Observatory Control System Project Management

Size: px
Start display at page:

Download "Observatory Control System Project Management"

Transcription

1 Project Documentation Document PMCS-0020 Revision A Observatory Control System Project Management Bret Goodrich Software September 1, 2015 Advanced Technology Solar Telescope 950 N. Cherry Avenue Tucson, AZ Phone dkist@nso.edu Fax

2 REVISION SUMMARY: 1. Date: September 14, 2011 Revision: DRAFT1 Changes: Created 2. Date: September, 30, 2011 Revision: DRAFT2 Changes: Updates due to internal review 3. Date: Sep 1, 2015 Revision: Rev A Changes: Updated for Baseline. PMCS-0020, Revision A Page ii

3 Table of Contents 1. INTRODUCTION CONSTRUCTION FABRICATION PURCHASE INTEGRATION, TESTING, AND COMMISSIONING QUALITY CONTROL VERIFICATION Requirements Verification Design Verification As-Built Verification Documentation Verification QUALITY ASSURANCE TASKS Unit Testing Integration Testing User Acceptance (Verification) Testing VERIFICATION TEST PLAN Unit Tests Integration Tests RISK RISK REGISTER RISK MITIGATION OCS-01: New user interface specifications OCS-02: Engineering archive performance... Error! Bookmark not defined OCS-03: Operational mode script performance OCS cannot run at the rates required by some scripts... Error! Bookmark not defined OCS-04: Support for Instrument tab developers developers cannot build their parameter interfaces as required... Error! Bookmark not defined. 5. COST ESTIMATES COST ESTIMATE Construction Labor Integration, Testing, and Commissioning Labor Construction Non-labor Contingency SCHEDULE CONFIGURATION ITEM DATA LIST PMCS-0020, Revision A Page iii

4 1. INTRODUCTION This document discusses the project management of the DKIST Observatory Control System (OCS). It is concerned with construction and development plans, quality control and assurance, risks, costs, and schedule. Each of these areas is covered in sections of this document. PMCS-0020, Revision A Page 1 of 15

5 2. CONSTRUCTION Construction phase planning involves the fabrication, purchase, and integration of the OCS. Planning for each of these areas is described here. 2.1 FABRICATION Fabrication of the OCS will take place at NSO/Tucson. Fabrication involves the development of the OCS software and the integration of the OCS with the DKIST end-to-end test bed. At the completion of fabrication, the OCS will be fully functional and capable of running science programs on the end-to-end test bed. The end-to-end test bed is the major test facility for integration testing of DKIST software. Each component of the test bed will be delivered by the relevant developer as a stand-in for the actual hardware, e.g., the telescope mount assembly vendor will deliver the Mount Control System (MCS) simulator, while the enclosure vendor delivers the Enclosure Control System (ECS). As the various control systems are developed, their simulators also mature, from simple interface simulators that only verify the accuracy of properties sent to it, to fully functional simulators that implement the final software components and only simulate the hardware mechanisms. The OCS will maintain the end-to-end test bed as new systems are added. Regular testing of the test bed occurs with the Quality Assurance System (QAS) nightly regression tests. 2.2 PURCHASE The OCS will purchase five computers for operations, including one desktop and two large monitors for the control room and four rack mount servers to run the OCS experiment database and facility services. The OCS also will purchase the five servers that operate the Common Services Framework environment (event server, databases, and spare). Additionally, NSO Operations will provide one machine at the summit to replicate the NSO experiment database this is the major interface between the OCS and Operations. All systems are commodity items, requiring various configurations of RAM, storage, and processing power that are met by currently available systems. The purchase of the operations systems will be delayed until needed at integration, testing, and commissioning in FY2016. Spares will also be purchased for all major computing components. 2.3 INTEGRATION, TESTING, AND COMMISSIONING OCS site integration begins during the second quarter of At this time, the Telescope Control System (TCS) should be installed. The first operations of the OCS will use the Instrument Control System simulators to test and commission the OCS. Later integration testing will be performed as each instrument system and telescope system is added to the observatory. Final user testing will likely not occur until shortly before handover to operations. The DKIST site computer room contains 16 racks, each 48U in height. The racks are fully cooled through the site HVAC system and hot/cold aisles. Each rack is connected to the observatory uninterruptible power supply (UPS) and facility network switch (10 Gbit backbone). The OCS and CSF will use two of these racks. The DKIST control room will contain three multi-headed computers workstations for operations. These are reserved for the Observer, Instrument Scientist, and Investigator as required by their roles in operations, per the Operational Concepts Definition (SPEC-0036). PMCS-0020, Revision A Page 2 of 15

6 The OCS plays a crucial role in the commissioning of the telescope. It is from this system that test scripts can be run to validate both operations and science requirements. Many test plans for other systems, especially instruments, expect to use the OCS for assembly and integration tests. PMCS-0020, Revision A Page 3 of 15

7 3. QUALITY CONTROL Quality assurance and quality control are essential elements in the DKIST construction plan. Many aspects of the QA/QC plan are based upon past history of telescope development, along with modern systems engineering process control. The following definitions apply to the DKIST QA/QC. Quality control, also known as verification, is a process used to evaluate whether or not a product, service, or system complies with regulations, specs, or conditions imposed at the start of development phase. Another way to think of this process is Are you building it right? Quality assurance, also known as validation, is a process used to establish evidence that provides a high level of confidence that the product, service, or system accomplishes its intended requirements. Another way to think of this process is Are you building the right thing? Change Control Board (CCB) is the name of the DKIST group that meets regularly to approve or reject requested changes in the DKIST specifications and interfaces. Specification and Interface Control Documents define the specifications for each Work Breakdown Structure element and the public interfaces between each element. Both sets of documents are held under change control and changes must be approved by the CCB. Design Document is the living document that defines the baseline design of the WBS element. This document is updated through the conceptual, preliminary, and final design phases to reflect the current design approach. During construction this document is updated to reflect the changes in scope or interfaces approved by the CCB. At the completion of construction the document should be a completed theory of operation manual for IT&C and operations. 3.1 VERIFICATION The following tasks will be performed as part of the QA process. The work package manager and the DKIST QC/QA personnel will perform auditing of these tasks Requirements Verification All new and changed requirements of the system will be verified to ensure the following: They are directly related to an approved item from the CCB; They are consistent, feasible, and testable; They have been appropriately allocated to the correct mechanical, hardware, software, and operational processes; and Those that are related to safety, security, and criticality have been verified by the rigorous processes governing those areas. The requirements verification process will be conducted by formal review. It will require participation and sign-off by the following team members: Work package primary investigator; Work package manager; and Work package engineer responsible for the change Design Verification All new and changed design elements will be verified to ensure the following: Design is traceable to requirements; PMCS-0020, Revision A Page 4 of 15

