DYASON S KLIP SOLAR ENERGY FACILITY 1 (PTY) LTD. TRANSPORT STUDY AND TRAFFIC MANAGEMENT PLAN

Similar documents
DYASON S KLIP SOLAR ENERGY FACILITY 1 (PTY) LTD. STORMWATER MANAGEMENT PLAN

Project: MOE Nationwide FLS - Avalon Block Accessibility Report

Fonterra Studholme. Lighting Design Report

APPENDIX C. Draft Erosion and Sediment Control Plan

Project: MOE FLS Reference Designs for Standard Classroom Upgrade 2-storey Nelson Block

17 September 2014 Revision: 1 Reference:

Caulfield to Dandenong Level Crossing Removal Project

State highway 1 Clarence to Oaro safety and amenity improvements Business case for implementation executive summary overlay NZ Transport Agency

Traffic Impact Assessment

GRINDROD INTERMODAL TAILOR-MADE SOLUTIONS

KEYSTONE PARK LOGISTICS, WAREHOUSING & LIGHT INDUSTRIAL PRECINCT

The Project will consist of the following key components: PV solar panels/modules (arranged in arrays); DC-AC current inverters and transformers;

Environmental goods in southern and eastern Africa. Trade patterns, tariffs and non-tariff barriers Willemien Viljoen 5 December 2011

TRAFFIC IMPACT ASSESSMENT REPORT FOR PORTION 296, FARM ZUURFONTEIN 33 IR FINAL REPORT JUNE 2017

Project: Auckland Central Access Plan

Global IT Procurement and Logistics. Simplifying the complex: an end-to-end IT supply chain solution

The following section summarises the present conditions related to transportation for the proposed development of the PSS in the Steelpoort area.

DURBAN INVEST Presentation by Eskom

August. RE Capital 11 (Pty) Ltd. Solar farm development. August. Scoping Engineering Report

A comparison of road vs rail investment options on the Gauteng-Durban Corridor

Transportation Engineering

IDS. Pavement Cost Impact Assessment from Increased Vehicle Mass Limits - Calculation Sheet Guide

Peer review of options for proposed crossings of Leongatha rail reserve, Clyde Railway Station and associated train stabling

NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd

THOMAS O BRIEN PERSONAL INFORMATION DIRECTOR: GEOTECH

21 July Anthony Yeates RATCH-Australia Corporation Limited Level 7, 111 Pacific Highway North Sydney NSW 2060

Annex B2.3. Background Information Document

FOR EXAMINERS USE ONLY:

Manage Centre. Manage your IT operations from a single graphical interface

SPECIALISED LOGISTICS & 3PL SERVICE PROVIDER 30 YEARS OF PERSONAL SERVICE

U.S. Shipping Information

RATCH-Australia. 15 February Collector Wind Farm. Traffic and Transport Assessment

Traffic Management Plan

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5

Coal market a makro trend

About Zosi Group Pty (Ltd) Corporate Overview. Our routes through Africa are:

Ipad Presentation: TFR Operation in SADC Countries

Construction Commissioning 2013 Demobalisation 2013

Hastings District Council. Whakatu Arterial Link Traffic Management Plan

INFRASTRUCTURE. US$2.27 billion 17% MW

TRAFFIC IMPACT STATEMENT SOUTHERN WASTEWATER TREATMENT WORKS

Renewable Energy Development in Africa

TRANSPORT. Networks that move Zimbabwe forward

NATIONAL ROAD 3: KEEVERSFONTEIN TO WARDEN (DE BEERS PASS SECTION) CHAPTER 1: INTRODUCTION

19. ROADS AND TRANSPORT

Each week, copies are circulated and read by readers (ABC figure of April to June 2018)

Botswana Trans-Kalahari Road Construction Project. Report date: March 2001 Field survey: August Project Profile and Japan s ODA Loan

Spencer Park Paddling Pool Tank Qualitative Engineering Evaluation

FACT SHEET AVENG GRINAKER-LTA

Country CAPEXIL Description HS Codes Value Qty AFGHANISTAN TIS Asbestos cement pipes

