Environmental and Social Data Sheet

Similar documents
Environmental and Social Data Sheet

Environmental and Social Data Sheet

1 Environmental and Social Action Plan

IMPACT REPORTING Green Bond Principles Conference 27 March 2015

Greater Amman Municipality

Morocco s experience in CSP projects

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE. I Estimated Board Date: July 27, 2017

Environmental and Social Data Sheet

EBRD Environmental and Social Action Plan

EBRD and Wind Energy in Turkey and Beyond

Environmental and Social Review Summary

Bosnia and Herzegovina Route Donja Gračanica - Klopče and Svilaj - Odzak (Part of Corridor Vc) ENVIRONMENTAL AND SOCIAL ASSESSMENT

Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP)

NOOR : THE MOROCCAN SOLAR PLAN

Syvash Wind Farm Environmental and Social Action Plan (ESAP)

Abeokuta, Nigeria Greenfield Power Generation Plant Environmental Impact Assessment (EIA) Background Information Document (BID) January 2015

Environmental and Social Data Sheet

Aquanova Nyzhniy Bystryi small hydropower plant project non-technical summary

Noor-Midelt Phase 1 Concentrated Solar Power Project

ENVIRONMENTAL IMPACT ASSESSMENT

DRAFT FOR CONSULTATION OCTOBER 7, 2014

Prepared by State Joint Stock Company UzbekEnergo for the Republic of Uzbekistan and the Asian Development Bank.

EBRD and Wind Energy

The Project will be undertaken in line with a number of national laws and standards. Key local laws relating to ESIA include:

IUCN Standard on the Protection of Natural Habitats

5 SCOPE OF THE ENVIRONMENTAL IMPACT ASSESSMENT. The scope of the EIA falls under three broad categories:

1 INTRODUCTION 1.1 TERMS OF REFERENCE FOR THIS ENVIRONMENTAL IMPACT ASSESSMENT REPORT

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE

Natural Heritage assessment of small scale wind energy projects which do not require formal Environmental Impact Assessment (EIA).

6 SUMMARY OF CUMULATIVE AND INDIRECT EFFECTS 6.1 INTRODUCTION

Environmental and Social Data Sheet

C. Project Description [from section 3 of PCN] The proposed project would comprise of the following three components:

4 APPROACH TO THE ENVIRONMENTAL IMPACT ASSESSMENT

SNTGN TRANSGAZ SA MEDIAS. ESAP BRUA Version 3 1

DRAFT ENVIRONMENTAL AND SOCIAL ACTION PLAN (ESAP)

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE

Case Study: Masen NOOR Ouarzazate Solar Complex

SAMOA ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK FOR A POST-TSUNAMI RECOVERY PROJECT

GREEN NORMS FOR WIND POWER. Potential Impacts and the Need for Green Norms

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

ENVIRONMENTAL AND SOCIAL ACTION PLAN

determine the effect of the Proposed Development together with the other planned changes within defined areas of influence;

RFP No: WB/MOF/MINIS/CS/CQS/1.1.9 (d)/2014. A. Background

Safeguard Requirements And the Framework Process

EMPLOYMENT RESEARCH BRIEF EMPLOYMENT IMPACT OF INFRASTRUCTURE INVESTMENTS IN MOROCCO

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI

Doc. No H1 Rev. 0 - July 2011 APPENDIX C ENVIRONMENTAL AND SOCIAL ACTION PLAN

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC5832. Date ISDS Prepared/Updated: 12/22/2010 I. BASIC INFORMATION. A. Basic Project Data

National Agency for RE and EE Development (ADEREE)

Environmental and Social Data Sheet

TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE

Ironstone Quarry Wind Energy Project Environmental Statement

SEA FOR STRATEGIC GRID PLANNING IN SOUTH AFRICA: Enabling the efficient and effective roll out of strategic electricity transmission infrastructure

ENVIRONMENTAL AND SOCIAL MANAGEMENT FRAMEWORK. for the. Partial Risk Guarantees Project for Independent Power Producers in Kenya DRAFT

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3946. Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION. A. Basic Project Data

Employment promotion via sustainable energy

Preliminary Environmental Information Report

The shift of Morocco to renewable energies: toward a complex system-of-systems perspective

Financing (In USD Million) Financing Source

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC6530. Date ISDS Prepared/Updated: 03/14/2012 I. BASIC INFORMATION. A. Basic Project Data

