DIVERSION CHANNEL OF BELO MONTE HPP

Similar documents
Clean or Dirty Energy? Challenges and Risks Associated to Belo Monte Hydroelectric Dam Complex on Xingu River Basin in the Amazon, Brazil

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

ONE DIMENSIONAL DAM BREAK FLOOD ANALYSIS FOR KAMENG HYDRO ELECTRIC PROJECT, INDIA

CURRICULUM VITAE. Born in Campina Grande, Paraiba- Brazil, on February 19, Public Profile:

PRELIMINARY DESIGN OF THE HYDRAULIC STRUCTURES DAM IN THE PISÃO RIVER

SMALL HYDRO BIG CHALLENGES Renewable Energy World Asia 2016 Martin P. Bieri. September 21, 2016

USE OF PERCOLATION WATER IN TRACTEBEL ENERGIA HYDROELECTRIC PLANTS REPLACING WATER TREATMENT STATIONS

Xayaburi Hydroelectric Power Project

Mijo River Project. Steve Hall, Spencer Taylor, Jennie Purcell Brigham Young University 4/11/2012

Reservoir on the Rio Boba

2.16 NAM POT HYDROPOWER PROJECT

Annex 5 - Hydropower Model Vakhsh

CASE STUDY OKUYOSHINO, JAPAN

Distribution Restriction Statement Approved for public release; distribution is unlimited.

Abstract. 1. Main features of the Cua Dat scheme. Hong Giang VNCOLD. Hanoi Vietnam. the Northern Central The reservoir storage purposes: - water

THE CONSTRUCTION PHASES OF THE NEW NAGA HAMMADI BARRAGE COFFERDAMS

Flood control and safety evaluation of Banqiao reservoir

Revision Nalcor Doc. No. MFA-SN-CD-0000-GT-DC C1 Date Page SLI Doc. No EC Dec-2013 ii DESIGN CRITERIA - GEOTECHNICAL

Some aspects of the sediment transit on the Mekong river in relation with hydropower development

Tangible benefits of technological prospection and prefeasibility studies in SHP projects Ing. Sergio Armando Trelles Jasso

COMMENTS BY LAO PDR ON THE MRCS TECHNICAL REVIEW REPORT OF THE PROPOSED XAYABURI DAM PROJECT

Water Resources. Associate Prof. Ahmed Moustafa Moussa Lecture -1 Lecture 4

6-5 Analysis of water storage state by the subsurface dam

Address for Correspondence

A Study on Physical Model Test for Cheongpyeong Dam Discharge Recalculation

Tulsi Prasad Phuyal Research Engineer Hydro Lab, Pulchowk, Lalitpur, Nepal

CASE STUDY JHIMRUK, NEPAL

Numerical unsteady flow model simulation during the sluice closure of Caruachi Dam

Lower Erkhuwa Hydropower Project (14.15 Mw) 1. INTRODUCTION. 1.1 General. 1.2 Establishment of the Company. 1.3 Special Features of the Project

Control and mitigation of floods along transbasin diversion channel of Mekong tributaries and Nan river, Thailand

Author: Brasil Pinheiro Machado CANABRAVA PROJECT

INITIAL INFLOW DESIGN FLOOD CONTROL SYSTEM PLAN PLANT MCMANUS ASH POND A (AP-1) 40 CFR

2.24 VIENGPHOUKA THERMAL PROJECT

THE ANTAS RIVER HYDROPOWER COMPLEX - CERAN

A Brief History of Dams in Iraq. The Case of Mosul Dam Presented to Al-Diwan, April 10, 2016 by Mosaid Al-Hussaini, Ph.D, PE

Dam Safety and Low Cost Spillway Designs

Performance improvement of headworks: a case of Kalignadaki A Hydropweor Project through physical hydraulic modelling

REHABILITATION OF THE LANGETENTAL FLOOD DIVERSION TUNNEL

2. SCOPE OF WORK Evolution of Plan of Study Hydrology ALASKA ENERGY AUTHORITY AEA ENGINEERING FEASIBILITY REPORT

Rapid Hydropower Assessment Model Identify Hydroelectric Sites Using Geographic Information Systems

