BPA Air Conditioner Test Results. Tests on November 22 nd and 28 th, 2016

Size: px
Start display at page:

Download "BPA Air Conditioner Test Results. Tests on November 22 nd and 28 th, 2016"

Transcription

1 BPA Air Conditioner Test Results Tests on November 22 nd and 28 th, 216

2 Key Takeaways Stalling Depends on many factors There is no single correct set of stall values to use These tests support the WECC phase 2 default values of Vstall=.45 and Tstall=2 cycles as reasonable conservative values More optimistic values that are still within the realm of reason are: Vstall=.45 and Tstall=5 cycles Vstall=.4 and Tstall=3 cycles or even 5 cycles

3 Factors which impact air conditioner stalling Factors impacting AC stalling Voltage dip magnitude Voltage dip duration Time to ramp down from initial voltage to dip voltage Final voltage (recovery voltage) Time to ramp up from dip voltage to final voltage Ambient temperature Fault initiating on the positive crest, zero crossing, or negative crest of the voltage wave cycle With all of these factors, there is no single correct value to use for Tstall and Vstall

4 Voltage Dip Test Variables V V recovery V dip T ramp T recovery T dip t

5 Test Background These tests were conducted with a Train brand reciprocating compressor air conditioner Tests were conducted on Nov. 22 nd with an ambient temperature in the mid 9s F, and Nov. 28 th with an ambient temperature at about 1 F

6 Nov. 22 nd BPA Lab Tests Tdip Vdip POW recovery ramp, starts at Stalled? Contactors opened? date temp 2 cycles.4 ramp.85 recovery.5 cycle ramp, crest yes yes 22-Nov mid 9's 2 cycles.45 ramp.85 recovery.5 cycle ramp, crest no yes 22-Nov mid 9's 3 cycles.45 ramp.85 recovery.5 cycle ramp, crest yes yes 22-Nov mid 9's 3 cycles.5 ramp.85 recovery.5 cycle ramp, crest no no 22-Nov mid 9's 4 cycles.5 ramp.85 recovery.5 cycle ramp, crest no no 22-Nov mid 9's 5 cycles.5 ramp.85 recovery.5 cycle ramp, crest no no 22-Nov mid 9's 6 cycles.5 ramp.85 recovery.5 cycle ramp, crest no no 22-Nov mid 9's 9 cycles.5 ramp.85 recovery.5 cycle ramp, crest no no 22-Nov mid 9's 12 cycles.5 ramp.85 recovery.5 cycle ramp, crest yes no 22-Nov mid 9's Tests assumed a.5 cycle ramp down to Vdip, ramp started at the crest, and an instantaneous recovery to.85 pu Key result here is that at Vdip=.5 pu the air conditioner does not stall even for long dips (Tdip at 6 cycles, which is longer than 5 kv and 23 kv normal clearing times) The data here also supports Vstall=.45 and Tstall=32 ms as conservative WECC default data May or may not stall for Vdip=.45 and Tdip=3 cycles

7 Nov. 28 th BPA Lab Tests Tdip Vdip POW recovery ramp, starts at Stalled? Contactors opened? date temp 2 cycles.45 ramp.85 recovery.5 cycle ramp, xing no no 28-Nov 1 3 cycles.45 ramp.85 recovery.5 cycle ramp, xing no no 28-Nov 99 3 cycles.4 ramp.85 recovery.5 cycle ramp, xing no yes 28-Nov 99 3 cycles.4 ramp.85 recovery.5 cycle ramp, xing yes yes 28-Nov 99 4 cycles.4 ramp.85 recovery.5 cycle ramp, xing yes yes 28-Nov 99 Tests assumed a.5 cycle ramp down to Vdip, ramp started at the zero crossing, and an instantaneous recovery to.85 pu Temperature was slightly higher than the Nov. 22 nd tests, also we applied the ramp starting a zero crossing instead of starting at the crest Key result here is that recommending Vstall=.45 and Tstall=.32 s is conservative. A sensitivity study can decrease Vstall to.4 and Tstall to 3 cycles and still be within the realm of reason. Results show the air conditioner may or may not stall at this point

8 Nov. 28 th BPA Lab Tests (2) Tdip Vdip POW recovery ramp, starts at Stalled? Contactors opened? date temp comments 2 cycles.45 ramp.85 recovery.5 cycle ramp, xing no no 28-Nov 1 no recovery ramp 2 cycles.45 ramp.85 recovery.5 cycle ramp, xing no no 28-Nov 1.5 cycle recovery ramp 2 cycles.45 ramp.85 recovery.5 cycle ramp, xing no no 28-Nov 1 1 cycle recovery ramp 2 cycles.4 ramp.85 recovery.5 cycle ramp, xing no yes 28-Nov 1 no recovery ramp 2 cycles.4 ramp.85 recovery.5 cycle ramp, xing no yes 28-Nov 1.5 cycle recovery ramp 2 cycles.4 ramp.85 recovery.5 cycle ramp, xing no yes 28-Nov 1 1 cycle recovery ramp Tests assumed a.5 cycle ramp down to Vdip, ramp started at the zero crossing, and varied ramp up to recovery of.85 pu Temperature was slightly higher than the Nov. 22 nd tests, also we applied the ramp starting a zero crossing instead of starting at the crest Key result here is that contactors consistently opened for Vdip=.4 pu and consistently did not open for Vdip =.45 pu, regardless of whether recovery voltage was instantaneous or ramped over a cycle Another result is that adding a 1 cycle ramp to the recovery voltage did not necessarily make the air conditioner more prone to stalling, at least not for Tdip=2 cycles.

