1 Document 15 Standard Operating Procedures Subject: SOP No.: Standard Procedure for Construction Services/4/d/02/1 Effective Date: 8 July 2009 Total pages: 9 1. Purpose Standardize construction inspection procedures for better quality control. 2. Reference Items No.8, No.15, and checking points mentioned in No.11 from the Quality Control and Management for Construction guidelines established by the Public Construction Commission of the Republic of China (Taiwan). 3. Application Applicable to all major construction, structural, and interior design projects carried out under contract at all Center locations. Not applicable to small, simple repair jobs 4. Specification In accordance with the standard construction specifications and general guidelines of construction inspection on architectural works developed by the Public Construction Commission of the Republic of China (Taiwan), and with contractual requirements for each individual construction project. 5. Definition 5.1 To ensure the items used during a construction project meet the specifications, and to ensure a construction project has been completed properly and in accordance with contractual requirements. s are carried out by checking, measuring, conducting a quantity survey, or visual inspection. 5.2 Checking Points Points during a project when inspection is required and approval is necessary before proceeding to the next construction stage. The checking points are set by the Architect, and should include all common stages of a project, such as materials delivery, setting layout, and installation. 1

2 6. Procedure and explanation 6.1 Operation procedures Arrival of Materials Upon the arrival of materials, the contractor is responsible for primary quality control. A self-inspection should be carried out according to the quality control plan based on the above-referenced quality control guidelines. After the self-inspection is completed, the contractor must inform the Architect s supervisor and the Center s technician, so that they may carry out a joint examination of the materials. The inspection criteria must follow the contractual drawings, standard specifications, and general guidelines for construction inspection. If the materials do not meet specifications, the Center s technician will work with the Architect s supervisor to immediately issue a Non-Conformity Report (NCR; Attachment 1) to the contractor. The contractor must then change the materials immediately upon receiving the NCR, and redo the primary self-inspection. After the self-inspection, the contractor must contact the Architect s supervisor and the Center s technician to request that the NCR be closed before the project moves to the next phase of construction Setting Layout After the materials are confirmed and accepted, the contractor can proceed in setting the layout. The contractor must perform a self-inspection of the layout, and then inform the Architect s supervisor and the Center s technician to inspect the layout work. If the layout work is unacceptable, the Center s technician will work with the Architect s supervisor to immediately issue an NCR to the contractor. Upon receiving the NCR, the contractor must immediately reset the layout and redo the primary self-inspection. After the self-inspection, the contractor must contact the Architect s supervisor and the Center s technician to request that the NCR be closed before the project moves to the next phase of construction Installation and Assembly After the setting layout work is confirmed and accepted, the contractor can proceed to the installation or assembly work. The contractor must perform a self-inspection of this work, and then inform the Architect s supervisor and the Center s technician to inspect the installation or assembly. If the installation or assembly is unacceptable, the Center s technician will work with the Architect s supervisor to immediately issue an NCR to the contractor. Upon receiving the NCR, the contractor must immediately reinstall or reassemble the work, and redo the primary self-inspection. After the self-inspection, the contractor must contact the Architect s supervisor and the Center s technician to request that the NCR be closed. At the completion of this phase, the Architect s supervisor and the Center s technician must both sign the quality control card for the completion of a specific working item. The contractor must attach the co-signed quality control card with the payment request for the interim payment approval. 6.2 Key points for inspection Priority of inspection checking points 2

3 Materials inspection a. Approve qualification data of subcontractor and material supplier. (Refer to the contractual drawings or specification requirement.) b. Review and inspect the material sample. (Refer to the contractual drawings or specification requirement.) c. Review and approve the shop drawings. (Confirm the construction drawings have been approved by the Architect and the Center.) d. Take sampling for material test after the arrival of materials. e. Pre-assemble the materials on-site if required on setting layout a. Follow the survey plan in the method statement for detail inspection. (Confirm the method statement has been approved by the Architect and the Center.) on installation or assembly a. Accessories of supports, connections, and joints b. Finish surface c. Embedment or openings d. Trim treatment e. Location and level f. Verticality and horizontality g. Cleaning and protection Please refer to the construction inspection flowchart (Figure 1) for the procedure. 7. Templates of form format 7.1 Non-Conformity Report (NCR): Attachment Quality Control Card: Attachments 2-1 to 2-4 (Format developed by the contractor s quality control staff according to the various construction items in contract, and approved by the Architect and the Center.) 3

