Laker Hall Program Study Intercollegiate Athletics. Preferred Concept & Project Phasing SUCF Project No

Similar documents
SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

date: 10 july 2012 the pennsylvania state university: burrowes building

Capital Projects Update

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015

Building Expansion Project Description. Rutgers The State University of New Jersey

College of the Desert Athletics Facilities

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

Minuteman Regional Vocational Technical School

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

School of Business Project # Overall Project Cost: $26,700, Architect: Urbahn. Scheduled Completion Date: 10/2014.

Becker Morgan Group, Inc. (architectural and site systems) Gipe Associates, Inc. (mech./elec./plumbing systems) Morabito Associates, Inc.

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS

ADDISON ATHLETIC CLUB. Master Plan Update

Space Program & Concept Design

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

Longmeadow High School Project. Public Forum April 08, 2010 LHS Cafeteria

NEIDIG ELEMENTARY SCHOOL ADDITION & RENOVATION PHASING. Neidig Community Meeting July 2018

NEW MIDDLE SCHOOL PROJECT

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

Assessment Report Burgess Park Gymnasium. Summary

TABLE R (5/97) CAPITAL PROJECT INFORMATION AND JUSTIFICATION SHEET CIP-Attachment 2

BALLOU SENIOR HIGH SCHOOL

LUFacilities Policy Service Level Agreement v1.1

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

BARNARD ELEMENTARY SCHOOL

Building Area Definitions Authored by: The Office of Space Management and Analysis

KENTUCKY STATE UNIVERSITY

Al Behrman Elementary School

APPENDIX A DEFINITIONS OF BUILDING AREAS

FACILITY COMPONENTS - ELEMENTARY SCHOOL

DIXON RECREATION CENTER SUSTAINABILITY FEATURES

BENSON CITY HALL/POLICE DEPARTMENT FACILITY ASSESSMENT AND FEASIBILITY STUDY

Use and Finance Bi-Annual Reporting Form

BOARD OF TRUSTEES OCTOBER 13, 2014

CONSOLIDATED DESIGN PRESENTATION (UP TO 18 September 2012)

University of North Florida BOARD OF TRUSTEES. CAMPUS PLANNING, DESIGN & CONSTRUCTION CAPITAL PROJECTS UPDATE January 18, 2011

Facility Improvements

Bronx Community College. Five-Year Capital Plan FY through FY

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Facilities Master Plan State University of New York College of Technology at Delhi

Evansville Public Schools. Facility Assessment Report January 28, 2 , General Building Data

GFW Schools Task Force Meeting 1/23/19 R.A. MORTON & ASSOCIATES GLT ARCHITECTS 1

Schematic Design D ecember 2018

ROD Grant Round 4 Presentation June 9, 2014

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Wissahickon School District Natatorium & Central Plant Project. Project Update March 27, 2017

School Without Walls

School Board Approved Capital Improvements Program. Fiscal Years

MAURY ELEMENTARY SCHOOL

Timberglen Recreation Center Summary

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923

East Los Angeles College Project Priority List Occupancy Date


SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

PHYSICAL EDUCATION September 30, 2010

GARFIELD ELEMENTARY SCHOOL

NORTHEAST IOWA COMMUNITY COLLEGE 2018 FACILITY ASSESSMENT MAY 15, 2018

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

Facilities Feasibility Study Frederick Douglass HS Condition Assessment

CENTENNIAL SCHOOL DISTRICT

facilities plan community input session Transylvania County Schools

Project Information. Nominations of Artists. University of Houston

Draft Feasibility Study for the Expansion of Southeast Library

CITY OF NOVI. Police Department

Section 4 - Design and Construction Overview

School Assessment Report

Lake Highlands North Recreation Center Summary

CONSTRUCTION UPDATE. April 2017 THIS IS PROGRESS. THIS IS AUBURN.

FACILITY COMPONENTS - ELEMENTARY SCHOOL

Long Bridge Park County Board Work Session

Corsicana High School

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

COOLIDGE SENIOR HIGH SCHOOL

Final Report. Community Recreation Inventory Beaver Creek. Capital Management Engineering Limited. April 2016 Project Number

FUTURE BOND PROGRAM PROPOSED PROJECTS Summary Report. September 2013

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016

Program Update. Chino Health Science Parking Lot

Building Condition Report. Building Condition

Juanita High School Modernization vs. New-in-lieu of Modernization Report

LOVEJOY Independent School District

Refer to Sheet A-203 and modify Floor Plan Demolition Keynote #23 as follows:

