Mosaic-1 Upgrade Project Execution Plan

Size: px
Start display at page:

Download "Mosaic-1 Upgrade Project Execution Plan"

Transcription

1 NATIONAL OPTICAL ASTRONOMY OBSERVATORY SYSTEM INSTRUMENTATION GROUP 950 N. Cherry Ave. P. O. Box Tucson, Arizona (520) FAX: (520) Mosaic-1 Upgrade Project Execution Plan NOAO Document M1U-AD Revision: 0 Authored by: David Sawyer Please send comments: dsawyer@noao.edu Page 1 of 16

2 Revision History Version Date Approved Sections Affected Remarks 0 01/07/2010 All Original Version Page 2 of 16

3 Table of Contents Revision History...2 Table of Contents...3 List of Figures...4 List of Tables Introduction Project Management ReSTAR Funding Budget Allocation NOAO Base Funding Budget Allocation Project WBS Project Plan and Schedule Project Management Detector System Dewar Assembly Software System Integration and Commissioning Coordination between KPNO Engineering and Systems Instrumentation Contingency Management Configuration Management Systems Engineering Requirements Management Risk Management Error Budget Management Observatory Interfaces Instrument Interface Detector Interface Facility Interface Design Reviews Project Plan Review Final Design Review Safety...16 Page 3 of 16

4 List of Figures Figure 1 - Work Breakdown Structure for the Mosaic-1 Upgrade Project...7 Figure 2 - Schedule for the Project Management Component of the Mosaic Project.8 Figure 3 - Schedule for the Detector System Component of the Mosaic Project...8 Figure 4 - Schedule for the Design Component of the Dewar Assembly...9 Figure 5 - Schedule for the Fabrication and Assembly Component of the Dewar...10 Figure 6 - Schedule for the Software Component of the Mosaic Project...11 Figure 7 - Schedule for the Integration and Commissioning Components of the Mosaic Project...11 Figure 8 - Project vs. Functional Lines of Authority for the Matrix Organization..12 List of Tables Table 1 - Effort levels for the assigned resources and labor skills derived from the project schedule described in section Page 4 of 16

5 1 Introduction The primary objectives of the Mosaic-1 Upgrade are to replace the aging (and obsolete) CCD controllers with modern MONSOON controllers, and to replace the CCD detectors to improve observing efficiency (faster readout times) and performance (quantum efficiency and read noise). Both the controllers and detectors must be replaced to achieve the desired gains in performance and efficiency. Beyond these objectives the only requirements are that the imaging performance must not be degraded, the instrument must use the same mechanical interface and ancillary equipment (filters, corrector, ADC, etc.), and the resulting data files must be compatible with the existing NOAO science data archive. Upgrading the controllers and detectors will provide the potential for several performance and operational enhancements beyond the scope of the requirements and these will be exploited as time and budget allow. There are two options for MONSOON controllers. One is a mature project, called Torrent, in progress to develop a new generation of MONSOON controllers. The Torrent controllers are designed for low power, ease of configuration, and use readily available components. The other option is the Orange controller, a previous generation MONSOON controller that is in use today on many instruments. The Torrent controllers are more suitable for the Mosaic upgrade application and thus are included in the baseline design. However, the Orange controllers will provide a fallback option if the Torrent project is not completed in time. 2 Project Management The responsibility of managing the Mosaic-1 Upgrade project has been assigned to the team of David Sawyer (Project Manager, or PM) and Steve Howell (Project Scientist, or PS). The PM will focus primarily on the administrative aspects of the project (budget, schedule, resource allocation, etc) while the PS focuses on the scientific and operational aspects (developing requirements, engaging the community, etc), although they will work together on most project-related activities. The PM reports to the NOAO System Technology Center (NSTC) Director, David Sprayberry, while the PS reports to the Kitt Peak National Observatory (KPNO) Director, Buell Jannuzi. The project is a joint KPNO/NSTC effort and both centers will provide the direction and oversight for the project. The management team is responsible for defining the requirements and scope of the project, developing a plan for completing the project, conducting reviews as appropriate, and providing suitable documentation. The management team will report on the status of the project at the weekly KPNO projects meeting and provide monthly written progress reports to the KPNO and NSTC Directors. It is expected that a broad group of people from within NOAO will be involved in the Mosaic-1 upgrade during the process of defining the project as well as during the construction, integration and commissioning phases. The management team will engage the NOAO group as appropriate and define work packages as required. Page 5 of 16

6 2.1 ReSTAR Funding Budget Allocation The total ReSTAR allocation to the Mosaic-1 Upgrade is $520,000. This amount is notionally allocated to capital equipment purchases in the approximate distribution of $500K for replacement detectors and $20K toward computers to drive the replacement controllers. Adjustments to the allocation of the funds may occur as the project progresses. The CCD detector selection was a critical component of the project regarding budget, science and mechanical design decisions and thus the detectors have been ordered from e2v Technologies as of December The cost of the replacement detectors was $520K, or $20K over the ReSTAR allocation, and so the difference will be covered in the base budget. 2.2 NOAO Base Funding Budget Allocation NOAO will supplement the ReSTAR funds with approximately $200K for labor from the base budget, and another $20K to make up the difference in the actual detector cost. These funds will pay for the PM and staff from the NOAO technical pool at the levels shown in Table 1. In addition, the PS will be paid from the KPNO operations budget. Table 1 - Effort levels for the assigned resources and labor skills derived from the project schedule described in section 2.4. Resource Skill Hours FTE Ditsler Tech support vacuum, detectors Daly Software engineer Dryden Electronic technician ET TBD MONSOON electronic technician Hunten Detector engineer NOAO Shop TBD Instrument maker KPNO Instrument Support Trainee KPNO Support Staff Instrument change Moore Detector engineer Rath Mechanical designer/instrument maker Rosin Draftsman Sawyer Project manager/systems engineer Schweiker Instrument specialist DHS Programmer TBD Software engineer Totals Project WBS The work breakdown structure for the Mosaic-1 Upgrade project is shown graphically in Figure 1. There are six major categories that, with the exception of project management, are matched to project deliverables. The detector system, Dewar assembly and software components can be developed in parallel and delivered independently. After that the project becomes more serial in that the system integration effort must follow the delivery of the components and the commissioning effort must follow the completion of system integration. In most cases the WBS is detailed to three levels, and at most four levels. The WBS is designed to provide adequate accounting and tracking for a project of this size while keeping the administrative effort modest. Page 6 of 16

7 Work Breakdown Structure for the Mosaic-1 Upgrade Project Figure Project Plan and Schedule A detailed schedule has been developed that accomplishes the primary objectives of the upgrade effort with realistic estimations of the resources available. The schedule follows the WBS organization and thus this description of the project plan and schedule will be broken down into the major WBS categories Project Management The project management component of the schedule is shown in Figure 2. The general project management responsibilities for the Mosaic upgrade project are projected to require one day a week each for the project manager and the project scientist for the duration of the project. In addition, there are specific project management tasks to development requirements and a project plan (this document), as well as preparing for two design reviews. The detailed design of the Dewar assembly is linked to Review 1 and is shown in Figure 4. The fabrication of the Dewar assembly is linked to Review 2 and is shown in Figure 5. The transition module component of the schedule is shown in Figure 3 and is linked to Review 2 (link not shown) because it is expected that the decision about the controller option will be finalized at that time. Page 7 of 16