4 Construction Flowchart Figure 1 Arrival of Materials NCR Notification Contractor s primary self-inspection Architect s supervisor / Center s technician Fail Materials Pass NCR Closeout after Improvement Setting Layout Installation & Assembly NCR Closeout after Improvement Contractor s primary self-inspection Pass Architect s supervisor / Center s technician Layout Fail NCR Notification NCR Notification Contractor s primary self-inspection Architect s supervisor / Center s technician NCR Closeout after Improvement Fail Installation Pass Co-sign on Quality Control Card Payment Request Center s technicians should implement the inspection based on the checking points in the flowchart. All NCRs should be issued by the Center and the Architect. TSO must record the NCR serial numbers and file copies of the NCR when they are closed out. 4

5 Attachment 1 Non-Conformity Report (NCR) on Construction Works Construction No. oo AVRDC ooo Contractor xx Construction Company xx Architect or AVRDC Date & No. Item & Site Statement on non-qualification (including photos) NCR No. Improvement Measures (including photos) Confirmation of Improvement Architect s : Center s Technician: 5

6 Attachment 2-1 Rebar Reinforcement Quality Control Card Contract No. Contractor: Working Item No. Construction site: Project name: Drawing No. Version: Architect: Date: Y M D Item Contents Specification No. or Reference Source Contractor s Quality Controller Architect s Physics, chemistry, and radiation Before Construction Rebar coupler s tension and sliding Location and height layout Rebar coupler s twist Under Construction Dimension, quantity, location and overlap Rebar spacing & protection Extension length & bending radius Vertical Dimension, quantity, location and overlap for the reserved rebar Dimension, quantity, location and overlap for the extra rebar Embedded parts results and comments: Rebar grade and quantity detail (Ton) SD280 SD280W SD420 SD420W (1) Fill out the specification no. or reference resource according to the contractual requirement. (2) Attach the contractor s self-inspection report to this form. (3) Write down the result with date and signature in sequence by Architect s supervisor. (4) Submit the Quality Control Card with 3 copies: one for the contractor s file, one for the Architect, and one for the payment request use. Contractor: Architect s : Center s Technician: 6

7 Attachment 2-2 Formwork Quality Control Card Contract No. Contractor: Working Item No. Construction site: Project name: Drawing No. Version: Architect: Date: Y M D Item Contents Specification No. or Reference Source Contractor s Quality Controller Architect s Setting layout Smooth on panel surface and if overused Cleaning and releasing agent application Construction Panel grade Working frame setup Panel size Support and accessories Expansion and construction joints Embedment Pre-openings and reinforcing supports Verticality and elevation control Thickness of protection results and comments: (1) Fill out the specification no. or reference resource according to the contractual requirement. (2) Attach the contractor s self-inspection report to this form. (3) Write down the result with date and signature in sequence by Architect s supervisor. (4) Submit the Quality Control Card with 3 copies: one for the contractor s file, one for the Architect and one for the payment request use. Contractor: Architect s : Center s Technician: 7

8 Attachment 2-3 Concrete Quality Control Card Contract No. Contractor: Working Item No. Construction site: Project name: Drawing No. Version: Architect: Date: Y M D Item Contents Vibrator s quantity and specification Vibrator s location and distance Average time of vibration Under Air bubble going up or not Construction Sound change or not during vibration Grout overflow or not between panels Specification No. or Reference Source Contractor s Quality Controller Architect s After Smooth finish surface or not Construction Curing results and comments: Quantity details: Unit: M 3 Cement type: TYPE I; TYPE II N/mm 2 N/mm 2 N/mm 2 N/mm 2 N/mm 2 (1) Fill out the specification no. or reference resource according to the contractual requirement. (2) Attach the contractor s self-inspection report to this form. (3) Write down the result with date and signature in sequence by Architect s supervisor. (4) Submit the Quality Control Card with 3 copies: one for the contractor s file, one for the Architect and one for the payment request use. Contractor: Architect s : Center s Technician: 8

9 Attachment 2-4 Interior Decoration Quality Control Card (Item ) Contract No. Contractor: Working Item No. Construction site: Project name: Drawing No. Version: Architect: Date: Y M D (1) Item Contents Qualification data of materials supplier and subcontractor Sample of material Specification No. or Reference Source Contractor s Quality Controller Architect s Materials Approval of Shop Drawings Material sampling and test Pre-assembly (2) Location and elevation layout Support, joint, and connection accessory Finish surface Construction Openings and embedment Trim treatment Verticality and horizontality Cleaning and protection results & comments: (1) Fill out the specification no. or reference resource according to the contractual requirement. (2) Attach the contractor s self-inspection report to this form. (3) Write down the result with date and signature in sequence by Architect s supervisor. (4) Submit the Quality Control Card with 3 copies: one for the contractor s file, one for the Architect and one for the payment request use. Contractor: Architect s : Center s Technician: 9

