Honeysuckle Reservoir decommissioning

Similar documents
Application for resource consent Form B Damming and diversion of water

Temporary Watercourse Crossing: Culverts

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

These potential changes and their implications are outlined in Annex 1.

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

Department of the Army Permit Application

E7. Taking, using, damming and diversion of water and drilling

Filter Tube Barriers (Instream)

South St. Vrain / Hall Meadows Restoration Planning August 20, 2015

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Municipal Class Environmental Assessment for Pottersburg Creek Slope Stability Study South of Hamilton Road, Schedule B

SCOTTISH ENVIRONMENT PROTECTION AGENCY PREVENTION OF POLLUTION FROM CIVIL ENGINEERING CONTRACTS: GUIDELINES FOR THE SPECIAL REQUIREMENTS

Welcome to the Boulevard Lake Dam Class Environmental Assessment. Public Information Session #1. June 14, 2016

REROUTING DRAINAGE SYSTEMS

1. The impacts of development and settlement intensification on biodiversity and Aboriginal cultural heritage;

Works, services and infrastructure code

Identifying low risk climate change adaptation:

Port of Brisbane Stormwater Management

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods.

Understanding the State Planning Policy July 2017 Changes to state interest statements, policies and assessment benchmarks

CHAPTER 7. San Dieguito River Flooding Adaptation

TOPIC 1: WHY DO WE STUDY HYDROLOGY AND OPEN CHANNEL HYDRAULICS TABLE OF CONTENTS

Low Head Stone Weirs By: Jon Fripp 1, Dr. Craig Fischenich 2, and Dr. David Biedenharn 2

Preface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF)

6 Risk assessment methodology

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

POOL 11 ISLANDS SUNFISH LAKE AND MUD LAKE OPERATION AND MAINTENANCE MANUAL

Beds of Water Bodies 14 September 2017

Erosion & Sedimentation Control Policy

STREAMBANK RESTORATION DESIGN

Types of Hydropower Facilities

Environmental Due Diligence (EDD) Of Renewable Energy Projects GUIDELINES. for. Small-Scale Hydroelectric Energy Systems

Upper Mississippi River Conference 2016 Action Agenda: Raise the Grade

Carp Creek 2013 Summary Report

Project Goals and Scoping

Lesson 2-2: Riparian Zones

Design Specifications & Requirements Manual

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

Natural Flood Management. Measures & Multiple Benefits. Steve Rose (JBA)

1 General questions on zone and catchment management plans

AP Environmental Science

Duwamish Waterway Self Guided Tour: Turning Basin Number Three and Terminal 105 Aquatic Habitat Restoration Sites

Notice No Closing Date: May 12, 2017

Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil. Version 1.0

WATER QUALITY IMPROVEMENT PLAN CATCHMENT MANAGEMENT AREA REPORT. 19 Pioneer River Main Channel

LEGAL AUTHORITY AND JURISDICTIONS

3.0 CUMULATIVE PROJECTS SCENARIO

Blanche Park Reservoir Decision Notice and Finding of No Significant Impact

THAI-AUSTRALIAN NORTHEAST VILLAGE WATER RESOURCE PROJECT

f) Culverts in series shall be spaced at least 20 feet between each other. 2.7 C Culverts

10.19 Post-Mining Closure and Rehabilitation

VICTORIA S NATIVE VEGETATION MANAGEMENT A FRAMEWORK FOR ACTION

Murra Warra Wind Farm Project Environmental Management Plan

Aquatic Fish and Wildlife Habitat Management

Chapter 13 Private Native Forestry: River Red Gum

DEPARTMENT OF THE ARMY Wilmington District, Corps of Engineers 69 Darlington Avenue Wilmington, North Carolina April 24, 2017

United States Army Corps of Engineers. Addicks and Barker Dam Safety Update

Emergency Underwater Rehabilitation of the Poti Main Diversion Weir, Georgia

Criteria for Siting Dams

E. STORMWATER MANAGEMENT

Water of Leith catchment profile

DECISION MEMO. West Fork Blacktail Deer Creek Hardened Crossing

Overview of the Walkover Assessments conducted on the Pont and Blyth catchments

Technical and economic comparison of Taivalkoski, Ossauskoski, Petäjäskoski and Valajaskoskifish pass alternatives

LOW WATER CROSSINGS, fords, or drifts, as they

WELCOME! Mill Creek Daylighting Technical Feasibility Study. Thank you! Open House December Please sign in and get a comment form.

