CONSTRUCTION UPDATE. April 2017 THIS IS PROGRESS. THIS IS AUBURN.

Similar documents
CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN.

CONSTRUCTION UPDATE. June 2017 THIS IS PROGRESS. THIS IS AUBURN.

CONSTRUCTION UPDATE FEBRUARY 2016 THIS IS AUBURN.

CONSTRUCTION UPDATE February 2019

CONSTRUCTION UPDATE November 2018

CONSTRUCTION UPDATE JUNE 2018

February 2018 THIS IS PROGRESS. THIS IS AUBURN.

CONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN.

$ % GAVIN ENGINEERING RESEARCH LABORATORY RENOVATION CLIENT: SAMUEL GINN COLLEGE OF ENGINEERING PROJECT UPDATE: JUNE MILLION

CONSTRUCTION UPDATE SEPTEMBER 2015 THIS IS AUBURN.

Auburn University Construction Project April

CONSTRUCTION UPDATE. April AUM Projects. Client: Housing and Residence Life Construction Cost: $28 million Completion Date: July 2013

Auburn University Construction Project Update March 2010

CONSTRUCTION UPDATE NOVEMBER 2015 THIS IS AUBURN.

Auburn University Construction Project Update June 2010

Oconomowoc Area School District Facility Construction Update July 27, 2018

Oconomowoc Area School District Facility Construction Update June 29, 2018

CONSTRUCTION REPORT. Zionsville Community Schools Zionsville, Indiana. October 2014 TSC NO

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement

Building Expansion Project Description. Rutgers The State University of New Jersey

Perimeter Site Improvements

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

July 15, 2010 Report No. 11 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

Civic Center Renovation News

Office of Planning, Design and Construction. Capital Program Update May 10, 2017

School Assessment Report

Collins Middle School

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

Building Excellence IV Capital Levy Projects Under Construction

Program Update. Chino Health Science Parking Lot

WILKINSON ELEMENTARY SCHOOL

June 10, 2010 Report No. 10 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY

Spring Run Assisted Living Willow Street, Pennsylvania Architectural The Pennsylvania State University Introduction

A4.01. Building Area: 69,930SF

NYC Department of Education

School Assessment Report

Scripps Ranch High School

Update on FCPS Construction/Renovation Projects. June 2016

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

Update on FCPS Construction/Renovation Projects. November 2015

Board Report. Bond Program Update:

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

FACILITIES LIFE CYCLE ANALYSIS

School of Business Project # Overall Project Cost: $26,700, Architect: Urbahn. Scheduled Completion Date: 10/2014.

Building Architecture

NYC Department of Education

Business Affairs Committee Dobo Recovery Update. February 7, 2019

SENIOR THESIS PROPOSAL STRUCTURAL REDESIGN USING STEEL FRAMING

Corsicana High School


Tech Assignment 1 University Medical Center of Princeton. Plainsboro Road, Township of Plainsboro, New Jersey

TODAY S DATE: January 24th, 2019

KENTUCKY STATE UNIVERSITY

Seattle Public Schools Building Excellence IV Projects Under Construction

School Assessment Report

Capital Projects Update

4.1.3 Project Manual

School Assessment Report

BRUCE-MONROE ELEMENTARY SCHOOL AT PARK VIEW MODERNIZATION HISTORIC PRESERVATION REVIEW

Former Special Needs Facility For Sale 110 Stephen Hands Path, Wainscott Town of East Hampton, NY

Structural Comparison between Pan Joist Concrete and Steel Frame Systems for UMCP Student Housing Building B

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

School Assessment Report

NYC Department of Education

School Assessment Report

School Assessment Report

Show how a KM database impacts: cost, time, and quality. Demonstrate how Parametric Design could be used to save time, money, and improve quality

Second Avenue Subway

Auxiliary Services 995 West Beardsley Place Salt Lake City, Utah Capital Projects Status Report October 1, 2018.

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING

Al Behrman Elementary School

Borough President and City Council Capital Funding Requests FY 2008

2019 Construction

NYC Department of Education

OBJECTIVE 1.1: To establish the acceptable use and capacity of each building.