8 Schedule for the Project Management Component of the Mosaic Project Figure Detector System The CCD Detector component of the schedule involves the procurement and testing/characterization of the detectors selected for the Mosaic upgrade. The detectors have been ordered from e2v Technologies and are expected to arrive by April 15, In the meantime there is design, fabrication and assembly work scheduled to build a chip mount for a universal test Dewar to allow testing the e2v devices in the lab. The plan is to build a chip mount that will allow the e2v detectors to be installed and tested two at a time. Schedule for the Detector System Component of the Mosaic Project Figure 3 Page 8 of 16

9 Before testing the e2v CCDs in the lab it will be necessary to configure the MONSOON controller electronics (Torrent or Orange) for the devices. This configuration is scheduled to begin immediately after the first design review so it can be completed by the time the detectors are delivered in mid-april as shown by the link (items 25 and 18) in Figure 3. The assembly and testing of the MONSOON controller electronics needed for the Mosaic upgrade is being provided by the MONSOON group as a deliverable and is thus not shown in this schedule. Following the Torrent configuration tasks, the Torrent transition module assemblies are scheduled for assembly and testing. The fabrication of the transition modules requires the enclosures to be fabricated and thus the module assembly task (item 29 on the schedule) is linked to item 47 (Figure 5) Dewar Assembly The first two components of the Dewar Assembly are the conceptual design and the detailed design phases as shown in Figure 4. The conceptual design phase primarily involves determining viable solutions for the upgrade components, including a new chip mount for the e2v detectors and the interface and mounting of the MONSOON controllers (either Torrent or Orange). The original Mosaic design was done using AutoCAD and since Solidworks is now the adopted CAD tool used at NOAO, there is a modest effort scheduled to convert the AutoCAD drawing to solid models. At the completion of the conceptual design there will be a design review (Review 1) where the proposed design solutions will be scrutinized. Following the approval of the conceptual designs, the detailed design phase will begin. The product of the detailed design phase will be fabrication-ready drawings for all new components and any modifications to existing components. A final design review is scheduled to occur at this point on March 23, 2010 and after that, upon acceptance of the final design, fabrication will begin. Schedule for the Design Component of the Dewar Assembly Figure 4 Figure 5 shows the fabrication and assembly components of the Dewar Assembly. The machining of the chip mount assembly will be done in the NOAO machine shop using a CNC mill to achieve the necessary machining tolerances for the CCD mounting holes and surface flatness. The machining of the connector pods and Torrent transition modules is scheduled to be done by S. Rath in the model shop, but using the NOAO machine shop as an additional resource is a viable option. During the fabrication phase, the new connector pods and their associated connectors and wiring will also be completed. Page 9 of 16

10 Schedule for the Fabrication and Assembly Component of the Dewar Figure 5 Following the completion of the fabrication phase, the Dewar rework and assembly phase begins with the assembly of the new focal plane. This involves mounting the eight CCD detectors on the chipmount and measuring/verifying the flatness of the detector focal plane. In the meantime, the Mosaic imager will be taken out of service on June 11, 2010, removed from the telescope and transported to the NOAO labs in Tucson. Once the instrument arrives in Tucson, the Dewar assembly will be separated from the filter/shutter mechanisms and the two components will be reworked in parallel. D. Dryden is scheduled to overhaul the filter/shutter mechanism to improve its performance and reliability (This is not actually part of the upgrade project, but is an opportune time to do this necessary servicing), while B. Ditsler is scheduled to complete the Dewar upgrades. The Dewar upgrade starts by removing the existing focal plane assembly and all of its associated wiring and placing it into safe storage. This will preserve the option of returning Mosaic to its current configuration as a technical contingency measure. During the removal of the focal plane careful measurements will be made to ensure that the focus position can be precisely duplicated with the new detectors. After disassembly, the Dewar will receive standard servicing (e.g., cleaning, bake desiccant, etc.) and any modifications that may be needed (e.g., grinding the surface of the radiative cold plate that attaches to the chip mount if better flatness is required.) The new focal plane will then be installed and measured through the Dewar window for focus position and tilt. The shims at the mounting posts will be lapped to adjust any positional errors. Once the focal plane is positioned the new wiring modules will be installed and, after attaching the radiative cold plate, they will be checked for continuity. The remainder of the Dewar will be assembled (LN2 tank, desiccant, and housing), checked for vacuum leaks and put through several pump-flush-pump cycles to maximize the vacuum and hold time. Once the Dewar rework is complete there is a week scheduled to cool the instrument and conduct thermal stability tests, and another week to test the detectors. These are really just functional verification tests but there is a two-week contingency scheduled at this point in case any problems are found or additional tests are required. Page 10 of 16

11 2.4.4 Software The user interface and user software must be changed as part of the upgrade project. Currently Mosaic-1 is run with an IRAF ARCON package as well as a few independent GUIs that control specific features of the instrument/telescope combination. Given the success of NEWFIRM s user interface and control system (NOCS), we are proposing this option to use for the new Mosaic-1 user interface. The advantages of choosing NOCS are 1) it has had two years of use and tuning at the Mayall telescope, 2) has complete and plentiful documentation, 3) a number of 4-m users are already experienced with its use, 4) the software will be going to Chile with NEWFIRM and so manuals already exist to teach the new system to the CTIO staff, 5) it is likely that NOCS will be used by KOSMOS at the Mayall, and 6) 90% of the functionality required to operate the new Mosaic-1 upgrade is already written and operational. The NOCS interface is already integrated with a Data Handling System (DHS) for NEWFIRM and only minor changes will be needed to modify the existing DHS for Mosaic. There is a modest software effort required to adapt the NOCS interface and DHS system for the Mosaic instrument. Figure 6 shows the tasks with rough estimates of time to complete them. These are only rough estimates of time, but there is plenty of schedule slack in this effort (item 74 to 75, almost two months) to absorb any increase in effort that may result from better estimates. Schedule for the Software Component of the Mosaic Project Figure System Integration and Commissioning The system integration phase of the project will involve the final assembly of all the subsystems in the lab where they will be tested as an end-to-end system. This component of the schedule requires that the Detector System, Dewar Assembly, and Software subsystems have all been completed, and thus the start date for this effort is driven by those links. The lab testing will involve functional verification, troubleshooting if required, and conducting the acceptance tests. An acceptance test plan will be prepared in advance and will ensure that the project requirements have been met. KPNO operations staff will be engaged during this system integration phase to provide a training opportunity. Once the integration is completed and the instrument has been accepted, it will be send to KPNO to start the commissioning phase. There is a two-week period scheduled for test and engineering in the telescope environment. Although the schedule shows the instrument being installed on the telescope at the start of the T&E period, it will probably occur a few days later to allow the functionality to be verified at the telescope before installation on the telescope. Most of the T&E testing will be done during the daytime and should not impact nighttime operations at the telescope, but a few T&E nights will be scheduled as Page 11 of 16

