Guten Tag. (good day)

Similar documents
The Planning Process Group

Project Time Management

Guten Tag. (good day)

PMP EXAMINATION PREP CHAPTER 6 SCHEDULE MANAGEMENT. PMP Exam Prep

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

PMP Exam Preparation Course Project Time Management

Project Stakeholder Management

Ninth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book:

THE PMP EXAM PREP COURSE

Time Management PLANNING

Guten Tag. (good day)

Project Risk Management

Project Management Professional (PMP) Exam Prep Course 6 - Project Schedule Management

Guten Tag. (good day)

Project Scope Management

Principles of Planning for Building and. by Eastwood Harris Pty Ltd. Introduction Emergency Evacuation. Course Outline.

Project Management Professional (PMP) Certification Exam Preparation Program Course Outline with Outcomes

6 PROJECT TIME MANAGEMENT

PMP TRAINING COURSE CONTENT

PMP Exam Prep Study Group Input-Output-Tools #3a

Content Break-up & Methodology for awarding Contact Hours / PDUs

Project vs Operation. Project Constraints. Pankaj Sharma, Pankaj Sharma,

Malay (Rumi, Roman script)

Project Management Process Groups. Monitoring & Controlling. Initiating Planning Executing. Closing. Check & Act. Rita: A project ends here!

PMI Lexicon of Project Management Terms

PMBOK Guide Fifth Edition Pre Release Version October 10, 2012

Appendix. Process Inputs and Outputs

Information Technology Project Management, Seventh Edition

International Association of Certified Practicing Engineers

After solving all the case studies, please forward your answers to for an extra credit.

PMP Q&As. Project Management Professional. Pass PMI PMP Exam with 100% Guarantee. Free Download Real Questions & Answers PDF and VCE file from:

Scheduling 2 Day Structure

Introduction to Project Management

S O Seminar Objective

Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter

PMI Scheduling Professional (PMI-SP)

PMP PMBOK Guide Sixth Edition Training Course Agenda

Total Questions: 370 MODULE QUIZ ANSWER KEY. Fundamentals 1 & 2

Project Time Management

Project Management Framework

A semaphore telegraph, optical telegraph, shutter telegraph chain, Chappe telegraph, or Napoleonic semaphore is a system of conveying information by

4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition?

Compiled by Rajan Humagai

The Project Planning Process Group

The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th

Time has the least. amount of flexibility; Schedule issues are the main reason for

The PMP CRAM. The Guide to Pass the PMP

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

Global Project Management, LLC

PMI EXAM PgMP Program Management Professional (PgMP)

PMP Exam Preparation Workshop. Chapter # 5 Project Scope Management

Estimating Project Schedule-Time and Cost

Project Management CSC 310 Spring 2017 Howard Rosenthal

Objectives of Project Management Framework. What are the Characteristics Of Project. Activities involved Project Management

Knowledge Areas According to the PMBOK edition 5. Chapter 4 - Integration

Project Management CSC 310 Spring 2018 Howard Rosenthal

MGT/437. Project Management. Session #2 University of Phoenix 02/12/2004 Brian Smithson. 02/12/2004 MGT/437 #2 -- Brian Smithson 1

A Guide to the Project Management Body of Knowledge (PMBOK Guide) Sixth Edition Errata 3 rd Printing

Network Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)

Course Outline. TEC D 205 Engineering Tech Project Planning Olympic College Bremerton, WA. Week 1 Chapter 4: DEFINING THE PROJECT

Integration Knowledge Area

JapanCert 専門 IT 認証試験問題集提供者

GLOSSARY. 1. Inclusions and Exclusions. 2. Common Acronyms

SCHOOL OF ACCOUNTING AND BUSINESS BSc. (APPLIED ACCOUNTING) GENERAL / SPECIAL DEGREE PROGRAMME END SEMESTER EXAMINATION JULY 2017

Initiation Group Process. Planning Group Process

Project Management PSGLE 122. Time and Resources

Index. Symbols. 80/20 Rule, /15 Rule, 306

PMP. Processexam.com. PMI Project Management Professional. Exam Summary Syllabus Questions

PROJECT TIME MANAGEMENT Powered by POeT Solvers Limited

Project Forecast Survey Results Good Scheduling Practices June 2016

Exam Questions PMI-001

Planning and Scheduling Training Program Course Brochure and Competency Matrix

EXAMINATION CONTENT OUTLINE-6

Synopsis 2017 of PS Project Management Course

KillTest *KIJGT 3WCNKV[ $GVVGT 5GTXKEG Q&A NZZV ]]] QORRZKYZ IUS =K ULLKX LXKK [VJGZK YKX\OIK LUX UTK _KGX

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)

Project Management Body of Knowledge Chapter 3 Project Processes

Project Management Professional (PMP) Exam Prep Course 4 - Project Integration Management

IT Project Management. Essentials of IT project management 25 Sep 2017

Forecast Scheduling Microsoft Project Online 2018

Project Management. Time and Resources DPLE 157

PMP Course Content. Chapter 1. Introduction to PMP Objectives of PMP Requirements for PMP Exam About PMP Exam PMP Exam Syllabus.

