Jhajjar Project Management An Insight. March 4, 2013

Similar documents
Contd7. Theft of water by using pumps on water lines from dam to TPS. 8. Plant premise is not compact hence piping's are long.

USE OF WHATSAPP MOBILE APPLICATION IN PROJECT MANAGEMENT OF LARGE INFRASTRUCTURE PROJECT

ABWR Construction Experience in Japan

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...


TROJAN DECOMMISSIONING STATUS. OPUC Meeting March 8, 2005 (draft)

Materials Selection and Quality Assurance in Capital Projects Materials Technology

His Worship Mayor Don Darling and Members of Common Council. SUBJECT: Project Performance Update Safe, Clean Drinking Water Project

Combined Heat and Power & District Heating Networks. For the East Midlands

TCN Revised `No deviation certificate as per enclosed Annexure-2. Bidder shall submit no deviation certificate as per enclosed format only.

RAMBOLL THERMAL TECHNOLOGY WITH DISTRICT ENERGY SYSTEMS

ARYAN M.P. POWER GENERATION PVT. LTD.

COMMISSIONING BEST PRACTICES AN EXPERIENCE SHARING

His Worship Mayor Don Darling and Members of Common Council. SUBJECT: Project Performance Update Safe, Clean Drinking Water Project

Tsunami Countermeasures at Hamaoka Nuclear Power Station

HPGCL HPGCL was incorporated as a company 17th March, The business of Generation of Power of erstwhile HSEB was transferred HPGCL

Emissions Control Project

nat Presentation Title ( Arial, Font size 28 ) Control of Sulphur Dioxide, Oxides of Nitrogen and Mercury Date, Venue, etc..( Arial, Font size 18 )

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD

Barilla Cogeneration Power Plant main tips

Schedule Guidance Document

Post Combustion CO 2 Capture Scale Up Study

District heating topics

ABOUT EIL. more than 5000 projects including over 400 major projects worth USD 200 Billion in total cost.

Energy & Water linkages in the power sector Implications for future planning

O&M CONFERENCE IPS 2013

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #69 Douthit Hills Student Community, Clemson University Project Joe Jett

Majuba Underground Coal Gasification

Feasibility Report Madian Hydropower Project. Conclusions and Recommendations. 7166P02/Vol. II, Recommendations

Accord Energy Corporation India Pvt. Ltd.

REVIEW OF LAND REQUIREMENT FOR THERMAL POWER STATIONS

Lodge Grove Development Sander and Sons 2 St. John s Wood Road NW8. CLP Produced by: Name Signature Date

Developing Infrastructure in Bihar

Gorgon Project Briefing Rick Robinson Director Perth Operations Kellogg Joint Venture. Karratha, Feb

MEC-QW-E-2005 Senior QA/QC Inspector / Test Package Coordinator PERSONAL DATA LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

Kogan Creek Power. Condenser. Contents. Update For ACC User Group. Kogan Creek Power Station and its Air

Holds a B. Sc. in Mechanical Power Engineering and has over 10 years hands-on experience working in construction and piping.

Gorgon Project Briefing Rick Robinson Director Perth Operations Kellogg Joint Venture. Perth, November

INDUSTRIAL ACCESSORIES COMPANY

High-Performing Home Certificate. Certified Solar

Initial Analysis, Planning and Calculation of Vertical Delivery in High-rise Building Construction

MEC-OS-E-1992 Commissioning / Operation Manager PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

SFT-S : HSE Advisor PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS CHRONOLOGICAL EXPERIENCE RECORD

Thompson Construction Group

Ⅰ. Introduction of Samcheok Green Power

ELE-CMOS-E : Commissioning Leader PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

ENCOCORP S.A.R.L. COMPANY PROFILE

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #110 Douthit Hills Student Community, Clemson University Project Joe Jett

To Study of Maximum Efficiency Of Power Generation in Thermal Power Plant

Flexible Operation. Integrating thermal power with Renewable Energy & Challenges. Y M Babu Technical Services, Noida

WELCOME CHAMERA-I DAM

Wet Flue Gas Desulfurization (FGD)