12 well. After the T&E period, there will be a few nights scheduled for conducting science programs to tune the operational efficiency and verify the scientific performance of the instrument. Schedule for the Integration and Commissioning Components of the Mosaic Project Figure 7 During the commissioning phase it is expected that KPNO staff will be involved to receive training and accept hand-over of the instrument. The user documentation will be completed and delivered as well. 2.5 Coordination between KPNO Engineering and Systems Instrumentation The PM will work with the appropriate managers within KPNO Engineering (T. Abraham) and NSTC/Electronics (M. Hunten) to identify and utilize their resources to the extent possible. The PM will utilize these resources in a matrix fashion by providing the project-related assignment and direction to the individuals, while leaving the functional obligations to their respective managers. Resource conflicts or concerns will be raised with the responsible manager and if a resolution cannot be reached the appropriate Director(s) will be notified. The PM will report the project status to both the KPNO Director (B. Jannuzi) and NSTC Director (D. Sprayberry) on a regular basis and, as part of the report, will provide a summary of the resource commitment and schedule status. Project vs. Functional Lines of Authority for the Matrix Organization Figure 8 Page 12 of 16

13 2.6 Contingency Management The contingency for budget and schedule are being managed through the scope of the upgrade effort. The schedule presented in section 2.4 was developed to meet the budget and schedule constraints of the project. There was a strong desire (goal) to build a new Dewar instead of retrofitting the existing one to minimize science downtime and risk associated with the upgrade project. However, this goal was not possible within the budget and timeline available and was not necessary to achieve the project requirements and thus was eliminated from the Project Plan. Additional project goals relating to user tools and operational modes may or may not be completed as time and budget allow. A source of schedule contingency will be available through additional labor (i.e., an increase in the base budget). The project will utilize staff from the KPNO and NSTC groups and, provided resources are available within those groups, they could be reassigned to the project to increase the work force. There is a modest cash contingency of $50K from the KPNO operations budget. Some of this contingency may be used to fabricate new Dewar parts if they have to be done by outside machine shops. This provides a contingency for the NOAO instrument shop that is notionally available for the Mosaic work but is currently involved in a large project (ODI) that could impact their availability. One of the technical risks of the project is the completion of the Torrent controllers. Torrent is well along toward meeting a production readiness state in March 2010 but is not complete and has not demonstrated performance at this time. A contingency plan to mitigate this risk will be to use the existing MONSOON Orange controllers instead of Torrents. The choice of controller will have minimal impact on the design phase of the project and thus this decision will be postponed until the Mosaic final design review (March 23, 2010) to give the Torrent project more time to progress. 2.7 Configuration Management This project will implement modest configuration management techniques to maintain revision control of drawings and documents. The PM and PS will have overall authority for acceptance of released documents and approval of changes thereafter. PDMWorks Enterprise software will be used as the document database for version control. The mechanical solid models will be developed in an initiated state where all project staff has access to them. Once the drawings are released by the PM or lead engineer the shop personnel will have access to them and no changes will be allowed unless the PM or lead engineer approve the changes and modify the drawing state to in revision. This process has been used effectively for several recent projects at NOAO. Documents will be entered into the PDMWorks database upon their initial release. There will be group access levels to the database that are appropriate for the types of documents. For instance, only a management group will have full access to documents with sensitive financial information, whereas the technical group can have full access to the technical documentation. In most cases any general user will have read-only access to project documents. 3 Systems Engineering The PM, David Sawyer, will also act as the Systems Engineer (SE) for the Mosaic-1 Upgrade project. The SE will ensure that the technical requirements and engineering decisions flow down from the science requirements as appropriate. Since this is a project to upgrade certain components of an existing instrument, only those components require validation. As such, this project will define a limited set of Page 13 of 16

14 requirements documents including the Science Requirements (SRD) in the context of the CCD detectors, and an Operations Concept Document (OCD) to define the user interface, observing modes and diagnostic tools. In addition to the requirements documents, the SE will be responsible for developing the Acceptance Test Plan (ATP) as well as any interface control documents (ICD) that are required for the mechanical, electrical and software interfaces. 3.1 Requirements Management The PS will lead the effort to define the science requirements. Once that is complete the operations and technical requirements can be defined as they flow down from the science requirements. The PS will lead the effort to define the operations requirements and the SE will lead the development of any technical requirements. For each operations and technical requirement that is defined, it will include statements about why the requirement is justified and how the requirements will be verified. The justification may include direct flow down from science requirements, derived to meet a science requirement, or allocated as a design choice. The verification methods may include demonstration of an actual component, controlled test of an experiment, or analysis through calculations or modeling. The verification statement will be used as the basis for developing the acceptance tests. 3.2 Risk Management There is a significant schedule risk since this is a fast-track project occurring simultaneously with other priority projects for KPNO. There is a fixed pool of resources that are distributed among project and operations responsibilities, and thus there is a limited group available for this project, especially in the area of detector technicians. As such, the availability of resources may be out of the project s control and could impact the schedule. The fast-track plan of this project is designed to avert some of the risk by utilizing key resources before they are needed for other scheduled projects. There is moderate Base (labor) funding budget risk since this project plan has minimized the scope of work as much as possible to match the budget allocation. Since the labor resources will be provided by the KPNO and NSTC groups it should be possible to supplement the Base budget by reassigning resources within those groups. There is a moderate technical risk with the Torrent controllers since Torrent is currently a development project and is not yet at a point where the performance can be demonstrated. The design of Torrent reuses much of the MONSOON Orange technology to mitigate the technical risk, but it also incorporates some new technologies. A contingency plan to mitigate this risk will be to use the existing MONSOON Orange controllers instead of Torrents. This contingency plan will require a modest additional effort to develop an electrical interface for the Orange controllers, and a mechanical package. This decision will not have any impact on the Dewar design and thus does not have to be considered until the Mosaic Final Design Review in late March Error Budget Management Error budget analyses will not be needed for this project since the components being upgraded will meet or exceed the performance of the components they are replacing. Page 14 of 16

15 3.4 Observatory Interfaces Instrument Interface The mechanical mounting of the Mosaic-1 imager and its ancillary equipment will not be changed as a result of the upgrade and thus a telescope interface control document (ICD) is not required. However, there will be changes to the CCD controllers that are mounted to the Dewar and so the SE will ensure that the new MONSOON controllers are mounted in such a way that they do not interfere mechanically or block access to any other equipment on or around the instrument. In addition, the SE will ensure the mounting of the controllers is optimal for servicing. For electrical interfaces the new controllers will only require 115V AC power and two data fibers. These services are already available at the instrument on the telescope and thus no changes are required. If the MONSOON Orange controller is used, there will have to be provisions for mounting the power supply near the instrument. The SE will work with KPNO personnel to determine the optimal location for mounting the power supply. Interface requirements for shutter and focal plane temperature control will have to be defined by the SE. Currently these functions are controlled within the CCD controllers that are being replaced. The Torrent controllers will have the capability of providing the shutter and temperature control but the Orange controllers do not. In either case, the requirements will have to be defined so that a new control interface can be designed and implemented. The software interface requirements will be described as part of the Operations Concept Document (OCD). The OCD will describe the interfaces required for the user GUI, the data handling system and the data pipeline Detector Interface A detector engineer will provide a detector interface document that is customized for the e2v CCD44-82 detectors that have been chosen. The document will describe controller configuration requirements, such as bias and clock voltage levels, clock timing, power sequencing, etc. The document will also detail the signal interconnection scheme from the CCD device, through the vacuum barrier, to the MONSOON controller Facility Interface The Mosaic-1 upgrade will have minimal impact on the telescope facility and is not expected to require any modifications or additions to the existing facility interfaces. 4 Design Reviews Since the Mosaic-1 upgrade project is a relatively minor project in terms of budget and scope, the review process will be limited to two reviews during the project. There will be a project plan review before the detailed design phase, and then a final design review before the fabrication phase. 4.1 Project Plan Review The project plan review will be held after the planning phase is complete and the project has been defined. The review will include the science requirements, operations concept and project plan including Page 15 of 16