ABNORMAL LOADS SUPER ROUTES A STRATEGIC INVESTMENT FOR PROMOTING SOUTH AFRICA S ECONOMIC GROWTH

EIA FOR THREE 10MW PHOTOVOLTAIC (SOLAR) ENERGY FACILITIES PROPOSED FOR MARIENTAL, OMARURU AND OKAHANDJA BACKROUND INFORMATION DOCUMENT

ENVIRONMENTAL IMPACT ASSESSMENT: TRAFFIC/TRANSPORTATION STUDY FOR PROJECT LIMA. for BOHLWEKI ENVIRONMENTAL

1 INTRODUCTION 1.1 PROJECT APPLICANT

Dimension Data Managed Cloud Services for Microsoft

The Benefits of Automated Permitting, Routing, and Bridge Analysis Systems

CAPITAL WIND FARM II, LAKE GEORGE

CONTACT COMPANY PROFILE. Procet Freight

ENVIRONMENTAL IMPACT ASSESSMENT: PROPOSED PHOTOVOLTAIC ENERGY PLANT ON FARM KLIPGATS PAN NEAR COPPERTON, NORTHERN CAPE

Douglas Woods Wind Farm

CITY OF VALLEJO PUBLIC WORKS DEPARTMENT TRAFFIC IMPACT Analysis/Study GUIDELINES

Clean TeQ Sunrise Project

Transport Solution 26 /10 /

Enel Green Power overview. Ruggero Arico Head of Institutional Affairs for Europe, North Africa, Sub-Saharan Africa, Asia and Australia

Victoria Park Toilets (Disabled) Qualitative Engineering Evaluation

ENGINEERING DIVISION CONCURRENT PLAN CHECK PROGRAM

PAVEMENT DESIGN: Flexible Pavement Design (JKR Method)

Respondents Countries by Countries by Region (18) RECS (6) Region Region Countries

AFRICA CLEAN ENERGY CORRIDOR Infrastructure for Renewable Power. Kudakwashe Ndhlukula Programme Officer, IRENA

Rural transport survey techniques Session: 5.5 Part 1

Rural transport survey techniques. Part 1

South Africa - Republic of LOCK-UP REPORT. Grain and Feed Update. Required Report - public distribution. Date: 5/7/2009 GAIN Report Number: SF9020

Sheldon Park - Cricket Shed Qualitative Engineering Evaluation

ACQUISITION OF MUCH ASPHALT 30 OCTOBER 2017

International Solutions

Preface. Table 1 distinguishes domestic exports from re-exports while other export tables give total exports, which is the sum of the two.

White Rock Wind Farm. Traffic and Transport Impact Assessment

The Challenges of Migration of a Plaza-Based operation to a National Back Office within an AET Environment: the South African experience

FOR SALE / LEASE 420,000 SF AC

EIA Update Report for the Keadby 2 Combined Cycle Gas Turbine Generating Station at Keadby, Lincolnshire. The business of sustainability

OVERVIEW: Treatment Length Segmentation KEY POINTS

NAMIBIA: LOGISTICS HUB FOR SOUTHERN AFRICA CAPE TOWN, SOUTH AFRICA 17 NOVEMBER 14 (& BEYOND)

Englefield Reserve Toilet Qualitative Engineering Evaluation

Photovoltaic Power Generation Facility, Prieska EXECUTIVE SUMMARY

TRAFFIC MANAGEMENT PLAN

2-2 ALTERNATIVES CONSIDERED AND ELIMINATED

Keywords: High Productivity Freight Vehicles, safety, productivity, access, local government

PROPOSED CAPACITY UPGRADES TO THE N3 FROM LYNNFIELD PARK (KM 30.6) TO GLADYS MANZI (FORMERLY MURRAY) ROAD (KM 6.1) (DEA REF NO: 14/12/16/3/3/1/1966)

PRIVATE ROAD AND DRIVEWAY STANDARDS Development Standard #1 (Rev 7/18)

