The Anatomy of a Tile Installation. A Panel Discussion Related to the Primary Disciplines of a Project

Size: px
Start display at page:

Download "The Anatomy of a Tile Installation. A Panel Discussion Related to the Primary Disciplines of a Project"

Transcription

1 The Anatomy of a Tile Installation A Panel Discussion Related to the Primary Disciplines of a Project

2 The Panel Nick Cipiti, Walworth Partners Representing Legal Council Dave Stutzman, Conspectus, Inc Representing Architects & Spec Writers Chris Wolf, Shelby Materials Co. Representing Division 3 and General Contractor Mike Micalizzi, Custom Building Products Representing Manufacturers David debear, Custom Building Products Moderator

3 For each discipline, we will identify and apply Learning Objective The role of legal council For all parties The role of the architect The role of the spec writer The role of the Contractor General contractor Subcontractors The role of the supply chain Manufacturer Distribution

4 This case study will look into a commercial flooring installation from beginning to end. This is based on an actual project of 25,000 sf +/- where we will not identify any of the parties or its name and location. This project has been completed, and is currently in service. The Case Study This project incorporated three different architects/design firms, and the affect on Division 9 was substantial. Our goal is to describe the project process flow, and with that information, we will open the floor for questions of the panel.

5

6 The Process The original design intent was to provide mixed finishes throughout the public areas. As such, the cast slab was depressed to accommodate any finish. As the project progressed, floor finishes were selected Multiple finishes were selected, requiring different slab elevations.

7

8 The Process With selections such as these, the effect on the flooring contractor(s) was substantial. The selected wood finish was 3/8 (9mm) thick plus 40 mil underlayment and adhesive. The selected stone tile was ¾ (19mm) plus mortar. (aprox 1 (26mm)). We must remember the original slab was depressed approximately 3 and has an FF and CSP equivalent of 5 or 6 at best.

9 Now things are getting messy Now the finishes are selected, we must go back to the GC to determine the best solution for floor preparation. Looking back at Division 3 vs. Division 9, the cost of such prep drives the conversation. SLU vs. Topping slab?? What is in the budget to accommodate the finish selections?

10 From the Specs Division RELATED SECTIONS A. Section Cast-in-Place Concrete: Substrate of postinstalled anchors. B. Section Structural Steel Framing: Components secured with post-installed anchors. C. Section Metal Fabrications: Components secured with post-installed anchors. D. Section Rough Carpentry: Components secured with post-installed anchors.

11 CAST-IN-PLACE CONCRETE TOLERANCES 1. CONCRETE COVER MEASURED PERPENDICULAR FROM THE SURFACE IN DIRECTION OF TOLERANCES: MEMBERS 12" OR LESS 3/8 MEMBERS OVER 12" ½ 2. STEEL REINFORCEMENT SPACING SHALL BE WITHIN THE FOLLOWING TOLERANCES: ¼ SPACING DISTANCE, NOT TO EXCEED 1" 3. PLACEMENT OF EMBEDDED ITEMS SHALL BE WITHIN THE FOLLOWING TOLERANCES: VERTICAL ALIGNMENT ---- LATERAL ALIGNMENT ---- LEVEL ALIGNMENT PLACEMENT OF FOOTINGS SHALL BE WITHIN THE FOLLOWING TOLERANCES: LATERAL ALIGNMENT ---- LEVEL ALIGNMENT +1/2" TO 2" (LEVEL ALIGNMENT SUPPORTING MASONRY) CROSS-SECTIONAL DIMENSION OF FOOTINGS SHALL BE WITHIN THE FOLLOWING TOLERANCES: FORMED FOOTINGS +2" TO -1/2" EARTHCAST FOOTINGS: 2' OR LESS +3" TO -1/2" GREATER THAN 2' BUT LESS THAN 6' +6" TO -1/2" GREATER THAN 6' +12" TO -1/2" FOOTING THICKNESS TOP OF FOOTING SLOPE 1" IN 10'

12 From the Specs Division SETTING AND GROUTING MATERIALS A. Manufacturers: 1. Atlas Minerals & Chemicals, Inc. 2. Boiardi Products Corporation. 3. Bonsal, W. R., Company. 4. Bostik. 5. C Cure. 6. Custom Building Products. 7. DAP, Inc. 8. LATICRETE International Inc. 9. MAPEI Corporation. 10. Southern Grouts & Mortars, Inc. 11. TEC Specialty Products Inc.

13 From the Specs Division 9 contd. B. Sand Portland Cement Grout: ANSI A108.10, composed of white or gray cement and white or colored aggregate as required to produce color indicated. C. Standard Sanded Cement Grout: ANSI A118.6, color as indicated. D. Standard Unsanded Cement Grout: ANSI A118.6, color as selected from Manufacturer s Standard and Custom Colors. E. Polymer Modified Tile Grout: ANSI A118.7, color as indicated.

14 From the specs Division 9 PART 3 EXECUTION 3.1 INSTALLATION - GENERAL A. Install tile, thresholds, and stair treads and grout in accordance with applicable requirements of ANSI A108.1a through ANSI A108.13, manufacturer's instructions, and TCNA (HB) recommendations. B. Lay tile to pattern indicated. Do not interrupt tile pattern through openings. C. Cut and fit tile to penetrations through tile, leaving sealant joint space. Form corners and bases neatly. Align floor joints.

