Feasibility Study on Pakbeng Hydropower Project

Similar documents
Profiles of 12 proposed Mainstream developments in the LMB

MRC SEA FOR HYDROPOWER ON THE MEKONG MAINSTREAM INCEPTION REPORT VOL II MAINSTREAM PROJECT PROFILE SUMMARIES 23 OCTOBER 2009

Some aspects of the sediment transit on the Mekong river in relation with hydropower development

ICEM and MRC - SEA of hydropower on mainstream Mekong River 1

Ecological effects & Hydropower dams & Transboundary river

2.16 NAM POT HYDROPOWER PROJECT

Meeting Vietnam s Energy Demands in a Sustainable Way

Report of the Mekong River Commission **

Water diversions in the lower Mekong basin current status and issues

CK Power Public Company Limited (CKP) Stable Income, Diversified Portfolio and High Growth Company

Annex 5 - Hydropower Model Vakhsh

multiconsult.no Hydropower modelling Vientiane January

EFFECTS OF UPSTREAM HYDROPOWER DAMS AND WATER DIVERSION PROJECTS TO THE DROUGHT AND SALINE INTRUSION OF THE MEKONG RIVER DELTA IN VIETNAM

The Mekong River Report Card on Water Quality ( )

Water Balance Assessment of the Roseires Reservoir

Water Resources Development in the Lancang River : Cooperation, Benefits and Opportunities

Benefit sharing in hydropower development. Initiative on Sustainable Hydropower

Commercial Transportation on the Mekong River By Timothy Hamlin

PRIOR CONSULTATION PROJECT REVIEW REPORT

The First Mekong River Commission Summit 2010

VIETNAM ENGAGEMENT IN TRANSBOUNDARY WATER COOPERATION IN MEKONG RIVER BASIN

Presentation -- Three Gorges Dam (TGD) on the Yangtze River

Read the following article from the United States Geological Survey and answer the questions that follow.

National Policy on Environmental and Social Sustainability of the Hydropower Sector in Lao PDR

Sediment management of hydropower cascade: example of CNR run-of-river developments, French Rhone River, France

Impacts of mainstream dams on fisheries and mitigation options - Current status of knowledge

SUMMARY 2013 EDITION

Silvan Dam and Revisions to Adapt for Latest Developments in High CFRD Design and Construction

Environmental and Social Impact Assessment and Strategic Environmental and Social Assessment at the World Bank

Mekong Climate Change and Adaptation Initiative and the Mekong River Commission

The Flow of the Mekong

FINAL REPORT SUMMARY OF THE. Prepared for the Mekong River Commission STRATEGIC ENVIRONMENTAL ASSESSMENT OF HYDROPOWER ON THE MEKONG MAINSTREAM

Environmental and Social Impact Assessment for Rogun Hydro Power Plant

Contents Overview of Laos Current energy policy and Measure Energy demand and Supply in Laos Energy outlook in Laos Difficulties and bottlenecks in fo

Introduction. General Description

NATIONAL INDICATIVE PLAN

STATUS ON DRY PORTS DEVELOPMENT IN LAO PDR

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

RIVER HEALTH, ENVIRONMENTAL FLOWS AND CASCADE MANAGEMENT IN LAO PDR

Mekong Climate Change and Adaptation Initiative of the Mekong River Commission

Equitable and Low-Carbon Society: Aspiration and Strategies for Southeast Asia

Site 31: Gilberton Farm, Tarnbrook

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems

MEKONG SITE VISIT TO LAOS FIRST TWO MAINSTREAM DAM PROJECTS. Letters from the EXECUTIVE SUMMARY OF THE SECOND LETTERS FROM THE MEKONG ISSUE BRIEF

Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling

THE FIRST MEKONG RIVER COMMISSION SUMMIT Hua Hin, Thailand

POWER POTENTIAL STUDIES A CASE STUDY OF KULSI MUTLTIPURPOSE PROJECT

Hydropower as Flexibility Provider: Modeling Approaches and Numerical Analysis

Increasing Flood Risk in the Lower Mekong River Region & Direction for Future Adaptation

Site 16: Slaidburn Saw Mill

Three Gorges Project. A Project with Tremendous Benefits and in Favour of Environmental Improvement. By Cao Guangjing May 22, 2004

PROJECT INFORMATION AND SHORTLISTING CRITERIA FOR SCREENING OF CONSULTING FIRM. Tamakoshi V Hydroelectric Project

Hydropower and Water Resources

Western Power Company Ltd. Ngonye Falls Hydroelectric Project October 2014

Site 15: Gresgarth Hall, Caton

Review of Groundwater Information in the Lower Mekong Basin

Mekong River Basin Water Resources Assessment: Impacts of Climate Change

European State Questionnaire on Hydropower and the WFD

Prepared by Ministry of Mahaweli Development and Environment for the Asian Development Bank.

