Schnabel Foundation Company

Similar documents
Lesson 4. Construction Techniques and Materials. Learning Outcomes. Basic Construction

Recent Advances in the Selection and Use of Drilled Foundations

SPECIAL SPECIFICATION 4401 Prestressed Ground Anchors

Case Study. The Challenge. Deep Micropile Installation Under Existing Multistory Building

STANDARDIZED STRUCTURES

SAS Micropile Manual. Basic dimensioning and design recommendations. Table of Content:

MICROPILE FOUNDATIONS FOR RECONSTRUCTION OF HISTORIC LA LOMA BRIDGE IN PASADENA, CALIFORNIA. Casey Garneau 1

Learning Outcomes. Background Definitions. Lesson 2 & 3. Definitions, Background, Classification, Applications and Costs

SPECIAL SPECIFICATION 4492 Tie Back Anchors

Foundation Strengthening Of Bascule Piers At The Bridge Of Lions

Rehabilitation of Masonry Piers at Nipigon, Ontario

STANDARD SPECIFICATION FOR MICROPILE CONSTRUCTION

DESIGN-BUILD-TEST PROCESS FOR HIGH CAPACITY MICROPILES: CONSTRUCTION CASE STUDY ON DUTCHESS RAIL TRAIL BRIDGE FOUNDATIONS, POUGHKEEPSIE, NEW YORK

CASE STUDY: LOAD TRANSFER ANALYSIS ON AN INSTRUMENTED AUGERCAST PILE USING EDC STRAIN GAUGES AND GEOKON REBAR STRAINMETERS

This drawing. is preliminary. and not for. construction or. implementation. purposes. project number 170 END VIEW DESIGN STRENGTHS: PLAN

Micropile Lateral Load Testing in the Charleston, SC Area

John James Audubon Bridge

Non-destructive Testing of Installed Soil Nails Using Sonic Echo Test Method

Final Estimates Level 2

HIGH CAPACITY MICROPILES IN WEAK DOLOMITIC LIMESTONE FOR CRANE FOUNDATION SUPPORT

CONSTRUCTION SPECIFICATIONS FOR ALABAMA STATE PORT AUTHORITY MCDUFFIE TERMINALS CONVEYOR 44 PILING INSTALLATION

DUCTILE IRON PILES ARE HIGHLY EFFECTIVE, FAST AND VERSATILE MODULAR DRIVEN MICROPILE SYSTEMS

Figure 1. Horst Aschenbroich, President/CEO, Con-Tech Systems Ltd.

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

The requirements for the above tender items are contained in OPSS 942.

Earth Retention Systems

CONCRETE TECHNOLOGY CORPORATION

DRILLED-IN DISPLACEMENT MICROPILES INSTALLED WITH NO VIBRATION + NO NOISE

Lesson 7 & 8 Construction Inspection/ Quality Control (QA/QC) Load Testing. Learning Outcomes. Quality Assurance and Quality Control (QA/QC)

Pushing the Envelope For 100 Years

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction

Case Histories. Cap and Compaction Grouting for Sinkhole Remediation R.M. Bivens, P.E. Rembco Geotechnical Contractors, Inc.

7 Bridges in 74 Days. NC 12 Detour

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

John James Audubon Bridge. Introduction

Rak Production Technology of Concrete Structures (2015) Concrete Reinforcement

Environmental Management Chapter

Foundation Innovations Ensure Successful Bridge Replacement

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2

MICROPILE LATERAL LOAD TESTING IN CHARLESTON, SOUTH CAROLINA, USA

Design of Deep Foundations for Slope Stabilization

A. Installer Qualifications: A firm shall have a minimum of five projects successfully constructed in the last ten (10) years.

DRILLED-IN DISPLACEMENT MICROPILES INSTALLED WITH NO VIBRATION + NO NOISE

6 CONTRACTOR, EQUIPMENT & PILES ARRIVE ON-SITE

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

Deep Water Drilled Shafts for the Herrington Lake Bridge Replacement Project

HAMMER GROUT PILES FOR THE BRONX WHITESTONE BRIDGE

STRUCTURE AND BRIDGE DIVISION

REINFORCED CONCRETE MASONRY SECTION

September 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE

SECTION NONPRESTRESSED ROCK ANCHORS. 1. Placing drawings. 2. Bar details. 3. Manufacturer s data, and recommendations for grout.

