Market Mechanics Review of Net Demand Variability from the E&AS Design Stream Working Group Meeting 6&8
|
|
- Dylan Cummings
- 6 years ago
- Views:
Transcription
1 Market Mechanics Review of Net Demand Variability from the E&AS Design Stream Working Group Meeting 6&8 Impact of Net Demand Variability Reference Case and High Cogen scenario
2 Background Dispatching to Net Demand The system is dispatched to meet net demand defined as the demand net of variable resources (on the transmission and distribution system) that effectively self dispatch The variability of net demand can pose challenges on the system. Current system operation practices and tools may need to evolve in order to manage the variability (Net Demand Variability) introduced by increased variable generation The AESO is modelling the expected range of variability as well as considering scenarios related to future asset mix, market rules or products to evaluate the impact of NDV and if needed mitigation options At the WG2 meeting, based on the preliminary analysis, we indicated that; The current market practices and behaviour may create performance issues above 3,000 MW of variable generation (VG) (compared to current 1450 MW on line) Early modelling results indicate that the 3,000MW VG threshold may be reached by 2022/23 1
3 Further Analysis Simulation methodology Early results were modelled based on the system as a single block and using inputs from the 2016 LTO New Analysis: Two models were developed to simulate; Market functions Market simulation model Operations functions System dispatch simulation model Simulated merit orders from the Market simulation model are input into the System dispatch simulation model to simulate operational behaviour Historic behaviour observations will form the foundation of the models Historic data used to validate the models Assumptions of future changes to system are considered The validated model is then used to simulate the future Alternate sensitivity and/or mitigation scenarios will be simulated based on initial observations from the base case simulation 2
4 Further Analysis: Key Assumptions Load Forecast Load forecasts for tested years are based on the 2017 LTO Future generation scenarios Generation forecasts (and generation cases) for tested years are based on the 2017 LTO Future variable generation profile Wind/solar profiles and simulations are based on 200 sites extrapolated to future Profiles are also based on 2014, 2015 and 2016 weather years extrapolated to future Operation practices are based on historic observed behaviour At system level (dispatch interval) Based on observed behaviour and related rules Parametric, validated / tuned by simulation (Historical backcast) At asset level Based on observed and expected behaviour (market and operation) 3
5 Metrics The metrics will demonstrate impacts on market and system operations as a result of changing supply and system characteristics between now and 2030 # Focus Metric Description 1 Market Supply surplus/shortfall situations To Identify impact of unit commitment on supply surplus and shortfall situations 2 Market Merit order / market asset characteristics To identify merit order characteristics under different generation mixes such as quantity of $0, Minimum Stable Generation (MSG) and ramp capability 3 Market Unit cycling Quantify cycling of different types of thermal generation units (CC, SC, CTG and coal for some years) 4 Operations Impact/expected changes to Control Performance Standard 2 (CPS2) violations To measure the10 minute ACE (Area Control Error Balancing authority MW imbalance) performance at or above the 90% of the time within required threshold 4
6 Metrics cont. # Focus Metric Description 5* Operations System Operating Limit (SOL) violation (TOP-007-AB-0) 6* Operations Area Control Error (ACE) events. Related to impact on interties and neighboring systems 7 Operations Variable energy spill due to power management tool activations To measure the 30 minute or longer ACE performance benchmark and resultant SOL violation. i.e. to measure the SOL violation that exceeds the tie line Total Transfer Capability (TTC) for more than 30 minutes or longer To measure the 30 minute or longer ACE performance benchmark. i.e. to measure when the intertie flow exceeds the schedule by more than the Transmission Reliability Margin (TRM) of 65MW for more than 30 minutes, but not exceeding TTC Potential spill of variable energy due to using the AESO s wind power management tool (how often and how much) *The difference between high ACE and SOL is based on how high the BC tie is scheduled during the event. If tie is scheduled near full ATC, then it may cause an SOL; if tie is scheduled low, then it may cause high ACE events. 5
