1 Page 1 of 13 ANNEXURE III User Requirement Specifications MACHINE :Linear Bottle Washing CAPACITY: 120 Bottles/ minute
2 Page 2 of 13 Table of Contents 1.0 APPROVAL SIGNATURES INTRODUCTION OVERVIEW PROCESS DESCRIPTION DESIGN REQUIREMENT SAFETY REQUIREMENT TESTING & DELIVERY QUALIFICATION REQUIREMENT TRAINING & TECHNICAL SUPPORT GOOD ENGINEERING PRACTICES CONSTRAINTS SCOPE OF SUPPLY ABBREVIATIONS...13
3 Page 3 of APPROVAL SIGNATURES This document has been prepared and reviewed by the technical team of project management and approved by following officials of GAPL. Prepared by Name/ Designation Signature Date Mrs Priyanka yeshi, AM production Checked by Name/ Designation Signature Date Mr. B. Demello, Maintenance Engineer Approved by Name/ Designation Signature Date Mr. Govind R. Tilve, Manager Production Authorized by Name/ Designation Signature Date Mr. D.N. Shetty, DGM CQA/RA
4 Page 4 of INTRODUCTION This document was generated under the authority of the GOA ANTIBIOTICS AND PHARMACEUTICALS LTD.( A SUBSIDIARY OF HLL LTD)for the purpose of specifying the user requirement for an linear bottle washing Machine that will clean empty GLASS / PET bottles required for liquid product filling. The User Requirements Specification (URS) is provided to aid the user through the important components, variables and options necessary to procure a functional bottle washer that meets the users needs in the most cost-effective method possible. The URS shall be provided to the Supplier to provide a price quote for machine supply including the design and manufacture of the equipment. This URS shall be recognized as an integral part of the procurement agreement with the selected equipment vendor. The equipment supplier or vendor will abide by the information and conditions set forth by this document as well as the standard purchasing term and conditions of the Company. The machine shall be installed and operated adjacent to existing conveyor systems as an integrated bottle filling line and will be located in a designated operating area of liquid oral filling and packing facility at production department. 3.0 OVERVIEW 3.1 Project Standard The facilities, upon completion, shall be in compliance with the cgmp requirement of Drugs And Cosmetic Act-1940/ WHO and also the GAPL s internal quality standards. The liner bottle washing machine must be capable of continuous operation over a 8 hour shift, in 3 shifts basis. 3.2 Equipment description The Linear Bottle Washing machine will be used for washing of empty PET/Glass bottles to be used for filling of Liquid formulation. The equipment should provide. loading: bottles will be loaded to feeding tray and manually pushed. washing: bottles to be carried by suitable carrier pockets moving in Linear indexing motion over a several washing stations where they are washed through a series of water jets/ compressed air from inside and external surface of the bottle in a tunnel type arrangement. unloading: washed bottles to be unloaded on the turntable of existing filling line Standard guidelines for equipment The equipment should comply with the current Good Manufacturing Practice for Pharmaceuticals
5 Page 5 of PROCESS DESCRIPTION 4.1 Bottles loaded on machine through feeding tray manually. 4.2 These bottle will be transferred in neck down position over spray nozzles through suitable carrier system. 4.3 Bottles will be washed by water pressure jets though spray nozzles from inside and outside 4.4 Inside wash Spray nozzles deliver water jets or compressed air to flush internal surface of bottles. 4.5 Bottles pass through a series of wash cycles 4.6 Duly washed bottles are than delivered to out feed with neck upward position and transfer through suitable conveyer to filling line turn table. 5.0 DESIGN REQUIREMENT 5.1 Capacity Desired speed: 120 bottles/minute Loading of bottles on machine through feed tray which shall be transferred by suitable conveyer system on machine to washing stations Facility for transfer of washed bottles from machine to turntable should be provided. Machine to operate with minimal/no change parts for different bottle sizes with similar neck diameter Bottles to be washed internally as well as externally on completion of washing cycle. Bottle washing should be achieved uniformly. 5.2 Input specifications MOC of infeed bottles: PET/ Glass/ Nylon size : 20 ml to 500 ml neck diameter ( od) : 25 mm /22mm base diameter : mm height : mm
6 Page 6 of Material of construction Machine main structure of SS304. Machine external finish :mirror finish Water Tanks & trays made from SS 316 mirror finish. Water contact parts and jet spray nozzles strictly of SS 316L Yesno Welding: argon arc type. Yesno Water transfer pump: SS 316 with mechanical seal( TC totc) Yesno All Parts coming in contact with washing zones/jet to be made from SS316. Yesno SS filter housing : SS 316. Yesno Other Exposed parts SS304.r Preferred makes for Motor:Kirloskar /Compton Greaves/ Siemens Other mechanical parts/ Motors: non corrosive material 5.4 Design specification Pressure guages to be provide at all washing stations to detect pressure of washing jets. Provision for recirculation of water at initial washing stations Pumps and tanks required to be preferably inbuilt Appropriate filter of NLT 20 µ ( preferably pp filter cartridge) to be provided to water storage tanks Minimum 3 wash cycles with water from inner side, one on outside of the bottle and one wash with filtered air provision Each wash station to be provided with separate circuit to prevent mixing of two different waters Provision for washing of bottles with height, neck, base diameter more/less than that mentioned in our input specifications to be available for the machine if required
7 Page 7 of Quality requirement No water stagnation in any part of the machine at any given time during operation /non-operation There should be no water leakage through machine except for drain water. Appropriate provision to be made for draining off all the rinse water from the interior of the bottles is to ensure that there is no residual rinse water left in the bottle prior to sending for product filling. 5.6 Utility requirement Vendor should state the utilities required for the normal operation of the machine Vendor should provide consumption details for Electricity, water, Compressed air and Other utilities o Cables, air tubes, etc required from the point (single utility point) to equipment is in scope of vendor. 5.7 Operation Single operator is expected to operate the machine Machine shall be safe from an Operator and environmental standpoint. The equipment shall have proper safeguards Control System Requirements Manual/automatic 5.8 Cleaning and Maintenance Filters & spray nozzles should be easy to dismantle & clean whenever required. Vendor to give information on the cleaning procedure for the machine. The equipment shall be easily accessible for cleaning the non-product contact part at maintenance side of the equipment. Vendor shall provide special tools for maintenance of the equipment. Vendor shall give recommended spare parts list.
