HANDOUT 3-1 REQUIREMENTS RECORD PROJECT TITLE: PROJECT MANAGER: REQUIREMENT: ASSUMPTIONS: CONSTRAINTS: REQUIRED RESOURCES:

Similar documents
PROJECT MANAGEMENT. By Pompeyo Rios

Successful Project Management. Third Edition

Managing Multiple Projects

Sample Outline of ICD-10 Three-Day Provider Curriculum

Ninth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book:

Abbreviations Foreword Author s Note. PART I Key Principles, Processes and Methodologies 1. 1 Introduction to Project Management Techniques 3

Document Review Part 1

Application Of A Project Planning Methodology In Construction Work

Successful Project Management. Second Edition

Methods of IT Project Management

Project Execution Plan For

WESDOME GOLD MINES LTD. MANDATE OF THE BOARD OF DIRECTORS

BANNER 9 IMPLEMENTATION PROJECT

Software Project & Risk Management Courses Offered by The Westfall Team

Through Collaboration with the Business Analyst & Project Manager. Hosted by Michael Kennedy Senior Consultant, DevelopMentor

LECTURE 8: Planning & Control Functions & Tools (Part II) Project Management BACA

THE STANDARD FOR PROGRAM MANAGEMENT

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

Project Origination: Item Description (Origination) Comments (or reasons for NOT completing)


Agenda. PMBOK Guide Third Edition. PMI Standards Background. PMI Life Cycle Plan for Standards. Presented by Kevin Chui, PMP. How Did We Get Here?

PMP Practice Questions

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)

Senior Design Documentation Library

Successful Project Management. Overview Houston Community College Fall, 2017

A Web-based Framework of Project Performance and Control System

Project Management Session 6.2. Project Initiation Phase Integration Management

Appendix. Process Inputs and Outputs

Exam 2012, Lecture Project Management

Connoisseur Solutions Project Scope Management

AURINIA PHARMACEUTICALS INC.

BOARD OF DIRECTORS CHARTER

Global Program Management

OR 680 / SYST 798 Spring 2012 Risk Identification Tool (RIT) for Aerospace Products March 29, 2012 Interim Progress Review

Project Management Framework

Exam Questions PMI-001

Project Management for Engineering and Technology

Parametric Project Monitoring and Control: Performance-Based Progress Assessment and Prediction

Principles of Planning for Building and. by Eastwood Harris Pty Ltd. Introduction Emergency Evacuation. Course Outline.

3.1 Edition APMP Syllabus APMP

Project Management Integration

Project Management Knowledge Areas SECTION III

Project Management Training Brochure

The ESRM Life Cycle In Action Simulation Exercise September 23, 2018

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

Project+ Examination Blueprint Version June 1, 2003

COAA EPCM CONTRACT PHILOSOPHY. COAA EPCM Contract Committee

PMI-001 Questions & Answers

ActualTests.CAPM.660Questions. Certified Associate in Project Management (CAPM)

Corporate Governance Guidelines

Project Management based on the Project Management book of knowledge

Managing Information System Projects. Railway Staff College, Vadodara November 2011

Certificate IV in Project Management Student Assessment Guide

PMP. Processexam.com. PMI Project Management Professional. Exam Summary Syllabus Questions

The Job of the Project Manager 1, 2

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide

Managing the Information Systems Project

<Project Name> Charter

SKYWEST, INC. CORPORATE GOVERNANCE GUIDELINES

James Cook University. Internal Audit Protocol

Unit 42: Project Management for Business

PMP Exam Prep Coaching Program

Project Charter. A. General Information

Unit 42: Project Management for Business

CMMI Project Management Refresher Training


International Diploma in Project Management. (Level 4) Course Structure & Contents

Course ID October 2015 COURSE OUTLINE. Business Administration 210 Foundations of Project Management

PMP Exam Preparation Workshop Project Communications Management

MSP 50 CONTROL OF CONTRACTORS

Index. NOTE: Boldface numbers indicate illustrations or code listing; t indicates a table.

