GIS Hydropower Resource Mapping Country Report for Niger 1

Similar documents
GIS Hydropower Resource Mapping Country Report for The Gambia 1

GIS Hydropower Resource Mapping Country Report for Burkina Faso 1

GIS Hydropower Resource Mapping Country Report for Togo 1

GIS Hydropower Resource Mapping Country Report for Guinea-Bissau 1

GIS Hydropower Resource Mapping Country Report for Senegal 1

GIS Hydropower Resource Mapping Country Report for Benin 1

GIS Hydropower Resource Mapping Country Report for Ghana 1

GIS Hydropower Resource Mapping Country Report for Côte d Ivoire 1

GIS Hydropower Resource Mapping Country Report for Sierra Leone 1

ECOWAS COUNTRIES. Technical Report on Methodology and Lessons Learnt for

NBI strategic water resources analysis Phase I findings

The Impact of Climate Change on a Humid, Equatorial Catchment in Uganda.

Annex 5 - Hydropower Model Vakhsh

Reservoir on the Rio Boba

Management Scenarios of the Grand Ethiopian Renaissance Dam and Their Impacts under Recent and Future Climates. and Fred Fokko Hattermann ID

Lecture 9A: Drainage Basins

GCSE 4242/02 GEOGRAPHY SPECIFICATION B FOUNDATION TIER UNIT 2 SECTION B

WASCAL initiative on climate change and sustainable Energy in West-Africa

CENTRAL ASSINIBOINE INTEGRATED WATERSHED MANAGEMENT PLAN SURFACE WATER HYDROLOGY REPORT

Sustainable Energy for All: The contribution of hydropower to a sustainable Energy Future. Mahama Kappiah/ Aminata Fall, Vienna, May

Camp Far West Hydroelectric Project Relicensing

Hydrology Overview of Lake Taupo and the Waikato River as it relates to the Waikato Hydro Scheme (WHS) (Ohakuri Site Visit)

From Upstream to Downstream:

ICELANDIC RIVER / WASHOW BAY CREEK INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT

Nile Basin Decision Support System (NB DSS)

The Fourth Assessment of the Intergovernmental

Welcome to AGRHYMET. Dr Abdou ALI, Hydroclimatologist PB 11011, AGRHYMET, Niamey, Niger

National Quali cations

National Quali cations

Measuring and Monitoring a Lack of Resilience, and Informing Resilience Operations

Regional climate and hydrological modeling in the Nile Basin. Mohamed Elshamy, Regional WR Modeler, NBI RICCAR 6 th EGM, Cairo 7 & 8 Dec 2012

The ECOWAS Small Scale Hydro Power Program: OUR COMMON VISION BY Mr. Mahama Kappiah/Mr. Martin Lugmayr, ECREEE-UNIDO, 19 April 2012

Geographical Information System-Assisted Water Availability Analysis for Grenada MAP COMPENDIUM

Assessing the impact of climate change on the hydroperiod of two Natura 2000 sites in Northern Greece

FISHER RIVER INTEGRATED WATERSHED MANAGEMENT PLAN STATE OF THE WATERSHED REPORT CONTRIBUTION SURFACE WATER HYDROLOGY REPORT

EVALUATION OF HYDROLOGIC AND WATER RESOURCES RESPONSE TO METEOROLOGICAL DROUGHT IN THESSALY, GREECE

THE DATA COLLECTION AND COMPILATION PROCESSES

Drought Monitoring and Early Warning in West Africa. At the AGRHYMET Regional Center. By Seydou B. TRAORE,

AN INTEGRATED FRAMEWORK FOR EFFECTIVE ADAPTATION TO CLIMATE CHANGE IMPACTS ON WATER RESOURCES

Assessment of Impact of Hydropower Dams Reservoir Outflow on the Downstream River Flood Regime Nigeria s Experience

REGIONAL FORECASTING OF GENERATION FROM SMALL HYDROPOWER PLANTS

Feasibility Report Madian Hydropower Project. Conclusions and Recommendations. 7166P02/Vol. II, Recommendations

ACHIEVING SDG7 IN AFRICA

CRT Operations in Low Water Conditions

Key features and development challenges for the Mekong River Basin

Overview of the Energy Sector Targets and Measures in ECOWAS Nationally Determined Contributions. (NDCs) RG

