1 BRtfVWRD COUNTY FINANCE AND ADMINISTRATIVE SERVICES DEPARTMENT 115 S. Andrews Avenue, Room 513 Fort Lauderdale. Florida FAX Memorandum November 7, 2007 To: Board of County Commissioners Thru: Bertha Henry, Interim County Administrator From: Michael J. Geoghegan, CFO/Director / ft/m^y- fof Finance and Administrative Services Department Re: Response to of the Application Services Section Report No This submittal is in response to the of the Application Services Division, Report No The following is the requested status for each of the findings and respective recommendations. Finding 1 OIT strategic planning lacks clear guidance for development of unified county-wide data and application systems. 1. Evaluate the validity of strategic initiatives documented in the 2006 IT Strategic Business Plan and present a comprehensive plan for approval. 2. Prioritize approved initiatives to enable development of organization level strategies. 3. Develop organization level strategies which outline how available County resources will be used to achieve approved strategic initiatives according to the established priority. 4. Establish a related timeline for accomplishment of the approved Plan. ETS concurs with the recommendations. Given Enterprise Technology Services (ETS) reorganization, the Application Services Division (ASD) will now be able leverage a framework that provides both strategic planning and program office services. Currently, ASD is participating in the strategic planning process for ETS. As a part of this process, ASD will draft a strategic roadmap that will contain a iist of approved initiatives while aligning the required resources. The prioritization process, currently under way, uses a methodology of weighting projects based upon the alignment of Broward Counly Board of County Commissioners Josephs Eggelleuon, Jr. Sue Gunzbuiger Kiishn D. Jacobs Ken Ksechl. llsne LJeberman. Slacy Riller John E. Rodslrom. Jr. Diana Wasserman-Rubin Lois Wexlar

2 County goals to ETS goals and objectives, strategic technological standardization, and financial availability to invest in each of the initiative. ETS' governance team, comprised of directors and select mangers from each of ETS disciplines, rate the projects accordingly. The result is a list of initiatives that will assist in the process of aligning resources with each of the respective projects. ETS will use the 2008 IT Strategic Plan (in development) to evaluate the validity of the 2006 IT Strategic Plan initiatives. The timeline for completion of the 2008 IT Strategic Plan is January 31, Finding 2 OIT staff place new programs and modifications to existing programs into operations without adequate change management controls. Recommendation; 5. Implement and require the use of a change control mechanism which restricts program changes and programmer access during and subsequent to review and acceptance testing. ETS concurs with the recommendations. ASD is currently replacing the Rational Unified Tool Set that manages the software development lifecycle. The new system, Team Systems by Microsoft, will provide the functionality to restrict programming changes during and subsequent to review and acceptance testing. Team Systems will also provide the functionality to implement a workflow approval process that requires code reviews, security scan reviews, and user acceptance testing sign-off at each phase. Throughout each of these phases, the programming code will be versioned and stored in accordance with industry best practices. Finding 3 ASD performance measures provide a misleading representation of ASD efforts. 6. Develop applicable, quantifiable, discrete measures of the services, efforts, and accomplishments produced by the ASD. 7. Develop and implement mechanisms for adequate and reliable capture of data related to ASD efforts. ETS concurs with the recommendations. ASD has drafted new key performance indicators (KPIs) that provide discrete measures of services, efforts, and accomplishments. With the creation of the Quality Assurance Group within ETS, ASD wili now have an independent review of the quality and effectiveness of the applications being developed. The KPIs that will measure the results are as follows: Business requirements test scenarios that pass quality assurance Average number of defects found per application before delivery Percentage of requirements actually met Application defects found after delivery within first 30 days Average number of days to correct defects before delivery Overall customer satisfaction Application Services Response rev.doc Page 2 of 5

3 Each of the KPI's data will be captured using the Performance Point Server, by Microsoft. This solution is specifically designed to capture and measure performance metrics. Finding 4 Application support and development services are provided by ASD and agency resources throughout the County. The $4.4 million ASD budget does not wholly represent the cost of County application technology services. 8. Evaluate the distribution of staff resources between OIT and agencies to determine the effectiveness and efficiency of the current distributed model. 9. Develop recommendations for an application support model as part of the strategic planning from Finding 1. ETS concurs with the recommendations. ASD will conduct a fact finding initiative to identify all applications within Broward County's administrative network. The results will be used to identify a resource/application ratio, determine the best support model, and establish a comprehensive IT Total-Cost-of-Ownership (TCO) across the County. Additionally, and subject to board approval, ETS will be planning to implement an Enterprise Resource Planning (ERP) system that will help remedy the existing distributed support model. ASD will draft a recommendation to the CIO for acceptance. Once the acceptance model is adopted, the model will become part of the 2008 IT Strategic Plan. Finding 5 ASD lacks accountability for the quality of services delivered to agency customers. 10. Implement a standard for documenting mutually agreed upon service level commitments and project proposals, including specific estimates of project costs, duration and staffing assignments. 11.Create an escalation path to assist agencies in reporting and resolving ASD project issues, including delays, unapproved or excessive costs, or staffing conflicts. ETS concurs with the recommendations. Given the implementation of a Program Office within ETS, ASD will now engage internal independent certified project managers that will assist in the development of project plans that will capture the following items among others: Agreed upon objectives and service level results Project proposals and timelines Identification of project sponsors Project costs estimates where applicable Resource allocation Application Services Response rev.doc Page 3 of 5

