1 HORIZONTAL DIRECTIONAL DRILLING: NEW ERA FOR UNDERGROUND UTILITIES Siddharth J. Jariwala 1, Prof. Jayeshkumar Pitroda 2, Prof. J. J. Bhavsar 3 1 P. G. Student (C.E & M), B.V.M Engineering College, Vallabh Vidhyanagar, siddharthjariwala510@gmail.com 2 Assistant Professor and Research Scholar, Civil Engineering Department, B.V.M. Engineering College, Vallabh Vidyanagar-Gujarat-India, jayesh.pitroda@bvmengineering.ac.in 3 Associate Professor, P.G. Cordinator of Construction Engineering & Management, B.V.M Engineering College, Vallabh Vidyanagar-Gujarat-India, jaydev_2004@yahoo.co.in ABSTRACT: Horizontal directional drilling (HDD) was pioneered in the United States for an innovative road boring contractor who successfully completed a 183 m river crossing using a modified rod pushing a tool with no steering capability. Horizontal Directional Drilling (HDD) is defined as A steerable system for the installation of pipes, conduits, and cables in a shallow arc using a surfaced launched drilling rig. Traditionally HDD is applied to large scale crossings such as rivers in which a fluid filled pilot hole is drilled without rotating the drill string, and this is then enlarged by a wash over the pipe and back reamer to the size required by the product. It is currently an efficient, safe, cost effective method for highway bores and is the current industry standard for Trenchless technology for bores between 2 and 48-inch diameters. The main objective is to install such services without using traditional trenching methods, helping to avoid any unnecessary environmental impact and provide added security. This paper focus on new era for construction sector of underground utilities in India. Keywords: Horizontal Directional Drilling, Environmental, Underground, Utilities INTRODUCTION Horizontal Directional Drilling (HDD) is defined as A steerable system for the installation of pipes, conduits, and cables in a shallow arc using a surfaced launched drilling rig. Traditionally HDD is applied to large scale crossings such as rivers in which a fluid filled pilot hole is drilled without rotating the drill string, and this is then enlarged by a wash over the pipe and back reamer to the size required by the product. This technology has been in existence since the 1970 s. It is currently an efficient, safe, cost effective method for highway bores and is the current industry standard for Trenchless technology for bores between 2 to 48-inch in diameters. Horizontal directional drilling(hdd) is also known as Directional Boring. HDD is used when trenching or excavating is not practical. HDD is used for installing infrastructure such as telecommunications and power cable conduits, water lines, sewer lines, gas lines, oil lines, product pipelines, and environmental remediation casings. The main objective is to install such services without using traditional trenching methods, helping to avoid any unnecessary environmental impact and provide added security. 1

2 Figure 1: Entry Pit Figure 2: Exit Pit COMPONENTS A directional drill rig sized for the job at hand. Drill rods linked together to form a drill string for advancing the drill bit and for pulling back reamers and products. A transmitter/receiver for tracking and recording the location of the drill and product. A tank for mixing and holding drilling fluid. A pump for circulating the drilling fluid. PROCESS OF HDD Figure 3: Components of Horizontal Directional Drilling (HDD) Stage 1 :- Site Investigation and Design Stage 2:-Pilot Hole Drilling Stage 3:-Hole Enlargement Stage 4:- Pullback 2

3 Stage 1:- Site Investigation and Design Project designs start with the gathering of necessary information. This information includes the, site survey including locations of existing pipelines and services, and a Geotechnical site investigation. This will determine the tools necessary to successfully drill the crossing and determine the design. Stage 2:- Pilot Hole Drilling Figure 4: Site Investigation and Design The pilot hole is drilled from the entry point to the exit point following a previously designed profile and alignment. The drilling tools and rig equipment selected for each job is largely determined based on the results of the Geotechnical investigation and the size of the crossing (length and diameter). During the pilot hole drilling, a directional guidance system is used to navigate the pilot hole along its pre-designed profile. The entry angle of the drill string is typically 8 to 16 degrees. The drill string, is advanced by a combination of rotation torque and thrust supplied by the rig. So that it allows the operator to change the direction to navigate the pilot hole along its pre-designed profile. There are many types of bits designed to navigate through different types of soil, from clays and sands to rock. Most drill bits have a slant-face. 3

4 To move in a straight line, the rig operator both rotates and pushes the drill string. To change direction, the operator, stops rotating the drill string and pushes the string. The path will change in the direction that the bit s slant-face is pointing. On-board controls allow the operator to monitor the orientation of the bit and the change in the general direction of the bore. A walkover tracking system is used to help guide and monitor the location of the bore. The system is comprised of a transmitter and receiver. The transmitter emits a continuous magnetic signal, which is picked up by a portable handheld receiver. Stage 3:- Hole Enlargement Figure 5: Pilot Hole Drilling In small diameter crossings the pipeline may be directly installed in the pilot hole. However in most cases pilot hole enlarging, known as prereaming, will be necessary. Pre-reaming is required to provide a bore diameter large enough so that the pipeline can be installed in the drilled crossing. Based on the final desired diameter and soil conditions this process may include one or more stages. Figure 6: Hole Enlargement 4

