CERN electricity consumption forecast & validation

Size: px
Start display at page:

Download "CERN electricity consumption forecast & validation"

Transcription

1 CERN electricity consumption forecast & validation Bruno Mouche, CERN Electrical Engineering Group EN-EL 23 November 2017

2 Presentation outline Part 1: Introduction to electricity at CERN Part 2: Electricity consumption monitoring tool (WebEnergy) Part 3: Electricity consumption forecasting tool 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 2

3 Introduction to electricity at CERN (Part 1) 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 3

4 CERN s accelerator complex LHC SPS PS 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 4

5 ME50 L9 L59 L1 L8 L6 L4 L2 CERN s electrical network (Single Line Diagram) 4 high voltage levels 400 kv (main incomer, FR) 66 kv (LHC machine) 18 kv (main distribution) 3.3 kv (power motors) kv alternative supply (CH) limited power 400 kv BE 18kV Pulsed Network (SPS / North Area) SPS Comp. Booster 17 MVAr BEQ3 EHT1 BEQ2 EHT2 BEQ1 90MVA 90MVA SPS SPS PS.. SPS Main conversion stations EHT102 ME59 70MVA ME9 Machine Meyrin - PSC ME59 ISOLDE NA NA BE9-18kV Autotransfert Backup lines to Meyrin & Prévessin General Services WA EHT3 90MVA 400 kv CERN 15 MVA ME9 General Services Meyrin - PSC ME10 General Services SPS / North Area / Prévessin BE91 Admin. G Prévessin 513 Computer Center FRANCE 400 kv RTE (Bois Tollot) EHT7 BE9 70MVA MP7 30MVA 66kV MP5 60MVA G ME9 Safety Network PS EHT4 110MVA EHT102 LHC1 70MVA SEM12 EHT102 38MVA Comp. 25 MVAr EHT5 110MVA EHT102 38MVA Comp. 25 MVAr EHT102 38MVA LHC Machine Network LHC General Services Loop Comp. 25 MVAr EHT102 38MVA Comp. 25 MVAr EHT103 38MVA LHC EHT611 60MVA EHT612 60MA 18 kv 130kV SIG SWITZERLAND 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 5

6 Electricity consumption: key figures (1) GWh (annual consumption) GWh (normal operation year) 350 GWh (shutdown year) MW (max active power) 185 MW (daily average) 200 MW (10-min average) 320 MW (instantaneous) City of Bucharest (~2 M inhab.): ~ 5000 GWh City of Bucharest: ~ 600 MW (daily average) Run 1 Long shutdown 1 Run Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 6

7 Electricity consumption: key figures (2) Run 1 Run 2 Long shutdown 1 57 % 25 % 11 % 7 % * * Site base = office buildings (Meyrin & Prevessin sites) central services (computer center, pumping station) 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 7

8 Electricity consumption: key figures (3) Current unit prices (up to ) (French supply only) Electricity: 37 / MWh (winter: 45; summer: 32) Provider: Transmission: 3.1 / MWh Provider: No taxes (international organization status) 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 8

9 Electricity consumption monitoring tool (WebEnergy) (Part 2) 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 9

10 ME50 L9 L59 L1 L8 L6 L4 L2 Basic principles (1) HISTORY 400 kv CERN FRANCE 400 kv RTE (Bois Tollot) Before 2012: publication of monthly reports manually generated PDF format 2012: start of the project of online tool 2013: first release of the WebEnergy : following Long Shutdown #1, complete review and upgrade (engine, counters, formulas) 2016: full usage and publicity via various CERN forums BE 18kV Pulsed Network (SPS / North Area) Comp. Booster 17 MVAr BEQ3 EHT1 BEQ2 EHT2 BEQ1 90MVA 90MVA SPS SPS PS.. SPS Main conversion stations EHT102 ME59 70MVA ME9 Machine Meyrin - PSC ME59 ISOLDE NA NA BE9-18kV Autotransfert Backup lines to Meyrin & Prévessin General Services WA EHT3 90MVA 15 MVA ME9 General Services Meyrin - PSC ME10 General Services SPS / North Area / Prévessin EHT611 60MVA 130kV SIG BE91 Admin. SWITZERLAND G Prévessin EHT612 60MA 513 Computer Center EHT7 BE9 70MVA MP7 30MVA 66kV MP5 60MVA G ME9 Safety Network EHT4 110MVA EHT102 LHC1 70MVA SEM12 EHT102 38MVA Comp. 25 MVAr EHT5 110MVA EHT102 38MVA Comp. 25 MVAr EHT102 38MVA LHC Machine Network LHC General Services Loop Comp. 25 MVAr EHT102 38MVA Comp. 25 MVAr EHT103 38MVA RTE official counter CERN s 1st stage of counters (other counters are disseminated throughout the high voltage network) 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 10

11 Basic principles (2) Use of positive and negative energy counters, embedded in the HV protection relays ; Named Ea+, Ea- (Energie active +/-) P (MW) 1 counter = 1 HV feeder Logged by the SCADA and stored in long-term database Ea+ (MWh) t counter reset Ea+(1) Ea+(2) t Daily consumption of facilities and sites calculated by addition (or substraction) of counters, following a table of coefficients («counting tree», published to users) Manual corrections possible Ea- (MWh) Ea = Ea+ Ea- P_avg = Ea / t Ea- t 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 11

12 Counting tree Level 1 CERN (classified by site) CERN (other classific ation) Level 2 LHC SPS PS Meyrin Level 3 Machine Experi ments General Services Pulsed Stable Magn ets PS Comp Center Level 4 Cryo CV 1 2 Level Counters Feeders 18kV / 3.3 kv Datapoints EMD118/BE Ea+ EMD212/BE Ea+ Ea- Ea- 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 12

13 Technical features / Usage statistics Feeders 257 energy counters ( ) 18 kv / 3.3 kv SPS Computer 116 end-consumers ( Cryo LHC4, Magnets, Center ) For each consumer, 1 daily value of average power and energy Display of yearly curves, with possible zoom on months Data available since 2008 New data published daily Global accuracy: 99.8% w.r.t. EDF invoice ~ 150 single users per year, from a large variety of CERN departments (50%) 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 13