16 the schedule, budget, risk assessment and contingency measures. The review will also cover the preliminary designs for the Dewar, detector and software systems. 4.2 Final Design Review The final design review will be held once the detailed mechanical design is complete. This review will be an internal review and is intended to identify any technical issues or concerns with the design before the major fabrication phase begins. Components of the project that are considered low technical risk may be fabricated before the final design review if there are cost/schedule benefits to doing so. 5 Safety The Mosaic-1 Upgrade project will be conducted in a way the meets the safety policies of KPNO and NOAO. The Mosaic-1 project will include handling heavy equipment, handling liquid cryogens, running machines, and working in observatory domes with overhead cranes. The personnel that will be required to conduct the work are all trained for proper safety practices. Working with liquid nitrogen will only be done in areas that are designated for such work (i.e., they have adequate ventilation or an oxygen warning sensor). Page 16 of 16

KOSMOS Work Breakdown Structure Summary

KOSMOS Work Breakdown Structure Summary KOSMOS Work Breakdown Structure Summary Version 1.11 July 14, 2010 Version Date Changes 1.8 November 19, 2009 Final version prior to issuing contract 1.9 December 8, 2009 Added documentation control to

More information

KOSMOS Work Breakdown Structure Summary

KOSMOS Work Breakdown Structure Summary KOSMOS Work Breakdown Structure Summary Version 1.9 December 8, 2009 Version Date Changes 1.8 November 19, 2009 Final version prior to issuing contract 1.9 December 8, 2009 Added documentation control

More information

Triple Spec 4: List of Deliverables. Mark Trueblood February 10, 2012

Triple Spec 4: List of Deliverables. Mark Trueblood February 10, 2012 Triple Spec 4: List of Deliverables Mark Trueblood February 10, 2012 1. Purpose The purpose of this document is to list and briefly describe all of the items to be delivered by any of the partner institutions

More information

ARRA Infrastructure Improvements at the National Optical Astronomy Observatory

ARRA Infrastructure Improvements at the National Optical Astronomy Observatory ARRA Infrastructure Improvements at the National Optical Astronomy Observatory Annual Project Report for August 2009 July 2010 Prepared for: National Science Foundation Scientific Program Order No. 16

More information

Industrialization process

Industrialization process Industrialization process Power couplers for XFEL project as an example ------------ Serge Prat TESLA meeting - 30 March 2005 1/41 Industrialization: Why? Start: Prototypes Quality: - uneven ( 30 Couplers)

More information

Instrument Control System Project Management

Instrument Control System Project Management Project Documentation Document PMCS-0021 Revision A Instrument Control System Project Management Bret Goodrich Software September 2015 Advanced Technology Solar Telescope 950 N. Cherry Avenue Tucson, AZ

More information

IMAKA Design Phases and Deliverables

IMAKA Design Phases and Deliverables IMAKA Design Phases and Deliverables History: 2010-09- 13: MC initial pass mostly PDR requirements 2010-09- 14: MC adding in CoDR and CDR requirements 2010-09- 15: MC editing, adding basic ICDs 2010-09-

More information

Observatory Control System Project Management

Observatory Control System Project Management Project Documentation Document PMCS-0020 Revision A Observatory Control System Project Management Bret Goodrich Software September 1, 2015 Advanced Technology Solar Telescope 950 N. Cherry Avenue Tucson,

More information

Change Control and Configuration Management Plan

Change Control and Configuration Management Plan LSST Change Control and Configuration Management Plan LPM-19 6/19/2011 Large Synoptic Survey Telescope (LSST) Change Control and Configuration Management Plan Chuck F. Claver, Victor Krabbendam and Donald

More information

Significant Risk Areas

Significant Risk Areas Keck MOSFIRE Detailed Design Review Report May 3, 2007 B. Bigelow D. DePoy T. Greene (editor) R. Joyce K. McCann A. Phillips Introduction and Context The MOSFIRE instrument Detailed Design Review (DDR)

More information

Management, Cost & Schedule, Controls, ES&H, manpower

Management, Cost & Schedule, Controls, ES&H, manpower Pre-CD1 Review Management, Cost & Schedule, Controls, ES&H, manpower F.Videbaek Brookhaven National Laboratory 1/26 Overview Organization Sub-system responsibilities Communication and Reporting DOE/BNL

More information

INSTITUTO DE ASTROFISICA DE CANARIAS La Laguna (Tenerife) - ESPAÑA - Phone (922) Fax (922)605210

INSTITUTO DE ASTROFISICA DE CANARIAS La Laguna (Tenerife) - ESPAÑA - Phone (922) Fax (922)605210 IAC TECHNOLOGY DIVISION DG/MD-EMI/850v.1 DGMDEMI_850v1.doc July 28, 2006 PROJECT / DESTINATION: EMIR TITLE: STATEMENT OF WORK FOR THE CONFIGURABLE SLIT UNIT CONTRACT INSTITUTO DE ASTROFISICA DE CANARIAS

More information

Safety Review. April 10-11, 2014

Safety Review. April 10-11, 2014 Safety Review April 10-11, 2014 Safety Review Executive Summary Background Victor Krabbendam, the Large Synoptic Survey Telescope (LSST) Project Manager, directed that a second project Safety Review be

More information

Custom Motion. Custom Design for High Performance Complex Machines

Custom Motion. Custom Design for High Performance Complex Machines Custom Motion Custom Design for High Performance Complex Machines Custom Motion Custom motion can provide the best Motion is used in a wide variety of solution for matching features and commercial, industrial

More information

Modicon Advance Program Your migration to the future

Modicon Advance Program Your migration to the future Modicon Advance Program Your migration to the future Improve process integrity. Maximize system expandability. Increase automation platform return on investment. Advance your legacy products to state-of-the-art

More information

GLAST Large Area Telescope:

GLAST Large Area Telescope: Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Calorimeter (CAL) Subsystem WBS: 4.1.5 W. Neil Johnson Naval Research Lab, Washington DC Calorimeter Subsystem Manager neil.johnson@nrl.navy.mil

More information

Community Needs for the Dark Energy Camera & Data Management System

Community Needs for the Dark Energy Camera & Data Management System Community Needs for the Dark Energy Camera & Data Management System Authors: R.C. Smith, A.R. Walker, T.M.C. Abbott Feedback on this document should be directed to: Alistair Walker, awalker @ctio.noao.edu

More information

BASELINE CHANGE PROPOSAL (BCP)

BASELINE CHANGE PROPOSAL (BCP) BASELINE CHANGE PROPOSAL (BCP) 1) BCP Number: LAT 002 2) BCP Title: Project Rebaseline 3) Budget Number: MIE # KA050102-EQU01CC 4) Title: Large Area Telescope (LAT) 5) Date Received (Field Office): Date

More information

Canada. Pulp and Paper Industry PI Specifics. How can process integration help me?