Modelling the Effects of Climate Change on Hydroelectric Power in Dokan, Iraq

Water Balance Assessment of the Roseires Reservoir

MODELLING OF NIGER RIVER BASIN DEVELOPMENT UNDER UNCERTAIN CLIMATOLOGICAL CONDITIONS

Impact of Climate Change on Water Resources of a Semi-arid Basin- Jordan

LOXAHATCHEE RIVER WATER QUALITY EVENT SAMPLING TASK 2: FINAL REPORT ASSESSMENT OF LOXAHATCHEE RIVER WATER QUALITY

Climate-resilient hydropower: Experiences from the EBRD region

Introducing the WBG Guidelines for selecting EFlow assessment methods. Cate Brown

Ecological effects & Hydropower dams & Transboundary river

Reservoir Drought Operations

1 THE USGS MODULAR MODELING SYSTEM MODEL OF THE UPPER COSUMNES RIVER

olumbia River Treaty The Columbia by Steve Oliver, Vice President, Generation Asset Management, Bonneville Power Administration 16 Oct

MODELLING STREAMFLOW TO SET AN ENVIRONMENTAL FLOW. A.M. De Girolamo*, A. Lo Porto IRSA, CNR, Bari, Italy

ECOWAS SUSTAINABLE ENERGY WEEK

Experimental drought early warning system in the Inner Niger Delta

Assessment of impacts of climate change on runoff: River Nzoia catchment, Kenya. Githui F. W, Bauwens W. and Mutua F.

Water Resources in Korea

John H. Kerr Dam and Reservoir Virginia and North Carolina (Section 216)

REGIONAL VALIDATION/TRAINING WORKSHOP ON THE USE OF GEOGRAPHIC INFORMATION SYSTEMs (GIS) IN THE ENERGY SECTOR

M.L. Kavvas, Z. Q. Chen, M. Anderson, L. Liang, N. Ohara Hydrologic Research Laboratory, Civil and Environmental Engineering, UC Davis

Solutions towards hydrological challenges in Africa in support of hydropower developments Ms. Catherine Blersch, Civil Engineer, Aurecon, South

A Case Study on Integrated Urban Water Modelling using Aquacycle NTUA, 2007

OPTIMISATION OF HYDROPOWER IN A MULTI-OBJECTIVE CONTEXT

Sustainable Energy Perspectives of the ECOWAS Region

COMMODITIES AND THE AfCFTA

The many faces of the Niger River

Available online at Nigerian Journal of Basic and Applied Science (December, 2012), 20(4):

Chapter 1 Introduction

Climate Change Impacts on Hydrological Regime in Latvia

Investigating the Impact of Climate Change on Flooding in the Sittaung River Basin, Myanmar

Drought monitoring and early warning in the Sahel : The AGRHYMET experience

Application of a Basin Scale Hydrological Model for Characterizing flow and Drought Trend

Improvement of the national water balance feasibility of water balances per river basin

Interannual Q c CV. Interannual CMI CV

CILSS / AGRHYMET Role in The Reduction of Food Crises and Other Hydroclimatic Disasters in West Africa

July 31, 2012

EXTREME EVENTS AFFECTING WATER RESOURCES IN THE HOPE RIVER WATERSHED IN JAMAICA: USE OF WETSPRO FOR BASEFLOW SEPARATION AND ITS LONG TERM TREND

Mekong Climate Change and Adaptation Initiative and the Mekong River Commission

Thailand-5. Mae Nam Wang. Map of River. 18 o o 00

Mekong Climate Change and Adaptation Initiative of the Mekong River Commission

Paul Whitehead and Emily Barbour (Oxford), (BUET, IIT Kanpur)

Renewables in Developing nations

An Investigation into the 2012 drought on Apalachicola River. Steve Leitman, Bill Pine and Greg Kiker

ECREEE Strategy to Promote Renewable Energy and Energy Efficiency Investments in the ECOWAS (2011 to 2016) Mr. Martin Lugmayr, ECREEE

M.L. Kavvas, Z. Q. Chen, M. Anderson, L. Liang, N. Ohara Hydrologic Research Laboratory, Civil and Environmental Engineering, UC Davis

San Antonio Water System Mitchell Lake Constructed Wetlands Below the Dam Preliminary Hydrologic Analysis