8 Design provides details describing how requirements will be met; and Design implements safety, security, and other critical requirements correctly as shown by suitably rigorous methods. The design verification process will be conducted by formal review and requires participation of the following team members: Work package manager; Work package engineer responsible for the change; and At least one engineering representative from a different DKIST work package As-Built Verification All new and changed components will be verified once construction is complete to ensure the following: Applicable standards are being followed; Applicable best practices standards are being followed; DKIST software coding and commenting standards are met; and DKIST software best practices are met per SPEC The as-built verification process will be conducted by an informal review process such as . The review process must be performed and signed off by at least one engineer from a different DKIST work package Documentation Verification In conjunction with new or changed component being released the following documentation must be provided/updated: Detailed design documentation, specifications, ICDs, etc.; Performance benchmarks (for performance critical modules); Test documentation (unit, component, integration, and user acceptance); and Operations document. The documentation verification process will be conducted by informal review, such as . The review process must be performed and signed off by the following team members: DKIST QA/QC representative; and DKIST release manager. 3.2 QUALITY ASSURANCE TASKS The following tasks shall be performed as part of the quality assurance process. The results of these tasks will be documented and reviewed as part of the Document Verification task of the QC process Unit Testing Unit testing involves the testing of individual units of work to ensure they are fit for use. A new or changed component shall be unit tested. This testing shall be performed before proceeding to component level testing. The tasks that must be completed as part of unit testing are as follows: Prepare new and/or changed unit tests and related documentation; Ensure traceability of new and/or changed tests to requirements; PMCS-0020, Revision A Page 5 of 15

9 Execute new, changed, and existing unit tests upon build of component; and Document unit test results. Unit testing will be performed by the work package engineer responsible for the change or his/her designee Integration Testing Integration testing involves testing an intended release to ensure it integrates correctly with all other DKIST systems for which it interfaces. Integration testing shall be performed in a qualified DKIST test environment that uses mechanical, hardware, and software systems equivalent to the production systems. Integration testing shall be performed before proceeding to user acceptance level testing. The tasks that must be completed as part of integration testing are as follows: Prepare new and/or changed integration tests and related documentation; Ensure traceability of new and/or changed tests to requirements; Coordinate integration test schedule with test engineer of interfacing systems; Execute new, changed, and existing integration tests; and Document integration test results. The work package engineer responsible for the change and the designated test engineer for each interfacing DKIST system will perform integration testing. Results shall be reviewed and signed off by the following team members before proceeding to user acceptance testing: Work package manager; Work package manager(s) for all systems that interface with the released component; Work package engineer responsible for release; and Test engineer for all systems that interface with the released component Software Specific Tasks The following tasks are specific to integration testing for software releases. Any software defects (bugs) identified in testing will be logged in JIRA tracking system; All test cases impacted by the defect must be re-tested once the defect is resolved; Any un-resolved software defects must be approved by the review team before proceeding to User Acceptance Testing; and Upon successful completion of integration testing the software source code will be tagged in CVS to indicate it is part of a release. Test documentation will include reference to this release number User Acceptance (Verification) Testing User acceptance testing involves performing tests for which the user will validate the output of the system to determine pass/fail status. User acceptance testing shall be performed in a production environment, or a qualified test environment that is approved by the user. User acceptance testing shall be performed before a release can be made operational for production use. The tasks that must be completed as part of user acceptance testing are as follows: User to prepare new and/or changed integration tests and related documentation; Ensure traceability of new and/or changed tests to requirements; Coordinate user acceptance test schedule with production or test environments and systems; Execute new, changed, and existing user acceptance tests; and PMCS-0020, Revision A Page 6 of 15

10 Document test results. User acceptance testing will be performed by the user, with the support of the work package engineer responsible for the release, and test engineers from other interfacing systems. Before proceeding to production, the release must be approved by the following team members: Work package user (i.e., owner or primary investigator); Work package manager(s) for all systems that interface with the released component; Work package engineer responsible for release; Test engineer for all systems that interface with the released component; and DKIST release manager Software Specific Tasks The following tasks are specific to user acceptance testing for software releases. Only software source code from the CVS tag that matches the release number identified in the integration test documentation may be used for user acceptance testing; Any software defects identified during testing will be logged in JIRA tracking system; All test cases impacted by the defect must be re-tested once the defect is resolved; Any un-resolved software defects must be approved by the review team before proceeding to production release; and Test documentation should include reference to the CVS tag for this release. 3.3 VERIFICATION TEST PLAN Unit Tests Unit tests will be written with the Test Automation Framework (TAF), as described in PROC All unit tests will test against the OCS compliance matrix. The major DHS system tests are described below User Support System tests OCS-supplied widgets Test procedure: The JES standalone application is started using the OcsJesManager for widget access and all OCS-supplied widgets created and executed in JES' programmed mode. User verifies that widgets are behaving as specified. Test result: No errors should be reported and behavior should be as expected User Support System tests standalone user interfaces Test procedure: These tests are performed with the cooperation of the OCS EMS and OCS LMS subsystems. Each of the USS-supplied standalone interfaces is operated in JES' live mode, connecting with the EMS and LMS facilities. User verifies that the standalone interfaces are behaving as specified. Test result: No errors should be reported and behavior should be as expected Experiment Management System experiment execution Test procedure: This test is performed with the cooperation of the DKIST End-to-End test bed running with OCS-supplied principal system simulations. The experiment execution user interface is executed with the end-to-end test bed running. The operation modes created in the test for are executed using the test bed. The user verifies that the correct behavior is exhibited by the end-to-end test bed and the execution status is properly reported by the experiment execution user interface. Test result: No errors or unexpected behavior should be noted. PMCS-0020, Revision A Page 7 of 15

11 Lifecycle Management System Application setup and distribution Test procedure: The LMS application editor standalone user interface is executed and used to describe the layout of containers and components across several systems when deploying the DKIST end-to-end test bed. The application database is inspected to verify that the correct layout has been recorded. Test result: No errors should be reported or found on inspection of the application database Lifecycle Management System Lifecycle control and health monitoring Test procedure: This test is performed with the cooperation of the DKIST End-to-End test bed running with OCS-supplied principal system simulations. The lifecycle control and health monitor user interfaces are run. The lifecycle control user interface is used to take the end-to-end test bed through its lifecycle states. The health monitor is checked to verify that it is correctly reporting system health status Lifecycle Management System Archiving and Logging Test procedure: The CSF-supplied tools for testing the engineering archive and log message database performance are run. The results are checked to verify that the performance specifications are met. The Archive and Log standalone user interfaces are then run to examine and extract information from the archive and database. The user verifies that those tools are functioning correctly Integration Tests Integration tests are performed both with the Tucson end-to-end test bed and at the summit Other Principal Systems Test procedure: This test is performed with the cooperation of the DKIST end-to-end test bed and the other principal systems. Each of the test beds supplied with each principal system are installed into the end-to-end test bed and the test bed is run. The verification tests specified in are then repeated. This test is repeated as each principal system's test bed becomes available. Test result: No errors resulting from incorrect OCS behavior should be produced. PMCS-0020, Revision A Page 8 of 15

