Overview First Draft of NERC s 2014 Business Plan and Budget
|
|
- Eric French
- 6 years ago
- Views:
Transcription
1 Overview First Draft of NERC s 2014 Business Plan and Budget Michael Walker, Chief Financial and Administrative Officer Finance and Audit Committee Meeting May 3, 2013
2 Agenda Update on business planning process Strategic plan goals and major activities Application of Section 215 criteria Revenue requirements to support: Ongoing operations Regulatory mandates Key initiatives Request for comments Next steps/review of business plan and budget schedule 2
3 Business Planning Process Update to strategic plan - May 2013 Board meeting Reviewed NERC and Regional activities in relation to strategic plan Identified gaps and initiatives to close gaps. Applied Section 215 criteria to NERC s major activities Potential funding of certain activities outside Section 215 Developed projected revenue requirements to support: NERC s ongoing core operations New regulatory mandates Key strategic initiatives Seeking stakeholder input 3
4 Strategic Plan Key Points Standards Clear, reasonable and sound mandatory standards Practical to implement and cost effective Compliance, Registration, and Certification Strong enforcement authority, objective and fair Culture of compliance addresses reliability risks Monitoring commensurate with entity roles and risk Risks to Reliability Most significant risks to reliability Accountable for mitigating reliability risks Culture of reliability excellence Coordination and Collaboration Collaborative enterprise with improved efficiencies 4
5 Goal 1: Clear, Reasonable, and Technically Sound Standards Objective 1a: Timely, clear, and responsive to risks Objective 1b: Practical and cost effective Focus for 2014 Departments Continue to accelerate standards clean up Standards reform efforts Independent expert review Risk-informed standards Reliability Standards Support from all other departments CIP transition Cost effectiveness assessment 5
6 Goal 2: Strong Enforcement Authority, Objective and Fair Objective 2a: Registration is risk based; certification is effective Objective 2b: Accountability is clear, timely, and transparent Objective 2c: Compliance monitoring is commensurate with risk Focus for 2014 BES Phase II exception process Functional model review Common and consistent approaches to risk-based registration RAI Implementation Consistent enforcement focused on priority risks Departments Reliability Standards Compliance Operations Compliance Enforcement Information Technology 6
7 Goal 3: Culture of Compliance Addresses Reliability Risks Objective 3a: Industry has effective internal controls to ensure reliability Objective 3b: ERO enforcement is efficient and uses proportional discretion Focus for 2014 RAI Implementation Emphasize proactive approaches, learning, internal controls Continue and expand use of Find, Fix, and Track Departments Compliance Operations Compliance Enforcement Critical Infrastructure Training, Education, and Operator Certification Information Technology 7
8 Goal 4: Most Significant Risks to Reliability Objective 4a: Risks identified and prioritized effectively Objective 4b: Events are well analyzed and inform the industry Focus for 2014 Departments Reliability Risk Register and Risk Profile development Risk analysis integrated with business planning Increased use of Event Analysis in risk considerations Reliability Assessment and Performance Analysis Events Analysis Information Technology Convergence of key metrics and analysis tools 8
9 Goal 5: Accountable for Mitigating Reliability Risks Objective 5a: ERO tracks accountability for critical recommendations Objective 5b: Industry is addressing security threats, and constantly improving security posture Focus for 2014 Departments Metrics to evaluate success of interventions Track implementation of recommendations ES-ISAC capability Promotion of maturity model self-assessments Reliability Assessments and Performance Analysis Events Analysis Situation Awareness Critical Infrastructure 9
10 Goal 6: Culture of Reliability Excellence Objective 6a: Leading information resource for industry and policy makers Objective 6b: Models and data are accurate and shared Focus for 2014 Departments Sharing of event information Develop reliability risk analysis center of excellence Investments in ERO trending and analysis tools Reliability Assessments and Performance Analysis Events Analysis Information Technology Modeling and data improvements 10
11 Goal 7: Collaborative Enterprise with Improved Efficiencies Objective 7a: Acquire, engage, and retain highly qualified talent Objective 7b: ERO processes are efficient and internal risks are managed Focus for 2014 Continued coordination with and between Regional Entities 5-year assessment Talent recruiting and retention ERO applications & technology migration Departments All operating departments Human Resources Information Technology Finance and Accounting Improved operating efficiency and internal risk management 11
12 Application of Section 215 Criteria All major activities fall within proposed guidelines Option to voluntarily separate and fund certain activities outside Section 215 ESCC support ES-ISAC Operator certification and testing Governance, accounting and funding details need to be addressed Revised ESCC governance model Accounting considerations Direct costs, working capital, operating reserves, overhead and administrative cost allocations Billing, collection, and other considerations Timing 12