5 Stage 4:- Pullback Once the drilled hole has been enlarged to the required diameter and cleaned adequately, the pipeline is installed. When applicable, the pipeline is preassembled in a single string and placed on rollers prior to pullback. For pullback, a reamer is connected to the drill pipe. Behind the reamer a swivel is connected allowing the drill pipe to rotate the reamer without allowing the transfer of torque to the product pipe. The drill pipe is then pulled back towards the entry point until the pipeline is fully installed. WHY CHOOSE HDD? Figure 7: Pullback 5

6 Trenchless Method For Establishing New Lines : In the past, the only way to establish a new line was through expensive and damaging trench work. With directional boring you can get the advantages of Trenchless methods where a preexisting line is either unavailable or needs to be relocated. Saves Money : A significant portion of the cost of a new line goes into digging for a new line and putting back excavated material. Tap into significant cost savings and skip the damage that comes with traditional methods used to establish new lines. Saves Time : Drilling not only saves money, but it also creates a significant time savings. Without trenches to dig or material to put back, the completion time on projects using drilling is significantly less than with conventional methods. MAJOR SECTORS OF HDD The HDD industry is divided into three major sectors according to their typical application areas. Large-diameter HDD (maxi-hdd) Medium-diameter HDD (midi-hdd) Small-diameter HDD (mini-hdd, also called guided boring) System Description Product Pipe Diameter Maxi-HDD 600-1,200 mm (24-48 in) Midi-HDD mm (12-24 in) Depth Range 61 m (200 ft) 23 m (75 ft) Table 1 Typical Application Areas Drive Length 1,818 m (6,000 ft) 274 m (900 ft) Torque kn-m kn-m Thrust/ Pullback Machine Weight (Including truck) Typical Application 445 kn 267 kn River, Highway crossings kn 160 kn Under rivers and roadways Mini-HDD mm (2-12 in) ADVANTAGES OF HDD 4.5 m (15 ft) 182 m (600 ft) 1.3 kn-m Source: (Iseley and Gokhale, NCHRP Synthesis 1997) 89 kn 80 kn Telecom and Power cables, Gas lines Avoid damage to your building, landscaping and Hardscaping. Trenchless option for establishing a new line. Significant cost savings compared to conventional line installation methods. Shorter completion times & safer for the environment. Less invasive than the traditional open cut. Surface disturbance is minimized. More secure than above ground or trenched installations. Can make deep installations and avoid surface obstacles such as rivers, railways, or highways. 6

7 DISADVANTAGES OF HDD Special equipment and very high degrees of operation skill is required. As the cost of the equipment and the operation are high, bore length should be sufficient in order for it to be economical. Mainly steel pipe is being installed by the method. CONCLUSIONS In the present era of new developments, Trenchless technology is quite useful. The HDD is such a type of Trenchless technology which has the benefit of significant cost saving compared to the conventional line installation methods. Though the greater initial cost of special equipment and greater degree of operational skill requirement, this method is faster and avoids damage to an existing structure and operation time is very less, so very good alternative to many conventional time consuming methods. ACKNOWLEDGEMENT The Authors thankfully acknowledge to Dr. C. L. Patel, Chairman, Charutar Vidya Mandal, Er.V.M.Patel, Hon.Jt. Secretary, Charutar Vidya Mandal, Mr. Yatinbhai Desai, Jay Maharaj construction, Dr. F.S.Umrigar, Principal, B.V.M. Engineering College, Dr. L.B.Zala, Head and Professor, Civil Engineering Department, Dr. A. K. Verma, Head and Professor, Structural Engineering Department, B.V.M. Engineering College, Vallabh Vidyanagar, Gujarat, India for their motivations and infrastructural support to carry out this research. REFERENCES Diamond, W. P. and Oyler, D. C., 1986, "Direction Drilling for Degasfication of Coalbeds in Advance of Mining", in Methane Control Research: Summary of Results, , U.S. Bureau of Mines Bulletin 687, pp Guidelines,planning horizontal directional drilling for pipeline construction,,canadian association of petroleum producers(capp), CAPP publication Diamond, W. P., Bodden, W. R., Zuber, M. D., and Schraufnagel, R. A., 1989, "Measuring the Extent of Coalbed Gas Drainage after 10 Years of Production at the Oak Grove Pattern, Alabama", in Proceedings of the 1989 Coalbed Methane Symposium, April 17-20, 1989, Tuscaloosa, Alabama, pp Directional Crossing Contractors Association (DCCA). (1994). Guidelines for a Successful Directional Crossing Bid. Dr. Neeraja Lugani Sethi, Pre- Requisites for Trenchless Technology. Civil Engineering and Construction Review October Iseley, T. and Gokhale, S. (1997). Trenchless installation of conduits beneath roadways. NCHRP Synthesis 242. Jagadish Chandra, Trenchless Technology in India: Need of the New Millennium. Civil Engineering and Construction Review October Maninder Singh, Techniques of Trenchless Technology In Use In India. Civil Engineering and Construction Review October

8 Youssef Hashash & Jamie Javier University of Illinois at Urbana-Champaign, Evaluation of Horizontal Directional Drilling, November wtd/construction/seattle/smagnolia CSOStorage 8

Agenda for Today s Workshop

Agenda for Today s Workshop Agenda for Today s Workshop 10:00 to 10:45: Introduction Dr. Mo Najafi 10:45 to 11:15: Research and Testing Mr. Jwala Sharma 11:15 to 11:45: Cost Comparison Ms. Trupti Kulkarni 11:45 to 12:00: Lab Tour

More information

YOUR GROUND DRILLING PARTNERS.

