TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE

Size: px
Start display at page:

Download "TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE"

Transcription

1 Greater Mekong Subregion Nam Ngum 3 Hydropower Project (RRP LAO 41385) Supplementary Appendix 5 TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE Strengthening Biodiversity Protection and Management in the Nam Ngum 3 Hydropower Project 1. Background 1. Nam Ngum 3 Hydropower Project (NN3) is one of a cascade of existing and planned hydropower projects in the Nam Ngum basin in central Laos. It will operate as a storage system with a maximum storage capacity of 1,407 million cubic meters. Water will flow through a kilometer (km) long headrace tunnel to an underground power station. A nearly 1 km long tailrace tunnel will return the water to the river 15.8 km downstream of the dam. The main features of NN3 include (i) 2 x 220 MW rated capacity turbines; (ii) a concrete-faced rockfill dam 220 meters (m) in height; and (iii) a 99 km long, 500 kv transmission line. The NN3 reservoir will inundate roughly 60 km of the Nam Ngum plus part of its tributaries. NN3 dam will reduce the flows downstream along 17 km down to the Nam Ngum 2 Hydroelectric Facility (NN2) reservoir. The proposed 500 kv transmission line will partly run through the Phou Khao Khouay National Protected Area parallel to the existing 230 kv transmission line route of NN2. 2. The NN3 has been in development since the late 1990s and studies have been done to determine the feasibility of the project. An environmental impact assessment (EIA) and cumulative impact assessment has been prepared for the Project. In preparing the final EIA in September 2011, the Nam Ngum 3 Power Company (NN3PC) used the inputs made for an earlier version of the EIA by the consultant RMR International. RMR conducted baseline biodiversity studies in the project area in 1998 before the area was disturbed by the construction and operation of other hydropower projects and mining operations (such as NN2, Nam Ngum 5, Phou Bia Mine), and the preparatory works for NN3. Information from studies done by Duckworth and Warren in the Nam Ngum were also used as reference, where appropriate, to augment the RMR studies. 3. However, given the developments in the river basin, NN3PC needs to undertake a comprehensive and updated Baseline Biodiversity Assessment. The initial biodiversity surveys to be undertaken as part of the assessment are expected to commence in the coming dry season (estimate November 2011) covering the following areas: (a) the river section and adjoining areas downstream of the dam to the backwaters of the NN2 reservoir, including the areas earmarked for quarry and disposal sites, (b) reservoir inundation and adjoin areas, (c) a relatively undisturbed stretch of Nam Ngum upstream of the confluence with the river Nam Ting and (d) the transmission line corridor and adjoining areas (but excluding any areas impacted by the NN2 230 kv transmission line). The planned biodiversity assessment would include collection of baseline data on (a) aquatic and terrestrial flora, and (b) fauna and their habitats, including the status of forest cover. The results of the assessment will include recommendations for the implementation of appropriate and effective measures to minimize and mitigate potentially adverse impacts and risks to the biodiversity, and the need for biodiversity offset, to mitigate any residual impacts in order to achieve a no net loss of the affected biodiversity. 4. The assessment of the impacts of NN3 to the biodiversity and natural resources including the proposed mitigating measures and its implementation and management is

2 2 complex and the capacity of the Government of Lao to undertake the necessary regulatory decisions including implementation is limited. Therefore, it is recommended that an Independent Advisory Panel (IAP) be established to assist the Government of Lao PDR to (a) assess these project impacts on biodiversity and natural resources, (b) decide on effective mitigation and offset measures, and (c) implement and manage mitigation and offset measures adequately. 2. Scope of IAP 5. The ADB will recruit three distinguished international specialists to provide technical assistance to the government The specialists will be required with expertise in (i) biodiversity assessment; (ii) protected/conservation area management; and (iii) social assessment including Indigenous People. The assistance will be for 190 person-days of technical advisory services. The IAP will be supported by specialists in additional disciplines, as needed. The assignment will be completed by December The services will be provided in two Phases: Phase I: Review and comment on Baseline Biodiversity Assessment (November 2011 to April 2013) undertaken by NN3PC Phase II: Review and Comment on Biodiversity Offset Studies and Implementation of its recommendations (March 2013 to December 2017) by the Government. 3. Terms of Reference for Panel Members a. Conservation Area Management Expert /Team Leader (90 person-days) 7. The conservation area management expert will lead the IAP and will be responsible to coordinate its activities and prepare the reports consolidating inputs from other panel members. The specific task of the expert, during the preparatory phase of the offset plan will include review and analysis of available information on the project and its impacts on biodiversity, review and comment on draft TOR for proposed Biodiversity Offset Studies for identification, design and implementation of offsets, lead the IAP during the field visits to the project impact and the offset sites, lead the investigation on environmental flow assessment, review the wildlife rescue plan and site specific mitigation measures for residual biodiversity impacts and review the biodiversity offset design methodology and design based on international and local good practice experience. During the implementation phase, the expert will be responsible to undertake two field visits and prepare and submit midterm and final report on effectiveness on offset implementation and suggest any additional measure if necessary. b. Biodiversity Assessment Expert (60 person-days) 8. The biodiversity assessment expert will be responsible for review of existing and additional information on biodiversity status of the project affected areas, visit the project affected sited as well as the offset locations, review biodiversity assessment conducted by the borrower for biodiversity impacts due to the project and offset needs, review environmental flow assessment for effectiveness of released flows to meet biodiversity conservation needs in the stretch downstream of the dam. The expert will also review the biodiversity status of the areas proposed for offset, advise on their ecological suitability to achieve measureable conservation outcomes as offsets for the affected biodiversity and review the indicators and monitoring plan for evaluation of effectiveness of biodiversity offsets and advice on implementation.