Information Request 37

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e)

Assessing Natural Resource Impacts from the Enbridge Pipeline Spill into the Kalamazoo River

Electricity Safety (Electric Line Clearance) Regulations 2010

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

FISHERIES AND OCEANS CANADA

Module 4. Hydraulic structures for flow diversion and storage. Version 2 CE IIT, Kharagpur

Avista Dam Relicensing Factsheet Commenting on the Draft License Application

Environmental and Social Impact Assessment for Rogun Hydro Power Plant

Construction of Artificial Riffles and Pools For Freshwater Habitat Restoration

PUBLIC NOTICE. REPLY TO: Denver Regulatory Office 9307 South Wadsworth Blvd 30 DAY NOTICE Littleton, CO FAX (303)

Doyle Park Reconstruction Project Improving Flood Control Facilities to Meet a TMDL

Sediment Basin. Fe= (Depends on soil type)

Faro Mine Remediation Project - A Risk-Based Approach to Work Planning - April, 2016

Kurnell Refinery Conversion Project

The Nore Suir River Trust Strategy Report Phase 1 Why Do The Nore and Suir Rivers Need a River Trust?

How can rivers be managed?

Living Shorelines & Coastal Resiliency: A Consultants Perspective. Presented by: Bethany Bearmore, P.E. Louis Berger

POND CONSTRUCTION. Woodland Steward Series

Geography Stage 4. Lesson plan Murky Waters

SECTION 6: MITIGATION STRATEGY

J O I N T P U B L I C N O T I C E

CHAPTER 9 DISCUSSIONS, CONCLUSIONS, AND RECOMMENDATIONS

Strickland River. ReportCard2009. Background to the first Report Card

Sediment Management Alternatives Analysis

The South Australian River Murray is a highly regulated system comprised of a series of

3 Objectives 3 Ob jec tives

Biodiversity Debate. To evaluate the biological, aesthetic, ethical, social and economic arguments with regard to maintaining biodiversity.

Murray-Darling Basin. - Objectives Hierarchy -

Conservation Practices. Conservation Choices. These five icons will show the benefits each practice offers... 6/4/2014

RIVERSIDE OXBOW FORT WORTH, TEXAS CHAPTER 3 IDENTIFICATION OF PROBLEMS AND OPPORTUNITIES

Transcription:

Honeysuckle Reservoir decommissioning Christopher Dwyer Earth Tech, PO Box 165 Wangaratta, 3676. Web: www.earthtech.com.au, Email: chris.dwyer@earthtech.com.au Abstract Often significant investment is required for the restoration of a relatively small reach of waterway. The Honeysuckle Reservoir decommissioning project at Violet Town in North East Victoria is one such example. A relatively small (120ML) on-stream storage was decommissioned in 2005 as the reservoir did not meet ANCOLD safety standards and could not continually supply a potable water supply. The project faced many technical and environmental challenges while also managing often hostile public perceptions. The design and construction process recognised the importance of maintaining the overall focus on the primary aims of the project which were to safely remove an unsafe structure, without mobilising sediment which could have a detrimental impact upon stream health downstream. At the same time the project aimed to maximise the potential to provide other stream health benefits to native fish, vegetation and platypus. The end result is a relatively small 300m restored reach of creek, with many stream health risks removed. Keywords Reservoir decommissioning, risk management, sediment mobilisation Introduction The Honeysuckle Reservoir was constructed in the early 1960 s to supply water to the town of Violet Town in North East Victoria (Figure 1). The reservoir was constructed on Honeysuckle Creek, approximately eight kilometres south east of the town, and consisted of an earthen embankment and concrete spillway. Figure 1. Locality plan. 73