SECTION DOOR HARDWARE

SECTION DOOR HARDWARE SECTION 087100 -DOOR HARDWARE PART 1- GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Union County Vocational - Technical Schools Scotch Plains, New Jersey

Union County Vocational - Technical Schools Scotch Plains, New Jersey SECTION 102239 - FOLDING PANEL PARTITIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

***************************************************************************************************************

*************************************************************************************************************** 03365 POST-TENSIONED CONCRETE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 38 00. ***************************************************************************************************************

More information

Division 03 - Concrete Section New Westminister Multi-Use Civic Facility & Office Building Project No Page 1

Division 03 - Concrete Section New Westminister Multi-Use Civic Facility & Office Building Project No Page 1 Project No. 210022 Page 1 PART 1 GENERAL 1.7 Documents.1 The General Conditions of the Canadian Standard Construction Document CCDC-2, together with all amendments and supplements and Division 1 General

More information

SECTION HANDRAILS AND RAILINGS. A. Section Cast-In-Place Concrete; coordination with substrate.

SECTION HANDRAILS AND RAILINGS. A. Section Cast-In-Place Concrete; coordination with substrate. SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES A. Welded stainless steel railing systems. 1.2 RELATED SECTIONS A. Section 03300 - Cast-In-Place Concrete; coordination with substrate.

More information

SPECIAL INSPECTION AGREEMENT

SPECIAL INSPECTION AGREEMENT PART 1 STATEMENT OF SPECIAL INSPECTIONS When special inspection is required to be performed in accordance with International Building Code Chapter 17, a building permit cannot be issued until a statement

More information

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS

SECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS SECTION 32 16 13 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and required

More information

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system.

SECTION WELDED STEEL PICKET FENCE. 1. Fusion welded and rackable ornamental steel picket fence system. PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Fusion welded and rackable ornamental steel picket fence system. B. Related sections: 1. Section 03310 Concrete Work for post support. 2. Section 09960

More information

Superior Aluminum Guide Specification 10/4/2016 Non-Welded Aluminum Pipe Railing

Superior Aluminum Guide Specification 10/4/2016 Non-Welded Aluminum Pipe Railing The following specification has been developed by: Superior Aluminum Products 555 East Main Street Russia, Ohio 45363-0430 to assist Architects and Designers in the specification of Non Welded Concealed

More information

Special Provision No. 199S53 January 2018

Special Provision No. 199S53 January 2018 PERFORMANCE REQUIREMENT - QUALITY PROCESSES Special Provision No. 199S53 January 2018 1.0 SCOPE This Special Provision describes the performance requirements for quality processes, assessment of conformance

More information

SPECIAL INSPECTION AGREEMENT

SPECIAL INSPECTION AGREEMENT DEVELOPMENT SERVICES DEPARTMENT BUILDING AND SAFETY DIVISION 156 S. BROADWAY, SUITE 130 TURLOCK, CALIFORNIA 95380 PHONE 209-668-5560 FAX 209-668-5107 SPECIAL INSPECTION AGREEMENT PERMIT NUMBER: DATE: OWNER:

More information

Statement. Special Inspection

Statement. Special Inspection Statement of Special Inspection Special Inspection Approval Project Name: Location: Owner: Owner s address: Architect of Record: Structural Engineer of Record: The Statement of Special Inspections printed

More information

Special Provision No. 199S53 February 2012

Special Provision No. 199S53 February 2012 PERFORMANCE REQUIREMENT QUALITY PROCESSES Special Provision No. 199S53 February 2012 1.0 SCOPE This Special Provision describes the performance requirements for quality processes, assessment of conformance

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-03 11 13.00 10 (May 2014) --------------------------------- Preparing Activity: USACE Superseding UFGS-03 11 13.00 10 (August 2010) UNIFIED FACILITIES GUIDE SPECIFICATIONS

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 12/12/2018 SECTION 08 1119 - STAINLESS STEEL DOOR AND FRAMES GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