4 ASD will implement a change control process whereby changes to the project baselines will require customer sign-off. The Communications Plan is the prescribed instrument for establishing and communicating the escalation process on a project. The Project Management Institute (PMI) indicates that the plan must include escalation time frames and management chain names in order to identify the process. PMI is the world's leading not-for-profit association for the project management profession. It is recognized for the advocacy programs they conduct with governments, organizations and industries around the world. The Project Management Office mandates that a Communications Plan be written for every project and is part of the project management checklist. Program Office oversight and project management discipline will provide enforcement of the escalation process for each software development project. Finding 6 OIT ASD operates without using basic project management cost controls. 12. Develop and implement procedures for managing the internal service costs of ASD, to include: - development of project cost estimates before project commencement, tracking of project expenditures with established milestones and/or deliverables, exception reporting when projects fail behind schedule or exceed cost estimates, regular reports to agency customers of project progress compared to estimated delivery "target" dates and budgets, tracking and recording of staff hours spent on individual projects to permit post-implementation performance analysis of efficiency and effectiveness. ETS concurs with the recommendations. As stated in the previous response, ASD will now leverage the Program Office's certified project managers to address each of the above bulleted items. The Project Management Office provides and maintains a standard methodology which conforms to the Project Management Institute Body of Knowledge. Project managers and coordinators are expected to conform and comply. Finding 7 The ASD organizational structure relies on key individuals without formal cross-training to minimize staff knowledge loss upon terminations and retirements. This places legacy systems at risk of impaired support as employees retire or leave the County. 13. Develop and implement procedures for succession planning, including provisions for cross-training and collaborative assignments among ASD support staff. The process should help ensuring knowledge transfer from key staff developing and maintaining critical applications. Application Services Response rev.doc Page 4 of 5

5 14. Require weekly supervisor reviews of ASD projects and project progress to increase supervisor involvement and decrease key-person reliance for project delivery and support. ETS concurs with the recommendations. The Professional Development section is currently pursuing a Learning Management System (LMS). An LMS provides the functionality to create developmental planning paths. The paths can be designed to address issues such as succession planning, crosstraining, and knowledge transfer. Additionally, ASD has already modified its approach on the assignment of projects. Managers now use a cross-matrix management process whereby resources from multiple teams work collaboratively. The knowledge of applications will now reside on multiple teams within ASD. The ETS Governance Leadership Team meets on a weekly basis to review ASD project status. Supervisors are held accountable for project status to be reported weekly. The leadership team will consistently evaluate project portfolio status and depend on management to ensure timely reporting. c: Pete Corwin, Assistant to County Administrator Carlos Alvarado, Interim CIO, Enterprise Technology Services Application Services Response rev.doc Page 5 of 5

FLORIDA DEPARTMENT OF JUVENILE JUSTICE PROCEDURE. Title: Information Technology (IT) Project Management and Governance Procedures

FLORIDA DEPARTMENT OF JUVENILE JUSTICE PROCEDURE. Title: Information Technology (IT) Project Management and Governance Procedures PROCEDURE Title: Information Technology (IT) Project Management and Governance Procedures Related Policy: FDJJ 1270 I. DEFINITIONS Agency for State Technology (AST) Rule Rules 74-1.001 through 74-1.009,

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS

APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS Shared denotes whether a Contractor Resource may be responsible for that in addition to another identified. Contractor Required

More information

ITSM Process/Change Management

ITSM Process/Change Management ITSM Process/Change Management Process Documentation Revision Date: December 13, 2017 Version Number: 2.0 Document Ownership Document Owner Maury Collins Revision History ITSM Role, Department Service

More information

Audit of the Management of Projects within Employment and Social Development Canada

Audit of the Management of Projects within Employment and Social Development Canada Unclassified Internal Audit Services Branch Audit of the Management of Projects within Employment and Social Development Canada February 2014 SP-607-03-14E Internal Audit Services Branch (IASB) You can

More information

Information Technology Independent Verification and Validation

Information Technology Independent Verification and Validation Florida Department of Management Services Information Technology Independent Verification and Validation RFP No. Work Plan and Methodology ; 2:30 PM EST 2150 River Plaza Drive Suite 380 Sacramento California

More information

International Association of Certified Practicing Engineers

International Association of Certified Practicing Engineers www.iacpe.com Knowledge, Certification, Networking Page: 1 71 IACPE No 19, Jalan Bilal Mahmood 80100 Johor Bahru Malaysia The International is providing the introduction to the Training Module for your

