Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

Similar documents
CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

A Trenchless Approach to Lift Station Elimination

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Trenchless Technology

Trenchless Pipeline Crossings

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY

Kathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016

Agenda for Today s Workshop

FUSIBLE PVC PIPE SYSTEMS Fusible C-900 Fusible C-905 FPVC

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill

Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River

North End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

5/16/2018. New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters. Dr. Marc Peters, Herrenknecht AG. Highlights.

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo

The City of Sergeant Bluff, IA Chooses Pilot Tube Microtunneling over Open Trench Construction

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

WARNING DO NOT BID ON THIS PROJECT

Section HORIZONTAL DIRECTIONAL DRILLING. 1. Installing water line by directional drilling methods.

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

Balancing Trenchless Permitting Requirements During HDD Design and Construction

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

SECTION UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD)

Design of pipeline installation D-GEO PIPELINE

Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic Fracture Factor of Safety

Design of pipeline installation. D-Geo Pipeline

DIVISION 33 UTILITIES SPECIFICATION : HORIZONTAL DIRECTIONAL DRILLING

Multiple Design Challenges Require Multiple Installation Techniques for High Pressure Water Line

The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump

E-Power Pipe : A new trenchless method for underground cable installation

LARGE DIAMETER HDD PROJECT FOR LAVWMA WESTERN TERMINUS

Sliplining 36-in. PCCP with Fusible PVC - DC Water's Long-Term Control Plan 'Division E'

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

Design of a 7,000 LF, Single Insertion Slipline Rehabilitation Project

Dig that Creek or Tunnel that Creek? Case Study of Crossing San Tomas Aquino Creek with an Inverted Sewer Siphon in Santa Clara, California

SECTION HORIZONTAL DIRECTIONAL DRILLING

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

ITEM 432 TUNNEL CONSTRUCTION

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

B. All materials to be installed shall be purchased in accordance with all applicable provisions of the Buy American Act.

REDUCING RISK AND VISITOR IMPACTS

Pearl City Force Main Repair Uses Sliplining Installation Method

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

Use of Jet Grouting in Challenging Infrastructure Renewal Situations in Hawaii

Problems Realized with Contractor-Proposed Pilot Tube Auger Boring

CC1602 Microtunneling

2013 ASCE Agenda. Microtunneling in Difficult Ground Craig Camp. Microtunneling Characteristics (NASTT) Akkerman MTBM Introduced 1995

PARRIS ISLAND FORCE MAIN PROJECT CREATES RECORD HDD INSTALLATION FOR PLASTIC PIPE

Reinforced Concrete Microtunnelling Pipe Designed for Project Conditions and MTBM Machines

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY

Dahlia Ponds Tunnel Project. Presented By: Nathan Soule, PE, PG Brierley Associates & Brenden Tippets, Project Executive, BTrenchless

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

SECTION TRENCHLESS INSTALLATION

Strength and Durability for Life. APPLICATIONS Horizontal Directional Drilling with Ductile Iron Pipe

A number of abbreviations and technical terms have been used in this guideline:

PUMPING STATION CONSOLIDATION AND TRENCHLESS INSTALLATION CASE STUDY

HORIZONTAL DIRECTIONAL DRILLING WITH DUCTILE IRON PIPE

Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking

Experts in tunneling with Tunnel Boring Machines

Pipe Jacking. Japan Sewage Works Association

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

Analysis of Design When You Should Consider Pipe Ram Over Traditional Auger/Jack & Bore

Pipe Bursting Water Mains

HORIZONTAL DIRECTIONAL DRILLING: NEW ERA FOR UNDERGROUND UTILITIES

Pump Station Excavation

Microtunnelling. Building infrastructures and power supply systems underground, while life above continues unaffected.

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries

APPENDIX: C. Stormwater and Wastewater Construction Specification. Tauranga City Council

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

Clark Public Utilities Uses HDD for Dual Crossings of the Lewis River in Southwest Washington

MICRO-TUNNELING LARGE DIAMETER SEWER MAY BE THE BEST OPTION FOR YOU

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

Horizontal Directional Drilling

Table of Contents TOC. Chapter 14 - Trenchless Construction. 14A General Information. 14B New Construction. 14C Rehabilitation

8Re: Northern Access 2016 Project. Ischua Creek Crossing (MP 62.4) Analysis of Feasibility and Risks of Direct Pipe Installation

DIVISION 300 TRENCHING SECTION 308 BORING AND JACKING 2.2 STEEL CASING PIPE

SECTION BORING AND/OR JACKING PIPE

SPECIAL CONDITIONS FOR HORIZONTAL AUGER BORING (HAB) October, 2006

Nowadays, horizontal directional drilling rigs are. Complex crossings made easy

Sustainable Utility Construction: Methods and Techniques

TABLE OF CONTENTS PART 2

Sewer Siphon Pre-Design Report for the Santa Clara River Crossing at Vista Canyon (2009)

LOMBARDI GULCH CREEK EMERGENCY HDD UNDERCROSSING

Selecting Watermain Materials for Replacement Projects

How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E.