Trans-boundary Flood Issue in Lower Mekong River Basin

Contemporary Issues on the Mekong River

Introducing the WBG Guidelines for selecting EFlow assessment methods. Cate Brown

REFERENCES. 1. Acres International, RSW and Hydro Quebec, Nam Tha 1 Hydropower Project, Report to SPB Hydro-Power Co. Ltd., November 1997.

Water. Power. HYDROMATRIX

Water Development Plan Template

Techno-Economic Assessment Study Rogun HPP. Phase II Considerations. Riparian Consultations

5. HYDROLOGICAL CONDITIONS IN THE MEKONG DELTA. 5.1 Key International Monitoring Stations in the Mekong Delta

Geographic context. Hydropower developments on the upper Rhone River

Tangible benefits of technological prospection and prefeasibility studies in SHP projects Ing. Sergio Armando Trelles Jasso

Chapter 6 Mekong at the Crossroads: Alternative Paths of Water Development and Impact Assessment

Voith s StreamDiver solution for decentralized low head hydropower plant operations

Nepalese Power System and Nepal Electricity Authority. Lila Nath Bhattarai Deputy Managing Director Engineering Services Directorate NEA

Study on the Impacts of Mainstream Hydropower on the Mekong River

NAM NGUM 5 HYDROPOWER PROJECT

Session: For more information:

Comparison of climate change impacts and development effects on future Mekong flow regime

Energy Policy in Lao PDR

TRANSBOUNDARY DIALOGUE

PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC SEPTEMBER 19, 2012

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP

LEAKAGE ASSESSMENT OF WATER CONVEYANCE TUNNEL FOR HYDROPOWER PLANT VIA WATER BALANCE

Theme 5: Small-scale Hydropower. By: Dr Khamphone Nanthavong Faculty of Engineering, National University of Laos

Northwest Power and Conservation Council

Water-Energy Nexus: Economics of Hydropower

Sustainable Management of Small Hydropower for Rural Electrification in Lao PDR by Economic, Social and Environment Blueprint Perspective

Thailand Power Development Plan (PDP 2007)

Maria Tereza F.R. Campos Power Superintendent CNEC WorleyParsons Brazil

The contribution of pumped storage schemes to energy generation in SA. By Bo Barta PrEng, Energy and Water Resources Engineering

Application of Pumped Hydroelectric Energy Storage for Photovoltaic based Rural Electrification

PROJECT HISTORY. * Under Fiscal Incentives through promotion policies - 200MW

Chinese Dams and the Great Mekong Floods of 2008

Environmental and social impacts of smallscale. Issues and Challenges. Glenn Morgan (LCSEN) World Bank Water Week February 18, 2009

Bloemwater Conduit Hydropower Plant launched

J O S E P H R. B E V E R I D G E

NARUC. Winter Committee Meetings. Committee On Water

FRAMEWORK FOR AQUACULTURE DEVELOPMENT ON THE VOLTA LAKE. Implementation Guidelines Document

PRELIMINARY INVESTIGATION AND DESIGN CONSIDERATIONS FOR THE REHABILITATION OF TRASH SCREEN AT JOR RESERVOIR LOW LEVEL OUTLET

OPTIMAL WATER MANAGEMENT MODELING FOR HYDROPOWER SYSTEM ON RIVER NIGER IN NIGERIA

3- Hydropower. Energy conversion and hydropower principles

Transcription:

Feasibility Study on Pakbeng Hydropower Project

CONTENTS 1. Background 2. Hydrology 3. Adjustment of FSL 4. Installed Capacity 5. Reservoir Inundation 6. Project Layout 7. Alteration to Installed Capacity

Part 1 Background

BACKGROUND Pakbeng station is in upper reach of Mekong River and the first cascade of hydropower development projects on the river. The dam site is in Pakbeng district in north of Laos. Pakbeng HPP

BACKGROUND In December 2008, the Feasibility Study Report to GOL was concluded, in which the FSL was 345m mainly according to Mekong Mainstream Run-of-River Hydropower published by MRC in 1994. At the same time, Initial Environmental Examination (IEE) jointly prepared by Norconsult and Earth Systems LAO was submitted.

