Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Similar documents
Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Trenchless Technology

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

Trenchless Pipeline Crossings

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

CC1602 Microtunneling

Short Drive Microtunnelling (MTBM) TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON

WARNING DO NOT BID ON THIS PROJECT

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

Agenda for Today s Workshop

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries

Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

PUMPING STATION CONSOLIDATION AND TRENCHLESS INSTALLATION CASE STUDY

5/16/2018. New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters. Dr. Marc Peters, Herrenknecht AG. Highlights.

Pipe Ramming with HDD. Presentation Outline

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking

A Trenchless Approach to Lift Station Elimination

A number of abbreviations and technical terms have been used in this guideline:

2013 ASCE Agenda. Microtunneling in Difficult Ground Craig Camp. Microtunneling Characteristics (NASTT) Akkerman MTBM Introduced 1995

Kathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii

How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E.

Weighing the Risks of Installing a Lake Tap with Microtunneling

Dahlia Ponds Tunnel Project. Presented By: Nathan Soule, PE, PG Brierley Associates & Brenden Tippets, Project Executive, BTrenchless

PILOT TUBE & PIPE RAMMING METHOD INSTALL LARGE DIAMETER CASING UNDER RR

Problems Realized with Contractor-Proposed Pilot Tube Auger Boring

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

CHALLENGES AND SUCCESSES OF OPEN SHIELD PIPE JACKING CONSTRUCTION IN A CONGESTED NEIGHBORHOOD

ITEM 432 TUNNEL CONSTRUCTION

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

Templeton Community Services District Eastside Force Main Improvements. Monthly Progress Report

Experts in tunneling with Tunnel Boring Machines

The City of Sergeant Bluff, IA Chooses Pilot Tube Microtunneling over Open Trench Construction

B. All materials to be installed shall be purchased in accordance with all applicable provisions of the Buy American Act.

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

The Pilot Pipe method is a very simple method for trenchless installation of supply lines. It is done in several steps:

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

SEMINAR. Introduction to Continuous Flight Auger (CFA) piling Thursday 21/8/2013. Facilitator: Martin Larisch

QUANTIFYING THE EFFECTS OF LUBRICATION ON JACKING FORCES

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

Amendment to OPSS 416 (Nov 2013) Construction Specification for Pipeline and Utility Installation by Jacking and Boring

Take Me to the Other Side:

Table of Contents TOC. Chapter 14 - Trenchless Construction. 14A General Information. 14B New Construction. 14C Rehabilitation

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

SECTION TRENCHLESS INSTALLATION

Sometimes Big Problems Require Small Solutions Microtunneling in New York City Reduces CSO Events


TRENCHLESS INSTALLATION OF ROAD DRAINAGE & SERVICE DUCTS

Ø1.8m Double Shield TBM for Mixed Ground Sewer Tunnels in Cincinnati

WEF Collection Systems Conference Noble Gulch Trunkline Relocation Project: Implementation of a Multifaceted Trenchless Technology Program

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

SECTION BORING AND/OR JACKING PIPE

MICRO-TUNNELING LARGE DIAMETER SEWER MAY BE THE BEST OPTION FOR YOU

Pipe Jacking. Japan Sewage Works Association

A Sigh of Relief: Completion of the San Mateo El Cerrito Relief Line. Kourosh Iranpour, PE

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

8Re: Northern Access 2016 Project. Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation

Diaphragm wall Construction

Draft. Not yet Approved TABLE OF CONTENTS. Page

What do you mean we can t do HDD?

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

HORIZONTAL BORING HORIZONTAL BORING. Underground Electric Distribution Standards I. GENERAL

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project

SECTION HORIZONTAL DIRECTIONAL DRILLING

North End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No

Reinforced Concrete Microtunnelling Pipe Designed for Project Conditions and MTBM Machines

Final Report FHWA/IN/JTRP-2002/7

E-Power Pipe : A new trenchless method for underground cable installation

APPENDIX: C. Stormwater and Wastewater Construction Specification. Tauranga City Council

Multiple Large Diameter Microtunnels with Limited Ground Cover

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

S.No Description Unit Quantity Rate (Rs) Amount (Rs)

SPECIFICATION : BORING AND JACKING

BRADSHAW CONSTRUCTION CORPORATION

SECTION UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD)

SECTION / ENGINEERED AGGREGATE PIERS (SOIL REINFORCEMENT AND FOUNDATION SYSTEM)

USE OF MICROTUNNELING TO INSTALL PIPES IN AN ENVIRONMENTALLY SENSISTIVE AREA. Miranda Roman D. *, LaFaso Edward

The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump

REDUCING RISK AND VISITOR IMPACTS

GEOTECHNICAL BASELINE REPORTS APPLYING THE GUIDELINES TO MICROTUNNELING

Transcription:

Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Introduction Purpose Provide engineers and owners with one example of a trenchless crossing evaluation. Outline Trenchless Considerations Trenchless Methods HDD, microtunneling, pipe jacking, auger-boring, pipe ramming. Martha Lake Sewer Project Overview Martha Lake Trenchless Evaluation Conclusion of Evaluation Next Steps

Trenchless Considerations Ground Conditions Soil Type Groundwater Rock / Boulders Mixed Face Conditions Wood Man-made Debris (concrete, steel, VW Bugs, etc.) Crossing Length Pipe / Casing Diameter Alignment (Horizontal and Vertical) Depth (cover over excavation)

Trenchless Methods Horizontal Directional Drilling (HDD) Microtunneling Pipe Jacking Auger Boring Pipe Ramming

Horizontal Directional Drilling (HDD) Pilot hole Reaming pass(es) Spoils removed by recirculation of drilling mud Pipe insertion

Horizontal Directional Drilling (HDD) Strengths Performs well in groundwater Drilling mud mix can be altered for ground conditions Very long crossings Curved alignments Weaknesses Elevated risk of frac-out or settlement Smaller diameters (< 36 ) Difficult to control line and grade Requires a 2% minimum slope for gravity applications Large area for pullback layout

Microtunneling Jacking shaft Spoil Removal via slurry lines Slurry pressure provides excavation face support Hydraulic jacks advance pipe string and MTBM

Microtunneling Strengths Performs well above or below groundwater Slurry pressure can be varied based on support needed at excavation face Longer Drive Lengths Good line and grade control Weaknesses Has difficulties excavating obstructions larger than 1/3 the diameter Most do not allow face access to remove obstructions Rescue pit required if stopped by an obstruction Can be deflected by mixed-face conditions

Pipe Jacking Jacking Shaft Open face allows manned access Spoil Removal via mechanical or manned methods Hydraulic jacks provide advance pipe string and pipe jacking machine

Pipe Jacking Strengths Face access allows removal of obstructions Longer Drive Lengths Good line and Grade Control Weaknesses Difficult to control groundwater Difficult to control flowing soils Can be deflected by mixed-face conditions

Auger-boring Jacking Shaft Spoil Removal via auger flight though jacking pipe Hydraulic jacks advance pipe string and auger flight

Auger-boring Strengths Good in cohesive soils Minor line and grade control Weaknesses Difficult to control groundwater Max. drive length of around 300

Pipe Ramming Excavated pit Pneumatic tool advances pipe Minimal Spoil Removal Face support provided by soil plug

Pipe Ramming Strengths Minimal risk of ground settlement Excavation continuously supported Performs well above or below groundwater Weaknesses Difficult to control line and grade Short drive lengths (< 300 )

Martha Lake Project Overview Alderwood Water & Wastewater District Lynnwood, WA Site

Martha Lake Project Overview I-5 and 164 th St. SW 3,400 LF of 12 to 15 gravity sewer Residential Septic Commercial Pump Stations 1700 LF of 24 water main added Currently at 60%

Martha Lake Trenchless Crossing Ground Conditions Soil Dense Glacial Till overridden by fill Groundwater Perched groundwater on top of Till Pockets within Till Rock / Boulders Boulders: 1.5 to 7 Mixed Face Conditions None Known Wood None Known Man-made Debris None Known

Martha Lake Trenchless Crossing TILL

Martha Lake Trenchless Crossing Drive Length 535 Pipe Diameter(s) 54-60 Casing 12 Ductile Iron Sewer 24 Ductile Iron Water Six 4 Conduits Alignment Vertical profile lies completely within Glacial Till Depth 14 minimum, 25 maximum

Martha Lake Trenchless Evaluation Trenchless Methods Soil Types (G Glacial Till) Gr round Water (Gr ravel Pockets) Ro ock / Boulders Set ttlement Risk Drive Length (535') Lin ne and Grade Control TOTAL HDD 6 8 5 6 9 4 38 Microtunnel 7 8 6 8 8 8 45 Pipe Jack 8 5 8 6 8 8 43 Auger-bore 5 4 5 6 1 4 25 Pipe Ramming 4 8 2 8 1 3 26

Conclusion Microtunneling or Pipe Jacking Two options increases number of eligible contractors Contractor can chose machine he believes will work best for ground conditions Three jacking pipe options give more flexibility HOBAS Reinforced Concrete Steel (PermaLok) GO BIG!!! = 60 Casing

WSDOT PUD

ulders!! Bou WSDOT

Next Steps Specifications Specify MTBM best suited for ground conditions Specify options for rescue shaft to free MTBM Require mitigation plan for encountering groundwater with a pipe jacking machine Require obstruction removal plan for pipe jacking GBR Must apply to both pipe jacking and microtunneling operations

Trenchless Tips Use in combination with other methods Pay a premium for short crossings Talk with machine manufacturers and local contractors!

Questions?