Water Supply Reallocation Workshop

REGIONAL ANALYSIS OF SMALL RESERVOIRS Potential for expansion in Sub-Saharan Africa

Analyzing water resources in a monsoon-driven environment an example from the Indian Western Ghats

Welcome STEP 1: STEP 2: STEP 3:

Failure of the Mtera-Kidatu Reservoir System in the Early 1990s

Reservoirs performances under climate variability: a case study

Agenda. Evaluation of Lake Superior Regulation Plans Using Robustness and Climate Informed Risk

AGENDA DATE: November 14, 2018

Hydrological Modelling of Narmada basin in Central India using Soil and Water Assessment Tool (SWAT)

Transcription:

GIS Hydropower Resource Mapping Country Report for Niger 1

GIS Hydropower Resource Mapping Country Report for Niger 2

GIS Hydropower Resource Mapping Country Report for Niger 3

GIS Hydropower Resource Mapping Country Report for Niger 4 PREFACE The 15 countries of the Economic Community of West African States (ECOWAS) face a constant shortage of energy supply, which has negative impacts on social and economic development, including also strongly the quality of life of the population. In mid 2016 the region has about 50 operational hydropower plants and about 40 sites are under construction or refurbishment. The potential for hydropower development especially for small-scale plants is assumed to be large, but exact data were missing in the past. The ECOWAS Centre for Renewable Energy and Energy Efficiency (ECREEE), founded in 2010 by ECOWAS, ADA, AECID and UNIDO, responded to these challenges and developed the ECOWAS Small- Scale Hydropower Program, which was approved by ECOWAS Energy Ministers in 2012. In the frame of this program ECREEE assigned Pöyry Energy GmbH in 2015 for implementation of a hydropower resource mapping by use of Geographic Information Systems (GIS) for 14 ECOWAS member countries (excluding Cabo Verde). The main deliverable of the project is a complete and comprehensive assessment of the hydro resources and computation of hydropower potentials as well as possible climate change impacts for West Africa. Main deliverables of the GIS mapping include: River network layer: GIS line layer showing the river network for about 500,000 river reaches (see river network map below) with attributes including river name (if available), theoretical hydropower potential, elevation at start and end of reach, mean annual discharge, mean monthly discharge, etc. Sub-catchment layer: GIS polygon layer showing about 1000 sub-catchments with a size of roughly 3000 km². This layer summarizes the data of all river reaches located within the subcatchment. Hydropower plants are investments with a lifetime of several decades. Therefore, possible impacts of climate change on future discharge were incorporated into the river network and sub-catchment GIS layers. The GIS layers are available in the ECREEE Observatory for Renewable Energy and Energy Efficiency (www.ecowrex.org). This report summarizes the results of the GIS layers for Niger and includes: General information Climate Hydrology Hydropower potential Climate change Mean Annual Flow [m³/s] 0 1 1 10 10 100 100 1000 > 1000 0 200

GIS Hydropower Resource Mapping Country Report for Niger 5 GENERAL INFORMATION The Republic of Niger is one of the largest countries in West Africa, but only has a population of 19 Mio inhabitants. The capital of Niger is Niamey in the south-western part of the country. The neighboring countries are Burkina Faso in the south-west, Mali in the west, Algeria in the northwest, Libya in the north, Chad in the east, as well as Nigeria and Benin in the south (see map below). Hydropower currently plays no role for energy generation in Niger, as there are no operational hydropower plants. However, Kandadji hydropower plant is currently under construction at the Niger River. Inhabitants (2014) Area (2014) GDP per capita (2014) General Information for Niger 19.1 Mio. 1,267,000 km² 427 USD Electrification rate total/urban/rural (2013) 9/45/1 % Hydro installed capacity (2013) Electricity generation (2013) Electricity generation from hydropower (2013) Number of existing hydropower plants with installed capacity > 1 MW (2016) Number of existing small hydropower plants with installed capacity 1-30 MW (2016) Number of existing medium hydropower plants with installed capacity 30-100 MW (2016) Number of existing large hydropower plants with installed capacity >100 MW (2016) 0 MW 443 GWh 0 GWh Source: ECOWAS Country Profiles (www.ecowrex.org) Reference year given in brackets. 0 0 0 0

GIS Hydropower Resource Mapping Country Report for Niger 6 CLIMATE The climate in West Africa can be grouped into six zones with distinctive seasonal rainfall patterns (L Hôte et al., 1996). In Niger the climate ranges from Semiarid tropical in the south, over Semiarid desert in the central parts, to Desert in the north. The diagrams below summarize the mean monthly rainfall and air temperature in these climate zones.