BACKGROUND In February 2009, GOL organized a meeting to examine the Report, and in May 2009, officially replied the Feasibility Study with the requirement of 'for the normal water level and tail water level shall be determined after completion of Optimization Study carried out by CNR ' for final FSR.

BACKGROUND In July 2009, CNR completed Optimization Study of Mekong Mainstream Hydropower. In January 2010,GOL made it clear that in order not to affect Thailand, the maximum operating water level of Pak Beng Project should not exceed 340m.

BACKGROUND After the FSL was adjusted from 345m to 340m, the reservoir inundation indicator and compensation cost would be greatly reduced, and the installed capacity would also be reduced from 1,230 MW to 855 MW accordingly. Therefore, this presentation mainly focus on design changes after the adjustment of FSL.

Part 2 Hydrology

Hydrology More hydrological data including Chiang Saen and Luangprabang Hydrological Stations were collected. Methodology is the same as that in last version of FS report Annual mean flow is 3,160 m 3 /s at Pak Beng dam site (Same as the data of last version) 1 2 3 4 5 6 7 8 9 10 11 12 year 1,350 1,060 912 973 1,440 2,740 5,450 7,770 6,770 4,490 2,950 1,870 3,160 3.56 2.80 2.41 2.57 3.80 7.23 14.4 20.5 17.9 11.8 7.78 4.93 100 Mean Flow

Hydrology Design flood discharge: 27,000 m 3 /s Check flood discharge: 30,200 m 3 /s Flood results is close to results of CNR or MRC P(%) Chiang Saen (m 3 /s) Laungprabang (m 3 /s) Dam site (m 3 /s) P(%) Chiang Saen (m 3 /s) Laungprabang (m 3 /s) Dam site (m 3 /s) 0.05 29800 30900 30200 2 20000 23700 21400 0.1 28100 29600 28700 5 17400 21600 18900 0.2 26200 28300 27000 10 15300 19900 17000 0.5 23800 26500 24800 20 13100 18100 14900 1 21900 25100 23100 50 9700 15000 11600

Part 3 Adjustment of FSL

Adjustment of FSL Main factors for determination of FSL The dam crest elevation is controlled by check flood level which is 343.81m, so it is economic to raise the full supply water level below 344m. Topographic and geological issues are not restrictive factors. GOL made it clear that the construction of Pak Beng Hydropower Project could not inundate KengPhaDai, and officially advised on January 5, 2010 that its normal water level should not exceed 340m.

Adjustment of FSL Pak Beng Reservior is shown as followed. Mainly Sensitive objects include KengPhaDai,Nam Ing River,Nam Ngao,etc. Nam Ing km115 Chiang Khong km125 KengPhaDai km97 Nam Ngao km105 PB HPP

Adjustment of FSL Overview of KengPhaDai Generally speaking,under natural condition, the water level of this area moves from 337m to 344m with the average of 340m in flood season, and it will be from 332m to 337m with the average of 335m in dry season. Thailand Laos

Adjustment of FSL Overview of KengPhaDai In flood season, most or even all reefs in KengPhaDai shall be submerged, and in dry season, some are exposed. When the water level remains around 337m, most reefs shall be entirely exposed.

Adjustment of FSL According to water level change and reef exposing at KengPhaDai, we prepared two schemes for technical and economic comparison. Scheme I: 340m in flood season, 335m in dry season Scheme II: 340m in all seasons Elevation(m) Operation level at 335m from from Dec. Dec. to to next May May Operation level at 340m from June to Nov. 1 2 3 4 5 6 7 8 9 10 11 12

Comparison of two schemes As to the power generation benefit, operation at 340m will generate extra 370GW h than that at 335m in dry season. According to engineering scheme, difference between two schemes is not so obvious. Energy 60 10 8 kw h 55 50 45 40 35 30 25 20 15 10 5 0 Annual Energy Enery in flood season Enery in dryseason 汛期 340m Scheme 枯期 I 335m 全年 Scheme 340mII

Comparison of two schemes As to the impact on Nam Ngao, Nam Ing River and Chiang Khong under flood condition, it is generally same between schemes. And the water level of the aforesaid areas changes slightly (almost can be neglected ) whether to build Pak Beng HPP or not: Item P=50% (Q m =11600m 3 /s) WL. with PB WL. without PB Diff. P=20% (Q m =14900m 3 /s) WL. with PB WL. without PB Diff. P=10% (Q m =17000m 3 /s) WL. with PB WL. without PB Diff. P=5% (Q m =18900m 3 /s) WL. with PB WL. without PB Diff. Ngao 347.90 347.48 0.42 350.27 350.25 0.02 351.72 351.72 0 353.03 353.03 0 Ing 349.64 349.37 0.27 352.02 352.00 0.02 353.52 353.52 0 354.79 354.79 0 Chiang khong 351.29 351.15 0.14 353.46 353.45 0.01 354.97 354.97 0 356.22 356.22 0