Page 1 of 5. FrontCounterBC Kamloops 441 Columbia Street Kamloops, BC V2C 2T3

Strategic Environment Assessment. For the. New Structure Plan for the Maltese Islands. Scoping Report

ACWA Power Business-driven Value Development. May 31, 2016

EIA FOR THREE 10MW PHOTOVOLTAIC (SOLAR) ENERGY FACILITIES PROPOSED FOR MARIENTAL, OMARURU AND OKAHANDJA BACKROUND INFORMATION DOCUMENT

Ex-Ante Evaluation (for Japanese ODA Loan)

Document of The World Bank FOR OFFICIAL USE ONLY PROJECT APPRAISAL DOCUMENT ON A PROPOSED LOAN IN THE AMOUNT OF US$200 MILLION AND A

Performance Requirements

EUROPEAN BANK FOR RECONSTRUCTION AND DEVELOPMENT. Programme for Supporting Renewable Energy in Ukraine

SUMMARY OF OPERATION EVALUATION. A wind farm. November 2013 EBRD EVALUATION DEPARTMENT

COMMISSION RECOMMENDATION. of XXX

Introduction to Environmental Impact Assessment for Masterplan Sites 25 April 2018

COMMISSION RECOMMENDATION

Project for Elaboration of the National Strategy for Treatment of Household and Similar Waste for the Kingdom of Morocco

Sector guide - Energy

BRYPAAL SOLAR POWER (PV) PROJECT AND ASSOCIATED INFRASTRUCTURE

RFP No: WB/MOF/MINIS/CS/CQS/1.1.14/2014

Svarychiv small hydropower plant project non-technical summary

EBRD requirements and lessons to date

Environmental and Social Policy

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP

Japanese ODA Loan. Ex-Ante Evaluation

ABENGOA SOLAR Solar Power for a Sustainable World

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE. Date prepared/updated: January 13, 2017 Report No.:

INTEGRATED SAFEGUARDS DATA SHEET APPRAISAL STAGE

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify)

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE ELECTRICTY TRANSMISSION

Environmental and Social Review Summary. Jamaica Water Supply Improvement Project

GLOBAL COMPACT COMMUNICATION ON PROGRESS

Environmental and Social Impact Assessment (ESIA) for Oil & Gas Projects, a Myanmar Context

Environmental and Social Action Plan Adjaristskali Hydropower Plants

SUBMISSION GUIDE ECOLOGICALLY SUSTAINABLE DEVELOPMENT. May

RECORD OF DECISION IMPLEMENTATION OF ENERGY, WATER, AND SOLID WASTE SUSTAINABILITY INITIATIVES FORT BLISS, TEXAS AND NEW MEXICO

Moroccan Agency for Sustainable Energy

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

NOORo III Tower CSP Plant, Ouarzazate, Morocco. Non-Technical Summary. ACWA Power. March Public Disclosure Authorized

EBRD Performance Requirement 10

GOLD STANDARD PASSPORT

Guyana s Nationally Determined Contribution. Office of Climate Change Ministry of the Presidency September 8, 2016

Managing Environmental Risks and Impacts in Geothermal Exploration Projects

Renewable Energy Policies Case Study For Morocco

Transcription:

Environmental and Social Data Sheet Luxembourg, 08.09.2014 Overview Project Name: Project Number: 2013-0468 Country: Project Description: OUARZAZATE III (TOWER) Morocco Construction and operation of a 150 MW CSP Tower plant under the third phase of the Ouarzazate solar power complex. EIA required: Project included in Carbon Footprint Exercise 1 : yes yes Summary of Environmental and Social Assessment, including key issues and overall conclusion and recommendation The project (Ouarzazate III) concerns the construction and operation of a third concentrated solar power (CSP) plant, using central tower technology, with an installed gross capacity of 150 MW, as part of the 500 MW Ouarzazate solar complex. It follows the first and second phases of the Ouarzazate complex which were approved for financing by the Bank in 2011 and 2013 respectively. The implementation of the project aims at increasing renewable power generation in Morocco, thereby mitigating greenhouse gas emissions and dependence on foreign energy imports in the country. The project will be implemented on a 3000 ha greenfield area located 10 km E-NE of Ouarzazate, already used for the development of the first and second phase projects. Construction is planned to start in mid-2015 and enter into operation by mid-2018, at the latest. The site was chosen because of its good solar resource, the availability of water, easy access and the proximity of a robust power grid to evacuate the electricity from the site and onto the Moroccan power grid. Within the EU, the project would fall under Annex II to the EIA Directive, leaving it to the Competent Authority to decide whether or not an EIA should be requested. Given the scale of the expected solar complex and the fact that this is the first of its kind in Morocco (and in the region) the Moroccan Competent Authority (the Secrétariat d État chargé de l Eau et de l Environnement SEEE) requested that an EIA be carried out, which the EIB considered to be appropriate Since the specific technical design of each phase in the complex is determined only at the stage where a winning bidder is selected, the promoter decided to first prepare a Framework Environmental and Social Impact Assessment (FESIA), which was approved by the EIB in mid- 2011. An updated FESIA was prepared by the promoter in March 2014, to the satisfaction of the EIB. The FESIA scope covers the different technologies (parabolic trough, power tower etc.) envisaged by the promoter for the Ouarzazate solar complex. The FESIA includes a Framework Environmental and Social Management Plan (FESMP), which covers institutional settings, general mitigation measures and monitoring plan for the potential impacts expected from project activities during construction and operation stages. According to the FESIA the main impacts of the planned Ouarzazate complex which would be relevant for the Ouarzazate III project relate to: (i) increased water use in a desert environment; (ii) potential pollution from leakage of thermal fluid, anti-freeze or rust inhibitor; (iii) thermal and / or chemical pollution of local waterways from cooling water and other waste water; and (iv) fire risk from solar converters at high temperatures. No physical or economic displacement of local population is foreseen. 1 Only projects that meet the scope of the Pilot Exercise, as defined in the EIB draft Carbon Footprint Methodologies, are included, provided estimated emissions exceed the methodology thresholds: above 100,000 tons CO2e/year absolute (gross) or 20,000 tons CO2e/year relative (net) both increases and savings. 1

There is no areas of high conservation value in the close vicinity of the site. The closest protected natural zone (habitats) is the Mansour Ed Dahbi dam lake, 6km south of the site. The FESIA concluded it is unlikely that the proposed Ouarzazate complex would significantly degrade any of these habitats. There are several potential impacts of climate change on the complex, in particular as it relies on water availability for part of its cooling needs. The Ouarzazate III project will rely on dry cooling technology thus reducing significantly its water consumption, which is considered appropriate by the Bank. In addition, and in line with the Bank s earlier recommendations (during the appraisal of the Ouarzazate I project), the promoter has launched a specific study to further assess the impact of climate change on the complex, for which findings should be available by end-2013. Like for the Ouarzazate I and II projects, the Special Purpose Vehicle (SPV) for Ouarzazate III (once established) will carry out a project-specific Environmental and Social Impact Study (ESIS) with appropriate mitigating and monitoring measures. This study and its corresponding Environmental and Social Management Plan (ESMP) will need to obtain clearance from the CNEI. This clearance, together with the submission to the Bank of the final version of the EIS and the ESMP as approved by the CNEI (and acceptable to the Bank) will be required. In addition environmental and social assessments for the infrastructures to be shared by the various phases of the Ouarzazate complex (transmission lines, water supply) are being carried out by the relevant Moroccan national agency (Office National de l Electricité et de l Eau Potable ONEE). Clearance on these studies from CNEI, and submission to the EIB of their final version (acceptable to the EIB) will be required. In summary, the project environmental and social impacts are considered acceptable for EIB financing, if it complies with the above mentioned requirements. Environmental and Social Assessment Environmental Assessment Environmental legislation and studies The Moroccan EIA Law (Law no 12-03) was promulgated in May 2003 and is generally in line with the principle of the EU EIA directive. Implementing decrees on public inquiries and environmental consent procedures were signed in November 2008. According to the procedure, the EIA should be submitted to the Comité National des Études d Impact (CNEI) together with the results of the public inquiry. The CNEI then formulates its recommendation to the Ministry of Environment which issues the environmental consent. A Framework Environmental and Social Impact Assessment (FESIA) for the Ouarzazate complex has been finalised by the promoter in 2011. An updated FESIA was prepared by the promoter in March 2014, to the satisfaction of the EIB. This FESIA provides a baseline environmental and social assessment of the project site. It has aimed to inform the process of integration of environmental and social concerns in the design and preparation of the project, and has also been closely followed by the different IFIs following project preparation. The FESIA scope covers the different solar technologies (parabolic trough, power tower, photovoltaic etc.) envisaged. The FESIA includes a Framework Environmental and Social Management Plan (FESMP), which covers institutional settings, general mitigation measures and monitoring plan for the potential impacts expected from project activities during construction and operation stages. The FESIA obtained its final clearance from the Comité National des Études d Impact (CNEI part of the SEEE) in November 2011. Given that the conclusions of the updated FESIA did not differ from those of the original FESIA, no additional clearance was sought from the CNEI. Following the award of the EPC contract to the winning bidder, the project SPV will carry out a project-specific Environmental and Social Impact Assessment (ESIA) with the setting of appropriate mitigation and monitoring measures. This project specific ESIS, and its corresponding Environmental and Social Management Plan (ESMP) will need to obtain clearance from the CNEI. 2

