KENTUCKY STATE UNIVERSITY

Similar documents
WESTERN KENTUCKY UNIVERSITY

East Los Angeles College Project Priority List Occupancy Date

Frost Technical Center

MOORESTOWN HIGH SCHOOL REFERENDUM PROJECTS

Bronx Community College. Five-Year Capital Plan FY through FY

School Assessment Report

Becker Morgan Group, Inc. (architectural and site systems) Gipe Associates, Inc. (mech./elec./plumbing systems) Morabito Associates, Inc.

3 CUMULATIVE METHODS AND PROJECTS

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

Architectural Services Consultant Registration Form

SEATON ELEMENTARY SCHOOL

NALLE ELEMENTARY SCHOOL

Borough President and City Council Capital Funding Requests FY 2008

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

BALLOU SENIOR HIGH SCHOOL

EASTERN HIGH SCHOOL. Site Plan East Capitol Street, N.E., Washington, DC INITIAL YEAR BUILT 1923

BOARD OF TRUSTEES OCTOBER 13, 2014

Auburn University Construction Project Update March 2010

The Total Cost of Ownership (TCO) is the total of all costs generated over the useful lifespan of the facility (30-50 years).

MIRACOSTA COMMUNITY COLLEGE DISTRICT

CONSTRUCTION UPDATE. April 2017 THIS IS PROGRESS. THIS IS AUBURN.

Laker Hall Program Study Intercollegiate Athletics. Preferred Concept & Project Phasing SUCF Project No

CONSTRUCTION UPDATE. April AUM Projects. Client: Housing and Residence Life Construction Cost: $28 million Completion Date: July 2013

DRAFT September 26th, 2003

Campus Improvement Review

SUNY Hospitals & A Healthier New York. Capital Briefing March 1, 2013

Program Update. Chino Health Science Parking Lot

SHEPHERD ELEMENTARY SCHOOL

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement

Cultural Facilities: Capital Needs Inventory and Priorities. Arts, Culture and Libraries Committee October 17, 2016

Scripps Ranch High School

CONSTRUCTION UPDATE SEPTEMBER 2015 THIS IS AUBURN.

Juanita High School Modernization vs. New-in-lieu of Modernization Report

School Assessment Report

/ Policy Number: Policy Name: Capital Planning and Development Processes Definitions

Stephen F. Austin State University Board of Regents - Building and Grounds Committee Construction Update July 23, 2018

DENNIS TOWNSHIP FEASIBILITY STUDY

WCU 1. Reports for Committee Members/University Campuses

Attachment A Master Plan Scope Matrix

PLUMMER ELEMENTARY SCHOOL

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015

Capital Projects Update April 18, 2018 CALIFORNIA STATE UNIVERSITY, CHICO

LEWIS ELEMENTARY SCHOOL

Corsicana High School

Cupertino Union School District

WILKINSON ELEMENTARY SCHOOL

Hinsdale Township High School District 86 Referendum Project Listing April 2, Approved

Mount Vernon Elementary School Grades PK 5

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

Capital Project Recommendations Presented to the Board of Education 9/23/2014

Major Project Request Biennium

LECKIE ELEMENTARY SCHOOL

BARNARD ELEMENTARY SCHOOL

School Assessment Report

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

Measure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014

School Assessment Report

Board Report. Bond Program Update:

Office of Planning, Design and Construction. Capital Program Update May 10, 2017

Belington Elementary School Grades PK 5

Governing Board Capital Construction Program Annual Workshop September 10, 2013 Agenda

FACILITIES UPDATE REPORT

Collins Middle School

Facilities Feasibility Study Frederick Douglass HS Condition Assessment

NOYES EDUCATION CAMPUS

EDUCATIONAL PLANT FIVE YEAR SURVEY REPORT

School Assessment Report

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

BOND CONSTRUCTION UPDATE

DEL MAR UNION SCHOOL DISTRICT BOND PROJECT DESCRIPTION

DAVIS ELEMENTARY SCHOOL

Business Affairs Committee Dobo Recovery Update. February 7, 2019

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

SOUTH DAKOTA BOARD OF REGENTS. Committee on Budget and Finance ******************************************************************************

Creative Performing Media Arts Middle School

SOUTH DAKOTA BOARD OF REGENTS. Budget and Finance ******************************************************************************

RAYMOND EDUCATION CAMPUS

July 1 September 30, 2008

CAPITAL OUTLAY APPROPRIATIONS SINCE as of December 7, 2017

Project Information. Nominations of Artists. University of Houston

SANTA ANA COLLEGE FACILITIES COMMITTEE MEETING OCTOBER 18, 2016

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

MIAMI DADE COLLEGE WOLFSON CAMPUS REMODEL & RENOVATION PROJECT FOR THE DAVID W. DYER FEDERAL BUILDING AND UNITED STATES COURTHOUSE MIAMI, FLORIDA

School Assessment Report

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

to a new facility will allow renovation of existing hospital space for expanded medical research and patient care.