Comparison of two schemes Monthly average water level change at KengPhaDai for scheme 1 is similar to the natural condition, and considering of the effects on Thailand, scheme I seems better than scheme II. For scheme I, water level change can be shown as followed schematic maps under natural or project condition:

Comparison of two schemes The watel levels at KengPhaDai Thailand Laos

Comparison of two schemes The watel levels at Nam Ngao River Thailand Laos

Comparison of two schemes The watel levels at Nam Ing River The distribution of farmland above EL.350m in Thailand Thailand Laos

Comparison of two schemes Both schemes can reserve most of the natural surface feature on Lao-Thai border and the scenery in KengPhaDai. But Scheme II with higher water level in dry seasons is comparatively not as good as Scheme I. Therefore, we recommend that the proposed FSL should be 340m, and the reservoir operates at 340m in flood season and 335m in dry season.

Adjustment of other operation water levels The setting of dead water level mainly considers factors as layout of key hydraulic structures and the flexibility of reservoir operation. Once the FSL adjusted to 340m, and the water level in dry season adjusted to 335m, the dead water level shall according be adjusted to 334m. The lowest navigable water level of upstream of the dam and dead water level are the same as 334m; Compared with values of FSL and reservoir water level corresponding to 3 years return period flood, the larger value shall be taken as the maximum navigable water level of upstream of the dam,which is 340m.

Part 4 Installed Capacity

Installed capacity Main Factors for Finalization Installed Capacity as Follows: The type of water turbine, the capacity of generating unit, manufacturing level and transportation conditions; The characteristics of the output; Power supply market and load characteristics of supply area; Topographical and geological conditions and layout of hydraulic structures; Index of hydropower energy of project; Economy. Six schemes of installed capacities such as 741 MW (13 57 MW), 798 MW (14 57 MW), 855 MW (15 57 MW), 912 MW (16 57 MW), 969 MW (17 57 MW) and 1,026 MW (18 57 MW) are proposed for comparision.

Selection of turbine type Water Head Range The water head range of the power plant is changed from 13m ~ 34.7m to 7 m~ 29.7m, lead to the installed capacity changed from 1,230MW to 855MW. Turbine Type The maximum water head less than 30m, bulb turbines are more suitable for this project

Selection of turbine type Single-Unit Capacity Scheme 1 with 14 units, scheme 2 with 15 units and scheme 3 with 16 units are preliminarily selected for consideration. According to the unit operating flexibility, equipment manufacturing factors, transport conditions, hydro energy and layout of hydraulic structures, the scheme of 57MW (15 units) is recommended.

The characteristics of the output According to the characteristic of the flow output, the total Installed capacity may not more than 1086MW. Output (MW) 1086MW 1162MW Output Head (m) Output after considering output limit Water head Discharge

Comparison of other factors Topographic and geological conditions at the dam site and layout and quantities of key hydraulic structures may not restrict the selection of installed capacity. The power transmission pattern, voltage grade and circuits of outgoing lines applied to the aforementioned different schemes are the same. 280m~460m 200m

Installed capacity Economically, the 855 MW is relatively good, while the other schemes are relatively poor in economic evaluation. In general, the proposed installed capacity shall be 855MW, 15 generating units with capacity of 57MW each. The firm output is 357MW, and annual average energy is 4846GW h.

Part 5 Reservoir Inundation

Reservoir Inundation KD has carried out comprehensive investigation on environment and social impact with Norconsult, with 1:5000 Lao PDR topographic map, in October 2008. In the FS stage, we committed NCG (National Consulting Group, Laos) to work for environmental and social impact assessment, and trans boundary, cumulative ESIA as well. ESIA will be reported soon afterwards.