Your success is our success Your success is our success

2008 Investor Site Visit - Maputo

INVESTING IN AFRICA. Company Profile

Capital Markets Day 13 June 2017

Review of Plans and Specs from a Constructability Perspective

KUYASA MINING (PTY) LTD KIPOWER IPP PROJECT INTEGRATED WATER USE LICENSE APPLICATION METHOD STATEMENT WORK IN WETLAND AREAS AND RIVERS

POSTMASBURG SOLAR PV ENERGY FACILITY 2 (PTY) LIMITED

B366 - REPAIRING CONCRETE PAVEMENT AND CONCRETE BASE - OPSS 366

A critical investigation into tyre life on an iron ore haulage system

AFRICA. Transforming Africa s energy landscape today

SOCIAL IMPACT ASSESSMENT PROPOSED KAKAMAS PHOTOVOLTAIC SOLAR ENERGY FACILTY NORTHERN CAPE PROVINCE INCA ENERGY

Transcription:

DYASON S KLIP SOLAR ENERGY FACILITY 1 (PTY) LTD. TRANSPORT STUDY AND TRAFFIC MANAGEMENT PLAN Reference: A43448 Prepared for: ATLANTIC RENEWABLE ENERGY PARTNERS (Pty) Ltd Revision: 1 4 November 2014

Document control record Document prepared by: Aurecon South Africa (Pty) Ltd Aurecon Centre 1 Century City Drive Waterford Precinct Century City, Cape Town, 7441 T F E W +27 21 526 9400 +27 21 526 9500 capetown@aurecongroup.com www.aurecongroup.com A person using Aurecon documents or data accepts the risk of: a) Using the documents or data in electronic form without requesting and checking them for accuracy against the original hard copy version. b) Using the documents or data for any purpose not agreed to in writing by Aurecon. Document control Report title TRANSPORT STUDY AND TRAFFIC MANAGEMENT PLAN Document ID A43448/TP/3 Dyason s Klip Project number A43448 File path Client P:\Projects\_RSK Projects\PRCPTENE03\A43448 Solek Solar Site Transport Studies\03 PRJ Del\6 REP\Dyasonsklip\A43448 DyasonsKlipSolarEnergyFacility1_Transport&TrafficManagementPlan_Oct2014-R1.docx ATLANTIC RENEWABLE ENERGY PARTNERS (Pty) Ltd Client contact Thys van der Hout Rev Date Revision details/status Prepared by Author Verifier Approver 0 30 October 2014 Draft HS HS JHBC JHBC 1 4 November 2014 Final HS HS JHBC JHBC Current Revision 1 Approval Author signature Name Title Approver signature Name Title November 2014 Revision 1

DYASON S KLIP SOLAR ENERGY FACILITY 1 (PTY) LTD. Date 4 November 2014 Reference A43448 Revision 1 Aurecon South Africa (Pty) Ltd Aurecon Centre 1 Century City Drive Waterford Precinct Century City, Cape Town, 7441 T F E W +27 21 526 9400 +27 21 526 9500 capetown@aurecongroup.com www.aurecongroup.com November 2014 Revision 1

Contents EXECUTIVE SUMMARY 1 1 INTRODUCTION 1 2 DEFINITIONS / ASSUMPTIONS 3 3 EVALUATION OF SITE TRANSPORT 4 3.1 General Freight Requirements 4 3.2 Dyasonsklip Solar Energy Facility 1 Access Route 5 4 CONCLUSION 15 Figures Figure 1: Key Plan 1 Figure 2: Site Description 5 Figure 3: Preferred Freight Route 6 Figure 4: Alternative Port Route 10 Figure 5: Routes from Other Manufacturing Centres 11 Figure 6: Access Road to Solar Facility 13 Figure 7: Accommodation of Traffic - Typical Layout 14 Tables Table 1: Route Elements - Details 7 Table 2: Route Elements - Evaluated 11 November 2014 Revision 1 Page 1