12 4. RISK The DKIST Risk Management Plan (SPEC-0037) defines the project approach to risk analysis and mitigation. The project maintains a risk register containing all identified risks at the beginning of the project and throughout the life of the project. The risks are categorized by the likelihood of occurring and the seriousness of impact on the project. Plans for mitigating each high-level risk and the subsequent results of the actions taken are also given. The risk register exists to accomplish the following risk management goals: provide a tool for managing and reducing the risks identified before and during the project; document risk mitigation strategies being pursued in response to the identified risks and their grading in terms of likelihood and seriousness; provide project management with a document from which status can be reported to oversight; ensure the communication of risk management issues to key stakeholders; provide a mechanism for seeking and acting on feedback to encourage the involvement of the key stakeholders; and identify the mitigation actions required for implementation of the risk management plan and associated costs. 4.1 RISK REGISTER Risk Item Probability Non-labor Cost Labor Cost HLSC-007 Expanded scope for NSO data handling integration 25% $340K $576K HLSC-073 Scope refinements, specification documents in transition 80% $216K $173K HLSC-002 Software Communications Infrastructure 5% $0K $72K 4.2 RISK MITIGATION General risk mitigation strategies are applied to all risks in the OCS These strategies include: Early Development: The OCS will finish construction in The IT&C period will be used to address issues arising from later instrument development or unplanned integration needs. End-to-end test bed: The end-to-end test bed will be used to test the interface to the TCS and ICS. As subassembly element test beds are added (e.g., mount, enclosure, VBI) the end-to-end test bed will be able to test full operational support. In addition, DKIST scientists can begin testing experiments and observations using the test bed. Interactions with Operations staff in Boulder. Regular communications has been established with the scientific and engineering staff in Boulder to demonstrate prototypes and receive feedback on the OCS displays and functionality. The following risk mitigation strategies are envisioned for each of the major risks defined in the risk register. PMCS-0020, Revision A Page 9 of 15

13 4.2.1 HLSC-007: Expanded scope for NSO data handling integration Based on HLS PDRs and subsequent discussions, there is some risk that additional implementation details/design changes will be required to integrate into the developing NSO model for both ingestion of scripts (Phase II Proposal preparation) and the export of data products. The OCS-to-Operations interface has not been finalized. At this time the OCS is assuming its own model for the format of the experiments, based upon the Data Model (SPEC-0122), which also has not been finalized. Mitigation: Early interaction with the operations group. The HLS developers have met with Operations during preliminary development to ascertain the currently known scope of the DHS to Operations interface. Current operations development plans in this area are still uncertain, but the HLS group will continue to work towards finalizing the interface. Mitigation: Get the DRD and Data Models approved and align the OCS design with the results HLSC-073: Scope refinements, specification documents in transition There may be additional work or delays in development due to formal specification changes. The OCS Design Requirements Document (SPEC-0161) has not been finalized. Operator experience with user interface might suggest new interfaces late in development. Some additional interactions may be necessary and are not covered under existing specifications and design. Examples would include experiment and observation management tools and status screens. Mitigation: Prioritize need for new interfaces and delay/omit implementation of less vital ones. Mitigation: Provide users with end-to-end simulation tools early to test typical observations and build experiments HLSC-002: Software Communications Infrastructure The required engineering data rates may be too high or large if there are many engineering parameters that need to be simultaneously saved. Current engineering archive hardware is selected on basis of best estimates from incomplete specifications. Mitigation: Upgrade hardware to either increase performance or split data streams onto separate databases or even networks. Mitigation: Hire database performance consultant. Database have been tuned only minimally; experience has shown that professional database consultants may be able to dramatically increase performance or make recommendations to operate more efficiently. PMCS-0020, Revision A Page 10 of 15

14 5. COST ESTIMATES The DKIST budget for the OCS is $743K. This escalated cost number was developed by a bottom-up cost analysis performed in March 2009, and assumed hardware technology available at that time. Project contingency applies only to hardware and 5% contingency was set aside. 5.1 COST ESTIMATE The August 2011 DKIST budget has created separate work packages for labor and materials of each OCS development area. New quotes were obtained all materials required by the OCS and CSF designs. The total cost of the OCS has not changed appreciably from 2009 and is still estimated at $743K. Additional labor costs were incurred with the end-to-end test bed, while hardware costs were lowered in all areas. S-WASW3-200 Management (ARRA) $53, S-WMSW3-202 OCS Hardware $89, S-WASW3-205 OCS - Scripting Support $17, S-WASW3-215 OCS Experiments $20, S-WASW3-225 OCS Facilities $45, S-WMSW3-210 OCS Final - Scripting Support $82, S-WMSW3-220 OCS Final Experiments $64, S-WMSW3-230 OCS Final Facilities $146, S-WMSW3-235 OCS - Integration ICS, TCS, and DHS $96, S-WASW3-226 OCS End-to-end Testing $74, S-WMSW3-226 OCS End-to-end Testing $51, Total $743, Construction Labor Labor costs for the OCS were recalculated in August 2011 for the individual schedule items. OCS total labor has been increased to by 0.5 FTE years due to the design changes and overall increase of necessary work. The new design has integrated labor items for the end-to-end test bed. Resource Work FY2011 FY2012 SW.1 End-to-end test bed 50% 33% Experiments 42% 58% 42% Facilities 92% Scripting 8% 100% 42% Integration 58% 58% 25% FY2013 FY014 FY2015 FY2016 FY2017 Construction labor for the OCS ceases in March 2017, although integration activities will continue through the end of construction under the IT&C budget Integration, Testing, and Commissioning Labor After construction, the OCS labor remains in the project to perform IT&C activities. The IT&C planning for these activities is currently under development. The activities include: PMCS-0020, Revision A Page 11 of 15

15 Construction of the summit control room, including operator s station; Installation of the OCS and CSF in the computer room; Site acceptance testing of the OCS; Integration of the TCS, DHS, ICS, and; Integration of the remaining instruments. IT&C labor begins April 2017 and completes in July Construction Non-labor Hardware costs for the OCS were recalculated in July 2011 for the latest design. OCS Hardware includes the equipment necessary to deploy CSF services on the summit. All computers are commodity items we expect to purchase shortly before integration. Therefore the configuration and prices are expected to change over the course of the next three to four years. In some areas, such as disk drives, new technology may supplant our baseline hardware. In all cases the current technology meets the OCS requirements. Total cost for all materials is $90K. This is comprised of both the OCS and CSF equipment. Item Model # Price Total OCS Equipment Observer Workstation Various 1 $3, $3, Inst Sci Workstation Various 1 $3, $3, Investigator Various 1 Workstation $3, $3, OCS Container server Various 1 $4, $4, Experiment DB server Various 1 $8, $8, Log DB server Various 1 $3, $3, CSF Equipment Archive DB server Various $8, $8, Property DB server Various 1 $8, $8, Event server Various 1 $8, $8, Header DB server Various 1 $15, $15, Spares Various 1 $12, $12, $89, Contingency DKIST contingency is held by the project management and is not a part of any specific work package. However, to determine the project contingency, the OCS non-labor activities were assessed of possible risk factors and assigned a contingency percentage based upon the criteria of the DKIST Contingency Management Plan. The calculated OCS contingency was 5% of non-labor activities. As mention, the OCS contingency was then rolled up into the project-wide contingency. PMCS-0020, Revision A Page 12 of 15