GIS Hydropower Resource Mapping Country Report for Niger 7 HYDROLOGY The Niger River is by far the most important river in the Republic of Niger. The Niger River traverses the western part of the country, entering from Mali and flowing in south-easterly direction where the river forms the border with Benin before flowing into Nigeria. About 40 % of the country is located in the Niger basin, but this includes desert area that in reality do not have any significant discharge. 10 % of the country belongs to the basin of Lake Chad, which includes the Yobe River (see map and table below). Other notable rivers include the Sirba River and the Maradi River. The Sirba River enters from Burkina Faso and can cause floods in August and September. The Maradi River enters from Nigeria, flows a short section in Niger towards the west and then re-enters Nigeria near Goronyo reservoir. The figures on the following page illustrate the annual and seasonal variations in discharge for the Niger River. Percentage of country s area located in different basins Niger River basin 43 % Lake Chad basin 10 %

Mean Discharge [m³/s] GIS Hydropower Resource Mapping Country Report for Niger 8 Historic Variation in Annual Discharge The Niger River at Niamey shows strong variations in annual discharge over the last 60 years. The 1950s and 1960s were the wettest period, followed by some extremely dry years in the 1980s, whereas the period 1998-2014 represents moderately wet conditions in the historic context. Niger River at Niamey Simulated annual discharge Bonou Simulated Annual discharge annual discharge simulated with water balance model 800 4000 Avgerage Average Avgerage 1998-2014 1998-2014 600 3000 400 200 2000 0 1000 1965 1970 Year 1975 1980 1985 1990 1995 2000 2005 2010 2015 0 1950 1955 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 Discharge [m³/s] Discharge [m³/s] Seasonality in Discharge The seasonality in discharge of the Niger River at Niamey is the result of the White Flood from local tributaries in August and September and the Black Flood between October and March, which basically is the outflow from the Inner Niger Delta upstream in Mali. Low flow occurs in May and June. Niger River at Niamey Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2000 1500 1000 500 0

GIS Hydropower Resource Mapping Country Report for Niger 9 Annual Water Balance The long-term mean annual water balance describes the partitioning of precipitation (rainfall) into actual evapotranspiration (transpiration by plants, evaporation from soil) and runoff, as over long time periods the change in storage (soil moisture, ground water) can be assumed to be negligible for the mean annual water balance. The regional distribution of the water balance components in West Africa is strongly controlled by spatial variations in mean annual precipitation. An annual water balance model calibrated with observed discharge data of 400 gauges was used to determine mean annual actual evapotranspiration and runoff for the period 1998-2014, as shown in the maps below. In most parts of West Africa mean annual actual evapotranspiration is considerably larger than mean annual runoff. This is also the case for the mean annual water balance in the Republic of Niger. However, even though mean annual runoff is very low in the country, most of the rivers have their headwater regions in wetter areas, like the Niger River (Guinea, Mali) and Sirba River (Burkina Faso). Mean annual discharge is computed by aggregating runoff along the river network, which together with channel slope determines the hydropower potential (see next section).