EXECUTIVE SUMMARY The transport needs for the proposed Dyason s Klip Solar Energy Facility 1 (Pty) Ltd. on the Rem of farm 454 Dyason s Klip was investigated to confirm access route and site access for the development of a Solar Farm. The general requirements are: Legal limits for normal heavy vehicle freight Abnormal Permits required for transport of transformers Maximum vertical clearance on most routes is 5,2m for Abnormal Load but should preferably be limited to 4,8m. The general freight for the solar farms comprise of building materials, solar panels and frames and an 80MVA transformer. The imported freight will be transported from South African ports to the respective sites. Building materials will be transported from sources in surrounding towns while certain elements will be transported from various manufacturing centres in South Africa. The preferred import origin of the imported elements to the proposed Dyason s Klip Solar Energy Facility 1 (Pty) Ltd. will be from the Saldanha port. The route distance of 773 km via Calvinia comprises of surfaced roads the full way. There is also an alternative route via Springbok available, should periodic maintenance limit the use of the preferred route. The transport distance in this case is 880 km. No toll fees are required. Abnormal Permits will be required for transport of the transformer in any event. The route is predominantly on National or Provincial Roads with suitable standards for transport of container freight. It is also suitable for abnormal loads with permits. There is a possibility of limited risk of delays for normal routine maintenance works (repairs and reseals) depending of the time of transport and scheduling of roads contracts. However, there is an alternative route on National roads available. The transport of elements from manufacturing centres within South Africa is predominantly on National and Provincial roads, which presents no limitations for normal freight. The proposed preferred access position on the National Road N14/4 at km 16,64E is at an acceptable safe point with sufficient sight distance and also more than 500m from the nearest access which would be acceptable to SANRAL as the road authority. The preferred access route on the site is predominantly on existing tracks / access roads which will require upgrade to suitable standards for accommodation of the freight. In general no obvious problems are expected with freight transport along the proposed routes to the site and also for accesses necessary for the construction and maintenance of the site. November 2014 Revision 1 Page 1

1 INTRODUCTION Atlantic Renewable Energy Partners (Pty) Ltd has engaged Aurecon to prepare a Transport Management Plan for the proposed Dyason s Klip Solar PV Facility approximately 22km south-west of Upington on the Rem of Farm 454 Dyason s Klip next to the N14. The site location is indicated on the Key Plan below: NAMIBIA N14 VRYBURG N10 PRIESKA KAKAMAS Dyason s Klip Solar Energy Facility 1 (Pty) Ltd. Rem of Farm 454 KENHARDT Figure 1: Key Plan The solar site will be developed to 75 MW capacity. November 2014 Revision 1 Page 1

The scope of the study is to evaluate the transport requirements to support the development of the Dyason s Klip Solar Energy Facility 1 (Pty) Ltd. The scope of the Transport Management Plan includes inter alia: Determine the access freight routes between points of delivery and departure for the components. Confirm the associated clearances required for the necessary equipment to be transported from the point of delivery to the various sites. Confirm freight requirements. Propose origins and destinations of equipment. Determine (Abnormal) Permit requirements if any. Propose traffic accommodation measures during potential upgrading of the access on the Provincial Road. November 2014 Revision 1 Page 2

2 DEFINITIONS / ASSUMPTIONS The following assumptions are made: Imported elements are imported and transported from the nearest or most practical South African Port to the site. Certain elements are transported from manufacturing centres within South Africa. Material for concrete piles and road construction are obtained locally from closest available commercial source. The largest potential load will be a single 80MVA transformer with a payload of approximately 70t. Freight will be transported predominantly on surfaced roads. Foundations will ultimately be dictated by site geotechnical conditions but generally comprise of concrete piles to reduce risk of failures due to varying conditions for the developer. The access location is approximately at km 18 on the N14/4 based on available information, but will have to be confirmed with SANRAL depending on where the access will be approved. November 2014 Revision 1 Page 3