YOUR GROUND DRILLING PARTNERS. YOUR GROUND DRILLING PARTNERS INDEX 2. ABOUT US 3. OUR SERVICES 4. OUR LOCATION 5. HORIZONTAL DRILLING 6. DIRECTIONAL BORING PROCESS 9. HDD DRILLING METHOD 12. MACHINE DETAILS 13. POLYETHYLENE PIPE CONDUIT

More information

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries

Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries Trenchless Technology The Missing Recipe for Sustainable Infrastructure s Construction and Maintenance in the Arab Countries Dr. Moustafa Kassab Systems Design Engineering / Civil Engineering Departments

More information

Trenchless Technology

Trenchless Technology TRENCHLESS TECHNOLOGY Gene Woodbridge Earth Boring Co. Limited www.earthboring.ca Earth Boring Co. Limited 1576 Ifield Road Mississauga, ON L5H 3W1 (905) 277-9632 fax (905) 274-9040 Trenchless Technology

More information

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e. No Dig Technology Introduction: No-Dig Technology is the art and science of installing, repairing or renewing underground pipes, ducts and cables using techniques that minimizes / eliminates the need for

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2002 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2O12 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING TABLE OF CONTENTS 450.01

More information

North End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No

North End and South End Section Hauled Wastewater Receiving Facilities Page 1 Bid Opportunity No Hauled Wastewater Receiving Facilities Page 1 Part 1 General 1.1 SECTION INCLUDES.1 Materials and installation for sewage force mains. 1.2 RELATED SECTIONS.1 CW 2110 Watermains and all specifications referenced

More information

Horizontal Directional Drilling

Horizontal Directional Drilling Horizontal Directional Drilling Horizontal Directional Drilling Why HDD Surface is neither broken nor damaged Restoration and repair are not required No public hazard or traffic disturbance Low social

More information

Final Report FHWA/IN/JTRP-2002/7

Final Report FHWA/IN/JTRP-2002/7 Final Report FHWA/IN/JTRP-2002/7 DEVELOPMENT OF A DECISION SUPPORT SYSTEM FOR SELECTION OF TRENCHLESS TECHNOLOGIES TO MINIMIZE IMPACT OF UTILITY CONSTRUCTION ON ROADWAYS By Dulcy M. Abraham, Ph.D. Associate

More information

Trenchless Pipeline Crossings

Trenchless Pipeline Crossings Trenchless Pipeline Crossings Overview Where we started Horizontal Directional Drilling 1960 s Evolution of the process Where we are today HDD Microtunneling Direct Pipe Crossing Process Where we re going

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 450 NOVEMBER 2007 (Reissued November 2010) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL BY HORIZONTAL DIRECTIONAL DRILLING

More information

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS.

TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS. TRENCHLESS SOLUTIONS FOR SEWER NETWORKS AND SEA OUTFALLS. Author: Frank B. Stevens Pr. Eng, BSc (Civil), HonFIMESA, FSAICE Technical Representative for Herrenknecht AG (Utility Tunnelling). stevens.frank@herrenknecht.de

More information

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS

CS-13 TRENCHLESS TECHNOLOGY TABLE OF CONTENTS TABLE OF CONTENTS CS-13.0 Trenchless Technology... 1 CS-13.1 Location of Existing Services... 1 CS-13.2 Alignment... 1 CS-13.3 Directional Drilling... 1 CS-13.4 Pipe Thrusting... 2 CS-13.5 Guided Boring/Auger

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD)

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING (HDD) ONTARIO METRIC PROVINCIAL OPSS 450 STANDARD October 2009 SPECIFICATION (Draft v1.0) CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION IN SOIL AND ROCK BY HORIZONTAL DIRECTIONAL DRILLING

More information

5/16/2018. New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters. Dr. Marc Peters, Herrenknecht AG. Highlights.

5/16/2018. New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters. Dr. Marc Peters, Herrenknecht AG. Highlights. Highlights. How to use a Jet Pump? Jet pump for HDD New Jet Pump Technology for HDD & Long-distance Pipe Jacking in small diameters Dr. Marc Peters, Herrenknecht AG Full-Face Hole opener & Downhole Jet

More information

Nowadays, horizontal directional drilling rigs are. Complex crossings made easy

Nowadays, horizontal directional drilling rigs are. Complex crossings made easy Dr. Hans Joachim Bayer, TRACTO TECHNIK GmbH & Co. KG, Germany, discusses the benefits of horizontal directional drilling, in particular the use of mega rigs. Complex crossings made easy Nowadays, horizontal

More information

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications.

There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications. Applications for New Installations There are several types of trenchless technology applications for new installations. The following are some of the most prominent applications. Note that some specifications

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

MICRO-PILE: RECENT ADVANCES AND FUTURE TRENDS

MICRO-PILE: RECENT ADVANCES AND FUTURE TRENDS MICRO-PILE: RECENT ADVANCES AND FUTURE TRENDS Jaydip V Chaudhari 1, Jayeshkumar Pitroda 2, J.J.Bhavsar 3 1 Student of first year M.E. (C.E M), B.V.M Engineering College, Vallabh Vidyanagar 2 Assistant

More information

SECTION UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD)

SECTION UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD) SECTION 33 05 07.13 UTILITY HORIZONTAL DIRECTIONAL DRILLING (HDD) PART 1 GENERAL 1.1 SCOPE A. Scope: 1. Design, furnish and install the proposed piping alignment by horizontal directional drilling (HDD)