3 3 c. The Social Assessment Expert with background in Indigenous People (60 person days) 9. The social assessment expert will be responsible for review of the proposed onsite biodiversity conservation measures as well as the proposed biodiversity offsets for their associated impacts to stakeholders on issues related to the sustainability of the offsets and their interactions with local communities. The social expert will review the socio-economic profile of inhabitants in project affected area as well as the locations identified for biodiversity offsets and provide comments on the social impact assessment of biodiversity offset plans including gender specific considerations. During the implementation stage the safeguards expert will visit the offset implementation sites and independently review the progress on implementation social safeguards in relation to involuntary resettlement and indigenous peoples development plan and community participation in the context of biodiversity offsets. 4. Specific Terms of Reference Phase I Baseline Biodiversity Studies to be conducted by NN3PC 10. The IAP is required to conduct a preliminary due diligence review of the Project based on internationally accepted criteria for such a review, specifically the review will consist of a visit to the project site and a desk stop study of the following documents: a. Environmental Impact Assessment (September 2011) b. RMR International studies: Social Action Plan and Environmental Management Plan to producing the Nam Ngum 3 Social Action Plan and Environmental Management Plan (Chapters 7, 9,10, 21, 32, 36) c. Wildlife of the Nam Ngum Basin, Lao PDR, by J.W. Duckworth, January 2010 d. Final Report by the Aquatic Environmental Specialist, Lao PDR, by Terry J. Warren, November e. Other relevant background biodiversity assessment reports; f. National biodiversity strategy to 2020, g. Legal frameworks for management of conservation areas in Lao PDR, and h. ADB Safeguard Policy Statement (2009) 11. The IAP will review the Baseline Biodiversity Assessment and comment on: a. the draft methodology for the biodiversity assessment including environmental flow assessment; b. the draft Baseline Biodiversity Assessment report including i. Biodiversity survey iv. Assessment of impacts on affected biodiversity Environmental flow assessment to conserve biodiversity in the river stretch downstream of the dam until the backwaters of NN2; The need for and adequacy of a Wildlife Rescue Plan to be implemented during the first impoundment of the reservoir in 2016; v. Compensatory reforestation vi. Recommendations for biodiversity offsets and potential biodiversity activities

4 4 v Biodiversity offset design methodology including criteria and process to select potential locations and activities to assess the biodiversity gains; c. the draft TOR for the proposed Biodiversity Offset Studies; 12. The IAP will participate in tripartite meetings among GOL, NN3PC and ADB to discuss their findings and recommendations on: a. Report on Baseline Biodiversity Assessment downstream of the dam including Environmental Flow Assessment (tentatively, July 2012) b. Report on Baseline Biodiversity Assessment for reservoir area and transmission line (tentatively March 2013) Phase II Biodiversity Offset Studies and Implementation to be conducted by GOL 13. The IAP will review and comment on: a. proposed biodiversity offset methodology including: i. Site level biodiversity offset survey; Stakeholder consultation, participation and Social Impacts Assessment (SIA) for potential offset locations; Assessment of costs and benefits of the proposed biodiversity offset plan; b. draft and final Biodiversity Offset Design reports providing advice on adequacy of proposed biodiversity offsets to address any residual impacts on biodiversity and associated natural habitats in order to achieve no net loss of biodiversity. The review will pay special attention to: i. Potential offset locations and biodiversity status. iv. Sites specific legal, policy and land use management arrangements Ecological suitability of offsets in terms of measurable conservation outcomes; Assessment of potential biodiversity gains at each location v. Social Impact Assessment of proposed offset activities on local stakeholders and their role in implementation of offsets vi. v v ix. Analysis of cost and benefits for affected stakeholders Proposed biodiversity offset activities, management and financing arrangements. Monitoring plans for the biodiversity offset implementation to measure the effectiveness of the biodiversity offsets Appropriate consultation and participatory approaches for affected communities and Indigenous Peoples in conservation areas, if any; 14. The IAP will further review the progress of implementation of biodiversity offsets program and advise corrective actions if necessary.

5 5 5. Implementation Arrangements 15. ADB will be the Executing Agency and MNRE will be the Implementing Agency. The MNRE and NN3PC will provide necessary assistance, including provision of documents without cost to the consultant, for the IAP to execute its mandate. It is envisaged that the IAP will make up to seven site visits over the duration of the services of about 6 years (tentatively November 2011 June 2017). 6. Reporting Arrangements 16. The consultants will report to MNRE and to the ADB. The IAP will submit their observations and comments in the form of reports: a. For Phase I on completion of Baseline Biodiversity Assessment covering downstream of the dam including Environmental Flow Assessment (tentatively August 2012) Baseline Biodiversity Study for reservoir and transmission line including proposed criteria for selection of offset areas and TOR for Phase II implementation (tentatively April 2013) b. For Phase II on completion of i. Inception Report of Phase II consultants (see para 11 a. and b.) (tentatively November 2012) Biodiversity Offset Design Report (see para. 11 c.) (tentatively June 2014) Implementation review reports (tentatively mid 2015, mid 2016 and mid 2017) 17. The IAP will submit its reports to the Government of Lao PDR, ADB and NN3PC simultaneously. 18. The ADB is required to disclose certain information to the public in accordance with its Public Communications Policy. The IAP reports will be posted on ADB's website except to the extent disclosure of such reports is not required under the Public Communications Policy.

6 COST ESTIMATES AND FINANCING PLAN ($'000) Total Item Cost A. Asian Development Bank 1. Consultants a. Remuneration and Per Diem i. International Consultants 281 b. International and Local Travel 116 c. Reports and Communications Miscellaneous Administration and Support Costs Contingencies 65 Subtotal (A) 500 B. Government Financing 1. Office Accommodation a Remuneration and Per Diem of Counterpart Staff Others 10 Subtotal (B) 30 Total 530 Notes: (a) MNRE will provide furnished office space for the consultants incl. telephone line and internet Source: ADB staff estimates

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:PHI 30546 TECHNICAL ASSISTANCE (Financed by the Japan Special Fund) TO THE REPUBLIC OF THE PHILIPPINES FOR INSTITUTIONAL STRENGTHENING FOR THE DEVELOPMENT OF THE NATURAL GAS

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE Appendix 3 9 PROJECT PREPARATORY TECHNICAL ASSISTANCE A. Justification 1. A project preparatory technical assistance (PPTA) is required to prepare all documents for the sector project framework and core

More information

USING CUMULATIVE IMPACT ASSESSMENT AND SUSTAINABILITY TOOLS FOR RIVER BASIN MANAGEMENT Peter John Meynell Chiang Mai, 11 March 2011

USING CUMULATIVE IMPACT ASSESSMENT AND SUSTAINABILITY TOOLS FOR RIVER BASIN MANAGEMENT Peter John Meynell Chiang Mai, 11 March 2011 USING CUMULATIVE IMPACT ASSESSMENT AND SUSTAINABILITY TOOLS FOR RIVER BASIN MANAGEMENT Peter John Meynell Chiang Mai, 11 March 2011 Water Governance in a River Basin Establishing water governance in the

More information

National Policy on Environmental and Social Sustainability of the Hydropower Sector in Lao PDR

National Policy on Environmental and Social Sustainability of the Hydropower Sector in Lao PDR National Policy on Environmental and Social Sustainability of the Hydropower Sector in Lao PDR By Xaypaseuth PHOMSOUPHA Deputy Director General Department of Energy Promotion and Development Ministry of

More information

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR Overview of Presentation 1. Objectives of the Consultancy 2. Hydropower in Myanmar 3. Draft Table of Contents 4.

