Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013
Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project Overview (review purpose, goals & scope) Developments since last public meeting Construction Construction phasing\sequence, Staging Areas Hours of work Mitigation of Impacts Communications program Contact Information
Design-Build Team Construction Contractors: Walsh Construction and McCourt Construction formed the Walsh-McCourt Joint Venture (JV1) With lead designer subconsultant HNTB Corporation Specialty Subconsultants include: Green International Affiliates, Inc. Survey, drainage, structural design Shadley Associates, P.C. Landscape Architecture Regina Villa Associates, Inc. Public outreach Public Archaeology Laboratory - Cultural resources Genesis Structures, Inc. Erection & demolition engineering
Current Project Schedule
DESIGN Project Overview & Design Developments
Project Description & Purpose Replace the structurallydeficient John Greenleaf Whittier Bridge carrying I- 95 over the Merrimack River Improve I-95 from Exit 57 (Rte. 113) to Exit 60 by widening the roadway, improving ramp geometry, upgrading drainage & lighting systems
Project Goals Improve safety Provide bridge that meets all current standards Improve traffic flow Improve air quality by reducing congestion Support non-motorized modes of transportation
Overall Project Map
New Whittier Bridge WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Network tied arch main spans Two new parallel structures, each carrying 4 lanes plus shoulders Shared Use Path (SUP) on NB structure with connections along approaches
Shared Use Path
Pine Hill (Ferry Rd) Bridge
Evans Place (Main St) Bridge
Rte. 110 Bridge
Abandoned RR Bridges
Design Changes & Refinements Since Last Public Meeting CCTV Cameras along SUP Evans Place Bridge - Alternative Superstructure Type & Span Whittier Bridge Pier Configuration Transparent barrier on NB Whittier SUP barrier Proposal to replace existing fan wall with new modular wall
Base Technical Concept Pier Configuration Piers with vertical columns and arch supported on cantilevered cap beam
Revised Pier Design WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Piers with sloping columns to provide support directly beneath arches
Transparent Fence on Shared Use Path Barrier on the Whittier Bridge
Relocation of Existing Wall adjacent to Laurel Road WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT
Existing Fan Wall Adjacent to Laurel Road
Comparision of Alternatives
Retaining Wall Finish WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT
CONSTRUCTION Phasing/sequence, Hours of Work, Mitigation of Impacts
Construction Construction Phasing/Sequencing Staging Areas Hours of Work Mitigation of Impacts a. Traffic\Real Time Traffic Management System b. Environmental c. Construction Noise d. Navigation channel
Traffic Maintenance Requirements I-95 NB & SB 3 lanes to be provided during peak travel times For I-95 NB: a. Single lane closure, Monday-Thursday 7:00 PM 5:00 PM b. Two lane closure, Monday-Thursday 10:00 PM 7:00 AM For I-95 SB: a. Single lane closure, Monday-Thursday 9:00 AM 6:00 AM b. Two lane closure, Monday-Thursday 9:00 PM 6:00 AM No lane closures during holiday weekends and summer weekends
Route 110 Single lane closure allowed: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Traffic Maintenance Requirements, cont d Monday-Friday 9:00 AM 3:00 PM Monday-Thursday 8:00 PM 6:00 AM All weekend (Saturday & Sunday) & holiday closures require MassDOT approval Evans Place Alternating traffic (with flaggers) allowed: Monday-Friday 9:00 AM 3:00 PM Route 110/I-95 NB On-Ramp Shall remain open between Memorial Day & Labor Day Pine Hill Road Alternating traffic in single lane, using temporary traffic signals, until new bridge constructed (There will be exceptions to the above, which will require MassDOT approval & public notifications will be issued prior to any changes)
Real Time Traffic Management System
Real Time Traffic Management System
Erection of the Whittier Bridge Approach spans become supply path for arch erection
Erection of the Whittier Bridge Arch deck erected with Mi-Jacks Arch ribs erected with small cranes
Erection of the Whittier Bridge Approach spans Mi-Jacks Arch span Mi-Jack, cranes
Erection of the Whittier Bridge Approach spans become supply path for arch erection
Erection of the Whittier Bridge Arch deck erected with Mi-Jacks Arch ribs erected with small cranes
COMMUNICATIONS PROGRAM
Communications Program Update stakeholders on project progress Website E-blast updates/advisories Social media Press advisories Business coordination, as necessary Abutter/coordination meetings and briefings as necessary
Project Website WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT
Project Contact Information Project website: www.mass.gov/massdot/whittierbridge Stephanie Boundy, MassDOT Public Outreach Coordinator e-mail: Stephanie.Boundy@state.ma.us office phone: (857) 368-8904