MIEL I Hydroelectric Power Plant

Restoration of the Old Drava Riverbed at the ^akovec Hydropower Plant

5 Muskrat Falls Project

TECHNICAL ASSISTANCE DESCRIPTION, COST ESTIMATES AND OUTLINE TERMS OF REFERENCE

Annex V Concrete Structures Removal Plan

HPP CEBREN. Prepared by: Development and Investments Department

Hydrotechnical Design Guidelines for Stream Crossings

OPTWASTEWATER: A COMPUTER PROGRAM FOR REGIONAL WASTEWATER SYSTEM PLANNING

Evaluation of the hydrological risk during the construction phase of Kavsakbendi Dam and HEPP

Text Andrew Tanner. Sixtus Tohlang.

Modeling and Simulation of Irrigation Canals with Hydro Turbines

The Study of Reservoir Immersion of a Hydropower Station

ARHAM VEERAYATAN INSTITUTE OF ENGINEERING, TECHNOLOGY & RESEARCH Haripar (Mota Asambia), Bhuj Mandvi road, Mandvi Tal.

Vinnie Naidoo Technical Executive GIBB (Pty) Limited South Africa

Water-Energy Nexus: Economics of Hydropower

2 Hydrology Studies. 2.1 Introduction

UNIT HYDROGRAPH AND EFFECTIVE RAINFALL S INFLUENCE OVER THE STORM RUNOFF HYDROGRAPH

Transactions on Ecology and the Environment vol 19, 1998 WIT Press, ISSN

2.29 XE KONG 5 HYDROPOWER PROJECT

Chakachamna Hydro. AEA Geothermal Conference

Introduction. General Description

Utilization of Water Flow in Existing Canal System for Power Generation through Flow Acceleration Using Converging Nozzles

Pumps, Turbines, and Pipe Networks, part 2. Ch 11 Young

The Enginering Important Components of Jatibarang Dam, Semarang, Indonesia

SEMINAR ON WATER SECURITY IN BULGARIA SOFIA, SEPTEMBER 18-19, 2017 DAM SAFETY IN ROMANIA

Feasibility Assessment of Hydroelectric Power Plant in Ungauged River Basin: A Case Study

EXHIBIT B PLANT OPERATION AND RESOURCES UTILIZATION

HY-12 User Manual. Aquaveo. Contents

Lecture 7: The Amazon River (contd)

HYDRODYNAMIC MODELLING IN LARGE RESERVOIRS FOR WATER RESOURCES MANAGEMENT. Alfredo Ribeiro Neto, Carlos E.O. Dantas, José Almir Cirilo

CVEN 339 Summer 2009 Final Exam. 120 minutes allowed. 36 Students. No curve applied to grades. Median 70.6 Mean 68.7 Std. Dev High 88 Low 24.

DAM BREAK ANALYSIS & DISASTER MANAGEMENT PLAN

The Texas A&M University and U.S. Bureau of Reclamation Hydrologic Modeling Inventory (HMI) Questionnaire

Keeyask Generation Project. Physical Environment. Supporting Volume. Environmental Impact Statement

CONCEPTION OF CHIYODA EXPERIMENTAL CHANNEL

Hackensack River Flood Reduction Study Update

2.32 XESET 2 HYDROPOWER PROJECT

Interlake Tunnel Project

World Journal of Engineering Research and Technology WJERT

Water Control Structures Selected Design Guidelines Alberta Environment Page 13-1

2.6 NAM FA HYROPOWER PROJECT

QU: How do human activities disrupt drainage basin processes. AIM: To example and explain the above through examining human uses of the Amazon basin.

AN INVESTIGATION OF THE USE OF OPTIMIZATION TECHNIQUES IN THE OVERALL EFFICIENCY ANALYSIS OF HYDROPOWER PLANTS

CITY OF KIMBERLEY HYDROLOGICAL & HYDRAULIC ASSESSMENT

WATER QUALITY MODEL FOR EL CAJON AND AGUAMILPA RESERVOIRS. Edith G. Lugo. Rushit Hila. Oliver Obregon. Final Report

Techno-Economic Assessment Study Rogun HPP. Phase II Considerations. Riparian Consultations

Level 6 Graduate Diploma in Engineering Hydraulics and hydrology

11/10/2009. Lake Uist - BAKER PT. Distributor from bore to penstocks Lowest level in draft tube FSL Top of surge tank.