7 Summary Results Reference case and High Cogen Scenario The following is a summary comparison between the reference case results (presented at WG 6) and the high cogeneration scenario (WG 8) # Metric Reference Case Results High-Cogen Results 1 Supply surplus/shortfall situations 2 Merit order / market asset characteristic Supply surplus hours exceed historical values around 2026 Model results show no concerns of supply shortfall due to unit commitment Preliminary work shows that future assets will individually have enhanced ramp capability. There is about 10% difference between $0 and MSG blocks. i.e. flexibility 3 Unit cycling Future generation, including coal-fired replacements, is anticipated to increase in cycling from monthly to weekly on average 4 CPS2 violations CPS2 is always above the required 90% (so not an issue) The results show that a generation mix with more cogeneration would likely lead to moderately more supply surplus events Fourteen supply shortfall events occur between 2026 and 2030 The results show flexibility is similar to the Reference Case, however, the overall ramp capability of the fleet is slower Results are similar to the Reference Case CPS2 is always above the required 90% But, is less than in the reference case (still not an issue) 6
8 Summary contd. # Metric Reference Case Results High-Cogen Results 5 System Operating Limit (SOL) violation (TOP-007-AB-0) Although the simulation indicated that the 1st simulated SOL violation is in 2021, it is when the tie line is out of service. With the tie line in service, the 1st simulated SOL violation was in 2022 If the system controller used the existing practice of dispatch for ramp, these violation are avoided Similar observations as per reference case Similar to the reference case, with the existing practice of dispatch for ramp, these violations are avoided However, more instances of dispatch for ramp will be needed 6 Area Control Error (ACE) events 7 Variable energy spill due to power management tool activations There are more big ACE events with the increased variable generation level Both the limited hours and energy are small numbers, with limited energy less than 0.1% of wind power generation Even less (~10 times) if only considering the non supply surplus periods A few additional instances of big ACE events are observed Similar to the reference case 7
9 Reference Case and High Cogen Results Reference case LTO Based on further analysis, the NDV impact is measured at approximately 3000 MW of variability on the system; however, the estimated date for when the system impact is felt differs depending on the metric, starting in the original timeline of 2022 The impact varies significantly based on availability of intertie No expected system performance issues; however, increased hours of supply surplus which will impact assets and dispatch. Enhanced system flexibility important in managing variability High Cogen A high Cogeneration scenario results in a less flexible fleet Although system operations could be reliably managed, the lower flexibility of the system may require the system controller to dispatch the EMMO (dispatch for ramp) more frequently and in larger volumes to manage NDV The more frequent use of the EMMO to manage ramp needs may result in; price impacts (price fidelity); increased instances of unit cycling supply surplus and in rare instances supply shortfall issues 8
10 Initial Market Approach Suggestions In order to mitigate the NDV impacts the following alternate options may be evaluated; procuring additional volumes of current ancillary service products (ex. AGC); Introduction of specific ramp product; Consideration of how real time pricing signals can incent flexibility Need for changes / value to different unit commitment models 9
11 Next Steps Further testing of asset scenarios to evaluate any change in impact Examples: changes in coal to gas assumptions Evaluation of current rules to mitigate system impact Wind power management, forecasting, use of AGC, Evaluation of dispatch protocol / rules related to ramp Examples: Dispatch tolerance, ramp response Evaluation of further market rules / products Pricing to incent more system flexibility, new ancillary services products Efficiency analysis to evaluate mitigation options impact to system, fleet, costs AESO Internal 10
Net Demand Variability (NDV) Summary
Net Demand Variability (NDV) Summary Executive Summary: This document provides a summary of the Net Demand Variability (NDV) work presented to the Energy and Ancillary Service (EAS) workgroup in WG meetings
More informationSystem Impact Study and Facilities Study Process Manual For Cleco Power LLC
System Impact Study and Facilities Study Process Manual For Cleco Power LLC Version 3 March 2010 System Impact Study and Facilities Study Manual for Cleco Power LLC 1.0 Introduction.3 1.1 Purpose.3 1.2