13 Cost of Ongoing Operations Reflects 2013 budgeted FTEs and headcount plus four (4) additional personnel to support current operations Engineer in RAPA to support Events Analysis Initiative Administrative support for legal and enforcement Database analyst Webmaster Net increase of.36 FTEs over 2013 Average salary increase below industry average Personnel attrition factor Continuation of 2013 reductions in medical and retirement benefits Market increases in health care costs Elimination of IDC and NASPI funding 13
14 Cost of Ongoing Operations 2013 Budget 2014 Budget Ongoing Operations $ 31,298,405 Total Personnel Expense $ 34,301,192 $ 4,098,310 Total Meeting Expense $ 3,907,500 $ 8,816,254 Contracts and Consultants $ 6,399,240 $ 8,251,187 Operating Expenses $ 8,465,150 $ 50,000 Non-Operating Expenses $ 50,000 $ 1,772,100 Capital Expenditures $ 1,701,800 $ 54,286,256 Total Budget $ 54,824, % 14
15 Additional 2014 Revenue Needs Additional revenue requirements fall in four (4) major categories: Regulatory mandates Standards Reform Initiative Reliability Assurance Initiative ERO Enterprise Information System Some initiatives require multi-year funding Additional ES-ISAC support addressed separately 15
16 Regulatory Mandates Vegetation research FERC FAC-3 Order $500K Formulate plan to conduct research on minimum vegetation clearance distance (MVCD) Empirical validation of MVCD Actual flash distances observed through testing Analysis of such events Draft statement of work from EPRI Vegetation management on public lands $100K Gather/analyze data regarding vegetation management issues on public lands As warranted, propose means to address issues Reliability effects GMD $250k Modeling studies/assessments 16
17 Standards Reform Initiative Benefits Reduce unnecessary compliance costs/regulatory uncertainty Clear, concise, cost effective and impactful results-based standards 2013 Standards Independent Expert Review Project Retain panel of independent industry experts ($378k) Identify existing standard requirements which are low quality, low reliability impact, and impose unnecessary costs on industry Provide roadmap for standards development plan Propose 2014 funding ($200k) $200k for experts to ensure progress against baseline 17
18 Reliability Assurance Initiative Benefits Improve BES reliability Increase efficiency, consistency Reduce cost of compliance on industry Resourcing approach Maximize use of existing NERC and Regional staff Draw from industry where possible Re-adjust priorities to increase bandwidth Use consultants to jump start and increase bandwidth Proposed funding for consulting support ($800k) Standardize ERO-wide audit processes ($500k) Develop/implement tools to support RAI process improvements ($300k) 18
19 Current State Compliance Risk Analysis Generator Metrics Transmission Metrics Demand Response Event Analysis Assessment Data Region Only Systems Technology Multiple Applications Multiple Databases Outdated Technology Limited Integration Multiple Logins Multiple Registrations Current Experience Inefficient Expensive Complex Redundant Effort Limited Usability Multiple systems Manual Data Cleansing Limited Analysis Labor Intensive 19
20 Future State Technology Single Sign-On Single Registration Integrated Databases Flexible Technology Robust Analytics Accessible (securely) Anywhere Common Architecture Future Experience Efficient Cost Effective Automated Business Intelligence / Analytics User Self-Service Risk Based Analytics Reduced Manual Effort Effective Resource Utilization 20
21 Compelling Benefits Registered Entities Regional Entities ERO Enterprise Reduces Resources to Sustain Systems, Usability, Data Entry, etc. Streamlines Application Experience, Saves Training Common Interfaces & Application Governance Ends Duplicate Data Entry Streamlines Data Submittal & Validation Expands Analytic Flexibility and Direct Reliability Value Makes Coordination Less Manual Improves Risk-Based Analysis & Prevention Centralized Data Replaces Many Inconsistent Copies Builds Framework for Culture of Learning Less Software to License Less System Maintenance Proactively Identifies Vulnerabilities Across Systems Reduced effort = improved resource utilization 21
22 Enterprise Timeline Initial Consolidation BES EIDS RADS Single Sign-On Application Registration Common Portal & Basic Analytics Integrated Database Enterprise Reporting Initial BI/Analytics RAI Future Applications Reduced Systems Enhanced Analytics Integrated Dashboard Enhanced Reporting Holistic View Reduced Complexity Increased Efficiency Standard Public Report Capability 22
23 ERO Enterprise Information System Estimated Cost Reliability Assessment Applications Compliance Applications Events/Risk/ Business Analytics Applications Year Estimate $700K $120K $120K $940K $150K $1.5M $500K $2.15M $500k $1.1M $400k $2M Data center $420K $480K $540k $1.4M Contractor Support $510K $600K $600K $1.71M Subtotal $2.18M $3.8M $2.16M $8.2M 23
24 Summary Additional Revenue Requirements Regulatory Mandates Standards Reform Initiative Reliability Assurance Initiative ERO Applications Subtotal $850K $200K $800K $2.18M $4.03M 24
