Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues

Similar documents
October 20, 2017 CAPITAL PROJECT AND PLANNING UPDATE MURDAUGH HALL:

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

BOARD OF TRUSTEES OCTOBER 13, 2014

State College Area School District Memorial Field Phase 2 Update

Facilities Planning & Management

Oconomowoc Area School District Facility Construction Update July 27, 2018

PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

Boynton High School & Blackford Site

Facilities Modernization Program Funded by Measure B Project Report

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS

MONTHLY PROGRESS REPORT

GREENE COUNTY PUBLIC SCHOOLS ADDITIONS + RENOVATIONS

Merritt Island High School

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016

DISTRICT ADVISORY COMMITTEE MEETING MAY 2, 2018 HALF CENT SALES TAX PROGRESS REPORT

Facilities Maintenance & Operations Update. Presidents Executive Cabinet March 6, 2017

Oconomowoc Area School District Facility Construction Update June 29, 2018

Heritage High School

Semi-Annual Report. January 1, 2012 June 30, 2012

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting

PROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min)

Biddeford School Department

Portsmouth Middle School Additional Funding Request

PHYSICAL RESOURCES COMMITTEE MEETING PROJECT UPDATES FEBRUARY 3, 2016

Completed projects. Projects in progress. Program developments

DEL MAR COLLEGE Capital Improvement Program for Proposed Southside Campus. Prepared by;

Facilities and Planning Department Measure E Update March 2017

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

Project Information. Nominations of Artists. University of Houston

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

MONTHLY EXECUTIVE UPDATE MARCH 21, Thursday, March 21, 13

Cultural Facilities: Capital Needs Inventory and Priorities. Arts, Culture and Libraries Committee October 17, 2016

CEFPI Monthly Meeting

Frost Technical Center

Cupertino Union School District

Bronx Community College. Five-Year Capital Plan FY through FY

PROJECT UPDATES: 1.01 Cox Building Annex - Tony Salcido (3 min)

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION

James Lick High School

Ohlone Community College District

July 1 September 30, 2008

Program Update. Chino Health Science Parking Lot

School of Business Project # Overall Project Cost: $26,700, Architect: Urbahn. Scheduled Completion Date: 10/2014.

HIDDEN VALLEY ELEMENTARY SCHOOL

MIRACOSTA COMMUNITY COLLEGE DISTRICT

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING APRIL 17, 2018

Governing Board Capital Construction Program Annual Workshop September 10, 2013 Agenda

January 1, 2009 March 31, 2009

PRESENTATION JANUARY 24, 2017

ATHLETIC FACILITIES. High School Football Stadium 1 Dragon Drive, Swartz Creek, Michigan. Cage Fieldhouse 4110 Morrish Road, Swartz Creek, Michigan

Instructional Science Facility Phase I

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

La Porte Independent School District 2014 Bond Program Status Report August 11, 2015

APSU PROJECT REPORT 8/2/2018

Chino Valley Unified School District Monthly Construction Update

Capital Projects Update

EL CAMINO COLLEGE. Facilities Master Plan Report November 2008 PROJECTS IN DESIGN

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

MCKINLEY INSTITUTE OF TECHNOLOGY BRAILSFORD & DUNLAVEY RGM AND ASSOCIATES MEASURE T BOND

Capital Improvement Program Monthly Status Report

Contract No. EX CS001 - Construction of an Annex to Baptist Lui Ming Choi Secondary School at Yuen Wo Road, Shatin, New Territories.

Berryessa Union School District Measure L Bond Construction Program

Board Report. Bond Program Update:

Through. February Current Strong Schools Bond Capital Improvement Projects. Prepared by

Auburn University Construction Project Update March 2010

Facilities Services Newsletter Summer 2012

2007 Projects: MEDFORD SCHOOL DISTRICT 549C Bond Funded Construction Projects Updated: September 4, North Medford High School:

Perimeter Site Improvements

Independence Adult Center

FUTURE BOND PROGRAM PRELIMINARY PROJECT LIST

Santa Teresa High School

Through. November Current Strong Schools Bond Capital Improvement Projects. Prepared by

Auburn University Construction Project Update June 2010

Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018.

PLUMMER ELEMENTARY SCHOOL

June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

Birmingham Public Schools

CONSTRUCTION UPDATE. April AUM Projects. Client: Housing and Residence Life Construction Cost: $28 million Completion Date: July 2013

LOVEJOY Independent School District

2016 CDM Smith All Rights Reserved July 2016 SECTION MULTIPLE CONTRACT SUMMARY

Capital Project Recommendations Presented to the Board of Education 9/23/2014

4. Commissioning is ongoing and will be completed by October 30, CPT to coordinate training with LASC staff, TBD

Request for Proposal for GC/CM Consultant Services Ferndale School District. Secondary High School GC/CM Program. October 19, 2018

Grossmont-Cuyamaca Community College District Facilities Construction Update

Physical Plant. Detailed Assessment Report

RATIONALE AND REASONING

Cazenovia Central Schools Proposed Building Project Information Session December 17, 2013