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Date ISDS Prepared/Updated: 23-Jul-2012

More information

Nam Theun 2. TNC workshop April 2014

Nam Theun 2. TNC workshop April 2014 Nam Theun 2 1 TNC workshop April 2014 The Hydropower Project Build, Operate, Transfer 25 year concession for Nam Theun Power Co. US$1.3 Billion cost, financed by 27 parties (1/3 Equity; 2/3 debt) Generating

More information

SUMMARY 2013 EDITION

SUMMARY 2013 EDITION SUMMARY 2013 EDITION RSAT Joint Initiative on Rapid Basin-wide Hydropower Sustainability Assessment Tool PART 1: OVERVIEW OF THE RSAT The RSAT is designed as an integrative tool to assess hydropower development

More information

2.29 XE KONG 5 HYDROPOWER PROJECT

2.29 XE KONG 5 HYDROPOWER PROJECT 2.29 XE KONG 5 HYDROPOWER PROJECT The Xe Kong 5 Hydropower Project is located in Kaleum District, Xe Kong Province on the upper reaches of the Xe Kong, immediately upstream of the proposed Xe Kong 4 Hydropower

More information

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme

PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME. 2 Objective of the Phase II Environmental and Social Programme PUBLIC DISCLOSURE OF PHASE II ENVIRONMENTAL AND SOCIAL MANAGEMENT PROGRAMME 1 Introduction and Background To meet its environmental and social obligations and commitments, the Lesotho Highlands Development

More information

COMPLIANCE REPORT ASSESSING APPLICATION OF ARTICLE 11 b (6) OF EMISSIONS TRADING DIRECTIVE TO HYDROELECTRIC PROJECT ACTIVITIES EXCEEDING 20 MW

COMPLIANCE REPORT ASSESSING APPLICATION OF ARTICLE 11 b (6) OF EMISSIONS TRADING DIRECTIVE TO HYDROELECTRIC PROJECT ACTIVITIES EXCEEDING 20 MW COMPLIANCE REPORT ASSESSING APPLICATION OF ARTICLE 11 b (6) OF EMISSIONS TRADING DIRECTIVE TO HYDROELECTRIC PROJECT ACTIVITIES EXCEEDING 20 MW Section 1: Description of the project (Final Version of 17

More information

TERMS OF REFERENCE FOR CONSULTANTS. Preparing the Central Cross Island Road Upgrading Project in Samoa

TERMS OF REFERENCE FOR CONSULTANTS. Preparing the Central Cross Island Road Upgrading Project in Samoa A. Consulting Firm TERMS OF REFERENCE FOR CONSULTANTS Preparing the Central Cross Island Road Upgrading Project in Samoa 1. Project Background 1. Samoa s land transport depends on key arterial roads that

More information

TERMS OF REFERNCE FOR CONSULTANTS

TERMS OF REFERNCE FOR CONSULTANTS Preparing the Advanced Knowledge and Skills for Sustainable Growth Project (TRTA INO 50395) TERMS OF REFERNCE FOR CONSULTANTS 1. Four consultants will be recruited individually using single source and

More information

TERMS OF REFERENCE FOR CONSULTANTS (Phase 1)

TERMS OF REFERENCE FOR CONSULTANTS (Phase 1) Strengthening Infrastructure Capacity and Innovation for Inclusive Growth TERMS OF REFERENCE FOR CONSULTANTS (Phase 1) I. OBJECTIVE AND PURPOSE OF ASSIGNMENT 1. The technical assistance (TA) will supplement

More information

PROJECT PREPARATORY TECHNICAL ASSISTANCE

PROJECT PREPARATORY TECHNICAL ASSISTANCE A. Justification PROJECT PREPARATORY TECHNICAL ASSISTANCE 1. The proposed project for additional financing involves implementing a carbon capture, utilization, and storage (CCUS) pilot project at the Tianjin

More information

GMS: Flood and Drought Risk Management and Mitigation Project

GMS: Flood and Drought Risk Management and Mitigation Project GMS: Flood and Drought Risk Management and Mitigation Project TERMS OF RERFERENCE (TOR) Consultants for Support to National Flood Forecasting Center (NFFC) and to Improve Hydraulic Design Standards 1.

More information

Mongolia: Reforms in Technical and Vocational Education and Training in Mongolia (Preparing the Skills for Employment Project)

Mongolia: Reforms in Technical and Vocational Education and Training in Mongolia (Preparing the Skills for Employment Project) Technical Assistance Report Project Number: 45010 Project Preparatory Technical Assistance (PPTA) December 2012 Mongolia: Reforms in Technical and Vocational Education and Training in Mongolia (Preparing

More information

Environmental and Social Impact Assessment and Strategic Environmental and Social Assessment at the World Bank

Environmental and Social Impact Assessment and Strategic Environmental and Social Assessment at the World Bank Environmental and Social Impact Assessment and Strategic Environmental and Social Assessment at the World Bank Agi Kiss Regional Safeguards Advisor, Europe and Central Asia Region The World Bank Economic

More information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized Generic Terms of Reference (ToR) for Consulting Services for Environmental Impact Assessment (EIA) and Preparation of Environmental Management Plans (EMPs) for Transport Sector (Bridge and/or Road) Projects