25 Cyber (ES-ISAC) Cost of current operations (without overhead allocations) $2.4M 7 FTEs Includes software licensing, contractor and consulting support for ESCC and ES-ISAC, security exercises, assessments Incremental 2014 ES-ISAC contractor/consulting support ($550k) Information sharing Intelligence gathering and reporting Cyber risk preparedness assessments Cyber threat modeling and analytics Incremental 2014 personnel (5 FTEs/$1.2M) 25
26 Stakeholder Input Requested Option and mechanics of funding ESCC support, ES-ISAC and Operator Certification and Testing outside 215 Standards Reform Initiative and funding requirements Reliability Assurance Initiative and funding requirements ERO Enterprise Information System strategy and funding requirements 26
27 Next Steps Schedule Date May 8 May 22 May 30 Early June June 10 July 11 Activity Presentation of first draft of NERC 2014 Business Plan and Budget at MRC Meeting FAC conference call and webinar to review REs Business Plans and Budgets Stakeholder comments on first draft due Closed FAC conference call to provide input to management for second draft of NERC business plan and budget NERC posts second draft of business plan and budget Comments due on second draft of business plan and budget 27
28 Next Steps Schedule Date July 19 August 12 Activity FAC meeting to review second draft of NERC Business Plan and Budget, and proposed final REs Business Plans and Budgets FAC meeting to approve final NERC and REs Business Plans and Budgets and assessments August 14 (If needed, recap of 2014 Business Plan and Budget) Discussion of 2015 Business Plan and Budget process August 15 August 23 Board of Trustees meeting to approve final NERC and REs Business Plans and Budgets and assessments Submit ERO Business Plan and Budget and assessments to FERC for approval. File with Canadian authorities 28
29 29
Electric Reliability Organization Enterprise Performance Metrics
Electric Reliability Organization Enterprise Performance Metrics In 2014, NERC and the Regional Entities introduced a common set of ERO Enterprise performance metrics. These metrics are intended as indicators
More informationFEDERAL ENERGY REGULATORY COMMISSION DOCKET NO. RR14- NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION
FEDERAL ENERGY REGULATORY COMMISSION DOCKET NO. RR14- NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION DRAFT FIVE-YEAR ELECTRIC RELIABILITY ORGANIZATION PERFORMANCE ASSESSMENT REPORT OVERVIEW OF NERC ACTIVITIES
More informationReliability Assurance Initiative. Sonia Mendonca, Associate General Counsel and Senior Director of Enforcement
Reliability Assurance Initiative Sonia Mendonca, Associate General Counsel and Senior Director of Enforcement Agenda Reliability Assurance Initiative (RAI) Overview 2015 ERO CMEP Implementation Plan Inherent
More informationOPERATIONAL EXCELLENCE ACROSS THE ERO ENTERPRISE: Adding Value to the Compliance Monitoring and Enforcement Program
OPERATIONAL EXCELLENCE ACROSS THE ERO ENTERPRISE: Adding Value to the Compliance Monitoring and Enforcement Program A Discussion Paper By the Midwest Reliability Organization I. INTRODUCTION This discussion
More informationCompliance Monitoring and Enforcement Program Implementation Plan. Version 1.7
Compliance Monitoring and Enforcement Program Table of Contents TABLE OF CONTENTS NERC Compliance Monitoring and Enforcement Program... 1 Introduction... 2 NERC Compliance Monitoring and Enforcement Program
More informationIT Governance Overview
IT Governance Overview Contents Executive Summary... 3 What is IT Governance?... 4 Strategic Vision and IT Guiding Principles... 4 Campus-Wide IT Strategic Vision... 4 IT Guiding Principles... 4 The Scope
More information2018 Business Plan and Budget
2018 Business Plan and Budget Draft 2 July 17, 2017 I Table of Contents Table of Contents... ii About NERC... 1 Overview... 1 Membership and Governance... 2 Scope of Oversight... 2 Statutory and Regulatory
More informationEnterprise Risk Management Program Development Update. Finance & Audit Committee Meeting September 25, 2015
Enterprise Risk Management Program Development Update Finance & Audit Committee Meeting September 25, 2015 Enterprise Risk Management Presentation Topics Enterprise Risk Management ( ERM ) Overview Lead
More informationFinal Report Evaluation of Translation Bureau Programs Volume 2: Translation and Other Linguistic Services Program
2012-603 Evaluation of Translation Bureau Programs Office of Audit and Evaluation January 21, 2014 Table of Contents MAIN POINTS... i INTRODUCTION... 1 PROFILE... 1 Background... 1 Authority... 2 Roles
More informationAgenda Corporate Governance and Human Resources Committee February 7, :00-8:45 a.m. Eastern
Agenda Corporate Governance and Human Resources Committee February 7, 2018 8:00-8:45 a.m. Eastern Hilton Fort Lauderdale Marina 1881 SE 17 th Street Fort Lauderdale, FL 33316 Conference Room: Grand Ballroom
More informationSOLUTION BRIEF EU GENERAL DATA PROTECTION REGULATION COMPLIANCE WITH RSA ARCHER
EU GENERAL DATA PROTECTION REGULATION COMPLIANCE WITH RSA ARCHER ARRIVAL OF GDPR IN 2018 The European Union (EU) General Data Protection Regulation (GDPR), which takes effect in 2018, will bring changes
More informationAudit of the Management of Projects within Employment and Social Development Canada
Unclassified Internal Audit Services Branch Audit of the Management of Projects within Employment and Social Development Canada February 2014 SP-607-03-14E Internal Audit Services Branch (IASB) You can
More informationRSA Solution for egrc. A holistic strategy for managing risk and compliance across functional domains and lines of business.