This clearance, together with the submission to the EIB of the final version of the ESIS and the ESMP as approved by the CNEI, will be required. In addition environmental and social assessments for the infrastructures to be shared by the various phases of the Ouarzazate complex (transmission lines, water supply) are being carried out by the respective Moroccan national agencies (Office National de l Electricité et de l Eau Potable ONEE). Clearance on these studies from CNEI, and submission to the satisfaction of the EIB of their final version will be required. Environmental impacts and mitigation measures During construction, the main expected impacts associated with the project are similar to other construction works impacts (waste, noise and impacts on flora and fauna should be managed in the same way as similar impacts for large construction projects (waste disposal, speed limitations, minimisation of wildlife disturbance, etc.). During operation, the key potential adverse impacts of the proposed project are summarised hereafter. The FESIA also specified several appropriate mitigation measures, environmental monitoring plans, institutional arrangements and training requirements, together with cost estimates for the implementation of the mitigation measures. A final assessment of these will be possible once the project-specific ESIS is available, and the acceptability of the residual impacts is evaluated in the light of the project s technical configuration. Water consumption for turbine cooling; but also for the humidification of roads, sanitary uses, and mirror cleaning, will be minimised thanks to the choice of a dry cooling configuration for the solar plant. The water will be provided from a nearby reservoir. For the project a maximum of 155 000 m 3 of water would be needed annually, which is approximately 10 times less than the needs for the Ouarzazate I project. Risk of pollution due to soil infiltration (and local contamination of rainwater) from molten salts and/or fossil fuels, all used on site. Proposed mitigation measures include the choice of key components with leak-proof designs, to be regularly maintained, cleaned and periodically replaced by appropriately trained staff. Biodiversity aspects There are no areas of high conservation value in the close vicinity of the site. The project site is recognised as being of low biodiversity value. None of the flora species found at the site is considered threatened or rare. Several protected natural zones (habitats) have been identified in the region, the closest being the Mansour Ed Dahbi dam lake, located some 6km south of the site. The FESIA concluded it is unlikely that the proposed Ouarzazate complex would significantly degrade any of these habitats. Climate change mitigation and adaptation It is foreseen that the project will avoid greenhouse gas emissions by producing renewable electricity, and displace the construction of new capacity using fossil fuels. There are several potential impacts of climate change on the complex, in particular as it relies on water availability for part of its cooling needs. The Ouarzazate III project will rely on dry cooling technology thus reducing significantly its water consumption, which is considered appropriate by the Bank. In addition, and in line with the Bank s earlier recommendations (during the appraisal of the Ouarzazate I project), the promoter has launched a specific study to further assess the impact of climate change on the complex, for which findings should be available by end-2013. EIB Carbon Footprint Exercise Absolute CO 2 emissions from the project in a standard year of operation will be around 20 kt CO 2 e/a. The baseline emissions are calculated assuming that electricity generated by the project will displace generation from a mix of existing thermal power and new generation (coal and renewable). Compared to this baseline the project is estimated to save ca. 266 kt CO 2 e/a. 3

