The RTD FasTracks Plan

Similar documents
Why a Public-Private Partnership might be used to deliver passenger rail

Innovative Improvement Driven Foundation for Denver s Transit Expansion Program

PENINSULA CORRIDOR JOINT POWERS BOARD STAFF REPORT. Executive Officer, Caltrain Modernization Program

North Metro Commuter Rail Line Conception to Implementation

Timothy Stokes, PE, MBA Parsons, Principal Project Manager Denver, Colorado

A Systems Engineering Approach to Enhance and Support the Acceptance Process for RTD FasTracks Projects

$500M Public Transportation Infrastructure Project with 5 Public/Private Partners, and 9 financing Sources

Transportation and NEPA The Role of Private Equity and PPPs in Public Transit 1

DENVER UNION STATION $500M TRANSPORTATION INFRASTRUCTURE FINANCING

IT TAKES A VILLAGE AND MULTIPLE SOURCES OF REVENUE: A CASE STUDY OF THE DENVER UNION STATION REDEVELOPMENT PROJECT

Using P3s to Deliver Multi-Modal Airport Transit Solutions

Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division

Mysore L. Nagaraja, P.E. Chairman

CM/GC Contracting Lessons Learned from Portland and San Francisco

Developing a Schedule for the R Line: RTD s New Suburban Light Rail Lacy Bell

I-15 Corridor Reconstruction Salt Lake City, Utah. DFW Connector Dallas/Fort Worth, Texas. SH99/Grand Parkway F & G Houston, Texas

Transportation and Utilities

AMERICAN PUBLIC TRANSPORTATION ASSOCIATION 2016 RAIL CONFERENCE WELCOME TO PHOENIX

Institute of Transporation Engineers (ITE) May 10, 2013

ERRATA to: Cost Savings through Innovation Eagle P3 Project, Regional Transportation District, Denver, CO by Rik Lor, P.E. and Scott Henning, P.E.

I-225 Rail Line Board Update. Chuck Culig I-225 Rail Line Project Manager Aug. 6, 2013

PROJECT: WESTSIDE SUBWAY EXTENSION TRANSIT CORRIDOR PROJECT

Realizing Transit: Clearing the funding hurdle. Presentation to the 8 th International Hydrail Conference June 11 th & 12 th Ryerson University,

BACKGROUND. The FasTracks Plan includes three core goals:

DART Capital Program Symposium WELCOME

Status Report on the 3 Rail Priorities

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1)

Metro Blue Line Improvements & Project Update

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Private Partnerships: Lessons from Florida

The Future of Transit in Colorado

Commonwealth Transportation Board I-66 Corridor Briefing Outside the Beltway Route 15 to I-495

MORE MARTA ATLANTA SUMMARY OF PUBLIC ENGAGEMENT Contents CONTENTS TABLE OF EXHIBITS APPENDIX 2 9/4/18

Transit P3s: Lessons Learned and Resources for Public Sector Sponsors. Jodie Misiak

Category: Contractor: Project Name:

State of the District. December 12, 2017

Regional Transit Framework Study

Table of Contents. EXECUTIVE SUMMARY... 1 INTRODUCTION Project Definition: Scope and Costs... 11

Construction Manager /General Contractor

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

1560 Broadway, Suite 700, Denver, CO phone

Philippine PPP Program SDG-6 (Water & Sanitation) and SDG-11 (Sustainable Cities)

A knowledge-sharing report to help RTD find better ways to serve the public. Best Practices

How Public Private Partnerships Can Create Real Value in Water Projects

For immediate questions, please contact Dr. Florine P. Raitano, Coalition Director and Project Manager for this project.

Gateway Corridor Transitway

DTX Project Delivery Methodology and Options. January 9, 2014

Who is DRCOG?