RSA Solution for egrc A holistic strategy for managing risk and compliance across functional domains and lines of business Solution Brief Enterprise Governance, Risk and Compliance or egrc is an umbrella
More informationBusiness Risk Intelligence
Business Risk Intelligence Bringing business focus to information risk It s a challenge maintaining a strong security and risk posture. CISOs need to constantly assess new threats that are complex and
More informationRSA ARCHER MATURITY MODEL: AUDIT MANAGEMENT
RSA ARCHER MATURITY MODEL: AUDIT MANAGEMENT OVERVIEW Internal Audit (IA) plays a critical role in mitigating the risks an organization faces. Audit must do so in a world of increasing risks and compliance
More informationINFORMATION SERVICES FY 2018 FY 2020
INFORMATION SERVICES FY 2018 FY 2020 3-Year Strategic Plan Technology Roadmap Page 0 of 14 Table of Contents Strategic Plan Executive Summary... 2 Mission, Vision & Values... 3 Strategic Planning Process...
More informationCorporate Brochure. Elevate Your Flexible Workforce Management and Services Procurement
Corporate Brochure Elevate Your Flexible Workforce Management and Services Procurement Table of Contents SAP FIELDGLASS: POWERING YOUR FLEXIBLE WORKFORCE 4 IDENTIFYING YOUR CHALLENGES 6 DELIVERING YOUR
More informationPeriodic Review Template INT Implementation of Interchange
INT-009-2.1 Implementation of Interchange Executive Summary The Subject Matter Expert (SME) stakeholder team completed an initial comprehensive review of INT- 009-2.1 Implementation of Interchange. The
More informationAdvanced Enterprise Work and Asset Management for Performance-Driven Utilities
Advanced Enterprise Work and Asset Management for Performance-Driven Utilities Asset & Resource Management (ARM) 2 CGI s Asset & Resource Management (ARM) 2 suite is a solution designed to streamline the
More informationBuild a Future-Ready Enterprise With NTT DATA Modernization Services
NTT DATA welcomed Dell Services into the family in 2016. Together, we offer one of the industry s most comprehensive services portfolios designed to modernize business and technology to deliver the outcomes
More informationSimplify and Secure: Managing User Identities Throughout their Lifecycles
PRODUCT FAMILY BRIEF: CA SOLUTIONS FOR IDENTITY LIFECYCLE MANAGEMENT Simplify and Secure: Managing User Identities Throughout their Lifecycles CA Identity & Access Management (IAM) Identity Lifecycle Management
More informationDrive more value through data source and use case optimization
Drive more value through data source and use case optimization BEST PRACTICES FOR SHARING DATA ACROSS THE ENTEPRRISE David Caradonna Director, Global Business Value Consulting Date Washington, DC Forward-Looking
More informationExecutive Steering Committee Meeting. Department of Revenue Building 2, Room 1250 July 27, 2016
Executive Steering Committee Meeting Department of Revenue Building 2, Room 1250 Roll Call and Opening Remarks Facilitator: Robert (Budd) Kneip, Chair Review of June 2016 Meeting Minutes Facilitator: Robert
More informationNERC Reliability Update Power System Reliability Regulation Overview
NERC Reliability Update Power System Reliability Regulation Overview Herb Schrayshuen Principal Power Advisors, LLC November 3, 2014 CNY Engineering Expo 1 Learning Objectives By the conclusion of this
More informationAudit of Shared Services Canada s Information Technology Asset Management
Audit of Shared Services Canada s Information Technology Asset Management Audit Report June 2017 Period of Examination from September 1, 2014, to September 30, 2015 TABLE OF CONTENTS Executive Summary...