8 Page 8 of SAFETY REQUIREMENT 6.1 General Following facilities must be provided to protect personnel, article and equipment: In the event of equipment malfunction or loss of utilities, the unit must contain all necessary protection devices to ensure that the equipment and the article remain in a safe condition. Noise level below 75 db at a distance of 1 m from the equipment Emergency stop function on all accessible areas Appropriate failure detection / alarm notification Appropriate closure of all the rotating parts Proper earthing of the equipment All electrical/ wirings properly insulated and cancelled 6.2 Power failure and recovery On power failure equipment shall come to rest, to protect operator, equipment the material and surroundings. On power resumption machine shall operate only after manual starting not directly 6.3 Failure mode detection Equipment shall be capable to detect the following failure, notify the operator with alarm: pressure drop at washing stations Feed water tank level low
9 Page 9 of TESTING AND DELIVERY 7.1 In order to verify labeler performance, the User shall witness the execution of the Factory Acceptance Test (FAT) procedures. 7.2 Vendor shall prepare FAT and SAT protocol and get approved from GAPL. 7.3 Delivery The labeler, with all options, equipment, and the documentation listed below, shall be delivered to the User s receiving bay Documentation Installation, operation, and maintenance instruction documentation for the labeling machine shall be developed Document format shall comply with the following requirements. User Requirements Specification Functional Specification/Requirements Design Specifications Controls Test Hardware Installation Test Operational Test Factory Acceptance Test Operator, Maintenance and Service Manuals Process and Instrumentation Diagram (P&ID) Control Schematics Control Panel Assembly Drawings Equipment Assembly Drawings Spare Parts List other relevant documents
10 Page 10 of QUALIFICATION REQUIREMENT 8.1 General 8.1.1Equipment shall be qualified for design phase (DQ), installation phase (IQ), Operational phase (OQ) and the performance phase (PQ) Vendor shall support client in execution of all the qualification phases. 8.2 Desired documents Supply package Following documents, but not limited to these, are expected from the vendor as part of the supply package Filled in URS Equipment layout drawing fitted in the room layout block Detail technical offer that support the compliance of the URS Critical list of major component, devices and instruments with their specific functions, specifications data sheet Schematic diagram of the equipment Post ordering Functional design specification and technical specification, that should contain the following: Equipment descriptions and its function Equipment operation steps List of failure indications List of input/outputs and its functions Delivery of the equipment Vendor shall provide the following documents in the delivery package Operation and maintenance manuals, preventive maintenance schedule for equipment major component as well as the operating system. Installation instructions/ guideline for equipment. Detailed drawing marking clearly all the necessary dimensions and locations of utilities along with requirement of utilities on the drawing along with the offer. Spare and/ or change parts list with ordering information. Types of Lubricants used for lubrication and specification. Instrument calibration certificates. Guaranty/ warranty certificates for each equipment. MOC certificates for S316 material used for the machine.