14 Tool overview Engine: Java 8 & Jqplot 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 14

15 Usage of the monitoring tool Understanding of CERN s processes and their influence on consumption + tracking of evolutions pilot consolidations of the electrical network Periodic communication to CERN s Energy Management Panel (EMP), bringing together CERN s major consumers: exchange of information; communication channels. Consumption forecasts (see next part) CERN internal budget plans Efficient purchasing of electricity Various use : open to all CERN users 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 15

16 Electricity consumption forecasting tool (Part 3) 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 16

17 CERN needs for electricity consumption forecasts (1) Need #1 (up to 2013): CERN s internal budget plans 5 years plan 1 value per month Need #2 ( ): new electricity contract ( open market) Tendering process Need for increased time-resolution : 1 value per day over 5 years 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 17

18 CERN needs for electricity consumption forecasts (2) Need #3 (2016): Purchasing of electricity under the new contract framework (open market) Rewards for accurate forecasts (bonus & super-bonus) 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 18

19 Overview of the forecasting tool (1) In-house developed tool (Microsoft Excel + VBA macros) For a list of 32 high level consumers (constituting the entirety of CERN) a certain number of consumption modes (RUN, TECHNICAL STOP, LONG SHUTDOWN ) are defined, with the corresponding daily power foreseen at a given period (RUN2, RUN3 ) Pavg_daily LHC LHC from (MW) General services Ventilation RUN 2 RUN TS YETS LS RUN 3 RUN (to be TS assessed) YETS LS additional modes (STARTING and STOPPING) are available for linear transition between two modes 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 19

20 Overview of the forecasting tool (2) The 32 consumers are grouped into 14 machines (according to their possible dependencies in terms of schedule) Based on official physics schedules of the 14 machines (or typical consumption patterns) the forecast daily electrical powers for each of the 32 high level consumers are tabulated and available for display and calculations DATES 32 CONSUMERS COLOR LEGEND FOR EACH MODE 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 20

21 Overview of the forecasting tool (3) Possibility of manual corrections for unmodeled / unforeseen events The tool also includes a versioning capability to keep track and easily recall the previous forecasts continuous improvement 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 21

22 Forecast VS reality Thanks to deep integration with the WebEnergy monitoring tool: throughout the year, the forecast curves can be compared to the real consumptions, at CERN level and for each consumer The comparison is presented 5 times per year to the Energy Management Panel to get feedback, discuss the deviations, improve the model, create new consumption modes, etc. 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 22

23 Usage of the forecasts (1) : MTP Editing the electricity document for CERN s MTP (Medium Term Plan) 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 23

24 Usage of the forecasts (2) : contract management CERN s electricity contract includes a monthly bonus system for accurate forecasts (new forecasts can be sent anytime, with 2 days notice) Discount = 0.1 / MWh if monthly_deviation 15% Additional 0.05 / MWh if monthly_deviation 5% monthly_deviation = hourly_deviations(mwh) monthly_consumption(mwh) Marginal amount ( % of the bill) but in absolute value = ~100 k discount per year = good incentive 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 24

25 Communication with the electricity provider (2016) First year: tuning of the model... Sent to EDF = model communication and modelization delays (dev 20%) (15%) (16%) (13%) (17%) (6%) (6%) (8%) (8%) (8%) (14%) (11%) = Main manual corrections REASONS FOR REFORECASTING: Manual correction of model drift: 8 Info incident: 2 Info beams operation: 2 Schedule change: 2 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 25

26 Communication with the electricity provider (2017) Second year: quite good Sent to EDF = model communication and modelization delays (dev 14%) (14%) (11%) (8%) (9%) (7%) (8%) (4.9%) (6%) (7%) Super bonus in august. REASONS FOR REFORECASTING: Info beams operation: 1 Schedule change: 5 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 26

27 Conclusion CERN has put in place a forecasting tool that is now working satisfactorily It relies on multiple inputs (power per mode for each main user, machine schedules) and is complemented by a monitoring tool open to CERN community These tools allow regular energy management and monitoring. In addition, it is expected that the acquired knowledge will be an asset when retendering for the next electricity contract (2021 onwards) The monitoring tool will also serve as a basis for a project of ʺvirtual invoicingʺ to the main consumers (consumption awareness) Next steps considered: Continuous maintenance/upgrades (machines/modes/electrical infrastructure) Increased time resolution Monitoring of reactive power Alternative counting tree electrical network oriented (load of substations, busbars, cables) 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 27

28 Thank you Questions?

29 Spare slides 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 29

30 CERN s electrical network (geographical) 4 high voltage levels 400 kv (main incomer, FR) 6 switchgears 66 kv (LHC machine) 17 switchgears 18 kv (main distribution) 3.3 kv (power motors) ~220 switchgears kv backup supply (CH) owned by Swiss DSO ~100 substations / 900 switchgears R.T.E. 400 kv 66 kv PS Backup 130 kv Limited power (60 MVA) 18 kv 3.3 kv 1 km 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 30

31 Basic principles (2) Use of positive and negative energy counters, embedded in the HV protection relays ; Named Ea+, Ea- (Energie active +/-) P (MW) 1 counter = 1 HV feeder Logged by the SCADA and stored in long-term database t Time integration = memory = security against loss of data (communication problems ) BUT needs detection of counter resets Ea+ (MWh) counter reset Ea+(1) Ea- (MWh) Ea+(2) t Ea- Daily consumption of facilities and sites calculated by addition (or substraction) of counters, following a table of coefficients («counting tree», published to users) Manual corrections possible Ea = Ea+ Ea- P_avg = Ea / t t 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 31

32 Questions Time resolution 1 day => 10 min? We intend to do it for internal needs (sizing of the network, roadmap for consolidations), but not for forecasting purposes : consumption variations are not predictable at this scale. + Low resolution of some counters (MWh). 23 Nov 2017 B. Mouche - CERN electricity consumption forecast & validation 32