More informationSOLUTION BRIEF EU GENERAL DATA PROTECTION REGULATION COMPLIANCE WITH RSA ARCHER
EU GENERAL DATA PROTECTION REGULATION COMPLIANCE WITH RSA ARCHER ARRIVAL OF GDPR IN 2018 The European Union (EU) General Data Protection Regulation (GDPR) that takes effect in 2018 will bring changes for
More informationFrequently Asked Questions August 2013
Frequently Asked Questions August 2013 General What is the Bulk-Power System or Bulk Electric System? NERC defines the Bulk-Power System as the electricity power generation facilities combined with the
More informationStaff Position Management Guidelines
Staff Position Management Guidelines PURPOSE AND FRAMEWORK To ensure USC is exercising the highest levels of responsible stewardship and accountability for managing its staff and related resources, the
More informationBuilding a Foundation for Effective Service Delivery and Process Automation
Building a Foundation for Effective Service Delivery and Process Automation Agenda Service Management World Tour IBM Service Management Customer Challenges Overview of Service Delivery and Process Automation
More informationMSP Purpose, Value & ROI
PERSPECTIVE ARTICLE MSP Purpose, Value & ROI A Comprehensive Look at Today s Global Managed Service Provider Programs In this perspective article, Bartech an industry professional services firm delivering
More informationMarket System Evaluation. June 2017
Market System Evaluation June 2017 How do we extend and protect MISO s value proposition? Execution of MISO s strategy is predicated on secure systems with the tools and information required to ensure
More informationInternal audit strategic planning Making internal audit s vision a reality during a period of rapid transformation
2015 State of the Internal Audit Profession Study Internal audit strategic planning Making internal audit s vision a reality during a period of rapid transformation 68% of companies have gone through or
More informationExtended Enterprise Risk Management
Extended Enterprise Risk Management Overview of Risks and Methodologies/Tools to Address FEI Presentation June 7, 2016 Our POV on Extended Enterprise Risk Management Operational Risk Framework Organizations
More informationThe importance of a solid data foundation
The importance of a solid data foundation Prepared by: Michael Faloney, Director, RSM US LLP michael.faloney@rsmus.com, +1 804 281 6805 February 2015 This is the first of a three-part series focused on
More information2014 Integrated Internal Control Plan. FRCC Spring Compliance Workshop April 8-10, 2014
2014 Integrated Internal Control Plan Contents Definitions Integrated Components of COSO Internal Control Framework The COSO Internal Control Framework and Seminole Control Environment Risk Assessment
More informationSolutions for Enterprise Risk Management SAS. Overview. A holistic view of risk of risk and exposures for better risk management SOLUTION OVERVIEW
SOLUTION OVERVIEW SAS Solutions for Enterprise Risk Management A holistic view of risk of risk and exposures for better risk management Overview The principal goal of any financial institution is to generate
More informationMRO s CMEP Approach Ten-Year Retrospective and A Bright Future
MRO s CMEP Approach Ten-Year Retrospective and A Bright Future Sara Patrick, MRO Vice President, Compliance Monitoring and Regulatory Affairs Joint Standards and Compliance Committees Meeting August 3,
More informationA. Introduction. B. Requirements. Standard PER System Personnel Training
A. Introduction 1. Title: System Personnel Training 2. Number: PER-005-1 3. Purpose: To ensure that System Operators performing real-time, reliability-related tasks on the North American Bulk Electric
More informationDepartment of Navy Audit Update
Department of Navy Audit Update Northern Virginia Chapter Association of Government Accountants April 28, 2017 Victoria Crouse, Chief Strategy Officer Agenda What We ve Done Journey to Date: Key Milestones
More informationSOLUTION BRIEF RSA ARCHER PUBLIC SECTOR SOLUTIONS
RSA ARCHER PUBLIC SECTOR SOLUTIONS INTRODUCTION Federal information assurance (IA) professionals face many challenges. A barrage of new requirements and threats, a need for better risk insight, silos imposed
More informationCABINET DIRECTIVE ON STREAMLINING REGULATION
CABINET DIRECTIVE ON STREAMLINING REGULATION Her Majesty the Queen in Right of Canada, 2007 Catalogue No. BT22-110/2007 ISBN 978-0-662-49149-1 Table of Contents Our Commitment to Canadians... 1 1.0 Introduction...
More informationWhite paper. Getting better business results from your CRM
White paper Getting better business results from your CRM Table of contents: Introduction...1 Customer relationship management continues to grow...1 Poor quality CRM data and its impact on an organization...1
More informationEnterprise-wide Risk Case
Enterprise-wide Risk Case December 4, 2013 Management Categorizing Costs and Savings for Clearer Return on Investment (ROI) Executive Summary Greater losses from financial crime incidents, pressure to
More information2018 ERO Enterprise Compliance Monitoring and Enforcement Implementation Plan
2018 ERO Enterprise Compliance Monitoring and Enforcement Implementation Plan Version 2.0 November 2017 NERC Report Title Report Date I Table of Contents Revision History... iv Preface... v Introduction...