Reservoir Inundation 168 households, and 1010 persons are living under 340masl. Kiengphaak 村 搬迁户 17 搬迁人口 102 Houay Moong 村 搬迁户 12 搬迁人口 72 Homxai 村 搬迁户 18 搬迁人口 126 Louangtong 村 搬迁户 47 搬迁人口 232 Pak Xo 村 搬迁户 18 搬迁人口 120 Pak Khob 村 搬迁户 21 搬迁人口 132 Houay Khoun 村 搬迁户 4 搬迁人口 28 Houay Chiko 村 搬迁户 12 搬迁人口 84

Part 6 Project Layout

PROJECT LAYOUT Ship lock (In future) Discharging & flushing sluice Number: 12 Size: 15 23m Concrete gravity dam Height: 69m Length: 894.5m Discharging & flushing sluice, Number: 2 Size: 15 23m Ship lock 500t Powerhouse Turbine type: Bulb 15 57 MW Fishway

Generating powerhouse The powerhouse is installed with 15 sets of bulb turbine units. Each unit has the capacity of 57MW and the total will be 855MW.

Design standard of navigation structure across the dam According to the navigation agreement on Lancang-Mekong river signed by China, Laos, Myanmar and Thailand, and Preliminary Design Guidance for Proposed Mainstream Dams in the Lower Mekong Basin,the navigation structures across the dam are designed as navigation channel of class IV for watercraft of 500t level. A 500t ship can get across one time by the effective dimension of ship lock. We adopt single line and single lock at persent, and it is possible for double lines to meet the demand of shipping growth in the future.

General construction schedule The general construction period is 63 months. The preparation period is 20 months. The period for construction of main works is 25 months. The first unit can be operated and generate power within 45 months after commencement.

Conclusions With the adjustment of FSL from 345m to 340m, the negetive effects on Thailand can be avoided, and the technical and economic indicator of Pak Beng project is still good and feasible, relatively.

Part 7 Alteration to Installed Capacity

After MOU feasibility study report, the Project had progressed in a relatively slow pace. During this period, KD conducted deeper and more detailed study on the project design. Given minor discrepancy in economic efficiency of installed capacity schemes of 798MW, 855MW and 912MW, further study was carried out. For the purpose of installed capacity of Pak Beng HPP, the same principle in MOU feasibility study is still adhered at this stage, i.e. economic comparison among different schemes. Along with deepening of the design, it can be perceived that difference between this comparison and that at MOU feasibility study stage is mainly reflected in project cost.

Economic Comparison

Economic Comparison Cost Comparison among Options Proposed at Two Stages

Economic Comparison Cost Breakdown of Options Proposed at Two Stages(10 6 $) Cost Breakdown 855MW 912MW 2010 2011 D-Value 2010 2011 D-Value I Project complex 882.3 935.1 52.9 910.6 947.7 37.0 1 Ancillary works 136.3 138.7 2.4 136.3 138.7 2.4 2 Construction works 357.5 401.8 44.3 368.5 408.8 40.3 3 Environment protection & water and soil conservation 34.3 34.3 0.0 34.3 34.3 0.0 4 M&E equipment and installation works 276.0 268.5-7.5 291.1 271.6-19.5 5 Metal structure and erection works 78.0 91.7 13.7 80.4 94.2 13.8 II Land acquisition & resettlement cost 10.3 8.8-1.4 10.3 8.8-1.4 III Independent cost 219.4 243.8 24.4 219.9 244.8 24.9 IV Contingency 118.3 118.8 0.5 121.2 120.1-1.1 V Power evacuation 60.8 51.2-9.6 60.8 51.2-9.6 VI Static Cost of Project 1291.0 1357.8 66.7 1322.8 1372.7 49.9

Recommendation Comparison on cost breakdowns shows M&E equipment and construction work under 912MW is remarkably less costly than 855MW and post-commissioning cost difference is narrowed. Comparing with MOU feasibility stage, postcommissioning cost difference between these two options is 16.8 10 6 $.

Conclusion on Comparison of Options Overall technical and economic comparison conducted at MOU feasibility study stage indicated all schemes are technically feasible. 855MW was most efficient economically, almost identical to 912MW. Due to further study on project design, difference in project cost between 855MW and 912MW has been narrowed, and 912MW has shown higher economic efficiency. Therefore, it is recommended to increase installed capacity of Pak Beng HPP up to 912MW.

Analysis on Other Influential Factors (1) With progress of manufacturing technology of turbine unit, larger capacity will be more efficient economically. (2) Huge potential of power market is likely to trigger escalation of electricity tariff in the future. In the event that electricity tariff is increased during operation period and all energy production is absorbed, then the option with larger capacity appears to be more economic.

Final Conclusion With reference to the latest results of analysis on installed capacity and possible impact of changes in relevant influential factors against various options, it is recommended to increase installed capacity of Pak Beng HPP up to 912MW.