Q93 SAFETY. Gerald Zenz. Graz University of Technology Institute of Hydraulic Engineering and Water Resources Management

Flow Measuring Structures

SEES 503 SUSTAINABLE WATER RESOURCES HYDROELECTRIC POWER. Assist. Prof. Dr. Bertuğ Akıntuğ

Uncertainty in Hydrologic Modelling for PMF Estimation

Hydrology and Flooding

PREDICTION OF "LIPTOS" LIBDA DAM FAILURE AND BREACH'S PARAMETERS

SEES 503 SUSTAINABLE WATER RESOURCES. Floods. Instructor. Assist. Prof. Dr. Bertuğ Akıntuğ

(b) Discuss in brief shaft spillway with neat sketches. Marks 04. OR Q (2) Explain in brief USBR stilling basin. Marks 08

Renewable and Alternative Energies

Elko Project Water Use Plan. Revised for Acceptance by the Comptroller of Water Rights

SECTION IV WATERSHED TECHNICAL ANALYSIS

River Current Resource Assessment and Characterization Considering Ice Conditions

Transcription:

DIVERSION CHANNEL OF BELO MONTE HPP INTRODUCTION The diversion channel of Belo Monte HPP is an important engineering work which required the engagement of several specialties to be able to address all the environmental, technical and economic challenges of a project of its magnitude to be implemented in the Amazon region. Due to the unprecedented characteristics of the project, several innovative thinking and engineering were required to solve issues of lining definition, stability assessment, head loss calculations and construction process/planning. BELO MONTE HPP Belo Monte HPP, owned by Norte Energia S.A, is under construction near the city of Altamira, in the state of Pará Brazil in the Xingu River, which is an Amazon River s tributary. The project has a total installed capacity of 11,233MW which is divided between a main Power House with 18 Francis turbines and a total capacity of 11,000 MW and a complementary Power House with 6 Bulb turbines and a total of 233MW. The Belo Monte HPP is the second largest Brazilian Power Plant and the third largest in the world. Belo Monte HPP is a project that has been under study for many decades. It s first concept was called Kararao and had a reservoir of 1,225km² of inundated Amazon and indigenous areas. Later studies proved that a better environmental/economical solution was to displace the location of the dam axis upstream the previous position. This solution enabled to reduce the environmental impact on main tributary of Xingu River, and eliminated any interference with indigenous areas and reduced the reservoir area of the project to 478 km², a reduction of more than 50%. This optimization was only possible with the implementation of the diversion channel. The final concept of project is located upstream a big bend of the Xingu River, approximately 80 km long to take advantage of a natural 90 m topographic drop for the hydropower generation. The distance between the main dam, at the Pimental Site, where the spillway and complementary power house are located, and the main Power House is nearly 50 km. The maximum generation flow in the main Power House is 13,950 m³/s and to connect the main reservoir to an intermediate reservoir upstream the main Power House, the so called diversion channel is under construction.

Figure 1. General Layout of Belo Monte HPP KEY FEATURES The diversion channel is 16km long with a trapezoidal transversal section. Its trapezoidal section is 210m wide at the bottom, approximately 360m wide at the top and a maximum water depth of 22m. The bottom of the channel is at a constant elevation 75m.a.s.l. and the excavated soil (slopes and bottom of the channel) is lined by a selected rockfill material. There is no slope along the channel because any slope over 16km, even if minimal, would result in a considerable drop from upstream, making the construction activities considerably more complex, both in excavation and for the rockfill lining. Next to the main reservoir, the channel has a wider intake at elevation 87m.a.s.l. and a 13m high cofferdam from bank to bank of the channel in order to protect the work inside the channel during construction.