11 Page 11 of TRAINING & TECHNICAL SUPPORT 9.1 User training shall consist of minimum 2 days of Operator training and 1 day of Maintenance training. 9.2 Technical support shall be provided by personnel visit via telephone / electronic media for a period of one years following the completion of validation activities. 9.3 A recommended replacement parts list including normal lead times shall be provided for the machine 10.0 GOOD ENGINEERING PRACTICES 10.1 Equipment must be fabricated following all Good Engineering Practices. The vendor s Quality System must follow applicable national standards 10.3 All sensors, controllers, PLC, indicators and will have to be calibrated, Original calibration certificate to be submitted by the vendor 10.4 All material of construction should have test certificates CONSTRAINTS Equipment location and available space at GAPL 11.1 This equipment will be installed in the existing available area - L X B X H: 2500 X 1500 X 2000 mm Conveyer height: 860 mm (to be verified by the vendor before fabrication of the machine). Floor: Ground Floor Department: Liquid oral (Production) location : Bottle washing room 11.2 Site visit preferred for the confirmation of exact location for new installation of the machine
12 Page 12 of SCOPE OF SUPPLY 1. The supply, installation, commissioning and validation has to be done by the supplier at Goa Antibiotics & Pharmaceuticals Ltd. Tuem -pernem Goa. However FAT will be perform by GAPL team at manufacture site. 2. Vender shall depute their technical person for installation, commissioning and validation of machine. 3. Adjusting Conveyer height of the machine to match the existing bottle packing line at GAPL is in the scope of supplier 4. All utility points such as electrical, compressed air line shall be provided by GAPL. 5. Utilities such as vaccum is in scope of the manufacturer 6. All the cabling, electrical fittings, transfer pipes etc., up to the functional point ( single utility point) is in the scope of GAPL and from functional point to the respective machine shall be in the scope of manufacturer. 7. Proper Concealing/ aesthetics of all electrical cables used for the machine is in the scope of manufacturer/supplier 8. Vendor shall prepare FAT protocol and get approved from GAPL. 9. Vendor shall prepare qualification document protocol and get approved from GAPL. 10. Calibration of instruments/ components is in the scope of vendor. 11. Vendor shall provide necessary test certificates at the time of installation. 12. Warrantee - 12 months from the date of commissioning. 13. Proper earthing to the machine is in the scope of the manufacturer/ supplier 14. DQ/IQ/OQ is in the scope of manufacturer/ supplier 15. Specific requirement for motor - Kirloskar / Compton Greaves/ Remi / Bharat Bijlee
13 Page 13 of ABBREVIATIONS 01. GAPL : Goa Antibiotics and Pharmaceutical Ltd. 02. HLL : Hindustan Life Care Limited 03. URS : User Requirement Specifications 04. cgmp : Current good manufacturing practices 05. PET : Polyethelyne terephthalate 06. UV : Ultra Violet 07. FAT : Factory Acceptance test 08. SA : Site acceptance Test 09. DQ : Design Qualification 10. OQ : Operational Qualification 11. PQ : Performance Qualification 12. IQ : Installation Qualification 13. WHO : World health Organization 14. SS : Stainless Steel 15. TC : Technetium 16. µ : Micron 17. NLT : Not Less Than 18. PLC : Programmable Logic Controller 19. SAT - Site Acceptance Test
35 STATION DOUBLE ROTORY COMPRESSION MACHINE
Page 1 of 16 User Requirement Specifications 35 STATION DOUBLE ROTORY Equipment ID: T-35COMP 01 Page 2 of 16 Table of Contents 1.0 APPROVAL SIGNATURES 2.0 OVERVIEW 3.0 PROCESS DESCRIPTION 4.0 PRODUCTIVITY
More informationUser Requirement Specifications
Page 1 of 15 User Requirement Specifications Tablet Inspection Belt Equipment ID: T-INSB01 Page 2 of 15 Table of Contents 1.0 APPROVAL SIGNATURES 2.0 OVERVIEW 3.0 PROCESS DESCRIPTION 4.0 PRODUCTIVITY REQUIREMENT
More informationUser Requirement Specifications
Page 1 of 18 User Requirement Specifications Fluid bed drier Equipment ID: T-FBD01 Page 2 of 18 Table of Contents 1.0 APPROVAL SIGNATURES 2.0 OVERVIEW 3.0 PROCESS DESCRIPTION 4.0 PRODUCTIVITY REQUIREMENT
More informationUser Requirement Specifications
Page 1 of 18 ANNEXURE I User Requirement Specifications Machine - Fluid Bed Dryer Capacity-250 kg Page 2 of 18 Table of Contents page no 1. APPROVAL SIGNATURES..03 2. INTRODUCTION.04 3. OVERVIEW..04 4.
More information«Company» «Address1» «Address2» «City» Sub.: Purchase of Capsule Polishing Machine. 01 No. Detailed Specifications as given below.
INDIAN INSTITUTE OF INTEGRATIVE MEDICINE (Formerly known as RRL) (Council of Scientific & Industrial Research CANAL ROAD, JAMMU Phones: 0191-2569000, 2569001, to 10 (11 Lines) Telefax: 2569023, 2569019,
More informationVALIDATION AS A KEY TOOL IN SUCCESSFUL TRANSFER OR ESTABLISHMENT OF A MEDICAL DEVICE COMPANY IN A NEW FACILITY
VALIDATION AS A KEY TOOL IN SUCCESSFUL TRANSFER OR ESTABLISHMENT OF A MEDICAL DEVICE COMPANY IN A NEW FACILITY Oren Levin, Diane Gordon VisionCare Ophthalmic Technologies, POB 3879, Petah Tikva 49130,