2015 CERN Water Consumption

2015 CERN Water Consumption 2015 CERN Water Consumption Water is supplied to CERN from Lake Geneva by a pumping station located in Vengeron (CH) by the Services Industriels de Genève (SIG). On some SPS Points (BA2, BA4) and on all

More information

2012 CERN Water Consumption

2012 CERN Water Consumption 2012 CERN Water Consumption The water is supplied to CERN from Lake of Geneva by a pumping station located in Vengeron (CH) by the Services Industriels de Genève (SIG). On some SPS Points (BA2, BA4) and

More information

2011 CERN Water Consumption

2011 CERN Water Consumption 2011 CERN Water Consumption The water is supplied to CERN from Lake of Geneva by a pumping station located in Vengeron (CH) by the Services Industriels de Genève (SIG). On some SPS Points (BA2, BA4) and

More information

2017 CERN Water Consumption

2017 CERN Water Consumption 2017 CERN Water Consumption The water is supplied to CERN from Lake of Geneva by a pumping station located in Vengeron (CH) by the Services Industriels de Genève (SIG). On some SPS Points (BA2, BA4) and

More information

EDF and Integration of Distributed Energy Resources

EDF and Integration of Distributed Energy Resources IEEE Power Engineering Society Tuesday, June 20, 2006. Montreal EDF and Integration of Distributed Energy Resources Bruno Meyer (presenter) Director Power Systems Technology and Economics Yves Bamberger,

More information

Energy consumption and savings potential of CLIC

Energy consumption and savings potential of CLIC Energy consumption and savings potential of CLIC Philippe Lebrun CERN, Geneva, Switzerland 55th ICFA Advanced Beam Dynamics Workshop on High Luminosity Circular e + e - Colliders Higgs Factory Beijing,

More information

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES

UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES UNOFFICIAL TRANSLATION SUPPLY OF REACTIVE POWER AND MAINTENANCE OF REACTIVE POWER RESERVES Guideline 1 (11) Contents 1 INTRODUCTION... 2 2 PRINCIPLES OF THE SUPPLY OF REACTIVE POWER... 2 2.1 Supply point

More information

THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks

THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Asset Management & Regulation, ESB Networks THE DISTRIBUTION SYSTEM SECURITY AND PLANNING STANDARDS. Issued by: Review Cycle: Asset Management & Regulation, ESB Networks Three years Contents 1.0 Introduction....3 1.1 Definitions...3 1.2 Aim of Planning...5

More information

GUIDANCE PAPER: CALCULATION METHODOLOGY FOR DISTRIBUTION LOSS FACTORS (DLFs) FOR THE VICTORIAN JURISDICTION

GUIDANCE PAPER: CALCULATION METHODOLOGY FOR DISTRIBUTION LOSS FACTORS (DLFs) FOR THE VICTORIAN JURISDICTION Level 2, 35 Spring St Melbourne 3000, Australia Telephone +61 3 9651 0222 +61 3 1300 664 969 Facsimile +61 3 9651 3688 GUIDANCE PAPER: FOR DISTRIBUTION LOSS FACTORS (DLFs) FOR THE N JURISDICTION 14 FEBRUARY

More information

Price Application Policy ABN

Price Application Policy ABN Price Application Policy ABN 38 362 983 875 Table of Contents 1. Interpretation 4 1.1 Definitions 4 1.2 Access Code definitions apply 5 1.3 Interpretation 5 2. National Market Identifiers (NMIs) 6 2.1

More information

Long Term Planning Method Comparison Considering DG Interconnection

Long Term Planning Method Comparison Considering DG Interconnection Long Term Planning Method Comparison Considering DG Interconnection Marie-Cécile Alvarez Co-authors : G2Elab: Raphaël Caire, Bertrand Raison, Nouredine Hadjsaid EDF R&D: Bogdan Enacheanu, Olivier Devaux

More information

Long-term forecasting of reactive power demand in distribution networks Dr Christos Kaloudas / Dr Rita Shaw. 3 rd November 2017

Long-term forecasting of reactive power demand in distribution networks Dr Christos Kaloudas / Dr Rita Shaw. 3 rd November 2017 Long-term forecasting of reactive power demand in distribution networks Dr Christos Kaloudas / Dr Rita Shaw 3 rd November 2017 Introducing Electricity North West 4.9 million 2.4 million 25 terawatt hours

More information

FINAL REPORT GREEN SQUARE ZONE ADDITIONAL TRANSFORMER

FINAL REPORT GREEN SQUARE ZONE ADDITIONAL TRANSFORMER FINAL REPORT GREEN SQUARE ZONE ADDITIONAL TRANSFORMER 31 st May 2010 Disclaimer This document has been prepared and made available solely for information purposes and consultation under the National Electricity

More information

Schedule 2 TECHNICAL INFORMATION

Schedule 2 TECHNICAL INFORMATION Schedule 2 TECHNICAL INFORMATION This document is intended to provide context to the Haida Gwaii Request for Expressions of Interest (RFEOI) for the potential electricity supply opportunity for clean electricity

More information

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics CERN TS DEPARTMENT

EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics CERN TS DEPARTMENT EUROPEAN ORGANIZATION FOR NUCLEAR RESEARCH European Laboratory for Particle Physics CERN TS DEPARTMENT EDMS Nr. 480988 CERN-TS-2004-017 (IC) Scheduling the installation of the LHC injection lines L. Lari,

More information

CitiPower Amended Revised Proposed Tariff Structure Statement

CitiPower Amended Revised Proposed Tariff Structure Statement CitiPower Amended Revised Proposed Tariff Structure Statement 2017 2020 This page is intentionally left blank. 2 CitiPower Amended Revised Proposed Tariff Structure Statement 2017 2020 Table of Contents