More information

H. Underground Transmission System Design

H. Underground Transmission System Design H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,

More information

2016 International Petroleum Environmental Conference HORIZONTAL DIRECTIONAL DRILLING AND WELL INSTALLATION AT SMALL SITES

2016 International Petroleum Environmental Conference HORIZONTAL DIRECTIONAL DRILLING AND WELL INSTALLATION AT SMALL SITES 2016 International Petroleum Environmental Conference HORIZONTAL DIRECTIONAL DRILLING AND WELL INSTALLATION AT SMALL SITES History of Horizontal Environmental Wells Horizontal/Directional Oil Wells in

More information

A Trenchless Approach to Lift Station Elimination

A Trenchless Approach to Lift Station Elimination A Trenchless Approach to Lift Station Elimination PRESENTED BY: SCOTT MAUGHN, P.E. DANIEL HUFFINES, P.E. FSAWWA Fall Conference November 27, 2018 1 AGENDA Project Background Preliminary Investigations

More information

E-Power Pipe : A new trenchless method for underground cable installation

E-Power Pipe : A new trenchless method for underground cable installation E-Power Pipe : A new trenchless method for underground cable installation Dr. Gerhard Lang Jan 31, 2018 - UCT 2018, Track XI High Voltage Power Grid in Germany. Intention to replace nuclear power plants

More information

Brief Discussion on Application of Guided Boring Non-excavation Technology in Repair of Sewage Pipes Mei-Di SHAN1,a,*, Feng ZHOU2,b

Brief Discussion on Application of Guided Boring Non-excavation Technology in Repair of Sewage Pipes Mei-Di SHAN1,a,*, Feng ZHOU2,b 2nd Annual International Conference on Advanced Material Engineering (AME 2016) Brief Discussion on Application of Guided Boring Non-excavation Technology in Repair of Sewage Pipes Mei-Di SHAN1,a,*, Feng

More information

Horizontal Directional Drilling for Water Supply Applications

Horizontal Directional Drilling for Water Supply Applications Horizontal Directional Drilling for Water Supply Applications 25 th Annual International Petroleum Environmental Conference Denver, Colorado October 30th, 2018 History of Horizontal Water Wells Horizontal/Directional

More information

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons

Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons WATER Sioux City Iowa Utilizes HDD to Install Twin 36 Casings for Sanitary Sewer Siphons Presented by Peter Merten, PE, HR Green, Inc. and David Reuter, PE, Underground Solutions UCT Underground Construction

More information

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE

HDD Training. Mitigation. Mark Miller, PE Jon Robison, PE HDD Training Mitigation Mark Miller, PE Jon Robison, PE Mitigating HDD Risks HDD construction risks need to be evaluated during the design process to reduce the risk of schedule delays, damage to existing

More information

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill

Technology. Trenchless. Planning, Equipment, and Methods. Mohammad Najafi. Mc Gravu Hill Trenchless Technology Planning, Equipment, and Methods Mohammad Najafi Mc Gravu Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New Delhi San Juan Seoul Singapore Sydney Toronto

More information

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY Bryan Thompson, Town of Westport Abhinav Huli, Haley & Aldrich, Inc Lori Carriero, P.E., Tighe & Bond PRESENTATION OUTLINE

More information

Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic Fracture Factor of Safety

Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic Fracture Factor of Safety North American Society for Trenchless Technology (NASTT) NASTT s 216 No-Dig Show Dallas, Texas March 2-24, 216 TA-T5-3 Direct Pipe Installations underneath USACE Levees Keeping Permitted Minimum Hydraulic

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 2 CONTRACT 2018.03 EXIT 44 SOUTHBOUND ON RAMP IMPROVEMENTS MILE 44.3 The following changes are made to the Proposal, Specifications, and Plans. PROPOSAL Proposal Sheets

More information

WARNING DO NOT BID ON THIS PROJECT

WARNING DO NOT BID ON THIS PROJECT WARNING DO NOT BID ON THIS PROJECT Nick H. Strater, P.G., Associate, Brierley Associates, Bedford, NH Brian C. Dorwart, P.E., P.G., Sr. Consultant, Brierley Associates, Bedford, NH For projects advertised

More information

Challenges on HDD Pipeline Shore Approach

Challenges on HDD Pipeline Shore Approach OIL & GAS Challenges on HDD Pipeline Shore Approach DNV GL New Recommended Practice Luis D'Angelo - Danilo Machado 02 November 2016 1 SAFER, SMARTER, GREENER Agenda Objectives Why to use HDD in Shore Approach?

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2

Pipe Jacking Association: Introduction Presentation. Lecture notes. Slide 1. Slide 2 Slide 1 PIPE JACKING An introduction to pipe jacking prepared by the Pipe Jacking Association This introduction to pipe jacking has been prepared by the Pipe Jacking Association as an aid to engineers

More information

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject

THE TRENCHLESS TREND. Traditionally, pipeline shore crossings have integrated the by shallow waters, which are typically subject 56 THE TRENCHLESS TREND Pipeline shore crossings are often one of the most Costs and risks involved will change with every site, and every complex and technically challenging elements of any project. subsea

More information

Challenger Drilling, Inc. s HS&E and Special Training

Challenger Drilling, Inc. s HS&E and Special Training Challenger Drilling, Inc. s HS&E and Special Training The safety and health policy of Challenger Drilling, Inc. is to perform the highest quality service as efficiently as possible, while maintaining the

More information

SECTION HORIZONTAL DIRECTIONAL DRILLING

SECTION HORIZONTAL DIRECTIONAL DRILLING SECTION 330532- HORIZONTAL DIRECTIONAL DRILLING PART 1 - GENERAL 1.1 DESCRIPTION A. Furnish all labor, materials, tools, and equipment required to install pipes below the outer perimeter prison fence using

More information

Section HORIZONTAL DIRECTIONAL DRILLING. 1. Installing water line by directional drilling methods.