COMMUNICATION MANAGEMENT PLAN

Project Management CSC 310 Spring 2018 Howard Rosenthal

Management of Software Development Projects

BrightPath Early Leaning Inc. Audit Committee Charter

Project Manager s Roadmap We re all smarter together

Audit Committee Charter

PMP Exam Preparation Workshop. Chapter # 5 Project Scope Management

KillTest *KIJGT 3WCNKV[ $GVVGT 5GTXKEG Q&A NZZV ]]] QORRZKYZ IUS =K ULLKX LXKK [VJGZK YKX\OIK LUX UTK _KGX

The Corporation of the City of London Building Permit Review Internal Audit Report

Project Management Body of Knowledge Chapter 3 Project Processes

Board of Directors (Board) Charter and Terms of Reference

Establishing a Program Management Office

The Essentials of. Project Management. Fourth Edition DENNIS LOCK GOWER

Table of Contents. Introduction xxv. Assessment Test xxxvi. Chapter 1 What Is a Project? 1. Is It a Project? 2. Projects versus Operations 3

Project Charter Date 4/16/08

THE AUSTRALIAN WINE CONSUMERS CO-OPERATIVE SOCIETY LIMITED BOARD CHARTER. Board Charter

SNAP-ON INCORPORATED STANDARD ON FACILITY SPECIFIC REQUIREMENTS

Chapter 7: Quality Project Review

Project Cost Management

Internal Audit & the Audit Committee

Scope of Services Traffic Signal Retiming Contract FM NO Florida Department of Transportation District Four

Design, Development and Implementation (DDI) Project Management Plan (PMP)

King III Chapter 2 Board Charter. September 2009

INFORMATION TECHNOLOGY PROJECT MANAGEMENT. Fourth Edition. International Student Version. Jack T. Marchewka WILEY. John Wiley & Sons, Inc.

<PROJECT NAME> PROJECT MANAGEMENT PLAN

Index. Symbols. 80/20 Rule, /15 Rule, 306

Fundamentals of Project Management

CORROSION MANAGEMENT MATURITY MODEL

Transcription:

Handouts

HANDOUT 3-1 REQUIREMENTS RECORD PROJECT TITLE: DATE: PROJECT MANAGER: REQUIREMENT: ASSUMPTIONS: CONSTRAINTS: REQUIRED RESOURCES: FUNCTIONAL GROUPS PARTICIPATING:

SAMPLE 3-1 REQUIREMENTS RECORD PROJECT TITLE: The Jacksonville Company Management Information System PROJECT MANAGER: Michael James DATE: May 14, 2002 REQUIREMENT: A Management Information System (MIS) to support a corporate office consisting of fifty people. The MIS will produce forms, reports, data, and analyses specified by the Information Systems Department's needs analysis (MIS Needs Analysis, dated January 30, 2002). The MIS will be operational no later than April 1, 2003. ASSUMPTIONS: The following assumptions have been made in determining the resource requirements for this project: Jack Smith will be assigned as the technical lead for the project Jean Jordan and Bill Williams will be available 50% of their time to support the project manager with clerical and financial assistance The IS department will complete their technology assessment by June 1, 2002 This project has priority 1 status CONSTRAINTS: Given the number of competing projects at Jacksonville, the schedule can be met only with complete functional area support of resources and materials A budget of $200,000 may be insufficient to support IS's technology recommendations REQUIRED RESOURCES: Technical lead Two full-time programmers One part-time programmer Two design engineers One systems engineer FUNCTIONAL GROUPS PARTICIPATING: Engineering Information Systems Software Development

HANDOUT 3-2

HANDOUT 3-3 Stakeholder Analysis Stakeholder Name + 0 Reason for Position Strengths & Weaknesses Strategy