More informationDate of Request for Comment: April 7, 2017 Period of Comment: April 7, 2017 through May 5, 2017
Market Participant Comments and AESO Replies Matrix Proposed Amended Section 304.3, Wind and Solar Power Ramp Up Management ( amended Section 304.3 ) Date of Request for Comment: April 7, 2017 Period of
More informationICA Demand Curve Development:
ICA Demand Curve Development: Proposed Approach for Ontario PRESENTED TO Market Renewal Incremental Capacity Auction Stakeholder Group PRESENTED BY Kathleen Spees Johannes Pfeifenberger Yingxia Yang John
More informationBest Practices in Conducting Grid Integration Studies
GREENING THE GRID Best Practices in Conducting Grid Integration Studies ENHANCING CAPACITY FOR LOW EMISSION DEVELOPMENT STRATEGIES (EC-LEDS) Agenda and Learning Objectives Part 1: Why conduct a grid integration
More informationSAM 3.0 Stakeholder Comment Matrix
SAM 3.0 Stakeholder Comment Matrix The AESO welcomes stakeholder input on the working group provisional recommendations and discussion context contained in Section 5 of SAM 3.0. Please review the following
More informationManaging Flexibility in MISO Markets
Managing Flexibility in MISO Markets Clean Energy Regulatory Forum November 9, 2012 Outline Impacts of Variable Generation on Ancillary Services Dispatchable Intermittent Resources Introduction to Proposed
More informationExecutive Summary MQRI-OPS 2
MQRI-OPS 1 Executive Summary On August 21, 2017 the ISO system experienced a solar eclipse with obscuration ranging from 58 percent in Southern California to 76 percent in Northern California. The eclipse
More informationSAM 2.0 Stakeholder Comment Matrix
SAM 2.0 Stakeholder Comment Matrix The AESO welcomes stakeholder input on the working group conclusions and discussion context contained in Section 5 of SAM 2.0. Please review the following instructions
More informationTechnical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations
Technical Bulletin 2009-06-03 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations June 15, 2009 Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations
More informationNorthwest Power and Conservation Council NW Power Markets Symposium Products & Transactions
Northwest Power and Conservation Council NW Power Markets Symposium Products & Transactions Presented by: John Wilkinson John.Wilkinson@MorganStanley.com 604-658-8132 July 2013 Disclaimer: The information
More informationSAM 3.0 Stakeholder Comment Matrix
SAM 3.0 Stakeholder Comment Matrix The AESO welcomes stakeholder input on the working group provisional recommendations and discussion context contained in Section 5 of SAM 3.0. Please review the following
More information2. Market Operations Overview
2. Market Operations Overview 2.5 Market Information This section summarizes and describes the common information that is used by the Day-Ahead and Real-Time processes. 2.5.1 Resource Static Data Static
More information2015 Economic Planning Study Assumptions
2015 Economic Planning Study Assumptions Erik Winsand, ATC Economic Planning May 13, 2015 atcllc.com Introduction Process Overview and Timeline MISO MTEP16 Futures Assumptions Next Steps atcllc.com 2 Process
More informationSolutions for Power Generation
EM SG SOLutions Solutions for Power Generation Energy Management Smart Grid Solutions Solutions for Power Generation Overview Power Applications Generation Planning and Trading Summary Page 2 Solutions
More informationFlexible Ramping Product Cost Allocation Straw Proposal
Flexible Ramping Product Cost Allocation Straw Proposal March 15, 2012 Flexible Ramping Product Cost Allocation Straw Proposal Table of Contents 1 Introduction... 3 2 Prior discussion on Flexible Ramping
More informationCHAPTER 1 EXECUTIVE SUMMARY
CHAPTER 1 EXECUTIVE SUMMARY The 2016 SD Electricity Supply Resource Procurement Plan The 2016 South Dakota Electricity Supply Resource Procurement Plan ( Plan ) evaluates NorthWestern Energy s ( NorthWestern
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...
More informationDATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans
ENTERGY GULF STATES LOUISIANA, L.L.C. & ENTERGY LOUISIANA, LLC LPSC DOCKET NO. I-33014 DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans This version
More informationISO REVISED STAGING PLAN NO. 7
ID Work Item Description 2 COMPLETE HIM Server An archival database is to be created for permanent historical storage of bidding, price and schedule data. HIM is defined in section 3.2.5 of the SI DSOW:
More informationFunctional Entity Roles and Responsibilities
Functional Entity Roles and Responsibilities NWPP MC Phase 3 Operations Integration Work Group 9/28/2014 Page 1 of 13 Table of Contents 1. Purpose... 3 2. Roles and Responsibilities of Functional Entities...