In the late 1990 s the owner and manager of the reservoir Goulburn Valley Water completed a dam safety review of the structure. The review found the spillway was not large enough to satisfy ANCOLD standards; these are safety standards for large dams in Australia. Furthermore the stability of the earthen embankment did not meet ANCOLD standards. Goulburn Valley Water had also experienced ongoing water supply issues from the reservoir. The storage proved to be unreliable in the volume of water that could be stored and supplied, and the quality of water supplied often required extensive treatment. As a consequence of the non-compliance of the reservoir structure with current day standards, Goulburn Valley Water installed a piped water supply to Violet Town from nearby Euroa, following consultation with the local community. The next stage of the project was to remove the unsafe structure, and in the process ensure sediment in the base of the reservoir (Figure 2) did not pose a major risk to the local environment, or those downstream of the site. In completing the decommissioning process other stream health benefits were obtained, however the primary focus of risk minimisation was achieved. Figure 2. Honeysuckle Reservoir prior to decommissioning. Methods A number of investigations on site, and via a desk top review were undertaken to determine the most appropriate means for decommissioning the reservoir. These measures would remove the risk of the unsafe structure, minimise the risk of sediment mobilisation, and provide other stream health benefits. The findings of these investigations are summarised. Sediment survey A feature sediment survey of the site established that approximately 23,000 m 3 of sediment, was held within the bed of the reservoir. Sediment varied in depth from 0.5m to approximately 2m through the bed of the reservoir. Sediment sampling Sediment samples were taken at four sites within the reservoir area. Copper concentrations were moderate on the surface sample at each site. This may have been due to copper sulphate dosing undertaken in the past to control algal outbreaks. Samples taken at surface level showed moderate concentrations of 200mg/kg to 96mg/kg. Given all surface samples for the sediments contained moderate copper contamination remedial actions needed to be taken (ANZECC guidelines). The decommissioning process therefore provided 74

remedial actions, including removing mobile sand in the upper reach, and avoiding mobilising sediment in the lower reach. Feature survey The stream bed upstream and downstream of the structure has a grade of approximately 100:1. Replicating this grade through the existing reservoir necessitates the construction of several grade control structures along the reconstructed bed, maintaining the bed in a stable condition and providing pool riffle sequences. Fish populations likely to be present within and in the vicinity of the Reservoir A fish survey was undertaken to collect baseline data on species presence and relative abundance. Galaxia and Blackfish were recorded upstream and downstream of the reservoir while a community of Australian Smelt were recorded downstream of the reservoir, but not upstream of the reservoir. Of the species recorded from Honeysuckle Creek in the present survey, only Australian Smelt are migratory. The removal of the Honeysuckle Reservoir therefore allows Smelt to freely pass along the stream and reunites gene pools of Blackfish and Galaxias. Other native fauna likely to be present within and in the vicinity of the Reservoir Although not endangered Platypus were anecdotally known to be present at the site. Ballarat University was engaged to establish the existence of platypus and to assess the potential impact of the removal of the weir pool on platypus, and to identify potential benefits that could be gained from the decommissioning process. Although burrows were found, no platypus was seen at the site. The main findings were the removal of the reservoir would maintain water levels at a constant elevation year round, benefiting species, in particular platypus. Site constraints When considering options for the actual decommissioning of the reservoir, the site posed a number of problems regarding silt location and other geographical features. These constraints included: The contaminated silt in the vicinity of the embankment was wide in area and deep. Removal or relocation within the reservoir would be difficult. The embankment had a limited volume of fill which could be utilised to build bunding walls should they be utilised. There were limited sites available within the reservoir to store embankment fill and silt. Mobilisation of any sediment would have an adverse impact on Honeysuckle Creek downstream, as such any structure had to hold silt in place. If it were to be mobilised this could only be at a time when the sediment could be diluted such that would have a minimal impact downstream. Design options considered Four options were considered for the decommissioning of the reservoir. Each option aimed to satisfy each of the two main criteria: Remove the existing reservoir safety risk. Have no negative impact on Honeysuckle Creek downstream (i.e. no sediment mobilisation). Additional benefits were then also considered: Leave a regime in place that will require minimum maintenance. Provide a regime that will encourage ecosystem diversity (including the provision of fish passage). Minimise the cost of decommissioning. The following options for decommissioning were considered: Option 1 Recreate original low flow channel via silt removal and rock chutes. 75