3 EVALUATION OF SITE TRANSPORT 3.1 General Freight Requirements 3.1.1 Legislation The general current limitations on road freight transport are: Axle load limitation of 7,7t on front axle, 9,0t on single rear axles. Axle unit limitations are 18t for dual axle unit and 24t for 3 axle unit. Bridge formula requirements to limit concentration of loads and to regulate load distribution on the vehicle. Gross vehicle mass of 56t. This means a typical payload of about 30t. Maximum vehicle length of 22m for a interlink, 18,5m for horse and trailer and 13,5m for a single unit. Width limit of 2,6m. Height limit 4,3m. Abnormal permits are required for vehicles exceeding these limits. 3.1.2 Solar Facility Freight Materials and equipment transported to the site comprise of: Building materials (concrete aggregates, cement and gravel). Construction equipment such as piling rigs and cranes. Solar panels (panels and frames). Transformer and cables. November 2014 Revision 1 Page 4

The following is anticipated: a) Building materials comprising of concrete materials for strip footings or piles will be transported using conventional trucks which should adhere to legal limits. b) Solar Panels and frames will probably be transported in containers using conventional heavy vehicles within the legal limits from nearest South African port. The number of loads will be a function of the capacity of the solar farm and the extent of the frames. c) Transformers will most probably be transported by abnormal vehicles from the nearest South African port. 3.1.3 Traffic Statement It is estimated from experience on other projects that the number of heavy vehicles per 7MW installation would be between 300 and 400 heavy vehicle trips depending on the site condition and founding requirements. The total trips for the 75MW would be between 3000 and 4000 heavy vehicle trips. These trips would be made over an estimated period of 9 to 12 months. In the worst case the number of heavy vehicle trips per day would be in the order of 15-20 trips. The impact of this on the general traffic would therefore be negligible as the additional peak hour traffic would be at most 2 trips. Current traffic volumes on N14 are estimated from the most recent SANRAL yearbook at about 3000 ADT and a maximum hourly flow of about 200 veh/h for this section of road. It can therefore be stated that the construction traffic and the post construction traffic would be low without any significant impact on the existing traffic as well as negligibly pavement structure consumption. 3.2 Dyasonsklip Solar Energy Facility 1 Access Route 3.2.1 Site Description The site description is as follows: Dyason s Klip Solar Energy Facility 1 (Pty) Ltd. Location Distance SW from Upington Generation Capacity Distance from Ports Saldanha (R27) Saldanha (N14) Port Elizabeth 28 32'42.20"S 21 2'20.91"E 22 km 75MW 773 km 880 km 939 km Farm Rem of Farm 454 Dyason s Klip Figure 2: Site Description November 2014 Revision 1 Page 5

3.2.2 Preferred Route from port The route for transportation of imported equipment is either from Saldanha or Port Elizabeth. Saldanha is the obvious preferred port with the shortest route as indicated in the figure below. It should be noted that the Ports Authority also has preferences on freight import which should be respected. November 2014 Revision 1 Page 6

The route elements are as follows: Table 1: Route Elements - Details Element Route Name From To Distance [km] 1 R27 Saldanha Velddrif 33 Type Surfaced Provincial Road R27 is a surfaced 2 lane road with surfaced shoulders 2 R399 Velddrif Piketberg 62 Surfaced Provincial Road R399 is a surfaced 2 lane road with gravel shoulders November 2014 Revision 1 Page 7

Element Route Name From To Distance [km] 3 N7 Piketberg Vanrhynsdorp 174 Type Surfaced National Road N7 is a single carriageway two lane road with gravel shoulders (Surfaced in places) 4 R27 Vanrhynsdorp Calvinia 121 Surfaced National Road R27 is a single carriageway two lane road with surfaced shoulders (Recently upgraded) November 2014 Revision 1 Page 8

Element Route Name From To Distance [km] 5 R27 Calvinia Keimoes 366 Type Surfaced National Road R27 is a single carriageway two lane road with gravel shoulders 6 N14 Keimoes Site 17 Surfaced National Road N14 is a single carriageway two lane road with gravel shoulders 7 Site access road N14 site 9 TOTAL DISTANCE [km] 782 Note: 1 The recommended route indicated in the table Gravel Access Road 6m wide 3.2.3 Route for Construction materials Material sources for road building and concrete works is available in Upington and all material will most likely be transported from there and possibly other surrounding towns on the National road. November 2014 Revision 1 Page 9