15 The discussion between GC and subs The flooring contractor would prefer to complete the prep work in house. This will ensure control for the entire floor installation. The GC disagrees Can you imagine why?

16 Things To Consider At This Point Required warranties Systems integration between divisions UCC law The role of the manufacturer The role of the supplier(s) Construction schedules Financial penalties Other considerations

17 Change Order The final decision was to go back to the Concrete Contractor to install a topping slab in place of traditional mortar bed(s) or SLU. This was done in protest by the flooring contractor Enter the flooring suppliers and setting materials manufacturers

18

19 The Results Attempted Repairs

20 The End Result

21 The next step was the owner to file a law suit against the Flooring Contractor, General Contractor, Suppliers of Tile and Installation Materials. The stone tile, and wood floor was replaced as a result of the defective topping slab installation. It was determined that all parties shared in the responsibility for the remedial work. Sooo how and why did we get here?

22

23 The Results Attempted Repairs

24 Tile Contractors' Association of America (TCAA) 9300 Contractor Magazine Survey Q1 Please list a few topics relating to industry issues/problems that you would like to see addressed in TCAA s 9300 Contractor magazine. Response from: Patrick Conway of Baybrent Tile, NY Architectural specifications (09300) are very ambiguous in regards to install methods and products. (ex. waterproofing, epoxy products, prep, Thinset vs Mud Set, crack suppressant membrane, etc.)

25 Response from: Patrick Conway of Baybrent Tile, NY Many specs mention anything and everything but don't tell you exactly what they want and where they want. Major issue when bidding projects. You figure something in the specs your competition didn't your number is high you lose the job. You don't figure something that is vague in the specs, you get the job and client expects X, Y,& Z that is mentioned in the specs among several other items. Then you lose money.

26 Response from: Patrick Conway of Baybrent Tile, NY I would also like to address the industry wide plague that affects ALL trades. The bidding process. The constant revisions, addendums, bulletins, rebids, etc. We spend half our time sifting through s, downloading addendum drawings only to find out 95% of the time has nothing to do with our trade! Waste of time, time = money. Huge industry time waster not to mention how easy it could be to miss something on the millions of revisions they send out!

27 Open Discussion We will discuss, in an open forum, all aspects of this flawed process.

28 Thank you for your participation Special thanks to our panel Nick Cipiti Dave Stutzman Chris Wolf Mike Micalizzi

SECTION TILING

SECTION TILING PART 1 GENERAL 1.01 SECTION INCLUDES A. Ceramic Tile for floor applications. B. Ceramic Tile for wall applications. C. Ceramic accessories. D. Ceramic trim. E. Non-ceramic trim. 1.02 RELATED REQUIREMENTS

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 093000 - TILING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SECTION CERAMIC TILE. B. Ceramic tile wall finishes including standard and custom designs.

SECTION CERAMIC TILE. B. Ceramic tile wall finishes including standard and custom designs. SECTION 09 30 13 CERAMIC TILE PART 1 GENERAL 1.1 SECTION INCLUDES A. Ceramic tile floor and base finishes. B. Ceramic tile wall finishes including standard and custom designs. 1.2 REFERENCES A. ANSI/TCNA

More information

SECTION BRICK FLOORING

SECTION BRICK FLOORING SECTION 09 63 13 BRICK FLOORING SPEC WRITER NOTE: Delete text between // // not applicable to project. Edit remaining text to suit project. PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Brick flooring

More information

Student Services & Classroom Addition

Student Services & Classroom Addition SECTION 093000 - TILING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

1.6 QUALITY ASSURANCE A. Source Limitations for Tile: Obtain tile of each type and color or finish from one source or producer.

1.6 QUALITY ASSURANCE A. Source Limitations for Tile: Obtain tile of each type and color or finish from one source or producer. SECTION 093000 - TILING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Bush Elem. Addition & Alterations QUARRY TILE SECTION QUARRY TILE PART 1 - GENERAL

Bush Elem. Addition & Alterations QUARRY TILE SECTION QUARRY TILE PART 1 - GENERAL 73651.01 QUARRY TILE 093016-1 1.1 RELATED DOCUMENTS: SECTION 093016 - QUARRY TILE PART 1 - GENERAL A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division

More information

SECTION TILING

SECTION TILING SECTION 093000 TILING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and General Provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

1.3 Work shall include all reinforcement and accessories necessary to complete installation.

1.3 Work shall include all reinforcement and accessories necessary to complete installation. CERAMIC TILING GENERAL INFORMATION 1.1 Ceramic mosaic tile floors and bases, glazed wall tile wainscots and walls, and marble thresholds. 1.2 Installation will typically be with latex-portland cement mortar

More information

***************************************************************************************************************

*************************************************************************************************************** 09330 QUARRY TILE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 09 30 16 ***************************************************************************************************************

More information

SECTION TILING PART 1 - GENERAL 1.1 SUMMARY. A. Section Includes: 1. Ceramic tile. 2. Waterproof membrane. 3. Metal edge strips.

SECTION TILING PART 1 - GENERAL 1.1 SUMMARY. A. Section Includes: 1. Ceramic tile. 2. Waterproof membrane. 3. Metal edge strips. SECTION 093000 - TILING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Ceramic tile. 2. Waterproof membrane. 3. Metal edge strips. 1.2 SUBMITTALS A. Product Data: For each type of product indicated.