Canada. Pulp and Paper Industry PI Specifics. How can process integration help me? How can process integration help me? Process integration (PI) is a very efficient approach to improving the energy efficiency of large and complex industrial facilities. PI refers to the application of

More information

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services ATTACHMENT A SAMPLE SCOPE OF SERVICES PLC & HMI PROGRAMMING City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services December, 2017

More information

GLAST Large Area Telescope:

GLAST Large Area Telescope: Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: Performance & Safety Assurance Darren Marsh SLAC Performance & Safety Assurance Manager Marsh@SLAC.Stanford.Edu 650-926-4577 Outline Tracker

More information

Monthly Mission Review. LAT Shipping and Environmental Test Planning. March 30, Neil Johnson Naval Research Lab

Monthly Mission Review. LAT Shipping and Environmental Test Planning. March 30, Neil Johnson Naval Research Lab Monthly Gamma-ray Large Area Space Telescope LAT Shipping and Environmental Test Planning March 30, 2006 Neil Johnson Naval Research Lab neil.johnson@nrl.navy.mil W N Johnson, NRL 1 Updates to LAT Transportation

More information

MODEL TEM Mill. Two independently adjustable TrueFocus ion sources

MODEL TEM Mill. Two independently adjustable TrueFocus ion sources MODEL 1050 TEM Mill A state-of-the-art ion milling and polishing system. It is compact, precise, and consistently produces high-quality transmission electron microscopy (TEM) specimens with large electron

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Course 50413B: Mastering Microsoft Project 2010 Page 1 of 10 Mastering Microsoft Project 2010 Course 50413B: 2 days; Instructor-Led About this Course This two-day instructor-led course provides students

More information

Rockwell Automation Drive Systems. Solutions for the Mining Industry

Rockwell Automation Drive Systems. Solutions for the Mining Industry Rockwell Automation Drive Systems Solutions for the Mining Industry Rockwell Automation: Experience You Can Trust Before new equipment is installed, we can assist you in planning for a fast start-up. Boosting

More information

"Change is inevitable; except in vending machines."

Change is inevitable; except in vending machines. Configuration Management Change is inevitable. In acquisition programs, missions, requirements, technologies, and environments change. In response, the system design will change as it evolves through the

More information

GEMINI 8-M Telescopes Project

GEMINI 8-M Telescopes Project GEMINI 8-M Telescopes Project Functional Specification for the Gemini Coating Plants R. Kneale Telescope and Enclosure Group May 23, 1994 GEMINI PROJECT OFFICE 950 N. Cherry Ave. Tucson, Arizona 85719

More information

1 - Introduction to Microsoft Project Describe how Project relates to the discipline of Project management.

1 - Introduction to Microsoft Project Describe how Project relates to the discipline of Project management. 55205 Mastering Microsoft Project 2016 The course begins with the basic concepts and leads students through all the functions they ll need to plan and manage a small to medium-size project, including how

More information

MODEL NanoMill TEM Specimen Preparation System. Ultra-low-energy, inert-gas ion source. Concentrated ion beam with scanning capabilities

MODEL NanoMill TEM Specimen Preparation System. Ultra-low-energy, inert-gas ion source. Concentrated ion beam with scanning capabilities MODEL 1040 NanoMill TEM Specimen Preparation System The NanoMill system uses an ultra-low energy, concentrated ion beam to produce the highest quality specimens for transmission electron microscopy. Ultra-low-energy,

More information

Mechanical Fabrication Department s Support of B-Factory Operations

Mechanical Fabrication Department s Support of B-Factory Operations Mechanical Fabrication Department s Support of B-Factory Operations Presentation by Karen Fant 4/26/06 1 MFD featured because: Department provides a broad range of services Accelerator Systems Division

More information

sinumerik SINUMERIK Manufacturing Excellence Services to increase the productivity of your machine tools

sinumerik SINUMERIK Manufacturing Excellence Services to increase the productivity of your machine tools SINUMERIK Manufacturing Excellence Services to increase the productivity of your machine tools sinumerik www.siemens.com/sinumerik/manufacturing-excellence The service portfolio for your machines and processes

More information

Design Integration and Analysis

Design Integration and Analysis LA LA Monthly Monthly Status Status Review Review 26 26 July July 2005 2005 Design Integration and Analysis Martin Martin Nordby Nordby John John Ku Ku Jack Jack Goodman Goodman LA Design Integration and

More information

Statement of Work for Repair of a Miniature Liquid Helium-3 Refrigerator

Statement of Work for Repair of a Miniature Liquid Helium-3 Refrigerator Statement of Work for Repair of a Miniature Liquid Document: G0107-0302-A-SOW Version A April 26, 2005 Table of Contents 1 General Description:... 3 2 Applicable Documents:... 3 3 Device Performance:...

More information

Southern African Large Telescope SALTICAM Preliminary Design Review. Document Number 3300AE0007: Management Structure

Southern African Large Telescope SALTICAM Preliminary Design Review. Document Number 3300AE0007: Management Structure 3300AE0007: Management 1 Southern African Large Telescope SALTICAM Preliminary Design Review Document Number 3300AE0007: Management Structure Geoff Evans Dave Carter Willie Koorts James O Connor Darragh

More information

DETERMINING THE RIGHT TIME TO UPGRADE

DETERMINING THE RIGHT TIME TO UPGRADE DETERMINING THE RIGHT TIME TO UPGRADE BY Daniel Reckrey, PE Newer distributed control systems (DCS) have features to optimize safety, performance, controllability and reliability. Upgrading to use these

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:

More information

Project Management Step by Step Guide

Project Management Step by Step Guide Project Management Step by Step Guide BNH Expert Software ADVISOR Enterprise User's Guide Copyright 995 to 208 BNH Expert Software Inc. Latest Update: February 2, 208 All rights reserved. No part of this

More information

MODEL 1061 SEM Mill ION MILLING. Ion milling is used in the physical. sciences to enhance the sample s surface. characteristics. Inert gas, typically

MODEL 1061 SEM Mill ION MILLING. Ion milling is used in the physical. sciences to enhance the sample s surface. characteristics. Inert gas, typically MODEL 1061 SEM Mill A state-of-the-art ion milling and polishing system. It is compact, precise, and consistently produces high-quality scanning electron microscopy (SEM) samples in the shortest amount

More information

Building the Project Plan Managing the Project Plan Results and Progress. Project Management. Mike McKerns, Caltech

Building the Project Plan Managing the Project Plan Results and Progress. Project Management. Mike McKerns, Caltech Building the Project Plan Managing the Project Plan Results and Progress Project Management Mike McKerns, Caltech Goals & Objectives The goal of DANSE is to build a software system for neutron scattering

More information

WAUSeON MACHINe. AND MANUf ACTURING. Robotic Automation. 995 Enterprise Avenue Wauseon, Ohio USA

WAUSeON MACHINe. AND MANUf ACTURING. Robotic Automation. 995 Enterprise Avenue Wauseon, Ohio USA WAUSeON MACHINe AND MANUf ACTURING 995 Enterprise Avenue Wauseon, Ohio USA 419.337.0940 www.wauseonmachine.com Robotic Automation was founded in 1983 as a small contract machine shop. By 1988, our business