Social Assessment Resettlement and land acquisition Like for the previous phases of the Ouarzazate complex, the project does not involve any physical or economic displacement of local populations. For the development of the Ouarzazate complex, however, the acquisition of approx. 2,500 hectares of collective land owned by the Ait Oukrour Toundout community (out of a total area of 64,000 hectares) was required. This land is uncultivated and of little economic value. The transaction was carried out following Moroccan standard procedure for similar types of voluntary land transactions between a local community and a public agency (article 11 of Dahir dated 27/04/1919). A Land Acquisition Plan (LAP) describes the detailed procedure through which the promoter proceeded with land acquisitions. The LAP document includes, in particular, copies of: (i) the land price committee determination of the price of the land; (ii) the written agreement by the community of Ait Oukrour Toundout on the sale and conditions for the transfer of the land; (iii) the authorisation of the Supervisory Board for the transaction; and (iv) the ONE/promoter/community tripartite agreement on land acquisition. The LAP is summarised in the FESIA, is in line with EIB s social standards, and is publicly available on the promoter s website since July 2011. In addition, a Social Development Plan (SDP) is being developed through a participatory approach involving the promoter, the Ministry of Interior and the local community, and will include measures in the area of education, sanitation and rural roads rehabilitation. A preliminary version of the SDP has been reviewed to the Bank s satisfaction, and its acceptability to the Bank in its final form will be confirmed at second-stage appraisal. Other social issues Morocco has ratified seven of the eight ILO core labour standards, except for Convention 87 on Freedom of Association. In order to ensure that the core principles and standards are adhered to in the context of the project, the promoter has requested in the bidding documents that the SPV s approach to social issues (articulated inter alia in the project-specific environmental and social management plan) is in accordance with EIB s Environmental and Social Standards The SPV will have direct responsibility for the implementation of the Environment, Health and Safety measures for the site during construction and operation, which should be prepared in accordance to EIB s environmental and social practice handbook guidelines, as requested in the bidding documents. The SPV will, inter alia, need to prepare a project-specific environmental and social management plan (ESMP), which should ensure that the negative impact on occupational and community Health & Safety are avoided or minimised. The social impact of the project is generally considered positive as it is creating temporary employment, stimulating local investments and supporting economic growth. Public Consultation and Stakeholder Engagement As part of the ESIA process, public enquiry should be held according to the related implementing decree signed in November 2008. The public consultation process covered by this implementation decree, however, has been more of an indirect kind, involving representatives from elected councils and from all relevant public institutions. This process thus follows national culture and legislation, but does not fully comply with the EIB s requirements, as it excludes stakeholders other than official representatives. A new government decree which opens up direct public consultation to all stakeholders - was enacted in February 2011. Despite the absence of legal requirement for full direct public consultation on the Ouarzazate solar complex (the latest implementation decree on public consultation does not apply retroactively), a formal public consultation meeting on the draft FESIA took place on 3 November 2010 in Ouarzazate, which confirmed the support from local officials and community representatives to the project. The main comments made during the meeting were related to natural risks (wind, earthquakes), water use, access road, economic and social impacts. The proceedings of this meeting are included in the final FESIA report. In addition the local population (the Ait Oukrour Toundout community and more specifically the village of Tasselmant) took part in consultations 4

organised by MASEN as part of the LAP process and the preparation of the SDP (see section on Social Assessment ). A public enquiry process was also undertaken on the final version of the FESIA and was concluded at the end of 2011. The project-specific ESIS should be subject to a stakeholder engagement process in the course of its preparation by the SPV. It is expected that more relevant and project-detailed information will be available (notably conclusions of the specific ESIS, discussion of recommended mitigating activities and plans) and should ensure more meaningful consultations. Other Environmental and Social Aspects Summary of E&S management arrangements Like for the previous phases of the Ouarzazate complex, the project will be implemented by a SPV to be created as a partnership between the promoter and a competitively selected private investor/developer with strong financial, technical and project management and implementation capabilities. As soon as it is established, the SPV will carry out a project-specific ESIS with appropriate mitigation and monitoring measures. The environmental and social capabilities of the counterpart entity/ies that will enter into the SPV will be fully assessed during the selection which will be carried out by the promoter with the assistance of reputable technical and transaction advisors. The implementation and monitoring of the framework environmental and social management plan will be the responsibility of the promoter. The promoter has appointed an Environmental and Social Coordinator and will hire environmental and social specialists as relevant, depending on the inhouse environmental and social capacity. The promoter will work closely with the appointed SPV to ensure that all environmental and social mitigation measures including occupational health & safety guidelines are mainstreamed into the project design, and that they are monitored and supervised. The SPV will also include an Environmental & Social Coordinator who will have direct responsibility for the implementation of the environmental, social and health & safety measures for the site during construction and operation. The SPV Environmental & Social Coordinator will, inter alia, prepare a monthly environment and health & safety report during the construction phase. Disclosure of key E&S documents The final version of the FESIA and LAP were reviewed by the EIB and are disclosed on its website. Project-specific ESIS which will be conducted by the winning bidder and national agencies in charge of water and electricity will also be subject to disclosure (on the promoter s website or on the EIB s website). 5