9 Nov. 28 th BPA Lab Tests (3) Tdip Vdip POW recovery ramp, starts at Stalled? Contactors opened? date temp comments 4 cycles.45 ramp.85 recovery.5 cycle ramp, xing no no 28-Nov 99 no recovery ramp 4 cycles.45 ramp.85 recovery.5 cycle ramp, xing no no 28-Nov 99.5 cycle recovery ramp 4 cycles.45 ramp.85 recovery.5 cycle ramp, xing no no 28-Nov 99 1 cycle recovery ramp 5 cycles.45 ramp.85 recovery.5 cycle ramp, xing no no 28-Nov 99.5 cycle recovery ramp 5 cycles.45 ramp.85 recovery.5 cycle ramp, xing no no 28-Nov 99 1 cycle recovery ramp Tests assumed a.5 cycle ramp down to Vdip, ramp started at the zero crossing, and varied ramp up to recovery to.85 pu Temperature was slightly higher than the Nov. 22 nd tests, also we applied the ramp starting a zero crossing instead of starting at the crest Key result here is that when doing sensitivity studies it is reasonable to set Vstall=.45 and increase Tstall to 5 cycles. Also, assuming a 1 cycle ramp up to the recovery voltage of.85 does not necessarily increase likelihood of stalling

10 Nov. 28 th BPA Lab Tests (4) Tdip Vdip POW recovery ramp, starts at Stalled? Contactors opened? date temp comments 3 cycles.4 ramp.85 recovery.5 cycle ramp, xing yes yes 28-Nov 1 no recovery ramp 3 cycles.4 ramp.85 recovery.5 cycle ramp, xing no yes 28-Nov 99 no recovery ramp, repeat test 4 cycles.4 ramp.85 recovery.5 cycle ramp, xing yes yes 28-Nov 99 no recovery ramp 3 cycles.4 ramp.85 recovery 1 cycle ramp, xing no no 28-Nov 1 no recovery ramp 3 cycles.4 ramp.85 recovery 1 cycle ramp, xing no no 28-Nov 1 no recovery ramp, repeat test 4 cycles.4 ramp.85 recovery 1 cycle ramp, xing no no 28-Nov 1 no recovery ramp 5 cycles.4 ramp.85 recovery 1 cycle ramp, xing no no 28-Nov 1 no recovery ramp Key result here is that assuming a 1 cycle ramp down for Vdip instead of a.5 cycle ramp down significantly improves performance If a 1 cycle ramp is assumed, then Vstall=.4 and Tstall=5 cycles is within the realm of reason For a.5 cycle ramp, the air conditioner may or may not stall for Vdip=.4 and Tstall=3 cycles. This supports the WECC recommended Vstall=.45 and Tstall=.32 s as conservative parameters

11 Nov. 28 th BPA Lab Tests (5) Tdip Vdip POW recovery ramp, starts at Stalled? Contactors opened? date temp 2 cycles.4 ramp.85 recovery.5 cycle ramp, xing no yes 28-Nov 1 2 cycles.4 ramp.85 recovery.5 cycle ramp, xing no yes 28-Nov 1 2 cycles.4 ramp.85 recovery no ramp, xing yes yes 28-Nov 1 2 cycles.4 ramp.85 recovery no ramp, crest yes yes 28-Nov 1 Key result here is that assuming a.5 cycle ramp instead of no ramp has a significant impact on performance

12 Nov. 28 th BPA Lab Tests (6) Tdip Vdip POW recovery ramp, starts at Stalled? Contactors opened? date temp 2 cycles.4 ramp.85 recovery no ramp, crest yes yes 28-Nov 1 2 cycles.4 ramp.85 recovery no ramp, crest, negative no no 28-Nov 1 Key result here is assuming the dip starts on a negative crest gives a different result from assuming the dip starts on a positive crest This may be because the air conditioner has an auxiliary winding with an in-run capacitor, so the positive voltage crest looks different from the negative voltage crest to the motor If a.5 cycle ramp is assumed, then Vstall=.4 and Tstall=2 cycles is within the realm of reason

13 Single Phase Motor Schematic Note the in-run capacitor on the aux winding Because of this, a positive voltage peak looks different than a negative voltage peak 13

14 Plots from Lab tests These plots are from Tests done November 22 nd and November 28 th, 216 at BPA using a Train brand reciprocating AC Results are sorted in order of Vdip from highest to lowest (best to worst case) For a given Vdip, results are sorted by Tdip from lowest to highest (best to worst case)

15 Vdip (% of initial voltage) Initial voltage Recovery voltage Tdip POW to start ramp down on Ramp duration date 24_5%_85%_3cyc_crest_ramp5cyc_ h5m39s.mat

16 Main winding voltage Hi pressure chamber 24_5%_85%_4cyc_crest_ramp5cyc_ h53m24s.mat Aux winding voltage Main current Aux current