More information

Aquanova Nyzhniy Bystryi small hydropower plant project non-technical summary

Aquanova Nyzhniy Bystryi small hydropower plant project non-technical summary Aquanova Nyzhniy Bystryi small hydropower plant project non-technical summary 1 Introduction This document provides a non-technical overview of Aquanova Development Nyzhniy Bystryi Hydropower Plant project

More information

Xayaburi Hydropower Project

Xayaburi Hydropower Project The 5 th Regional Stakeholder Forum Basin Planning and Environmental Management 20-21 September 2018 Landmark Hotel, Vientiane, Lao PDR Review of the Design Changes made for the Xayaburi Hydropower Project

More information

COMPLIANCE APPRAISAL: SUMMARY OF RESULTS

COMPLIANCE APPRAISAL: SUMMARY OF RESULTS May 16, 2016 Office of the Compliance Advisor Ombudsman (CAO) COMPLIANCE APPRAISAL: SUMMARY OF RESULTS Enso Albania (IFC Project #30979) Albania On September 28, 2011, IFC approved an early stage equity

More information

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Kabeli A Hydroelectric Project. Component 2: Ministry of Energy

PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE. Kabeli A Hydroelectric Project. Component 2: Ministry of Energy Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Project Name PROJECT INFORMATION DOCUMENT (PID) APPRAISAL STAGE Kabeli A Hydroelectric

More information

TECHNICAL ASSISTANCE RAJASTHAN RENEWABLE ENERGY CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT

TECHNICAL ASSISTANCE RAJASTHAN RENEWABLE ENERGY CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT TECHNICAL ASSISTANCE RAJASTHAN RENEWABLE ENERGY CAPACITY DEVELOPMENT AND IMPLEMENTATION SUPPORT A. Introduction 1. The State of Rajasthan is committed and poised to becoming a leader in the generation,

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3946. Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3946. Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 01/26/2009 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

SEMINAR ON CUMULATIVE IMPACT ASSESSMENT & MANAGEMENT

SEMINAR ON CUMULATIVE IMPACT ASSESSMENT & MANAGEMENT SEMINAR ON CUMULATIVE IMPACT ASSESSMENT & MANAGEMENT 29 February 2016 Seminar Agenda Time Item 09.00 Agenda/objectives 09.05 Impact Assessment Toolbox: Situating the CIA 09.15 What is Cumulative Impact

More information

ASIAN DEVELOPMENT BANK

ASIAN DEVELOPMENT BANK ASIAN DEVELOPMENT BANK TAR:PRC 37596 TECHNICAL ASSISTANCE TO THE PEOPLE'S REPUBLIC OF CHINA FOR PREPARING THE GUANGXI NANNING URBAN INFRASTRUCTURE DEVELOPMENT PROJECT September 2004 CURRENCY EQUIVALENTS

More information

Environmental and Social Impact Assessment for Rogun Hydro Power Plant

Environmental and Social Impact Assessment for Rogun Hydro Power Plant Environmental and Social Impact Assessment for Rogun Hydro Power Plant Environmental and Social Impacts July 14-19, 2014 Content Project History Purpose and Scope The Project Area The Project The Project

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5136 Project Name

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5136 Project Name PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.: AB5136 Project Name Luhri Hydro Electric Project Region SOUTH ASIA Sector Power (50%); Renewable energy (50%) Project ID P102843 Borrower(s)

More information

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI

220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI 220 KV TRANSMISSION LINE AKHALTSIKHE-BATUMI ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT TERMS OF REFERENCE Transmission line Akhalsikhe-Batumi Georgia Terms of Reference for Tender docs and ESIA 2 1 PROJECT

More information

The First Mekong River Commission Summit 2010

The First Mekong River Commission Summit 2010 15th Anniversary 5 April 1995 5 April 2010 The First Mekong River Commission Summit 2010 The Mekong Basin as a source of economic prosperity The water resources of the 795,000 square kilometer Mekong Basin

More information

Implementing the Greater Mekong Subregion Human Resource Development Strategic Framework and Action Plan (Phase 2)

Implementing the Greater Mekong Subregion Human Resource Development Strategic Framework and Action Plan (Phase 2) Technical Assistance Report Project Number: 46071 Regional Policy and Advisory Technical Assistance (R-PATA) December 2013 Implementing the Greater Mekong Subregion Human Resource Development Strategic

More information

Aquatic habitat offset to address cumulative impacts in the context of hydropower development

Aquatic habitat offset to address cumulative impacts in the context of hydropower development Aquatic habitat offset to address cumulative impacts in the context of hydropower development Special IAIA Symposium on Biodiversity & Ecosystem Services in Impact Assessment Aquatic Biodiversity and Ecological

More information

Terms of Reference I. PROJECT MANAGEMENT SUPPORT AND CAPACITY DEVELOPMENT CONSULTANTS

Terms of Reference I. PROJECT MANAGEMENT SUPPORT AND CAPACITY DEVELOPMENT CONSULTANTS Terms of Reference I. PROJECT MANAGEMENT SUPPORT AND CAPACITY DEVELOPMENT CONSULTANTS A. Background 1. The Government of the Socialist Republic of Viet Nam, has requested a loan and grant from the Asian

More information

TECHNICAL ASSISTANCE. Restoration of Wetlands in Dalai Lake Nature Reserve of Inner Mongolia

TECHNICAL ASSISTANCE. Restoration of Wetlands in Dalai Lake Nature Reserve of Inner Mongolia Inner Mongolia Road Development Project (RRP PRC 43029) TECHNICAL ASSISTANCE Restoration of Wetlands in Dalai Lake Nature Reserve of Inner Mongolia A. Introduction 1. The Government of Inner Mongolia Autonomous

More information

RFP No: WB/MOF/MINIS/CS/CQS/1.1.9 (d)/2014. A. Background

RFP No: WB/MOF/MINIS/CS/CQS/1.1.9 (d)/2014. A. Background Terms of Reference for a Cumulative Impacts Assessment in Baganuur Coal Mine in Mongolia to be financed by Mining Infrastructure Investment Support Project (MINIS) RFP No: WB/MOF/MINIS/CS/CQS/1.1.9 (d)/2014