SECTION LAGUNA SERIES TOP HUNG SLIDING DOOR SYSTEM

SECTION LAGUNA SERIES TOP HUNG SLIDING DOOR SYSTEM Page 1 of 6 SECTION 08 32 20 LAGUNA SERIES TOP HUNG SLIDING DOOR SYSTEM USE THIS SECTION WHEN SPECIFYING OVERHEAD SUPPORTED GLASS SLIDING DOORS. SECTION INCLUDES OVERHEAD SLIDING TUBE ASSEMBLY, MOUNTING

More information

SECTION ORNAMENTAL ALUMINUM RAILING

SECTION ORNAMENTAL ALUMINUM RAILING SECTION 05730 ORNAMENTAL ALUMINUM RAILING PART 1 GENERAL 1.1 SECTION INCLUDES A. Decorative Wire Rope Railing 1.2 RELATED SECTIONS A. Section 03300 Cast-In-Place Concrete: Placement of sleeves cast in

More information

SECTION EZ-SLIDE 80 AND 180 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS

SECTION EZ-SLIDE 80 AND 180 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS Page 1 of 6 SECTION 08 32 20 EZ-SLIDE 80 AND 180 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS USE THIS SECTION WHEN SPECIFYING OVERHEAD SUPPORTED GLASS PANEL PARTITIONS. SECTION INCLUDES OVERHEAD TRACK ASSEMBLY,

More information

CONCRETE FORMWORK. .2 CSA , Supplement No.1 to CAN/CSA , Engineering Design in Wood. .4 CSA O151, Canadian Softwood Plywood.

CONCRETE FORMWORK. .2 CSA , Supplement No.1 to CAN/CSA , Engineering Design in Wood. .4 CSA O151, Canadian Softwood Plywood. CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 03100-1 PART 1 GENERAL 1.1 Related Work.1 All Division 1 Specification Sections.2 Section 02233 Granular Base.3 Section 02311 Site Grading.4 Section 03200

More information

SECTION CRL50 AND CRL51 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS

SECTION CRL50 AND CRL51 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS SECTION 08 32 20 CRL50 AND CRL51 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS Page 1 of 6 USE THIS SECTION WHEN SPECIFYING OVERHEAD SUPPORTED GLASS PANEL PARTITIONS. SECTION INCLUDES OVERHEAD TRACK ASSEMBLY,

More information

SPECIFICATIONS: Architectural Aluminum Railings

SPECIFICATIONS: Architectural Aluminum Railings PART ONE: GENERAL 1.1 SUMMARY SPECIFICATIONS: Architectural Aluminum Railings A. Work in this section includes custom and standard Interior and Exterior aluminum railings and guardrails. 1.2 PERFORMANCE

More information

Special Provision No. 199S66 March For the purpose of this Special Provision, the following definitions apply:

Special Provision No. 199S66 March For the purpose of this Special Provision, the following definitions apply: QUALITY CONFORMANCE REQUIREMENTS Special Provision No. 199S66 March 2018 1.0 SCOPE This Special Provision describes the process for the assessment of conformance to the quality requirements and the administrative

More information

1. Division 01: Administrative, procedural, and temporary work requirements.

1. Division 01: Administrative, procedural, and temporary work requirements. SECTION 10 2219 DEMOUNTABLE PARTITIONS PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Demountable partition system. 2. Doors. 3. Glazed panels. B. Related Sections: 1. Division 01: Administrative,

More information

Rapid Axial Load Testing of Drilled Shafts

Rapid Axial Load Testing of Drilled Shafts Supplemental Technical Specification for Rapid Axial Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 4, 2015 1.0 GENERAL This work shall consist of performing a rapid axial

More information

SECTION ORNAMENTAL ALUMINUM RAILING

SECTION ORNAMENTAL ALUMINUM RAILING SECTION 05730 ORNAMENTAL ALUMINUM RAILING PART 1 GENERAL 1.1 SECTION INCLUDES A. Aluminum Pipe Railing 1.2 RELATED SECTIONS A. Section 03300 Cast-In-Place Concrete: Placement of sleeves cast in concrete.