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement

,A MULTIPURPOSE FACILITY FOR NOVAGGIO, SWITZERLAND/ by Allan William Kehrt

Prepared By Construction Manager September 2011

BUILDING FOR OUR FUTURE

Building Standards Department. Guide to Building Permits Understanding the Different Building Permit Types and their Submission Requirements

PACKAGE 3 ELEMENTARY AND MIDDLE SCHOOLS IMPROVEMENTS REPORT December 2015 Issue 1

NYC Department of Education

WARREN CONSOLIDATED SCHOOLS 2016 BOND PROJECT UPDATE M a y

Andover Schools Facilities Update

STATE UNIVERSITY CONSTRUCTION FUND

DAVIS ELEMENTARY SCHOOL

Cherry Hill School District Building Project Summary. August 8, 2018

STUART-HOBSON MIDDLE SCHOOL

Superintendent Proposed Capital Improvements Program. Fiscal Years

Capital Projects Update

Health Life Safety Survey and Master Facilities Plan

The Creative and Performing Arts High School (CAPA) Pittsburgh, PA 9/30/2002 Andrew Tech Mechanical Option Prof. S. A. Mumma

Transcription:

Laker Hall Program Study Intercollegiate Athletics Preferred Concept & Project Phasing SUCF Project No. 101009 26 January 2017

Agenda Preferred Concept - Existing Site Plan - Existing Floor Plans - Space Program Summary - Proposed Floor Plans Phasing Summary - Project Priorities - Project Phasing Cost Estimates - Square Foot Costs - Other Costs - Single-Phase Project - Phased Renovation (Options 1 & 2) Future Considerations Next Steps

Preferred Concept

Existing Site Plan

Existing Floor Plans

Existing Floor Plans

Existing Floor Plans

Space Program Summary Space Type Existing NASF Proposed NASF Preferred Option NASF Delta Existing NASF Delta Proposed NASF Activity/Competition 57,884 54,147 54,222 (3,662) 75 Administration 6,973 8,208 8,996 2,023 788 Coaching Staff 3,730 5,164 5,340 1,610 176 Locker Rooms 13,745 16,990 16,145 2,400 (845) Sports Medicine 2,533 2,533 2,533 0 0 Storage/Support 10,440 7,699 7,868 (2,572) 169 Total 95,305 94,741 95,104 (201) 363 Future Space = 310 NASF

Space Program Summary Activity/Competition NASF Existing 57,884 Proposed 54,147 Preferred Option 54,222 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 45,000 50,000 55,000 60,000 Administration NASF Existing 6,973 Proposed 8,208 Preferred Option 8,996 Coaching Staff Existing 3,730 Proposed 5,164 Preferred Option 5,340 Locker Rooms Existing 13,745 Proposed 16,990 Preferred Option 16,145 Sports Medicine Existing 2,533 Proposed 2,533 Preferred Option 2,533 Storage Existing 10,440 Proposed 7,699 Preferred Option 7,868 2,000 4,000 6,000 8,000 10,000 12,000 14,000 16,000 18,000

Proposed Floor Plans

Locker Rooms

Proposed Floor Plans

Proposed Floor Plans

Office Suite

Phasing Summary

Project Priorities Building Systems - Replace Mechanical Equipment - Provide Air-Conditioning Basement Level Renovations - Home Team Locker Rooms - Fitness Center - Laundry/Equipment Room - Visiting Team Locker Rooms Second Floor Renovations First Floor Renovations Building Exterior

Project Phasing Phase 1: 18 Months Phase 2: 12 Months Phase 3: 18 Months Phase 4: 12 Months

Underutilized Space - General Locker Rooms - Wrestling Hot Room - Central Storage - Racquetball Courts - Squash Courts - Student Lounge - Staff Lounge - Classroom

Temporary Storage Space - Equipment storage temporarily moves to Squash Court 102

Mechanical Space - Replace mechanical equipment (size systems for new building layout) - Install new electrical service and generator - Install new sprinkler service and fire pump - Optional: Install air-conditioning

Phase 1A - Office and support space temporarily moves to Student Lounge 210 - Equipment storage temporarily moves to Squash Courts 103 & 104 - Fitness Center and Physical Fitness Room temporarily move to Auxiliary Gym 108 - Computer Room/Study Room temporarily move to Classroom 216 - Athletic Communications temporarily moves to Faculty Lounge 204

Phase 1B - Provide new floor structure to infill first floor racquetball courts - Provide new windows in exterior walls - Expand Fitness Center - Renovate portion of basement, first floor, and second floor - Maintain access to stair and elevator during construction