More information8/28/2017 Readiness Criteria PGE EIM Readiness
8/28/2017 Criteria EIM 1 2 3 Generation, Interchange and Load comparison Comparison of SCADA measurement State Estimator solution Load, EIM Internal Intertie and EIM External Interties, and Generating
More informationEconomic Viability of Combined Heat and Power in ERCOT
WADE Annual Meeting & DistribuGen Conference and NYSERDA CHP Expo October 14-17, 2014, Westchester, New York Economic Viability of Combined Heat and Power in ERCOT PRESENTED BY Yingxia Yang O c t 1 6 t
More informationTucson Electric Power 2017 Integrated Resource Plan. Southern Arizona Regional Solar Partnership Jeff Yockey, PE
Tucson Electric Power 2017 Integrated Resource Plan Southern Arizona Regional Solar Partnership Jeff Yockey, PE May 2017 Integrated Resource Plan (IRP) Overview Just a Plan Additional steps for specific
More informationElectricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)
For the first quarter of 2015, Ontario experienced overall demand that was typical for the province in winter, and strong generator output. Demand for Ontario electricity increased as a result of cold
More informationBest Practices in Risk-Based Resource Planning A Case Study of NorthWestern s Acquisition of Hydros
Best Practices in Risk-Based Resource Planning A Case Study of NorthWestern s Acquisition of Hydros Presenters: Gary Dorris, PhD August 4, 2015 Overview of Ascend Short, Intermediate, & Long-Tem: operating
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 34. Real-Time Market... 3 34.1 Inputs To The Real-Time Market... 3 34.1.1 Day-Ahead Market Results as Inputs to the Real-Time Market... 3 34.1.2 Market Model and System Information...
More informationRenewable Integration at ERCOT
Renewable Integration at ERCOT Dan Woodfin Director of System Operations ERCOT CIGRE Chile September 12, 2016 The ERCOT Region The interconnected electrical system serving most of Texas, with limited external
More informationAnjan Kumar Sinha NTPC Ltd
Flexibilisation of Thermal Stations-NTPC's Approach Anjan Kumar Sinha NTPC Ltd Contents Variability of Renewable Power Flexibilization: Need for Benchmarking Operationalisation of flexibility Design and
More informationCOGENERATION: Opportunities in Today s Power Markets
COGENERATION: Opportunities in Today s Power Markets COGEN Europe Annual Conference 2005 10-11 March 2005 Paul Dillon Planning Executive: Europe, Middle East and Africa ExxonMobil Refining & Supply Taking
More informationANNUAL REPORT ON MARKET ISSUES & PERFORMANCE
ANNUAL REPORT ON MARKET ISSUES & PERFORMANCE Department of Market Monitoring ACKNOWLEDGEMENT The following members of the Department of Market Monitoring contributed to this report Eric Hildebrandt Keith
More information6.1.9 IFM Initial Conditions
6.1.9 IFM Initial Conditions A Generating Unit that was committed in the previous day s Day-Ahead Market (IFM or RUC) run (TD-2 for TD-1) but was de-committed before HE24 would normally be considered initially
More informationCosts and Benefits of the Smart Grid. Hans de Heer 10 October 2012
Hans de Heer The DNV Group DNV Group DNV KEMA Energy & Sustainability DNV Maritime Oil & Gas DNV Business Assurance 300 offices 100 countries 10,400 employees 2 DNV KEMA Energy & Sustainability DNV KEMA
More information2017 IRP Advisory Group. July 21, 2017 IRPAG
2017 IRP Advisory Group Today s Agenda 2 General Rate Case Caution Need to avoid the possibility of unintentionally violating ex-parte communication rules Please refrain from bringing up any rate case
More informationValue-based Transmission Investment and Operations. Marija Ilic Invited Panel, IEEE PES 2014 Washington DC
Value-based Transmission Investment and Operations Marija Ilic milic@ece.cmu.edu Invited Panel, IEEE PES 2014 Washington DC 2 Outline The evolving role of on-line T&D management Basic definition of an
More informationSummary of 2016 MISO State of the Market Report
Summary of 2016 MISO State of the Market Report Presented to: MISO Board Markets Committee David B. Patton, Ph.D. MISO Independent Market Monitor July 20, 2017 Introduction As the Independent Market Monitor
More informationPolicy Direction for Alberta s Capacity Market Framework
Policy Direction for Alberta s Capacity Market Framework August 15, 2017 Alberta Department of Energy Table of Contents Executive Summary... 1 1 Introduction... 2 2 Policy Direction for Alberta s Capacity
More informationSurvey of Modeling Capabilities and Needs for the Stationary Energy Storage Industry
Survey of Modeling Capabilities and Needs for the Stationary Energy Storage Industry Prepared for: Energy Storage Association 1155 15th Street, NW Suite 500 Washington, DC 20005 202.293.0537 energystorage.org