More information

STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING DEVELOPMENT & INTEGRATION (SSPEDI) Space Solutions (SpS)

STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING DEVELOPMENT & INTEGRATION (SSPEDI) Space Solutions (SpS) SSPEDI SpS J.1(a), Attachment 1 80ARC018R0007 National Aeronautics and Space Administration Ames Research Center Moffett Field, CA 94035-0001 STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING

More information

Information Day on F4E-OFC-0905 Provision of Manufacturing Engineering Support for the Diagnostics Systems Technical Scope

Information Day on F4E-OFC-0905 Provision of Manufacturing Engineering Support for the Diagnostics Systems Technical Scope Information Day on F4E-OFC-0905 Provision of Manufacturing Engineering Support for the Diagnostics Systems Technical Scope Sandra Julià Technical Project Officer April 18th 2018 Introduction ITER Diagnostics

More information

GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule Review 12/15/03

GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule Review 12/15/03 Gamma-ray Large Area Space Telescope GLAST Large Area Telescope: I & T Input to Monthly Technical/Cost/Schedule Review 12/15/03 Elliott Bloom SU-SLAC Subsystem Manager Brian Grist SU-SLAC Subsystem Engineer

More information

Model TEM Mill. Tabletop precision preparation for producing high-quality TEM specimens from a wide variety of materials EXCELLENCE MAGNIFIED

Model TEM Mill. Tabletop precision preparation for producing high-quality TEM specimens from a wide variety of materials EXCELLENCE MAGNIFIED Model 1050 TEM Mill Tabletop precision preparation for producing high-quality TEM specimens from a wide variety of materials EXCELLENCE MAGNIFIED Modular design for basic instrument operation or fully

More information

- 1 - InfraStruXure InRow SC Assembly and Start-Up. Installation Service

- 1 - InfraStruXure InRow SC Assembly and Start-Up. Installation Service Installation Service - 1 - InfraStruXure InRow SC Assembly and Start-Up Statement of Work 1.0 Executive Summary InfraStruXure InRow SC Assembly & Start-Up Service Table of Contents 1.0 Executive Summary

More information

Supplier Quality Survey. 1. Type of Business: g) Commodities supplied? Supplier Changes/comments: 2. Headcount breakdown by group: Purchasing

Supplier Quality Survey. 1. Type of Business: g) Commodities supplied? Supplier Changes/comments: 2. Headcount breakdown by group: Purchasing Supplier: Phone: Prime Contact/Title: Sales Contact/Title: Address: Fax: e-mail address e-mail address Quality Contact/Title: e-mail address 1. Type of Business: a) Number of years in business? b) Company

More information

Special Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control

Special Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control Special Specification 6292 Radar Vehicle Detection System for Signalized Intersection Control 1. DESCRIPTION 2. MATERIALS Furnish, install, relocate, or remove radar vehicle detection systems (RVDS) of

More information

FUNDAMENTALS OF ENGINEERING DESIGN

FUNDAMENTALS OF ENGINEERING DESIGN FUNDAMENTALS OF ENGINEERING DESIGN 1 Best way to learn design is to design 2 Types of designs Original design: Employs an innovative concept. A truly original design involves invention, eg. design of microprocessor.

More information

Aerocom s AC660 System

Aerocom s AC660 System Aerocom s AC660 System The Aerocom AC660 System is one of our most versatile applications available. From basic reports to complex system network integration, the AC660 will get the job done. This fully

More information

Summary of TL 9000 R4.0 Requirements Beyond ISO 9001:2000

Summary of TL 9000 R4.0 Requirements Beyond ISO 9001:2000 This summary identifies the additional TL 9000 Release 4.0 requirements beyond those stated in ISO 9001:2000. See the TL 9000 R4.0 Handbook for the actual TL 9000 R4.0 requirements. ISO 9001:2000 section

More information

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2 Passit4Sure.OG0-093.221Questions Number: OG0-093 Passing Score: 800 Time Limit: 120 min File Version: 7.1 TOGAF 9 Combined Part 1 and Part 2 One of the great thing about pass4sure is that is saves our

More information

Quality Assurance Plan For VOILA. Dwg. No

Quality Assurance Plan For VOILA. Dwg. No Rev. ECO Description Checked Approval Date 01 85-002 Initial Release for Internal Comment M. Smith RFGoeke 1/8/01 02 85-055 External pre-release for comment B.Klatt RFoster 10/6/03 A 85-056 First Alpha

More information

Integrated Program Management. Gordon M. Kranz President, Enlightened Integrated Program Management, LLC July 28, 2016

Integrated Program Management. Gordon M. Kranz President, Enlightened Integrated Program Management, LLC July 28, 2016 Integrated Program Management Gordon M. Kranz President, Enlightened Integrated Program Management, LLC July 28, 2016 Learning Objectives Understand one Definition of Integrated Program Management Discuss

More information

WHITE PAPER. Integrated Design and Production Planning for Ship Block Assembly and Construction

WHITE PAPER. Integrated Design and Production Planning for Ship Block Assembly and Construction WHITE PAPER Integrated Design and Production Planning for Ship Block Assembly and Construction Contents 1. Summary... 1 1.1. Nomenclature... 2 2. Introduction... 3 3. Key Considerations in Ship-block Production

More information

Work Plan and IV&V Methodology

Work Plan and IV&V Methodology Work Plan and IV&V Methodology Technology initiatives and programs should engage with an IV&V process at the project planning phase in order to receive an unbiased, impartial view into the project planning,

More information

Electronic document management offers many advantages

Electronic document management offers many advantages Electronic document management offers many advantages Improves engineering productivity Fast Forward: Database-centric electrical computer-aided engineering (E-CAE) enhances productivity. In using E-CAE

More information

MODEL SEM Mill. Two independently adjustable TrueFocus ion sources

MODEL SEM Mill. Two independently adjustable TrueFocus ion sources MODEL 1060 SEM Mill A state-of-the-art ion milling and polishing system. It is compact, precise, and consistently produces high-quality scanning electron microscopy (SEM) samples for a wide variety of

More information

IceCube Project Monthly Report February 2007

IceCube Project Monthly Report February 2007 IceCube Project Monthly Report February 2007 Accomplishments A total of 1424 IceCube DOMs are installed on the 22 strings and 52 IceTop tanks. Basic commissioning tests indicate that essentially all of

More information

THE STANDARD FOR PROGRAM MANAGEMENT

THE STANDARD FOR PROGRAM MANAGEMENT THE STANDARD FOR PROGRAM MANAGEMENT COURSE STRUCTURE INTRODUCTION Module 1 PROGRAM MANAGEMENT PERFORMANCE DOMAINS Module 2 PROGRAM STRATEGY ALIGNMENT Module 3 PROGRAM BENEFITS MANAGEMENT Module 4 COURSE

More information

Project Execution Plan For

Project Execution Plan For Project Execution Plan For [Insert Name Here] Project Document Revision History Revision Date Project Manager Project Sponsor Page 1 of 24 About This Project Execution Plan Template: This template is intended

More information

Commissioning Guide. Transportation and Works Building Design and Construction Division

Commissioning Guide. Transportation and Works Building Design and Construction Division Commissioning Guide Transportation and Works December 13, 2013 TABLE OF CONTENTS 1. COMMISSIONING 12 STEP PROCESS... 1 2. PURPOSE OF THE GUIDE... 2 3. INTENT OF COMMISSIONING... 2 4. DEFINITION OF COMMISSIONING...