More informationMarket Systems Enhancement
Market Systems Enhancement Update for the Technology Committee MISO Board of Directors November 28, 2017 Executive Summary Market System Enhancement Program is refining its seven-year plan, including key
More informationCIP Cyber Security - Supply Chain Risk Management. A. Introduction
A. Introduction 1. Title: Cyber Security - Supply Chain Risk Management 2. Number: CIP-013-1 3. Purpose: To mitigate s to the reliable operation of the Bulk Electric System (BES) by implementing security
More informationIBM Institute for Business Value. Brazil Point of View IBM Corporation
IBM Institute for Business Value Brazil Point of View Introduction The 2010 IBM CFO Study is the fourth edition since 2003 and builds upon our primary research from 2005 and 2008 CFO Studies 2003 2005
More informationCompliance Monitoring and Enforcement Program Standards and Guidance
Compliance Monitoring and Enforcement Program Standards and Guidance This document is based on the standards found in the Yellow Book of the United States Government Accountability Office, produced by
More informationTHE COST OF DOING BUSINESS IMPROVING UTAH S REGULATORY SYSTEM
THE COST OF DOING BUSINESS IMPROVING UTAH S REGULATORY SYSTEM KEEPING UTAH THE BEST STATE FOR BUSINESS As the statewide voice for business, the Salt Lake Chamber works to ensure Utah s business climate
More informationPublic Service Commission of Canada
Public Service Commission of Canada 2013-14 Estimates Report on Plans and Priorities Public Service Commission of Canada 2013-14 Report on Plans and Priorities Table of Contents PRESIDENT S MESSAGE...
More informationCIP Cyber Security Security Management Controls
A. Introduction 1. Title: Cyber Security Security Management Controls 2. Number: CIP-003-5 3. Purpose: To specify consistent and sustainable security management controls that establish responsibility and
More informationLeveraging Internal Audit and Corporate Compliance for Effective Risk Management
Leveraging Internal Audit and Corporate Compliance for Effective Risk Management April 18, 2016 Don Sinko Chief Integrity Officer Cleveland Clinic Agenda Cleveland Clinic Integrity Office Model The 3 Lines
More informationFulfilling CDM Phase II with Identity Governance and Provisioning
SOLUTION BRIEF Fulfilling CDM Phase II with Identity Governance and Provisioning SailPoint has been selected as a trusted vendor by the Continuous Diagnostics and Mitigation (CDM) and Continuous Monitoring
More informationERO Enterprise Inherent Risk Assessment Guide
ERO Enterprise Inherent Risk Assessment Guide October 2014 I Table of Contents Introduction... ii Revision History... ii 1.0 IRA Introduction...1 1.1 IRA Role within the Overall Risk-Based Compliance Oversight
More informationBaseline assessments. The Connected Enterprise Execution Model. Stage 1. Data and reporting. Network infrastructure
Stage 1 Baseline assessments Without a solid infrastructure you can t achieve the desired value you re looking for. Therefore, a comprehensive infrastructure and network assessment will establish to what
More informationBuilding a Winning Business Case for HCM SaaS
Building a Winning Business Case for HCM SaaS Mark Bray, Principal Consultant ISG WHITE PAPER 2016 Information Services Group, Inc. All Rights Reserved INTRODUCTION The number of enterprises that experience
More informationAligning and rationalizing your business applications. How to simplify the IT portfolio and reduce costs in financial services
Aligning and rationalizing your business applications How to simplify the IT portfolio and reduce costs in financial services Contacts Atlanta Ajay Nayar Principal +1-404-271-3890 ajay.nayar@strategyand.pwc.com
More informationCOUNTY OF SAN JOAQUIN STRATEGIC DIRECTION FOR INFORMATION TECHNOLOGY
COUNTY OF SAN JOAQUIN STRATEGIC DIRECTION FOR INFORMATION TECHNOLOGY San Joaquin County government will transform the manner in which it provides services to the public and its employees so as to promote
More informationPeriodic Review Template INT Dynamic Transfers
INT-004-3.1 Dynamic Transfers Executive Summary The Subject Matter Expert (SME) stakeholder team completed an initial comprehensive review of INT- 004-3.1 Dynamic Transfers. The SME stakeholder team finds
More informationExtended Enterprise Risk Management
Extended Enterprise Risk Management Driving performance through the extended enterprise October 2015 A network within a network The Extended Enterprise is the concept that an organization does not operate
More informationORACLE DAILY BUSINESS INTELLIGENCE FOR HCM
ORACLE DAILY BUSINESS INTELLIGENCE FOR HCM KEY BENEFITS Drive workforce engagement with better insight Reduce retention and prepare workforce capacity to deliver Improve profitability through workforce
More informationStatewide Technology Cooperative Contracting Program
DATA, INFORMATION, AND KNOWLEDGE MANAGEMENT Statewide Technology Cooperative Contracting Program Transforming Traditional Procurement to Knowledge-Driven Sourcing in Texas EXECUTIVE SUMMARY The competitiveness
More informationACCENTURE & SAP SUCCESS FACTORS INVESTIGATE CAPABILITIES WORKBOOK. Imagine where we will go together...