More informationYOUR PARTNER FOR TURNKEY SOLUTIONS IN PHARMA & BIOTECH INDUSTRY AN ISO 9001:2008 CERTIFIED COMPANY
CHEMION PURIFIED WATER GENERATION, STORAGE AND DISTRIBUTION SYSTEM YOUR PARTNER FOR TURNKEY SOLUTIONS IN PHARMA & BIOTECH INDUSTRY AN ISO 9001:2008 CERTIFIED COMPANY CHEMION ENGINEERING THE COMPANY The
More informationQUALITY ASSURANCE PROTOCOL (QAP)
PREFACE This Standard details the level of documentation that PVT.LTD (IET) will provide during a contract for fabricating tank(s) or portable equipment s. Extensive documentation is required for this
More informationSPECIFICATION. Ir-192 hot cell
SPECIFICATION Ir-192 hot cell 1. Scope The purpose of this document is to define the specifications for the construction of a class C hot cell with two chambers (hereinafter referred as the System ) intended
More informationIstanbul May 31, 2001
Pürifiye Su Sistemleri Validasyonu Istanbul, Turkey May 31, 2001 Peter Drechsler Aventis Pharm- Frankfurt, Germany Aventis Pharma Exubera Inhaled Insulin Table of content for Presentation: * Validation
More informationGAMP 4/5 Prospective / retrospective Qualification of water treatment plants) P. Dony
GAMP 4/5 Prospective / retrospective Qualification of water treatment plants) P. Dony 31.03.2008 Table of contents Slide 2 1. GAMP 4 and GAMP 5 differences 2. CHRIST prospective Qualification strategy
More informationSECTION VERTICAL MEZZANINE GATE U.S. Patent No:
Page 1 of 6 Part 1. GENERAL SECTION 05522 VERTICAL MEZZANINE GATE U.S. Patent No: 5806245 1.1 SECTION INCLUDES A. Specialty custom designed, manual, fully electric, electric/pneumatic or fully pneumatic
More informationValidation. An Easy to Understand Guide Validating Purified Water Systems
Validation Overview Validation Documentation Validation Activities Validation Mistakes Validation Protocols Test Selection Common Verifications When to test Test Layout and Content Validation Protocol
More informationEquipment Qualification Ensure Fit for Intended Use. IVT Amsterdam Conference Mary Sexton. 19 Mar 2015
Equipment Qualification Ensure Fit for Intended Use IVT Amsterdam Conference Mary Sexton 19 Mar 2015 Equipment Qualification Ensure Fit for Intended Use 1. Types of Qualification 2. Validating Equipment
More informationLAB DIVISION. STERILIZATION cglp Process Equipment for Research and Microbiological Laboratories
LAB DIVISION STERILIZATION cglp Process Equipment for Research and Microbiological Laboratories LAB division Company LAST Technology is the worldwide provider for cleaning, decontamination, disinfection
More informationOki (High Pressure Boiler Plant)
Bharat Heavy Electricals Limited 1717TC.1 Oki (High Pressure Boiler Plant) Tiruchirappalli 620014, TAMIL NADU, INDIA An ISO 9001 MATERIALS MANAGEMENT / CAPITAL EQUIPMENT Company ENQUIRY Phone: +91 431
More informationSuncombe Ltd, Jade House, Lockfield Avenue, Brimsdown, Enfield, Middlesex, EN37JY, United Kingdom T +44(0) F +44(0) E
Suncombe Ltd, Jade House, Lockfield Avenue, Brimsdown, Enfield, Middlesex, EN37JY, United Kingdom T +44(0)20-8443-3454 F +44(0)20-8443-3969 E info@suncombe.com W www.suncombe.com Message From Chairman
More informationManaging Validation. Paperless Recorders
Managing Validation Paperless Recorders Multitrend Plus Validation Background The past five years has seen an increase in the use of computerized systems and products in the pharmaceutical and bio-pharmaceutical
More informationDesign, Fabrication, Supply, Installation & Commissioning of Scissor Lift for ITMT Building at. CREST, Hosakote. Indian Institute of Astrophysics
Design, Fabrication, Supply, Installation & Commissioning of Scissor Lift for ITMT Building at CREST, Hosakote Indian Institute of Astrophysics Bangalore October 2017 1. Introduction The required scissor
More informationDepyrogenation Oven. depyrogenation and dry heat sterilization
Depyrogenation Oven depyrogenation and dry heat sterilization Lytzen philosophy The philosophy behind the Lytzen Depyrogenation ovens is never to compromize on our high level of quality in every detail.
More informationStainless Steel Aeration Equipment Specification
Section 15 Stainless Steel Aeration Equipment Specification Part 1 - General 1.01 Description A. Scope of Work 1. Furnish, install and test aeration system including air mains, drop pipes, valves, expansion
More informationSECTION INSTALLATION OF OWNER-FURNISHED PRODUCTS
SECTION 13 00 50 INSTALLATION OF PART 1 GENERAL 1.1 GENERAL A. Furnish and install all tools, supplies, materials, equipment, appurtenances, and labor necessary for the installation, testing, and placing
More informationSECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS
SECTION 260548 - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Isolation pads. 2. Spring isolators. 3. Restrained spring isolators. 4. Channel
More information1. Vertical reciprocating conveyor, Hydraulic straddle VRC.
PART 1: GENERAL 1.01 Section Includes: 1. Vertical reciprocating conveyor, Hydraulic straddle VRC. a. Machine, controller, platform, structural steel hoist frame. b. Wire mesh enclosure and gates. Related
More information1. Vertical reciprocating conveyor, Hydraulic straddle VRC.