GLOSSARY AND INDEX. Glossary Index Project Management Institute, 130 South State Road, Upper Darby, PA USA 155

ActualTests.CAPM.660Questions. Certified Associate in Project Management (CAPM)

Project Time Management

Project Management Concepts, Tools & Techniques

Week 5 Project Work Plan

Course Outline. Project Management Concepts Course PM12: 3 days Instructor Led

nam I BIA Un IVERS ltv OF SCIEnCE AnD TECHnOLOGY

Professional Training Services

CSU Project Management Certificate Program. Project Scope Management

Successful Project Management. Overview Houston Community College Fall, 2017

GUIDE TO THE CHANGES IN PMP simpl learn i

Project Management Professional

Project Planning and Estimating DJ

PMP Exam Prep Coaching Program

PROJECT SCHEDULING & CONTROL

Mastering Microsoft Project 2010

THE PROJECT DEFINITION WIZARD. Project Management processes, terms and definitions. Contents

Transcription:

Guten Tag (good day)

Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources 10. Communications 11. Risk 12. Procurement 6. 1 2 3456 Monitoring & Controlling 6.7 Closing 6.7 Control Schedule

Initiating Process Group Planning Process Group Executing Process Group Monitoring & Controlling Process Group Closing Process Group Project Time Management 6.1 Plan Schedule Management - the process for planning 6.2 Define Activities - decompose the WBS into activities 6.3 Sequence Activities - predecessors & successors 6.4 Estimate Activity Resources - who is doing the work? 6.5 Estimate Activity Durations - how long will it take? 6.6 Develop Schedule - put the activities into software 6.7 Control Schedule - monitor the project progress Outputs.1 Schedule management plan Outputs.1 Activity list.2 Activity attributes.3 Milestone list Outputs.1 Project schedule network diagrams.2 Project documents Outputs.1 Activity resource requirements.2 Resource breakdown structure.3 Project documents Outputs.1 Activity duration estimates.2 Project documents Outputs.1 Schedule baseline.2 Project schedule.3 Schedule data.4 Project calendars.5 Project management plan.6 Project documents

6.7 Control Schedule Inputs Tools & Techniques Outputs What & Why?.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 To monitor project progress To manage changes to the schedule baseline as they occur To recognize deviation from the baseline and take corrective and/or preventive actions to minimize risk Updating the schedule requires knowing the actual performance to date

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Work Performance Data, the raw data of observations and measurements: Key performance indicators Technical performance measures Start and finish dates Number of change requests Number of defects Actual costs Actual durations

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Project Calendars: a chart that identifies working days and shifts that are available for scheduled activities Schedule Data: Schedule milestones, activities & their attributes Assumptions and constraints A histogram of resource requirements Alternative schedules (e.g.. best-case or worst-case)

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Performance Reviews: Trend analysis - examine a project performance to determine whether performance is improving or deteriorating

Milestone Trend analysis

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Performance Reviews: Critical path method: Compare progress along the critical path Variance on the critical path will have a direct impact on the project end date Looking at the progress of activities near critical paths can identify schedule risk

Critical Path analysis 6 5 10 1 5 5 B 11 5 15 Path A B D = 25 16 15 30 Start A D Finish 1 0 5 6 10 15 C 16 0 30 Path A C D = 30 (Critical Path) 6 0 15 KEY Activity Node Early Start Duration Early Finish Activity Name Late Start Total Float Late Finish NOTE: This example uses the accepted convention of the project starting on day 1 for calculating calendar start and finish dates. There are other accepted conventions that may be used. Critical Path Link Non-Critical Path Link Figure 6-18. Example of Critical Path Method See 014-time notes for more information

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Performance Reviews: Critical chain method: Accounts for the effects of project uncertainty Allow each activity to occur as late as possible and, starting at the project end, add buffers (called Feeding Buffers) at key milestones to account for resource risk & limitations