More information

Large Synoptic Survey Telescope. Final Design Review. December 2-6, Panel Report

Large Synoptic Survey Telescope. Final Design Review. December 2-6, Panel Report Large Synoptic Survey Telescope Final Design Review December 2-6, 2013 Panel Report December 30, 2013 With LSST Project Response January 14, 2014 Document-15442 Version 2 Recommendations are in blue italics.

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

Project Management Integration

Project Management Integration Project Management Integration Integration Management the processes required in ensuring that the various elements of a project are properly coordinated balancing, making trade-offs plan, execute and control

More information

Procurement of Project Management Training Services-

Procurement of Project Management Training Services- Statement of Work Table of Contents 2. Purpose and Scope... 3 3. Background Information... 3 4. Objectives... 3 5. Statement of Work... 3 6. Requirement Specifications for Services... 4 7. Requirement

More information

Mechatronics Courses by School Period

Mechatronics Courses by School Period Mechatronics Courses by School Period Year One P1 P1 P2 P3 P3 P3 P4 P4 P4 Integrated Systems Industrial Math (Geometry, Trig, Algebra,) Blueprint Reading Machine Tool I (Hand tools-measuring-saws & Drill

More information

ILC ASIAN DRAFT SCHEDULE

ILC ASIAN DRAFT SCHEDULE ILC ASIAN DRAFT SCHEDULE K Foraz, M Gastal & J Osborne Many thanks to all contributors Objectives and scope To provide a target baseline construction schedule for the 2 Asian sample sites Address remarks

More information

Installing Solar Water and Pool Heating Systems Objectives and Task Analysis for Solar Water and Pool Heating Systems Installation Contractor

Installing Solar Water and Pool Heating Systems Objectives and Task Analysis for Solar Water and Pool Heating Systems Installation Contractor North American Board of Certified Energy Practitioners Technical Committee Document Approved April 11, 2005 Installing Solar Water and Pool Heating Systems Objectives and Task Analysis for Solar Water

More information

A System for LSST Follow UP

A System for LSST Follow UP A System for LSST Follow UP Robert Blum, NOAO AAS 231, 2018 January, National Harbor 1 LSST Follow Up System The Team Andy Adamson (Gemini) John Blakeslee (Gemini) Bob Blum (NOAO) Adam Bolton (NOAO) Todd

More information

Ninth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book:

Ninth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book: Rita s Course in a Book for Passing the Project Management Professional (PMP) Exam Rita Mulcahy s Ninth Edition Inside this book: Tricks of the Trade What you really need to know to pass the exam Straightforward

More information

C A P A B I L I T I E S S U M M A R Y Assured Performance

C A P A B I L I T I E S S U M M A R Y Assured Performance C A P A B I L I T I E S S U M M A R Y Assured Performance CAPABILITIES SUMMARY Lexatys, LLC 10253 Stone Creek Drive #1 Laurel, DE 19956-4700 P: 302.715.5029 Ext. 1001 F: 302.309.9173 Email: sales@lexatys.com

More information

SECTION COMMUNICATIONS SYSTEMS QUALITY ASSURANCE & TESTING

SECTION COMMUNICATIONS SYSTEMS QUALITY ASSURANCE & TESTING SECTION 16707 COMMUNICATIONS SYSTEMS QUALITY ASSURANCE & TESTING PART 1 - GENERAL 1.01 SECTION INCLUDES A. These quality control (QC) system requirements define characteristics, in addition to those in

More information

The Maintenance Pro s Guide to Controller Replacement: Plan Your Strategy

The Maintenance Pro s Guide to Controller Replacement: Plan Your Strategy Digital Factory The Maintenance Pro s Guide to Controller Replacement: Plan Your Strategy usa.siemens.com/modernize The Maintenance Pro s Guide to Controller Replacement: Plan Your Strategy Digital Factory

More information

CAPS TM V5. Software Suite. Get the Most Out of Your Anneal Shop. RAD-CON, Inc Athens Ave.

CAPS TM V5. Software Suite. Get the Most Out of Your Anneal Shop.   RAD-CON, Inc Athens Ave. CAPS TM V5 RAD-CON, Inc. 13001 Athens Ave. Suite 300 Lakewood, OH 44107 Phone: +1 440-871-5720 Fax: +1 216-221-1135 E-mail: sales@rad-con.com Web: www.rad-con.com Optimized by: Software Suite Get the Most

More information

Lens barrel optomechanical design principles

Lens barrel optomechanical design principles Lens barrel optomechanical design principles M. Bayar Lens barrel optomechanical design principles Optical Engineering 20(2)[1981] Synopsis by: Jennifer Harwell November 1, 2010 University of Arizona,

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

8.0 PRE-ENVIRONMENTAL REVIEW (PER)

8.0 PRE-ENVIRONMENTAL REVIEW (PER) GSFC-STD-1001 Page 36 of 52 8.0 PRE-ENVIRONMENTAL REVIEW (PER) At the PER, the project discloses to the Integrated Independent Review Team (IIRT) the complete and comprehensive project status in order

More information

Electrochemical Die-Sinking (ECM) in Practice

Electrochemical Die-Sinking (ECM) in Practice Electrochemical Die-Sinking () in Practice Copyright by Maschinenfabrik Köppern GmbH & Co.KG. Distribution, forwarding or duplication of this document, whether in part or in full, is only allowed with

More information

MODEL 1051 TEM Mill ION MILLING. Ion milling is used on physical science. specimens to reduce thickness to electron

MODEL 1051 TEM Mill ION MILLING. Ion milling is used on physical science. specimens to reduce thickness to electron MODEL 1051 TEM Mill A state-of-the-art ion milling and polishing system offering reliable, high performance specimen preparation. It is compact, precise, and consistently produces high-quality transmission

More information

INDUSTRY EXPERTISE IN AUTOMATION AND ELECTRONICS AUTOMATION

INDUSTRY EXPERTISE IN AUTOMATION AND ELECTRONICS AUTOMATION INDUSTRY EXPERTISE IN AUTOMATION AND ELECTRONICS AUTOMATION HEITEC is an innovative maker of automation solutions and electronics for a wide range of industries. We offer solutions, products, and services

More information

Logistics Community of Interest 1152 Production Control Series Competency-Based Learning Map and Training Strategy. Page 1

Logistics Community of Interest 1152 Production Control Series Competency-Based Learning Map and Training Strategy. Page 1 Page 1 Production Control Competency-Based Learning Map Overview The United States Marine Corps (USMC) Logistics Community of Interest (COI) developed this competency-based learning map to support 1152

More information

NSF s National Center for Optical-Infrared Astronomy (NCOA) Science Possibilities and Planning Updates

NSF s National Center for Optical-Infrared Astronomy (NCOA) Science Possibilities and Planning Updates NSF s National Center for Optical-Infrared Astronomy (NCOA) Science Possibilities and Planning Updates 1 NCOA Context and Background Emerging science connections across NOAO, Gemini, and LSST Status of

More information

Case Study XMM Newton Satellite RGA Structure By The Peregrine Falcon Corporation

Case Study XMM Newton Satellite RGA Structure By The Peregrine Falcon Corporation 1051 Serpentine Lane, Ste. 100, Pleasanton, CA 94566-8451 phone 925/461-6800, x102 fax 925/461-6804 www.peregrinecorp.com email: rhardesty@pereginecorp.com Case Study XMM Newton Satellite RGA Structure

More information

Centerwide System Level Procedure

Centerwide System Level Procedure 5.ARC.0004.1 1 of 17 REVISION HISTORY REV Description of Change Author Effective Date 0 Initial Release D. Tweten 7/17/98 1 Clarifications based on 7/98 DNV Audit and 6/98 Internal Audit (see DCR 98-028).