GIS Hydropower Resource Mapping Country Report for Niger 10 HYDROPOWER POTENTIAL The theoretical hydropower potential of a river is defined as the amount of power that would be produced if the full head of the river was used and if 100 % of the mean annual discharge was turbinated (i.e. no spillway losses or environmental flow constraints). In this study overall plant efficiency (turbines, hydraulic losses) is assumed with 87 %. The theoretical hydropower potential for the Republic of Niger is estimated to be 529 MW (reference period 1998-2014), which is the total of all rivers in the country. The following table and figure show how the total potential of the country is subdivided into theoretical potential for hydropower plants (HPP) of different plant size. A classification scheme based on mean annual discharge (m³/s) and specific hydropower potential (MW/km) was applied to determine the preferred plant size for river reaches with a typical length of 1-10 km. Four classes were considered for the preferred plant size, including pico/micro/mini HPP (< 1 MW installed capacity), small HPP (1-30 MW installed capacity), medium/large HPP (> 30 MW installed capacity), and No attractive potential for river reaches with too low specific hydropower potential. For the latter in some cases it may still be worthwhile to utilize this potential in e.g. multi-purpose schemes. Almost all of the attractive theoretical potential is classified as medium/large HPP, and there is no significant potential for pico/micro/mini HPP and small HPP in the country. The technical potential was not assessed in this study. 40% Theoretical Hydropower Potential Republic of Niger: 529 MW 1% 59% Niger Theoretical hydropower potential: 529 MW Pico/micro/mini HPP Small Theoretical HPP potential for pico/micro/mini HPP < 1 MW Medium/large Theoretical potential HPP for small HPP 1-30 MW No Theoretical attractive potential potential for medium/large HPP > 30 MW Not suitable Pico/micro/mini HPP Small HPP Medium/large HPP No attractive potential Theoretical Hydropower Potential of Rivers in the Republic of Niger Total of all rivers in country Total of rivers with attractive theoretical potential for pico/micro/mini, small, or medium/large HPP 0 MW 3 MW 312 MW 214 MW 529 MW 315 MW

GIS Hydropower Resource Mapping Country Report for Niger 11 Longitudinal Profiles of Selected Rivers The following graph shows the longitudinal profile of the Niger River, plotting elevation (red) and mean annual discharge (blue) from the source to the mouth of the river. Inflow from tributaries is clearly identifiable as sudden increase in river discharge. Diversions and floodplain losses cause a decrease of discharge in some sections of the Niger River. The Kainji and Jebba reservoirs in Nigeria are identifiable by constant elevation in the reservoir lake and sudden drop of elevation at the dam site. The background color indicates if a river reach has an attractive theoretical hydropower potential for pico/micro/mini HPP (< 1 MW installed capacity), small HPP (1-30 MW installed capacity), or medium/large HPP (> 30 MW installed capacity).

GIS Hydropower Resource Mapping Country Report for Niger 12 Hydropower Potential in Selected Sub-catchments The following maps and tables give information about the theoretical hydropower potential of selected sub-catchments in the Republic of Niger. All of the selected sub-catchments are located along the Niger River. The table data summarizes the total theoretical hydropower potential of all river reaches within the sub-catchment. River reaches were grouped according to preferred plant size for pico/micro/mini HPP (< 1 MW installed capacity), small HPP (1-30 MW installed capacity), or medium/large HPP (> 30 MW installed capacity). Similarly, the color code of the river network displayed in the maps indicates the preferred plant size. A grey color indicates no attractive potential for hydropower development. River network showing preferred hydropower plant size Pico/micro/mini HPP Small HPP Medium/large HPP Map overlays Selected sub-catchments with ID number Lake or reservoir Country border

GIS Hydropower Resource Mapping Country Report for Niger 13 Theoretical Hydropower Potential of Rivers in Sub-Catchment #988 Pico/micro/mini HPP Small HPP Medium/large HPP 0 MW 0 MW 80.8 MW The Niger River upstream of the Kandadji HPP dam site has considerable potential for medium/large HPP. There is no potential for pico/micro/mini or small HPP. Theoretical Hydropower Potential of Rivers in Sub-Catchment #1014 Pico/micro/mini HPP Small HPP Medium/large HPP 0 MW 0 MW 70.9 MW Also the Niger River downstream of the Kandadji HPP dam site has considerable theoretical potential. There is no potential for pico/micro/mini or small HPP. River network showing preferred hydropower plant size Pico/micro/mini HPP Small HPP Medium/large HPP No attractive potential Map overlays Existing hydropower plant Lake or reservoir Sub-catchment boundary Country border

GIS Hydropower Resource Mapping Country Report for Niger 14 Theoretical Hydropower Potential of Rivers in Sub-Catchment #1057 Pico/micro/mini HPP Small HPP Medium/large HPP 0 MW 0 MW 28.7 MW The Niger River a short distance upstream of Niamey has some theoretical potential for medium/large HPP. There is no potential for pico/micro/mini or small HPP. River network showing preferred hydropower plant size Pico/micro/mini HPP Small HPP Medium/large HPP No attractive potential Map overlays Existing hydropower plant Lake or reservoir Sub-catchment boundary Country border