Exam: This technique may be mentioned 3 times on the exam Critical Chain analysis

Further activity and schedule reduction using the Agile (Scrum) a methodology:

If an agile approach is utilized control schedule is concerned with: Knowing the current status of the schedule by comparing the total amount of work delivered and accepted against the baseline Conducting lessons learned reviews to correct processes Reprioritizing the remaining work plan (backlog) Determining the rate at which the deliverables are produced, validated and accepted (typically 2-4 weeks) Determine if the project schedule has changed Managing changes as they occur

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Performance Reviews: Earned value management: determines the current status of the project and tracks progress. It integrates scope, cost and schedule measures For the schedule we look at: Schedule variance (SV) - the difference between Earned Value (EV) and Planned Value (PV) Schedule performance index (SPI) - the ratio between Earned Value (EV) and Planned Value (PV)

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Earned value management, why? To determine the degree of variance To estimate the implications of those variances for future work To decide whether corrective or preventive action is required For projects not using earned value management compare planned activity start or finish dates with actual start or finish dates Determine the cause of the variance and any corrective or preventative actions needed

Earned value management, 3 basic elements: Planned Value (PV) - the planned cost of the work The total planned value for the project is known as Budget at Completion (BAC). Planned Value = (Planned % Complete) x BAC Earned Value (EV) - value of actual work completed to date Earned Value = (% of completed work) x BAC Actual Cost (AC) - the amount of money spent to date

Earned value management with regards to Schedule: Schedule variance (SV) = Earned Value Planned Value Measures work completed compared with what was planed - if the SV is positive you are ahead of schedule - if the SV is negative you are behind schedule Schedule performance index (SPI) = Earned Value / Planned Value Tells you how efficiently you are actually progressing compared to the planned progress - if the SPI is more than one you are ahead of schedule - if the SPI is less than one you are behind schedule

Earned Value Management

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Project Management Software: MS project / Gantter... Resource Optimization Techniques: Resource Leveling: used when resources are in limited supply to balance resource demand. This typically lengthens the critical path Resource Smoothing: Similar to leveling but the resources are only leveled within the limits of the float in their activity. Completion dates are not delayed

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Modeling Techniques: What-If Scenario Analysis, for example: delaying a major component delivery or extending specific durations Simulation: most commonly, a Monte Carlo analysis

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Leads and Lags: adjust leads and lags to bring activities in line with the schedule

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Schedule Compression: shortening the schedule without reducing scope Fast tracking: change activities to perform in parallel Crashing: adding (or adjusting) resources to shorten the schedule and maintain the scope This adds cost

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Scheduling Tool: MS Project / Gantter... Work Performance Information: calculated SV or SPI values

6.7 Control Schedule Inputs Tools & Techniques Outputs.1 Project management plan.2 Project schedule.3 Work performance data.4 Project calendars.5 Schedule data assets.1 Performance reviews.2 Project management software.3 Resource optimization techniques.4 Modeling techniques.5 Leads and lags.6 Schedule compression.7 Scheduling tool.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets PMBOK p. 185 Schedule Forecasts: of the project s future which includes: Past performance Expected future performance Earned value performance indicators

Initiating Process Group Planning Process Group Executing Process Group Monitoring & Controlling Process Group Closing Process Group Project Time Management 6.1 Plan Schedule Management - the process for planning 6.2 Define Activities - decompose the WBS into activities 6.3 Sequence Activities - predecessors & successors 6.4 Estimate Activity Resources - who is doing the work? 6.5 Estimate Activity Durations - how long will it take? 6.6 Develop Schedule - put the activities into software 6.7 Control Schedule - monitor the project progress Outputs.1 Work performance information.2 Schedule forecasts.3 Change requests.4 Project management plan.5 Project documents assets Outputs.1 Schedule management plan Outputs.1 Activity list.2 Activity attributes.3 Milestone list Outputs.1 Project schedule network diagrams.2 Project documents Outputs.1 Activity resource requirements.2 Resource breakdown structure.3 Project documents Outputs.1 Activity duration estimates.2 Project documents Outputs.1 Schedule baseline.2 Project schedule.3 Schedule data.4 Project calendars.5 Project management plan.6 Project documents

Q

Question Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Answer Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Question Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Answer Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Question Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Answer Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Question Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Answer Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Question Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Answer Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Question Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Answer Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Question Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Answer Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Question Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Answer Rita Mulcahy s Pmp Exam Prep Copyright 2013 RMC Publications, Inc.

Auf Wiedersehen (good bye)