More information

University of Wisconsin-Extension Cooperative Extension

University of Wisconsin-Extension Cooperative Extension next Generation project Charter Version: 1.1 Created: November 8, 2016 Updated: December 6, 2016 Charter, Version 1.1 Document Control This Charter serves as the governing and constitutional document for

More information

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2 Passit4Sure.OG0-093.221Questions Number: OG0-093 Passing Score: 800 Time Limit: 120 min File Version: 7.1 TOGAF 9 Combined Part 1 and Part 2 One of the great thing about pass4sure is that is saves our

More information

Project Management Advisory Board Deep Dive Study of Program Management

Project Management Advisory Board Deep Dive Study of Program Management Project Management Advisory Board Deep Dive Study of Program Management Purpose The purpose of this study is twofold: 1. Understand how Saint Louis companies are managing programs 2. Study the maturity

More information

2. Creating and monitoring the overall program milestone plan and cross-functional dependencies and issues.

2. Creating and monitoring the overall program milestone plan and cross-functional dependencies and issues. Deloitte 2200 Ross Ave Suite 1600 Dallas, TX 75201 www.deloitte.com Chris Garcia Director of Operations PharmaKat 123 Main St. Dallas, TX Dear Chris, Deloitte is pleased to confirm that it will provide

More information

Project+ Examination Blueprint Version June 1, 2003

Project+ Examination Blueprint Version June 1, 2003 Introduction The Project + examination is designed for business professionals involved with projects with a technology component. The examination is designed for candidates possessing at least 12 months

More information

Services Description. Transformation and Plan Services. Business Transformation and Plan Services

Services Description. Transformation and Plan Services. Business Transformation and Plan Services Services Description Business ation and Plan Services Business ation and Plan Services SAP Business ation and Plan Services provides consulting and prototyping services to facilitate Licensee innovation

More information

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT)

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) MOSAIC Quality Assurance Plan v04.02 Prepared by: Approved by: QUALITY ASSURANCE PLAN APPROVALS QA/QC Program

More information

Final Audit Report. IT Client Services - Application Development and Maintenance Process

Final Audit Report. IT Client Services - Application Development and Maintenance Process Health Canada Santé Canada Final Audit Report IT Client Services - Process June 20, 2012 Table of Contents Executive summary... i A - Background... 1 1. Audit objective... 1 2. Scope and approach... 1

More information

<Project Name> Business Case

<Project Name> Business Case Business Case Author(s) Contributors Department Campus DOCUMENT HISTORY Version Date Person Notes 1.0 ITS Portfolio Management Office Business Case Page 1 TABLE OF CONTENTS

More information

CHAPTER 1 Introduction

CHAPTER 1 Introduction CHAPTER 1 Introduction The Standard for Program Management provides guidelines for managing programs within an organization. It defines program management and related concepts, describes the program management

More information

Guidance on portfolio, programme and project management

Guidance on portfolio, programme and project management Guidance on portfolio, programme and project management The Standard for Infrastructure Procurement and Delivery Management (SIPDM) defines the following two generic terms: Portfolio: collection of projects

More information

Program Management. a practical application. November 19 th, Project Management Symposium Breakout Session D

Program Management. a practical application. November 19 th, Project Management Symposium Breakout Session D 0 Program Management a practical application November 19 th, 2010 2010 Project Management Symposium Breakout Session D 1 Overview As projects become larger and more complex, the effective management of

More information

Oilpocalypse Now: Weathering the Storm with Integrated Project Management Samarth Jain Andrew Lavinsky

Oilpocalypse Now: Weathering the Storm with Integrated Project Management Samarth Jain Andrew Lavinsky Oilpocalypse Now: Weathering the Storm with Integrated Project Management Samarth Jain Andrew Lavinsky June 2, 2015 Devon Energy Center Oklahoma City, Oklahoma, USA Welcome 3 Agenda Business Context Importance

More information

Follow-up Audit of the CNSC Performance Measurement and Reporting Frameworks, November 2011

Follow-up Audit of the CNSC Performance Measurement and Reporting Frameworks, November 2011 Audit of Mobile Telecommunication Devices June 21, 2012 Follow-up Audit of the CNSC Performance Measurement and Reporting Frameworks, November 2011 Presented to the Audit Committee on November 21, 2016

More information

IT Prioritization CHARTER

IT Prioritization CHARTER IT Prioritization CHARTER VERSION: 2.0 REVISION DATE: July 22, 2013 Background In late 2012, UW-Platteville conducted an assessment of University-wide IT Prioritization, defined as the framework for decision

More information

INFORMATION SERVICES FY 2018 FY 2020

INFORMATION SERVICES FY 2018 FY 2020 INFORMATION SERVICES FY 2018 FY 2020 3-Year Strategic Plan Technology Roadmap Page 0 of 14 Table of Contents Strategic Plan Executive Summary... 2 Mission, Vision & Values... 3 Strategic Planning Process...