More information

B. Related Sections: 1. Division 07 Section "Joint Sealants" for sealing of expansion, contraction, control, and isolation joints in tile surfaces.

B. Related Sections: 1. Division 07 Section Joint Sealants for sealing of expansion, contraction, control, and isolation joints in tile surfaces. SECTION 093000 - CERAMIC TILE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

TILING Lutheran Church of the Holy Spirit

TILING Lutheran Church of the Holy Spirit SECTION 093000 - TILING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Porcelain tile. 2. Tile backing panels. 3. Metal edge strips. 1.2 SUBMITTALS A. Product Data: For each type of product indicated.

More information

TILE TILE

TILE TILE 09300 - TILE 09300-1 PART ONE: GENERAL 1.1 Description TILE 1.1.1 Work of this Section, as shown or specified, shall be provided by the Interior Contractor and shall be in accordance with the requirements

More information

Sections Paver Tiling Guide Specification; for installation of Marion Ceramics, Thin Brick Tiles; Flooring, Veneer

Sections Paver Tiling Guide Specification; for installation of Marion Ceramics, Thin Brick Tiles; Flooring, Veneer Sections 09 30 19 Paver Tiling Guide Specification; for installation of Marion Ceramics, Thin Brick Tiles; Flooring, Veneer PART 1 GENERAL 1.1 SUMMARY A. Related Documents: General and Supplementary Conditions

More information

SECTION CERAMIC and QUARRY TILE

SECTION CERAMIC and QUARRY TILE PART 1 GENERAL 1.1 RELATED DOCUMENTS SECTION 09 30 13 CERAMIC and QUARRY TILE A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 specification

More information

SECTION CERAMIC TILE

SECTION CERAMIC TILE SECTION 09300 CERAMIC TILE PART 1 GENERAL 1.1 SCOPE A. Drawings and general provisions of the Contract, including General and Supplementary General Conditions, Division 00 & 01 Specification Sections,

More information

SECTION CONCRETE PAVING SLABS SET IN MORTAR

SECTION CONCRETE PAVING SLABS SET IN MORTAR SECTION 32 14 13.16 CONCRETE PAVING SLABS SET IN MORTAR (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs mortared to a concrete base and grouted joints

More information

Finish Flooring- Hard Flooring Materials

Finish Flooring- Hard Flooring Materials Finish Flooring- Hard Flooring Materials The most desirable types of flooring by designers and building owners Types of Hard Flooring Materials Concrete Stone Ceramic Tiles Quarry Tiles Bricks and Brick

More information

ADDENDUM NO. 6. Acknowledge receipt of this Addendum in the space provided in the Proposal Form. Failure to do so may disqualify the Bidder.

ADDENDUM NO. 6. Acknowledge receipt of this Addendum in the space provided in the Proposal Form. Failure to do so may disqualify the Bidder. PROJECT: Lovington Fire Station # 2 WDG PROJECT NO: 445-01 DATE: July 120, 2018 ADDENDUM NO. 6 NOTICE TO PROPOSERS: This Addendum forms a part of the Contract Documents and modifies the original Specifications

More information

A. Product Data: For each type of tile, mortar, grout, and other products specified.

A. Product Data: For each type of tile, mortar, grout, and other products specified. SECTION 09310 - CERAMIC TILE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections,

More information

Division 09 Finishes Section Ohio Utilities Protection Service New Office Building Bid Package B TILING

Division 09 Finishes Section Ohio Utilities Protection Service New Office Building Bid Package B TILING SECTION 09 30 00 TILING PART 1 GENERAL 1.1 SUMMARY A. Section includes: 1. Porcelain Paver Tile. 2. Mortars and Grouts. 3. Floor Preparation Materials. B. Related Sections: Documents relating to the work

More information

SECTION GRANITE TILING

SECTION GRANITE TILING SECTION 09 30 33.13 GRANITE TILING This guide specification utilizes recommendations and formats contained in references of the Construction Specifications Institute (CSI), including the CSI Practice Guides

More information

SECTION MORTAR-BED STONE TILING [Interior Applications] [SECTION ]

SECTION MORTAR-BED STONE TILING [Interior Applications] [SECTION ] (Specifier Note: The purpose of this guide specification is to assist the specifier in correctly specifying Porphyry Stone Pavers. The specifier needs to edit these guide specifications to fit the needs

More information

Construction Specification

Construction Specification PART 1 - GENERAL 1.01 SUMMARY A. Furnish all labor, materials, tools and equipment required for completing tile work and related items indicated on the drawings and herein specified. B. Related work specified

More information

WOOD FLOORING WOOD FLOORING

WOOD FLOORING WOOD FLOORING 09550 - WOOD FLOORING 09550-1 PART ONE: GENERAL 1.1 Description WOOD FLOORING 1.1.1 Work in this Section, as shown or specified, shall be provided by the Interior Contractor and shall be in accordance

More information

SECTION TILING

SECTION TILING SECTION 09 30 00 TILING PART 1 - GENERAL 1.1 SUMMARY A. Section includes tile as indicated on new surfaces and as specified. 1.2 SUBMITTALS A. Samples: 1. Submit samples of colors and sizes of tile. B.