17 24_5%_85%_5cyc_crest_ramp5cyc_ h54m32s.mat

18 24_5%_85%_6cyc_crest_ramp5cyc_ h55m13s.mat

19 24_5%_85%_9cyc_crest_ramp5cyc_ h56m21s.mat

20 24_5%_85%_12cyc_crest_ramp5cyc_ h57m29s.mat

21 24_45%_85%_2cyc_zero_ramp1cyc_ h3m52s.mat

22 24_45%_85%_2cyc_zero_ramp5cyc_ h27m38s.mat

23 24_45%_85%_2cyc_zero_ramp1cyc_ h1m59s.mat

24 24_45%_85%_2cyc_zero_ramp5cyc_ h7m29s.mat

25 24_45%_85%_2cyc_zero_ramp5cyc_ h54m8s.mat

26 24_45%_85%_2cyc_zero_ramp5_cyc_ h26m14s.mat

27 24_45%_85%_2cyc_zero_ramp5_1cyc_ h28m5s.mat

28 24_45%_85%_2cyc_crest_ramp5cyc_ h38m26s.mat

29 24_45%_85%_2cyc_crest_ramp5cyc_ h49m17s.mat

30 24_45%_85%_3cyc_zero_ramp5cyc_ h9m54s.mat

31 4 24_45%_85%_3cyc_crest_ramp5cyc_ h47m23s.mat

32 24_45%_85%_3cyc_crest_ramp5cyc_ h47m23s.mat

33 24_45%_85%_4cyc_zero_ramp5cyc_ h38m29s.mat

34 24_45%_85%_4cyc_zero_ramp5_1cyc_ h39m25s.mat

35 24_45%_85%_4cyc_zero_ramp5_cyc_ h37m32s.mat

36 24_45%_85%_5cyc_zero_ramp5cyc_ h42m21s.mat

37 24_45%_85%_5cyc_zero_ramp5_1cyc_ h43m1s.mat

38 24_45%_85%_5cyc_zero_ramp5_cyc_ h44m6s.mat

39 24_4%_85%_2cyc_zero_ramp5cyc_ h31m9s.mat

40 24_4%_85%_2cyc_zero_ramp5_1cyc_ h32ms.mat

41 24_4%_85%_2cyc_zero_ramp5_cyc_ h29m59s.mat

42 24_4%_85%_2cyc_zero_ h18m24s.mat

43 24_4%_85%_2cyc_crest_ramp5cyc_ h2m58s.mat

44 24_4%_85%_2cyc_crest_ramp5cyc_ h1m51s.mat

45 24_4%_85%_2cyc_crest_ramp5cyc_ h4m11s.mat

46 24_4%_85%_2cyc_crest_ramp5_cyc_ h4m25s.mat

47 24_4%_85%_2cyc_crest_ h21m58s.mat

48 24_4%_85%_2cyc_zero_ramp5cyc_ h17m4s.mat

49 24_4%_85%_2cyc_zero_ramp5cyc_ h16m33s.mat

50 24_4%_85%_2cyc_zero_ramp5cyc_ h15m38s.mat

51 24_4%_85%_3cyc_zero_ramp1_cyc_ h52m1s.mat

52 24_4%_85%_3cyc_zero_ramp1_cyc_ h51m3s.mat

53 24_4%_85%_3cyc_zero_ramp5cyc_ h13m18s.mat

54 24_4%_85%_3cyc_zero_ramp5_1cyc_ h48m51s.mat

55 24_4%_85%_3cyc_zero_ramp5_cyc_ h54m14s.mat

56 24_4%_85%_3cyc_zero_ramp5_cyc_ h34m27s.mat

57 24_4%_85%_3cyc_crest_ramp5_cyc_ h58m53s.mat

58 24_4%_85%_3cyc_crest_ramp5_cyc_ h57m25s.mat

59 24_4%_85%_4cyc_zero_ramp1_cyc_ h52m57s.mat

60 24_4%_85%_4cyc_zero_ramp5cyc_ h17m4s.mat

61 24_25%_85%_3cyc_zero_ramp5cyc_ h11m26s.mat

California Independent System Operator Renewable Integration Study

California Independent System Operator Renewable Integration Study California Independent System Operator Renewable Integration Study Clyde Loutan Proposed Transmission Plan for Integration of Renewables Transmission System Analysis - Overview Joint Study between the

More information

8 th Annual Electric Power Industry Conference

8 th Annual Electric Power Industry Conference 8 th Annual Electric Power Industry Conference STATCOM Application to Address Grid Stability and Reliability: Part I November 11 th, 2013 Authors: Donald Shoup, P.E. and Dr. Gregory Reed Support: Nick

More information

Wind turbine model validation with measurements

Wind turbine model validation with measurements 9 th Deep Sea Offshore Wind R&D Seminar, 19-20 January 2012, Trondheim Wind turbine model validation with measurements - Comparison between measured and simulated responses to voltage dips in the grid

More information

POWERTECH LABS INC. CONNECTABILITY TESTING OF COPPER AND ALUMINUM WIRING, PHASE 2: Current Cycling Tests Mechanical Connectors PROJECT PL-00236

POWERTECH LABS INC. CONNECTABILITY TESTING OF COPPER AND ALUMINUM WIRING, PHASE 2: Current Cycling Tests Mechanical Connectors PROJECT PL-00236 Management System Registered to ISO 9001/14001 12388-88 th Avenue Tel: (604)590-7500 Surrey, British Columbia Fax: (604)590-5347 Canada V3W 7R7 www.powertechlabs.com POWERTECH LABS INC. CONNECTABILITY

More information

Modeling DER in Transmission Planning CAISO Experience

Modeling DER in Transmission Planning CAISO Experience Modeling DER in Transmission Planning CAISO Experience Irina Green Regional Transmission Senior Advisor, California ISO NERC Load Modeling Task Force Meeting April 18-19 2017 DER Types (NERC Reliability

More information

Understanding Power Factor, Crest Factor, and Surge Factor

Understanding Power Factor, Crest Factor, and Surge Factor Understanding Power Factor, Crest Factor, and Surge Factor White Paper #17 Revision 0 Executive Summary This paper explains the technical terms of Power Factor, Crest Factor, and Surge Factor. The use

More information

UNS 5kA Arrester. Certified Test Report IEC

UNS 5kA Arrester. Certified Test Report IEC CP No.: CP0504 Page 1 of 10 UNS 5kA Arrester Certified Test Report IEC 60099-4 2004 CERTIFICATION Statements made and data shown are, to the best of our knowledge and belief, correct and within the usual

More information

Ancillary Service. the WEM System Management. June 2018

Ancillary Service. the WEM System Management. June 2018 Ancillary Service Report for the WEM 2018-19 June 2018 System Management Important notice PURPOSE AEMO publishes the Wholesale Electricity Market Ancillary Services report under clause 3.11.13 of the Wholesale

More information

MEDIUM FREQUENCY WELDING

MEDIUM FREQUENCY WELDING MEDIUM FREQUENCY WELDING Introduction With the introduction of carbon foot printing, a measure for determining the quantity of greenhouse gases released as a result of an activity, it has become important