16 6. SCHEDULE The OCS construction schedule began in October 2009 with the development of the preliminary versions of the experiment, facility, and scripting systems. Beginning October 2011, the development of the endto-end test bed commenced. In April 2013, the initial development of the experiment, facility, and scripting services commenced. In November 2013, the OCS started integration of all services with the ICS and TCS systems, including the final assembly of the end-to-end test bed. Continuing work of the OCS includes the final development of the OCS experiment execution through the end of 2015 and the release of the OCS Beta 2. During 2016 the OCS work will focus on the interface to NSO Operations for both experiment ingestion and status reporting. The OCS will also finalize the interface to the telescope with the completion of all major telescope subsystem packages, leading to the OCS Beta 3 release. During 2017 the OCS will provide necessary changes to the user interfaces from input during the IT&C effort. At the end of OCS construction, the OCS programmer will move to an Integration, Commissioning, and Testing position to assemble the OCS and the major software systems at Haleakela. PMCS-0020, Revision A Page 13 of 15

17 PMCS-0020, Revision A Page 14 of 15

18 7. CONFIGURATION ITEM DATA LIST The Configuration Item Data List (CIDL) describes the status of all major deliverable software and documentation items. At present, the CIDL for the DHS contains the following: Source Code Packages OCS Final Release 1.0 Documentation SPEC-0015, OCS Specification Document SPEC-0161, OCS Design Requirement Document TN-0064, OCS Critical Design Document CMX-0008, OCS Compliance Matrix MAN-0010, OCS Operations Manual PROC-0017, HLS Software Test Plan ICD-4.2/4.3, OCS to DHS Interface ICD-4.2/4.4, OCS to TCS Interface ICD-4.2/7.0, OCS to Operations Interface OCS Factory Assembly Test Plan PMCS-0020, Revision A Page 15 of 15

Instrument Control System Project Management

Instrument Control System Project Management Project Documentation Document PMCS-0021 Revision A Instrument Control System Project Management Bret Goodrich Software September 2015 Advanced Technology Solar Telescope 950 N. Cherry Avenue Tucson, AZ

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING DEVELOPMENT & INTEGRATION (SSPEDI) Space Solutions (SpS)

STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING DEVELOPMENT & INTEGRATION (SSPEDI) Space Solutions (SpS) SSPEDI SpS J.1(a), Attachment 1 80ARC018R0007 National Aeronautics and Space Administration Ames Research Center Moffett Field, CA 94035-0001 STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING

More information

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide processlabs CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide CMMI-DEV V1.3 Process Areas Alphabetically by Process Area Acronym processlabs CAR - Causal Analysis and Resolution...

More information

Instrument Control System Final Acceptance Test Results Rob Hubbard Systems

Instrument Control System Final Acceptance Test Results Rob Hubbard Systems Project Documentation Document TN-0284 Revision A Instrument Control System Final Acceptance Test Results Rob Hubbard Systems Dec 19, 2016 REVISION SUMMARY: 1. Date: Dec 19, 2016 Revision: A Changes: Created

More information

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT)

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) MOSAIC Quality Assurance Plan v04.02 Prepared by: Approved by: QUALITY ASSURANCE PLAN APPROVALS QA/QC Program

More information

Work Plan and IV&V Methodology

Work Plan and IV&V Methodology Work Plan and IV&V Methodology Technology initiatives and programs should engage with an IV&V process at the project planning phase in order to receive an unbiased, impartial view into the project planning,

More information

Software Testing Life Cycle

Software Testing Life Cycle Software Testing Life Cycle STLC (Software Testing Life Cycle) is an integral component of SDLC (Software Development Life Cycle). Testing has become a distinct phenomenon during and after the development

More information

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B 1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework

More information

Osprey Technologies, LLC. Quality Manual ISO9001:2008 Rev -

Osprey Technologies, LLC. Quality Manual ISO9001:2008 Rev - February 8, 2015 1 Osprey Technologies, LLC Quality Manual ISO9001:2008 Rev - February 8, 2015 Released by Dave Crockett President 6100 S. Maple Avenue, Suite 117 Tempe, AZ 85283 www.osprey-tech.com February

More information

Project Manager s Roadmap We re all smarter together

Project Manager s Roadmap We re all smarter together Version 7.0a Project Manager s Roadmap We re all smarter together Think Top Down! Methodology Checklists Define Plan Execute Close Conflict Resolution Modes Contract Outsource Management Mentoring References

More information

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes

More information

SCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE

SCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE 1 (11) TA Template V3.0 SCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE 1. SCOPE This document describes the Scope of Work

More information

CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide

CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide processlabs CMMI-SVC V1.3 CMMI for Services Version 1.3 Quick Reference Guide CMMI-SVC V1.3 Process Areas Alphabetically by Process Area Acronym processlabs CAM - Capacity and Availability Management...

More information

This document describes the overall software development process of microcontroller software during all phases of the Company Name product life cycle.

This document describes the overall software development process of microcontroller software during all phases of the Company Name product life cycle. Maturity Process Owner Check Release Description Valid Name / Department Name / Department Name / Department Detailed procedure for software development Title: Software Development Procedure Purpose: This

More information

GAMP Guideline & Validation Documentation

GAMP Guideline & Validation Documentation GAMP Guideline & Validation Documentation Danilo Maruccia Milano, 21 Marzo 2006 GAMP Guideline & Validation Documentation GAMP Guideline Planning documents Specification Documents Testing Documents Acceptance

More information

Navigation Support Services

Navigation Support Services OPS QMS QMS-EIMO-SERV-PR-4500-OPS Issue 1.1 May 2006 European Space Agency Agence spatiale européenne Copyright: 2004 European Space Agency : ii DOCUMENT APPROVAL Prepared by L. Agrotis, J. Dow, R. Zandbergen

More information

LVC-IA EC WBS/Dictionary Dictionary

LVC-IA EC WBS/Dictionary Dictionary WBS 1.0 LVC-IA EC 1.1 LVC-IA Products 1.1.1 Live Integration Products 1.1.2 Virtual Integration Products 1.1.3 Constructive Integration Products 1.1.4 Gaming Integration Products 1.1.5 Integrated Architecture

More information

Quality Assurance / Quality Control Plan

Quality Assurance / Quality Control Plan Quality Assurance / Quality Control Plan Table of Contents MANAGEMENT APPROACH... 3 SUBCONTRACT MANAGEMENT... 3 QUALITY MANAGEMENT APPROACH... 3 METHODOLOGY... 4 CONCEPT OF OPERATIONS... 5 QUALITY MANAGEMENT