Update on FCPS Construction/Renovation Projects. July 2016

Update on FCPS Construction/Renovation Projects. December 2015

Texas State University System Telephonic Called Board of Regents Meeting

FOR SALE. BHSMiami.com Miller Dr (SW 56 Street) Miami, FL 33156

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

Division 09 FINISHES TABLE OF CONTENTS

March 24, 2011 Report No. 17 MONTHLY CONSTRUCTION PROGRESS REPORT

Drexel Hill Middle School

BOND CONSTRUCTION UPDATE

Update on FCPS Construction/Renovation Projects. August 2016

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #142 Douthit Hills Student Community, Clemson University Project Tony Greene

Appendix J - Custom Uniformat for EDU Migration

Facilities Modernization Program Funded by Measure B Project Report

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #133 Douthit Hills Student Community, Clemson University Project Tony Greene

NYC Department of Education

STRUCTURAL CONDITION ASSESSMENT

New Hall High School Project Summary Report to the Board of Education June 3, 2015

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

MONTHLY PROGRESS REPORT

NYC Department of Education

HOT SPRINGS FIRE DEPARTMENT EVALUATION OF DOWNTOWN LEGACY STRUCTURES Savoy Hotel Thompson Building Dugan Stewart Building May 16, 2012

Yorkshire United Methodist Church

CITY OF NOVI. Police Department

SAMUEL CLEMENS ADDITIONS & RENOVATIONS ( )

Commercial Remodel Permit

Transcription:

CONSTRUCTION UPDATE April THIS IS AUBURN.

RISK MANAGEMENT AND SAFETY ADMINISTRATIVE BUILDING RISK MANAGEMENT AND SAFETY SEAY SEAY & LITCHFIELD ARCHITECTS CAM BUILDERS Entrance to the Risk Management and Safety Building. $2.8 APRIL Project Overview: This new building, within the Facilities Management Complex, will consolidate Risk Management and Safety personnel who currently utilize office space in the Leach Science Center and the Safety Annex on Camp Auburn Road. The building will include office space, meeting rooms, support space and associated parking. Construction of the building s two labs is complete. Project Update: The project is 90 percent complete. The final installation of interior finishes and painting is underway. Outside of the building, the parking lot has been paved, and the concrete sidewalks are being poured. Risk Management and Safety will occupy the facility in early May. Installation of reclaimed wood within the lobby area is complete. APRIL - CONSTRUCTION UPDATE

FOOD ANIMAL RESEARCH FACILITY COLLEGE OF VETERINARY MEDICINE FOIL WYATT ARCHITECTS AND PLANNERS NEAREN CONSTRUCTION Exterior brick masonry is complete for the Food Animal Research Facility. $3.4 MAY Project Overview: This project will construct a Food Animal Research Facility that will provide state-of-the-art capabilities for research related to large food animals, particularly cattle and sheep, in support of the College of Veterinary Medicine s mission in research and clinical education. View of the interior fence panels for the food animal stalls. Project Update: This project is 90 percent complete. The electrical and mechanical systems, ceilings and interior fence panels are complete. Epoxy floor coating will begin in early April. Final exterior grading and fencing will be complete by the end of April. Owner furnished equipment will be installed in early May. View of the tack room. APRIL - CONSTRUCTION UPDATE

AUBURN BAND PRACTICE COMPLEX COLLEGE OF LIBERAL ARTS BARGANIER DAVIS SIMS ARCHITECTS WHATLEY CONSTRUCTION Brick masonry is complete on the storage building. $3.0 MAY Project Overview: The Band Practice Complex project will construct men s and women s dressing rooms and a storage building at the Complex located off Hemlock Drive. This project also included installation of an artificial turf field in the summer of 2016. Block masonry continues on the women s dressing room. Project Update: This project is 75 percent complete. Mechanical, electrical and plumbing installation is in progress. Brick masonry is complete on the men s dressing room and storage building. Block masonry installation is ongoing for the women s dressing room building. The next step is to install metal panels on each building. Brick masonry continues on the men s dressing room. APRIL - CONSTRUCTION UPDATE