More information

ABB AG - EPDS. FC-Protector Innovative fault current limiter for indoor and outdoor applications

ABB AG - EPDS. FC-Protector Innovative fault current limiter for indoor and outdoor applications ABB AG - EPDS FC-Protector Innovative fault current limiter for indoor and outdoor applications Agenda Short-circuit challenge New member of fault current limiter family New power part New control unit

More information

Power Quality Assessment of Large Motor Starting and Loading for the Integrated Steel-Making Cogeneration Facility

Power Quality Assessment of Large Motor Starting and Loading for the Integrated Steel-Making Cogeneration Facility Power Quality ssessment of Large Motor Starting and Loading for the Integrated Steel-Making Cogeneration Facility Cheng-Ting Hsu, Member, IEEE Department of Electrical Engineering Southern Taiwan University

More information

Briefing on stepped constraint parameters initiative

Briefing on stepped constraint parameters initiative Briefing on stepped constraint parameters initiative Market Impacts of Shift Factor Truncation Scott Harvey Market Surveillance Committee Member Market Surveillance Committee Meeting General Session June

More information

CRM-A Series High Power Thick Film Resistor

CRM-A Series High Power Thick Film Resistor *RoHS COMPLIANT, **HALOGEN FREE & AEC-Q200 COMPLIANT Features Thick film technology Power rating up to 2 watts at 70 C High power surge withstanding Sulfur-resistant design (ASTM B-809) RoHS compliant*

More information

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm

SYNOPSIS OF THE THESIS. Enhanced Power Quality Management of Grid Connected Wind Farm SYNOPSIS OF THE THESIS Enhanced Power Quality Management of Grid Connected Wind Farm INTRODUCTION OF THE THESIS Faster depletion of fossil fuels and environmental damage has resulted into increased use

More information

Power Quality Improvement in Distribution System Using Distribution Static Compensator

Power Quality Improvement in Distribution System Using Distribution Static Compensator Power Quality Improvement in Distribution System Using Distribution Static Compensator Jay Kumar Sharma 1, Om Prakash Mahela 2 and Sunil Agarwal 1 1 Department of Electrical Engineering, Apex Institute

More information

Heat Pump Water Heaters: Eco-cute Living Lab Tests

Heat Pump Water Heaters: Eco-cute Living Lab Tests Heat Pump Water Heaters: Eco-cute Living Lab Tests Presentation at the ACEEE Hot Water Forum June 9, 2009 Ammi Amarnath Technical Leader, Energy Efficiency 1 Electric Power Research Institute (EPRI) Founded

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014 No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide

More information

WE-LLCR Resonant Converter

WE-LLCR Resonant Converter A Dimensions: [mm] B Recommended land pattern: [mm] D Electrical Properties: Properties Test conditions Value Unit Tol. Inductance 100 khz/ 100 mv L 400 µh ±10% Turns ratio n 27 : 6 : 6 : 2 ±3% Saturation

More information

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway SUMMARY Cost efficient utilisation of the wind energy resource requires wind farms to be located

More information

Utility Tools and Design Modifications to Mitigate the Impact of PV on the Distribution System

Utility Tools and Design Modifications to Mitigate the Impact of PV on the Distribution System Utility Tools and Design Modifications to Mitigate the Impact of PV on the Distribution System? IEA-Task 14/SEPA High Penetration PV Workshop Dec. 1, 2010 Overview Service Territory & PV Activity PV System

More information

IECRE OPERATIONAL DOCUMENT

IECRE OPERATIONAL DOCUMENT IECRE OD-551-16 Edition 1.0 2017-11-07 IECRE OPERATIONAL DOCUMENT IEC System for Certification to Standards relating to Equipment for use in Renewable Energy applications (IECRE System) Assessment of RETLs

More information

The Use of Reflective and Permeable Pavements as a Potential Practice for Heat Island Mitigation and Stormwater Management

The Use of Reflective and Permeable Pavements as a Potential Practice for Heat Island Mitigation and Stormwater Management The Use of Reflective and Permeable Pavements as a Potential Practice for Heat Island Mitigation and Stormwater Management H. Li 1*, J. T. Harvey 2, T. J. Holland 3 and M. Kayhanian 4 1, 2 University of

More information

Emerging ancillary service products in large-scale renewable energy integrated system

Emerging ancillary service products in large-scale renewable energy integrated system Emerging ancillary service products in large-scale renewable energy integrated system Zakir H Rather Dept. of Energy Science and Engineering, IIT Bombay, India 1 st international conference on Large-Scale

More information

BPA Wind Voltage Control Requirements

BPA Wind Voltage Control Requirements BPA Wind Voltage Control Requirements PJM Conference Dmitry Kosterev Bonneville Power Administration Many of BPA Paths are Stability-Limited Cross-Cascades North Montana - Northwest Cross-Cascades South

More information

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0

SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON. Rev. 1.0 No. RC0610 SYSTEM OPERATING LIMITS METHODOLOGY FOR THE OPERATIONS HORIZON Rev. 1.0 By California Independent System Operator (CAISO RC) No. RC0610 Table of Contents A. Conventions... 5 B. Introduction

More information

THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks

THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Issued by: Review Cycle: Asset Management & Regulation, ESB Networks Three years Contents 1.0 Introduction....3 1.1 Definitions...3 1.2 Aim of Planning...5

More information

LIQUID AIR ENERGY STORAGE (LAES) Pumped Hydro Capability No Geographical Constraints

LIQUID AIR ENERGY STORAGE (LAES) Pumped Hydro Capability No Geographical Constraints LIQUID AIR ENERGY STORAGE Large scale, Long duration LIQUID AIR ENERGY STORAGE (LAES) Pumped Hydro Capability No Geographical Constraints Stuart Nelmes Engineering Director Copyright of Highview Power