ACCENTURE & SAP SUCCESS FACTORS INVESTIGATE CAPABILITIES WORKBOOK Imagine where we will go together... Imagine where we will go together... AGENDA TUESDAY APRIL 19TH 12:00 PM Lunch (outside Ali Conference
More informationGroup Accountant (Children s Services)
Grade: 54,000 Group Accountant (Children s Services) Section: Division: Department: Reports to: As Required Finance Chief Executive Group Manager (Services) Purpose of the Job You are employed to provide
More informationTIAA-CREF, Our Journey to Enhanced Data Quality
TIAA-CREF, Our Journey to Enhanced Quality Carl Gerber, Director, Transformation Program, TIAA-CREF cgerber@tiaa-cref.org events.techtarget.com SearchBusinessAnalytics SUMMIT TechTarget Our Journey to
More informationMarket System Evaluation. March 2017
Market System Evaluation March 2017 Executive Summary MISO s ability to execute its strategy is predicated upon having secure systems providing the tools and information required. Last fall we initiated
More informationReining in Maverick Spend. 3 Ways to Save Costs and Improve Compliance with e-procurement
3 Ways to Save Costs and Improve Compliance with e-procurement Contents The Need to Eliminate Rogue Spending Exists for all Businesses...3 Leveraging Technology to Improve Visibility...5 Integrate your
More informationIT Management Maturity Model
IT Management Model In support of the implementation of the Federal Information Technology Acquisition Reform Act (FITARA) Published September 2015 Version 1 Advancing Government Through Collaboration,
More informationCorporate Risk Profile. National Film Board of Canada
Corporate Risk Profile National Film Board of Canada Approved by the NFB Board of Trustees March 1 st, 2013 Contents 1. Introduction... 3 1.1 Integrated risk management at the NFB Background... 3 1.2 MAF
More informationThe Next Frontier in HR Analytics
BUSINESS ANALYTICS The Next Frontier in HR Analytics Oracle Transactional Business Intelligence Enterprise for HCM Cloud Service Copyright 2014 Oracle Corporation. All Rights Reserved. 2 Analytics are
More informationBuilding a Roadmap to Robust Identity and Access Management
Building a Roadmap to Robust Identity and Access Management Elevating IAM from Responsive to Proactive From cases involving private retailers to government agencies, instances of organizations failing
More information6. Cross-Cutting Issues Indicators
6. Cross-Cutting Issues Indicators This thematic area evaluates in more detail several key topics that transcend each of the first four thematic areas. As such, the indicators in this section can be applied
More informationEnabling Dynamic Enterprise Catalogs to Improve Customer Experience By Chun-Ling Woon and R. Kripa Kripanandan
www.pipelinepub.com Volume 5, Issue 11 Enabling Dynamic Enterprise Catalogs to Improve Customer Experience By Chun-Ling Woon and R. Kripa Kripanandan The Current Service Provider Dilemma Next generation
More informationIBM Impact Grants. Offering Portfolio
Offering Portfolio The consultative services provided by IBM for our strategic plan were used as a catalyst for our programming model. The facilitators were excellent and the leadership model positioned
More informationCEO Performance Planning and Review Process
DRAFT 01 Feb 2017 CEO Performance Planning and Review Process A good leader is not the person who does things right, but the person who finds the right things to do. Anthony T. Padovano, theologian and
More informationThe SAS Intelligence Architecture
Enterprise Intelligence Supplier Intelligence Organizational Intelligence Customer Intelligence Intelligence Architecture The SAS Intelligence Architecture The flexible foundation for enterprise intelligence
More informationTelecom Network Inventory Transformation Mere network information is not enough
Telecom Network Inventory Transformation Mere network information is not enough Inventory modernization as a part of the modernization In any organization, there are several groups that rely on information
More informationPlanview Enterprise One
Data sheet Planview Enterprise One Accelerate strategic execution enterprise-wide across all work and resources Savvy business leaders aspire to confidently drive change that advances their strategic objectives,
More informationSecuring Intel s External Online Presence
IT@Intel White Paper Intel IT IT Best Practices Information Security May 2011 Securing Intel s External Online Presence Executive Overview Overall, the Intel Secure External Presence program has effectively
More informationHuman Resources Information System Business Case Executive Summary
Human Resources Information System Business Case Executive Summary January 2009 Oregon Department of Administrative Services Statewide (503) 373-3270 Human Resource Management System (HRIS) BusinE-mail
More informationPHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008)
PHASE TWO FOLLOW-UP REPORT ON THE AUDIT OF CONTRACTS (2008) PREPARED BY: Government Audit Services Branch Government of Yukon APPROVED BY: Audit Committee Table of Contents Page PREFACE 3 EXECUTIVE SUMMARY
More informationWelcome to the postmodern era for public sector ERP
Welcome to the postmodern era for public sector ERP Time to update your public sector enterprise resource planning (ERP)? Consider a postmodern strategy to address your unique requirements. Welcome to
More informationFinancial Services Compliance
Financial Services Compliance Amidst frequently changing regulations, heightened risk, and a growing volume of disparate data, compliance has become complex, inefficient, and costly. Mitigating new risk
More informationElevate your organization. To reach the Cloud.