More information

IT PROJECT ANALYST/MANAGER

IT PROJECT ANALYST/MANAGER IT PROJECT ANALYST/MANAGER I. DESCRIPTION OF WORK Positions in this banded class are responsible for project management work involving planning and coordination of information technology projects. To ensure

More information

1. IDENTIFICATION. Freebalance coding: PURPOSE 3. SCOPE

1. IDENTIFICATION. Freebalance coding: PURPOSE 3. SCOPE 1. IDENTIFICATION Position No. Job Title Supervisor s Position 14-02986 Manager Informatics Projects Director Government Information and Planning Department Division/Region Community Location Community

More information

Business Case for Value Realization During Implementation Delivering Projects on Time, on Budget, and on Value

Business Case for Value Realization During Implementation Delivering Projects on Time, on Budget, and on Value SAP Thought Leadership Value Realization Business Case for Value Realization During Implementation Delivering Projects on Time, on Budget, and on Value The Business Transformation Services group of SAP

More information

1.0 PART THREE: Work Plan and IV&V Methodology

1.0 PART THREE: Work Plan and IV&V Methodology 1.0 PART THREE: Work Plan and IV&V Methodology 1.1 Multi-Faceted IV&V Methodology Large, complex projects demand attentive and experienced IV&V and project management support to meet expectations. Monitoring

More information

Program/Project Management

Program/Project Management PROCEDURE OVERVIEW PROGRAM/PROJECT MANAGEMENT PROCEDURE defines the project management infrastructure, reporting relationships and project management activities within SDLC.com. Project Managers, Program

More information

TOGAF Foundation Exam

TOGAF Foundation Exam TOGAF Foundation Exam TOGAF 9 Part 1 (ESL) Time Limit 90 minutes Number of questions 40 Pass-through 22 1. Which of the following best describes the meaning of "Initial Level of Risk" in Risk Management?

More information

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Project Management Framework with reference to PMBOK (PMI) July 01, 2009 Introduction Context Agenda Introduction to Methodologies What is a Methodology? Benefits of an Effective Methodology Methodology

More information

Article from: CompAct. April 2013 Issue No. 47

Article from: CompAct. April 2013 Issue No. 47 Article from: CompAct April 2013 Issue No. 47 Overview of Programmatic Framework and Key Considerations Key elements Description Items to consider Definition and identification of EUCs The statement that

More information

Job Family Matrix. Core Duties Core Duties Core Duties

Job Family Matrix. Core Duties Core Duties Core Duties Job Function: Information Technology Job Family Matrix Job Family: IT Project Management - Professional Job Family Summary: Perform or manage a range of activities related to the design, planning, execution,

More information

Policy and Procedure Examples

Policy and Procedure Examples Appendix 1 Policy and Procedure Examples Four sample documents are shown in this appendix to illustrate the type of administrative guidelines that should be developed in support of project operations within

More information

Why PMOs Fail: Is Your Organization at Risk?

Why PMOs Fail: Is Your Organization at Risk? Why PMOs Fail: Is Your Organization at Risk? June 10, 2010 Presented by Phil Kyle Infinitive 2010 1 Agenda» Defining Our Terms» How PMOs Create Tangible Value» What Are the Common PMO Pitfalls?» Assessing

More information

OPM The Missing Link. Jane Betterton, BS,ChE., PMP PMIRGC JaneBetterton.com/ BTSResults.com

OPM The Missing Link. Jane Betterton, BS,ChE., PMP PMIRGC JaneBetterton.com/ BTSResults.com OPM The Missing Link Jane Betterton, BS,ChE., PMP PMIRGC 11-2-18 Jane@BTSResults.com JaneBetterton.com/ BTSResults.com Presentation Overview In this session you will learn how PMI s latest foundational

More information

OPM The Missing Link

OPM The Missing Link OPM The Missing Link Jane Betterton, BS,ChE., PMP PMIRGC 11 2 18 Jane@BTSResults.com JaneBetterton.com/ BTSResults.com Presentation Overview In this session you will learn how PMI s latest foundational

More information

Internal Audit Quality Analysis Evaluation against the Standards International Standards for the Professional Practice of Internal Auditing (2017)

Internal Audit Quality Analysis Evaluation against the Standards International Standards for the Professional Practice of Internal Auditing (2017) Internal Audit Quality Analysis Evaluation against the Standards International Standards for the Professional Practice of Internal Auditing (2017) Assessor 1: Assessor 2: Date: Date: Legend: Generally

More information

PROCESS TRAINING. DIR PM Lite 2.0 Process Training v2.0 1

PROCESS TRAINING. DIR PM Lite 2.0 Process Training v2.0 1 PROCESS TRAINING 1 PM Lite (Project Management Lite) is a project management process made up of tools, templates, and best practices that empowers its users to be more efficient and effective in project