More information

SUMMARY OF PRICES FOR 30MVA 161/24/36 kv MOBILE SUBSTATION ACCORDING to SR-152

SUMMARY OF PRICES FOR 30MVA 161/24/36 kv MOBILE SUBSTATION ACCORDING to SR-152 Israel Electric Corporation Ltd. Tender no. Name of Contractor: SUMMARY OF PRICES FOR 30MVA 161/24/36 kv MOBILE SUBSTATION ACCORDING to SR-152 1. GENERAL INSTRUCTIONS 2.1. Prices for the above captioned

More information

A JOINT DSO-TSO REACTIVE POWER MANAGEMENT FOR AN HV SYSTEM CONSIDERING MV SYSTEMS SUPPORT

A JOINT DSO-TSO REACTIVE POWER MANAGEMENT FOR AN HV SYSTEM CONSIDERING MV SYSTEMS SUPPORT A JOINT DSO-TSO REACTIVE POWER MANAGEMENT FOR AN HV SYSTEM CONSIDERING MV SYSTEMS SUPPORT Juliette MORIN juliette.morin@ensam.eu Frédéric COLAS frederic.colas@ensam.eu Xavier GUILLAD xavier.guillaud@ec-lille.fr

More information

The Distribution System Security and Planning Standards

The Distribution System Security and Planning Standards The Distribution System Security and Planning Standards (Demand customers only) Date: September 2003 Status: Approved Distribution System Operator ESB Networks Revision 1 September 2003, Page 1 of 26 Contents

More information

Ergon Energy Corporation Limited

Ergon Energy Corporation Limited Ergon Energy Corporation Limited Final Report Emerging Distribution Network Limitations in the Central Toowoomba Area 16 May 2013 Disclaimer While care was taken in preparation of the information in this

More information

Microgrid impact on the development of electricity infrastructure

Microgrid impact on the development of electricity infrastructure MORE MICROGRIDS Workshop Paris, 29 January 2010 Microgrid impact on the development of electricity infrastructure Pierluigi Mancarella, Goran Strbac Imperial College London Outline Background Microgrid

More information

Uncontrolled Document when printed. Refer to internet for latest version. Disclaimer refer

Uncontrolled Document when printed. Refer to internet for latest version. Disclaimer refer Issue June 2013 Page 83 of 91 SA Power Networks 2013 Network Tariff & Negotiated Services Manual No. 18 Issue June 2013 Page 84 of 91 SA Power Networks 2013 Network Tariff & Negotiated Services Manual

More information

DISTRIBUTION SYSTEM PLANNING TUTORIAL. MN Power Systems Conference November 6, 2014

DISTRIBUTION SYSTEM PLANNING TUTORIAL. MN Power Systems Conference November 6, 2014 DISTRIBUTION SYSTEM PLANNING TUTORIAL MN Power Systems Conference November 6, 2014 CONNEXUS ENERGY 128,000 customers 1,000 sq. miles territory 44 substations 8,800 miles distribution 12.47 kv Wholesale

More information

AURORA ENERGY LTD. Use-of-System Pricing Methodology

AURORA ENERGY LTD. Use-of-System Pricing Methodology AURORA ENERGY LTD Methodology Applicable from 1 April 2009 Prices Applicable from 1 April 2009 1 INTRODUCTION 2 PRICING OBJECTIVES 3 COST STRUCTURE 4 REVENUE STRUCTURE 5 PRICING COMPONENTS 5.1 Distribution

More information

REVENUE METERING REQUIREMENTS MANUAL (REDLINE VERSION)

REVENUE METERING REQUIREMENTS MANUAL (REDLINE VERSION) REVENUE METERING REQUIREMENTS MANUAL (REDLINE VERSION) 9-10-2004 Revenue Meter Requirements Manual Revision: 1.0 Revision Date:9-10-2004 Disclaimer The information contained within this manual, along with

More information

LOW POWER FACTOR AT WINGHAM TS ASSESSMENT

LOW POWER FACTOR AT WINGHAM TS ASSESSMENT LOW POWER FACTOR AT WINGHAM TS ASSESSMENT Date: October 18 th, 2016 Prepared and Reviewed by: Sacha Constantinescu, P.Eng Transmission Planner System Planning Jerry Vo Distribution Planner Distribution

More information

Hydro Pumped Storage Power Plants perspectives in SEERC Region

Hydro Pumped Storage Power Plants perspectives in SEERC Region Hydro Pumped Storage Power Plants perspectives in SEERC Region Tomislav Plavšić, PhD. HRO CIGRE SC C2 HOPS Croatian Transmission System Operator Ltd. CONTENT 1. EU Energy Policy and Internal Electricity

More information

Impact of innovation on renewables Integration on renewables

Impact of innovation on renewables Integration on renewables 16 TH ERRA ENERGY INVESTMENT AND REGULATION CONFERENCE, SEPTEMBER 25-26, 2017, ASTANA, KAZAKHSTAN Impact of innovation on renewables Integration on renewables DR. ALEXANDRE OUDALOV, MARKET INNOVATION,

More information

The strongest link. Captive power plant-smelter interface for increased power plant efficiency. Reprint from ABB Review 4/2007

The strongest link. Captive power plant-smelter interface for increased power plant efficiency. Reprint from ABB Review 4/2007 The strongest link Captive power plant-smelter interface for increased power plant efficiency Reprint from ABB Review 4/2007 Power Plant Picture Courtesy by Alstom The strongest link Captive power plant-smelter

More information

Joint DSO TSO reactive power management for an HV system considering MV systems support

Joint DSO TSO reactive power management for an HV system considering MV systems support 24th International Conference & Exhibition on Electricity Distribution (CIRED) 12-15 June 2017 Session 3: Operation, control and protection Joint DSO TSO reactive power management for an HV system considering

More information

Lesson learned about the integration of large amount of volatile Renewable Energy Resources

Lesson learned about the integration of large amount of volatile Renewable Energy Resources Francesco Rizzo, Area Manager America & Iberia III BIREGIONAL FORUM WEC N.A. AND LAC- Cancun, Dec. 6-7, 2012 How to Satisfy the Energy Demand of the Americas in a World with Greater Environmental and Financial

More information

Revised Proposal Attachment Tariff Structure Statement. January 2019

Revised Proposal Attachment Tariff Structure Statement. January 2019 Revised Proposal Attachment 10.01 Tariff Structure Statement January 2019 Content 1 ABOUT THIS TARIFF STRUCTURE STATEMENT... 3 1.1 Introduction... 3 1.2 Structure of this Tariff Structure Statement...