3.2.4 Alternative Route from Port Should the preferred route not be acceptable or engaged under periodic maintenance works, then the route via Springbok could be used as alternative. This route from Saldanha ( a distance of 880km) is shown in the following figure and follows the National Road. Figure 4: Alternative Port Route The route from the alternative port of Port Elizabeth is about 940km and the least preferred route but also offers an alternative should Saldanha port not be available for any reason. 3.2.5 Routes from other Larger Manufacturing Centres The other potential main manufacturing centres include Gauteng - greater Johannesburg area (Modderfontein, Edenvale, Nigel, Germiston, Brakpan, Elandsfontein) for inverters and support structures. Pinetown (Kwazulu-Natal) for PV modules. November 2014 Revision 1 Page 10

The routes to the site from these centres are predominantly on Provincial and National roads. The following figure shows the most probable routes. Gauteng to the site Pinetown to the site Distance : 805 km Distance : 1205 km Figure 5: Routes from Other Manufacturing Centres There are no limitations on normal freight on these routes. 3.2.6 Authority and Permit Requirements The following is noted: a) No toll fees required on the routes from the port. On the routes from the other manufacturing centres certain portions of the national routes are tolled which will required toll fees. b) An Abnormal permit will be required for the transport of the transformer. The estimated permit value will be a function of the actual vehicle configuration but is estimated at R7000 R9000 per trip. 3.2.7 Route Limitations of the Preferred Route from the Port The routes elements are evaluated as follows: Table 2: Route Elements - Evaluated Element Road Remark Comment General No limitations on normal heavy vehicles. Permits required from the Provincial Authorities for abnormal loads such as the transformer. Vertical clearance of bridges in general 5,2m. However, should the transformer exceed 5,2m then the route will have to be confirmed or altered as required but the permit conditions will direct the load on an approved route. 1 R27 None 2 R299 Possible delays due to periodic maintenance Currently no contracts active. November 2014 Revision 1 Page 11

Element Road Remark Comment required by Provincial Authorities. 3 N7 Possibility of periodic maintenance required by SANRAL for repairs / reseal Currently Rehabilitation between Clanwilliam to Vanrhynsdorp ending middle/end 2016 4 R27 None Recently upgraded 5 R27 None Recently resealed 6 New Access Road None 7 New Access Road None Part of the internal roads 3.2.8 Site Access 3.2.8.1 Access to Road Network The access to the site is proposed off the National Road 14 Section 4. There are three possibilities: Access Road Alternative 1: At the current property access to the N14/4 at km 16,64. Access Road Alternative 2: At the new access to the proposed CSP plant on the neighbouring farm McTaggarts Camp 453 at km 18.3. Access Road Alternative 3: From the Provincial Road D3276. Access 1 has sufficient sight distances and should therefore be approved by SANRAL as development access. The only probable requirement would be the potential upgrading of the intersection to surfaced standards with turning lanes. This access upgrading will be limited to the current road reserve. Access 2 is already upgraded to surfaced standards with turning lanes for use by the CSP plant under construction on McTaggarts Camp 453. Access 3 is an access off the current gravel Provincial road and will require nominal provision for drainage and turning. The final access position selected will also depend on the most suitable access route. 3.2.8.2 Internal Access Road to Site There are a number of options available as follows:. Route 1: Access road from Access 1. Route 2: Access Road from Access 2. Route 3: Access road from Access 3. November 2014 Revision 1 Page 12