JAYPEE NIGRIE SUPER THERMAL POWER PLANT

Arlington East WRF Influent Channel Rehabilitation - Final

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT

Challenges & Successes of Candu Energy (former AECL) in Nuclear Construction: Case Study of China and Romania

PROTECH Energy Services Limited

JOTUN B P&A CAMPAIGN DRILLING CONTRACTORS EXPERIENCE

We are here to:

License/ Certification No Oct 8, 1988

ENVIRONMENTAL STATEMENT FORM-V SYNTHETIC GYPSUM MANUFACTURING PLANT M/S SHREE CEMENT LIMITED, BEAWAR, (RAJASTHAN) APRIL, 2010 to MARCH 2011 PART A

Ironton Russell Bridge Project

Fairfield Board of Education Proposed Capital Non-Recurring Projects

Flue Gas Desulphurization (FGD) plant 2 x 600 MW Coal based Thermal power plant Cuddalore, Tamil Nadu. By MK Parameswaran 23 rd Dec, 2016

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #53 Douthit Hills Student Community, Clemson University Project Joe Jett

Our Motto aims to be "NEW ZESCO" New Value Creater. Endless Innovation. Work with Passion for Stakeholders

Case Study : Underground Coal Gasification (UCG) Majuba Update. Mark van der Riet Corporate Consultant Eskom Holdings Ltd South Africa

Mars TLP Recovery Project

REPORT ON THE LAND REQUIREMENT OF THERMAL POWER STATIONS

Suburbia, USA. Image Courtesy of The Whiting-Turner Contracting Company

General Procurement Notice

Evolution of a Deep Lake Cooling System

nalcofabtech.com A Nalco Champion Company

Structural Breadth Study

BROAD Sustainable Building (BSB) Sunny Wang January 31, 2017

INDUSTRIAL VISIT TATA THERMAL POWER PLANT PROJECT MANAGEMENT BATCH ( )

Scottish Court Service. Carbon Trust Standard Case Study

Ironton Russell Bridge Project

HI HI-TECH ENGINEERING & PROJECTS (INDIA) PRIVATE LIMITED

TOTAL WATER MANAGEMENT

ABSTRACT EXECUTIVE SUMMARY

MEC-CM-E-2004 Head Section Maintenance Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

CDM Carbon Finance Workshop. Session 9: Discussion of project risks and mitigation strategies. Accra, June

Watts Bar Nuclear Plant Unit 2 Completion Project

TCN 02, Dated: WITH REFERENCE TO ABOVE FOLLOWING CHANGES MAY PLEASE BE NOTED AND COMPLIED WHILE SUBMITTING THE OFFER FOR THE SUBJECT JOB:

Pumped hydro Storage Plants

Toshibaʼs Activities in Carbon Capture

Welcome to. ASHTECH TECHNOLOGIES PVT. LTD. (Pneumatic Conveying Systems) ASHTECH House, 30 POPATWADI, KALABDEVI ROAD MUMBAI (India)

NLC INDIA LIMITED PRE FEASIBILITY REPORT

CAPABILITY STATEMENT PRIZM Engineering Pty Ltd ABN

Willkommen zu allen स स व गतम

Adoption of USC CFB Technology to Achieving Lower Cost Generation and Environmental Sustainability. Gerd Heiermann & Douglas Spalding

Centre for Science and Environment MILESTONE TRACKER

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #103 Douthit Hills Student Community, Clemson University Project Joe Jett

Polaris Engineering. Excellence in service. Every time

Proposed Water Pipeline Route

Ironton Russell Bridge Project

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa

Rosatom Energy Solution: Engineering Perspective

Ironton Russell Bridge Project

Transcription:

Jhajjar Project Management An Insight March 4, 2013

2 x 660 MW Mahatma Gandhi Thermal Power Plant Jhajjar, Haryana, INDIA 2

A Brief Introduction 2x 660 MW greenfield project, named as Mahatma Gandhi Thermal Power Plant built by Jhajjar Power Limited (JPL) The Plant is located in Jhajjar district of Haryana The Project awarded by Government on 23rd July, 2008 with target completion date of 22nd July 2012 The Plant started commercial operation on 19th July, 2012 i.e. 3 days ahead of the schedule 3