More information

PROJECT STANDARDS AND GUIDELINES

PROJECT STANDARDS AND GUIDELINES PROJECT STANDARDS AND GUIDELINES A Guide to DTAS Project Management Abstract This document defines our DTAS project management terminology and the outlines the standards and guidelines of our project management

More information

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are:

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are: Introduction Scope Management involves the management of techniques that make sure that the project comprises a Processes included in Scope Management are: 1. Collect Requirements In this process, project

More information

1 P a g e P r i s m e t r i c T e c h n o l o g i e s

1 P a g e P r i s m e t r i c T e c h n o l o g i e s 1 P a g e P r i s m e t r i c T e c h n o l o g i e s Our Methodology Over the years of developing challenging technology solutions for our multi-national clients, we have devised a practical process of

More information

Program Management Office (PMO)

Program Management Office (PMO) Program Management Office (PMO) White Paper CHRISTOPHER TORREGOSA Senior Manager November 2018 CONTACT For further information about Coker Group and how we can be of assistance, call 800-345-5829 x137

More information

Strategic Sourcing Manager: Academic Services and Equipment

Strategic Sourcing Manager: Academic Services and Equipment Strategic Sourcing Manager: Academic Services and Equipment Position Number 00022192 Department: Campus: Strategic Procurement Services SWS Date of Issue: August 2013 I. Primary Purpose of Position The

More information

Federal Segment Architecture Methodology Overview

Federal Segment Architecture Methodology Overview Federal Segment Architecture Methodology Background In January 2008, the Federal Segment Architecture Working Group (FSAWG) was formed as a sub-team of the Federal CIO Council s Architecture and Infrastructure

More information

Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017

Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Background Deloitte s Scope Conduct a review of the City s project planning, design, delivery and

More information

Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit

Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit Internal Audit Report Toll Operations Contract Management TxDOT Office of Internal Audit Objective To determine whether the Toll Operations Division (TOD) contract management structure is designed and

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Service Delivery Manager (People HERA Grade: 8 Management Systems) Responsible to: Assistant Director (Business Services) Accountable for: Day to day leadership of team members

More information

POSSE System Review. January 30, Office of the City Auditor 1200, Scotia Place, Tower Jasper Avenue Edmonton, Alberta T5J 3R8

POSSE System Review. January 30, Office of the City Auditor 1200, Scotia Place, Tower Jasper Avenue Edmonton, Alberta T5J 3R8 1200, Scotia Place, Tower 1 10060 Jasper Avenue Edmonton, Alberta T5J 3R8 edmonton.ca/auditor POSSE System Review January 30, 2017 The conducted this project in accordance with the International Standards

More information

Project Integration Management

Project Integration Management Project Integration Management Presented by Project Masters Inc. *Throughout this presentation, we reference and recognize the following trademarks, service marks, and copyrights of the Project Management

More information

Reference B Project Management Requirements

Reference B Project Management Requirements Reference B State of Alaska TABLE OF CONTENTS 1... 2 1.1 Project Life Cycle Methodology... 2 1.2 Preliminary Project Management Narrative and Work Plan... 2 2 Master Project Management Plan and Master

More information

New Point Electronic Solutions. Oracle Fusion HCM Statement of Work

New Point Electronic Solutions. Oracle Fusion HCM Statement of Work New Point Electronic Solutions Oracle Fusion HCM Statement of Work Agenda Overview... 3 Assumptions... 3 Change Management Process... 4 Project Objectives... 5 Scope of Work... 5 Period of Performance...

More information

City of Fort Lauderdale Quality Manual

City of Fort Lauderdale Quality Manual City of Fort Lauderdale Quality Manual Quality Management System- FL 2 STAT Certified ISO 9001:2008 March 24, 2016 Certificate #53058 Page 1 of 9 CONTENTS A. The City of Fort Lauderdale... 3 B. ISO 9001:2015

More information

Rational Software White Paper TP 174

Rational Software White Paper TP 174 Reaching CMM Levels 2 and 3 with the Rational Unified Process Rational Software White Paper TP 174 Table of Contents Abstract... 1 Introduction... 1 Level 2, Repeatable... 2 Requirements Management...

More information

Govern IT. On Demand Insurance Business Imperative. Business objectives are aligned with my IT infrastructure. Business.