More information

LVC-IA EC WBS/Dictionary Dictionary

LVC-IA EC WBS/Dictionary Dictionary WBS 1.0 LVC-IA EC 1.1 LVC-IA Products 1.1.1 Live Integration Products 1.1.2 Virtual Integration Products 1.1.3 Constructive Integration Products 1.1.4 Gaming Integration Products 1.1.5 Integrated Architecture

More information

T Software Testing and Quality Assurance Test Planning

T Software Testing and Quality Assurance Test Planning T-76.5613 Software Testing and Quality Assurance 10.10.2007 Test Planning Juha Itkonen Outline Test planning, purpose and usage of a test plan Topics of test planning Exercise References: IEEE Std 829-1998,

More information

Systems Engineers provide a Key Contribution and Role in System Integration and Test

Systems Engineers provide a Key Contribution and Role in System Integration and Test s Engineers provide a Key Contribution and Role in Integration and Test National Defense Industrial Association (NDIA) 9 th Annual s Engineering Conference October 23-26/2006 Test & Evaluation Track, Tuesday

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 032 TITLE: SQS PLAN AND SURVEILLANCE PROCESS

More information

version NDIA CMMI Conf 3.5 SE Tutorial RE - 1

version NDIA CMMI Conf 3.5 SE Tutorial RE - 1 Requirements Engineering SE Tutorial RE - 1 What Are Requirements? Customer s needs, expectations, and measures of effectiveness Items that are necessary, needed, or demanded Implicit or explicit criteria

More information

Independent Verification and Validation (IV&V)

Independent Verification and Validation (IV&V) Independent Verification and Validation (IV&V) 12 th Annual NDIA CMMI Conference November 2012 - Denver, CO The MITRE Corporation The author s affiliation with The MITRE Corporation is provided for identification

More information

Integration and Testing

Integration and Testing Integration and Testing 1 Today Software Quality Assurance Integration Test planning Types of testing Test metrics Test tools 2 Deliverables by Phase Possible Deliverables by Phase Concept Document Statement

More information

EXHIBIT A: STATEMENT OF WORK

EXHIBIT A: STATEMENT OF WORK EXHIBIT A: STATEMENT OF WORK TABLE OF CONTENTS 1. INTRODUCTION 2. PROJECT PLANNING AND MANAGEMENT 6 3. INFRASTRUCTURE / TECHNICAL ENVIRONMENT 10 r-e'" 4. FMS UPGRADE 13 4.1 BUILD PHASE 13 4.2 ACHIEVE PHASE

More information

CMMI V2.0 MODEL AT-A-GLANCE. Including the following views: Development Services Supplier Management. CMMI V2.0 outline BOOKLET FOR print.

CMMI V2.0 MODEL AT-A-GLANCE. Including the following views: Development Services Supplier Management. CMMI V2.0 outline BOOKLET FOR print. CMMI V.0 MODEL AT-A-GLANCE Including the following views: Development Services Supplier Management CMMI V.0 outline BOOKLET FOR print.indd CMMI V.0 An Integrated Product Suite Designed to meet the challenges

More information

Professional Engineers Using Software-Based Engineering Tools

Professional Engineers Using Software-Based Engineering Tools Professional Engineers Ontario GuidEline Professional Engineers Using Software-Based Engineering Tools Contributors: Eric Brown, P.Eng. / Colin Cantlie, P.Eng., / Norm Fisher, P.Eng., / Jeremy Jackson,

More information

FLORIDA DEPARTMENT OF JUVENILE JUSTICE PROCEDURE. Title: Information Technology (IT) Project Management and Governance Procedures

FLORIDA DEPARTMENT OF JUVENILE JUSTICE PROCEDURE. Title: Information Technology (IT) Project Management and Governance Procedures PROCEDURE Title: Information Technology (IT) Project Management and Governance Procedures Related Policy: FDJJ 1270 I. DEFINITIONS Agency for State Technology (AST) Rule Rules 74-1.001 through 74-1.009,

More information

Biometrics Enterprise Architecture Systems Engineering Management Plan (BMEA SEMP)

Biometrics Enterprise Architecture Systems Engineering Management Plan (BMEA SEMP) Biometrics Enterprise Architecture Systems Engineering Management Plan (BMEA SEMP) Version 1.0 Prepared by: Date: November 24, 2009 Revision History Purpose Revision Date Level 11/17/2009 First Draft 1.0

More information

Program Summary. Criterion 1: Importance to University Mission / Operations. Importance to Mission

Program Summary. Criterion 1: Importance to University Mission / Operations. Importance to Mission Program Summary DoIT supports and provides the infrastructure and custom development for NIU s student administration system known collectively as MyNIU. Over 55,000 students, applicants, faculty and advisors

More information

Windchill System Validation Technical Brief

Windchill System Validation Technical Brief Technical Brief Contents About This Document... 2 Supported Releases and Products... 2 Audience... 2 Support Policy for Enterprise Deployment Resources... 2 Challenge... 3 Solution... 3 Planning... 4 Preparing...

More information

"Change is inevitable; except in vending machines."

Change is inevitable; except in vending machines. Configuration Management Change is inevitable. In acquisition programs, missions, requirements, technologies, and environments change. In response, the system design will change as it evolves through the

More information

Project Planning and Management (PPM) V2.0. WBS Dictionary

Project Planning and Management (PPM) V2.0. WBS Dictionary Project Planning and Management (PPM) V2.0 WBS Dictionary Software as a Service (SaaS) Version 1.0 August 2014 1 Table of Contents PPM V2.0 Work Breakdown Structure (WBS) Dictionary 1 Project Type: Software

More information

Patrick Malloy Communities Quality Assurance System

Patrick Malloy Communities Quality Assurance System Patrick Malloy Communities Quality Assurance System Page 1 of 83 Log of Quality Manual Revisions Version Number Revision Date Type of Revision 1 April 9, 2007 1 st release 1 April 13, 2007 Sec 1.10 removed

More information

Continuous Diagnostic and Mitigation and Continuous Monitoring as a Service. CMaaS TASK AREAS

Continuous Diagnostic and Mitigation and Continuous Monitoring as a Service. CMaaS TASK AREAS Continuous Diagnostic and Mitigation and Continuous Monitoring as a Service CMaaS TASK AREAS CMaaS TASK AREAS The contractor shall provide functional, strategic, and managerial business consulting and

More information

Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO

Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO Improving Project Management to Realize Successful Outcomes by Focusing on Requirements Management Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO Introduction Begin at the beginning,

More information

APPENDIX C Configuration Change Management Verification and Validation Procedures

APPENDIX C Configuration Change Management Verification and Validation Procedures DCMA-INST 217 APPENDIX C Configuration Change Management Verification and Validation Procedures Table of Contents C1. Introduction... C-1 C2. Implementation... C-1 C3. Pre-Inspection: Verification... C-1

More information

PRECISE INDUSTRIES INC. Quality Manual

PRECISE INDUSTRIES INC. Quality Manual PRECISE INDUSTRIES INC Revision N Issued July 5, 2017 Conforms to AS9100 Rev. D and ISO 9001:2015 Copyright Year2017 [PRECISE INDUSTRIES INC]; all rights reserved. This document may contain proprietary