More informationAlberta & Saskatchewan Renewable Energy Finance Summit Alberta and Saskatchewan Climate Policy Developments and Implications for Renewables
Alberta & Saskatchewan Renewable Energy Finance Summit 2018 Alberta and Saskatchewan Climate Policy Developments and Implications for Renewables Lisa (Elisabeth) DeMarco DeMarco Allan LLP lisa@demarcoallan.com
More informationEnvironmental Compliance (Slides 7-15) Angila Retherford, Vice President Environmental Affairs and Corporate Sustainability
Vectren 2016 Integrated Resource Plan (IRP) July 22, 2016 Stakeholder Meeting 2 Summary The following is a summary of the second of three Vectren IRP stakeholder meetings in 2016 and is meant to provide
More informationIntegrating variable renewables: Implications for energy resilience
Integrating variable renewables: Implications for energy resilience Peerapat Vithaya, Energy Analyst System Integration of Renewables Enhancing Energy Sector Climate Resilience in Asia Asia Clean Energy
More informationElectricity Generation Optimization in a Period of Surplus Baseload Generation
Electricity Generation Optimization in a Period of Surplus Baseload Generation Carnegie Mellon School of Business Bruce Boland SVP - Commercial Operations & Environment Outline Introduction to Ontario
More informationThe Role of Oil Sands Cogeneration in the 2030 Alberta Generation Mixture. Ariane Ouellette, Dr. Andrew Rowe and Dr. Peter Wild April
The Role of Oil Sands Cogeneration in the 2030 Alberta Generation Mixture Ariane Ouellette, Dr. Andrew Rowe and Dr. Peter Wild April 13 2013 Motivation Province of Alberta targets a 2050 GHG emissions
More informationCAN YOU RELY ON A RELIABILITY OPTION?
CAN YOU RELY ON A RELIABILITY OPTION? Andy Kelly National Power Summit, February 2017 OVERVIEW OF PRESENTATION TOPICS New capacity mechanism is complex but aim today to focus on some key topics RO price
More informationEMS of the Future. EMS Users Conference Chicago, Illinois. John McDaniel September 20, Proprietary 1 Experience you can trust.
EMS of the Future EMS Users Conference Chicago, Illinois John McDaniel September 20, 2010 Proprietary 1 Experience you can trust. Overview Key Issues Shaping EMS Implementations Operational Issues Being
More informationIntegrating High Penetrations of Variable Renewable Generation Lori Bird and Debra Lew, NREL NCSL Webinar March 28, 2012
Integrating High Penetrations of Variable Renewable Generation Lori Bird and Debra Lew, NREL NCSL Webinar March 28, 2012 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy
More informationResidual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources
Market Issues Bulletin Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources March 10, 2015 www.caiso.com 250 Outcropping Way, Folsom, CA 95630 916.351.4400
More informationINDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)
INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) Paul L. Joskow September 28, 2007 ALTERNATIVE SYSTEM OPERATOR MODELS System operator (SO) is vertically integrated utility (G+T) Functional
More informationANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM
ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM January 2017 PRESENTED BY JENNY RIESZ SLIDE 1 AGENDA 1. Introduction to the NEM 2. Future Power System Security Program 3. Identifying
More informationUpdate on the Market Renewal Program
Update on the Market Renewal Program Update to Technical Panel September 26, 2017 Overview Introduction Defining Market Renewal Update on Engagement and MRWG Priorities Looking Ahead Appendix: Why We Need
More informationMISO SPP Interregional Stakeholder Advisory Committee. April 8 th, 2014 Carmel, IN
MISO SPP Interregional Stakeholder Advisory Committee April 8 th, 2014 Carmel, IN 1 Agenda Introductions Discussion on Draft Coordinated System Plan (CSP) Study Scope Lunch Continue Discussion on Draft
More informationCAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments
CAISO s Flexible Resource Adequacy and Must Offer Obligation Phase 2 Revised Straw Proposal Public Generating Pool and Public Power Council Comments May 22, 2017 Public Generating Pool (PGP) and Public
More informationEugene Water & Electric Board. The Future of Utilities in the Pacific Northwest
Eugene Water & Electric Board The Future of Utilities in the Pacific Northwest 1 Eugene Water & Electric Board The Future of Utilities in the Pacific Northwest Erin Erben Manager, Power & Strategic Planning
More informationMTEP18 Futures. Planning Advisory Committee June 14, 2017
MTEP18 Futures Planning Advisory Committee June 14, 2017 Overview Objective: Present final MTEP18 Futures and an overview of stakeholder feedback Key Takeaways: Four Futures to be used in MTEP18 to consider