More information

SECTION STONE FLOORING

SECTION STONE FLOORING PART 1 - GENERAL 1.1 DESCRIPTION: SECTION 09 63 40 STONE FLOORING SPEC WRITER NOTE: Delete // // if not applicable to project. Also delete any other item or paragraph not applicable in the section and

More information

A. Module Size: Actual tile size (minor facial dimension as measured per ASTM C 499) plus joint width indicated.

A. Module Size: Actual tile size (minor facial dimension as measured per ASTM C 499) plus joint width indicated. SECTION 093000 - TILING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Special Conditions and Division 01 Specification Sections, apply

More information

SECTION ORNAMENTAL ALUMINUM RAILING

SECTION ORNAMENTAL ALUMINUM RAILING SECTION 05730 ORNAMENTAL ALUMINUM RAILING PART 1 GENERAL 1.1 SECTION INCLUDES A. Decorative Wire Rope Railing 1.2 RELATED SECTIONS A. Section 03300 Cast-In-Place Concrete: Placement of sleeves cast in

More information

Editing notes to assist users are separated from specification text by rows of asterisks. Delete these notes prior to final printing.

Editing notes to assist users are separated from specification text by rows of asterisks. Delete these notes prior to final printing. SECTION 09635 LIMESTONE FLOORING This guide specification has been prepared by TexaStone Quarries LLC to assist design professionals in the preparation of a specification section covering cut limestone

More information

SECTION SUBSURFACE PREPARATION FOR FLOOR FINISHES

SECTION SUBSURFACE PREPARATION FOR FLOOR FINISHES PART 1 - GENERAL 1.1 DESCRIPTION SECTION 09 05 16 SUBSURFACE PREPARATION FOR FLOOR FINISHES SPEC WRITER NOTES: 1. Delete between // // if not applicable to project. Also delete any other item or paragraph

More information

DIVISION 9 - FINISHES

DIVISION 9 - FINISHES Part 1 - General 1.01 Work Included: A. All materials, labor services and incidentals necessary for the completion of this section of the work. 1.02 Quality Assurance: A. Standards: 1. Tile Council of

More information

BuildingName The Description of the Project P DOCUMENTS

BuildingName The Description of the Project P DOCUMENTS ARCHITECTURE, ENGINEERING AND CONSTRUCTION P00000000 0000 DOCUMENTS ARCHITECTURE & ENGINEERING 326 East Hoover, Mail Stop B Ann Arbor, MI 48109-1002 Phone: 734-764-3414 Fax: 734-936-3334 SPECIFICATION

More information

SECTION ORNAMENTAL ALUMINUM RAILING

SECTION ORNAMENTAL ALUMINUM RAILING SECTION 05730 ORNAMENTAL ALUMINUM RAILING PART 1 GENERAL 1.1 SECTION INCLUDES A. Aluminum Pipe Railing 1.2 RELATED SECTIONS A. Section 03300 Cast-In-Place Concrete: Placement of sleeves cast in concrete.

More information

Superior Aluminum Guide Specification 10/4/2016 Non-Welded Aluminum Pipe Railing

Superior Aluminum Guide Specification 10/4/2016 Non-Welded Aluminum Pipe Railing The following specification has been developed by: Superior Aluminum Products 555 East Main Street Russia, Ohio 45363-0430 to assist Architects and Designers in the specification of Non Welded Concealed

More information

SECTION PAVER TILE

SECTION PAVER TILE SECTION 09340 PAVER TILE PART 1 - GENERAL 1.01 DESCRIPTION: A. This section specifies providing paver tiles, typically in patron areas as shown. These tiles are noted on Drawings as: 1. Paver tile. 2.

More information

Chevy Chase Club June 2, 2008 Bowie Gridley Architects

Chevy Chase Club June 2, 2008 Bowie Gridley Architects SECTION 093033 - STONE TILING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SECTION CERAMIC TILING

SECTION CERAMIC TILING SECTION 09 3013 CERAMIC TILING PART 1 - GENERAL 1.1 SUMMARY A. Includes But Not Limited To: 1. Furnish and install ceramic tile and tile setting materials and accessories as described in Contract Documents.

More information

Uncoupling Membranes for Tile Installations. Technical White Paper UNCOUPLING MEMBRANES

Uncoupling Membranes for Tile Installations. Technical White Paper UNCOUPLING MEMBRANES Uncoupling Membranes for Tile Installations By Steve Taylor Director of Architecture and Technical Marketing, Custom Building Products Have you ever wondered when and why an uncoupling mat should be installed

More information

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows: ADDENDUM NO. 1 TO THE DRAWINGS AND SPECIFICATIONS FOR THE New Dishman-McGinnis Elementary School Bowling Green Independent Schools Bowling Green, Kentucky BG 12-256 RTA 1209 March 11, 2013 To All Plan

More information

SECTION LATEX-MODIFIED MEDIUM BED MORTAR

SECTION LATEX-MODIFIED MEDIUM BED MORTAR SECTION 09305.24 LATEX-MODIFIED MEDIUM BED MORTAR This product guide specification can be used to specify Hydroment Big Tile & Stone Mortar, a latex-modified, medium bed mortar designed for setting large

More information

Installation of Large Format Tile & Stone

Installation of Large Format Tile & Stone Installation of Large Format Tile & Stone TDS 193 Use of Large Format Tile and Stone Twenty to twenty five years ago choosing tile was simple. Floor tile was typically 8 x 8 (200mm x 200mm) and wall tile

More information

A. Prepare formwork shop drawings using qualified professional engineer. Include detail of fabrication, assembly, and support of formwork.