More information

Expanding visibility and controllability requirements: The solar PV case. IEA: Task 14 Lisboa - May 11 th 2011

Expanding visibility and controllability requirements: The solar PV case. IEA: Task 14 Lisboa - May 11 th 2011 Expanding visibility and controllability requirements: The solar PV case IEA: Task 14 Lisboa - May 11 th 2011 Solar generation in Spain today Influence of solar technologies in system operation The new

More information

Analysing grid flow over time as a cornerstone of the Smart Grid strategy

Analysing grid flow over time as a cornerstone of the Smart Grid strategy Analysing grid flow over time as a cornerstone of the Smart Grid strategy European Utility Week 15-17 October 2013 - Amsterdam Einar Hoffmann, Managing IT Architect, DONG Energy, Denmark eihof@dongenergy.dk

More information

Distribution Network Planning for Mumbai

Distribution Network Planning for Mumbai Newsletter Issue 98 January 2006 Distribution Network Planning for Mumbai Carsten Böse Project Manager Siemens AG, PTD SE PT carsten.boese@siemens.com Introduction The Indian utility Reliance Energy Ltd.

More information

PJM Roadmap for edart

PJM Roadmap for edart PJM Roadmap for edart As of March 15, 2017 Background edart (electronic Dispatcher Application and Reporting Tool) is suite of electronic applications used to facilitate dispatcher-todispatcher communications,

More information

Distribution - Reset RIN, Basis of Preparation

Distribution - Reset RIN, Basis of Preparation L Distribution - Reset RIN, 2019-2024 Basis of Preparation Introduction TasNetworks (Tasmanian Networks Pty Ltd, ABN 24 167 357 299) is the owner and operator of the electricity distribution network in

More information

Telecommunications. Generator Data Requirements. PJM State & Member Training Dept. PJM /27/2015

Telecommunications. Generator Data Requirements. PJM State & Member Training Dept. PJM /27/2015 Telecommunications Generator Data Requirements PJM State & Member Training Dept. Objectives Students will be able to: Identify the various PJM communication protocols and procedures Identify the various

More information

NERC PLANNING STANDARDS

NERC PLANNING STANDARDS NERC PLANNING STANDARDS North American Electric Reliability Council April 2004 Version of All Planning Standards Terms and Their Definitions As Used in the Analysis (Study) an examination or simulation

More information

Transmission Losses Report 2015

Transmission Losses Report 2015 SP Energy Networks October 2015 Transmission Losses Report 2015 1. INTRODUCTION Special condition 2K of SPT s transmission licence requires SPT to publish an annual transmission losses report detailing

More information

Guy Crockford, BE/OP/LHC, CERN

Guy Crockford, BE/OP/LHC, CERN Automation in the SPS and LHC and its effect on operator skills The past 20 years have seen great advances in the CERN accelerator control systems. Low level operation skills have been largely replaced

More information

GENERATION CURTAILMENT AS A MEANS TO INCREASE THE WIND POWER HOSTING CAPACITY OF A REAL REGIONAL DISTRIBUTION NETWORK

GENERATION CURTAILMENT AS A MEANS TO INCREASE THE WIND POWER HOSTING CAPACITY OF A REAL REGIONAL DISTRIBUTION NETWORK GENERATION CURTAILMENT AS A MEANS TO INCREASE THE WIND POWER HOSTING CAPACITY OF A REAL REGIONAL DISTRIBUTION NETWORK Anna KULMALA Sami REPO Jouni PYLVÄNÄINEN VTT Finland Tampere University of Techlogy

More information

SECTOR ASSESSMENT (SUMMARY): ENERGY

SECTOR ASSESSMENT (SUMMARY): ENERGY Power Sector Rehabilitation Project (RRP KGZ 44198) SECTOR ASSESSMENT (SUMMARY): ENERGY Sector Road Map 1. Sector Performance, Problems, and Opportunity a. Introduction 1. The Kyrgyz Republic is a landlocked

More information

A Case Study of Latham Water District s Mohawk View High Lift Pump Station Rehabilitation

A Case Study of Latham Water District s Mohawk View High Lift Pump Station Rehabilitation A Case Study of Latham Water District s Mohawk View High Lift Pump Station Rehabilitation Outline The Mohawk View High Lift Pump Station & Latham Water District Energy Incentive Programs Pump Evaluation

More information

Distribution Information Exchange Code

Distribution Information Exchange Code Distribution Information Exchange Code Version 5.1 Approved September 2007 Comments to this document can be forwarded to: The RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission

More information

Distribution Value Added

Distribution Value Added Distribution Value Added Eng.. Carlos A. Pérez P MéndezM 1 CONTENTS 1. Introduction 2. How to calculate DVA 3. Costs by Voltage Levels 4. Required Revenue 5. NRV Optimization 6. Grid Operation Costs 2

More information

Daniel Feltes Phone: Fax:

Daniel Feltes Phone: Fax: Coordination of Controls of Renewable Power Plants to Meet Steady State and Dynamic Response Requirements for Voltage Control and Reactive Power Supply Dinemayer Silva Phone: 518-395-5169 Fax: 518-346-2777

More information

BASIC CONCEPTS. Yahia Baghzouz Electrical & Computer Engineering Department

BASIC CONCEPTS. Yahia Baghzouz Electrical & Computer Engineering Department BASIC CONCEPTS Yahia Baghzouz Electrical & Computer Engineering Department INSTANTANEOUS VOLTAGE, CURRENT AND POWER, RMS VALUES AVERAGE (REAL) POWER, REACTIVE POWER, APPARENT POWER, POWER FACTOR INSTANTANEOUS

