Eglinton Crosstown LRT Construction Liaison Committee

Similar documents
2

WHO IS METROLINX? PLAN BUILD OPERATE

CROSSTOWN LRT Construction Liaison Committee November 1, 2017

CROSSTOWN LRT Science Centre June 15, 2017

3.6 Construction Methods

EGLINTON CROSSTOWN Fairbank Oakwood CLC April 19, 2018

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

WHO IS METROLINX? PLAN BUILD OPERATE

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Second Avenue Subway

Photos by Susie Fitzhugh. BEX IV Projects Update: Arbor Heights, Genesee Hill, Pinehurst, Thornton Creek

6 Preliminary Assessment of Construction Method and Constructability Issues

Welcome to the Online Consultation

WELCOME LOCAL SEGMENT PUBLIC MEETING SUMMARY OF PRELIMINARY RESULTS CORRIDOR EVALUATION

COMMUNITY BOARD EIGHT

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

Fleet Elementary School

Ironton Russell Bridge Project

The Construction of the Langham Place in Mong Kok An Introduction

Dulles Corridor Metrorail Project Phase 1 & Phase 2 Updates

Community Meeting 1269 Danforth Road Traction Power Substation, No Frills and Winter Avenue Emergency Exit Buildings November 7, 2018

Constructability Guidelines

Dulles Corridor Metrorail Project

Progress update (November to March) 03/23/2009 2

Ironton Russell Bridge Project

Phase 2 Exposition Metro Line Project

Ironton Russell Bridge Project

Dulles Corridor Metrorail Project

Purple Line Extension. Wilshire/La Cienega and Wilshire/Rodeo Stations December 12, 2018

Regional Connector Transit Project Construction Update. June 9, 2016 Project Wide Community Meeting

Building Excellence IV Capital Levy Projects Under Construction

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

Seven Wonders of the Ancient World

4.0 CONSTRUCTION METHODS AND ACTIVITIES

Ironton Russell Bridge Project

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

Ironton Russell Bridge Project

Dulles Corridor Metrorail Project

Gautrain construction update

Capital Rail Constructors: Quarterly Update to MWAA Board of Directors

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.

Jobsite Layout Considerations

Eastside Transit Corridor Phase 2

Preferred Elevated Tank Site

Trenchless Crossing of a Failure Prone Watermain in Poor Soil Conditions

DETROIT RIVER INTERNATIONAL CROSSING STUDY MAG

Ironton Russell Bridge Project

Purple Line Extension. Beverly Hills Community Meeting August 22, 2016

The Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok

Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options

Phase 2 Exposition Metro Line Project

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

Ironton Russell Bridge Project

Index to Technical Specifications

Dulles Corridor Metrorail Project PHASE 2 MONTHLY COST AND SCHEDULE UPDATE AS OF SEPTEMBER 30, 2018 NOVEMBER 2018

An Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System

Construction of a Semi-Buried Building A Super-sized Shopping Mall : The Festival Walk

CWRP WEEKLY CONSTRUCTION PROGRESS REPORT Week ending March 2, 2013

New Main Hospital, Site Park, and Underground Garage Construction Progress Update #15

Andy Kirby. Prepared for: Senior Project Manager for The Church of Jesus Christ of Latter-day Saints. April Graduate Mentor: Andrew Luna

Ironton Russell Bridge Project

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

HUDSON TUNNEL PROJECT

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53

CTA Capital Construction Update August 8, 2007

Presented by: Frank Guyamier

Hamilton Rapid Transit Preliminary Design and Feasibility Study

Chuck Brooks, P.E., P.Eng. C&S Engineers

Technical Report II. The Office Building. Rendering courtesy of DAVIS. Brett Miller. Dr. Gannon Construction

Dulles Corridor Metrorail Project

Woodbridge Redevelopment Update. CLC Meeting #6 Wednesday, December 13, 2017

Structural Design Engineers 120 Montgomery Street, Suite 1410 San Francisco, California / Fax 415/

Westside Purple Line Extension Section 1 Project Overview

Dulles Corridor Metrorail Project

Project Status Report

Project: King Abdulaziz International Airport KAIA 2

COMMUNITY BOARD EIGHT

Formwork being erected

TCC Systems. Timber-Concrete Composite TIMBER IMAGINEERING INNOVATIVE TIMBER SOLUTIONS

CAC Meeting Construction Update April 8, 2014

Exposition Light Rail Transit Project

VTA s BART Silicon Valley Phase II Extension

Section 4 - Design and Construction Overview

Capital Rail Constructors a Clark & Kiewit Joint Venture Jim Ansari Senior Vice President & General Manager

TRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT

Ground Freezing for Tunnel, Shafts, and Adits

Review of Plans and Specs from a Constructability Perspective

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Westside Subway Extension

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA

John Hart Generating Station Replacement Project. May 2017 Community Construction Update Report #47

Technical Report #2. Matthew R Peyton

Tilikum Crossing Transit Bridge. Portland, OR

Elevated Slab Sequence

Construction of the Manulife Tower Redevelopment of the previous Lee Gardens Hotel in Causeway Bay

John Hart Generating Station Replacement Project. June 2017 Community Construction Update Report #48

Previous Tunnel News

New Reclaim Tunnel at Coal Fired Plant

Transcription:

Eglinton Crosstown LRT Construction Liaison Committee May 30, 2017

Agenda Eglinton Crosstown LRT Overview Eglinton Maintenance & Storage Facility Mount Dennis Station Railway Corridor West Portal & Elevated Guideway Tunnel Fit Out Keelesdale Station Caledonia Station 2

Eglinton Crosstown LRT A 19-kilometre route separated from regular traffic 10-kilometres underground in west and central areas; 9-kilometres at surface in east 15 underground stations and 10 surface stops A maintenance and storage facility Transit communications system Links to 54 bus routes, 3 subway stations, GO Transit, UP Express station 3

Eglinton Crosstown LRT: Key Milestones 74 Months Substantial Completion Ready for Testing and Commissioning March 2020 4 LRV Delivery Dates November 2018 3 EMSF Ready 1 st LRV Delivery October 2018 2 Contract signed and Mobilization July 2015 1 4

Maintenance & Storage Facility Concept: Aerial View 5 3 2 1 4 1. Vehicle Cleaning Staff Building 2. Vehicle Cleaning & Inspection Facility (VCIF) *60% rendering 3. Maintenance Building 4. Operations Control Center 5. Operations Company (OPSCO) 5

Eglinton Progress Maintenance to Date EMSF and Storage Facility Maintenance Building foot print Train Wash Staff Building 6

Progress to to date: Date EMSF EMSF Environmental & geotechnical testing Foundations for Maintenance, OPSCO, Vechile Cleaning and Staff Buildings Site services dry/wet utilities (ongoing) Steel erection for Maintenance Building (started) 7

Mount Dennis Concept: Aerial View 5 6 1 4 7 3 8 2 1. Bus Loop 2. Main Entrance 3. Second Entrance 4. Building 9 Third Entrance 5. Maintenance Building 6. Operations Company 7. New Photography Drive Bridge 8. Rail Corridor *60% rendering 8

Mount Dennis Station No. 9 Building CP Rail Station Box Secondary Entrance 9

Progress to date: Mount Dennis Station Foundations Mount Dennis station box concrete structure main entrance (ongoing) Site services water main, sanitary and storm sewer placement Building 9 foundation 10

West Portal & Elevated Guideway 11

Progress to date: West Portal & Elevated Guideway 2000 m3 reinforced concrete poured to date Ongoing Walls and roof formwork and rebar box tunnel construction Utility relocation works for Elevated Guideway To follow: Retaining wall and backfilling for Eglinton Avenue West realignment 12

Tunnel Fit Out Invert Pour With the completion of the tunnel boring, we now start the next step for work in the tunnels with pouring of concrete slabs to invert or flatten the tunnel floor. This must occur prior to the installation of track and transit systems. Concrete slab to be poured 13

Tunnel Fit Out Concrete Pour Overview Concrete trucks deliver concrete every 30-60 minutes, depending on how far down the tunnel the work is occurring Trucks park beside the shaft at Cedarvale (Allen Rd. and Eglinton), and unload 9 m 3 of concrete into a large pipe, into one of two mini concrete trucks (4.5 m 3 each) at the shaft floor. The mini truck in the shaft then drives down the tunnel to the next section of tunnel to be inverted. The first stage of concrete pour began in tunnel section 1 on April 4, 2017, and tunnel section 2 on April 17, 2017. On average, crews complete a section approximately 80 metres in length of the concrete slab per day in each tunnel. 14

Tunnel Invert Pour Stage 1 Concrete trucks deliver loose concrete to the work area Loose concrete mix is used to fill the bottom of the tunnel Tunnel Fit Out Crew flatten and smooth it 15

Tunnel Invert Pour Stage 2 Workers install welded mesh which functions like rebar to help reinforce the next layer of concrete Higher strength concrete is poured to provide the flat track slab for the rail tracks Workers spread the concrete, and a truss screed machine vibrates it into a perfectly level surface 16

Keelesdale Concept: Aerial View 4 3 1 5 2 1. Main Entrance 2. Third Entrance 3. Second Entrance 4. Traction Power Substation (TPSS) 5. Bus Loop 17

Keelesdale Station Main Entrance Third Entrance Secondary Entrance TPSS Building 18

Progress to date: Keelesdale Station First station to start construction in March 2016 Utility relocations Shallow Excavation complete on the North Side of intersection Excavation at the Traction Power Substation (TPSS), third & main entrance North side major utility support beams installed North east side deck beams and timber mat installation All lanes to re-open to east and westbound traffic end May 2017 19

Caledonia Station Construction Update Complete Installation of geotechnical monitoring equipment Hydro utility relocation work Bell utility relocation Traffic signal relocation at Blackthorn Ave and Eglinton Ave W Piling of the station box Installation of dewatering system Shallow excavation to first round of tie-backs Installation of first round lagging, tie-backs, braces and walers Tower crane erection Spring/Summer 2017 Site service connection to wet utilities (one month) Dewatering (ongoing) Deep excavation (8 months) Monitoring of geotechnical instruments (ongoing)

Current Construction Staging Began May 29 for 1.5 weeks 21

Current Construction Staging Beginning June 8 for two (2) weeks 22

Caledonia Station Aerial Concept 23

Caledonia Station Construction Progress Drilling Tie-backs Pile Installation 24

Caledonia Station Construction Progress Hauling Spoils Trenching for Dewatering Tower Erection 25

Thank you! For more information about the Eglinton Crosstown LRT please visit: www.thecrosstown.ca