Govern IT. On Demand Insurance Business Imperative. Business objectives are aligned with my IT infrastructure. Business. Govern IT On Demand Insurance Business Imperative GOAL Business objectives are aligned with my IT infrastructure Business On Demand Insurance CEO Operations Development REWARD Achieve optimized IT investment

More information

State of Oklahoma CIO Assessment Study

State of Oklahoma CIO Assessment Study in collaboration with State of Oklahoma CIO Assessment Study October 21, 2010 Government Modernization Committee Alex Z. Pettit Chief Information Officer State of Oklahoma Table of Contents Confirmation

More information

Who Should be on Your Project Team: The Importance of Project Roles and Responsibilities

Who Should be on Your Project Team: The Importance of Project Roles and Responsibilities Who Should be on Your Project Team: The Importance of Project s and One significant factor contributing to the success of projects is having the right people engaged in the process. Who are the right stakeholders

More information

Tennessee Board of Regents Shared Services Initiative*

Tennessee Board of Regents Shared Services Initiative* Tennessee Board of Regents Shared Services Initiative* Governance Model 1/17/2017 * Note: Tentative project name pending final branding approval Modification History: Date Change made by Description of

More information

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management

Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Modernization and Migration Management (M3) Playbook GSA, Unified Shared Services Management Introduction How to Read an Activity Description Objective: Provides the overall objective of the activity :

More information

IT MANAGER - BUSINESS & TECHNOLOGY APPLICATIONS (12235) ( )

IT MANAGER - BUSINESS & TECHNOLOGY APPLICATIONS (12235) ( ) GENERAL DESCRIPTION OF WORK IT MANAGER - BUSINESS & TECHNOLOGY APPLICATIONS (12235) (31000275) Positions in this banded class are responsible for supervisory and managerial work in directing a designated

More information

Project Governance. Melissa McCall PMO Director

Project Governance. Melissa McCall PMO Director Project Governance Melissa McCall PMO Director In this session we will cover. Project Governance o What is Project Governance o The Steering Committee o An easy approach to establishing a Steering Committee

More information

PMO In A Box. Prepared for UBS

PMO In A Box. Prepared for UBS PMO In A Box Prepared for UBS Roadmap Why PMO In A Box? Establish PMO Governance Standardize Methodology Create a Stakeholder Partnership Plan 2 PMOs Are In Transition 3 CEB PMO Executive Council pmo in

More information

CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS

CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS CHAPTER 2: IMPLEMENTATION PHASES AND OFFERINGS Objectives Introduction The objectives are: Describe the purpose of the phase planning activity, preconditions, and deliverables in the implementation methodology.

More information

Chapter 4 Project Management

Chapter 4 Project Management Chapter 4 Project Management For internal use of BSNL only Page 1 Project Management 1.0 Introduction Project management is concerned with the overall planning and co-ordination of a project from conception

More information

ServiceNow Custom Training and Adoption

ServiceNow Custom Training and Adoption ServiceNow Custom Training and Adoption Overview... 3 Adoption Toolkit Deliverables... 3 Change Enablement Deliverables... 4 Custom Training Deliverables... 5 Custom Training Applications by Business Function...

More information

Work Plan and IV&V Methodology

Work Plan and IV&V Methodology Work Plan and IV&V Methodology ISG Public Sector has been helping public sector organizations acquire and implement (from a project oversight and organizational change management perspective) new, enterprise-wide

More information

BCBS 239 Alignment with DCAM (Data Management Implications related to the Principles of Risk Data Aggregation) July 2015

BCBS 239 Alignment with DCAM (Data Management Implications related to the Principles of Risk Data Aggregation) July 2015 BCBS 239 Alignment with DCAM 1.2.2 ( Management Implications related to the Principles of Risk Aggregation) July 2015 Principle 1: Governance Paragraph Summary Component Capability/Sub- Capability 27 Management

More information

CORROSION MANAGEMENT MATURITY MODEL

CORROSION MANAGEMENT MATURITY MODEL CORROSION MANAGEMENT MATURITY MODEL CMMM Model Definition AUTHOR Jeff Varney Executive Director APQC Page 1 of 35 TABLE OF CONTENTS OVERVIEW... 5 I. INTRODUCTION... 6 1.1 The Need... 6 1.2 The Corrosion

More information

OE RESOURCE REQUEST APPLICATION IT GOVERNANCE

OE RESOURCE REQUEST APPLICATION IT GOVERNANCE Page 1 of 10 OE RESOURCE REQUEST APPLICATION IT GOVERNANCE University of California, Berkeley I. SPONSORSHIP A. Initiative Initiative Initiative Manager OE- Information Technology Design Team Lyle Nevels

More information

IT MANAGER - BUSINESS & TECHNOLOGY APPLICATIONS (12235) ( )

IT MANAGER - BUSINESS & TECHNOLOGY APPLICATIONS (12235) ( ) GENERAL DESCRIPTION OF WORK Positions in this banded class are responsible for supervisory and managerial work in directing a designated team of computer applications analysts and applications programmers

More information

REQUEST FOR PROPOSAL. Customer Inquiry Tracking Planning and Implementation Project Phase I March 25, 2014

REQUEST FOR PROPOSAL. Customer Inquiry Tracking Planning and Implementation Project Phase I March 25, 2014 REQUEST FOR PROPOSAL Customer Inquiry Tracking Planning and Implementation Project Phase I March 25, 2014 This Request for Proposal (RFP) is being sent to consulting firms to act as the Consultant in the

More information

Self-Study Guide Administrative Program Review

Self-Study Guide Administrative Program Review Self-Study Guide Administrative Program Review Introduction This guide is a companion document to the APR Program Handbook. Its purpose is to assist selfstudy team members with conducting their department

More information

E2-E3: MANAGEMENT. CHAPTER-3 PROJECT MANAGEMENT (Date of creation: )

E2-E3: MANAGEMENT. CHAPTER-3 PROJECT MANAGEMENT (Date of creation: ) E2-E3: MANAGEMENT CHAPTER-3 PROJECT MANAGEMENT (Date of creation: 01-04-2011) Page: 1 Project Management Introduction: Project management is concerned with the overall planning and co-ordination of a project

More information

On Demand IT Governance: A powerful tool for enhancing the strategic value of IT.