A. Prepare formwork shop drawings using qualified professional engineer. Include detail of fabrication, assembly, and support of formwork. DIVISION 03 CONCRETE 03 0100 MAINTENANCE OF CONCRETE 03 0505 UNDER SLAB VAPOR BARRIER A. Sheet vapor retarder shall be polyethylene sheet, ASTM D 4397, 10 mils thick minimum. Consult with Facilities Management

More information

STEAM SHOWER / ROOM; WOOD OR METAL STUDS Wood or Metal Studs Cement Backer Board Walls, Mortar Bed Floor Ceramic Tile

STEAM SHOWER / ROOM; WOOD OR METAL STUDS Wood or Metal Studs Cement Backer Board Walls, Mortar Bed Floor Ceramic Tile STEAM SHOWER / ROOM; WOOD OR METAL STUDS Wood or Metal Studs Cement Backer Board Walls, Mortar Bed Floor Ceramic Tile MAPEI: MSR614 TCNA: SR614-13 TTMAC: 321SR-B SLOPED CEILING 2" (50 mm) PER FOOT CEMENT

More information

Selecting and Specifying Ceramic Tile with ANSI and ISO Standards

Selecting and Specifying Ceramic Tile with ANSI and ISO Standards Selecting and Specifying Ceramic Tile with ANSI and ISO Standards Learning Objectives Review Industry Standards and Resources ANSI - American National Standards Institute ISO International Standards Organization

More information

SECTION TILING

SECTION TILING SECTION 09 30 00 - TILING PART 1 PRODUCTS 1.01 SUMMARY A. Section Includes: 1. Floor and Wall Tile and Accessories 2. Crack Suppression Membrane 3. Leveling Coat, Mortar, Grouts, and Adhesives 4. Thresholds

More information

for Mortar-Set Concrete Tiling Installations

for Mortar-Set Concrete Tiling Installations The following specification refers to the Stepstone, Inc. product known as: Large Scale CalArc Pavers for Mortar-Set Concrete Tiling Installations Large Scale CalArc Pavers are part of the California Architectural

More information

Specification Note: For the name of the local Robbins Performing Arts representative or dealer, call

Specification Note: For the name of the local Robbins Performing Arts representative or dealer, call ROBBINS PERFORMING ARTS DANZAIRE BATTEN FLOOR WITH VINYL Page 1 of 6 Specification Note: The following specifications call out the material and default installation requirements necessary for the floor

More information

SHOWER RECEPTORS Solid Backing, Bonded Waterproof Membrane Intergraded Bonding Flange Ceramic Tile

SHOWER RECEPTORS Solid Backing, Bonded Waterproof Membrane Intergraded Bonding Flange Ceramic Tile SHOWER RECEPTORS Solid Backing, Bonded Waterproof Membrane Intergraded Bonding Flange Ceramic Tile MAPEI: MB422 TCNA: B422-13 TTMAC: 326DR-A SOLID BACKING CERAMIC TILE 1). GROUT 2). CEMENTITIOUS BOND COAT

More information

Tile on Existing. Viewpoint

Tile on Existing. Viewpoint Viewpoint Tile on Existing Exterior Reinforced Concrete BalconieS By Steven C. Turner Exterior reinforced concrete balconies are often covered by tile set in mortar beds with grouted joints. These installations

More information

DIVISION 03 CONCRETE. Number CONCRETE

DIVISION 03 CONCRETE. Number CONCRETE 03 00 00 CONCRETE 03 10 00 CONCRETE FORMING AND ACCESSORIES 03 11 00 Concrete Forming 03 11 13 Structural Cast-in-Place Concrete Forming 03 11 16 Architectural Cast-in-Place Concrete Forming 03 15 00 Concrete

More information

Concrete Restoration.

Concrete Restoration. Concrete Restoration www.specchemllc.com Repair Products Duo Patch GREENCONSCIOUS Two-component, polymer-modified concrete repair mortar A two-component, polymer modified concrete repair mortar with integral

More information

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES. Chapter 10

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES. Chapter 10 CONTENTS 10.1 PLASTERWORK 10.2 SECOND AND THIRD FIX FINISHES 283 Chapter 10 FUNCTIONAL REQUIREMENTS FUNCTIONAL REQUIREMENTS 10.1 PLASTERWORK Workmanship i. All workmanship must be within the tolerances

More information

SECTION GYPSUM BOARD ASSEMBLIES

SECTION GYPSUM BOARD ASSEMBLIES SECTION 09260 GYPSUM BOARD ASSEMBLIES PART 1 GENERAL 1.1 SUMMARY A. Provide gypsum board assemblies. 1.2 SUBMITTALS A. Product Data: Submit manufacturer's product data and installation instructions for

More information

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK ND AND 3 RD FIX FINISHES

CHAPTER 10: Finishes CONTENTS 10.1 PLASTERWORK ND AND 3 RD FIX FINISHES CONTENTS 10.1 PLASTERWORK 10.2 2 ND AND 3 RD FIX FINISHES FUNCTIONAL REQUIREMENT 10.1 Plasterwork Workmanship Design Technical Manual TS-011-09-010412 i. All workmanship must be within defined tolerances

More information

ECO OUTDOOR INSTALLATION TIPS FLOORING COBBLESTONES

ECO OUTDOOR INSTALLATION TIPS FLOORING COBBLESTONES ECO OUTDOOR INSTALLATION TIPS FLOORING COBBLESTONES FLOORING WALLING FURNITURE WWW.ECOOUTDOORUSA.COM Installations Tips Please note these tips are guides only and should be used in addition to the relevant

More information

Multi-Institutional Academic Health Science and Research Center. See attached PCIS Project Addendum Number 2 for the project as a whole.