More information

Feasibility Study to Substitute the EER with the SEER Case Study Chiang Mai, Thailand

Feasibility Study to Substitute the EER with the SEER Case Study Chiang Mai, Thailand , October 24-26, 2012, San Francisco, USA Feasibility Study to Substitute the EER with the SEER Case Study Chiang Mai, Thailand Chutchawan Tantakitti, Thutchai Rungpairojcharoen, NaruemonTontanasarn, and

More information

Conservation Voltage Reduction

Conservation Voltage Reduction Conservation Voltage Reduction April 12, 2012 Joshua Jones PE Joshua Jones, PE Douglas Marx, PE PacifiCorp s Distribution System Customers (approx) Utah 830,500 Oregon 594,700 Wyoming 142,500 Washington

More information

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System

Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Lesson Learned Loss of Wind Turbines due to Transient Voltage Disturbances on the Bulk Transmission System Primary Interest Groups Balancing Authorities (BAs) Transmission Operators (TOPs) Generator Operators

More information

Inverter-Based Resources During a Cascading Failure: Present State and Future State

Inverter-Based Resources During a Cascading Failure: Present State and Future State 1 Inverter-Based Resources During a Cascading Failure: Present State and Future State IEEE PES GM 2018 - CFWG Panel 08/08/2018, Portland, OR Ryan Quint, NERC (ryan.quint@nerc.net) Andrew Groom, AEMO (andrew.groom@aemo.com.au)

More information

A statistical analysis of a 4.5 MW solar energy center

A statistical analysis of a 4.5 MW solar energy center Scholars' Mine Masters Theses Student Research & Creative Works Summer 216 A statistical analysis of a 4.5 MW solar energy center Archit Patnaik Follow this and additional works at: http://scholarsmine.mst.edu/masters_theses

More information

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria March 2016 Section 1 Overview and General Discussion The primary purpose of East Kentucky Power Cooperative s (EKPC s) transmission

More information

CLARIFICATION OF GENERATOR TECHNICAL PERFORMANCE REQUIREMENTS (S5.2.5)

CLARIFICATION OF GENERATOR TECHNICAL PERFORMANCE REQUIREMENTS (S5.2.5) CLARIFICATION OF GENERATOR TECHNICAL PERFORMANCE REQUIREMENTS (S5.2.5) 1. PURPOSE AEMO has prepared this document to clarify AEMO s interpretation of particular clauses in Schedule 5.2 of the National

More information

Community Clean Energy Resiliency Initiative PON-ENE BESS Request for Proposals Question and Answer Log

Community Clean Energy Resiliency Initiative PON-ENE BESS Request for Proposals Question and Answer Log Community Clean Energy Resiliency Initiative PON-ENE-2014-036 BESS Request for Proposals Question and Answer Log 03/09/16 Lead Time 1. The schedule included in the BESS RFP for the energy storage project

More information

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection 7th Solar Integration Workshop, 24-25 October 2017, Berlin, Germany Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection Baheej

More information

Accelerated Testing of Grid-Tied Photovoltaic Inverters

Accelerated Testing of Grid-Tied Photovoltaic Inverters Accelerated Testing of Grid-Tied Photovoltaic Inverters John Michael (Mike) Fife Director of Quality and Reliability mikefife@pvpowered.com Travis Bizjak Systems Engineer PV Powered, Inc. Overview of PV

More information

Product failure mechanisms and reliability testing

Product failure mechanisms and reliability testing Technology Report Product failure mechanisms and reliability testing Part 1: Motors and transformers Masahiro Yamaura Analysis Center, Calibration Group ESPEC CORP., Reliability Research Headquarters,

More information

Centralia Power Plant Closure Study. Initial Study Results DRAFT. March 17, 2011

Centralia Power Plant Closure Study. Initial Study Results DRAFT. March 17, 2011 Centralia Power Plant Closure Study Initial Study Results DRAFT March 17, 2011 Conditions Studied 5 and 10-year Winter and Summer Peak 5-year Light Autumn High Transfers to and from British Columbia Additional

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

April and May 2018 Fault Induced Solar Photovoltaic Resource Interruption Disturbances Report

April and May 2018 Fault Induced Solar Photovoltaic Resource Interruption Disturbances Report April and May 2018 Fault Induced Solar Photovoltaic Resource Interruption Disturbances Report Southern California Events: April 20, 2018 and May 11, 2018 Joint NERC and WECC Staff Report January 2019 NERC

More information

PV Lifetime Modeling an Example: PID ensuring 25 years of service life

PV Lifetime Modeling an Example: PID ensuring 25 years of service life PV Lifetime Modeling an Example: PID ensuring 25 years of service life PV Lifetime Modeling Workshop, Apr 7 th, 2015, Orlando, Florida Max B. Koentopp, Christian Taubitz, Matthias Schütze, Marcel Kröber

More information

Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study

Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study 2018-2019 Transmission Planning Process Increased Capabilities for Transfers of Low Carbon Electricity between the Pacific Northwest and California Informational Study Ebrahim Rahimi Lead Regional Transmission

More information

Wind Power Onshore & Offshore. Lindsey Hopf Andrew Letsinger Carl Reed Brandon Kelley Tong Wu Keith McKenzie

Wind Power Onshore & Offshore. Lindsey Hopf Andrew Letsinger Carl Reed Brandon Kelley Tong Wu Keith McKenzie Wind Power Onshore & Offshore Lindsey Hopf Andrew Letsinger Carl Reed Brandon Kelley Tong Wu Keith McKenzie November 1, 2013 1 Presentation Outline History and Basic Theory State-of-the-art Designs/Products

More information

Standard MH-TPL Transmission System Planning Performance Requirements

Standard MH-TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: MH-TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

NERC Planning Committee Report

NERC Planning Committee Report NERC Planning Committee Report 2017 Meeting Highlights John Seidel, on behalf of Dale Burmester - MRO member rep on NERC PC MRO Board of Directors November 30, 2017 Midwest Reliability Organization Operating