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS

Ellis Powell, PE NCDOT State Construction Engineer

SECTION PORTLAND CEMENT CONCRETE

LOAD FACTOR RESISTANCE DESIGN

Bridge Manual - Part I - June CHAPTER 5 SPECIAL PROVISIONS AND ESTIMATE

Construction Measurement III SBQ3314. Precast Pre stressed Concrete Works. Dr. Sarajul Fikri Mohamed

Structural Lightweight Concrete for Accelerated Bridge Construction

BORED MICROPILES. I.S.M 2009 London (10 th to 13 th may) 9 th International worksop on micropiles - by A. Jaubertou -

Ironton Russell Bridge Project

Specialty Applications. for Keystone Walls

THE EVOLUTION OF MICRO PILES IN AMERICA

TECHNICAL ASSISTANCE REPORT EFFECT OF CONCRETE REMOVAL EQUIPMENT AND METHODS ON THE CONDITION OF DECK CONCRETE LEFT IN PLACE

US-131 Over the Muskegon River. Corey Rogers, P.E. Bridge Construction Engineer

Bond Strength of Hollow-Core Bar Micropiles

Chapter 8 Anchoring Structures

Report D4.3. Field demo of bridge in Florida

Analysis of Four Load Tests on Augered Cast-in-Place Piles in the Texas Gulf Coast Soils Raghu Dass, PE, Woodward Vogt, PE, and Frank Ong, PE

Halls River Bridge Update

TYPICAL INSTALLATION INSTRUCTIONS

Design of Buchanan County, Iowa, Bridge Using Ultra High Performance Concrete and PI Girders

Ironton Russell Bridge Project

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

PRECAST CONCRETE GIRDER ERECTION

Exploration, Sampling, and In Situ Soil Measurements. Dr. Omar Al-Hattamleh

HIGH CAPACITY ROCK ANCHORS IMPLEMENTATION OF QA/QC PROGRAMS. JULIO DIAMANTE, P.E.

703 - DRILLED SHAFTS SECTION 703 DRILLED SHAFTS

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

CHEMICAL /4" 3/8" to 5/8" /8" 3/4" to 1-1/4" 1 10

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

Special Requirements for Precast Bent Cap Connections C General

Design Specifications- Micropile Foundation System. Geopier Calculations

SR 600 (US 92) Concrete Slab Replacement Reconstruction Project with Precast Pre-Stressed. Florida Department of Transportation District Five

Section REINFORCING STEEL

I-495 HOT LANES PROJECT VIRGINIA CONCRETE CONFERENCE CONCRETE: LEADING THE WAY. Dan Staron, P.E. HNTB Corporation MARCH 4, 2010

GEOTECHNICAL RESISTANCE FACTORS

Bi-Directional Static Load Testing of Driven Piles

Appendix VIII. Guidelines for groundwater bores and wells

CONCRETE TECHNOLOGY CORPORATION

Our Tour Stops. A Foundation Engineering gtrip down the Mississippi River. Dan Brown, P.E. Dan Brown and Associates 9/6/2010.

B. Extent of the Work: The Work specified in this Section shall include, but is not limited to, the following principal items:

Design Construction Of Bored Pile Foundation

CHAPTER 32 - WELL ABANDONMENT ORDINANCE OF DUBUQUE COUNTY, IOWA. Adopted September 5, Part 1 Introduction...2

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

CW 3615 RIPRAP TABLE OF CONTENTS

ISM 2007 Toronto, Canada Horst Aschenbroich Dipl. Ing. President & CEO of Con-Tech Systems LTD. Titan Hollow Bar

UNDERWATER BRIDGE INSPECTION REPORT DISTRICT 6 - RICE COUNTY

Over the last decade, drilled and postgrouted micropile foundations have

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

WELCOME TO THE PILE DRIVING INSPECTOR COURSE

Transcription:

Micropiles for Roadway Support, Bridge Abutments and Metal Signal Poles on US-158 from US-17B to East of Pasquotank River, in Elizabeth City, NC Schnabel Foundation Company Presenter: Stephen Dimino, P.E.

Owner -NCDOT Team Prime Contractor-Archer Western Construction Micropile Subcontractor-Schnabel Foundation Company

Project Overview Install micropiles to support the roadway, metal signal poles (MSP), bridge abutment and pump station The roadway and approach micropiles were installed through the concrete roadway deck Bridge micropiles were installed in the river MSP micropiles and the pump station piles were installed in foundation excavation.