Section HORIZONTAL DIRECTIONAL DRILLING. 1. Installing water line by directional drilling methods. Section 02450 PART 1 GENERAL 1.01 SUMMARY A. This Section includes: 1. Installing water line by directional drilling methods. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for water lines installed

More information

The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump

The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump The new HDD Tooling from Herrenknecht Full Face Hole Opener / Down Hole Jet Pump Simon Herrenknecht, Product Manager Pipeline, Herrenknecht AG Herrenknecht Introduction Herrenknecht AG, Germany Founded

More information

A number of abbreviations and technical terms have been used in this guideline:

A number of abbreviations and technical terms have been used in this guideline: Page No: i CONTENTS 1.0 BACKGROUND 2 2.0 DEFINITIONS 2 3.0 INTRODUCTION 2 4.0 HORIZONTIAL DIRECTIONAL DRILLING GUIDELINE 2 4.1 HDD Process 2 4.2 HDD Methods 2 4.2.1 Pilot Bore 2 4.2.2 Reaming 2 4.2.3 Pullback

More information

NZQA registered unit standard version 3 Page 1 of 5

NZQA registered unit standard version 3 Page 1 of 5 Page 1 of 5 Title Operate the drill rig for horizontal directional drilling Level 3 Credits 15 Purpose People credited with this unit standard are able to: care for and maintain horizontal directional

More information

Sustainable Utility Construction: Methods and Techniques

Sustainable Utility Construction: Methods and Techniques Sustainable Utility Construction: Methods and Techniques September 19, 2011 APWA Congress Denver, Colorado Murv Morehead ROW Coordinator Overland Park, Kansas Monty Zimmerman Row Manager Lenexa, Kansas

More information

Kathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016

Kathryn Wallin Bennett Trenchless. Bo Botteicher Underground Solutions. Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016 www.norcalpug.com Pipe Users Group Sharing Technologies Seminar Berkeley, CA February 18, 2016 Kathryn Wallin Bennett Trenchless Bo Botteicher Underground Solutions Project Area Existing Sewers 66-inch

More information

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-16 ISSUE: Initial DATE: 14-10-2009 PAGE: 1 of 19 REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) ISSUE DATE DESCRIPTION /

More information

Geotechnical Investigations Water Main Construction

Geotechnical Investigations Water Main Construction Geotechnical Investigations Water Main Construction GHD Water Andrew R. Glitzer, P.E. Sr. Project Engineer Water Main Construction Why Consider Geotechnical Evaluations? Not a typically a part of routine

More information

A CRITICAL LITERATURE REVIEW ON FACTORS AFFECTING PERFORMANCE OF CONTRACTORS IN BUILDING CONSTRUCTION

A CRITICAL LITERATURE REVIEW ON FACTORS AFFECTING PERFORMANCE OF CONTRACTORS IN BUILDING CONSTRUCTION A CRITICAL LITERATURE REVIEW ON FACTORS AFFECTING PERFORMANCE OF CONTRACTORS IN BUILDING CONSTRUCTION Chiragkumar Chaudhari 1, Parthkumar Vaghela 2, Sanjaykumar Memakiya 3, Ashishkumar Prajapati 4, Prof.

More information

APPENDIX D DIRECTIONAL BORING GUIDELINES

APPENDIX D DIRECTIONAL BORING GUIDELINES The City of Winnipeg Appendix D Bid Opportunity No. 180 163-2016 Page 1 of 1 Template Version: C420150806 - RW APPENDIX D DIRECTIONAL BORING GUIDELINES Corporate Safety & Health Division Directional Boring

More information

APPENDIX D C DIRECTIONAL BORING GUIDELINES

APPENDIX D C DIRECTIONAL BORING GUIDELINES The City of Winnipeg Appendix C D Bid Opportunity No. 19-2015 18 2015 Page 1 of 1 Template Version: C420150116 - RW APPENDIX D C DIRECTIONAL BORING GUIDELINES Corporate Safety & Health Division Directional

More information

How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E.