More information

WESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY

WESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY WESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY A. Introduction A.1. Title: Generating Unit Model Validation Policy A.2. Purpose: Accurate models of generators and associated

More information

TECHNOLOGY SUPPORT SPECIALIST (12264)( )

TECHNOLOGY SUPPORT SPECIALIST (12264)( ) GENERAL DESCRIPTION OF WORK This is advanced work in providing consultation, support and/or training for technology-based systems. Employees may provide support of hardware, applications, operating systems,

More information

BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM

BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM BOARD OF SUPERVISORS FINANCE/GOVERNMENT OPERATIONS AND ECONOMIC DEVELOPMENT COMMITTEE ACTION ITEM Date of Meeting: # 3 SUBJECT: ELECTION DISTRICT: Monthly Report/Implementation of the Enterprise Resource

More information

Alternatives to Optimize Gas Processing Operations

Alternatives to Optimize Gas Processing Operations Mark E. Roop esimulation, Inc. Houston, Texas, U.S.A. Jean Leger Enogex, Inc. Oklahoma City, Oklahoma, U.S.A. Steve Hendon esimulation, Inc. Houston, Texas, U.S.A. CHALLENGES AND REQUIREMENTS Gas processing

More information

INTEGRATED TEST PLATFORMS: TAKING ADVANTAGE OF ADVANCES IN COMPUTER HARDWARE AND SOFTWARE

INTEGRATED TEST PLATFORMS: TAKING ADVANTAGE OF ADVANCES IN COMPUTER HARDWARE AND SOFTWARE 2005-01-1044 INTEGRATED TEST PLATFORMS: TAKING ADVANTAGE OF ADVANCES IN COMPUTER HARDWARE AND SOFTWARE By Mark D. Robison Uson, L.P. ABSTRACT Ongoing hardware, software and networking advances in low-cost,

More information

Maintenance Service. 1.0 Executive Summary 1.1 ANNUAL PREVENTIVE MAINTENANCE VISIT 1.2 ON-SITE REMEDIAL SERVICES

Maintenance Service. 1.0 Executive Summary 1.1 ANNUAL PREVENTIVE MAINTENANCE VISIT 1.2 ON-SITE REMEDIAL SERVICES Maintenance Service Statement of Work Advantage Plus Plan for UPS & PDU with RMS Advantage - 1 - Plus Plan for UPS & PDU with RMS Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0

More information

Global Value 7. Productivity Suite for GammaVision. Optimizing Gamma Spectrometry Processes through Secure Data Management and Measurement Automation.

Global Value 7. Productivity Suite for GammaVision. Optimizing Gamma Spectrometry Processes through Secure Data Management and Measurement Automation. Productivity Suite for GammaVision Optimizing Gamma Spectrometry Processes through Secure Data Management and Measurement Automation. Global Value was designed to transform the standard GammaVision spectroscopy

More information

DUKE UNIVERSITY CONSTRUCTION STANDARDS

DUKE UNIVERSITY CONSTRUCTION STANDARDS 1 23 08 00 Commissioning of HVAC Systems 1. GENERAL A. GENERAL PROVISIONS 1. Drawings and general provisions of the Contract, including General Conditions and Division - 1 Specifications Sections, apply

More information

Report of SEO. SEO = System Engineering Office, chaired by PM (project manager)

Report of SEO. SEO = System Engineering Office, chaired by PM (project manager) 140213_SAITO Report of SEO SEO = System Engineering Office, chaired by PM (project manager) Task of SEO = to manage the project schedule, budget and commissioning sequence, according to the guideline decided

More information

TOPIC DESCRIPTION SUPPLEMENT for the SYSTEMS ENGINEERING SURVEY DESCRIPTION

TOPIC DESCRIPTION SUPPLEMENT for the SYSTEMS ENGINEERING SURVEY DESCRIPTION 1 2 Objectives of Systems Engineering 3 4 5 6 7 8 DoD Policies, Regulations, & Guidance on Systems Engineering Roles of Systems Engineering in an Acquisition Program Who performs on an Acquisition Program

More information

Telescope Project Development Seminar

Telescope Project Development Seminar Telescope Project Development Seminar Session 1b: Systems Engineering Matt Johns 1/20/2017 U. Tokyo 2/9/2017 Telescope Project Development 1 Session 1 Outline Session 1a Introduction 1. Introduction 2.

More information

Command and Control Software Development Lessons Learned. Lt Col Michael D. Sarchet Deputy Director, Space Systems Command and Control Division

Command and Control Software Development Lessons Learned. Lt Col Michael D. Sarchet Deputy Director, Space Systems Command and Control Division Command and Control Software Development Lessons Learned Lt Col Michael D. Sarchet Deputy Director, Space Systems Command and Control Division 1 UNCLASSIFIED Agenda Two real world case studies Lessons

More information

Special Purchase Order Clauses

Special Purchase Order Clauses SC-1 Quality System: The Supplier shall have a quality management system that conforms to: a) SAE AS9100 Quality Management Systems Aerospace Requirements b) SAE AS9110 Quality Management Systems Aerospace

More information

Risk and Opportunity Management - Overview

Risk and Opportunity Management - Overview Risk and Opportunity Management - Overview Webinar Learning Objectives At the end of this Webinar, you will: Understand the 5 step Risk and Opportunity Management (R&OM) process Recognize R&OM as a tool

More information

ORDINANCE NO BE IT ORDAINED BY THE MAYOR AND COUNCIL OF THE CITY OF DAVID CITY, NEBRASKA:

ORDINANCE NO BE IT ORDAINED BY THE MAYOR AND COUNCIL OF THE CITY OF DAVID CITY, NEBRASKA: ORDINANCE NO. 1183 AN ORDINANCE RELATING TO ELECTRIC SERVICE RATES AND MINIMUM CHARGES, TO PROVIDE NEW SCHEDULES OF ELECTRIC RATES, TO REPEAL ALL PARTS OF THE CODE, RESOLUTIONS AND ORDINANCES IN CONFLICT

More information

Swivel and Marine Systems. Swivel stack and fluid transfer systems for multiple applications

Swivel and Marine Systems. Swivel stack and fluid transfer systems for multiple applications Swivel and Marine Systems Swivel stack and fluid transfer systems for multiple applications Swivel Stack Systems The swivel stack is the heart of the turret mooring and fluid transfer system (FTS). Reliability,

More information