Geotechnical Investigations Water Main Construction

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3

PIPE JACKING. An introduction to pipe jacking prepared by the Pipe Jacking Association

November 16, 2017 Via Electronic Filing

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

SHAFT CONSTRUCTION SECANT PILE

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)

2016 International Petroleum Environmental Conference HORIZONTAL DIRECTIONAL DRILLING AND WELL INSTALLATION AT SMALL SITES

Transcription:

WATER Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons Presented by Peter Merten, PE, HR Green, Inc. and David Reuter, PE, Underground Solutions UCT Underground Construction Technology International Conference & Exhibition January 30 February 1, 2018 Ernest N. Morial Convention Center, New Orleans, Louisiana

Presentation Outline 1. Problem Definition 2. Design Process a. Trenchless Technique Selection b. Profile Geometry & Pipe Material Selection c. Plan Approvals & Permitting 3. Construction a. Overview b. Work Site Logistics c. Aerial Insertion d. Keys to Success 4. Lessons Learned 2

Problem Definition 3 Part of the I-29 Segment 2 Utility Replacement Project Owned by Sioux City, Iowa. New Siphon designed in 2013 & constructed in 2014. Replaces an existing Double Barrel Siphon located in IaDOT Right-Of-Way in the way of the highway expansion; specifically a bridge abutment. Located approximately 1,100-ft upstream of the original location.

Problem Definition 4 800 ft ENTRY 400 ft 500 yr EXIT FLOYD RIVER 6 ft 34 ft 30 ft 120 ft 60 ft

Problem Definition 5 Subsurface Conditions: Missouri River alluvium. High groundwater table. Random layers of sand, clayey sand, and sandy clay overlain by fatty clay and man-made fill. Bedrock was not encountered.

Problem Definition 6 UP RAIL SPUR ENTRY 2 MORE UP RAIL SPURS LEVEE UP RAILYARD DOUBLE BARREL SIPHON EXIT SOUTH LAFAYETE STREET FLOYD BLVD INDUSTRIAL FACILITY LEVEE FLOYD RIVER

Design Trenchless Technique Selection Microtunneling (MT) Alternate 24 & 30 PVC or HDPE carrier pipes bundled into a single 72 steel pipe casing. Grouted annulus. Budget level EOPC $5.3 million. 9 months to one year to construct. MT Constructability Issues Use the slurry method w/ closed face earth pressure balance tunnel boring machine (EPB-TBM). 60-ft deep bore pit shafts. Continuous dewatering. Pipe lubrication during jacking. At least one intermediate jacking station. 7

Design Trenchless Technique Selection 8 Preferred Alternate! HDD Alternate Each carrier pipe is installed in its own casing pipe. Twin siphon casing pipes are installed in parallel horizontally and vertically. Grouted annulus. Budget level EOPC $2 million. 6 months to construct. HDD Constructability Issues 36 casing pipe in 48 borehole. Requires a maxi-rig for the installation. Bend radius estimate eliminated steel and ductile iron pipe. PVC and HDPE were remaining choices.

Design Profile Geometry DRILL ENTRY/11⁰ DRILL EXIT/10⁰ FLOYD RIVER ENTRY EXIT APPROXIMATE BORE PATH LENGTH=1,500-ft 9

Design Pipe Material Selection 10 It s all about pipe stiffness! A pullback force of 235,000-lbs was estimated requiring a pipe stiffness of approximately 224 psi. Pipe stiffness, PS = (2*E/(3*(DR-1)^3))/0.149 E = Modulus of Elasticity of the pipe material, psi. DR = Dimension Ratio of the pipe section; OD/tw. HDPE has a modulus of elasticity = 100,000 psi. PVC has a modulus of elasticity = 400,000 psi. Evaluation of the pipe material choices for identical installation and external loads resulted in: For HDPE, a 36 DR13.5, BUT, a 42 DR9 is necessary to meet required inside casing diameter tolerance. For Fusible PVC, a 36 DR21 is necessary and meets the inside casing diameter tolerance.