The respective access routes and access positions are shown in the following figure: Access 3 Legend National Road Provincial Road New Road On Existing Dyasons Klip PV solar facility Access 2 Access 1 Figure 6: Access Road to Solar Facility The potential access routes are discussed in more depth below: (i) Route 1 This access route will follow the existing track /access road to an old tungsten mine as far as possible and could require upgrading (as gravel road) to accommodate the construction freight. If the route cannot follow the existing track for any reason, (such as limitations by drainage elements or ownership) then new alignments will be required. (ii) Route 2 This access route will follow the newly constructed surfaced road for the McTaggerts Camp CSP plant and be extended with a gravel road to the site. It will require agreements with the owners of the McTaggarts CSP plant and the Rooipunt Farm owners as the route will be on neighbouring properties. The advantage is that no upgrading of the intersection on the N14 will be required but it will need the consent of the CSP plant developer and other owners. (iii) Route 3 This access route will be on a new alignment within the Dyason s Klip farm for most of the distance and then follow the existing track / access road to the old tungsten mine. 3.2.8.3 Preferred Access Route The upgrading of the existing access and access route 1 is the preferred option as it is not dependent on other developments or owners consent. The road should be upgraded to at least a 5m width (preferable 6m with sufficient shoulders) and gravel wearing course layer. November 2014 Revision 1 Page 13

3.2.8.4 Structures and Services Existing structures and services such as drainage structures and pipelines will be evaluated if crossed as part of the access route and suitable strengthened if required. The site drains to the South-East. Suitable drainage elements will be provided along the preferred access route to ensure minimal disturbance of the existing drainage patterns. 3.2.9 Accommodation of Traffic during Construction SANRAL may require upgrading of the intersection to the site. During upgrading of the access, traffic will have to be accommodated as per SADC Road Traffic Signs Manual requirements. The following typical minimum signage requirements will have to be implemented to ensure safety if the road needs closure during construction. Figure 7: Accommodation of Traffic - Typical Layout November 2014 Revision 1 Page 14

4 CONCLUSION The transport needs for the proposed Dyason s Klip Solar Energy Facility 1 (Pty) Ltd. on the Rem of farm 454 Dyason s Klip was investigated to confirm access route and site access for the development of a Solar Farm. The general requirements are: Legal limits for normal heavy vehicle freight Abnormal Permits required for transport of transformers Maximum vertical clearance on most routes is 5,2m for Abnormal Load but should preferably be limited to 4,8m. The general freight for the solar farms comprise of building materials, solar panels and frames and an 80MVA transformer. The imported freight will be transported from South African ports to the respective sites. Building materials will be transported from sources in surrounding towns while certain elements will be transported from various manufacturing centres in South Africa. The preferred import origin of the imported elements to the proposed Dyason s Klip Solar Energy Facility 1 (Pty) Ltd. will be from the Saldanha port. The route distance of 773 km via Calvinia comprises of surfaced roads the full way. There is also an alternative route via Springbok available, should periodic maintenance limit the use of the preferred route. The transport distance in this case is 880 km. No toll fees are required. Abnormal Permits will be required for transport of the transformer in any event. The route is predominantly on National or Provincial Roads with suitable standards for transport of container freight. It is also suitable for abnormal loads with permits. There is a possibility of limited risk of delays for normal routine maintenance works (repairs and reseals) depending of the time of transport and scheduling of roads contracts. However, there is an alternative route on National roads available. The transport of elements from manufacturing centres within South Africa is predominantly on National and Provincial roads, which presents no limitations for normal freight. The proposed preferred access position on the National Road N14/4 at km 16,64E is at an acceptable safe point with sufficient sight distance and also more than 500m from the nearest access which would be acceptable to SANRAL as the road authority. The preferred access route on the site is predominantly on existing tracks / access roads which will require upgrade to suitable standards for accommodation of the freight. In general no obvious problems are expected with freight transport along the proposed routes to the site and also for accesses necessary for the construction and maintenance of the site. November 2014 Revision 1 Page 15

Aurecon South Africa (Pty) Ltd Aurecon Centre 1 Century City Drive Waterford Precinct Century City, Cape Town, 7441 T +27 21 526 9400 F +27 21 526 9500 E capetown@aurecongroup.com W www.aurecongroup.com Aurecon offices are located in: Angola, Australia, Botswana, China, Ethiopia, Ghana, Hong Kong, Indonesia, Lesotho, Libya, Malawi, Mozambique, Namibia, New Zealand, Nigeria, Philippines, Qatar, Singapore, South Africa, Swaziland, Tanzania, Thailand, Uganda, United Arab Emirates, Vietnam.