Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Similar documents
USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Trenchless Technology

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Experts in tunneling with Tunnel Boring Machines

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

Pipe Jacking. Japan Sewage Works Association

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

Trenchless Pipeline Crossings

Pipejacking Tunnel Boring Machines TBMs. Michael Frenke, LOVAT Inc.

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

2013 ASCE Agenda. Microtunneling in Difficult Ground Craig Camp. Microtunneling Characteristics (NASTT) Akkerman MTBM Introduced 1995

Agenda for Today s Workshop

An introduction to. pipe jacking

SECTION TRENCHLESS INSTALLATION

Dahlia Ponds Tunnel Project. Presented By: Nathan Soule, PE, PG Brierley Associates & Brenden Tippets, Project Executive, BTrenchless

Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries

Concrete Pipe Jacking

Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Pump Station Excavation

IPC Company & DPI Presentation. February 2017

1.0 Micro Tunnelling An overview

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

The City of Sergeant Bluff, IA Chooses Pilot Tube Microtunneling over Open Trench Construction

E-Power Pipe : A new trenchless method for underground cable installation

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill

Tel: Neil: Tony: Website:

Design Data 4. Jacking Concrete Pipe

SECTION HORIZONTAL DIRECTIONAL DRILLING

CC1602 Microtunneling

Diaphragm wall Construction

WARNING DO NOT BID ON THIS PROJECT

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

A number of abbreviations and technical terms have been used in this guideline:

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

Developed countries require a modern infrastructure Roads Railways Power Communications Water Wastewater

Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

Design Data 4M. Jacking Concrete Pipe

5/16/2018. New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters. Dr. Marc Peters, Herrenknecht AG. Highlights.

TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

Behavior of Surrounding Soil during Construction and Its Countermeasures Using Pipe Jacking Method in Deep Strata

PIPE JACKING & TUNNELING SYSTEMS DRIVEN FOR CUSTOMER SUCCESS

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL

Modeling Microtunnelling Construction Operations with WebCYCLONE

Draft. Not yet Approved TABLE OF CONTENTS. Page

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

Table of Contents TOC. Chapter 14 - Trenchless Construction. 14A General Information. 14B New Construction. 14C Rehabilitation

Venice Pumping Plant Dual Force Main Project Draft EIR

Section TUNNEL GROUT. A. Mix design requirements, testing, furnishing, and production of grout for:

4th International Engineering and Construction Conference - July 28, 2006

MICRO-TUNNELING LARGE DIAMETER SEWER MAY BE THE BEST OPTION FOR YOU

6 Preliminary Assessment of Construction Method and Constructability Issues

Misan University - College of Engineering Civil Engineering Department

Wastewater Capital Projects Management Standard Construction Specification

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

2 Technology of closed-face tunnelling machines

Pipe Ramming with HDD. Presentation Outline

H. Underground Transmission System Design

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

SPECIFICATION : BORING AND JACKING

DUCTILE IRON PILES ARE HIGHLY EFFECTIVE, FAST AND VERSATILE MODULAR DRIVEN MICROPILE SYSTEMS

ITEM 432 TUNNEL CONSTRUCTION

Expert in Tunneling Systems & Trenchless Technology (HDD, Microtunneling, Pipe Jacking, Thrustboring, Sheet Piling)

Reinforced Concrete Microtunnelling Pipe Designed for Project Conditions and MTBM Machines

Section WATER LINE IN TUNNELS

* The use of these areas can vary from car park space, where little waterproofing is required through to store rooms or plant rooms where a high

Pipe Jacking Association An introduction to pipe jacking and microtunnelling

Multiple Large Diameter Microtunnels with Limited Ground Cover

Concrete Pipe Jacking

PILOT TUBE & PIPE RAMMING METHOD INSTALL LARGE DIAMETER CASING UNDER RR

Tunnel. Immersed Tunnels

Design of pipeline installation D-GEO PIPELINE

Design of pipeline installation. D-Geo Pipeline

Construction Technology B (CON4313)

Final Report FHWA/IN/JTRP-2002/7

Presented By: Brenden Tippets, Project Executive

COMPETITIVENESS OF PIPE-JACKING TUNNEL LININGS

WATER LINE IN TUNNELS

2 Support of the cavity and settlement Support of the face Natural support Mechanical support...

Table of Contents. Section Trench Excavation and Backfill Section Includes Description of Work 1. 1.