More information

Invitation for Expression of Interest to provide Flexible Services 3 April 2018

Invitation for Expression of Interest to provide Flexible Services 3 April 2018 Invitation for Expression of Interest to provide Flexible Services 3 April 2018 Flexible Services Expression of Interest/3 April 2018 Page 1 of 21 VERSION HISTORY Version Date Author Status Comments 1.0

More information

International ejournals

International ejournals ISSN 2249 5460 Available online at www.internationalejournals.com International ejournals International Journal of Mathematical Sciences, Technology and Humanities 21 (2011) 205 212 ENERGY CONTROL CENTER

More information

Economic assessment of distribution network planning: a practical approach

Economic assessment of distribution network planning: a practical approach Economic assessment of distribution network planning: a practical approach Seminar@University of Liège Yannick PHULPIN EDF R&D - EFESE February 8, 2013 1 EDF R&D 08/02/2013 Outline of the talk! Context

More information

LOCAL PLANNING REPORT

LOCAL PLANNING REPORT Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 LOCAL PLANNING REPORT Strathroy TS Transformer Capacity Region: London Area Date: September 12, 2016 Revision: Final Prepared by: Strathroy

More information

GUYANA POWER AND LIGHT INC

GUYANA POWER AND LIGHT INC GUYANA POWER AND LIGHT INC The Terms of Reference REQUEST FOR PROPOSALS: CONSULTANCY SERVICES COORDINATING GENERATOR PROTECTION WITH TRANSMISSION PROTECTION AND GENERATOR CONTROLS (GPL-PI-094-2016) November

More information

(Version 05.1) Salkhit Wind Farm. Clean Energy LLC Swedish Energy Agency. Mongolia

(Version 05.1) Salkhit Wind Farm. Clean Energy LLC Swedish Energy Agency. Mongolia CDM-MR-FORM Monitoring report form (Version 05.1) Complete this form in accordance with the Attachment Instructions for filling out the monitoring report form at the end of this form. MONITORING REPORT

More information

Modeling of Electricity Markets and Hydropower Dispatch Task 4.2: Global observatory of electricity resources

Modeling of Electricity Markets and Hydropower Dispatch Task 4.2: Global observatory of electricity resources Modeling of Electricity Markets and Hydropower Dispatch Task 4.2: Global observatory of electricity resources Martin Densing, Evangelos Panos Energy Economics Group, PSI 14.9.2017 Task 4.2 for Energy Economics

More information

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES --------------------------------------------- GAINESVILLE RENEWABLE ENERGY CENTER OPERATING PROCEDURES Revision 0; September 1, 2012 Revision 1; November

More information

A PARADIGM SHIFT IN BUILDING DESIGN TOWARDS ENERGY OPTIMIZED BUILDINGS THAT INTELLIGENTLY INTERACT WITH THE POWER GRIDS

A PARADIGM SHIFT IN BUILDING DESIGN TOWARDS ENERGY OPTIMIZED BUILDINGS THAT INTELLIGENTLY INTERACT WITH THE POWER GRIDS A PARADIGM SHIFT IN BUILDING DESIGN TOWARDS ENERGY OPTIMIZED BUILDINGS THAT INTELLIGENTLY INTERACT WITH THE POWER GRIDS ANNA MARSZAL- POMIANOWSKA IKER DIAZ DE ZERIO MENDAZA DFF POSTDOC RESEARCH QUESTION:

More information

Gas Natural Fenosa s Experiences on Renewable Energy Integration

Gas Natural Fenosa s Experiences on Renewable Energy Integration Gas Natural Fenosa s Experiences on Renewable Energy Integration Julio Gonzalo García Asset Management 17 th October 2013 Outline 1.About us 2.Spanish Regulation 3.R+D projects 4.Conclusions 2 About us

More information

Transmission Expansion Advisory Committee Meeting Market Efficiency Analysis Preliminary Input Assumptions

Transmission Expansion Advisory Committee Meeting Market Efficiency Analysis Preliminary Input Assumptions Transmission Expansion Advisory Committee Meeting 2014 Market Efficiency Analysis Preliminary Input Assumptions March 6, 2014 Study Years Market Simulation Input Data 2015 and 2019 to study approved RTEP

More information

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Addressing System Restoration Issues for the ISO New England System Michael I. Henderson ISO New England Inc. PES General Meeting July 2015 Key Power System and Market Facts (2014) 6.5 million households

More information

IBM Business Automation Content Services on Cloud

IBM Business Automation Content Services on Cloud Service Description IBM Business Automation Content Services on Cloud This Service Description describes the Cloud Service IBM provides to Client. Client means the contracting party and its authorized

More information

Impact of Variable Generation on the Vermont Transmission Grid. Chris Root Vermont Electric Power Company, Inc.

Impact of Variable Generation on the Vermont Transmission Grid. Chris Root Vermont Electric Power Company, Inc. Impact of Variable Generation on the Vermont Transmission Grid Chris Root Vermont Electric Power Company, Inc. croot@velco.com VELCO-managed assets 738 miles of transmission lines, 115kV to 450kV, predominantly

More information

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE

ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE GERHARD HACKL 1 HERWIG RENNER 2 MANFRED KRASNITZER 3 CHRISTIAN HOFBAUER 1 ELECTRIC ARC FURNACE WITH STATIC VAR COMPENSATOR PLANNING AND OPERATIONAL EXPERIENCE Abstract The paper describes the process of

More information

Public disclosure of WEL Networks 1 April 2012 pricing methodology

Public disclosure of WEL Networks 1 April 2012 pricing methodology Public disclosure of WEL s 1 April 2012 pricing methodology This document relates to WEL s Limited s (WEL) obligations under the Electricity (Information Disclosure) Regulations of the Commerce Commission