On Demand IT Governance: A powerful tool for enhancing the strategic value of IT. White Paper On Demand IT Governance: A powerful tool for enhancing the strategic value of IT. Today, IT plays a key role in determining a company's success by leading strategic initiatives and providing

More information

Establishing a Comprehensive IT Process Governance Framework

Establishing a Comprehensive IT Process Governance Framework Establishing a Comprehensive IT Process Governance Framework Ensuring clear accountability and assigned responsibility for IT process operations, integration and continual improvement. Thorsten Manthey

More information

The CXO s Guide To IT Governance

The CXO s Guide To IT Governance The CXO s Guide To IT Governance A Roadmap To Driving Top-Down Alignment Between Business & IT Strategy Presented by Executive Summary IT Governance solutions enable CXOs to align their business strategy

More information

PgMP Exam Prep Training - 4 Days

PgMP Exam Prep Training - 4 Days PgMP Exam Prep Training - 4 Days Course Length: 4 Days Course ID: PgMP Credits: 21 PDUs Course Duration: 3 or 4 days (Live in person or online class) Course Level: Advanced Day workshop- PgMP Boot Camp

More information

PROJECT MANAGEMENT PLAN

PROJECT MANAGEMENT PLAN PROJECT MANAGEMENT PLAN AS A TOOL TO DEVELOP EFFECTIVE COMMUNICATION TO MANAGE STAKEHOLDERS AND THE DESIGN TEAM Adelaide Airport plaza Event: Design and Development of Stations and Terminals Conference

More information

VMware Network Virtualization Deploy Service

VMware Network Virtualization Deploy Service DATA SHEET VMware Network Virtualization Deploy Service AT-A-GLANCE The primary objective of this service is a rapid installation, configuration, and high-level validation (deployment) of a reference design

More information

Monthly Independent Verification and Validation Assessment Report

Monthly Independent Verification and Validation Assessment Report Monthly Independent Verification and Validation Assessment Report Florida Planning, Accounting, and Ledger Management (PALM) Project February 2018 Date: 3/12/2018 Version 1.0 Table of Contents Executive

More information

Project Planning and Management (PPM) V2.0. WBS Dictionary

Project Planning and Management (PPM) V2.0. WBS Dictionary Project Planning and Management (PPM) V2.0 WBS Dictionary Software as a Service (SaaS) Version 1.0 August 2014 1 Table of Contents PPM V2.0 Work Breakdown Structure (WBS) Dictionary 1 Project Type: Software

More information

ecap Health Check Evaluation

ecap Health Check Evaluation ecap Health Check Evaluation ECAP utilizes a multi-faceted engagement approach with our clientele to provide more efficient and effective services. There are 3 phases to the engagement: Phase I: Onsite

More information

The roadmap to EU-MDR Implementation

The roadmap to EU-MDR Implementation ...the practical approach Scope and Plan GAP Assessment Portfolio Rationalization Global Impact Analysis Master Compliance Roadmap EU-MDR Compliance Regulatory Training Effectiveness Check Implementation

More information

ICMI PROFESSIONAL CERTIFICATION

ICMI PROFESSIONAL CERTIFICATION ICMI PROFESSIONAL CERTIFICATION Contact Center Management Competencies The ICMI Professional Certification Contact Center Management Competencies specify job role-specific knowledge, skills and abilities

More information

Large Federal Agency Leverages IV&V to Achieve Quality Delivery for Critical Modernization Initiative

Large Federal Agency Leverages IV&V to Achieve Quality Delivery for Critical Modernization Initiative Large Federal Agency Leverages IV&V to Achieve Quality Delivery for Critical Modernization Initiative Capgemini Government Solutions provides Independent Verification and Validation (IV&V) services to

More information

Response to County Auditor's Review of Airport Parking Revenues and Parking Information Systems (Report 17-11)

Response to County Auditor's Review of Airport Parking Revenues and Parking Information Systems (Report 17-11) FLORIDA BERTHA W. HENRY, County Administrator 115 S. Andrews Avenue, Room 409 Fort Lauderdale, Florida 33301 954-357-7362 FAX 954-357-7360 MEMORANDUM DATE: May 26, 2017 TO: /.om missioners FROM: SUBJECT:

More information

PMO Services Checklist

PMO Services Checklist PMO Services Checklist by IMPACTbyLaura.com Services Checklist This resource is a list of possible services and categories that you can consider when determining how you will drive IMPACT with your PMO.