PART 1: GENERAL 1.01 Section Includes: 1. Vertical reciprocating conveyor, Hydraulic straddle VRC. a. Machine, controller, platform, structural steel hoist frame. b. Wire mesh enclosure and gates. Related
More informationMachine Specification
Machine Specification Machine Type: 1230A 2 Component: 1x Base 1x Hardener Adhesive pump system Table of Contents 1230A Machine Specification ------------------------------------------------------------
More informationSPECIFICATION CUM COMPLIANCE CERTIFICATION FOR PRESSURE TESTING PUMP
BHARAT HEAVY ELECTRICAL LIMITED Enquiry No. : UNIT'S ADDRESS Due Date : UNIT'S PHONE NOS. Supplier Qtn. No.: CONTACT PERSON'S NAME/DESIGN./PHONE NO. Date : E-MAIL (FROM PURCHASE DEPTT.) NOTE:- SPECIFICATION
More information# 3: KMI Pulp Moulding System # KMI
# 3: KMI Pulp Moulding System # KMI-400-600 Moulder #M400-600, Process #P400-600, Dryer #- D400-600, stacker and packing table, Estimated Delivery: 7 months from receipt of deposit for machine On site
More informationPERFORMANCE QUALIFICATION PROTOCOL HVAC SYSTEM
Page 1 of 24 PERFORMANCE QUALIFICATION PROTOCOL FOR HVAC SYSTEM Signing of this Performance Qualification Protocol indicates agreement with the Validation Master Plan approach of the equipment. Further
More informationUser Requirement Specification Specyfikacja Wymagań Użytkownika
\ Project / Projekt: Albumina dożylna nowej generacji oparta o wielostopniowy proces inaktywacji wirusów Plasma Fractionation Department BIOMED-LUBLIN Wytwórnia Surowic i Szczepionek S.A. ALBUMINA / ALBUMIN
More informationNORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017
SECTION 22 0548 - PIPING AND EQUIPMENT PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationProject QMS and Quality by Design Activities
QMS and Quality by Design Activities Main Topics of the Presentation Quality by Design Structure Critical Control Points in the Different Phases 1. Acquisition Phase 2. Design and Engineering Phase 3.
More informationFS 1000/3000 SIP BIOREACTORS/FERMENTORS FOR INDUSTRIAL PROCESSES
FS 1000/3000 SIP BIOREACTORS/FERMENTORS FOR INDUSTRIAL PROCESSES THE COMPANY Bionet is a specialist in bioprocesses engineering. We provide equipment (Bioreactors, Cross-Flow Filtration Systems and Cleaning-In-Place
More informationEquipment Design Consideration for Cleaning & Cleaning Validation
Equipment Design Consideration for Cleaning & Cleaning Validation Gamal Amer, Ph. D. Principal Premier Compliance Services, Inc. All rights reserved. Do not copy without permission. 1 Cleaning and Cleaning
More informationBID DOCUMENT IFB: GAPL/TENDER/PM/001/ / DT TENDER FOR SUPPLY AND DELIVERY OF PACKAGING MATERIAL (FOILS AND FILMS)
GOA ANTIBIOTICS & PHARMACEUTICALS LTD (SUBSIDIARY OF HLL LIFECARE LIMITED A GOVERNMENT OF INDIA ENTERPRISE) NEAR TUEM INDUSTRIAL ESTATE TUEM, PERNEM-GOA. 403512 PH NO. 0832 2201416/7 FAX NO. 0832 2201278
More informationTYPICAL INSTALLATION INSTRUCTIONS
TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect
More informationEDGEWATER, FLORIDA JUNE 14, 2010
SECTION 12 2413 - ROLLER WINDOW SHADES PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationTABLE OF CONTENTS II. MISSION VISION & OBJECTIVES... 4 III. SERVICES ) INDUSTRIAL AUTOMATION SOLUTIONS... 5 I.
COMPANY PROFILE TABLE OF CONTENTS... 2... 3 II. MISSION VISION & OBJECTIVES... 4 III. SERVICES... 5 1) INDUSTRIAL AUTOMATION SOLUTIONS... 5 A) TURNKEY PLC/SCADA SOLUTIONS... 5 B) FIELD SERVICES... 6 C)
More informationMATERIAL SPECIFICATION FOR LUMINAIRE RAISING AND LOWERING EQUIPMENT
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 2476 JANUARY 1990 MATERIAL SPECIFICATION FOR LUMINAIRE RAISING AND LOWERING EQUIPMENT 2476.01 SCOPE 2476.02 REFERENCES 2476.05 MATERIALS TABLE OF CONTENTS
More informationStudent Services & Classroom Addition SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS
SECTION 26 05 48 - VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Isolation pads. 2. Spring isolators. 3. Restrained spring isolators. 4. Channel
More informationInnovative. to the pharmaceutical, biotechnology and advanced technology. and equipment. Our learning management
Innovative S o l u t i o n s Pharma-Tech Process and Facilities Services is an industry leader in providing innovative technical consulting and staff-augmentation services to the pharmaceutical, biotechnology
More informationGLOBAL INDUSTRIAL WATER
MANUFACTURING FACILITY, TAMPA, FL USA 5321 West Crenshaw Street Tampa, FL 33634 USA 1 P age Trade Name: GENERAL INFORMATION Global Industrial Water Inc. (GIW) Date Incorporated: January 16 th, 2009 Factory
More informationSECTION SANITARY WASTE INTERCEPTORS