Orange County Transit

Evaluating the Potential Economic Efficiency of Project Delivery Options

A powerful partner. Transportation / Public-Private Partnerships

EXECUTIVE SUMMARY REGIONAL TRANSPORTATION PLAN 2050

Single-Entity Progressive Lump Sum Contracting Approach to Project Delivery

Peninsula Corridor Electrification Project DBE Project Goal

10. PROJECT DEVELOPMENT, LEADERSHIP, AND OVERSIGHT GUIDELINES

2040 Transportation Policy Plan Conversion to Performance Based Planning Basis. 25 th Annual CTS Transportation Research Conference May 21, 2014

View from Cabot Yard, South Boston. ACEC State Markets Conference April 2019

Regional Transit System Plan

Southeast Rail Extension Pre-Proposal Briefing. March 25, 2015

Quality of Life Study High Level Measures

MEMORANDUM. Executive Summary. Recommendation. Background

Securing & Implementing Legislative Authority for Alternative Delivery of Projects at Sound Transit

Date: January 28, TriMet Contract Review Board. Daniel W. Blocher, P.E.

2007 Annual Report to DRCOG on FasTracks. December 2007

2018 STATE LEGISLATIVE PROGRAM

Executive Summary i Regional Transportation Plan March 2018

North Metro Rail Line The Making of a Commuter Rail Corridor. Authors. Number of Words 7258

TRANSPORTATION OPTIONS PROGRAM PLAN TAP MEETING #1 1/23/17

2010 Minnesota Comprehensive Statewide Freight and Passenger Rail Plan. Minnesota Department of Transportation

Southwest Corridor Plan Project Update. June 11, 2013

UNITED KINGDOM Intercity Express Programme SUMMARY

2. Establish an Office of Capital Program and Performance Measurement. 3. Retain planners and capital program planning in modal offices

Dumbarton Transportation Corridor Study

I-880 Integrated Corridor Management: Building on Existing Planning Efforts

Port of Whitman County Request for Proposal for Washington State Grain Train Strategic Plan

ISSUES & RISKS Potential timing and coordination with a future system planning process Coordination with jurisdictions and partner transit agencies

Colorado Statewide Intercity and Regional Bus Network Plan Scope of Work October 5th, 2006

Developing New Revenue Streams For Transit

Hazardous Materials Technical Memorandum

Statewide Transit Plan

ITE MICHIGAN TECHNICAL SESSION LIVING THE P3 DESIGN DREAM DESIGN BUILD ON STEROIDS PRESENTER: TOM WESTON, PE

Richard Clarke Executive Director Program Management. Capital Program Management

FOCUS40 MassDOT Board Presentation March 13, 2017

APPENDIX A - PLANS AND POLICY REVIEW FEBRUARY 2017

INTEGRATED MOBILITY PLAN

REGIONAL EXPRESS RAIL (RER)

Enhancing the Interconnectivity of a public transport system

Fiscal Management and Control Board Briefing APRIL 30, 2018

I-66 Corridor Improvements Outside the Capital Beltway in Northern Virginia, USA

History and Background

Progressive Design Build

CORE Competencies. Procurement strategy leads to bigger, better, faster delivery of Utah s I-15

COUNCIL COMMUNICATION

ABC Ramps Research Overview

Caltrain Rapid Rail Plan

Chicago BRT Initiative Branding Consultant Communications Consultant REQUEST FOR PROPOSAL

Amman Transportation Strategy

Caltrain Business Plan Draft Business Strategy and Scope. Board of Directors December 7, 2017 Agenda Item 9

Denver Regional Council of Governments Strategic Plan

What is the Transportation Policy Plan (TPP)?

Transcription:

PROJECT DELIVERY METHODS Prepared for: PCJPB August 2013 Prepared by: Richard F. Clarke (Assistant General Manager, Capital Programs) The RTD FasTracks Plan 122 miles of new light rail and commuter rail 18 miles of Bus Rapid Transit (BRT) service Voters approved sales tax increase in 2004 Multi-modal hub at Denver Union Station FasTracks is a program of projects 2 1

FasTracks Status 64 miles of new rail line currently complete or under contract ($5 billion) Environmental processes complete Light rail maintenance facility, light rail vehicle purchases, platform extensions, power upgrades and other enhancements to the existing system also complete Moving forward with committed projects and maximizing funding opportunities 3 Challenge Effectively managing approximately $5 billion of simultaneous construction within budget and schedule constraints. 2