Project Overview Install 258 Roadway Micropiles Install 16 Bridge Approach Micropiles Install 10 ea. Bridge Abutment Micropiles Install 4 Micropiles at 8 separate MSP foundations for a total of 32 piles. Install 8 Pump Station Support Micropiles Install 4 Generator Slab Support Micropiles Install 4 Electrical Building Micropiles

Roadway/Approach Piles Install 258 Roadway Micropiles 8-5/8 x 60 ft. casing with casing tip elevation of -52 ft. Bond length of 28 ft. Full length of corrosion protected Center bar Three sacrificial demonstration piles Fifteen proof tests on production piles

Bridge Piles Install 10 Bridge Abutment Micropiles 10-3/4 x 60 ft. casing with casing tip elevation of -58 ft. Bond length of 40 ft. Full length of corrosion protected center bar tied into pile cap One sacrificial demonstration piles Two proof tests on production piles

MSP Piles Install 32 Bridge Abutment Micropiles (4 each at 8 separate pile caps) 10-3/4 casing with casing tip elevation varies from -40 ft. to -58 ft. Bond length of 22 ft. Full length of corrosion protected center bar tied into pile cap One proof tests at each of the 8 pile caps

Pump Station Piles Install 16 Pump Station Micropiles 7 casing with casing tip elevation of -40 ft. Bond length of 20 ft. Full length of corrosion protected center bar tied into pile cap One proof tests at each of the 8 pile caps One demonstration test for the 7 piles

Design The permanent micropile design is in accordance with FHWA Implementation Manual for Micropile Design and Construction Guidelines (FHWA-SA-97-070), dated June 2000 using the Load Factor Design (LFD) Method; AASHTO LRFD Bridge Design Specifications 2010; and The Recommendations of Prestressed Rock and Soil Anchors, PTI, 2004. In this design the micropiles are Type A micropiles

Design Design loads and test loads given in Contract Documents Roadway/Approach DL=25T (comp) TL=36T Bridge DL=50T (comp) TL=72T MSP DL=24T (comp) ;14T (tension) Specified casing diameter and thickness based on method of installation

Design The overburden soils were very soft/weak. The grout to ground bond strengths are per Table 6.3 in The Recommendations of Prestressed Rock and Soil Anchors, PTI, 2004, and AASHTO Table C10.9.3.5.2-1. The bond strengths of the soils of the pile above the minimum tip elevation shown the plans were neglected. Roadway and Approach Piles 3.8klf Bridge Piles 4.5klf MSP Piles 4.5klf

Issues

Design Grout mix design Use either of the two grouts: A neat mix of Portland Cement (Type I/II) and potable water at an approximate mix ratio of 5 to 6 gallons of water per cubic foot of grout. Minimum compressive strength at 28 days, fc=3,500 psi. An approved ready mix grout with a minimum compressive strength at 28 days, fc=3,500 psi

Testing Tested per ASTM D3689 8.1.2 Quick Test Roadway Piles-The contract called for 3 Demonstration Tests and 15 Proof Tests. Roadway micropiles test load is 36T (72 kips) Bridge Piles-The contract called for 1 Demonstration Test and 2 Proof Tests. Bridge micropiles test load is 72T (144 kips) MSP Piles-The contract called for 1 Proof Test at each pile cap. MSP micropiles test load is 24T (48 kips)

Testing

Testing

Issues We had to stabilize the hole and the environmental requirements affected our planning Original method was not productive Constraints of working on road deck limited our work process Tight schedule due to MOT Changing methods is time consuming Working near the water

Overall view of jobsite

Construction Method 1 100 lf x 11 dia. Continuous Flight Auger Drill down to depth and pump grout through auger Push casing and center bar down through plastic grout Main issue was that the auger walked and we could not put the casing in to depth Cleaning the fat clay off the auger took a long time.

Method 1 CFA installation

Method 1 CFA Installation

Method 1 CFA Installation

Construction Method 2 Drill down to pile tip elevation using the casing as the drill string Pump grout through the casing as the casing is pulled up to so that the bottom of casing matches pile tip elevation. The casing and grout stabilize the hole. Push bar through plastic grout. Hooking the casing up at the rotary head took a long time.

Method 2 Drilling with Casing

Method 2 Drilling with Casing

Method 2 Drilling with Casing

Construction Method 3 Vibrate casing down to casing tip elevation Drill through casing and down to pile tip elevation. Pump grout through drill string as we retracted the inner rod. Very successful in the soil type. We were able to use smaller equipment.

Drilling through the Vibrated Casing

Drilling through Vibrated Casing

Drilling through Vibrated Casing

Vibrated Piles at MSP Pile Cap

Completed MSP Micropiles