MGTPP Site Layout Plan NORTH JPL TOWNSHIP TIEJUN LIVING AND OFFICE AREA GUEST HOUSE NDCT SWITH TIEJUN TIEJUN LABOUR COLONY YARD CONSTRUCTION MAIN AREA POWER HOUSE CHIMNEY BOP COAL HANDLING AREA RESERVOIR RAW WATER ROAD TO PLANT RAILWAY SIDING ASH DISPOSAL AREA DRAWING NOT TO SCALE 4

Preparations for the journey. Entire Main Plant contract awarded on turnkey basis to SEPCO-III/ TIEJUN after extensive deliberation & evaluation CLP Engineering team identified & included the list of reputed Chinese vendors for critical equipment in the Owner s Technical Requirement (OTR) Basic Engineering finalized by CLP Engineering team with inputs from the other CLP Assets The specifications of critical equipment like Turbine, Boiler, Generator, Transformer etc. were reviewed by CLP Engineering team Site team involved in the review of construction drawings to ensure compliance to Indian Standards and ensure constructability & Plant operability & maintainability 5

Major Contracts Structure 2 X 660 MW COAL FIRED POWER PLANT INFRASTRUCTURE WORK MAIN POWER HOUSE & EQUIPMENT SUPPLY BY M/S SEPCO-III (JPL) DESIGN ERECTION & COMMISSIONING ENGINEERING BY M/S TIEJUN RAILWAY SIDING BY M/S GDCL INTAKE WATER SYSTEM BY M/S FLOWMORE, M/S SIMPLEX & M/S GRPAHITE INDIA TOWNSHIP, ASH DYKE BY M/S SUBHASH INFRA ENGINEERS SITE BOUNDARY WALL BY M/S BHAYANA, AAKAR BUILDERS 6

Staffing Model for Project Execution Integrated Project Execution Team comprised of mainly new recruits from various organizations with diversified work culture Maintenance staff recruited as construction team ensuring continuity & ownership Operational staff recruited well in advance for familiarization, training and active participation in the commissioning activities 7

JPL SAFETY MISSION Everyone goes home safely to the family 8

JPL follows SAFETY FIRST Philosophy Measures taken in line with the CLP safety objective of Zero Incident Direct employee involvement in Safety Issues (Project Sun Flower) Animated safety induction program Safety Task Forces for high risk activities Improving & spreading safety awareness at site Providing EHS related amenities (e.g. Drinking water, sanitation etc.) in the labor camps. Weekly environmental audits to ensure desired standards Regular On-site Tool Box Talks (TBTs) 9

Co-operation from main & sub-contractors on safety Round the clock availability of medical facilities including doctor, nurse, paramedics, ambulance etc. Class room and on-job safety training for staff and contractors employees Management safety walk downs twice a week Reward and recognition on safety performance to Contractors 10

Salient technical features Super -Critical technology Mini Oil Ignition technology to reduce oil consumption Flue Gas Desulphurization (FGD) for reduction of SOx emission Combination of ESP & fabric filter to reduce particulate emission Chimney flue duct with Titanium lining to prevent corrosion Polymeric insulated SF6 filled current transformer (CT) to reduce the explosion risk level Use of bolted joints instead of welded joints in major structures for reduction in construction time & cost. 11

Project Uniqueness Compact Main Plant & CHP layout 12

Project Uniqueness Zero discharge philosophy 100% dry ash utilization to reduce environmental impacts & ash storage area requirement De-aerator level reduced by locating the BFP Booster Pumps at Ground Floor to decrease the turbine building height 13

Project Uniqueness Use of bolted connections for Boiler, TG and Switchyard Structures to reduce construction time & cost. 14

Project Uniqueness Use of deck sheets for safer & faster concreting for reduction in construction time 15

Project Uniqueness Chimney flue duct with Titanium lining to prevent corrosion of flue duct during FGD operation 16

Innovations during Project Execution Use of Tower Cranes for faster & safer erection & Gantry cranes for extensive pre-fabrication 17