More information

2017 IRP Advisory Group. July 21, 2017 IRPAG

2017 IRP Advisory Group. July 21, 2017 IRPAG 2017 IRP Advisory Group Today s Agenda 2 General Rate Case Caution Need to avoid the possibility of unintentionally violating ex-parte communication rules Please refrain from bringing up any rate case

More information

804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION

804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION Operating Policies and Procedures Emergency System Operations OPP 804 Issued:2008-11-13 Supersedes Interim OPP Effective:2008-05-01 804 OFF-NOMINAL FREQUENCY LOAD SHEDDING AND RESTORATION 1. Purpose To

More information

Operations Highlights

Operations Highlights Operations Highlights Description Highlights of Operations System Performance. A high-level summary of notable events and update of important operation information not otherwise covered in other Board

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Steady State Power System Security Analysis with PowerWorld Simulator

Steady State Power System Security Analysis with PowerWorld Simulator Steady State Power System Security Analysis with PowerWorld Simulator S8: Security Analysis for a Generator Interconnection Study 2001 South First Street Champaign, Illinois 61820 +1 (217) 384.6330 support@powerworld.com

More information

IRP 101. Intro to Integrated Resource Planning. Scott Benson Manager, Resource & Transmission Planning. March 23, 2017

IRP 101. Intro to Integrated Resource Planning. Scott Benson Manager, Resource & Transmission Planning. March 23, 2017 IRP 101 Intro to Integrated Resource Planning Scott Benson Manager, Resource & Transmission Planning March 23, 2017 1 What is an IRP? Definition Integrated resource planning is a process by which a power

More information

Electricity generation, electricity consumption, system integration, production and consumption balance

Electricity generation, electricity consumption, system integration, production and consumption balance Prof. Dr. Andrej Gubina University of Ljubljana, Faculty of Electrical Engineering Electricity generation, electricity consumption, system integration, production and consumption balance Maribor, Slovenia,

More information

UHS 10kA Arrester. Certified Test Report IEC

UHS 10kA Arrester. Certified Test Report IEC CP No.: CP0606 Page 1 of 10 UHS 10kA Arrester Certified Test Report IEC 60099-4 2004 CERTIFICATION Statements made and data shown are, to the best of our knowledge and belief, correct and within the usual

More information

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM January 2017 PRESENTED BY JENNY RIESZ SLIDE 1 AGENDA 1. Introduction to the NEM 2. Future Power System Security Program 3. Identifying

More information

Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs

Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs Dynamic Reactive Power issue in Wind Integrated Power Systems and LVRT Compliance of WPPs RE integration workshop, Chennai January 23, 2018 Zakir H Rather, IIT Bombay Email: zakir.rather@iitb.ac.in Wind

More information

CRM-A Series High Power Thick Film Resistor

CRM-A Series High Power Thick Film Resistor *RoHS COMPLINT, **HLOGEN FREE & EC-Q200 COMPLINT Features n Thick film technology n Power rating up to 2 watts at 70 C n High power surge withstanding n Sulfur-resistant design (STM -809) n RoHS compliant*

More information

Standard Development Timeline

Standard Development Timeline Standard TPL-001-4 Transmission System Planning Performance Requirements Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be

More information

FRENIC4800VM5, a Water-Cooled High Capacity, High Voltage Inverter

FRENIC4800VM5, a Water-Cooled High Capacity, High Voltage Inverter FRENIC4800VM5, a Water-Cooled Capacity, Voltage Inverter MOKUTANI Masafumi HANAZAWA Masahiko ADACHI Akio ABSTRACT -voltage inverters used to drive main rolling mills for steel and non-ferrous metal materials,

More information

WIND TURBINE PLANT CAPABILITIES REPORT

WIND TURBINE PLANT CAPABILITIES REPORT WIND TURBINE PLANT CAPABILITIES REPORT 2013 Wind Integration Studies Published by AEMO Australian Energy Market Operator ABN 94 072 010 327 Copyright 2013 AEMO AEMO 2013 WIND TURBINE PLANT CAPABILITIES

More information

Recent US Wind Interconnection Experience

Recent US Wind Interconnection Experience Wind Energy and Grid Integration Recent US Wind Interconnection Experience J. Charles Smith Nexgen Energy LLC Utility Wind Integration Group January 24-25, 2006 Madrid, Spain Outline of Topics Background

More information

7 th NATIONAL CERTIFICATION EXAMINATION Nov FOR ENERGY MANAGERS & ENERGY AUDITORS

7 th NATIONAL CERTIFICATION EXAMINATION Nov FOR ENERGY MANAGERS & ENERGY AUDITORS Regn No: Name: (To be written by the candidates) 7 th NATIONAL CERTIFICATION EXAMINATION Nov. 2008 FOR ENERGY MANAGERS & ENERGY AUDITORS PAPER 3: Energy Efficiency in Electrical Utilities Date: 23.11.2008

More information

Wind Farms in Weak Grids Compensated with STATCOM

Wind Farms in Weak Grids Compensated with STATCOM Nordic PhD course on Wind Power (June 5-11, 2005) Final Examination Report Ph.D. Candidate: Akarin Suwannarat Supervisors: Birgitte Bak-Jensen Institute of Energy Technology, Aalborg University Pontoppidantstraede

More information

Grid Tied RES Source Control Technique to mitigate harmonic and Reactive Power Compensation by using UPQC.

Grid Tied RES Source Control Technique to mitigate harmonic and Reactive Power Compensation by using UPQC. Grid Tied RES Source Control Technique to mitigate harmonic and Reactive Power Compensation by using UPQC. R.N. Sudheer kumar 1 K Girinath Babu 2 T V N Latish 3 Asst. Professor, Dept. of EEE,Dept. of EEEDept.