PHARMACEUTICAL RESEARCH FACILITY HARRISON SCHOOL OF PHARMACY GOODWYN MILLS CAWOOD/COOPER CARRY BAILEY-HARRIS CONSTRUCTION Metal panel installation has begun on the front of the building. $16.6 APRIL Project Overview: This project constructs a pharmaceutical research building for the Harrison School of Pharmacy. Located on the corner of South Donahue Drive and Lem Morrison Drive, it is one of two buildings under construction in the university s new Health Sciences Sector of campus. The three-story building will include pharmaceutical and interdisciplinary research laboratories and support space. Project Update: The project is 90 percent complete. Work underway on the exterior of the building includes installation of metal panels and sidewalks, as well as construction of the roadways and the parking lot. The interior is nearing completion, with final work being performed on the building systems and finishes. Final inspections and clean-up are ongoing. Installation of lab equipment is in progress. Lounge area adjacent to lab space. APRIL - CONSTRUCTION UPDATE

JORDAN-HARE STADIUM NORTH END ZONE CONCOURSE WIDENING ATHLETICS ENGINEER: LBYD J.A. LETT CONSTRUCTION Concourse widening construction site. $1.9 JUNE Project Overview: This project will widen the north end zone pedestrian concourse in Jordan-Hare Stadium. Project Update: This project is 50 percent complete. Once steel installation is complete in early April, the concrete will be poured on the metal decking. The project will temporarily stop for A-Day and the Music and Miracles Superfest Concert in late April. The project will then resume with installation of new lights and floor coating in May, after which the exterior concourse fence will be relocated. The project is on track to finish in June. Underside view of the concourse expansion s metal decking. New metal decking shows extent of concourse widening. Diagonal bracing to be removed prior to completion. APRIL - CONSTRUCTION UPDATE

THE HOTEL AT AUBURN UNIVERSITY PORTE COCHERE ADDITION COLLEGE OF HUMAN SCIENCES INOX DESIGN BL HARBERT INTERNATIONAL Glass installation is in progress. $1.2 MAY Project Overview: This project will construct a porte cochere at The Hotel at Auburn University and Dixon Conference Center entrance and make modifications to the existing front drive to improve traffic flow. Project Update: This project is 50 percent complete. Glass roof panels are currently being installed. The brick pavers and landscaping for the hotel s entryway off South College Street will start immediately after the glass is complete. The metal column covers are currently being manufactured and will be installed in May. This project is on track to be completed by the end of May. Northern view of the porte cochere construction site. APRIL - CONSTRUCTION UPDATE

ENGINEERING SHOPS & L BUILDING DEMOLITION SAMUEL GINN COLLEGE OF ENGINEERING ENGINEERS: FORESITE GROUP BEAR BROTHERS CONSTRUCTION View of the demolition site from the Shelby Center webcam. $2.0 AUGUST Project Overview: This project will include demolition of the three Samuel Ginn College of Engineering Shops and the L Building. Once demolition is complete, the university will begin construction of an elevated area and terrace in this location. This new area will serve as the south entrance of the Gavin Engineering Research Laboratory to allow students a more convenient entry to the building, while also providing accessibility to the Brown-Kopel Engineering Student Achievement Center. Project Update: The overall project is 80 percent complete. Demolition of the Engineering Shop Buildings (including the foundations) is complete. L-Building demolition is 70 percent complete with only the building s foundation remaining to be removed. The demolition of abandoned utilities has begun, as well as the installation of new utilities. View of the demolition site from the Haley Center webcam. Remaining concrete and masonry demolition waste. APRIL - CONSTRUCTION UPDATE

MELL CLASSROOM ACADEMIC BUILDING OFFICE OF THE PROVOST WILLIAM BLACKSTOCK ARCHITECTS/ TVS DESIGN BAILEY-HARRIS CONSTRUCTION View from the Mell Classroom construction webcam. $35.0 JULY Project Overview: The Mell Classroom project is the first in a series of construction projects that will transform and enhance teaching and learning at Auburn University by building modern, flexible, problem-based learning spaces. The project will include a 69,000-square-foot Mell Classroom Building addition to the existing Ralph Brown Draughon Library, 40 new and renovated group study rooms, 29 active learning classrooms, two lecture halls and food venues. Project Update: The project is 75 percent complete. Exterior brick masonry and window installation is 75 and 90 percent complete respectively. Installation of new fire sprinkler systems on levels three and four of the Library was finished in March. Drywall is being installed on all levels, and ceiling grid installation is underway. Permanent power to the building is in place allowing for testing of mechanical systems. Electrical wiring and audio/visual cabling is being installed in all areas of the facility. The building is on track to be opeational for the fall semester. Rail installation is underway in the central atrium. One of the 29 active learning classrooms. APRIL - CONSTRUCTION UPDATE One of two 166-seat lecture halls.