Innovations during Project Execution Deep excavated foundations to substitute time & cost intensive pile foundations 18

Innovations during Project Execution Use of GRP & HDPE pipes in underground water piping system to reduce capital & maintenance cost and installation time 19

Innovations during Project Execution Steam blowing was done on coal firing instead of the usual practice of doing it on oil firing No water storage facility (overhead tank) throughout the plant by designing round-the-clock running water supply system Use of Extranet for review of engineering drawings during construction to win over geographical constraint. The thermal insulation of ESP, Main Steam Piping, Ducts etc. except Boiler was started before the boiler hydro test to mitigate the delay in the boiler erection. 20

Best Practices during Project Execution In addition to following the CLP standard procedures, manuals & guidelines Development of Project Execution Plan & Procedures e.g. Contract Management Procedure Invoice Processing Procedure Budget Control & Monitoring Procedure Departmental Construction & Commissioning Procedures Review & approval of Shop Inspection & Test Plan (ITP) for all critical equipment including owner s hold points Third party inspection & internal inspection by CLP at manufacturer s facility Review & approval of Field Quality Plans (FQP) 21

Challenges overcome SAFETY Difference in safety approach between CLP, TIEJUN/ Sub Contractors High turnover of workmen who are mostly from villages, unskilled and illiterate Prevailing fatalistic attitude amongst workers Lack of support from Contractor / Sub Contractors site management on safety issues 22

Challenges overcome Language barrier between SEPCO III/ TIEJUN and JPL Timely supply of offshore materials & equipments Land related issues for installation of raw water pipeline and railway line through the villages Daily commute of approx. 150 km by the project personnel during the construction phase 23

Project Execution Milestones MILESTONE DATE TIME (Days) w.r.t. NTP NOTICE TO PROCEED (NTP) 23-Mar-09 0 FIRST CONCRETE MAIN POWER HOUSE 16-May-09 54 1-Nov-09 223 COMPLETION OF ERECTION OF BOILER STEEL STRUCTURE 6-Sep-10 532 START OF ERECTION OF BOILER STEEL STRUCTURE TG BED PLATE POSITIONING (START) 15-Nov-10 602 DCS CHARGING 17-Mar-11 724 CHIMNEY OUTER SHELL COMPLETION 18-Apr-11 756 GENERATOR STATOR POSITIONING 24-May-11 792 2-Jun-11 801 COMPLETION OF BOILER HEATING SURFACE ERECTION 28-Jun-11 827 BOILER HYDRO TEST COMPLETION 18-Aug-11 878 (29 months) START UP POWER (BACK ENERGISATION) 24

MILESTONE DATE TIME (Days) w.r.t. NTP TG BOX-UP 20-Aug-11 880 DM WATER GENERATION 27-Aug-11 887 COMPLETION OF CHEMICAL CLEANING OF BOILER 20-Nov-11 972 COMPLETION OF TG OIL FLUSHING 23-Nov-11 975 COMPLETION OF BOILER INSULATION WORKS (only to support steam blowing) 30-Nov-11 982 BOILER LIGHT UP 7-Dec-11 989 (33 months) START OF STEAM BLOWING (on Coal firing) 8-Dec-11 990 COMPLETION OF STEAM BLOWING 19-Dec-11 1001 (33.4 months) SYCHRONIZATION & TRIAL OPERATION 11-Jan-12 1024 (34 months) ACHIEVE FULL LOAD 12-Jan-12 1025 (34 months) COD AS PER PPA 22-Jan-12 1035 (34.5 months) COD 29-Mar-12 1102 (36.7 months) 25

Achievements Project completed within schedule and budget Achieved synchronization of Ist Unit within 34 months of the Notice to Proceed (NTP) Achieved Unit full load within 27 hours of first synchronization 26

Awards & Recognitions ECB financing for the Project received the prestigious Indian Deal of the Year 2010 award from Project Finance International Indian Power Deal of the Year 2010 award from Euromoney CNBC TV18 s Infrastructure Excellence Award for the Year 2012 (Energy & Power Category) 27

The Journey continues