Option 2 Recreate low flow channel using bunding walls. Option 3 Leave a low level pool in the vicinity of the existing embankment. Option 4 Scour silt from reservoir through water regime management. Option four was finally agreed upon as it was the option that best satisfied all criteria. Results Detailed design then proceeded with the final design consisting of a number of innovative features. In the vicinity of the former embankment, a 96m long by 27m wide rock chute was constructed. This chute was designed to withstand a 100 ARI flood event. In the occurrence of a larger flood event some damage to this chute could be expected. In this instance the mobilisation of sediment could occur. Sediment transport analysis was undertaken which determined under such an event sediment would become highly diluted, with most sediment dropping out on floodplains where the impact of sedimentation would be negligible. A rock fishway was incorporated into the main chute to facilitate fish passage upstream. The chute consists of continuous vee shaped arrangements down the fishway. Each vee diverts flow to the outside of the channel, reducing velocity and creating resting pools. The fishway is approximately 100m in length, and drops 6m; it provides a number of resting points, low velocity zones and on average approximately 30cm depth of flow. As such the fishway is designed to provide passage for both large and small bodied fish. Three smaller chutes are located upstream of the low level pool created by the main chute. The site was revegetated, with wetland planting a feature around the low level pool. The construction of the main chute necessitated the removal of several mature native trees. The revegetation of the site provides adequate vegetation Net Gain to compensate these losses. Given the Honeysuckle Creek catchment consists of highly erosive granitic material, it is anticipated the low level pool will silt up in the longer term. The volume of sediment in and out of the former reservoir area should then balance. No formal monitoring has occurred since the completion of the project. In the longer term the authority may elect to undertake monitoring to assess the success of fish passage through the fishway, as well as ongoing water quality changes. Figure 3. Commencing the embankment removal Figure 4. Embankment with initial breach in place 76

Discussion Following the completion of the detailed design, approval for the decommissioning works was provided by the licensing authority Goulburn Murray Water. Approval for the vegetation removal was sought from Strathbogie Shire. The decommissioning process was also supported by the Victorian government through the Department of Sustainability and Environment. Such was the discontent in some community quarters, regarding the removal of a reservoir, the native vegetation removal was challenged at the Victorian Civil and Administrative Tribunal (VCAT). This challenge to the project at VCAT demonstrated the importance of establishing the primary aims of the project and secondary benefits; it also revealed the importance of thorough planning and following statutory process. While opponents aimed to discredit the project on several fronts, the proposed Honeysuckle Reservoir decommissioning project was able to proceed. Construction works proceeded largely without issue. The material in the embankment was relocated on site to a stockpile above the 100 year ARI flood level. The main challenge was to remove the embankment (Figure 3), while maintaining flows down Honeysuckle Creek. Given the large catchment area and the propensity of the site to flooding and water logging, a five day window of opportunity with dry weather was found when the embankment was breached, with flows then allowed to pass over the main chute (Figure 4). Conclusion When undertaking major risk management activities on, or in the vicinity of waterways it is important to keep the key focus of the project on the major risks to be managed. In the case of the Honeysuckle Reservoir decommissioning some stream health benefits have been achieved in the form of: Localised improvement in fish passage (a barrier remains downstream) (Figure 5). Localised improvement in riparian vegetation via revegetation (poor riparian vegetation exists upstream and downstream of the site) (Figure 6). Improved platypus habitat via more consistent water levels (Centre for Environmental Management University of Ballarat, 2004). In excess of $500,000 of works were invested in removing the structure and rehabilitating 300m of creek. Importantly in this instance the cost of the project should be measured by the risk removed, rather than simply the measurable improvements to stream health. Figure 5. Main chute with completed fishway. Figure 6. Revegetation 2007. Acknowledgments This project was fully funded and undertaken by Goulburn Valley Water. 77

References Centre for Environmental Management University of Ballarat (2004). Honeysuckle Creek Reservoir Platypus Survey. University of Ballarat, Victoria. Earth Tech (2002). Honeysuckle Reservoir Decommissioning Stage 1 - Pre Decommissioning Ecological Assessment of Honeysuckle Creek. Earth Tech (2003). Honeysuckle Reservoir Decommissioning Stage 2 - Silt Survey and Ancillary Works. Earth Tech (2004). Honeysuckle Reservoir Decommissioning - Native Vegetation Removal Report. Earth Tech (2005). Honeysuckle Reservoir Decommissioning Construction Management Plan. Hydro Tasmania (2000). Honeysuckle Creek Review. ID&A (1999). Honeysuckle Reservoir Decommissioning Impact Study Preliminary Investigation. Marine and Freshwater Research Institute Snobs Creek (2002). Honeysuckle Creek Fish Survey Report. Sinclair Knight Merz (1996). Violet Town PMF Assessment Preliminary Assessment of Spillway Adequacy for Honeysuckle Creek Storage, Version 1. 78