More information

RESCUING A TROUBLED PROJECT

RESCUING A TROUBLED PROJECT RESCUING A TROUBLED PROJECT INTRODUCTION Most endeavors, business or personal, are bound to face challenges at one point or another. The introduction of a new product may encounter problems while manufacturing

More information

Accounts Receivable Shared Service Center. Johns Hopkins Enterprise Service Level Agreement

Accounts Receivable Shared Service Center. Johns Hopkins Enterprise Service Level Agreement Accounts Receivable Shared Service Center Johns Hopkins Enterprise Service Level Agreement Agreement Published Date: July 24, 2006 Agreement Period of Performance: June 30, 2019 Agreement Effective July

More information

Performance Management in Higher Education

Performance Management in Higher Education Performance Management in Higher Education Advisory Services and Software Solutions That Enable Colleges and Universities to Succeed in a Changing Environment Given the number and magnitude of pressures

More information

City of Saskatoon Business Continuity Internal Audit Report

City of Saskatoon Business Continuity Internal Audit Report www.pwc.com/ca City of Saskatoon Business Continuity Internal Audit Report June 2018 Executive Summary The City of Saskatoon s (the City ) Strategic Risk Register identifies Business Continuity as a high

More information

Gaining and Maintaining IT & Business Alignment. presented by Robert Sheesley for PMI Pittsburgh Chapter

Gaining and Maintaining IT & Business Alignment. presented by Robert Sheesley for PMI Pittsburgh Chapter Gaining and Maintaining IT & Alignment presented by Robert Sheesley for PMI Pittsburgh Chapter Agenda The Dynamics: Not an Accidental Love Triangle The Problem: The Vicious Cycle of Alignment Aligning

More information

Content of the ITIL 2011 Process Library

Content of the ITIL 2011 Process Library 1 Content 1 Content...1 2 Processes...2 2.1 Service Strategy...2 2.1.1 Business Relationship Management...2 2.1.2 Management of IT Service Strategy...2 2.1.3 Demand Management...3 2.1.4 Service Portfolio

More information

PARKS FORWARD COMMISSION Implementation Assessment November 2015

PARKS FORWARD COMMISSION Implementation Assessment November 2015 PARKS FORWARD COMMISSION Implementation Assessment November 2015 This report assesses the implementation to date by the California Department of Parks and Recreation (Department) of the recommendations

More information

A Freshwater Partners White Paper

A Freshwater Partners White Paper C r e a t i n g B u s i n e s s C a p a b i l i t y w i t h a P M O A Freshwater Partners White Paper Whether you view the coordinated management of multiple projects as program management, or portfolio

More information

VMware Cloud Automation Design and Deploy IaaS Service

VMware Cloud Automation Design and Deploy IaaS Service DATASHEET VMware Cloud Automation AT A GLANCE The VMware Cloud Automation Design and Deploy IaaS Service expands the power of virtualization and moves IT services away from existing infrastructure delivery

More information

Functionality First: A Prescriptive Approach to Simpler, Faster and More Cost-effective Project and Portfolio Management (PPM)

Functionality First: A Prescriptive Approach to Simpler, Faster and More Cost-effective Project and Portfolio Management (PPM) Functionality First: A Prescriptive Approach to Simpler, Faster and More Cost-effective Project and Portfolio Management (PPM) Copyright 2014 CA. All rights reserved. Why the Need for Smarter PPM? The

More information

4.2.8 Tab 6: ACCESS Florida System O&M Approach and Methodology Approach

4.2.8 Tab 6: ACCESS Florida System O&M Approach and Methodology Approach 4.2.8 Tab 6: ACCESS Florida System O&M Approach and Methodology Our approach to providing ongoing Operations and Maintenance support for ACCESS Florida focuses on stability of the existing system, retaining

More information

Sponsor/CRO Partnership Optimization

Sponsor/CRO Partnership Optimization Insight Brief Sponsor/CRO Partnership Optimization Developing a CRO Governance Model Geoff Garabedian, Vice President and Managing Director, Consulting at Quintiles Josh Samon, Principal Life Sciences

More information

The Corporation of the City of London Building Permit Review Internal Audit Report

The Corporation of the City of London Building Permit Review Internal Audit Report The Corporation of the City of London Building Permit Review Internal Audit Report Audit performed: November - December 2017 Final report issued: January 2018 The Corporation of the City of London Internal

More information

Balanced Perspective. Managing software development from a business and technical point of view. IBM Software Group

Balanced Perspective. Managing software development from a business and technical point of view. IBM Software Group IBM Software Group Balanced Perspective Managing software development from a business and technical point of view Michel Speranski IBM Rational michel.speranski@fr.ibm.com 2006 IBM Corporation Agenda The

More information