More information

CMMI for Acquisition Quick Reference

CMMI for Acquisition Quick Reference AGREEMENT MANAGEMENT PROJECT MANAGEMENT (ML2) The purpose of Agreement Management (AM) is to ensure that the supplier and the acquirer perform according to the terms of the supplier agreement. SG 1 The

More information

DESIGN CONTROL. Your Logo Here. Operational Procedure: EOP Rev.: A Pg. 1 1 of 7 DISTRIBUTION

DESIGN CONTROL. Your Logo Here. Operational Procedure: EOP Rev.: A Pg. 1 1 of 7 DISTRIBUTION Your Logo Here DESIGN CONTROL Operational Procedure: EOP-04-01 Rev.: A Pg. 1 1 of 7 DISTRIBUTION President Purchasing Human Resources Design Engineering Service Quality Assurance Production Marketing Quality

More information

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3)

3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) 3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) Emagine IT s approach to Independent Verification and Validation (IV&V) has been shaped over the years by hands-on experience and contributions

More information

This resource is associated with the following paper: Assessing the maturity of software testing services using CMMI-SVC: an industrial case study

This resource is associated with the following paper: Assessing the maturity of software testing services using CMMI-SVC: an industrial case study RESOURCE: MATURITY LEVELS OF THE CUSTOMIZED CMMI-SVC FOR TESTING SERVICES AND THEIR PROCESS AREAS This resource is associated with the following paper: Assessing the maturity of software testing services

More information

Implement Effective Computer System Validation. Noelia Ortiz, MME, CSSGB, CQA

Implement Effective Computer System Validation. Noelia Ortiz, MME, CSSGB, CQA Implement Effective Computer System Validation Noelia Ortiz, MME, CSSGB, CQA Session Outline 1 2 3 4 5 Understanding Regulations and Guidelines Pertaining to Computer Systems Integrate SDLC and GAMP 5

More information

Space Flight Configuration Management Requirements

Space Flight Configuration Management Requirements LPR 8040.1 Effective Date: January 8, 2009 Expiration Date: January 8, 2014 Langley Research Center Flight Projects Directorate Space Flight Configuration Management Requirements National Aeronautics and

More information

CHANGE MANAGEMENT PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT)

CHANGE MANAGEMENT PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) CHANGE MANAGEMENT PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) MOSAIC Change Management Plan v03.01 CHANGE MANAGEMENT PLAN VERSION CONTROL Version Date Change Description

More information

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan M3 Playbook Guidance Phase 1: Readiness This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration

More information

Quality Management System Manual

Quality Management System Manual 19240 144 th Ave NE, ldg 2 Woodinville, WA 98072 (425) 487-0672 FAX (425) 487-4669 Quality Management System Manual Approvals Name Title Initial Name Title Initial Lisa Tiffany President On File Dan McDrummond

More information

Safety assurance for a signalling system based on quality management

Safety assurance for a signalling system based on quality management Risk Analysis IX 499 Safety assurance for a signalling system based on quality management F. Yan School of Electronics and Information Engineering, Beijing Jiaotong University, China Abstract The fast

More information

Ten Requirements for Effective Process Control

Ten Requirements for Effective Process Control Published in ASQ Quality Progress and won the Paper of the Year Award in 2002. Ten Requirements for Effective Process Control Thomas A. Little Ph.D. Thomas A. Little Consulting 12401 N Wildflower Lane

More information

State of Washington. WIC Cascades Project MIS Transfer and Implementation Scope of Work. Department of Health

State of Washington. WIC Cascades Project MIS Transfer and Implementation Scope of Work. Department of Health State of Washington Department of Health Prevention & Community Health Division Office of Nutrition Services Women, Infants, and Children (WIC) Program MIS Transfer and Implementation Scope of Work July

More information

Business Management System Manual Conforms to ISO 9001:2015 Table of Contents

Business Management System Manual Conforms to ISO 9001:2015 Table of Contents Table of Contents 1.0 Welcome to Crystalfontz... 3 2.0 About the Crystalfontz Business Systems Manual... 4 3.0 Terms and Conditions... 5 4.0 Context of the Organization... 6 4.1. Understanding the Organization

More information

TELEPHONICS SUPPLIER QUALITY MANAGEMENT AS9102 FIRST ARTICLE INSPECTION GUIDELINES

TELEPHONICS SUPPLIER QUALITY MANAGEMENT AS9102 FIRST ARTICLE INSPECTION GUIDELINES WELCOME TELEPHONICS SUPPLIER QUALITY MANAGEMENT AS9102 FIRST ARTICLE INSPECTION GUIDELINES -1 BACKGROUND Telephonics customer base is increasingly requiring by contract that Telephonics provide full AS9102

More information

INS QA Programme Requirements

INS QA Programme Requirements Specification Date: 20/3/17 INS QA Programme Requirements UNCONTROLLED WHEN PRINTED Author: J Cooch AUTHORISATION Date: 20/3/17 A Brown Owner: J Cooch (Signature) N.B. only required for hard copy If issued

More information

Deliverable: 1.4 Software Version Control and System Configuration Management Plan

Deliverable: 1.4 Software Version Control and System Configuration Management Plan Deliverable: 1.4 Software Version Control and System Configuration VoteCal Statewide Voter Registration System Project State of California, Secretary of State (SOS) Authors This document was prepared

More information

Copyright Software Engineering Competence Center

Copyright Software Engineering Competence Center Copyright Software Engineering Competence Center 2012 1 Copyright Software Engineering Competence Center 2012 5 These are mapped categories to the waste categories of manufacturing. An excellent overview

More information

Project Execution Plan For

Project Execution Plan For Project Execution Plan For [Insert Name Here] Project Document Revision History Revision Date Project Manager Project Sponsor Page 1 of 24 About This Project Execution Plan Template: This template is intended

More information

Space product assurance

Space product assurance ECSS-Q-ST-10C Space product assurance Product assurance management ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands Foreword This Standard is one of the series of

More information

ISO 9001:2000 Drives Process Changes at Siemens

ISO 9001:2000 Drives Process Changes at Siemens Select Q&A, M. Davis Research Note 20 December 2002 ISO 9001:2000 Drives Process Changes at Siemens Siemens Medical Solutions Health Services is an early enterprise vendor adopter of ISO 9001:2000. It

More information

Implementing an Automated Testing Program

Implementing an Automated Testing Program Implementing an Automated Testing Program An Innosphere Ritepaper INNOSPHERE SYSTEMS DEVELOPMENT GROUP LTD. 147 WYNDHAM ST. NORTH, SUITE 306 GUELPH, ONTARIO, CANADA, N1H 4E9 TEL: 519.766.9726 WWW.INNOSPHERE.CA

More information

Report of the Reliability Improvement Working Group (RIWG) Volume II - Appendices

Report of the Reliability Improvement Working Group (RIWG) Volume II - Appendices Report of the Reliability Improvement Working Group (RIWG) Volume II - Appendices Appendix 1 Formulate Programs with a RAM Growth Program II-1 1.1 Reliability Improvement Policy II-3 1.2 Sample Reliability