SECTION 22 13 23 SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable in the section
More informationTypical Clientele. Products
Message From Chairman Our company was created over 50 years ago specifically to supply a high quality range of process cleaning and sanitary processing equipment. To continually achieve our goals, we use
More informationSAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES
SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:
More informationSECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System
SECTION 13096 RADIO FREQUENCY SHIELDING ENCLOSURE RF Welded System Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13096-1 RF WELDED SYSTEM PART 1 GENERAL 1.1 SECTION
More informationMOTHER DAIRY A UNIT OF GUJARAT CO-OPERATIVE MILK MARKETING FEDERATION LIMITED PURCHASE ENQUIRY
PURCHASE ENQUIRY Inquiry No : MDG/PUR/PKS/ENQ/BT, Dated: April 17, 2014 Description Qty : Purchase Inquiry for Supply, Installation and commissioning and testing of fully automatic Butter Thermoforming,
More informationUniversity of Delaware
SECTION 22 05 00_COMMON WORK FOR PLUMBING SYSTEM University Contact: Energy & Engineering Group (302) 831-1744 Part 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality
More informationB. Provide equipment complying with this specification and manufactured by one of the following:
SECTION 230910 PAINT SPRAY BOOTH PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Provide Paint Spray Booth, Prep Booth and Paint Mix Room, and associated ventilation equipment, complying with the
More informationSECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT
Page 220548-1 SECTION 220548 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationGMP Compliance. George Acevedo, CQV Senior Engineer M+W Singapore Pte. Ltd
GMP Compliance George Acevedo, CQV Senior Engineer M+W Singapore Pte. Ltd June 2017 Overview GMP Definition and Regulation Our Philosophy and Strategy for Compliance Project Lifecycle Deliverables Master
More informationWorld Journal of Pharmaceutical Research SJIF Impact Factor 5.990
SJIF Impact Factor 5.990 Volume 4, Issue 9, 444-454. Review Article ISSN 2277 7105 COMPUTER SYSTEM VALIDATION: A REVIEW Patil Yogesh* Mali Kamlesh, Bodhane Mohini, Ram Phad, Shaikh Ismail, Lale Shivam
More informationA. This Section includes the following sump pumps and accessories, inside the building, for building storm drainage systems:
SECTION 221429 - SUMP PUMPS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationá1058ñ ANALYTICAL INSTRUMENT QUALIFICATION
USP 41 General Information / á1058ñ 1 á1058ñ ANALYTICAL INSTRUMENT QUALIFICATION INTRODUCTION A large variety of analytical instruments, ranging from a simple apparatus to complex computerized systems,
More informationSPECIFICATION FOR AUTOMATIC DRILL POINT GRINDER
SPECIFICATION FOR AUTOMATIC DRILL POINT GRINDER NOTE :- 1. The vendor (OEM) must fill the "offered" column in compliance to specified requirements and also "Deviations". (OEM- Original Equipment Manufacturer)
More informationSECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Modular Pan System
SECTION 13096 RADIO FREQUENCY SHIELDING ENCLOSURE RF Modular Pan System Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13096-1 RF MODULAR PAN SYSTEM PART 1 GENERAL 1.1
More informationIndustry Post Package Auxiliary Equipment
Industry Post Package Auxiliary Equipment Pandpco not only supplies full-set of filling equipment but also support the filling manufacturers for updating or improving their older filling system with some
More informationStandard Monitoring System
Cleanroom-Requirements according to Annex 1, EU-GMP-Guidelines Strict requirements for compliance with the environmental conditions in the relative cleanroom classes Continuous data recording and archiving
More informationSCOPE OF WORK SUBSTATIONS
Page 2 of 11 REVISION CONTROL Issued for Internal Review Issued for Client Review Issued for DFS REVISION HISTORY Revision Date Pages Revised Remarks 00 29/08/2017 Multiple Comments incorporated 01 05/04/2018
More informationSTANDARD TECHNICAL SPECIFICATION FOR ROTAMETER VOLUME - IIB. SPECIFICATION No: PE-SS I010
STANDARD TECHNICAL SPECIFICATION FOR ROTAMETER VOLUME - IIB SPECIFICATION No: PE-SS-999-145-I010 BHARAT HEAVY ELECTRICALS LIMITED POWER SECTOR PROJECT ENGINEERING MANAGEMENT DIVISION NOIDA, INDIA SPECIFICATION
More informationPIP PCEPA003 Process Analyzer System Field Installation Guidelines
January 2016 Process Control PIP PCEPA003 Process Analyzer System Field Installation Guidelines PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry facilities,