HANDOUT 3-4 Project Charter Outline I. Purpose (Scope statement) II. III. IV. Project Establishment (Business reason for the project) Project Manager Designation and Authority Project Manager's Responsibility A. Support organization's responsibilities B. Project organization and structure C. Project team composition V. Project Initiation A. Formal project plan B. Approved budgets C. Approved plan VI. VII. VIII. IX. Project Personnel (By name if possible, but at least by skill area) A. Assignments to projects B. Reporting structure C. Performance appraisals Communication Plan Definitions Appendixes

SAMPLE 3-4 Sample Project Charter Project Title: Project Management Control System (PMCS) Date: April 7, 2000 Scope and Objectives: The Jacksonville Information Systems Company is undergoing rapid change and growth resulting in an urgent need for a more efficient use of capital funds and for managing our many projects. To this end, we are implementing a new project management control system that will satisfy both these needs and will enhance our project teams' ability to better focus on our customers' requirements. General Objectives: 1. Enable better communication among project, group, and corporate management with regard to progress of major projects. 2. Enable senior management to more closely monitor progress of major projects. 3. Provide project personnel the capability to manage and control their projects. Specific Objectives: 1. Reporting and Control System (a) For communication of project activity within and between groups and senior management (b) Initially for high-cost projects, then for "critical," then for all projects 2. Computer Support Systems (a) Survey with recommendations to determine the amount and cost of computer support 3. Procedures Manuals (a) Document procedures and policies (b) Preliminary manual available by end of year for operator and user training 4. Project Management Training Course (a) Provide basic project planning and control skills to personnel directly involved in project management (b) Follow-on courses to provide software, financial, and contracting skills needed by project managers Defining Conditions, Constraints, and Assumptions: The PMCS must be operational on the last day of this year. The first phase of this project is a technical survey and a feasibility study with a go/no-go decision point at the conclusion of the study. Implementation of the PMCS will commence on July 1 if the recommendation is to proceed. Project Organization: The key members of the project organization are: Sponsor: Dr. Jack Malloney, VP of IS Project Manager: Mr. James Martin User Representatives: Ms. Jean Matthews and Mr. John Collier Technical Lead: Mr. Sean O'Reilly

SAMPLE 3-4 Team Members: To be nominated by functional managers based upon the project manager's skill set requirements and his recommendations. Functional managers will provide team members for the project duration and they will be 100% dedicated to the project. Project Manager Authority and Responsibilities 1. Staffing the project manager will determine the skill requirements for the PMCS project and provide them, along with specific team member names, by June 1 to the appropriate functional managers. The project manager is authorized one clerical person and one cost analysis to assist him. Because of other project priorities, the project team is limited to no more than 10 technical members without specific authority from the President. 2. Budget the initial estimate of the project cost is $500,000. This budget cannot be exceeded without authority from the President and the Chief Financial Officer. 3. Communications status reports will be provided to the President, CFO, and the Sponsor bi-monthly. 4. Planning/Tracking This project will be tracked using our in-house project management software. An earned value analysis will be provided in every other status report beginning with the second report. 5. Change Control the project manager is authorized to make project changes provided they do not exceed $5,000 in additional cost and do not impact the schedule. Otherwise, any changes will be made through the Configuration Change Control Board. 6. Document/System Access the project manager is authorized access to any company document or system in the pursuit of this project completion. 7. The project manager will provide a project plan to the Sponsor no later than May 12. The project plan will include a description of the work, schedules, budget, spending plan, resource utilization charts, risk management plans, and a quality plan. Support Requirements from Other Organizations: The PMCS project has the top priority in The Jacksonville Information Systems Company. Functional groups will provide all support possible to the project manager. Where conflicts in personnel assignments occur, the President will resolve them. Approvals: VP Project Management VP Information Systems Chief Financial Officer VP Human Resources President