More information

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services ATTACHMENT A SAMPLE SCOPE OF SERVICES PLC & HMI PROGRAMMING City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services December, 2017

More information

THE CLUSO VISION SYSTEM AREAS OF APPLICATION

THE CLUSO VISION SYSTEM AREAS OF APPLICATION AREAS OF APPLICATION FIRST ARTICLE INSPECTION Originally designed as a First Article Inspection system, Cluso excels in this space. If human visual inspection is occupying too much time during the line

More information

AUTOMOTIVE SPICE v3.1 POCKET GUIDE

AUTOMOTIVE SPICE v3.1 POCKET GUIDE EXTENDED VDA SCOPE ASPICE v3.1 AUTOMOTIVE SPICE v3.1 POCKET GUIDE 4 5 6 7 8-9 10 11-13 14-15 16-19 20-43 44-49 50-51 52-69 70-93 94-103 104-105 106 Automotive SPICE at a glance Automotive SPICE application

More information

CUSTOMER AND SUPPLIER ROLES AND RESPONSIBILITIES FOR 21 CFR 11 COMPLIANCE ASSESSMENT. 21 CFR Part 11 FAQ. (Frequently Asked Questions)

CUSTOMER AND SUPPLIER ROLES AND RESPONSIBILITIES FOR 21 CFR 11 COMPLIANCE ASSESSMENT. 21 CFR Part 11 FAQ. (Frequently Asked Questions) 21 CFR Part 11 FAQ (Frequently Asked Questions) Customer and Supplier Roles and Responsibilities for Assessment of METTLER TOLEDO STARe Software Version 16.00, including: - 21 CFR 11 Compliance software

More information

ANCHOR ISO9001:2008 RPR-007 MARINE SERVICES ADDITIONAL PROCEDURE PRODUCT REALISATION

ANCHOR ISO9001:2008 RPR-007 MARINE SERVICES ADDITIONAL PROCEDURE PRODUCT REALISATION PRODUCT REALISATION Document Control Revision History PAGE REASON FOR CHANGE REV. REVIEWER / AUTHORISED BY: RELEASE DATE: ALL NEW DOCUMENT A J.BENTINK 5/08/2016 Revision Approval: J.BENTINK Signature:

More information

Assessment of String Tests Strategy for an En Route Air Traffic Control System

Assessment of String Tests Strategy for an En Route Air Traffic Control System Assessment of String Tests Strategy for an En Route Air Traffic Control System Jeff O Leary Federal Aviation Administration 800 Independence Avenue, SW Washington, DC 20591 202-385-8377 Jeff.OLeary@faa.gov

More information

Chapter 6. Software Quality Management & Estimation

Chapter 6. Software Quality Management & Estimation Chapter 6 Software Quality Management & Estimation What is Quality Management Also called software quality assurance (SQA) s/w quality:- It is defined as the degree to which a system, components, or process

More information

PCA ELECTRONICS, INC. Quality Manual

PCA ELECTRONICS, INC. Quality Manual PCA ELECTRONICS, INC. Conforms to ISO 9001:2015 (c) 2018 PCA Electronics, Inc.; all rights reserved. This document may contain proprietary information and may only be released to third parties with approval

More information

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013)

Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Summary of 47 project management processes (PMBOK Guide, 5 th edition, 2013) Integration Management: processes & activities needed to properly coordinate all aspects of the project to meet stakeholder

More information

Project+ Examination Blueprint Version June 1, 2003

Project+ Examination Blueprint Version June 1, 2003 Introduction The Project + examination is designed for business professionals involved with projects with a technology component. The examination is designed for candidates possessing at least 12 months

More information

1. Can you explain the PDCA cycle and where testing fits in?

1. Can you explain the PDCA cycle and where testing fits in? 1. Can you explain the PDCA cycle and where testing fits in? Software testing is an important part of the software development process. In normal software development there are four important steps, also

More information

Independent Verification and Validation of SAPHIRE 8 Software Project Plan

Independent Verification and Validation of SAPHIRE 8 Software Project Plan INL/EXT-09-17022 Rev. 1 Independent Verification and Validation of SAPHIRE 8 Software Project Plan December 2009 The INL is a U.S. Department of Energy National Laboratory operated by Battelle Energy Alliance

More information

DO-178B 김영승 이선아

DO-178B 김영승 이선아 DO-178B 201372235 김영승 201372237 이선아 Introduction Standard Contents SECTION 1 INTRODUCTION SECTION 2 SYSTEM ASPECTS RELATING TO SOFTWARE DEVELOPMENT SECTION 3 SOFTWARE LIFE CYCLE SECTION 4 SOFTWARE PLANNING

More information

INTRODUCTION: Plan and Schedule Development Task Identification and Work Breakdown Structure

INTRODUCTION: Plan and Schedule Development Task Identification and Work Breakdown Structure What This Is INTRODUCTION: Plan and Schedule Development Task Identification and Work Breakdown Structure The detailed guidelines and examples start on the following page First of a series of six templates

More information

Program/Project Management

Program/Project Management PROCEDURE OVERVIEW PROGRAM/PROJECT MANAGEMENT PROCEDURE defines the project management infrastructure, reporting relationships and project management activities within SDLC.com. Project Managers, Program

More information

Change Control and Configuration Management Plan

Change Control and Configuration Management Plan LSST Change Control and Configuration Management Plan LPM-19 6/19/2011 Large Synoptic Survey Telescope (LSST) Change Control and Configuration Management Plan Chuck F. Claver, Victor Krabbendam and Donald

More information

CAPITAL AVIONICS, INC. Quality Manual

CAPITAL AVIONICS, INC. Quality Manual CAPITAL AVIONICS, INC. Issued 31 July 2018 Conforms to ISO 9001:2015 2018 ; all rights reserved. This document may contain proprietary information and may only be released to third parties with approval

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

Testing 2. Testing: Agenda. for Systems Validation. Testing for Systems Validation CONCEPT HEIDELBERG

Testing 2. Testing: Agenda. for Systems Validation. Testing for Systems Validation CONCEPT HEIDELBERG CONCEPT HEIDELBERG GMP Compliance for January 16-17, 2003 at Istanbul, Turkey Testing for Systems Validation Dr.-Ing. Guenter Generlich guenter@generlich.de Testing 1 Testing: Agenda Techniques Principles

More information

Appendix C: MS Project Software Development Plan and Excel Budget.