More informationAlberta Capacity Market
Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Rationale Document Section 7: Capacity Auction Monitoring and Mitigation Prepared by: Alberta Electric System Operator Date: January 26,
More informationFlexible Ramping Product. Draft Technical Appendix
Flexible Ramping Product Draft Technical Appendix June 10, 2015 Table of Contents 1. Introduction... 3 2. Generalized flexible ramping capacity model... 3 3. Flexible ramping product summary... 5 4. Flexible
More informationBPA s HERMES Project: a Multi-objective, Multi-user Approach to Reservoir Optimization
BPA s HERMES Project: a Multi-objective, Multi-user Approach to Reservoir Optimization Damon Pellicori and Shane Mosier BPA RiverWare User Group Meeting Boulder, Colorado August 23-24, 2016 Presentation
More informationElectricity Grid of the Future. Program Director: Dr. Sonja Glavaski
Electricity Grid of the Future Program Director: Dr. Sonja Glavaski Outline ARPA-e Overview US Energy Landscape DERs and Grid Integration Grid of the Future (Vision & Long Term Goals) Going Forward The
More informationGeneration Capacity Mechanisms and Resource Adequacy Planning
Generation Capacity Mechanisms and Resource Adequacy Planning Jennifer Heintz Public Service Commission of the State of Missouri February 7, 2013 Abu Dhabi, UAE Electricity Markets in the U.S. and Canada
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents Appendix N... 2 Pseudo-Tie Protocol... 2 1. Pseudo-Ties of Generating Units to the CAISO Balancing Authority Area... 2 1.1 Consistency with NERC/WECC Requirements... 2 1.2 CAISO Operating,
More informationBusiness Practice Manual for Market Operations
Business Practice Manual for Market Operations Version 5354 Revised: July 13October 30, 2017 Page 1 of 345 Approval History Approval Date: March 23, 2009 Effective Date: March 31, 2009 BPM Owner: David
More informationOptimization and Flexibility First: The Clear Case for Energy Storage
Optimization and Flexibility First: The Clear Case for Energy Storage Ontario s Long-Term Energy Plan (2017) Submission of Energy Storage Canada (ESC) December 16, 2016 1 Executive Summary In the last
More informationCoal Closure In Ontario
MINISTRY OF ENERGY Coal Closure In Ontario August 2015 Purpose Ontario has experience in phasing out coal-fired electricity generation. This deck provides insight into Ontario s experience through a thorough
More informationDynamic Transfers Revised Draft Final Proposal
Dynamic Transfers Revised Draft Final Proposal Provided in Support of 2009-2011 Stakeholder Process to Consider Expansion of Dynamic Transfer Services in ISO Tariff Revised February 18, 2011 CAISO/M&ID/Dynamic
More informationTEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY
TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY 1 1. Summary When one part of the grid is facing security of supply risk where local generation in one region of the grid is not enough for
More informationSpring 2014 Release Training
Spring 2014 Release Training January 22 and 23, 2014 Cynthia Hinman California ISO The information contained in these materials is provided for general information only and does not constitute legal or
More informationEducating System Operators in the New Millennium! Background. Course Level. Target Audience. NERC Continuing Education Hours
Background The class will be delivered over a 3-day period. The class is comprised of three training modules covering the areas of: Communications, Critical Thinking, and Restoration. The course consists
More informationMarket Simulation Structured Scenarios
Market Simulation Structured Scenarios Flexible Ramping Product August 30, 2016 Location of Link Revision History Date Version Description Author 08/02/16 1.0 Initial publication Christopher McIntosh 08/22/16
More informationThe Optimisation of the supply-demand balance, the role of interconnections, and the impact of nuclear shutdown in Germany for EDF
The Optimisation of the supply-demand balance, the role of interconnections, and the impact of nuclear shutdown in Germany for EDF 08 June 2011 Philippe TORRION Executive Vice President Optimisation and
More informationIncluding Advanced Energy Storage in Integrated Resource Planning: Cost Inputs and Modeling Approaches
Including Advanced Energy Storage in Integrated Resource Planning: Cost Inputs and Modeling Approaches November 2016 v1.1 Advanced energy storage costs are declining rapidly and large-scale storage deployments
More informationContingency Modeling Enhancements Issue Paper
Contingency Modeling Enhancements Issue Paper March 11, 2013 California ISO Contingency Modeling Enhancements Issue Paper Table of Contents I. Executive Summary... 3 II. Plan for Stakeholder Engagement...