How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study. Jessica M. W. Hou, P.E. How to Apply the Virginia Underground Utility Damage Prevention Act to a Jack and Bore Operation: A Case Study Jessica M. W. Hou, P.E., BCEE Agenda What is a jack and bore? What is does the Underground

More information

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TM1-T2-03 Cutting-Edge Trenchless Technology Proposed for Challenging CSO Project

More information

How PGW Manages Pipeline Installation in a Congested Underground. Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works

How PGW Manages Pipeline Installation in a Congested Underground. Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works How PGW Manages Pipeline Installation in a Congested Underground Presentation by Mike Parzanese Project Manager Construction Philadelphia Gas Works Summary Philadelphia by the numbers Philadelphia Gas

More information

DRILLING INSTEAD OF DIGGING SEPARATING THE SCRIPPS INSTITUTION OF OCEANOGRAPHY S COMBINED OUTFALL SYSTEM

DRILLING INSTEAD OF DIGGING SEPARATING THE SCRIPPS INSTITUTION OF OCEANOGRAPHY S COMBINED OUTFALL SYSTEM North American Society for Trenchless Technology 2008 No-Dig Conference & Exhibition Dallas, Texas April 27 May 2, 2008 DRILLING INSTEAD OF DIGGING SEPARATING THE SCRIPPS INSTITUTION OF OCEANOGRAPHY S

More information

Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River

Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River Fifty Feet of Peat: Design Challenges of Three Long HDD Crossings of the Sacramento River 3 rd Annual Rocky Mountain Regional No Dig Conference & Exhibition Westminster, CO November 8, 2012 David Bennett,

More information

Productivity Analysis of Horizontal Directional Drilling Muhammad Adel 1 and Tarek Zayed 2

Productivity Analysis of Horizontal Directional Drilling Muhammad Adel 1 and Tarek Zayed 2 835 Productivity Analysis of Horizontal Directional Drilling Muhammad Adel 1 and Tarek Zayed 2 1 Graduate Student, Dept. of Building, Civil & Environmental Engineering, Concordia University, Montreal,

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

Design of pipeline installation. D-Geo Pipeline

Design of pipeline installation. D-Geo Pipeline Design of pipeline installation D-Geo Pipeline Design of pipeline installation D-Geo Pipeline General Pipelines are an important part of the underground infrastructure. They are the lifelines of our modern

More information

The City of Sergeant Bluff, IA Chooses Pilot Tube Microtunneling over Open Trench Construction

The City of Sergeant Bluff, IA Chooses Pilot Tube Microtunneling over Open Trench Construction North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 Paper MM-T4-02 The City of Sergeant Bluff, IA Chooses Pilot Tube Microtunneling

More information

FOR TRENCHLESS TECHNOLOGIES

FOR TRENCHLESS TECHNOLOGIES MEMPEX LTD TRENCHLESS TECHNOLOGIES 220004 Minsk, Belarus ul. Rakovskaya, 34 Tax ID 100944009, OKPO 37328184 Hydraulic equipment FOR TRENCHLESS TECHNOLOGIES 2016, ООО MEMPEX, 34, Rakovskaya St., Minsk,

More information

SKSC Civils (pty) LTD. Brilliance Technology Quality - Innovation

SKSC Civils (pty) LTD. Brilliance Technology Quality - Innovation SKSC Civils (pty) LTD Brilliance Technology Quality - Innovation About us SKSC Civils was inspired by numerous individuals in South Africa, ranging from the civil to the construction industry, to truly

More information

New Technologies, Innovations

New Technologies, Innovations New Technologies, Innovations Drilling New Technologies, Innovations Advances in technologies used for well drilling and completion have enabled the energy industry to reach new sources of oil and natural

More information

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines Trenchless Crossing Evaluation on the Martha Lake Gateway Sewer An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines Introduction Purpose Provide engineers and owners

More information

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY

More information

Table of Contents TOC. Chapter 14 - Trenchless Construction. 14A General Information. 14B New Construction. 14C Rehabilitation

Table of Contents TOC. Chapter 14 - Trenchless Construction. 14A General Information. 14B New Construction. 14C Rehabilitation Design Manual Chapter 14 - Trenchless Construction Table of Contents TOC Table of Contents Chapter 14 - Trenchless Construction 14A General Information 14A-1---------------------------------General Information

More information

7/17/2017 Page 1 of 5

7/17/2017 Page 1 of 5 HORIZONTAL DIRECTIONAL DRILLING AND BORING PART 1.0 GENERAL 1.1 DESCRIPTION This section covers the work necessary for the installation of conduit duct banks by directionally controlled horizontal drilling

More information

Strength and Durability for Life. APPLICATIONS Horizontal Directional Drilling with Ductile Iron Pipe

Strength and Durability for Life. APPLICATIONS Horizontal Directional Drilling with Ductile Iron Pipe Strength and Durability for Life APPLICATIONS Horizontal Directional Drilling with Ductile Iron Pipe Last Revised: May 2016 Horizontal Directional Drilling (HDD) is a trenchless methodology that provides

More information

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January

2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January Program: Title: Author: 2008 Underground Construction Technology International Conference & Exhibition, Cobb County Galleria Center, Atlanta, GA - January 29-31. Successful Technology for Utility Installations

More information

Overview of horizontal directional drilling for utility construction

Overview of horizontal directional drilling for utility construction Calhoun: The NPS Institutional Archive Theses and Dissertations Thesis Collection 1999 Overview of horizontal directional drilling for utility construction Barlas, Alexander W. Monterey, California. Naval

More information

HORIZONTAL DIRECTIONAL DRILLING WITH DUCTILE IRON PIPE

HORIZONTAL DIRECTIONAL DRILLING WITH DUCTILE IRON PIPE HORIZONTAL DIRECTIONAL DRILLING WITH DUCTILE IRON PIPE HORIZONTAL DIRECTIONAL DRILLING WITH DUCTILE IRON PIPE By Richard W. Bonds, P.E. DIPRA Research and Technical Director Introduction Horizontal Directional