Bruce Powers, Park Analyst / Project Manager Parks & Recreation Department

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

Southwest Health System Construction Newsletter October 7, 2017

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS

CESAR CHAVEZ LANGUAGE ACADEMY

Assistant Superintendent for Business Services. Executive Director of Facility Services Assistant Director of Facility Services

Assistant Superintendent for Business Services. Executive Director of Facility Services Assistant Director of Facility Services

Projects Currently in Planning, Design and Construction. April 12, 2017

Addendum to Agenda Item: SUPERINTENDENT S PROPOSED CAPITAL IMPROVEMEMT PLAN

Transcription:

February 24, 2017 CAPITAL PROJECT AND PLANNING UPDATE OLD NORTH Phase III and West Campus Entry: Three major components: Bid Set I and II (Interiors) Start Date: Aug. 2014 Completion: Feb. 2017 Size: 41,803 sq ft Total Project Budget: $8,450,000 CMSWillowbrook/Miles Associates Punch list items still in process all floors Work will continue the week of March 13. Temporary Door installation will remain on 3 rd and 4 th floors with 2-3 week delivery of real doors and may be delayed until Spring Break (pending delivery) Temporary clear glass in both permanent and temporary doors until delivery of frosted glass with 1-3 week delivery and installation and will be delayed until Spring Break (pending delivery) Bid Set III (Exterior West Campus Entry) Start Date: May 2016 Completion: Dec. 2016 Size: NA Total Project Budget: $1,600,000 Landscape elements will be completed between now and Spring Break by UCO Contractor should have resolved parking lot lighting issues Bid Set IV (Exterior and Interior Completion Elements) Start Date: July 2016 Completion: Feb. 2017 Size: NA Total Project Budget: $350,000 Donor recognition signage: o Donor Wall final parts and pieces to be installed Feb. 22-24 o Room Signs complete o Individual Donor signs complete o RUSO plaques (3 each) complete o Exterior site furniture delivery scheduled week of Feb. 27 Campus Entry Signage Alpha Building Corp/Miles Associates o Construction fencing, etc. will go up Monday, Feb. 27 o Long lead time materials on order by contractor 1

MURDAUGH HALL: Start Date: May 2016 Completion: May 2017 Size: 79,432 sq ft Total Project Budget: $9,000,000 Anderson House Construction/FSB Architects Another CO is in progress with AH, includes multiple deducts to be used to offset discovered new work Contractor is still behind schedule and will need to work harder to maintain the completion schedule of May 8, 2017 South Ramp plaza excavation work will be suspended until documents are revised to correct drainage and access issues SOFTBALL COMPLEX: Start Date: June 2016 Completion: March 2017 Size: 2,709 sq ft Total Project Budget: $2,490,000 Timberlake Construction/Sparks Reed Architects TCI has identified that facility will be open for March 15 home game with minor work still in progress on interiors TCI states that the current completion date remains March 13, 2017 Our understanding is that an opening will be scheduled for March 24 th (Athletics to confirm) Roofing has started on both buildings for completion March 10 Exterior brickwork started on Press box Mechanical and electrical work continues in the Team Building. Wall paint is complete in several areas of the building Ceramic Tile work in bathrooms is complete Concrete site paving (walkways) are complete pending installation of Backstop poles Installation of Backstop poles is week of Feb 27 and concrete site paving will be completed week of March 6 Athletics has requested a list of additional project support items for consideration of funding Meeting today with Athletics, AES, and OIT to finalize IT and A/V components TURF: Start Date: July 2016 Completion: February 2017 Size: NA Total Project Budget is $550,000 FieldTurf International/Athletics/AES The FieldTurf is in place and is basically complete pending final grooming end of Feb. or early March (To be scheduled with PP and Athletics). FieldTurf will return end of Feb. to do UCO punch list items, final grooming and training 2

DINING FACILITY: Start Date: Dec. 2017 Completion: Jun. 2019 Size: TBD Total Project Budget: $19,000,000 Lingo Construction (CMR)/ADG Architects Kick off planning meeting was held January 25 with Client/ADG/Lingo/AES AES met with Lingo on Feb. 14 to finalize contract discussions MOU to be issued for Pre-Construction services ADG/AES met Feb 21 to begin coordination meetings in preparation of next client meeting Client meeting with ADG/Lingo/AES TBS for March 6 or 7 PERFORMING ARTS CENTER: Start Date: TBD Completion: TBD Size: TBD Total Project Budget: TBD City of Edmond is set to issue an initial planning RFQ to help establish City requirements and needs Programming interviews with (4) selected firms are being scheduled for March 7 th. o Beck o Hornbeek Blatt o HSE o Huitt-Zollars (Elliott) CAMPUS MASTER PLAN: Start Date: Dec. 2015 Completion: Aug. 2017 Size: NA Total Project Budget: $250,000 Rees Associates Next planning meetings will begin March 2017 Interim report to be prepared for review by Admin late March/early April TRANSPORTATION AND PARKING: Start Date: Jan. 17 Completion: Late July 2017 and Late July 2018 Size: NA Total Project Budget TBE Dewberry Design/Wallace Engineering/AES AES will coordinate work for the following: Consultants have been hired to begin the planning and design process for modifications to the lots to include: LOT 10 Reconfiguration, LOT 14, 15 (Visitor and Event Parking) (Dewberry Design) LOT 13 (Acadia Inn site) with work to begin as soon as possible (Wallace Engineering) Fielding Building Site with work to begin upon completion of Mitchell in May 2017 (Wallace Engineering) 3