More information

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region

PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE. Rural Electrification and Transmission Interconnection Project (RETP) Region PROJECT INFORMATION DOCUMENT (PID) CONCEPT STAGE Report No.:45460 Project Name Rural Electrification and Transmission Interconnection Project (RETP) Region EAST ASIA AND PACIFIC Sector Energy Project ID

More information

RFP No: WB/MOF/MINIS/CS/CQS/1.1.14/2014

RFP No: WB/MOF/MINIS/CS/CQS/1.1.14/2014 Terms of Reference for a Cumulative Impacts Assessment in Tavan Tolgoi Coal Mine Region in Mongolia to be financed by Mining Infrastructure Investment Support Project (MINIS) RFP No: WB/MOF/MINIS/CS/CQS/1.1.14/2014

More information

(Financed by the Japan Fund for Poverty Reduction)

(Financed by the Japan Fund for Poverty Reduction) Technical Assistance Report Project Number: 45124 Regional Capacity Development Technical Assistance (R-CDTA) December 2011 Smart Grid Capacity Development (Financed by the Japan Fund for Poverty Reduction)

More information

1.2 BIODIVERSITY IN EA AT THE WORLD BANK Mainstreaming Biodiversity in Development

1.2 BIODIVERSITY IN EA AT THE WORLD BANK Mainstreaming Biodiversity in Development 1.2 BIODIVERSITY IN EA AT THE WORLD BANK 1.2.1 Mainstreaming Biodiversity in Development The World Bank s Mainstreaming Biodiversity in Development (1995) sets out how the Bank can best direct efforts

More information

ASIAN DEVELOPMENT BANK Operations Evaluation Department

ASIAN DEVELOPMENT BANK Operations Evaluation Department ASIAN DEVELOPMENT BANK Operations Evaluation Department PROJECT PERFORMANCE AUDIT REPORT ON THE NAM LEUK HYDROPOWER PROJECT IN LAO PEOPLE'S DEMOCRATIC REPUBLIC In this electronic file, the report is followed

More information

10 Project Cost Estimation

10 Project Cost Estimation 10 Project Cost Estimation Contents 10 Project Cost Estimation... 1 10.1 Project Overview... 1 10.2 Principles of Project Cost Estimation... 2 10.3 Data Basis and Assumptions for Project Cost Estimation...

More information

ENVIRONMENT ASSESSMENT TOOLS FOR IMPROVING THE SUSTAINABILITY OF DEVELOPMENT IN THE MEKONG REGION

ENVIRONMENT ASSESSMENT TOOLS FOR IMPROVING THE SUSTAINABILITY OF DEVELOPMENT IN THE MEKONG REGION ENVIRONMENT ASSESSMENT TOOLS FOR IMPROVING THE SUSTAINABILITY OF DEVELOPMENT IN THE MEKONG REGION INTRODUCTION This brief introduces the main environmental assessment tools now used in the Mekong region

More information

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT EXTERNAL/INDEPENDENT SOCIAL, ENVIRONMENTAL, HEALTH, AND SAFETY COMPLIANCE MONITORING

NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT EXTERNAL/INDEPENDENT SOCIAL, ENVIRONMENTAL, HEALTH, AND SAFETY COMPLIANCE MONITORING NEWMONT GHANA GOLD LTD. AHAFO SOUTH PROJECT EXTERNAL/INDEPENDENT SOCIAL, ENVIRONMENTAL, HEALTH, AND SAFETY COMPLIANCE MONITORING GENERAL TERMS OF REFERENCE APRIL 2006 BACKGROUND Newmont Ghana Gold Ltd.

More information

SUSTAINABLE HYDROPOWER DEVELOPMENT A NORWEGIAN-GEORGIAN COOPERATION PROGRAM. A Citizen s Guide. Communication and Hydropower EIA

SUSTAINABLE HYDROPOWER DEVELOPMENT A NORWEGIAN-GEORGIAN COOPERATION PROGRAM. A Citizen s Guide. Communication and Hydropower EIA Communication and Hydropower EIA September, 2014 Dhillion, S.S. and Bakhtadze, M. 2014. A Citizen s Awareness Guide: Communication and Hydropower EIA. Sustainable Hydropower Development in Georgia. Report

More information

Two Case Studies from USAID s Multilateral Development Bank Project Review Team

Two Case Studies from USAID s Multilateral Development Bank Project Review Team IAIA18 Conference Proceedings Environmental Justice in Societies in Transition 38 th Annual Conference of the International Association for Impact Assessment 16-19 May 2018 Durban Intl. Convention Center

More information

SOCIAL DEVELOPMENT PLAN

SOCIAL DEVELOPMENT PLAN Nam Theun 2 Hydroelectric Project SOCIAL DEVELOPMENT PLAN ADDENDA AND SUPPLEMENTARY INFORMATION, JANUARY 2005 VOLUME 1: INTRODUCTION AND CROSS CUTTING ISSUES VOLUME 2: NAKAI PLATEAU EMDP AND RAP VOLUME

More information

Comments on CNR s report for the Government of Laos on the Xayaburi Dam June 2012

Comments on CNR s report for the Government of Laos on the Xayaburi Dam June 2012 Comments on CNR s report for the Government of Laos on the Xayaburi Dam June 2012 In April 2011, the four governments of the Mekong River Commission (MRC) Cambodia, Laos, Thailand, and Vietnam met to discuss

More information

EFFECTS OF DAMS ON DOWNSTREAM RESERVOIR FISHERIES, CASE OF NAM NGUM

EFFECTS OF DAMS ON DOWNSTREAM RESERVOIR FISHERIES, CASE OF NAM NGUM ISSN 0859-290X, Vol. 4, No. 2 December 1998 EFFECTS OF DAMS ON DOWNSTREAM RESERVOIR FISHERIES, CASE OF NAM NGUM By Roel Schouten* For the sustainable development of the Nam Ngum watershed, it is becoming

More information

2.16 NAM POT HYDROPOWER PROJECT

2.16 NAM POT HYDROPOWER PROJECT 2.16 NAM POT HYDROPOWER PROJECT Nam Pot is a hydropower project of around 20 to 25 MW located in Xiangkhouang Province. Due to its size, location and economics, Nam Pot project is best suited to a domestic

More information

Some aspects of the sediment transit on the Mekong river in relation with hydropower development