Multi-Institutional Academic Health Science and Research Center. See attached PCIS Project Addendum Number 2 for the project as a whole. Skanska USA Civil Midwest, Inc. Multi-Institutional Academic Health Science and Research Center 413 Walnut Street Evansville, IN 47708 Phone 812 401 1980 Web www.skanska.com Bid Package Addendum No.1 Date

More information

DIVISION 03 CONCRETE CONCRETE REINFORCING Reinforcing Steel Welded Wire Fabric Reinforcing Fibrous Reinforcing

DIVISION 03 CONCRETE CONCRETE REINFORCING Reinforcing Steel Welded Wire Fabric Reinforcing Fibrous Reinforcing 03 00 00 CONCRETE 03 10 00 CONCRETE FORMING AND ACCESSORIES 03 11 00 Concrete Forming 03 11 13 Structural Cast in Place Concrete Forming 03 11 16 Architectural Cast in Place Concrete Forming 03 15 00 Concrete

More information

Sample Specification

Sample Specification Sample Specification Enclosed is a template for you to use in preparing a final, quarry tile specification incorporating products manufactured by Metropolitan Ceramics, by Ironrock Capital, Inc. Quarry

More information

Continuing Education Courses

Continuing Education Courses 2014 Continuing Education Courses National Terrazzo & Mosaic Association AGGREGATE STUNNING Objective: How does aggregate stunning manifest, what is the cause and how to avoid this problem will be discussed

More information

Sample Specifications

Sample Specifications Sample Specifications Below is a template for you to use in preparing a final, quarry tile specification incorporating products manufactured by Metropolitan Ceramics, by Ironrock Capital, Inc. Quarry tile

More information

Mapeguard UM. Underlayment membrane for ceramic and stone tile

Mapeguard UM. Underlayment membrane for ceramic and stone tile Mapeguard UM Underlayment membrane for ceramic and stone tile Mapeguard UM Mapeguard UM is a uniquely engineered, tri-layered underlayment membrane that combines crack suppression, waterproofing, vapor

More information

DIVISION 03 CONCRETE. Section Title Number CONCRETE

DIVISION 03 CONCRETE. Section Title Number CONCRETE 03 00 00 CONCRETE ***ALL CONCRETE HARDSCAPE & RELATED SITE CONCRETE MUST ALSO ADHERE TO THE 2015 LANDSCAPE MASTER PLAN AS WELL AS THE DIVISION 3 TECHNICAL STANDARDS. THE LANDSCAPE MASTER PLAN CAN BE FOUND

More information

INTERIOR WALLS OVER SOLID BACKING

INTERIOR WALLS OVER SOLID BACKING INTERIOR WALLS OVER SOLID BACKING Mortar Bed (One-Coat Method) Stone Tile MAPEI: MW222-Stone TCNA: W222-15-Stone TTMAC: N/A Version: 2015 SOLID BACKING: WOOD, PLASTER, MASONRY, OR GYPSUM BOARD STONE TILE

More information

RECTIFICATION OF WATERPROOFING IN AGED SWIMMING POOLS ON ROOFTOPS & ABOVE CAR PARKS WITH FRP. Jeda Pte Ltd Tel:

RECTIFICATION OF WATERPROOFING IN AGED SWIMMING POOLS ON ROOFTOPS & ABOVE CAR PARKS WITH FRP. Jeda Pte Ltd Tel: RECTIFICATION OF WATERPROOFING IN AGED SWIMMING POOLS ON ROOFTOPS & ABOVE CAR PARKS WITH FRP Jeda Pte Ltd Tel: 6275 0040 http://jeda.com.sg ISSUES WITH LEAKING SWIMMING POOLS Most swimming pools in condominiums

More information

SECTION EPOXY TERRAZZO

SECTION EPOXY TERRAZZO SECTION 09 66 23.16 EPOXY TERRAZZO THIS GUIDE SPECIFICATION HAS BEEN PREPARED BY THE NATIONAL TERRAZZO AND MOSAIC ASSOCIATION, INC., AND IS DISTRIBUTED FOR USE BY ITS MEMBERS AND DESIGN PROFESSIONALS.

More information

Narrow Modular Pavers (NMP) for Mortar-Set Concrete Tiling Installations

Narrow Modular Pavers (NMP) for Mortar-Set Concrete Tiling Installations The following specification refers to the Stepstone, Inc. product known as: Narrow Modular Pavers (NMP) for Mortar-Set Concrete Tiling Installations Narrow Modular Pavers are part of the California Architectural

More information

Section Pedestrian Traffic Coatings

Section Pedestrian Traffic Coatings Guide Specification MiraFlex II - For Concrete Surfaces Pedestrian Deck and Waterproofing System (Specification writer shall choose the most appropriate section that applies to a given scope of work, including

More information

SECTION UNIT MASONRY

SECTION UNIT MASONRY SECTION 04200 UNIT MASONRY PART 1 GENERAL 1.01 SUMMARY A. Furnish labor, materials, and equipment and perform functions required in the installation and maintenance of the work covered by this Section.