More information

Managing Energy Use and Cost with Integrated Metering

Managing Energy Use and Cost with Integrated Metering Managing Energy Use and Cost with Integrated Metering Regional Municipality of Durham October 29, 2015 Joe Green P.Eng, CEM Overview Duffin Creek WPCP Jointly owned by York and Durham Regions Capacity

More information

Distribution System Operator (DSO) Construct as a Bridge for End-to-End Transactive Operation

Distribution System Operator (DSO) Construct as a Bridge for End-to-End Transactive Operation Distribution System Operator (DSO) Construct as a Bridge for End-to-End Transactive Operation Farrokh Rahimi, Ph.D. Senior Vice President Market Design and Consulting Ali Ipakchi, Ph.D. Senior Vice President

More information

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional and renewable power generation Power transmission

More information

Energy efficiency and saving potential analysis of the high intensity proton accelerator HIPA at PSI

Energy efficiency and saving potential analysis of the high intensity proton accelerator HIPA at PSI Journal of Physics: Conference Series PAPER OPEN ACCESS Energy efficiency and saving potential analysis of the high intensity proton accelerator HIPA at PSI To cite this article: A Kovach et al 2017 J.

More information

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional and renewable power generation Power transmission

More information

Power System Integration of Offshore Wind Farms:

Power System Integration of Offshore Wind Farms: Power System Integration of Offshore Wind Farms: Challenges Towards Horizon 2020 Tobias Hennig, M.Sc. Fraunhofer IWES Agenda What is EERA JP Wind? Power system integration challenges towards 2020 Example

More information

Focus on Medium Voltage Value for the customer Solutions Ormazabal

Focus on Medium Voltage Value for the customer Solutions Ormazabal Focus on Medium Voltage Value for the customer Solutions 2 Distribution Power Network 3 What Is Our Experience in Wind Energy MEDIUM VOLTAGE ELECTRICAL DISTRIBUTION SPECIALISTS More than 15 GW installed

More information

DSM Initiatives. Rajib Das Senior Manager (Distribution New Initiatives) December 2, 2013

DSM Initiatives. Rajib Das Senior Manager (Distribution New Initiatives) December 2, 2013 DSM Initiatives Rajib Das Senior Manager (Distribution New Initiatives) December 2, 2013 CESC Numbers Item Nos. Item Nos. Area Served 567 sq. km. No. of Consumers 2.7 Million Peak Demand met 1904 MW Loss

More information

Embedded microgrids within the InterFlex project

Embedded microgrids within the InterFlex project Embedded microgrids within the InterFlex project Christian Dumbs Enedis, France Peder Kjellen E.ON Sverige A major European Horizon-2020 Smart Grid project 3-years project duration 2017 2019 with a total

More information

ISOLDE AND N_TOF CONSOLIDATION

ISOLDE AND N_TOF CONSOLIDATION ISOLDE AND N_TOF CONSOLIDATION R. Catherall, CERN, Geneva, Switzerland Abstract The ISOLDE Facility [1] resumed operation in July 2014 providing low energy radioactive ion beams (RIB) to a physics community

More information

Transmission Losses Report 2017

Transmission Losses Report 2017 SP Energy Networks October 2017 Transmission Losses Report 2017 1. INTRODUCTION Special condition 2K of the SP Transmission plc (SPT) transmission licence requires SPT to publish an annual transmission

More information

Metering Fundamentals for Demand Response

Metering Fundamentals for Demand Response Metering Fundamentals for Demand Response Horace Horton Senior Market Trainer, Market Training, NYISO Demand Response In-Depth Course June 26-28, 2018 Rensselaer, NY 12144 1 Session Objectives Identify

More information

PRODUCTION, DISTRIBUTION AND SUPPLY OF ELECTRICITY IN KOSOVO FOR THE PERIOD

PRODUCTION, DISTRIBUTION AND SUPPLY OF ELECTRICITY IN KOSOVO FOR THE PERIOD International Journal of Civil Engineering and Technology (IJCIET) Volume 9, Issue 3, March 2018, pp. 1017 1027, Article ID: IJCIET_09_03_102 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=9&itype=3

More information

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS Christos KALOUDAS The University of Manchester UK christos.kaloudas@manchester.ac.uk Ben MARSHALL National Grid UK ben.marshall@nationalgrid.com

More information

Microgeneration and new end-use technologies in ADDRESS, INCA and SEESGEN-ICT

Microgeneration and new end-use technologies in ADDRESS, INCA and SEESGEN-ICT Microgeneration and new end-use technologies in ADDRESS, INCA and SEESGEN-ICT Jussi Ikäheimo (VTT) (& Regine Belhomme, Giovanni Valtorta) IEA DSM 17 workshop in Sophia Antipolis, France 18th May 2011 2

More information

Distribution Deficiency Report (DDR) Author s Guide

Distribution Deficiency Report (DDR) Author s Guide Distribution Deficiency eport (DD) Author s Guide This document is intended to provide guidance to legal owners of electric distribution systems (also referred to as Distribution Facility Owners or DFOs

More information

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES --------------------------------------------- GAINESVILLE RENEWABLE ENERGY CENTER OPERATING PROCEDURES Revision 0; September 1, 2012 Revision 1; November

More information

Transmission grid tariffs for 2018

Transmission grid tariffs for 2018 Transmission grid tariffs for 2018 Model description and rates Photo: Statnett Tariffs 2018 Changes in the Energy Act were adopted with effect from 1 July 2016. Among other things, the Act defines changes

More information

Primary control - description of main technical and design characteristics

Primary control - description of main technical and design characteristics Primary control - description of main technical and design characteristics Summary The purpose of this note is to give enough clarification on the needed requirements a market player has to respect to

More information

PROCESS & SYSTEMS PROCESS & SYSTEMS

PROCESS & SYSTEMS PROCESS & SYSTEMS saveonenergy Baseline Methodology Guidelines Baseline Methodology Guidelines Purpose This document is intended to provide Program Participants and engineering consultants with guidelines around acceptable

More information

High Frequency Modulation in France and in TRIMET Saint-Jean de Maurienne for F and G Lines