SCHOOL OF NURSING ACADEMIC FACILITY SCHOOL OF NURSING STACY NORMAN ARCHITECTS/ AYERS SAINT GROSS BAILEY-HARRIS CONSTRUCTION View of the new School of Nursing facility from Lem Morrison Drive. $29.0 JUNE Project Overview: This project includes construction of a new 89,000-square-foot School of Nursing facility. It will include tiered classrooms, active learning classrooms, a skills lab and a clinical laboratory suite for emergency room and ICU simulations. The facility will also include faculty offices, group meeting rooms, a student lounge and public spaces. Project Update: The project is 70 percent complete. Work continues on the exterior of the building, which includes brick masonry, precast concrete and roofing installation. Inside the south building, which includes offices and classrooms, painting and ceiling installation is underway. Inside the north building, which includes simulation labs and lecture halls, mechanical and electrical installation is underway with drywall soon to follow. This project is on track for the School of Nursing to occupy the building over the summer and to be operational for the fall semester. One of two 150-seat lecture halls. Student collaboration and study space. APRIL - CONSTRUCTION UPDATE

BROUN HALL RENOVATION SAMUEL GINN COLLEGE OF ENGINEERING CHAMBLESS KING ARCHITECTS BEAR BROTHERS CONSTRUCTION The original Broun Hall entry has been removed. $5.0 NOVEMBER Project Overview: This project includes improvements to several existing student study areas. The new layout will include a two-story main entrance addition and revised lighting and finishes. It also includes updated information technology and mechanical and electrical systems. In addition, new landscaping will be installed adjacent to the Ginn Concourse. Construction on the ground floor. Project Update: This project is currently 10 percent complete. Interior demolition for Phase 1 and all exterior demolition has finished. The concrete foundation work is currently underway. The flooring on the second level has been removed to create an atrium. APRIL - CONSTRUCTION UPDATE

GAVIN ENGINEERING RESEARCH LABORATORY RENOVATION SAMUEL GINN COLLEGE OF ENGINEERING STEVENS & WILKINSON BEAR BROTHERS CONSTRUCTION A stairwell once located behind Gavin has been removed. $16.7 DECEMBER Project Overview: This is a comprehensive renovation of the former Textile Building. It will include an additive manufacturing facility which will allow students to gain experience with emerging fabrication technologies. It will also house a new Center for Advanced Polymers and Composites to continue the college s research in this area to meet industry needs. The renovated structure will include new research laboratories, as well as a facility for the Nuclear Power Generations Systems Program, a new wind tunnel system, a series of hands-on student project areas and collaborative meeting spaces. Project Update: The project is 15 percent complete. All interior demolition has finished. Exterior demolition of the south elevator and west stair tower are complete. Installation of overhead heating/air conditioning and plumbing systems are underway. The project is currently on track to complete at the end of the year. Installation of new water lines on the second floor. Third floor demolition is complete and ready for partition construction to begin. APRIL - CONSTRUCTION UPDATE

LAB SPACE RESEARCH/INSTRUCTIONAL THIS IS AUBURN. NUMBER OF LABS SQUARE FOOTAGE OF LABS 941,000 Total Square Footage of Research/Instructional Labs on Campus 619,000 322,000 Research Labs 2,287 Total Number of Research/Instructional Instructional Labs 1,791 Labs 496 Research Labs Instructional Labs 800 700 600 Age of Campus Labs Instructional Labs Research Labs 734 (41%) NUMBER OF LABS 500 400 300 200 100 35 *(7%) 376 (21%) 164 (33%) 322 (18%) 49 (10%) 243 (14%) 116 (6%) 25 223 0-10 11-20 21-30 31-40 41 + AGE OF LABS (YEARS) *Represents the percentage of the following: 496 instructional labs and 1,791 research labs. (5%) (45%)

COVER: The Mell Classroom Building construction crane can be seen in the background of this photo. The crane has been located at the site since spring 2016. Construction has progressed to the point where the crane is no longer needed. It will be removed from campus the first week of April. Photo by Charlotte Weaver. 1161 W. Samford Avenue, Auburn, AL 36849 auburn.edu/facilities 334-844-4810 AU_Facilities Auburn University is an equal opportunity educational institution/employer. Produced by the Office of Communications and Marketing, January 2015.