More information

Operating High Variable, Renewable Generation Power Systems Lessons Learned from Ireland and Northern Ireland

Operating High Variable, Renewable Generation Power Systems Lessons Learned from Ireland and Northern Ireland Operating High Variable, Renewable Generation Power Systems Lessons Learned from Ireland and Northern Ireland 16 th September 2015 Overview 2 EirGrid s Role EirGrid is the Transmission System Operator

More information

Code No: II B. Tech II Semester Regular Examinations, April/May 2009 POWER SYSTEMS I. ( Electrical & Electronics Engineering)

Code No: II B. Tech II Semester Regular Examinations, April/May 2009 POWER SYSTEMS I. ( Electrical & Electronics Engineering) Code No: 3220201 II B. Tech II Semester Regular Examinations, April/May 2009 SET - 1 POWER SYSTEMS I ( Electrical & Electronics Engineering) Time: 3 hours Max Marks: 80 Answer Any FIVE Questions All Questions

More information

Information Document Protection System Information ID# R

Information Document Protection System Information ID# R Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between the Information Document and the related authoritative document(s)

More information

Fault current interruption in HVDC networks. Tim Schultz

Fault current interruption in HVDC networks. Tim Schultz Fault current interruption in HVDC networks Tim Schultz 1 Structure 1. Power transmission basics 2. Current developments 3. Research: Fault current interruption in HVDC grids Simulation: How are breaker

More information

Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012

Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012 Fault Current Contributions from Wind Plants Dean Miller PacifiCorp July 25, 2012 1 Presentation Overview Joint Working Group The Issue Structure of the Report Wind Plant Configuration Wind Turbine Generators

More information

Distribution Bus Protection Upgrade Considerations When Integrating Distributed Generation

Distribution Bus Protection Upgrade Considerations When Integrating Distributed Generation Distribution Bus Protection Upgrade Considerations When Integrating Distributed Generation Edsel Atienza Schweitzer Engineering Laboratories, Inc. Presented at the 50th Annual Minnesota Power Systems Conference

More information

Charles D. Corbin & Gregor P. Henze

Charles D. Corbin & Gregor P. Henze Assessing Impact of Large-Scale Distributed Residential HVAC Control Optimization on Electricity Grid Operation and Renewable Energy Integration May 11, 2015 Charles D. Corbin & Gregor P. Henze Department

More information

STEAM TURBINE-GENERATOR & AUXILLIARY SYSTEMS Presentation by: RANA NASIR ALI General Manager, Power Plants Projects, at PITCO November 02, 2017

STEAM TURBINE-GENERATOR & AUXILLIARY SYSTEMS Presentation by: RANA NASIR ALI General Manager, Power Plants Projects, at PITCO November 02, 2017 STEAM TURBINE-GENERATOR & AUXILLIARY SYSTEMS Presentation by: RANA NASIR ALI General Manager, Power Plants Projects, at PITCO November 02, 2017 CO-GENERTATION POWER PLANT CONCEPT For dimensioning, design

More information

Wave Batch Picking. Contents. 1 Version KRC

Wave Batch Picking. Contents. 1 Version KRC Wave Batch Picking Contents Description... 2 Setup:... 2 Pick Lists Types:... 2 Pick Lists Options:... 2 Wave Batch Order Process:... 3 Creating A Single Master List:... 3 Creating a Split lists:... 4

More information

PGE s 2013 Integrated Resource Plan

PGE s 2013 Integrated Resource Plan PGE s 2013 Integrated Resource Plan OPUC Public Meeting 2014 Portland General Electric. All rights reserved. Today s topics IRP public process Load-resource balance Assumptions and inputs E3 low-carbon

More information

The Odyssey of Ulysses: Mobile Laboratory For Testing Wind Turbines

The Odyssey of Ulysses: Mobile Laboratory For Testing Wind Turbines The Odyssey of Ulysses: Mobile Laboratory For Testing Wind Turbines Madrid, 24-25 Enero 2006 2 Plan -Introduction to E2Q -The challenge of E2Q: ULYSSES -The real-life tests on Wind Turbines -Conclusions

More information

WECC Short Circuit Analysis. Update: WECC Staff Short Circuit Modeling Zach Garrard, Tyson Niemann

WECC Short Circuit Analysis. Update: WECC Staff Short Circuit Modeling Zach Garrard, Tyson Niemann WECC Short Circuit Analysis Update: WECC Staff Short Circuit Modeling Zach Garrard, Tyson Niemann 2 Overview Purpose Scope Methodology Flow Chart Key Identifiers Limitations Entity Feedback Interpreting

More information

UET Welcomes IEEE PES Seattle Chapter. May 2014

UET Welcomes IEEE PES Seattle Chapter. May 2014 UET Welcomes IEEE PES Seattle Chapter May 2014 UniEnergy Technologies Mission: Be a major global provider of bulk energy storage solutions through innovation, quality and strategic partnerships We will

More information

Integrated Air Conditioning System

Integrated Air Conditioning System Integrated Air Conditioning System a smart solution for every building Contents TVR System 03 TVR System Advantage 04 TVR System Applications 05 Features - Inverter System 07 Features - Higher Reliability

More information

ELECTRICAL DISTRIBUTION SYSTEMS. IV-B.Tech I- SEM (EEE) UNIT-I. General Concepts

ELECTRICAL DISTRIBUTION SYSTEMS. IV-B.Tech I- SEM (EEE) UNIT-I. General Concepts ELECTRICAL DISTRIBUTION SYSTEMS IV-B.Tech I- SEM (EEE) UNIT-I General Concepts Introduction to Distribution Systems: The electric utility industry was born in 1882 when the first electric power station,

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

Energy Communities Guide to the 2018 Technical Workbook. April 2018

Energy Communities Guide to the 2018 Technical Workbook. April 2018 Energy Communities Guide to the 2018 Technical Workbook April 2018 Contents: 1. Technical Workbook.2 2. Application Tab..3 3. Project Summary Tab 4 4. Domestic Energy Credit Tab..7 5. Non-Domestic Tab