RTD PROJECT HISTORY Corridor Project Delivery Method Cost (millions) Opening Date Central Corridor 5.3 Mile Design Bid Build $117 million September 1994 Southwest Corridor 8.6 Mile Design Bid Build $180 million July 2000 Central Platte Valley 1.8 Mile Design Bid Build $48 million April 2002 Southeast Corridor T REX 19.2 Mile Design Build; Multi Modal Project with CDOT $1.7 billion (LRT $900 million) November 2006 5 FasTracks Summary Status Corridor Project West Rail Denver Union Station US 36 Phase I US36 Phase II Eagle P3 Description/Delivery Method 12.1 Mile Light Rail/ Construction Manager General Contractor Multimodal Terminal/ Design Build 11 Mile Bus Rapid/ Transit/Managed Lane with CDOT Design Build 5 Mile Bus Rapid Transit/Managed Lane with CDOT/ Design Build/PPP 36 Mile Electrified Commuter Rail/ Design Build Operate Maintain/PPP Cost (millions) Opening Date Delivery Status $707 April 2013 Opened April 26, 2013 on budget, ahead of schedule $500 May 2014 Under construction 80% Complete $312 January 2015 Under Construction 19% Complete $109 End of 2015 Awarded Final Close Summer 2013 $2,100 Through 2016 Under Construction 37% Complete I 225 10.5 Mile Light Rail/ Design Build North Metro 18.5 mile Electrified Commuter Rail (5.8 Miles to 72 nd Avenue)/Received unsolicited design build proposal $687 Spring 2016 In final design; Construction started $180 (funded) 2017 Segment One to 72 nd Avenue in Final Design on hold pending unsolicited proposal and RFP (July 2013) Southeast Extension 2.3 Miles/ TBD $205 TBD In New Starts (entry to PE) 6 3

Design-Bid-Build Works well when owner wants control over design (e.g. Elati Maintenance Facility), risks are unknown until more advanced design can be done or when challenging stakeholder issues exist Takes more time in the schedule Limits innovation from the private sector More change orders (owner has risk for design) and more contentious relationships between owner and contractor Construction Manager General Contractor Contractor is bought in early when design is proceeding Contractor provides constructability and value engineering input during design A final guaranteed maximum price (GMP) is negotiated Owner has control and risk for design although contractor involvement during design can limit that risk Requires strong cooperation of design firm, owner and contractor Negotiated GMP limits competitive pricing and will impact schedule if negotiations are not successful 4

Design-Build Faster schedule from overlap in activities Best value selection fosters collaboration and innovation Effective partnering is key Shifts certain risks (i.e. design) to the Design-Build contractor Fewer change orders, but they are larger on average Requires fewer resources for the owner oversight Requires quick decision making Design-Build (continued) Well matched with a systems (electrification) project where manufacturers/suppliers do much of the design Best value selection fosters collaboration and innovation Effective partnering is key Shifts certain risks (i.e. design) to the Design-Build contractor Still requires effective oversight by the owner Variations include design-build-maintain (DBM) and designbuild-operate-maintain (DBOM) 5

Public Private Partnership Adds financing from the concessionaire (DBFOM) Provides long-term integrated delivery Availability payments are tied to operational performance criteria so provides great incentive to consider life cycle costs and operability Good value for the money Procurement period can be longer, more complex and expensive Private financing more expensive than public financing Lessons Learned at RTD Match the project and its risks with the delivery method In many cases there is not necessarily a right or wrong delivery method. All types of delivery methods have been successful. If they are not, there is usually some other fundamental reasons One size does not fit all projects Make sure agency management and project staff is vested in the delivery method Bring the right expertise in to manage that delivery method 6

Lessons Learned at RTD (continued) Best value selections have resulted in strong proposals and teams In choosing a delivery method consider risk, schedule, cost, innovation of private sector, number of contracts/contractors, stakeholder involvement Reflect the agency goals in the evaluation criteria (i.e. price, public outreach, DBE programs, safety, quality) Keep the Board and stakeholders informed during the procurement process while respecting the need for confidentiality RTD Commitment RTD and Caltrain are the two agencies currently implementing a 25kV electrified commuter rail. We are both in this together and welcome our collaboration and mutual support. 7

Questions www.rtd-fastracks.com 15 8