High Frequency Modulation in France and in TRIMET Saint-Jean de Maurienne for F and G Lines High Frequency Modulation in France and in TRIMET Saint-Jean de Maurienne for F and G Lines Olivier Granacher 1, Quentin Denoyelle 2, Frédéric Charvoz 3, Alexandre Riot 4 and Matthieu Dhenaut 5 1. Process

More information

PV + Storage for Load-Shifting in the Cook Islands

PV + Storage for Load-Shifting in the Cook Islands 1 Jason Bylsma Prof. Fthenakis - EAEE E4190 Photovoltaic Systems Engineering December 8, 2014 PV + Storage for Load-Shifting in the Cook Islands Source: http://spasifikmag.com/ 2 Executive Summary It has

More information

Project ENDORSE Energy Downstream Service Providing energy components for GMES Grant Agreement no

Project ENDORSE Energy Downstream Service Providing energy components for GMES Grant Agreement no Project ENDORSE Energy Downstream Service Providing energy components for GMES Grant Agreement no 262892 D407.1: Report on the Product E1 Load Balancing Type of document: Product Report Version Number

More information

LOCAL PLANNING REPORT

LOCAL PLANNING REPORT Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 LOCAL PLANNING REPORT Kent TS Transformation Capacity Region: Chatham-Kent/Lambton/Sarnia Date: June 28 th, 2017 Revision: Final Prepared

More information

Bernstein Innovative Energy Technologies Conference

Bernstein Innovative Energy Technologies Conference Bernstein Innovative Energy Technologies Conference Ram Sastry Director, Distribution Services Support March 25, 2014 Safe Harbor Statement under the Private Securities Litigation Reform Act of 1995 This

More information

Session 5 Shutdown schedule 2008/9 and Future shutdowns

Session 5 Shutdown schedule 2008/9 and Future shutdowns Where are we with the current shutdown? LHC Performance rm Workshop 2009 Session 5 Shutdown schedule 2008/9 and Future shutdowns EN/MEF/LPC J.Coupard & K.Foraz LHC Performance 04th Feb. 2009 1 Key drivers

More information

Capacity-based network tariffs for Italian electricity households

Capacity-based network tariffs for Italian electricity households Capacity-based network tariffs for Italian electricity households Luca Lo Schiavo Emanuele Regalini ARERA - Regulatory Authority for Energy, Networks and Environment lloschiavo@arera.it eregalini@arera.it

More information

CERN experience and strategy for the maintenance of cryogenic plants and distribution systems

CERN experience and strategy for the maintenance of cryogenic plants and distribution systems IOP Conference Series: Materials Science and Engineering PAPER OPEN ACCESS CERN experience and strategy for the maintenance of cryogenic plants and distribution systems Related content - Management of

More information

Experience with MPS during the 2010 run

Experience with MPS during the 2010 run Experience with MPS during the 2010 run J. Wenninger BE-OP-LHC Acknowledgments: M. Zerlauth (statistics!), R. Schmidt, MPP(r) colleagues and UFO crews. 1 Outline Commissioning and intensity increase Reviews

More information

Energy Savings Analysis Generated by a Real Time Energy Management System for Water Distribution

Energy Savings Analysis Generated by a Real Time Energy Management System for Water Distribution Energy Savings Analysis Generated by a Real Time Energy Management System for Water Distribution Sarah Thorstensen Derceto Ltd, Auckland, New Zealand sthorstensen@derceto.com Abstract Washington Suburban

More information

PQ04. Understanding Power Monitoring

PQ04. Understanding Power Monitoring PQ04 Understanding Power Monitoring Understanding Power Monitoring Randy Keranen Drives, Motors, and Power Monitors Product Manager April 9, 2015 Related Classes at the Expo PQ05 Energy Intelligence: EnergyMetrix

More information

Addressing reliability requirements in the Flemington substation load area

Addressing reliability requirements in the Flemington substation load area Addressing reliability requirements in the Flemington substation load area Notice on screening for non-network options May 2018 Title of Contents DISCLAIMER... 1 1 INTRODUCTION... 2 2 FORECAST LOAD AND

More information

Domain Knowledge and Data Analytics: Towards a Holistic Approach to Power System Condition Monitoring and Asset Management

Domain Knowledge and Data Analytics: Towards a Holistic Approach to Power System Condition Monitoring and Asset Management Domain Knowledge and Data Analytics: Towards a Holistic Approach to Power System Condition Monitoring and Asset Management Dr Bruce Stephen Advanced Electrical Systems Group Institute for Energy and Environment

More information

FRCC Requirements for Analysis of Protection Misoperations and Corrective Actions Reporting

FRCC Requirements for Analysis of Protection Misoperations and Corrective Actions Reporting FRCC - PROC - RC PRC-003 FRCC Requirements for Analysis of Protection Misoperations and Corrective Actions Reporting Effective Date: December 2, 2010 Revisions Rev. No. Date Description Developed by: Approved

More information

CIRED Workshop - Helsinki June 2016 Paper ABSTRACT PROPOSED APPROACH INTRODUCTION. N. Natale, F. Pilo, G. Pisano, G. G.

CIRED Workshop - Helsinki June 2016 Paper ABSTRACT PROPOSED APPROACH INTRODUCTION. N. Natale, F. Pilo, G. Pisano, G. G. ASSESSMENT OF PRICE AND QUANTITY OF ANCILLARY SERVICES PROVIDED BY ACTIVE DISTRIBUTION SYSTEMS AT THE TSO/DSO INTERFACE N. Natale, F. Pilo, G. Pisano, G. G. Soma M. Coppo, R. Turri G. Petretto, M. Cantù,

More information

Dispatch Data Exchange Manual. June, 2012

Dispatch Data Exchange Manual. June, 2012 Dispatch Data Exchange Manual June, 2012 Table of Content Page No. 1 Introduction...1 2 Overview of the NITS...2 3 Major Transmission lines...2 4 Existing Generating Plants...4 5 Responsibility of the

More information