Elevate your organization. To reach the Cloud. En route to Digital. Results from KPMG s Harvey Nash Survey. The Harvey Nash Survey 4,500 Responses 2 Decades $1-3trn IT budget 86 Countries 118 Government
More informationEstablishing a Sustainable Succession Planning Program
Keeping your workforce vibrant: Establishing a Sustainable Succession Planning Program 2015 Accounting Leadership Conference & Chief Audit Executives Conference ParenteBeard and Baker Tilly merged in October,
More information4/26. Analytics Strategy
1/26 Qlik Advisory As a part of Qlik Consulting, Qlik Advisory works with Customers to assist in shaping strategic elements related to analytics to ensure adoption and success throughout their analytics
More informationAudit of Entity Level Controls
Unclassified Internal Audit Services Branch Audit of Entity Level Controls February 2014 SP-606-03-14E You can download this publication by going online: http://www12.hrsdc.gc.ca This document is available
More informationDriving Business Performance
Workforce Scheduling Driving Business Performance How Workforce Scheduling Optimization Aligns the Workforce with Business Demands for Customer Satisfaction and Success While many factors affect an organization
More informationPOSSE System Review. January 30, Office of the City Auditor 1200, Scotia Place, Tower Jasper Avenue Edmonton, Alberta T5J 3R8
1200, Scotia Place, Tower 1 10060 Jasper Avenue Edmonton, Alberta T5J 3R8 edmonton.ca/auditor POSSE System Review January 30, 2017 The conducted this project in accordance with the International Standards
More informationIT S TIME! PRIMARIS OPERATIONAL EFFICIENCY SOLUTION. Using Lean Thinking to Save Time & Money. Benefits of Operational Efficiency. Why Primaris?
IT S TIME! PRIMARIS OPERATIONAL EFFICIENCY SOLUTION Using Lean Thinking to Save Time & Money Healthcare executives are well aware that both government agencies and private insurers are moving away from
More informationINTERNATIONAL ACCOUNTING EDUCATION STANDARDS BOARD STRATEGY AND WORK PLAN March 2017
INTERNATIONAL ACCOUNTING EDUCATION STANDARDS BOARD STRATEGY 2017 2021 AND WORK PLAN 2017 2018 March 2017 Strategy 2017 2021 IAESB Strategy 2017 2021 The International Accounting Education Standards Board
More informationAN EXECUTIVE S GUIDE TO BUDGETING FOR SECURITY INFORMATION & EVENT MANAGEMENT
WHITE PAPER AN EXECUTIVE S GUIDE TO BUDGETING FOR SECURITY INFORMATION & EVENT MANAGEMENT COST ANALYSIS OF TWO DELIVERY MODELS: SELF-MANAGED SIEM VS. MANAGED SIEM SERVICES AN EXECUTIVE S GUIDE TO BUDGETING
More informationAn Automated Decision Support System to Assist with Project Planning, Program Management and Work Flow Analysis of an Enterprise
An Automated Decision Support System to Assist with Project Planning, Program Management and Work Flow Analysis of an Enterprise NBS Enterprises Competition Sensitive Natasha J. Schebella / CEO & Owner
More informationQUICK FACTS. Delivering a Managed Services Solution to Satisfy Exponential Business Growth TEKSYSTEMS GLOBAL SERVICES CUSTOMER SUCCESS STORIES
[ Financial Services, Application Management Outsourcing ] TEKSYSTEMS GLOBAL SERVICES CUSTOMER SUCCESS STORIES Client Profile Industry: Financial Services Revenue: Approximately $30 billion annually (parent
More informationFORM A: UCLA IT Investment Request Form (FY ) UCLA Student Information System (SIS)
FORM A: UCLA IT Investment Request Form (FY 20152016) Project Name: Project Sponsor(s): Project Manager(s): CFO / VC Steve Olsen, VC Janina Montero, VC Administration (TBD), VP Robin Garrell, and VP Patricia
More information36th Board Meeting Prioritized Action Plan (PAP) to Accelerate Management for Impact For Board Information
36th Board Meeting Prioritized Action Plan (PAP) to Accelerate Management for Impact For Board Information GF/B36/27 Montreux, Switzerland 16-17 November 2016 Prioritized Action Plan Help the Secretariat
More informationClient onboarding and Legal Entity Data Solutions from Thomson Reuters
Client onboarding and Legal Entity Data Solutions from offers a broad and integrated suite of KYC, client onboarding and legal entity data solutions to support your ongoing client lifecycle management
More informationRegulatory system strengthening
SIXTY-SEVENTH WORLD HEALTH ASSEMBLY A67/32 Provisional agenda item 15.6 14 March 2014 Regulatory system strengthening Report by the Secretariat 1. The Executive Board at its 134th session noted an earlier
More informationManagement Excluded Job Description
Management Excluded Job Description 1. Position Identification Position Number 993234 Position Title Department Reports to (title) Associate Director, Supply Management Purchasing Services Director, Purchasing
More informationReview of Duke Energy Florida, LLC Internal Audit Function
Review of Duke Energy Florida, LLC Internal Audit Function MAY 2017 B Y A U T H O R I T Y O F The Florida Public Service Commission Office of Auditing and Performance Analysis Review of Duke Energy Florida,
More information