HANDOUT 3-5 Kickoff Meeting Agenda Format 1. Introductions 2. Vision 3. Scope and objectives 4. Risks, challenges, and project constraints 5. Project approach 6. Team members and project organization chart 7. Roles and responsibilities 8. Timeline 9. Major milestones 10. Process, standards, methods, and tools 11. Quality plan 12. Project management and schedule planning standards and guidelines 13. Centralized documentation storage facility 14. Time collection and project status requirements 15. Training schedule 16. Lessons learned from previous post-project reviews 17. Success factors 18. Project expectations and next steps 19. Unresolved issues, responsibility assignments, and target dates 20. Adjournment

HANDOUT 3-6

HANDOUT 4-1 TASK RESPONSIBILITY MATRIX PROJECT: TASK ID(WBS #) TASK DESCRIPTION TEAM MEMBER RESPONSIBLE/TASK DURATION Legend: P = Primary S = Supporting Note: Write the name of the person responsible for the task and indicate whether they have a primary or supporting role.

HANDOUT 4-2 PROJECT MANAGEMENT PLAN FORMAT I. Executive Summary II. Project Requirements and Objectives III. General Methodology or Technical Approach IV. Contractual Requirements V. Schedules VI. Resource Requirements A. Equipment B. Materials C. People VII. Potential Risks VIII. Performance Evaluations Appendices Project Charter Supporting plans Drawings Specifications

HANDOUT 5-1

HANDOUT 5-2

HANDOUT 5-3 A Risk-Management Plan Format I. Project summary and description 1.1 Project summary 1.1.1 Project and organizational objectives 1.1.2 Operational and technical characteristics 1.1.3 Key functions 1.2 Project description 1.2.1 Requirements 1.2.2 Schedule 1.2.3 Special contractual requirements II. Approach to Risk Management 2.1 Definitions 2.1.1 Technical risk 2.1.2 Programmatic risk 2.1.3 Supportability risk 2.1.4 Cost risk 2.1.5 Schedule risk 2.2 Risk assessment methods overview 2.2.1 Techniques applied 2.2.2 Implementation of assessment results III. Application 3.1 Risk Assessment 3.1.1 Risk identification 3.1.2 Risk quantification 3.1.3 Risk prioritization 3.2 Risk response development 3.3 Risk response control 3.3.1 Control evaluation 3.3.2 Risk documentation IV. Other relevant plans V. Conclusions and Recommendations VI. Approvals

HANDOUT 5-4

HANDOUT 5-5

HANDOUT 5-6 Exercise 5-2 You are working on a project that was estimated to be completed on May 5 for a cost of $150,000. Today is May 9 and the project is 85% complete. You have spent $145,000. Answer the following questions. 1. What is the BAC for this project? 2. What are the BCWS, BCWP, and ACWP for the project? 3. What is the CV? 4. What is the SV? 5. What are the CPI and the SPI? 6. What is the new EAC? 7. What is the ETC?

HANDOUT 6-1

HANDOUT 6-2 Project Audit Format The project manager and team must perform an audit of the project to ensure that all the requirements are met and that the financial records are complete. A typical final audit format report includes: I. Executive summary II. Introduction III. Project Review A. Project objectives B. Method or approach IV. Effectiveness of Planning V. Effectiveness of Project Management VI. Effectiveness of Technical Solutions VII. Project Deliverables A. Description B. Assessment against requirements VIII. Quality A. Standards used B. Measurement IX. C. Assessment against requirements Schedule A. Delays 1. Reasons 2. Recovery actions B. Assessment against plan X. Finances A. Problems 1. Reasons 2. Recovery actions B. Assessment against plan XI. XII. XIII. XIV. Resource Utilization A. Effectiveness B. Problems 1. Reasons 2. Recovery actions Lessons Learned Individual Team-Member Assessment and Recommendations (submit as separate confidential report) Recommendations

HANDOUT 6-3 Project Close-Out Checklist Prepare a close-out plan Verify scope Contractual obligations Administrative obligations WBS (tasks and deliverables) Obtain customer acceptance of deliverables Document and archive files and records Document lessons learned Reassign resources Notify all stakeholders of project completion Celebrate success

HANDOUT 6-4