More information

East US Route 36 Sewer Extension Addendum #1

East US Route 36 Sewer Extension Addendum #1 East US Route 36 Sewer Extension Addendum #1 To: All Bidders From: Tyler Bumbalough, City Engineer Date: May 22, 2014 Re: Horizontal Directional Drilling Alternate #1; Soil Boring Report for Pump Station;

More information

An Introduction to Trenchless Technology

An Introduction to Trenchless Technology An Introduction to Trenchless Technology An Introduction to Trenchless Technology Steven R. Kramer William J. McDonald James C. Thomson m CHAPMAN & HALL New York London DISCLAIMER-LEGAL NOTICE This book

More information

Public Works and Utilities Department RIGHT-OF-WAY USE PERMIT APPLICATION

Public Works and Utilities Department RIGHT-OF-WAY USE PERMIT APPLICATION RIGHT-OF-WAY USE PERMIT APPLICATION INSTRUCTIONS 1. The Engineering Section of the City of Bradenton Department of Public Works and Utilities is responsible for processing and approving all ROW Use Permits.

More information

JOURNAL OF INTERNATIONAL ACADEMIC RESEARCH FOR MULTIDISCIPLINARY Impact Factor 1.393, ISSN: , Volume 2, Issue 4, May 2014

JOURNAL OF INTERNATIONAL ACADEMIC RESEARCH FOR MULTIDISCIPLINARY Impact Factor 1.393, ISSN: , Volume 2, Issue 4, May 2014 TECHNO ECONOMICAL DEVELOPMENT OF LOW-COST INTERLOCKING PAVERBLOCK BY PARTIALLY REPLACEMENT OF PORTLAND POZZOLANA CEMENT WITH USED FOUNDRY SAND WASTE DIXIT N. PATEL* JAYESHKUMAR R. PITRODA** *Final Year

More information

Design of pipeline installation D-GEO PIPELINE

Design of pipeline installation D-GEO PIPELINE Design of pipeline installation D-GEO PIPELINE Design of pipeline installation D-GEO PIPELINE General Pipelines are an important part of the underground infrastructure. They are the lifelines of our modern

More information

Modeling of Productivity for Horizontal Directional Drilling. (HDD) Operation and Applications

Modeling of Productivity for Horizontal Directional Drilling. (HDD) Operation and Applications Modeling of Productivity for Horizontal Directional Drilling (HDD) Operation and Applications Mohmd Sarireh Assistant Professor, Tafila Technical University, Department of Civil Engineering, P.O. Box 179,

More information

TECHNICAL NOTE HDPE Pipe and Utility Crossings

TECHNICAL NOTE HDPE Pipe and Utility Crossings TECHNICAL NOTE HDPE Pipe and Utility Crossings TN 5.09 April 2008 Introduction Underground utilities include storm sewer, electric, sanitary sewer, gas, water, telephone and cable. Utility conflicts are

More information

Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking

Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking Australasian Society for Trenchless Technology Standard for Microtunnelling & Pipe Jacking - 2 Minor changes JP JP JP JP 1 June 2015 1 General Revisions JC MI NH JP 03 Feb 2010 0 Issued for Use Client

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

B. All materials to be installed shall be purchased in accordance with all applicable provisions of the Buy American Act.

B. All materials to be installed shall be purchased in accordance with all applicable provisions of the Buy American Act. 33 05 23 TRENCHLESS UTILITY INSTALLATION SECTION 1 GENERAL 1.1 SUMMARY A. This specification addresses systems of piping and general requirements for water distribution and sewer collection systems which

More information

Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo

Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo Moncton Watermain Relocation Moncton, New Brunswick TRS 2010 Dr Mark Knight University of Waterloo Presentation Outline Overview of the project Design and construction Issues Trenchless construction Lessons

More information

Experts in tunneling with Tunnel Boring Machines

Experts in tunneling with Tunnel Boring Machines www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution

More information

Introduction to Horizontal Remediation Wells for Improved Site Cleanup Training Workshop

Introduction to Horizontal Remediation Wells for Improved Site Cleanup Training Workshop Horizontal Wells for Sub-Slab Vapor Intrusion Mitigation and Remediation Southeastern States Vapor Intrusion Symposium February 8, 2018 Presenter: Kyle J. Carlton, PG kcarlton@directionaltech.com Senior

More information

Imperial s Sarnia Products Pipeline Mississauga, Ontario. Credit River Valley Project

Imperial s Sarnia Products Pipeline Mississauga, Ontario. Credit River Valley Project Imperial s Sarnia Products Pipeline Mississauga, Ontario Credit River Valley Project Preventative pipeline maintenance in Mississauga s Credit River Valley Imperial s Sarnia Products Pipeline (SPPL) carries

More information

Keyhole Technology House connections installed with minimal invasion using the trenchless method

Keyhole Technology House connections installed with minimal invasion using the trenchless method Keyhole Technology House connections installed with minimal invasion using the trenchless method The increasing sensivity of the residents affected, impairment of local infrastructure and mobility restrictions

More information

Fly Ash (F-Class): Oppertiunities For Sustainable Development Of Low Cost Rural Roads

Fly Ash (F-Class): Oppertiunities For Sustainable Development Of Low Cost Rural Roads Fly Ash (F-Class): Oppertiunities For Sustainable Development Of Low Cost Rural Roads Darsh Belani 1, Prof. Jayeshkumar Pitroda 2 1 Student of first year M.E (C.E & M), B.V.M Engineering College, Vallabh