Brief of evidence Tunnelling construction

Transcription:

Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods Moling/Piercing Pipe Ramming Auger Boring Pipe Jacking Microtunnelling Horizontal Directional Drilling 2 1

Pipe Jacking Oldest method of trenchless technology Applications Larger Diameter Pipe (1050 mm and up) Lengths can range from 3 to over 200m 3 Pipe Jacking Person entry Pipe diameters greater than 900 mm (36 ) Difficult to work in excavations of this size Practically limited to dia. greater than or equal to 1075 mm (42 ) Pipe installation process occurs from entrance and exit shaft Access way locations 4 2

Pipe Jacking Process 5 Pipe Jacking Material excavation completed by persons within the excavation Manual or machine face excavation Excavation takes place in front of an articulated shield Designed for worker safety Maintains open bore for pipe jacking or tunnel lining construction Shield guided with individually controlled hydraulic jacks 6 3

Pipe Jacking Excavation 7 Pipe Jacking Excavation 8 4

Pipe Jacking Types of Tunneling Hand mining Liner Plate Jack Reinforced Concrete Pipe Jack Steel Liner Cap and Leg (Wood Lined Tunnel) 9 Pipe Jacking Process Simple cyclic procedure Utilizes thrust from hydraulic jacks to force the pipe forward Pipe placed on cradle in the entry or jacking pit Thrust developed from thrust blocks Concrete, steel, soil excavation 10 5

Pipe Jacking Pit 11 Pipe Jacking Pit 12 6

Pipe Jacking Process Unstable soil Face excavated simultaneously with the jacking operation Minimize over excavation and the risk of face collapse After pipe jacked into place hydraulic rams are retracted and another pipe length is installed 13 Pipe Jacking Process Stable soil Face excavation may precede the jacking operation All spoils removed through the inside of the pipe to the jacking pit 14 7

Hand Excavation 15 Pipe Jacking Process 16 8

Pipe Jacking Pit Jacking pit size is function of: Length of pipe segments Pipe diameter Shield dimensions Thrust wall design Jack size Pressure rings Guide rail systems 17 Pipe Jacking Pit Pit should be shored Timber, steel piling or shaft liner plate, ground freezing For projects requiring large thrust Design of launch pit is critical Pit should be dry Floor preparation key for controlling alignment 18 9

Pipe Jacking Pit For a large job the placement of a concrete mud slab on the shaft floor is recommended For a smaller job the placement of a 300mm of crushed stone is recommended 19 Pipe Jacking Force Force on jacked pipe includes: Pipe dead weight Penetration resistance Soil-pipe friction Jacking force applied by two, four or six jacks 20 10

Other Forces Soil dead load Railway or highway live loads Jacking force must not exceed allowable pipe compressive strength Critical design location is the joints Low surface area - high stress Water tightness?? 21 Pipe Jacking Force Soil-pipe frictional force minimized by the application of lubricant to the outer pipe surface Can reduce jacking force by 50% Manual application or pumping of bentonite slurry around pipe Polymers Advantage only small amount required 22 11

Pipe Jacking Force To minimize pipe damage during jacking Packing material can be placed between the pipe joints 12 to 19mm plywood 12 to 25mm manila rope, jute, oakum Provides joint cushioning and flexibility 23 Pipe Jacking Force For long pipe installations Intermediate jacking stations may be used Set of hydraulic jacks placed between pipe segments 24 12

Intermediate Jacking Station (IJS) 25 Intermediate Jacking Station (IJS) 26 13

Intermediate Jacking Station (IJS) Total drive expected to exceed capacity of main jacks Capacity 100 to 1600 tons Diameter around 36 length 56 IJS assembled in four segments IJS must match pipe dia. for proper operation 27 Intermediate Pipe Jacking Three step pipe jacking process: 1. Intermediate jacks are used to jack the forward sections of pipe Thrust is provide by the pipe section behind the intermediate jacks 2. Intermediate jacks are retracted 3. Back section of pipe is jacked using the launching pit cradle 28 14

Jacking Pipe REINFORCED CONCRETE PIPE CLAY PIPE 29 Jacking Pipe Material Reinforced concrete (RCP) Polymer concrete Fibreglass (Hobas) Vitrified clay (VCP) Steel Ductile Iron Composites 30 15

31 PIPE JOINTS 32 16

Pipe Joints Must withstand high jacking forces Create water tight seals Flush joints to decrease jacking forces 33 PJ Applications Sewers, and drainage construction Gas and watermains Oil pipelines Industrial pipelines Telecommunication Pedestrian subways (access tunnels) 34 17

PJ Advantages Quick set-up When grade is critical Versatile in various ground conditions Cost efficient for large diameter pipe Small surface settlements Settlement controlled by face excavation 35 PJ Limitations Access to the face of the tunnel is needed at all times Speed of the mining operation is reliant on: Speed of labour (workers) Soil Matrix Rock Soft Soil Water Table Dewatering of tunnel path is usually required 36 18

New Installation Steering Methods Microtunnelling Horizontal directional drilling (HDD) 37 Microtunnelling New Installations Non-Steering Methods Steering Methods Moling Pipe Ramming Auger Boring Pipe Jacking Microtunnelling Horizontal Directional Drilling 38 19

Microtunnelling Remotely controlled and guided pipe jacking technique that provides support to the excavation face and does not require personnel entry into the tunnel Laser guided micro TBM used for soil excavation Drive from access way to access way (manhole locations) Mainly used for gravity sewers but can be used for large water mains 39 Microtunnelling Non-person entry Machine excavated (mini TBM) Remote controlled Similar to pipe jacking Pipe OD less than 1.0m 40 20

Tunnel Boring (TBM) World largest tunneling machine (14.2 m in diameter) Chunnel people 41 Microtunnelling 42 21

Microtunnelling 43 Microtunnelling Accuracy typically better than ± 25 mm per drive Laser controlled Variety of machines for different soil conditions Main applications: deep systems 44 22