GIS Hydropower Resource Mapping Country Report for Niger 15 CLIMATE CHANGE Climate change may have considerable impact on future water resources and thus hydropower generation. The following figures show an assessment of climate change projections for West Africa based on 15 Regional Climate Models of the CORDEX-Africa ensemble. Two Representative Concentration Pathways (RCP4.5 and RCP8.5) were considered, thus yielding a total of 30 climate model runs. Future runoff was simulated by driving a water balance model with precipitation and temperature climate change signals with respect to the reference period 1998-2014. Projections for the Near Future 2026-2045

GIS Hydropower Resource Mapping Country Report for Niger 16 Projections for the Far Future 2046-2065 The maps below show the expected impact of climate change on future mean annual water resources. From the 30 climate model runs the median result was computed to generate the maps, which show change signals comparing the future periods 2026-2045 (previous page) and 2046-2065 (this page) vs. the reference period 1998-2014. In large parts of West Africa increase or almost no change is projected for future precipitation. This is also the case for Niger. The combined effects of future precipitation and considerable warming (which affects evapotranspiration) were simulated with a water balance model to compute future runoff. In Niger runoff is projected to decrease in the central parts and increase in the southern parts of the country (median of 30 model runs).

Discharge [%] relative to 1998-2014 GIS Hydropower Resource Mapping Country Report for Niger 17 Projected Change in Discharge for Selected Gauges Future mean annual discharge was estimated with data from 30 different climate model runs. Boxplots are presented to summarize the spread in the simulation results (see explanation at right). For the Niger River at Niamey future discharge is projected to increase by about +7%. Some of the individual climate model runs show a decrease in future discharge, whereas the majority of the climate model runs show an increase in future discharge (see boxplot below). Overall the climate change impact assessment shows that given the projections with the most detailed climate models currently available (CORDEX-Africa) Niger River discharge at Niamey is projected to increase in the future. This would be beneficial for hydropower development along the Niger River in the Republic of Niger. 150 Niger River at Niamey 100 50 2026-2045 2046-2065 Period

GIS Hydropower Resource Mapping Country Report for Niger 18 ACKNOWLEDGEMENTS This study was conducted by Pöyry Energy GmbH (Vienna, Austria) for the ECOWAS Centre for Renewable Energy and Energy Efficiency (ECREEE, Praia, Cabo Verde). This is a contribution to the ECOWAS Small-Scale Hydro Power Program, which aims to develop the small-scale hydropower sector in West Africa and is funded by the Austrian Development Agency (ADA) and the Spanish Agency for International Development Cooperation (AECID). Observed discharge data were used for hydrological model calibration and were obtained from the following sources: Global Runoff Data Centre (GRDC), Volta Basin Authority, Niger Basin Authority, Senegal & Gambia Basin Authorities (OMVS, OMVG), Liberia National Hydrological Service, Sierra Leone National Hydrological Service, Japan International Cooperation Agency (JICA). Precipitation data 1998-2014 are based on Tropical Rainfall Measurement Mission (TRMM 3B42 v7). Additional precipitation data 1950-2010 for model calibration were obtained from the Global Precipitation Climatology Centre (GPCC). Air temperature and potential evapotranspiration data were obtained from the Climatic Research Unit (CRU, Univ. East Anglia), with additional data from the CLIMWAT database of FAO. River network and elevation data were derived from the Hydrosheds dataset (USGS). Climate model data were obtained from the Coordinated Regional Downscaling Experiment for Africa (CORDEX-Africa), which is a project of the World Climate Research Program. The delineation of climate zones is based on: L`Hôte Y, Dubreuil P, Lerique J. 1996. Carte des types de climats en Afrique Noire à l ouest du Congo. Rappels, et extension aux régimes hydrologiques. In: L hydrologie tropicale: géoscience et outil pour le développement (Actes de la conférence de Paris, mai 1995). IAHS Publ. no. 238, p. 55-65 More information about the general methodology for the GIS hydropower resource mapping is available in: Kling H, Stanzel P, Fuchs M. 2016. Regional assessment of the hydropower potential of rivers in West Africa. Energy Procedia, Elsevier, Special Issue of ERE, 8 pp.