LASALLE - BACKUS EDUCATION CAMPUS

Grossmont-Cuyamaca Community College District Facilities Construction Update

SYCAMORE HALL RENOVATION

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

School Assessment Report

Hartsville Area Schools - Building Evaluations

LOVEJOY Independent School District

RATIONALE AND REASONING

Semi-Annual Report. January 1, 2012 June 30, 2012

Edmonton Public School District No. 7

Madison School District. Strategic Five-Year Facility Maintenance Plan

FREMONT UNIFIED. Thornton Middle School Conversion S C H O O L D I S T R I C T. Quattrocchi Kwok Architects. Sept 26, 2018

CORVALLIS SCHOOL DISTRICT Long-Range Facility Master Plan. Community Information Meeting

Transcription:

KENTUCKY STATE UNIVERSITY Proposed Projects Involving the State General Fund (cash or bonds)* Priority Project Title / Description Total Budget 2004-2006 1 Hathaway Hall Renovation Phase II $11,200,000 Completion of current project titled "Hathaway Hall Renovation". Original project funds were based on only partial renovation of this, our major classroom building. Complete renovation of space and HVAC systems is programmed for this 66,257-ft building. The original 3$.7 million Phase I project would have only renovated 25,454 ft or 38% of total building (HVAC systems and offices). This Phase II project will complete the total building renovation that is so necessary to meeting student educational needs for the units of Liberal Arts, Education, Computer and Technical Sciences, Social Work and Criminal Justice, Americorp National Service Program, Behavioral and Social Science, Literature Language and Philosophy, Communication Skills and other student service and academic programs. An additional 6,000 s.f. is also proposed to infill existing space on the basement level of the building. 2 Renovate Young Hall $10,282,000 Entire building needs complete architecture, electric, and mechanical renovation. Completely replace plumbing and HVAC. Renovation to improve student living spaces, add study rooms on each floor and an addition of an elevator. 3 Bradford Hall Structural Repair $900,000 Structural study and correction of masonry cracks and floor slab settlement is underway to establish full scope of work for the structural repair project for Bradford Hall. Significant cracking and settling has been observed and damages continue to be incurred. Immediate remedy is required once the full extent of the scope has been determined. 4 Expand Business Wing & Renovate Bradford Hall $25,000,000 This project is a building renovation and addition to further accommodate the needs of the Business and Fine Arts programs. Due to expanding program requirements of the Fine Arts Programs and the Business Programs additional square footage is required for co-locating units so that programmatic needs of both units can be met. 5 Extend Fiber Network to South Campus $839,000 Install permanent underground fiber optic cable to far south side of campus. Project involves trenching for a considerable distance plus crossing a railroad and blue line stream to reach the desired locations. 6 Implement Smart Card Technology $1,165,000 Implement smart card technology for student services and educational delivery (e.g., debit and smart card system, registration, grades and transcripts, account balances, etc. Incorporate and use smart card or one card technology in the delivery of services to enrolled students. The card will be used for building access, food service, photocopy duplication, lab use and a host of other services that are available today using a smart card system. 7 Add New Chiller $2,392,000 Add an additional chiller and cooling tower in the central plant and replace an existing chiller. Replacement chiller will bring the University into compliance with the CFC laws and reduce the operating costs of the central plant. Another chiller will increase the plant's capacity to that recommended in a 1994 study of the central plant. 1

Priority Project Title / Description Total Budget 8 Hill Student Center 3rd Floor Build-out $600,000 This project consists of the complete build-out and furnishing of "white-box" (unfinished space) within the renovated Hill Student Center. This space was planned to be completed, but funding did not allow it at bid time. The approximate square footage is 2,800 s.f. 9 Hill Student Center Addition Phase II $5,450,000 This project will include completion of the Phase I Renovation Addition, now being referred to as Phase II. Architectural Consultants estimate of cost associated with original program requirements exceeded the approved funds. This project will allow completion of original program. Addition will include an enlarged Ballroom and Theatre with additional dining/meeting rooms. 10 Roof Repairs & Replacement Exum/Combs/ Bell Gym $900,000 Roof repair and replacement of older and deteriorating roofs. 2006-2008 Business Software Upgrade/Migration $3,000,000 Business Software Upgrade/Migration Kentucky State University will be looking to move its business operations to a client server business processing model. Construct Whitney Young Leadership Building $10,400,000 Additional space (60,000 s.f.)is required for Leadership Studies College, which includes the Honors program, Liberal Studies, Integrative Studies and the Endowed Chair in the Humanities. Decentralized functions will be combined into a single facility. Enhance Distance Education $583,000 Enhance Distance Education through acquisition of enhanced servers and software which will generate more distance courses. Establish continuous training opportunities for faculty to make use of distance learning software tools. Expand & Renovate Betty White Nursing Building $4,450,000 This project will provide formally designated space for the Nursing program. The available space is inadequate and not well designed for the needs that are required by the Nursing program. This project would provide adequate program space by means of the addition and renovation of existing space to serve the administrative needs. Hathaway Hall Tech. Enhancements $600,000 Add electronic classroom instructional technology to all classrooms in Hathaway Hall. Network Infrastructure Upgrade $1,200,000 This project entails replacing all network hubs, switches and network servers throughout campus and installing upgraded network switches with multiple capability of transmitting data, voice and video. Renovate Bell Gym $3,952,000 Complete renovation of existing building to accommodate student needs. Renovate Jackson Hall $1,356,000 Complete architectural and HVAC renovation of an existing historical structure. 2