More information

SECTION CEMENT BOARD SUPPORTED ADHERED MASONRY VENEER. 2. Installation materials including adhesives, mortars, and pointing mortars.

SECTION CEMENT BOARD SUPPORTED ADHERED MASONRY VENEER. 2. Installation materials including adhesives, mortars, and pointing mortars. (Specifier Note: The purpose of this guide specification is to assist the Specifier in correctly specifying cement board supported adhered masonry. The Specifier needs to edit these guide specifications

More information

Contract18. Vitrified paving FLAT ROOF BALCONY ROOF TERRACE DISPLAY AREA

Contract18. Vitrified paving FLAT ROOF BALCONY ROOF TERRACE DISPLAY AREA Contract18 Vitrified paving FLAT ROOF BALCONY ROOF TERRACE DISPLAY AREA Contract 18 Vitrified Paving Installation Methods Installation Method 1 Dry Installation Using Our Range of Paving Support Pads Installation

More information

SPECIFICATION FOR INSTALLATION OF WALKER ZANGER KAZA CONCRETE TILES ONTO VARIOUS SUBSTRATES

SPECIFICATION FOR INSTALLATION OF WALKER ZANGER KAZA CONCRETE TILES ONTO VARIOUS SUBSTRATES INSTALLATION INSTRUCTIONS SPECIFICATION FOR INSTALLATION OF WALKER ZANGER KAZA CONCRETE TILES ONTO VARIOUS SUBSTRATES QUALITY REQUIREMENTS All work to be carried out in accordance with TCNA (Tile Council

More information

CONCRETE STAIRS Note:

CONCRETE STAIRS Note: With the increased use of concrete tile and stone over the past decade, there has been an increase in demand for installing concrete tile or stone on stairs. Historically, these types of installations

More information

SECTION WOOD AND ATHLETIC FLOORING. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION.

SECTION WOOD AND ATHLETIC FLOORING. A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. SECTION 096466 PART 1 GENERAL 1.01 GENERAL REQUIREMENTS A. PART A and DIVISION 1 of PART B are hereby made a part of this SECTION. B. Examine all conditions as they exist at the project prior to submitting

More information

SECTION CERAMIC TILING

SECTION CERAMIC TILING SECTION 093013 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to

More information

C. Module Size: Actual tile size plus joint width indicated.

C. Module Size: Actual tile size plus joint width indicated. PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

More information

Colphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate

Colphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate Colphene BSW Training and Application Guide Colphene BSW Waterproofing Membrane. 1. Prepare substrate Substrate must be structurally sound. Surface must be free of voids, spalled areas, loose aggregate,

More information

Gypsum Board Shaft-Wall Assemblies Gypsum board shaft-wall assembly for elevator and mechanical shafts over 2 stories.

Gypsum Board Shaft-Wall Assemblies Gypsum board shaft-wall assembly for elevator and mechanical shafts over 2 stories. 09 00 00 - FINISHES 09 00 00 General Information Architects, in the design of project specific building systems, shall consider the unique characteristics of the generally hot-humid environment of Conway,

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 096623 - RESINOUS MATRIX TERRAZZO FLOORING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

2018 Flooring Specification - Tile Set Method TECTURA DESIGNS CEMENT TERRAZZO TILES

2018 Flooring Specification - Tile Set Method TECTURA DESIGNS CEMENT TERRAZZO TILES 2018 Flooring Specification - Tile Set Method 09300 TECTURA DESIGNS CEMENT TERRAZZO TILES PART 1 - GENERAL 1.1 INTRODUCTION A. Tectura Designs, Terrazzo Tiles are to be installed following the tile setting

More information

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION ARDEX GUIDE SPECIFICATION ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) Cast-In-Place Concrete to Receive the ARDEX Concrete Management Systems including ARDEX Self-Leveling Underlayments SECTION 03 30 00

More information

THIN PORCELAIN TILE TPT

THIN PORCELAIN TILE TPT THIN PORCELAIN TILE TPT TPT At the end of this program, participants will be able to: Understand what is a Thin Porcelain Tile (TPT) Know how (TPT) is made and its benefits Identify the various types of

More information

SECTION UNIT PAVERS

SECTION UNIT PAVERS PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following: 1. Concrete pavers. 2. Detectable warning pavers. 3. Warning stripe pavers. 1.2 SUBMITTALS A. Product Data: For the following: 1. Pavers.