Design Pipe Material Selection 11 AWWA Standards: C905 FPVC C906 HDPE Key is the need for a minimum casing ID = 34 in order to slipline a 30 carrier pipe with an OD of 32 (2 tolerance). A 36 HDPE DR13.5 has an ID = 32.29 (Out of tolerance by 1.71 ).

Design Plan Approvals & Permitting 12 Two key agencies from which approval was required: Union Pacific Railroad (UPRR) ~ had most stringent criteria: AREMA (AREMA 2013) Manual for Railway Engineering Sections 5.3 & 5.6. Pipe External Load Analysis. Pipe Axial Stress Analysis. Hydro-Fracture Risk. Borehole Collapse Potential. Work Site Logistics. Machine Performance Prediction. Mud Circulation, Volume & Disposal. Operation & Maintenance.

Design Plan Approvals & Permitting 13 Iowa Department of Natural Resources (DNR): Required the siphon pipelines be cased for the segments located beneath the river; and Required and obtained a variance for the use of trenchless technology. Submittal documentation structured using AREMA topic format. Includeded evaluation of worksite logistics, rig compatibility, hydro-fracing, borehole collapse, mud circulation/volume/disposal. With slight adaptation, the documentation prepared for the UPRR was submitted to the DNR for review and approval.

Construction Overview 14 General Contractor: Minger Construction of Chanhassen, Minnesota. Directional Drill Subcontractor: Gabe s Construction of Sheboygan, Wisconsin. Equipment: American Augers DD330 Maxi Rig w/ 330,000 lbs of thrust. Mud Technology MCT 1000 Recycling System w/ Tulsa TT 660 Mud Pump. Pilot hole drilled with a wireline location system.

Construction Overview 15 Drilling Process: 10-5/8 Pilot Hole. Reaming passes of 30, 42, and 52 - using a fly cutter. Final hole conditioning swab with ball reamer prior to pull-in.

Construction Overview 16 30 FPVC Carrier Pipe in 36 FPVC Casing: Full length of carrier & casing fused prior to pull-in. Carrier pipe was pre-loaded into casing. Water ballasted. 7 hour pull-in time w/ 130,000 lb max recorded pull force. Annular space grouting. 24 FPVC Carrier Pipe in 36 FPVC Casing: Full length of carrier & casing fused prior to pull-in. Carrier pipe was pre-loaded into casing. Water ballasted. 7.25 hour pull-in time w/ 140,000 lb max recorded pull force. Annular space grouting.

Construction Work Site Logistics 17 Pipe String Layout Bore Path 1,140 LF Floyd River Pipe Insertion Location Drill Rig Setup Location

Construction Work Site Logistics 18 During Design Conceptualize drill operation. Prepare a worksite layout plan. Set expectations for equipment & facility space allocation. Identify location to fuse and string pipe. Get City & DOT buy-in.

Construction Work Site Logistics 19 During construction Does the design plan work? Modifications based on contractors work plan. Discovery of unknowns? Getting the right equipment & support facilities placed at the site. Continuous coordination with City & DOT. Execution of the plan.

Construction Aerial Insertion 20

Construction Aerial Insertion 21

Construction Keys to Success 22 Space was available for a maxi-rig operation. Ability to fuse and layout the full length of pipe. Carrier pipe pre-loading. Closing of I-29 on-ramp during pull-in. Aerial insertion. Water ballasting. Communication.

Lessons Learned Defensible Constructible Design Use AREMA as a template! 23 Pipe Material Selection The right pipe for the right application its all about pipe stiffness! Worksite Logistics Designers need to do their homework! Design-Build Designer-Contractor collaboration!

Lessons Learned 24 Profile Geometry Direct correlation with pipe axial stress beware of the capstan effect! Field Adjustments / Modifications Construction means & methods flexibility! Communication Communicate-communicate-communicate!

25 QUESTIONS FROM THE AUDIENCE Ask away

26 Thank You! Peter Merten, MSCE, PE, M.ASCE, Project Engineer 16020 Swingley Ridge Road, Suite 205, Chesterfield, MO 63017 314-249-9436, packdog60@gmail.com David Reuter, PE, Vice President of Sales, Western Region 6810 Roe Avenue, Prairie Village, KS 66208 816-518-5162, dreuter@undergroundsolutions.com