More information

PARRIS ISLAND FORCE MAIN PROJECT CREATES RECORD HDD INSTALLATION FOR PLASTIC PIPE

PARRIS ISLAND FORCE MAIN PROJECT CREATES RECORD HDD INSTALLATION FOR PLASTIC PIPE North American Society for Trenchless Technology (NASTT) No-Dig Show 2011 Washington, D.C. March 27-31, 2011 Paper C-1-01 PARRIS ISLAND FORCE MAIN PROJECT CREATES RECORD HDD INSTALLATION FOR PLASTIC PIPE

More information

SECTION TRENCHLESS INSTALLATION

SECTION TRENCHLESS INSTALLATION SECTION 02250 PART 1 GENERAL 1.01 Section Includes A. Trenchless installation of casing pipe. B. Trenchless installation of carrier pipe. C. Open cut installation of casing pipe. 1.02 Description of Work

More information

NTC 2015 SOIL SAMPLING UTILIZING HORIZONTAL/DIRECTIONAL DRILLING METHODS

NTC 2015 SOIL SAMPLING UTILIZING HORIZONTAL/DIRECTIONAL DRILLING METHODS NTC 2015 SOIL SAMPLING UTILIZING HORIZONTAL/DIRECTIONAL DRILLING METHODS Directional Control The bit is navigated along a prescribed path The bore path need not be horizontal or straight Bore path is design

More information

For NGTL to file calculation of operating condition on pull back stress analysis.

For NGTL to file calculation of operating condition on pull back stress analysis. NOVA Gas Transmission Ltd. Exhibit No. B85 National Energy Board Hearing Order GH-001-2014 Undertaking U-10 Submitted November 25, 2014 Response to Undertaking given by Mr. Trout to Chairman Vergette at

More information

PILOT TUBE & PIPE RAMMING METHOD INSTALL LARGE DIAMETER CASING UNDER RR

PILOT TUBE & PIPE RAMMING METHOD INSTALL LARGE DIAMETER CASING UNDER RR PILOT TUBE & PIPE RAMMING METHOD INSTALL LARGE DIAMETER CASING UNDER RR TOM LOYER, ENGINEERS CONSTRUCTION INC JOHN HRABOSKY, HAMMERHEAD TRENCHLESS NASTT s 2019 No-Dig Show What is pipe ramming? A pneumatic

More information

Pipe Jacking. Japan Sewage Works Association

Pipe Jacking. Japan Sewage Works Association Pipe Jacking Japan Sewage Works Association June, 2013 1 Pipe Jacking Yosuke Matsumiya y.matsumiya@ngsk.or.jp Japan Sewage Works Association Suisui Bldg. 2-10-12 Uchikanda, Chiyodaku Tokyo 101-0047 Japan,

More information

DIRECT COMPARISON OF HDD AND OPEN-CUT PIPE INSTALLATION UNDERNEATH FLEXIBLE PAVEMENT: PAVEMENT AND PIPE PERFORMANCE EVALUATION

DIRECT COMPARISON OF HDD AND OPEN-CUT PIPE INSTALLATION UNDERNEATH FLEXIBLE PAVEMENT: PAVEMENT AND PIPE PERFORMANCE EVALUATION DIRECT COMPARISON OF HDD AND OPEN-CUT PIPE INSTALLATION UNDERNEATH FLEXIBLE PAVEMENT: PAVEMENT AND PIPE PERFORMANCE EVALUATION Adedamola Adedapo (Graduate student, Department of Civil Engineering, University

More information

CITY OF RICHMOND INVITATION TO TENDER

CITY OF RICHMOND INVITATION TO TENDER CITY OF RICHMOND INVITATION TO TENDER Contract T.2892 Contract: AC Watermain Replacement, Comstock Area The City of Richmond invites tenders for construction work at the above-mentioned locations. Work

More information

APPLICATION FOR RIGHT OF WAY PERMIT

APPLICATION FOR RIGHT OF WAY PERMIT City of Danville Department of Engineering & Urban Services APPLICATION FOR RIGHT OF WAY PERMIT PROJECT LOCATION: CONTRACTOR S BUSINESS NAME: CONTRACTOR'S ADDRESS: CONTRACTOR'S PHONE: OWNER S NAME: OWNER

More information

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY

WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY WESTPORT S PUMP STATION NO. 2 FORCE MAIN REPLACEMENT PROJECT USING HDD: A CASE STUDY By: Bryan Thompson, Town of Westport, CT Abhinav Huli, Haley & Aldrich, Inc. Lori Carriero, Tighe & Bond Figure 1: Project

More information

TRENCHLESS TECHNOLOGY. Department of Civil Engineering.

TRENCHLESS TECHNOLOGY. Department of Civil Engineering. TRENCHLESS TECHNOLOGY GUIDED BY Ms. PRAJEESHA.M.P Lecturer. Department of Civil Engineering. PRESENTED BY DEEPAK.C Semester 7,Civil Roll No:58 CONTENTS INTRODUCTION TRENCHLESS CONSTRUCTION METHODS TRENCHLESS

More information

4th International Engineering and Construction Conference - July 28, 2006

4th International Engineering and Construction Conference - July 28, 2006 4th International Engineering and Construction Conference - July 28, 2006 BOX-JACKING - A USEFUL CONSTRUCTION TOOL By Anthony Lynn, Berkeley Engineering Company, Inc. Box jacking is jacking a large precast

More information