More informations c r e w - c a p p i n g s e a l i n g p u s h - o n c a p p i n g HIGH-PERFORMANCE CAPPING Custom-designed machines to suit your applications
s c r e w - c a p p i n g s e a l i n g p u s h - o n c a p p i n g HIGH-PERFORMANCE CAPPING Custom-designed machines to suit your applications Scope Zalkin Signature Capping High quality dedicated to
More informationProponent Signature: Request for Quotes: Bottling Line Equipment & Installation RFQ# 2017PIC02
Request for Quotes: Bottling Line Equipment & Installation RFQ# 2017PIC02 Send bid to: Perennia Food & Agriculture Inc. Attention: Craig Doucet 173 Dr. Bernie MacDonald Drive Bible Hill NS B6L 2H5 Final
More informationPART A QUALIFYING CRITERIA FOR SUPPLY OF 65 M LONG WALKING BEAM TYPE COOLING BED
PART A QUALIFYING CRITERIA FOR SUPPLY OF 65 M LONG WALKING BEAM TYPE COOLING BED SECTION I The BIDDER / VENDOR has to compulsorily meet the following requirements to get qualified for submitting an offer
More informationSECTION RADIO FREQUENCY SHIELDING ENCLOSURE RF Modular Galvanized System
SECTION 13096 RADIO FREQUENCY SHIELDING ENCLOSURE RF Modular Galvanized System Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13096-1 RF MODULAR GALVANIZED SYSTEM PART
More informationTalwandi Sabo Power Limited Tender document for Design & Engineering, Supply and Erection of Slurry pumping system from Plant to Ash Dyke
Techno commercial offers are invited from the competitive bidders for the EPC contract i.e. Design, Engineering, Manufacture/Supply, Civil and Structural, Erection, Testing, Commissioning, Demonstration
More informationSection 4. Annex to IAEA Request for Proposal STATEMENT OF WORK. Primary/Secondary cooling water Heat Exchangers
Section 4 Annex to IAEA Request for Proposal 25919 STATEMENT OF WORK Primary/Secondary cooling water Heat Exchangers WWR-SM Research Reactor, UZBEKISTAN Page 1 of 17 1. Scope 1.1 This Statement of Work
More informationSPECIFICATIONS FULL AUTOMATION OF THE MULTIPURPOSE GAMMA IRRADIATION FACILITY
SPECIFICATIONS FULL AUTOMATION OF THE MULTIPURPOSE GAMMA IRRADIATION FACILITY 1. Scope This Statement of Work (SOW) describes the requirements for equipment and services necessary for the full automation
More informationEquipment Risk Management
Equipment Risk Management A Quality Systems Approach Palash Chandra Das Agenda Brief Introduction Correlation between Quantitate and qualitative approach Implementation and assessment Discussion with practical
More informationTECHNICAL SPECIFICATION OF HORIZONTAL MILLING MACHINE
SCOPE: SUPPLY, ERECTION & COMMISSIONING OF HORIZONTAL MILLING MACHINE WITH SPECIFICATIONS AS BELOW : SL. NO. DESCRIPTION OF BHEL REQUIREMENT REQUIRED OFFERED DEVIATION REMARKS 1.0 PURPOSE & WORKPIECE MATERIAL
More informationTank Scale Service Checklist
Tank Scale Service Checklist Specifying Service for Optimized Weighing Processes Selecting the right weighing equipment is an important first step to ensuring that your weighing processes are able to meet
More informationTechnical Specifications, M.O.C., Parameters, Size Range, Applications & Constructive
Technical Specifications, M.O.C., Parameters, Size Range, Applications & Constructive Points For ANJNEY brand PPCH FR Pneumatic Pipes and Fittings Product Name Anjney Brand PPCH FR Pneumatic (Inbuilt Glass
More informationCapital Projects Group Mechanical Work Commissioning Specification
Capital Projects Group Mechanical Work Commissioning Specification Specification 20 05 40 Revision 0 Date: August 2018 Mechanical Work Commissioning Specification Specification 20 05 40 Publication Date:
More informationPULSED AIR MIXING SYSTEM
PART 1: GENERAL 1.01 SCOPE OF WORK A. Background and Objective: Gulf Coast Waste Disposal Authority s (GCA S) Bayport Facility located at 10800 Bay Area Blvd., Pasadena, Tx.77505 has experienced an ongoing
More informationSECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION
Page 210500-1 SECTION 210500 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationFLARING MACHINE MAINTENANCE & INSTRUCTIONS MANUAL. Allswage UK. Roebuck Street, West Bromwich, B70 6RB
FLARING MACHINE MAINTENANCE & INSTRUCTIONS MANUAL A. WARRANTY AND RESPONSIBILITY Warranty: It's the supplier's responsibility to guarantee the conformity of the product, assuring that it's manufactured
More informationInstallation Qualification Equipment (Reference SOP: )
Installation Qualification Equipment (Reference SOP: ) Project: Equipment Description: Project No: Serial No: Manufacturer: Model No: Equipment No: Location: Protocol: PROGRAM INDEX 1. OBJECTIVE...3 2.