Ayers Closure initial planning will begin January 2017 (Dewberry Design will assist with planning efforts) Initial Planning for Parking Structure East of LOT 14 (Dewberry Design) Parking lot planning for Duplex site north of Lot 54, (University and Edwards)(Wallace Engineering) AES/Aux Enterprises/T&P/Dewberry met Dec. 9 to review design options, schedules and work scope for use in preparation of a fee proposal Dewberry PO issued AES/T&P/Aux Enterprises met with Dewberry/Wallace/ADG Feb 23 MITCHELL HALL BACKSTAGE: Start Date: Dec. 2015 Completion: April 2017 Size: 20,000 sq ft Total Project Budget: $5,750,000 Majority of the furniture has been ordered. (scheduled for installation April 24-28) Shiloh s updated construction schedule (received 02.21.17) reflects substantial completion at April 17th. Project schedule is dependent upon near term completion of buried heating/cooling lines west of building. Grand Opening is set for May 3 rd, 2017 A/V installation scheduled for after grand opening. SOUTH CENTRAL PLANT: Start Date: Jul. 2016 Completion: Fall 2017 Size: 6,500 sq ft Total Project Budget: $18,500,000 Three major components: (Work for all three is currently underway) $3M building to house the plant equipment - start date: 11/15/16 completion: 09/01/17 Construction of the building has commenced. Concrete work underway. Pre-cast concrete structure scheduled to go up mid-march. $12M chiller plant equipment and controls - start date: 2/24/17 completion: 11/30/17 $3.5M underground piping - start date: 07/01/16 completion: 07/30/17 Underground piping work, on the STEM building site, is complete. Main piping project at 30% completion Remaining installation on hold until May 4

STEM TEACHING & RESEARCH CENTER: Start Date: Jan. 2017 Completion: Fall 2018 Size: 55,000 sq ft Total Project Budget: $24,000,000 Site work is underway. Construction meetings are on-going. Project website with construction camera is available online at Facilities or College of Math & Science home pages. A&E Services requested that Elliott + put together a finishes presentation to share with the college. (March 2017) SPORTS PERFORMANCE CENTER: Phase 1 Start Date: Apr. 2017 Completion: Jun. 2018 Size: 42,000 sq ft Total Project Budget: $14,000,000 Construction is scheduled to begin mid -April 2017. This is contingent upon the delivery and bidding of an early site work bid package. (Drawings due Feb. 02.24.17) Project needs to be available for Athletic Dept. use July 30, 2018. Project meetings occur twice a month and include: construction manager (JE Dunn), architect (Studio), Athletic Dept., and A&E Services. Updated estimate provided by JE Dunn 02.24.17 NORTH HAMILTON ANNEX: Start Date: Summer 2018 Completion: Fall 2019 Size: 26,000 sqft Total Project Budget: $9,000,000 Design work will begin March 2017. Meeting to discuss project 03.08.17. Construction scheduled to begin May 2018. (involves demolition of northern portion of Hamilton Field House) Bonding request contingent upon Legislature approval. Project account is set-up. LIBERAL ARTS ADDITION: Start Date: Fall 2017 Completion: Summer 2019 Size: 52,000 sqft Total Project Budget: $17,500,000 Design work continues. Beck Design and A&E Services met with the college 02.23.17. (monthly meetings with the college will be on-going) Bonding request contingent upon Legislature approval. CAMPUS PROJECTS: (ADM) GUEST HOUSE: Start Date: 12/05/16 End Date: 03/31/17 Total Cost: $42,167.73 Submitted proposed interior paint color to Nancy for approval on 02/20/17. Moving of furniture from yellow house scheduled for end of March. 5

DPS ANNEX: Start Date: 11/01/16 End Date: mid to late March Total Cost: $14,200.00 Project at 85% completion Received quote from Patco to upgrade existing electrical service on 02/16/17. Met with Patco to review existing conditions and scope of work on 02/14/17. Requested quote from Patco per purchasing department requirements on 02/13/17. BUILDING SURGE PROTECTION: Objective protect hvac and other sensitive equipment from damage as the result of EE power failures. PO in place to install protection on (14) buildings Work to be performed during summer 17 ELECTRICAL PANEL UPGRADES: Objective replace aging electrical panels in (8) buildings These panels are either overloaded or replacement parts are no longer available Process will take a minimum of 3 years depending on access to classroom buildings Building will be without electrical service for 2 to 3 days during retrofit Meeting to be scheduled with Provost and Deans to coordinate priorities and scheduling JCI LIGHTING RETROFIT: Project at 50% completion JCI will begin work in Housing over spring and summer breaks 6