More information

Specification Note: For the name of the local Robbins Performing Arts representative or dealer, call

Specification Note: For the name of the local Robbins Performing Arts representative or dealer, call ROBBINS PERFORMING ARTS ÉLAN BASKETWEAVE FLOOR WITH VINYL Page 1 of 6 Specification Note: The following specifications call out the material and default installation requirements necessary for the floor

More information

Kolorines Glass Mosaic Tiles Project Specification

Kolorines Glass Mosaic Tiles Project Specification Kolorines Glass Mosaic Tiles Project Specification SUGGESTED SPECIFICATION Glass Mosaic Tile Installation for Swimming Pools NOTES TO SPECIFIER: 1. Specify PremiumPlus Thin-Set mixed with CustomFlex Additive

More information

THIN PORCELAIN TILE TPT

THIN PORCELAIN TILE TPT THIN PORCELAIN TILE TPT TPT At the end of this program, participants will be able to: Understand what is a Thin Porcelain Tile (TPT) Know how (TPT) is made and its benefits Identify the various types of

More information

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1

SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1 SAN FRANCISCO UNIFIED SCHOOL DISTRICT 2006 PROPOSITION A BOND PROGRAM 300 SENECA NEW ACADEMIC CAMPUS ADDENDUM NO. 1 PROJECT: 300 Seneca New Academic Campus DATE: September 23, 2013 300 Seneca Ave., S.F.,

More information

CTIOA FIELD REPORT

CTIOA FIELD REPORT CERAMIC TILE INSTITUTE OF AMERICA, INC. 12061 Jefferson Blvd., Culver City, CA 90230-6219 CTIOA FIELD REPORT 2004-6-4 SUBJECT: UNDERSTANDING MOVEMENT JOINTS IN CONCRETE WORK By John Gallup, CTC - Movement

More information

SECTION EPOXY TERRAZZO TILE WITH RECYCLED GLASS MATRIX

SECTION EPOXY TERRAZZO TILE WITH RECYCLED GLASS MATRIX GlassPLANK GUIDE SPECIFICATION Manufacturer: GLASS RECYCLED LLC 2939 Irving Blvd Suite 305 Dallas TX 75247 (888) 523-7894 toll free voice www.glassrecycled.com SECTION 09 66 18 EPOXY TERRAZZO TILE WITH

More information

Information regarding the Application for Approval to 1. Install Interior or Lanai Tile 2. Install Hard Surface Flooring

Information regarding the Application for Approval to 1. Install Interior or Lanai Tile 2. Install Hard Surface Flooring BAY HARBOR CLUB OF BONITA BEACH CONDOMINIUM ASSOCIATION, INC. c/o Towne Properties 1016 Collier Center Way, Suite 102 Naples, FL 34110 (239) 596-1031 Fax (239) 596-1082 Information regarding the Application

More information

Horizontal Surfaces. An excerpt from the Dimension Stone Design Manual, Version 7.2 (July 2011)

Horizontal Surfaces. An excerpt from the Dimension Stone Design Manual, Version 7.2 (July 2011) Horizontal Surfaces An excerpt from the Dimension Stone Design Manual, Version 7.2 (July 2011) Produced and Published by the Marble Institute of America 380 East Lorain Oberlin, Ohio 44074 Telephone: 440-250-9222

More information

California Architectural Pavers for Mortar-Set Concrete Tiling Installations

California Architectural Pavers for Mortar-Set Concrete Tiling Installations The following specification refers to the Stepstone, Inc. product known as: California Architectural Pavers for Mortar-Set Concrete Tiling Installations Stepstone, Inc. also manufactures California Architectural

More information

LAYOUT CONSIDERATIONS

LAYOUT CONSIDERATIONS 1-800-447-2838 Installation Instructions Vanishing Lid System Layout Cover-Pools Vanishing Lid design is an adjustable, tray-support system for any kind or style of deck material you prefer to use for

More information

SECTION MODIFIED BITUMINOUS MEMBRANE ROOFING Peel & Roof

SECTION MODIFIED BITUMINOUS MEMBRANE ROOFING Peel & Roof SECTION 07550 MODIFIED BITUMINOUS MEMBRANE ROOFING Peel & Roof This section is based on the products of MFM Building Products Corp., which is located at: 525 Orange St. P. O. Box 340 Coshocton, OH 43812

More information

ADDENDUM NO. 2 Consisting of 3 pages and Attachments

ADDENDUM NO. 2 Consisting of 3 pages and Attachments 10404-125 Street, Edmonton, AB. T5N 1T2 Tel: 780.455.5975 Fax: 780.454.2397 info@cdyarchitect.com ADDENDUM NO. 2 Consisting of 3 pages and Attachments PROJECT: Maina Centre Ville Phase II, Beaumont, Alberta

More information

EPOXY TERRAZZO 1 REV. 8/02

EPOXY TERRAZZO 1 REV. 8/02 PART 1 - GENERAL GUIDE SPECIFICATIONS section 9400 EPOXY THINSET TERRAZZO (Without A Crack Suppression Membrane) REVISED MAY 2003 1.1 RELATED DOCUMENTS A. Section includes thin-set epoxy terrazzo flooring

More information

PRESTON HEALTH SERVICES ARCHITECT'S NO MITCHELL-HOLLINGSWORTH NURSING & REHAB ADPH #B

PRESTON HEALTH SERVICES ARCHITECT'S NO MITCHELL-HOLLINGSWORTH NURSING & REHAB ADPH #B SECTION 09 3000 - TILING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SECTION PORTLAND CEMENT TERRAZZO FLOORING

SECTION PORTLAND CEMENT TERRAZZO FLOORING PART 1 - GENERAL 1.1 DESCRIPTION SECTION 09 66 13 SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Delete between //---// if not applicable to project. Also delete any other item or paragraph

More information