANNING
DOD MANUAL 4140.01, VOLUME 12 DOD SUPPLY CHAIN MATERIEL MANAGEMENT PROCEDURES: SALES AND OPERATIONS PLANNING Originating Component: Office of the Under Secretary of Defense for Acquisition, Technology,
More informationSoS Considerations in the Engineering of Systems
SoS Considerations in the Engineering of Systems Dr. Judith Dahmann The MITRE Corporation Kristen Baldwin Principal Deputy, Office of the Deputy Assistant Secretary of Defense for Systems Engineering,
More informationLife Cycle Metrics and OSD Oversight: Discipline With Flexibility
ITEA Journal 2008; 29: 263 266 Copyright 2008 by the International Test and Evaluation Association Life Cycle Metrics and OSD Oversight: Discipline With Flexibility Randy T. Fowler Assistant Deputy Under
More informationEnterprise Architecture as an Essential Tool Supporting Army Transformation. Fernando Mezquita
Enterprise Architecture as an Essential Tool Supporting Army Transformation Fernando Mezquita There are two ways of spreading light: to be the candle or the mirror that reflects it. Edith Wharton, 1862-1937
More informationPersistent Surveillance & Border Security (An Automated Means of Aircraft Deconfliction)
ECONOMICALLY DISADVANTAGED, WOMAN-OWNED SMALL BUSINESS (ED-WOSB) SBA CERTIFIED 8(M), HUB-ZONE & VIRGINIA CERTIFIED SWAM Decision Support for Persistent Surveillance & Border Security (An Automated Means
More informationSoS Considerations in the Engineering of Systems
SoS Considerations in the Engineering of Systems Kristen Baldwin Principal Deputy, Office of the Deputy Assistant Secretary of Defense for Systems Engineering, USD(AT&L) Dr. Judith Dahmann The MITRE Corporation
More informationServices Description. Transformation and Plan Services. Business Transformation and Plan Services
Services Description Business ation and Plan Services Business ation and Plan Services SAP Business ation and Plan Services provides consulting and prototyping services to facilitate Licensee innovation
More informationModernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management
Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Introduction 3 Updated date: 7/2/216 Version 1. How to Read an Activity Description Objective: Provides the
More informationDefense Procurement & Acquisition Policy Acquisition Exchange Program. Project Description #1
Defense Procurement & Acquisition Policy Acquisition Exchange Program Project Description #1 Opportunity: FAR/DFARS Projects Organization: OUSD(AT&L)DPAP/DARS Posting Date: May 15, 2006 Closing Date of
More informationSelected Acquisition Report (SAR)
Selected Acquisition Report (SAR) RCS: DD-A&T(Q&A)823-474 F-22 Increment 3.2B Modernization (F-22 Inc 3.2B Mod) As of FY 2017 President's Budget Defense Acquisition Management Information Retrieval (DAMIR)
More informationCost-Effective Readiness
AIR FORCE SUSTAINMENT CENTER Cost-Effective Readiness Readiness Optimization in a Budget Constrained Environment AFMC/AFSC/DS, Ginger.Keisling@us.af.mil 4/1/2014 A proven, scientific approach that challenges
More informationOverview: Status Reports/Dashboards provide program leadership and governance with updates on program progress, and strategic program risks/issues.
M3 Playbook Guidance Phase 4: Migration This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration
More information2014 ICEAA Annual Professional Development Workshop June 10-13, 2014 Denver, CO. A Comprehensive Approach for Lifelong Learning
2014 ICEAA Annual Professional Development Workshop June 10-13, 2014 Denver, CO A Comprehensive Approach for Lifelong Learning Dr. Darcy Lilley, EdD., DAFC Kevin Cincotta, CCEA, PMP Lauren Nolte, CCEA
More informationA Comprehensive Approach for Lifelong Learning. Abstract: Key Points
2014 ICEAA Annual Professional Development Workshop June 10-13, 2014 Denver, CO A Comprehensive Approach for Lifelong Learning Dr. Darcy Lilley, EdD., DAFC Kevin Cincotta, CCEA, PMP Lauren Nolte, CCEA
More informationInteroperability Developmental Test & Evaluation Guidance
Developmental Test & Evaluation Guidance May 2017 DT&E Initiative Team BLUF DT&E Guidance Include interoperability as part of overall DT&E strategy, developed early Outline DT&E activities in the TEMP
More informationJoint Program Manager Individual Protection Nuclear, Biological, Chemical Defense Overarching Model
Joint Program Manager Individual Protection Nuclear, Biological, Chemical Defense Overarching Model Charleston, SC 9 Mar 2006 Salvatore Clementi JPM-IP Senior Engineer (703) 432-3201 salvatore.clementi@usmc.mil
More informationQuantitative Model Olympics
Quantitative Model Olympics Debra L Smith Kerry Trujillo November 5-8, 2012 Copyright 2012 Raytheon Company. All rights reserved. Customer Success Is Our Mission is a registered trademark of Raytheon Company.
More informationDATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date:
DATA ITEM DESCRIPTION TITLE: TRAINING SITUATION DOCUMENT Number: DI-SESS-81517C Approval Date: 20130524 AMSC Number: N9379 Limitation: N/A DTIC Applicable: N/A GIDEP Applicable: N/A Office of Primary Responsibility:
More informationProject vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,
Project vs Operation PROJECTS OPERATIONS Temporary Ongoing Unique Repetitive Closes after attaining the objectives Objective is to sustain business Prototyping the new car model Assembly line production
More informationFramework Definition Procedures Guide
ATS Framework Working Group Framework Definition Procedures Guide March 2015 INTRODUCTION This document was created by the ATS Framework Working Group (formerly known as the ATS R&D IPT - ARI) under the
More informationDr. Fatma Dandashi October, 2003
Systems Technical Operational DoD Architecture Framework Overview Dr. Fatma Dandashi October, 2003 Outline Policy and Guidance on Architecture History of the Framework Framework Definitions and Purpose
More informationSystems Engineering Updates for Parts Management PMSC Fall meeting November 1-3, 2011
Systems Engineering Updates for Parts Management PMSC Fall meeting November 1-3, 2011 Institute for Defense Analyses 4850 Mark Center Drive Alexandria, Virginia 22311-1882 SECDEF Priorities as stated in
More information