More information

Medium speed Heavy Fuel Oil (HFO)

Medium speed Heavy Fuel Oil (HFO) OUR PRODUCTS Medium speed Heavy Fuel Oil (HFO) Modular power plants Our HFO power source gives you cost effective power, ready when you need it - reliable and round the clock. HFO POWER PLANTS Fuel diversity

More information

Better Energy Communities Guide to the 2018 Technical Workbook. January 2018

Better Energy Communities Guide to the 2018 Technical Workbook. January 2018 Better Energy Communities Guide to the 2018 Technical Workbook January 2018 Contents: 1. Technical Workbook.2 2. Application Tab..3 3. Project Summary Tab 4 4. Domestic Energy Credit Tab..7 5. Non-Domestic

More information

Lead Free Tin Whiskering Study. Grayhill DIP Switches

Lead Free Tin Whiskering Study. Grayhill DIP Switches Lead Free Tin Whiskering Study Grayhill DIP es May 11, 2004 Revision A TABLE OF CONTENTS 1. Introduction...3 2. Test Specification...4 2.1. Intent...4 2.2. Preconditioning...4 2.2.1. Wave Temperature Processing...4

More information

NATIONAL CERTIFICATION EXAMINATION 2004 FOR ENERGY MANAGERS

NATIONAL CERTIFICATION EXAMINATION 2004 FOR ENERGY MANAGERS NATIONAL CERTIFICATION EXAMINATION 004 FOR ENERGY MANAGERS PAPER EM3: Energy Efficiency in Electrical Utilities Date: 3.05.004 Timings: 0930-30 HRS Duration: 3 HRS Max. Marks: 50 General instructions:

More information

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid Greening the Grid Andhra Pradesh Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid State-specific results from Volume II, which includes all of India. The full reports

More information

Highview Enterprises Limited, Liquid Air Energy Storage (LAES)

Highview Enterprises Limited, Liquid Air Energy Storage (LAES) Liquid Air Energy Storage (LAES) Liquid Air Energy Storage Process 1. Charge 2. Store 3. Discharge 1. Charge: Offpeak or excess electricity is used to power an air liquefier, which produces liquid air.

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

OBSERVATION, ANALYSIS

OBSERVATION, ANALYSIS GREEN TEST OBSERVATION, ANALYSIS and REPORT EXCLUSIVELY FOR CONDUCTED BY What is a GREEN TEST? Green Test is a method adopted to empirically demonstrate the performance of ENERGY SAVER in your air-conditioning

More information

Oswego Complex Export Transient Stability. Limit Analysis. Prepared by Operations Engineering Staff New York Independent System Operator, Inc.

Oswego Complex Export Transient Stability. Limit Analysis. Prepared by Operations Engineering Staff New York Independent System Operator, Inc. Oswego Complex Export Transient Stability Limit Analysis Prepared by Operations Engineering Staff New York Independent System Operator, Inc. Approved by NYISO Operating Committee March 15, 2012 Caution

More information

100% Renewables for Australia?

100% Renewables for Australia? 100% Renewables for Australia? Challenges and Opportunities Dr Jenny Riesz Engineers Australia 20 th Nov 2014 Who am I? Overview 100% renewables worth thinking about? 100% renewables technically feasible?

More information

Lessons Learned in Wind Integration

Lessons Learned in Wind Integration Lessons Learned in Wind Integration 2009 Southwest Renewable Energy Conference Flagstaff, AZ September 11, 2009 J. Charles Smith Executive Director UWIG What is UWIG? Non-profit corporation established

More information

RENEWABLE ENERGY INTEGRATION: VARIABILITY & UNCERTAINTY IMPACTS AND MITIGATION OPTIONS BRENDAN KIRBY

RENEWABLE ENERGY INTEGRATION: VARIABILITY & UNCERTAINTY IMPACTS AND MITIGATION OPTIONS BRENDAN KIRBY RENEWABLE ENERGY INTEGRATION: VARIABILITY & UNCERTAINTY IMPACTS AND MITIGATION OPTIONS BRENDAN KIRBY WWW.CONSULTKIRBY.COM KIRBYBJ@IEEE.ORG BALANCING IS A CRITICAL POWER SYSTEM RELIABILITY REQUIREMENT Power

More information

Technical considerations for integration of distributed renewables on the grid

Technical considerations for integration of distributed renewables on the grid Technical considerations for integration of distributed renewables on the grid A paper by Dr Charlotte Higgins, Dr Bunmi Adefajo & Kumbuyani Chisoro Kumbuyani Chisoro Manager Southern Africa TNEI Services

More information

OBSERVATION, ANALYSIS

OBSERVATION, ANALYSIS GREEN TEST OBSERVATION, ANALYSIS and REPORT EXCLUSIVELY FOR CONDUCTED BY What is a GREEN TEST? Green Test is a method adopted to empirically demonstrate the performance of ENERGY SAVER in your air-conditioning

More information

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005

2005 Integrated Electricity Plan. Resource Options Workshop #2 Planning Criteria March 09, 2005 2005 Integrated Electricity Plan Resource Options Workshop #2 Planning Criteria March 09, 2005 Agenda for Presentation Introduction Review industry reliability standards and regulatory Generation Reliability

More information

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013

SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 SCE s Renewable Market Adjusting Tariff (Re-MAT) Bidders Conference September 18, 2013 WebEx: https://www.webex.com/login/attend-a-meeting Meeting number: 807 052 262 Meeting password: remat Teleconference:

More information

Energy efficiency of low voltage electrical installations

Energy efficiency of low voltage electrical installations Energy efficiency of low voltage electrical installations One new area within international standards is the integration of requirements for energy efficiency into IEC 60364 (the international standard

More information