Some aspects of the sediment transit on the Mekong river in relation with hydropower development Some aspects of the sediment transit on the Mekong river in relation with hydropower development Daniel Loudière Société Hydrotechnique de France A presentation in three parts - the situation when starting

More information

2.6 NAM FA HYROPOWER PROJECT

2.6 NAM FA HYROPOWER PROJECT 2.6 NAM FA HYROPOWER PROJECT The Nam Fa Project is located in Bokeo Province on the Nam Fa (Nam Pha). The layout of the Project is shown in the attached plan. The project configuration developed for the

More information

Preparing the Greater Mekong Subregion Flood and Drought Risk Management and Mitigation Project

Preparing the Greater Mekong Subregion Flood and Drought Risk Management and Mitigation Project Regional Technical Assistance Report Project Number: 40190 April 2008 Preparing the Greater Mekong Subregion Flood and Drought Risk Management and Mitigation Project (Financed by the Japan Special Fund)

More information

The World Bank. Central Asia Energy Water Development Program

The World Bank. Central Asia Energy Water Development Program The World Bank Central Asia Energy Water Development Program ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT FOR THE PROPOSED ROGUN HYDROPOWER AND REGIONAL WATER RESERVOIR PROJECT TERMS OF REFERENCE INDEPENDENT

More information

TERMS OF REFERENCE FOR CONSULTANTS

TERMS OF REFERENCE FOR CONSULTANTS Implementing Innovative Approaches for Improved Water Governance (KSTA MON 51099) TERMS OF REFERENCE FOR CONSULTANTS 1. The knowledge and support technical assistance (TA) consultants will be recruited

More information

TABLE OF CONTENTS 2 CONSTRUCTION SCHEDULE 12 3 ENVIRONMENT AND SOCIAL POLICIES 14

TABLE OF CONTENTS 2 CONSTRUCTION SCHEDULE 12 3 ENVIRONMENT AND SOCIAL POLICIES 14 TABLE OF CONTENTS 1 GENERAL 1 1.1 Background of the Nam Ngiep 1 Hydropower Project 1 1.2 About the ESMMP-CP 2016 2 1.2.1 Purpose of the ESMMP-CP 2016 2 1.2.2 Scope of the ESMMP-CP 2016 2 1.3 Related Management

More information

UNRAVELING THE MYRAID OF STANDARDS AND TOOLS

UNRAVELING THE MYRAID OF STANDARDS AND TOOLS UNRAVELING THE MYRAID OF STANDARDS AND TOOLS HYDRO POWER DEVELOPMENT IN MEKONG REGION: CYCLING THROUGH FROM POLICY TO IMPLEMENTATION WORKSHOP SEPTEMBER 12-13, 2013 Basin Wide National regulations Project

More information

Concept of WSM Country Status on Watershed Management Planning Institution and Legislation relevant to WSM in Laos Application of Watershed Management

Concept of WSM Country Status on Watershed Management Planning Institution and Legislation relevant to WSM in Laos Application of Watershed Management Watershed Management in the Lao PDR Dr. Khamla Phanvilay Assoc. Prof. Dr. Sithong Thongmanivong Faculty of Forestry National University of Laos 1 Outlines of Presentation Concept of WSM Country Status

More information

EBRD and Wind Energy in Turkey and Beyond

EBRD and Wind Energy in Turkey and Beyond EBRD and Wind Energy in Turkey and Beyond Climate Investment Funds Managing the Impact of Wind Energy Development on Birds and Bats September 2012 Jack Mozingo and Robert Adamczyk Environmental and Sustainability

More information

FOR DISCUSSION ONLY. (A) ADB Safeguard Policy Statement. (C) Extent of Equivalence 2

FOR DISCUSSION ONLY. (A) ADB Safeguard Policy Statement. (C) Extent of Equivalence 2 Comparative Analysis of Lao PDR s Legal Framework and Environment Safeguards in the Environmental Safeguards Objectives: To ensure the environmental soundness and sustainability of projects and to support

More information

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives: ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP 1. Objectives The aim of the study is to achieve the following objectives: Review of existing EIA and RAP reports on sections of the line which are not

More information

Trishuli River Case Study

Trishuli River Case Study Moving from a Project-level to River Basin-level CIA: Trishuli River Case Study January 2018 Insert then choose Picture select your picture. Right click your picture and Send to back. Trishuli River Basin

More information

Report and Recommendation of the President to the Board of Directors. Proposed Grant Nepal: Project Preparatory Facility for Energy

Report and Recommendation of the President to the Board of Directors. Proposed Grant Nepal: Project Preparatory Facility for Energy Report and Recommendation of the President to the Board of Directors Project Number: 47036 September 2013 Proposed Grant Nepal: Project Preparatory Facility for Energy CURRENCY EQUIVALENTS (as of 16 August

More information

Joint Environmental Monitoring (JEM)

Joint Environmental Monitoring (JEM) The 5 th Regional Stakeholder Forum Basin Planning and Environmental Management 20-21 September 2018 Landmark Hotel, Vientiane, Lao PDR Joint Environmental Monitoring (JEM) Contents of Presentation Background

More information

Tanahu Hydropower Limited

Tanahu Hydropower Limited Tanahu Hydropower Limited (A subsidiary company of Nepal Electricity Authority) Trade Tower Building, 4 th Floor, Thapathali, Kathmandu, Website: http://www.thl.com.np NEWS LETTER - 074/075-18 February,

More information

TERMS OF REFERENCE FOR TA CONSULTANTS

TERMS OF REFERENCE FOR TA CONSULTANTS Skills for Competitiveness Project (TRTA CAM 50394) TERMS OF REFERENCE FOR TA CONSULTANTS A. Individual consultants for preliminary analytical work 1. Industrial Human Resource Development Specialist (2.5

More information

Report and Recommendation of the President to the Board of Directors

Report and Recommendation of the President to the Board of Directors Report and Recommendation of the President to the Board of Directors Project Number: 43281 August 2010 Proposed Grant and Administration of Technical Assistance Grant Nepal: Detailed Engineering Study