More informationPART- A ROTARY TABLE : 3000 X 4000 MM
ROTARY TABLE : SIZE - 3000 X 4000 The BIDDER has to compulsorily meet the following requirements to get qualified for considering the technical offer for the ROTARY TABLE - 3000 X 4000 MM SL NO 1.0 REQUIREMENTS
More informationSECTION LINEAR MOTION SLUDGE MIXERS
SECTION 11480 LINEAR MOTION SLUDGE MIXERS PART 1 -- GENERAL 1.01 THE REQUIREMENT A. The Contractor shall furnish, install, adjust, finish paint and test one (1) linear motion sludge mixer for mounting
More informationMOTHER DAIRY A UNIT OF GUJARAT CO-OPERATIVE MILK MARKETING FEDERATION LIMITED AMENDED PURCHASE INQUIRY
AMENDED PURCHASE INQUIRY Inquiry No : MDG/PUR/PKS/ENQ/Powder, Dated: July 27, 2013 Description : Purchase Inquiry for Supply Installation and Commissioning of fully Automatic Powder packing machine. Qty
More informationHISTORY AND MILESTONES
HISTORY AND MILESTONES HISTORY AND MILESTONES DOC S.r.l., Documentation Organization & Consultancy, was established in 1997 by MASCO group C.E.O. Eng. Alberto Borella and Eng. Paolo Curtò who became Managing
More informationArchitect s Project Number of 5 Decentralized HVAC Equipment District Master Specs 2013 Edition
PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 23 81 00 DECENTRALIZED HVAC EQUIPMENT A. The other Contract Documents complement the requirements of this section. The General requirements apply to the work
More informationGuaranteed not to jam
FreeGlide The only In-Line Powder Sampler guaranteed not to jam Patent Pending QUOTR REQUEST Tel: +44 (0)1675 466992 Email: www.qclabequipment.com info@sampling.com Web: www.sampling.com 1 FreeGlide The
More informationUniversity of Delaware
SECTION 23 05 00_COMMON WORK FOR HVAC SYSTEMS University Contact: Energy & Engineering Group (302) 831-1744 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Start up 2. Factory Training 3. Quality Control
More informationMicroBio MB1 IQ/OQ/PQ
Document No: MicroBio MB1 IQ/OQ/PQ Installation, Operational and Performance Qualification Protocol and Report for the MicroBio MB1 Bioaerosol Sampler Issue: 2 P0001W004 : Issue: 2 / 1 26 Cantium Scientific
More informationBAUSCH + STRÖBEL. Technical Specification SP100/200 SP3060. Filling machine for bottles Page 1 of 6
BAUSCH + STRÖBEL Technical SP100/200 Filling machine for bottles 2012-06-04 Page 1 of 6 Contents 1. General 3 1.1 Application 3 2. Machine design 3 2.1 Basic construction 3 2.2 Container infeed 3 2.3 Dosing
More informationPIKES PEAK PARKING RESTORATION TABLE OF CONTENTS
23 HEATING, VENTILATING AND AIR CONDITIONING TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING - Basic HVAC Requirements 238239.19 - Wall and Ceiling Unit Heaters
More informationBHARAT HEAVY ELECTRICAL LIMITED, JHANSI Specification No.
NOTE : SCOPE : BHARAT HEAVY ELECTRICAL LIMITED, JHANSI Specification No. CRJ/9577 Item No. SP/CRJ/9577/1 & SP/CRJ/9577/2 Location NEW M.G.HOUSE Quantity 2 NOS. DESIGN, MANUFACTURING, SUPPLY, ERECTION &
More informationC960 - C970 AUTOMATIC TUBEFILLER FOR PHARMACEUTICAL, COSMETIC AND CHEMICAL PRODUCTS. Solid Dose Sol
C960 - C970 AUTOMATIC TUBEFILLER FOR PHARMACEUTICAL, COSMETIC AND CHEMICAL PRODUCTS Solid Dose Sol A COURSE OF CONTINUOUS GROWTH IT WAS IN 1970 THAT COMADIS LAUNCHED THE FIRST OF A SUCCESSFUL TUBEFILLERS
More informationBus Facility
SECTION 32 31 13.53 PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply
More informationGMP WORKSHOP. WATER for Pharmaceutical Use
GMP WORKSHOP WATER for Pharmaceutical Use DCVMN WORKSHOP - Victor Maqueda - May 30, 31, Learning objectives At the end of this module, the participant should be able to identify critical points in Water
More informationARRANGEMENT AND WORKING OF MULTIPORT FLOW SELECTOR VALVE IN PRODUCTION MANIFOLD:
GENERAL DESCRIPTION Crude oil well test manifold to be provide as Multiport Flow Selector (MPFS) technology. It provides a cost effective method for selecting and diverting well fluids from an individual
More informationSECTION COOLING TOWER
PART 1 GENERAL 1.1 SECTION INCLUDES A. Mechanical induced draft Cooling Tower B. Controls C. Ladder and handrails 1.2 REFERENCES SECTION 23 65 00 COOLING TOWER A. ANSI/AFBMA 9 - Load Rating and Fatigue
More informationThe procurement, qualification and calibration of lab instruments: An Overview
The procurement, qualification and calibration of lab instruments: An Overview The reliability of analytical data generated from chemical and physical analyses is critically dependent on three factors:
More informationCRON HDI-920 Site Planning. Customer Responsibilities
Customer Responsibilities CRON HDI-920 Site Planning You are responsible for providing the following items below to help ensure a trouble free installation. Adequate delivery access (i.e. Company Loading
More informationSECTION SANITARY WASTE INTERCEPTORS
SECTION 22 13 23 SANITARY WASTE INTERCEPTORS PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Delete between //----// if not applicable to project. Also delete any other item or paragraph not applicable
More informationSPECIFICATIONS - DETAILED PROVISIONS Section Progressing Cavity Pump C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 11938 - Progressing Cavity Pump C O N T E N T S PART 1 - GENERAL... 1 1.01 GENERAL... 1 1.02 RELATED SPECIFICATION SECTIONS... 1 1.03 MANUFACTURERS... 1 PART
More informationPRELIMINARY QUOTATION No for the supply of. STACKER FOR SHEET max L3000 x W2100 mm
Preliminary quotation No. 16-024.00 pag. 1 PRELIMINARY QUOTATION No. 16-024.00 for the supply of STACKER FOR SHEET max L3000 x W2100 mm Preliminary quotation No. 16-024.00 pag. 2 Preliminary quotation
More informationUnion County Vocational - Technical Schools Scotch Plains, New Jersey
SECTION 102239 - FOLDING PANEL PARTITIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification
More informationSECTION CONVECTORS
SECTION 23 82 33 PART 1 - GENERAL 1.1 DESCRIPTION SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between // // if not applicable to project. Also delete any other item or paragraph