Phase 2A - Fitness Center and Physical Fitness Room move to permanent space in basement - Team locker rooms move to temporary and permanent space in basement - General locker rooms move to permanent space on first floor - Office and support space moves to temporary and permanent space on second floor - Utilize general locker rooms for visiting teams during next phase of construction

Phase 2B - Install new elevator adjacent to north entrance - Renovate portion of basement for locker rooms and instructional space

Phase 3A - Classroom 207 moves to permanent space in basement - Equipment storage and team locker rooms move to permanent space in basement - Pool Office and Pool Storage temporarily move to student lounge - Utilize general locker rooms for swimming and diving during next phase of construction - Utilize staff locker rooms for visiting teams during next phase of construction

Phase 3B - Provide new floor structure to infill first floor squash courts - Provide new windows in exterior walls - Renovate portion of basement, first floor, and second floor - Maintain access to north entrance and elevator during construction

Phase 4A - Computer Room/Study Room to move to permanent space on first floor - Team locker rooms to permanent space on first floor - Pool Office and Pool Storage move to permanent space on first floor - Office and support space move to permanent space on first and second floor - Provide temporary space for remaining second floor offices

Phase 4B - Renovate lobby and toilet rooms (two phases may be required to maintain egress from gymnasium, swimming pool, and locker rooms) - Reconstruct existing light wells and provide skylights into lobby - Provide interior windows into gymnasium and swimming pool - Renovate portion of second floor for office and support space

Scope of Work - Major Renovations: 70,700 GSF - Minor Renovations: 56,270 GSF - Replace Mechanical Equipment and Install Sprinkler System: 7,820 GSF - Install Sprinkler System Only: 17,410 GSF

Cost Estimates

Square Foot Costs Infill Racquetball/Squash Courts Fitness Center Instructional Space Office and Support Space Locker Rooms/Toilet Rooms Circulation Space Mechanical System Sprinkler System Hazardous Material Abatement $250/SF $115/SF $140/SF $155/SF $325/SF $90/SF $55/SF $5/SF $12/SF

Other Costs Reconstruct Light Wells New Skylights New Elevator Replace Wall Panels New Windows @ North Wall New Windows @ South Wall Interior Windows @ Gym and Pool Reinforce Roof for Mech. Equip. New Electrical Service $208,000 $151,000 $275,000 $168,000 $20,000 $34,000 $25,000 $50,000 $375,000

Window Alternates Phase 1: Provide windows for men s lacrosse, women s lacrosse, cross country, and track and field Phase 3: Provide windows for Director, Associate Director, Assistant Director, reception area, waiting area, and community service office

Window Alternate #1 Add $40,000

Window Alternate #2 Add $205,000

Window Alternate #3 Add $525,000

Single-Phase Project Major Renovations Minor Renovations Escalation (June 2019) Construction Cost Soft Costs (35%) Project Cost $17,674,000 $3,843,000 $1,614,000 $23,131,000 $8,096,000 $31,227,000* * Does not include window alternate

Phased Renovation: Option 1 Phase 1 Phase 2 Phase 3 Phase 4 Additional Work Project Cost $7,323,000 $6,871,000 $6,012,000 $5,829,000 $11,290,000 $37,325,000* Each phase includes escalation, phasing premiums and soft costs * Does not include window alternate

Phased Renovation: Option 2 Install Air-Conditioning Phase 1 Phase 2 Phase 3 Phase 4 Additional Work Project Cost $7,480,000 $6,504,000 $6,752,000 $5,843,000 $5,395,000 $11,612,000 $43,586,000* Each phase includes escalation, phasing premiums and soft costs * Does not include window alternate

Cost Summary Single-Phase Project Phased Renovations: Option 1 Phased Renovations: Option 2 Project Cost $31,227,000 $37,325,000 $43,586,000 Delta $6,098,000 $12,359,000

Future Considerations

Future Considerations As part of the future design project, detailed construction phasing plans will be developed that include: - Contractor Staging - Egress Requirements - Location of Temporary Construction Walls - Mechanical System Phasing This program study assumes that the number of athletic teams remains constant it will need to be adjusted if the number of teams changes The College should consider increasing the size of the generator to include additional life safety loads (fire alarm system, egress lighting) and standby loads (IT, HVAC) A comprehensive hazardous materials survey should be completed prior to the work

Next Steps SUCF & SUNY Oswego Review Prepare Draft Report - Building Condition Assessment - Summary of Programming Interviews - Proposed Space Programs - Proposed Floor Plans - Phasing Strategy - Cost Estimates SUCF & SUNY Oswego Review Prepare Final Report