FIDIC AWARDS 2015 Figure 2. General Layout of the Diversion Channel The excavation of the channel is done both in soil and rock with a variable elevation of the rock surface along the channel, which implies that the effective hydraulic area of flow varies along the channel. The soil excavation is done with 1(Vertical):2,5(Horizontal) slopes and is lined with a rockfill layer with a selected grain size distribution. The lining rockfill size is coarser at the side slopes and finer at the bottom in order to ensure the required design head losses. The rock excavation is done with a subvertical slope of 1(Vertical):0.25(Horizontal). There is no precedent engineering experience in magnitude of such a channel for a hydroelectric power plant as the diversion channel of Belo Monte HPP. The magnitude of the diversion channel has a total excavation work of nearly 75,000,000m³ of soil and 25,000,000 m³ of rock, carried out in a record time of 5 years. The environmental constraints in projects in the Amazon Basin led to a specific design requirements for the diversion channel. The main axis of the diversion channel follows two main streams which have more than forty smaller tributaries flowing to the main streams. Particular engineering solutions were produced, especially to control these water flows in the area under excavation. The main condition was to keep these tributaries flows coming into construction area by a controlled way during the rainy season both during the construction and the operation phase. The magnitude of the rainfall in the Amazon Basin is among the highest in the world and calculations of the flows incoming to the channel through the tributaries are outstanding high flows. For this reason a drainage system was designed consisting of 18 dikes, each one 10m to 15m high with a

concrete spillway on its crest and a drainage gallery underneath. The dikes with the drainage galleries have the purpose of routing the high flows enabling their management. With this system, the natural course of the tributaries was held as close as possible to their natural condition. DESIGN Channels design is a well-known subject for hydraulic engineers all over the world. However, the magnitude of Belo Monte s diversion channel requires a special care in every aspect because the current theories were developed in general for much smaller channels. A simple extrapolation of these theories could lead to a strong negative consequence for the project, in meeting the expected head-losses. For that reason, the design of the channel was broken down in several smaller parts in order to pay the required attention, especially for the following definition: Axis Positioning Geometry of the channel Type of lining Lining rockfill grain size distribution and roughness coefficient Material stability Head-losses In the feasibility studies, the channel was defined with two parallel channels. In order to optimize the channel, nearly 15 different axes were studied and the final configuration reduced near 40% of the total excavation volume. For the geometry, different side slopes, widths and bottom elevation were studied. Side slopes and bottom elevations came to be defined mainly because of the construction methods and the width was connected to the head losses requirements. Two different types of lining were studied, concrete and rockfill. The concrete lining had the advantage of reducing the total excavation because of its smoother surface, but questions over its stability, which had to withstand a medium velocity of 2.5 m/s with no steel, and constructive difficulties led to the choice for the rockfill lining. Once the lining was defined, studies were carried out on site for the definition of the best grain size distribution for both side slopes protection and bottom in order to meet the roughness coefficients required. The studies came to the conclusion that the bottom roughness was more important for head loss then the side slopes and, for this reason, a finer and more controlled grain size distribution was adopted for the bottom lining. The above definition was done with an unidimensional hydraulic model of the channel but because of the magnitude and complexity of such channel, additional and more complex studied were carried on in order to confirm the assumptions and especially to confirm the rockfill lining stability for the design conditions. The first analysis was a reduced physical model of a straight portion of the channel where the rockfill lining of the bottom, which is finer, was simulated to verify its stability. The simulations showed that the material was stable even for higher mean velocities.

As showed in the general layout, the channel is composed of sequential curves and questions arose whether the rockfill lining in the bend stretches would suffer an additional stress due the flow velocity. To answer that question a three-dimensional mathematical hydraulic model of the channel was performed and came to the conclusion that a region, approximately 300m long, on the right bank slope will need an extra protection. The solution foresees the use of coarser rockfill in this stretch. With all the above variables defined, a two dimensional analysis of the head loss was conducted to ensure the results were consistent. CONCLUSION The magnitude of Belo Monte s diversion channel is unprecedented in engineering worldwide. The design and construction of such channel, taking into account all the environmental, technical and economic aspects proof to be a challenge for all engineers involved and the lessons learned surely will be applicable for future projects.