Project Title / Description Total Budget Renovate Shauntee Hall $3,314,000 Complete architectural, mechanical and electrical renovation of the existing 19,710 gsf building. 2008-2010 Campus Landscape Improvements $500,000 Landscape improvements at entrances to university, to correct temporary road at amphitheater and for campus beautification. Center for Excellence & Study of KY African Amer $10,312,000 This project will construct a facility for the study of Kentucky African Americans and other related heritages. The program housed will include art, artifacts, music, sculpture, rare documents and photographs and space for research and study. In addition, space will be provided to maintain and preserve display exhibits and offices. Construct Parking Structure $13,833,000 Construct new four story parking structure on North Campus with elevator and security office. This structure will serve several purposes, accommodating faculty/staff/student parking needs, but most specifically for community event parking. Create Pedestrian Mall $1,011,000 This project includes construction of a major plaza in the area between Bell Health Building and Hathaway Hall on the North Campus. Expand & Renovate Alumni Stadium $2,392,000 Addition of a second level on existing facility to accommodate offices and support functions of the intercollegiate athletics, including renovations to the existing facility. Expand & Renovate Jordan Maintenance $2,392,000 This project will renovate the original buildings and construct an addition to keep pace with the revitalized campus. New trade shops will be developed for welding, plumbing and carpentry. Those new features will allow the University to provide a complete service for campus buildings and other related equipment. Renovate Business Annex (SGA Bldg) $516,000 Complete renovation of interior spaces and HVAC systems for use by KSU Police Department. *Notes - Unless otherwise indicated, the total budget would be financed from the state General Fund (cash or bonds). - Priority rankings were required to be assigned only to those projects proposed for 2004-06; projects for 2006-08 and 2008-10 are listed in alphabetical order. - Descriptions are as provided in the Brief Description and Justification field of the agency s capital plan submission. 3

KENTUCKY STATE UNIVERSITY Proposed Projects NOT Involving the State General Fund* Project Title / Description Total Budget Source(s) 2004-2006 Alumni Stadium Structural Repair $400,000 RF Structural study and correction of deteriorated expansion joints in stadium grandstand and masonry of Dressing Room Bldg. Approximately 2500 lineal feet of expansion joints plus 750 lineal feet of cracks. Plus Repair/Replacement of approximately 360 lineal feet of masonry fence. Construct New Residence Hall $20,000,000 OT-LTF A new residence hall is needed for two reasons; 1) to house displaced students as a result of the Young Hall renovation, and 2)to house additional students as enrollment projections increase and the resident student population increases. An independent market analysis is being pursued to provide detailed parameters for the new facility. The new facility is anticipated to contain approximately 650 beds set up in a combination of suites and apartment layouts. The site will be on the south campus near Young Hall. Energy Savings Program $5,000,000 OT-LTF This project will perform energy saving retrofits in various campus buildings and is necessary in reducing energy consumption in campus buildings. Expand Cooperative Extension Bldg (Add'l) $3,353,000 FF A resource technology center will be built. It will be an annex to the existing Cooperative Extension Building. This authorization will allow additional funding for a currently approved project. Softball Field $500,000 RF A new field for women's softball to be on campus to comply with Title 9 requirements. Telecommunication Equip. (PBX) $1,352,000 OT-LTF New central telecommunications equipment will net savings over current system expenditures in the long term. 2006-2008 Aquaculture Pond Expansion $1,300,000 FF Expansion of the aquaculture pond facility for additional pond research. Expansion includes 24 new ponds on approximately 2 acres of land owned by the University. The project will be funded with USDA Facility Funds. Baseball Field $1,000,000 FF Replace current men's baseball field when the Aquaculture ponds expand into the existing facility. Renovate Combs Hall $3,940,000 OT-LTF Architectural renovation to improve student living space, define study space on each floor and addition of an elevator. Layout changes will include development of living suites. Complete replacement of HVAC system and plumbing fixtures is also included. 4

Project Title / Description Total Budget Source(s) 2008-2010 Renovate Hunter Hall $3,855,000 OT-LTF Hunter Hall needs a complete renovation of architectural, HVAC and plumbing. Student study room will be included on each floor. Student Living space is to be improved with renovation to suites where two dorm rooms share a bathroom. An elevator will be added. *Notes - Priority rankings were required to be assigned only to those projects proposed to be financed from the state General Fund (cash or bonds) in 2004-06; all other projects are listed in alphabetical order. - Descriptions are as provided in the Brief Description and Justification field of the agency s capital plan submission. - Sources: AB = Agency Bonds; FF = Federal Funds; RF = Restricted Funds; OT = Other Funds; TF = Road Fund 5