More information

KYNSHI-I HEP (270 MW), MEGHALAYA

KYNSHI-I HEP (270 MW), MEGHALAYA ANNEXURE-IV PROPOSED TERMS OF REFERENCE FOR EIA/EMP FOR KYNSHI (270 MW) HYDROELECTRIC PROJECT IN MEGHALAYA AS PER THE MODEL TERMS OF REFERENCE ISSUED BY MOEF & CC FOR NORTH-EAST PROJECTS I. SALIENT FEATURES

More information

PROGRAM PREPARATORY TECHNICAL ASSISTANCE. 1. The program preparatory technical assistance (TA) is required to:

PROGRAM PREPARATORY TECHNICAL ASSISTANCE. 1. The program preparatory technical assistance (TA) is required to: Appendix 3 11 A. Justification PROGRAM PREPARATORY TECHNICAL ASSISTANCE 1. The program preparatory technical assistance (TA) is required to: (i) Undertake sector preparatory work, define the scope of the

More information

Republic of Fiji: Urban Development Planning and Institutional Capacity Building

Republic of Fiji: Urban Development Planning and Institutional Capacity Building Technical Assistance Report Project Number: 47237-001 Capacity Development Technical Assistance (CDTA) December 2013 Republic of Fiji: Urban Development Planning and Institutional Capacity Building (Cofinanced

More information

Table A1 - Environmental and Social Safeguard Policies Policy Objectives and Operational Principles

Table A1 - Environmental and Social Safeguard Policies Policy Objectives and Operational Principles Operational Manual - Table A1 - Environmental and Social Safeguard Policies Policy and Staff Connections- World Bank Intranet WB External Site WBG Directory Help Site Map Feedback Home News & Events Countries

More information

Mekong River Commission

Mekong River Commission Mekong River Commission 184 Fa Ngoum Road, P.O. Box 6101, 184 Fa Ngoum Road, Unit 18 Ban Sithane Neua, Sikhottabong District, Vientiane 01000, Lao PDR Telephone: (856-21) 263 263. Facsimile: (856-21) 263

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3842. Date ISDS Prepared/Updated: 03/09/2009 I. BASIC INFORMATION. A. Basic Project Data

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Report No.: AC3842. Date ISDS Prepared/Updated: 03/09/2009 I. BASIC INFORMATION. A. Basic Project Data Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Date ISDS Prepared/Updated: 03/09/2009 I. BASIC INFORMATION A. Basic Project Data INTEGRATED

More information

Performance Requirements

Performance Requirements Environmental and Social Policy 15 Performance Requirements PR 1: Environmental and Social Appraisal and Management Introduction 1. The EBRD considers it important that all companies receiving EBRD financing

More information

Guidelines for the Environmental and Social Screening of Activities Proposed under the Simplified Approval Process

Guidelines for the Environmental and Social Screening of Activities Proposed under the Simplified Approval Process Guidelines for the Environmental and Social Screening of Activities Proposed under the Simplified Approval Process 10 January 2018 Introduction 1. Environmental and social screening is an essential and

More information

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number:

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: Comprehensive Study Scoping Document for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: 07-03-26302 Prepared pursuant to Subsection 21(1) of the Canadian Environmental Assessment

More information

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project

Environmental Impact Assessment. GEO: East West Highway (Khevi Ubisa Section) Improvement Project May 2018 Third Draft GEO: East West Highway (Khevi Ubisa Section) Improvement Project Section F2 of the Khevi Ubisa Shorapani Argveta Road (E60 Highway) Part 6 Appendices A D Prepared by JV IRD Engineering

More information

BURUNDI, RWANDA, TANZANIA

BURUNDI, RWANDA, TANZANIA Financing water for growth in Africa Rusumo Falls: water for power generation and multipurpose use, Burundi, Rwanda, Tanzania Summary The Regional Rusumo Falls Hydroelectric and Multipurpose Project is

More information

MRC's role in relation to planning and implementation of mainstream dams and its strategic assessment framework

MRC's role in relation to planning and implementation of mainstream dams and its strategic assessment framework MRC's role in relation to planning and implementation of mainstream dams and its strategic assessment framework Jeremy Bird, Chief Executive Officer MRC Secretariat 1 Average flow in Kratie 1960-2004 Flow

More information

LOCAL AUTHORITY AND SUBPROJECT SELECTION CRITERIA

LOCAL AUTHORITY AND SUBPROJECT SELECTION CRITERIA Additional Financing of Local Government Enhancement Sector Project (RRP SRI 42759) LOCAL AUTHORITY AND SUBPROJECT SELECTION CRITERIA A. Eligible Local Authority and Subprojects 1. Unless otherwise agreed

More information

TECHNICAL ASSISTANCE

TECHNICAL ASSISTANCE TECHNICAL ASSISTANCE Additional Financing of Food and Nutrition Social Welfare Project (RRP MON 42322) A. Introduction 1. Background. The Government of Mongolia requested the Asian Development Bank (ADB)

More information

The World Bank s Safeguards Policies in Context of Hydropower Projects International Conference on Sustainable Hydropower in the Dinaric Arc

The World Bank s Safeguards Policies in Context of Hydropower Projects International Conference on Sustainable Hydropower in the Dinaric Arc The World Bank s Safeguards Policies in Context of Hydropower Projects International Conference on Sustainable Hydropower in the Dinaric Arc Dubrovnik, 07 October 2009 Structure of Presentation 1. A Bit

More information

ASIAN DEVELOPMENT BANK TAR: INO 32359

ASIAN DEVELOPMENT BANK TAR: INO 32359 ASIAN DEVELOPMENT BANK TAR: INO 32359 TECHNICAL ASSISTANCE (Cofinanced by the Japan Special Fund) TO THE REPUBLIC OF INDONESIA FOR PREPARING THE PARTICIPATORY IRRIGATION SECTOR PROJECT December 2001 CURRENCY

More information

A CITIZEN S GUIDE. Awareness Raising on Hydropower Project Development and EIA for Citizens (part I)

A CITIZEN S GUIDE. Awareness Raising on Hydropower Project Development and EIA for Citizens (part I) A CITIZEN S GUIDE Awareness Raising on Hydropower Project Development and EIA for Citizens (part I) Prepared by Lasha Gurgenidze and Tamar Mtvarelidze with Dr. Shivcharn S. Dhillion May, 2014 Content of

More information

MEKONG RIVER COMMISSION

MEKONG RIVER COMMISSION MEKONG RIVER COMMISSION THE COUNCIL STUDY Key Findings from the Study on Sustainable Management and Development of the Mekong River Basin, including Impacts of Mainstream Hydropower Projects Version 0.3

More information

Text Andrew Tanner. Sixtus Tohlang.