More informationOperating Procedure PURPOSE... 1
Table of Contents PURPOSE... 1 1. RESPONSIBILITIES... 2 2. SCOPE/APPLICABILITY... 2 2.1. Background... 2 2.2. Scope/ Applicability... 2 3. PROCEDURE DETAIL... 3 3.1. Order of Steps... 3 3.2. Restricted
More informationOverview of Control Area / Balancing Authority Functional Requirements Matt Wolf Manager Operations Support May 5, 2010
Overview of Control Area / Balancing Authority Functional Requirements Matt Wolf Manager Operations Support May 5, 2010 1 Outline of Presentation Importance of balancing power production with power demand.
More informationFinal Flexible Capacity Needs Assessment for 2018
Final Flexible Capacity Needs Assessment for 2018 April 28, 2017 1 Table of Contents 1. Introduction... 3 2. Summary... 3 3. Defining the ISO System-Wide Flexible Capacity Need... 5 4. Forecasting Minute-by-Minute
More informationTerms of Reference AG 2017/01
Long-term Analysis of the Chilean National Electricity System Considering Variable and Intermittent Energy Resources Terms of Reference AG 2017/01 February 2017 Index 1. Introduction... 2 2. Objectives
More informationMISO-PJM Interface Pricing Post Implementation Metrics and Criteria
MISO-PJM Interface Pricing Post Implementation Metrics and Criteria Contents 1 Introduction... 2 2 Real-Time Market Interchange Price Signal Effectiveness Metrics... 2 2.1 Post Implementation Pricing Monitoring
More information2016 ANNUAL VRL ANALYSIS
2016 ANNUAL VRL ANALYSIS Published on 08/01/2016 By Ops Market Support/Forensics Chris Davis Ricky Finkbeiner REVISION HISTORY DATE OR VERSION NUMBER AUTHOR CHANGE DESCRIPTION COMMENTS 7/11/2016 Ricky
More informationElectricity Authority Work Programme. 1 July June June 2017
Work Programme 1 July 2017 30 June 2018 30 June 2017 Contents Executive summary... 3 Introduction and purpose... 4 Programme A: Evolving technologies and business models... 7 Programme B: Consumer choice
More informationIntegrated Grid Planning Symposium
Integrated Grid Planning Symposium State of IGP Technology 16 November 2017 Derek Stenclik, GE s Hawaii Grid Planning Experience Evaluation of Sustainable Energy Options for the Big Island Oahu Wind Integration
More informationcpmplus Energy Manager
Mark Reed, Automation, Data Center Industry Segment Initiative cpmplus Energy Manager December 13, 2012 Slide 1 Collaborative Production Management (CPM) Collaboration: A synonym for cooperation To work
More informationMarket Performance Report February 2014
Market Performance Report February 2014 March 26, 2014 ISO Market Quality and Renewable Integration CAISO 250 Outcropping Way Folsom, California 95630 (916) 351-4400 Executive Summary 1 The market performance
More informationMarket Simulation Presentation Spring 2014 Release
Market Simulation Presentation Spring 2014 Release Christopher McIntosh Lead Market Simulation Coordinator Spring 2014 Release February 20 th, 2014 Agenda Spring 2014 Market Simulation Initiatives and
More informationBEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION DETERMINISTIC STUDIES
BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA Order Instituting Rulemaking to Integrate and Refine Procurement Policies and Consider Long Term Procurement Plans Rulemaking 13 12 010
More informationEIM Winter Reliability notes and processes for EIM entities. Craig Williams Training and Readiness
EIM Winter 2017 Reliability notes and processes for EIM entities Craig Williams Training and Readiness The information contained in these materials is provided for general information only and does not
More informationStudy of Using Energy Storage to Mitigate the Impact of High Renewable Energy Penetration to the Grid
Study of Using Energy Storage to Mitigate the Impact of High Renewable Energy Penetration to the Grid 2017. 05. 17 Che-I Lin (TPRI) Taiwan Power Company Outline Introduction Development of Renewable Energy
More informationISO New England Available Transfer Capability. Implementation Document. Version 1.0
ISO New England Available Transfer Capability Implementation Document Version 1.0 1 Effective: 04/01/2011 Table of Contents 1. Introduction... 3 2. Transmission Service in the New England Markets... 6