Microtunnelling Accurate monitoring and adjusting of the alignment and grade as work proceeds Pipe can be installed on precise line and grade Generally used for pipe diameters less than 900mm (36 inches) Can be used for larger diameters 45 Launching and Exit Pits Use same design procedure as for pipe jacking Length of tunneling machine can control launch and exit pit size 46 23

Entrance and Exit Pit Shields Neopreme sheet stock held in steel ring 47 Entrance and Exit Pit Shields Prevents slurry and ground water from entering into shafts 48 24

Jacking System 49 History Originated in Japan and Germany in 1970 s Development government sponsored Need for pipe construction method with minimum surface disruption in over congested areas Komatsu introduced first Microtunnelling machine in 1975 - IRONMOLE ISEKI inc introduced there machine in 1976 Ability to counter balance earth pressure mechanically and hydraulically 50 25

History First Microtunnelling project in North America Fort Lauderdale Florida in 1984 615 feet of 72 inch pipe under I-95 Second project Bridgeport CT in 1986 3610 feet of 72 inch pipe 51 History As of October 1996 Total MT North America footage 547,100 feet Total number of projects = 254 52 26

MT Classification Methods Based on mode of operation Slurry method Auger method 53 Slurry Method Tunnel face is supported mechanically or by a pressurized slurry Spoils (cuttings) removed hydraulically in the form of a slurry Conveying fluid is used to counteract hydrostatic forces caused by ground water pressure and soil removal 54 27

Slurry Method LOVAT MTS 1000 55 Slurry Method 56 28

Slurry Method Soil cut mechanically Cutting head designs depends of soil or rock type Cuttings removed by hydraulic action Cuttings enter bore head through inlet openings and placed in suspension in the slurry chamber - water and bentonite 57 Slurry Method 58 29

Lubrication System Typical system components: Variable speed discharge pump Charge pump Intermediate pumps Flow meter Flow controller Pit by pass to permit diversion of flows Piping, flexible hoses and cabling 59 Slurry Separation Typical separation plant components: Vibrating screens Cyclones for small particle separation Clay ball separator Settlement tank 60 30

Slurry System Depth of ground water up to 30m can be managed Due to efficiency of shield small pipes can be used Full measurement and control of slurry flows 61 Auger Method Soil cutting at the face by a bore head and soil removal by means of a continuous flight of augers Augers run in a separate guiding pipe Better suited for cohesive soils 62 31

Auger Method 63 Auger Method LOVAT MTS 1000 64 32

Auger Method (Drill) Phase I a steerable pilot tube is jacked into the ground displacing the soil. 65 Steerable pilot tube 66 33

Phase I 67 Guidance System 68 34

Phase I 69 Auger Method (Drill) Phase II install a temporary steel casing 70 35

Standard Reaming Heads 71 Phase II 72 36

Standard Reaming Heads 73 Phase II 74 37

Full face with Ground water control 75 Phase II Casing with Augers 76 38

Phase II Casing Installation 77 Auger Method (Drill) Phase III the product pipe is installed 78 39

Auger Method (Drill) Phase III the product pipe is installed 79 Phase III 80 40

Auger Method (Drill) Steered pilot tube Combined Phase II & III (<150mm OD) Phase III (150 to 225mm) Shafts 2m dia Drive lengths 60m plus 81 MT Equipment Selection Variety of machine types Choice depends on ground condition Type of soil/rock Sand, gravel, clay, boulders, etc Ground water table Project success depends on have a proper soil investigation 82 41

MT Equipment 83 MT Advantages Grade and alignment accuracy (± 25 mm) Works well in a wide variety of soil conditions Some problems with boulders Works well below groundwater table No expensive dewatering systems required Up to approx 30m below GWT Increasing line depths does not significantly increase cost 84 42

MT Advantages Worker safety No ground surface settlement 85 MT Disadvantages High equipment capital cost Lateral connections? Difficulty with boulders Changing ground conditions Wood and debris 86 43

Microtunnelling Pipe Same as for pipe jacking 87 Other Recommendations Ensure sufficient room adjacent to the launch pit for: Pipe and machine storage Drill fluid mixing and recycling Spoil/cutting removal 88 44

Safety Precautions Safe pit design Overhead clearance for equipment Lower pipe and machine into the access launch pits Retrieve machine from exit pits Underground utility clearance 89 MT Risks Pipe diameter Risk decreases as diameter increases Length Risks increases as length increases 90 45

Cost 36 (900 mm) = $650 to 850/ft 48 (1200 mm) = $800 to 1200/ft Shafts 50 to 100k Depends on groundwater, depth & soil conditions Need over 1million dollar project to start to look at Microtunnelling 91 Microtunnelling in KL 92 46

Microtunnelling in KL Approx. 70km 1800mm OD sewer LOVAT MTS (Toronto Canada) 3 to 4 pipe sections 2950mm long per day Drive length 64 sections (~190m long) ~RM90,000,000 Project 93 Microtunnelling in KL EXIT SHAFT 94 47

Microtunnelling in KL MT machine currently stuck under the river Will sink rescue shaft to recover 95 48