Text Andrew Tanner. Sixtus Tohlang. Text Andrew Tanner C4 SEED JV Project Manager andrew.tanner@af.aurecongroup.com Sixtus Tohlang Chief Delegate LHWC Lesotho (GOL) mabesa@lhwc.org.ls Peter Van Niekerk Head: Delegation Study Management Committee

More information

LESOTHO HIGHLANDS WATER PROJECT - PHASE II

LESOTHO HIGHLANDS WATER PROJECT - PHASE II LESOTHO HIGHLANDS WATER PROJECT - PHASE II ABSTRACT The Lesotho Highlands Water Project (LHWP) is a multipurpose project which, through the construction of a series of dams and tunnels, manages some of

More information

ATTACHED TECHNICAL ASSISTANCE: CAPACITY DEVELOPMENT FOR INDUSTRIAL CORRIDOR MANAGEMENT IN ANDHRA PRADESH

ATTACHED TECHNICAL ASSISTANCE: CAPACITY DEVELOPMENT FOR INDUSTRIAL CORRIDOR MANAGEMENT IN ANDHRA PRADESH Visakhapatnam Chennai Industrial Corridor Development Program (RRP IND 48434) ATTACHED TECHNICAL ASSISTANCE: CAPACITY DEVELOPMENT FOR INDUSTRIAL CORRIDOR MANAGEMENT IN ANDHRA PRADESH A. Introduction 1.

More information

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE

INTEGRATED SAFEGUARDS DATA SHEET CONCEPT STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Report No.: Date ISDS Prepared/Updated: March 10, 2015 I. BASIC INFORMATION A. Basic

More information

Mongolia: Preparing the Energy Efficiency and Urban Environment Improvement Project (Financed by the Japan Fund for Poverty Reduction)

Mongolia: Preparing the Energy Efficiency and Urban Environment Improvement Project (Financed by the Japan Fund for Poverty Reduction) Technical Assistance Report Project Number: 46343 Project Preparatory Technical Assistance (PPTA) April 2014 Mongolia: Preparing the Energy Efficiency and Urban Environment Improvement Project (Financed

More information

INLAND WATERWAYS AUTHORITY OF INDIA (Ministry of Shipping, Government of India) Head Office : A-13, Sector 1, Noida

INLAND WATERWAYS AUTHORITY OF INDIA (Ministry of Shipping, Government of India) Head Office : A-13, Sector 1, Noida Project Management Unit (World Bank Assisted Development Project for NW-1) INLAND WATERWAYS AUTHORITY OF INDIA (Ministry of Shipping, Government of India) Head Office : A-13, Sector 1, Noida - 201301 Phone

More information

Summary Report on the Preparatory Study for Environmental and Social Considerations

Summary Report on the Preparatory Study for Environmental and Social Considerations Summary Report on the Preparatory Study for Environmental and Social Considerations October 25, 2007 1. Title of the Cooperation Project, Relevant Project Report 1-1 Title of the cooperation project Feasibility

More information

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP

Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP Darial Energy LLC Dariali Hydro Power Plant Construction and Operation Project Environmental and Social Plan, Dariali HPP Tbilisi 2014 Dariali Energy JSC, the Sponsor, is planning construction and operation

More information

Socialist Republic of Viet Nam: Capacity Building for Project Management Unit Professionalization

Socialist Republic of Viet Nam: Capacity Building for Project Management Unit Professionalization Technical Assistance Report Project Number: 48279-001 Capacity Development Technical Assistance (CDTA) May 2015 Socialist Republic of Viet Nam: Capacity Building for Project Management Unit Professionalization

More information

The LMB Sustainable Hydropower Development Strategy. Regional Power Trade Coordination Committee 24 Nay Pyi Taw, 20 June 2018

The LMB Sustainable Hydropower Development Strategy. Regional Power Trade Coordination Committee 24 Nay Pyi Taw, 20 June 2018 The LMB Sustainable Hydropower Development Strategy Regional Power Trade Coordination Committee 24 Nay Pyi Taw, 20 June 2018 The Lower Mekong Basin Most of Cambodia Most of Lao PDR North-East Thailand

More information

BACKGROUND INFORMATION DOCUMENT (BID)

BACKGROUND INFORMATION DOCUMENT (BID) BACKGROUND INFORMATION DOCUMENT (BID) BAYNES HYDROPOWER PROJECT Background In 1969 the Governments of Portugal and South Africa entered into an agreement on the first phase of development of the water

More information

Safeguard Requirements And the Framework Process

Safeguard Requirements And the Framework Process Safeguard Requirements And the Framework Process The World Bank Europe & Central Asia Region Biskek,Tblisi March/April 2008 1 Role of Bank and Borrower Bank Screens and Sets EA Category Advises Borrower

More information

Notes for NEPA for Generic Terms of Reference

Notes for NEPA for Generic Terms of Reference TERMS OF REFERENCE IIRRIIGATIION AND WATER MANAGEMENT Notes for NEPA for Generic Terms of Reference This generic Terms of Reference (TOR) is applicable to the construction and/or the development of Irrigation

More information

AFRICAN DEVELOPMENT BANK GROUP REQUEST FOR EXPRESSIONS OF INTEREST

AFRICAN DEVELOPMENT BANK GROUP REQUEST FOR EXPRESSIONS OF INTEREST AFRICAN DEVELOPMENT BANK GROUP REQUEST FOR EXPRESSIONS OF INTEREST ENVIRONMENT AND CLIMATE CHANGE DIVISION ENERGY, ENVIRONMENT AND CLIMATE CHANGE DEPARTMENT Expressions of interest are being requested

More information

Hydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) This summary was produced by the

Hydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) This summary was produced by the Hydropower Project License Summary KERN RIVER, CA KERN CANYON HYDROELECTRIC PROJECT (P-178) Photo Credit: Bakersfield.com This summary was produced by the Hydropower Reform Coalition KERN RIVER, CA KERN

More information