Appendix C: MS Project Software Development Plan and Excel Budget. 1. Introduction. Appendix C: MS Project Software Development Plan and Excel Budget. Project: PickUp Game App The Project plan for this Application consist of 76 days; In this plan is defined how long each

More information

Sample Company. Risk Assessment and Mitigation Plan

Sample Company. Risk Assessment and Mitigation Plan Sample Company Revision History DATE VERSION DESCRIPTION AUTHOR 08-07-04 0.01 Initial Version F. Jack Anderson 09-07-04 0.02 Revised with changes from team reviews Michael Bennett 09-08-04 2.00 Initial

More information

Quality Manual ISO 9001:2008 ISO 9001:2015

Quality Manual ISO 9001:2008 ISO 9001:2015 Quality Manual ISO 9001:2008 ISO 9001:2015 SAE CIRCUITS, INC. 4820 63 rd Street Suite 100 Boulder, CO 80301 USA www.saecircuits.com Table of Contents 1. Company Information 3 2. QMS Scope and Exclusions

More information

Risk Mitigation in a Core Banking Conversion

Risk Mitigation in a Core Banking Conversion Risk Mitigation in a Core Banking Conversion Greg Meidt, chief information officer Chemical Bank Dick Smies, vice president IBS Conversion Services 1 800 822 6758 Introduction A core banking migration

More information

Volume III ARCHITECTURE MAINTENANCE PLAN

Volume III ARCHITECTURE MAINTENANCE PLAN Kansas Statewide Intelligent Transportation System Architecture KDOT Project No. 106 KA-0380-01 Volume III ARCHITECTURE MAINTENANCE PLAN Version 1.00 Prepared for: Prepared by: January 2008 Page Left Blank

More information

Project Procedures 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /21/2012 PAGE 1 OF 13 BASIS OF OPERATION

Project Procedures 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /21/2012 PAGE 1 OF 13 BASIS OF OPERATION Project Procedures BASIS OF OPERATION 09/21/2012 PAGE 1 OF 13 1.0 PURPOSE The purpose of this procedure is to establish the basis of operations that ensures that Project activities, including engineering,

More information

Capability Maturity Model for Software (SW-CMM )

Capability Maturity Model for Software (SW-CMM ) PHASE-IV: SYSTEMS IMPLEMENTATION Software Quality Assurance Application Development Installation and Support Software Quality Assurance Capability Maturity Model for Software (SW-CMM ) The Capability Maturity

More information

Supplier Quality Survey. 1. Type of Business: g) Commodities supplied? Supplier Changes/comments: 2. Headcount breakdown by group: Purchasing

Supplier Quality Survey. 1. Type of Business: g) Commodities supplied? Supplier Changes/comments: 2. Headcount breakdown by group: Purchasing Supplier: Phone: Prime Contact/Title: Sales Contact/Title: Address: Fax: e-mail address e-mail address Quality Contact/Title: e-mail address 1. Type of Business: a) Number of years in business? b) Company

More information

TÜV SÜD BABT Production Quality Certification Scheme

TÜV SÜD BABT Production Quality Certification Scheme TÜV SÜD BABT Production Quality Certification Scheme The Production Quality Certification Scheme for Manufacturers A Certification Body of Copyright TÜV SÜD BABT 2014 Page 1 of 38 CONTENTS Page AMENDMENT

More information

ENERGY PERFORMANCE PROTOCOL QUALITY ASSURANCE SPECIFICATION

ENERGY PERFORMANCE PROTOCOL QUALITY ASSURANCE SPECIFICATION ENERGY PERFORMANCE PROTOCOL QUALITY ASSURANCE SPECIFICATION Version 1.0 April 2015 Table of Contents 1.0 INVESTOR CONFIDENCE PROJECT 1.1 ENERGY EFFICIENCY PERFORMANCE QUALITY ASSURANCE SPECIFICATION 1.2

More information

Project Plan. For Building a Data Management System for FORCE. Prepared for: Andrew Lowery Fundy FORCE

Project Plan. For Building a Data Management System for FORCE. Prepared for: Andrew Lowery Fundy FORCE Project Plan For Building a Data Management System for FORCE Prepared for: Andrew Lowery Fundy FORCE Submitted by: SEG Consulting Inc. www.segconsulting.ca Version 1.0 June 29, 2017 Version Log The following

More information

TECHNICAL REVIEWS AND AUDITS

TECHNICAL REVIEWS AND AUDITS Chapter 11 Technical Reviews and Audits CHAPTER 11 TECHNICAL REVIEWS AND AUDITS 11.1 PROGRESS MEASUREMENT The Systems Engineer measures design progress and maturity by assessing its development at key

More information

Test Workflow. Michael Fourman Cs2 Software Engineering

Test Workflow. Michael Fourman Cs2 Software Engineering Test Workflow Michael Fourman Introduction Verify the result from implementation by testing each build Plan the tests in each iteration Integration tests for every build within the iteration System tests

More information

Software product quality assurance

Software product quality assurance Software product quality assurance by-john R. RYAN Texas Instruments, Inc. Austin, Texas ABSTRACT Providing clear objectives, guidelines, and requirements in an environment conducive to high productivity

More information

INSTRUMENTATION AND CONTROL ACTIVITIES AT THE ELECTRIC POWER RESEARCH INSTITUTE TO SUPPORT COMPUTERIZED SUPPORT SYSTEMS

INSTRUMENTATION AND CONTROL ACTIVITIES AT THE ELECTRIC POWER RESEARCH INSTITUTE TO SUPPORT COMPUTERIZED SUPPORT SYSTEMS INSTRUMENTATION AND CONTROL ACTIVITIES AT THE ELECTRIC POWER RESEARCH INSTITUTE TO SUPPORT COMPUTERIZED SUPPORT SYSTEMS J.NASER Electric Power Research Institute, Palo Alto, United States of America XA9643050

More information

Independent Verification and Validation of SAPHIRE 8 Software Project Plan

Independent Verification and Validation of SAPHIRE 8 Software Project Plan INL/EXT-09-17022 Independent Verification and Validation of SAPHIRE 8 Software Project Plan October 2009 The INL is a U.S. Department of Energy National Laboratory operated by Battelle Energy Alliance

More information

Automated System Validation By: Daniel P. Olivier & Curtis M. Egan

Automated System Validation By: Daniel P. Olivier & Curtis M. Egan Automated System Validation By: Daniel P. Olivier & Curtis M. Egan In today s technical environment validation practices are both a requirement and an important tool in the medical and pharmaceutical industry.

More information

BASICS OF SOFTWARE TESTING AND QUALITY ASSURANCE. Yvonne Enselman, CTAL

BASICS OF SOFTWARE TESTING AND QUALITY ASSURANCE. Yvonne Enselman, CTAL BASICS OF SOFTWARE TESTING AND QUALITY ASSURANCE Yvonne Enselman, CTAL Information alines with ISTQB Sylabus and Glossary THE TEST PYRAMID Why Testing is necessary What is Testing Seven Testing principles

More information

Enterprise SM VOLUME 2, SECTION 2.6: TROUBLE AND COMPLAINT HANDLING

Enterprise SM VOLUME 2, SECTION 2.6: TROUBLE AND COMPLAINT HANDLING VOLUME 2, SECTION 2.6: TROUBLE AND COMPLAINT HANDLING 2.6 TROUBLE AND COMPLAINT HANDLING [C.3.4.2, M.3.7] 2.6.1 TROUBLE AND COMPLAINT ORGANIZATION AND RESOURCES [L.34.2.3.6] The Level 3 Team provides a

More information