More informationSimulatie van het EU-wijde elektriciteitsysteem. Modellering van de elektriciteitsmarkt en de hierin gebruikte elektriciteitsinfrastructuur
Document number Simulatie van het EU-wijde elektriciteitsysteem Modellering van de elektriciteitsmarkt en de hierin gebruikte elektriciteitsinfrastructuur Presentatie voor Kivi Niria Utrecht, 16 April
More informationGas-Electric Coordination in PJM: Trends, Issues, Interactions, and Looking Ahead
Gas-Electric Coordination in PJM: Trends, Issues, Interactions, and Looking Ahead Harvard Electricity Policy Group 68 th Plenary Session Paul M. Sotkiewicz, Ph.D. Chief Economist PJM Interconnection October
More informationPortland General Electric 2016 Integrated Resource Plan. OPUC Public Meeting December 20, 2016
Portland General Electric 2016 Integrated Resource Plan OPUC Public Meeting December 20, 2016 Agenda Process and Compliance Approach and Summary Analysis Action Plan Next steps 2 2013 IRP Order Resource
More informationEnergy Imbalance Market Year 1 Enhancements Phase 2. Draft Final Proposal
Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal September 8, 2015 Energy Imbalance Market Year 1 Enhancements Phase 2 Draft Final Proposal Table of Contents 1 Introduction... 3
More informationThe Decarbonized Electrification Pathway: Taking Stock of Canada s Electricity Mix and Greenhouse Gas Emissions to 2030.
The Decarbonized Electrification Pathway: Taking Stock of Canada s Electricity Mix and Greenhouse Gas Emissions to 2030 Final Report Research commissioned by CanSIA and CanWEA Dave Sawyer dave@enviroeconomics.ca
More informationINTEGRATED TRANSMISSION PLANNING MANUAL
INTEGRATED TRANSMISSION PLANNING MANUAL Published on July 20, 2017 Pending FERC approval of Tariff language By SPP staff REVISION HISTORY DATE OR VERSION NUMBER AUTHOR CHANGE DESCRIPTION COMMENTS 10/13/2010
More informationMarket System Evaluation. March 2017
Market System Evaluation March 2017 Executive Summary MISO s ability to execute its strategy is predicated upon having secure systems providing the tools and information required. Last fall we initiated
More informationUNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Offer Caps in Markets Operated by ) Docket No. RM16-5-000 Regional Transmission Organizations ) and Independent System Operators
More informationGas-Electric Infrastructure Challenges. WPUI Gas Program September 17, September 13, 2012 Madison, WI
Gas-Electric Infrastructure Challenges WPUI Gas Program September 17, 2012 MISO EPA/Gas related efforts - Timeline EPA Rules & Regulations MISO EPA Impact Study, Oct 2011 Gas Consultant Phase 1 Study,
More informationJanuary 3, 2018 MEMORANDUM. Council Members. John Ollis, Power System Analyst. SUBJECT: Marginal Carbon Emissions Rate Study Draft BACKGROUND:
Henry Lorenzen Chair Oregon Bill Bradbury Oregon Guy Norman Washington Tom Karier Washington W. Bill Booth Vice Chair Idaho James Yost Idaho Jennifer Anders Montana Tim Baker Montana January 3, 2018 MEMORANDUM
More informationParameter Tuning for Uneconomic Adjustments. Lorenzo Kristov, Principal Market Architect
Parameter Tuning for Uneconomic Adjustments Lorenzo Kristov, Principal Market Architect Stakeholder Meeting May 13, 2008 Topics for Discussion Objectives of Current Parameter Tuning Effort Parameter Tuning
More informationATTACHMENT C Methodology to Assess Available Transmission Capability
Improvement and Power District Revised Sheet No. 107 ATTACHMENT C Methodology to Assess Available Transmission Capability This methodology is excerpted from the report Determination of Available Transfer
More informationDecember 20, Amendment to Attachment C to the Southern Companies OATT Docket No. ER14-
PIYANKA GHOSAL t: (205) 226-3454 f: (205) 488-5839 e: pghosal@balch.com December 20, 2013 BY ELECTRONIC FILING Ms. Kimberly D. Bose, Secretary Mr. Nathaniel J. Davis, Sr., Deputy Secretary Federal Energy
More informationStepped Constraint Parameters. Straw Proposal
Stepped Cstraint Parameters February 28, 2017 Table of Ctents 1. Background... 3 2. s from issue paper... 3 3. Plan for Stakeholder Engagement... 5 4. Transmissi cstraint relaxati parameter... 5 5. Power
More information