More information

Statement of Special Inspections

Statement of Special Inspections Statement of Special Inspections SUCF Project No: Project Title: Registered Design Professionals in Responsible Charge: (Name) (Address) Architect: Structural Engineer: Mechanical Engineer: Identification

More information

A-ONE Insulated Forms Installation Manual

A-ONE Insulated Forms Installation Manual A-ONE Insulated Forms Installation Manual Rockford, MN www.aoneform.com www.diversifoam.com info@diversifoam.com A-ONE Manual 180426.docx Disclaimer Notice The information in the A-ONE Insulated Forms

More information

SECTION CRL70 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS

SECTION CRL70 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS Page 1 of 6 SECTION 08 32 20 CRL70 HEAVY GLASS TOP HUNG SLIDING DOOR SYSTEMS USE THIS SECTION WHEN SPECIFYING OVERHEAD SUPPORTED GLASS [OR WOOD] PANEL PARTITIONS. SECTION INCLUDES OVERHEAD TRACK ASSEMBLY,

More information

SECTION CONTRACTOR QUALITY CONTROL

SECTION CONTRACTOR QUALITY CONTROL SECTION 01451 CONTRACTOR QUALITY CONTROL PART 1 GENERAL 1.1 REFERENCES The publications listed below form a part of this specification to the extent referenced. The publications are referred to within

More information

STRUCTURAL MASONRY SPECIAL INSPECTOR. Study Guide

STRUCTURAL MASONRY SPECIAL INSPECTOR. Study Guide STRUCTURAL MASONRY SPECIAL INSPECTOR Study Guide May 2017 Examination: The Structural Masonry Inspector Examination is based on the references cited in this document. It is 3 hours in length, is an open-book

More information

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS

SECTION GENERAL REQUIREMENTS PART 1 - GENERAL I 1 GENERAL REQUIRMENTS SECTION 01 00 00 GENERAL REQUIREMENTS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Summary of Work: 1. General 2. Contract. B. Contract Considerations: 1. Schedule of values. 2. Applications for payment. 3.

More information

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04 UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04 1. Description This work shall consist of the design, manufacture and construction of a T-WALL structure

More information

Trex Commercial Products page Metal Railing

Trex Commercial Products page Metal Railing SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES A. Classic Railings (Picket). B. GridGuard Railings (Mesh). C. Post Rail (Glass). D. Tensiline Railings (Cable). E. Track Rail (Glass).

More information

Framed Decorative Panel Systems

Framed Decorative Panel Systems Note: This document contains information and notes in hidden text. If you need assistance to view & hide text, instructions are at this link: http://www.marlite.com/hidden-notes-instructions.aspx Delete

More information

CARPENTER STATUTORY DECLARATION OF WORK EXPERIENCE

CARPENTER STATUTORY DECLARATION OF WORK EXPERIENCE To qualify to challenge certification in this trade or be granted authority to supervise and sign-off on apprentices in this trade, individuals must have: worked a minimum of 9,720 hours performing the

More information

SECTION HANDRAILS AND RAILINGS. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION HANDRAILS AND RAILINGS. Display hidden notes to specifier. (Don't know how? Click Here) SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES Display hidden notes to specifier. (Don't know how? Click Here) A. Classic Railings (Picket). B. GridGuard Railings (Mesh). C. Post

More information

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS SECTION 32 14 13.16 PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs used as ballast and/or paving on

More information

1. Bullet resistant hollow metal door and frame assemblies tested in accordance with UL 7 52 and in compliance with the following:

1. Bullet resistant hollow metal door and frame assemblies tested in accordance with UL 7 52 and in compliance with the following: Various Locations PROJECT#: R1401-01 SECTION 083400 -BULLET RESISTANT DOOR AND FRAMES PART 1-GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary

More information

SECTION SECURITY PROTECTION PART 1 GENERAL

SECTION SECURITY PROTECTION PART 1 GENERAL SECTION 13 1010 - PART 1 GENERAL 1.01 SECTION INCLUDES A. Bullet Resistant Aluminum Windows. B. Bullet Resistant Transaction Equipment. C. Bullet Resistant Speakers. D. Bullet Resistant Glazing. E. Bullet

More information

Site Preparation... 2

Site Preparation... 2 TRUFIREWALLS INSTALLATION MANUAL This Installation Manual is intended to assist in the preparation and installation of TruFireWalls products manufactured by Oldcastle Enclosure Solutions. The TruFireWalls

More information

1. Supply, delivery, engineering and installation of new storage equipment.

1. Supply, delivery, engineering and installation of new storage equipment. SECTION 10 51 13 - METAL LOCKERS * ALL FIELDS IN [ ] MUST BE EDITED PART 1 - GENERAL 1.1. RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection SECTION 13090 RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13090-1 LOW INTENSITY RADIATION PROTECTION

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

STRUCTURAL STEEL FRAMING

STRUCTURAL STEEL FRAMING SECTION 05 12 00 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 SUMMARY A. Section includes 1. Structural steel framing 2. Structural steel framing required for support and framing of rooftop mechanical

More information

Marlite Guide Specification 2/24/2017 Surface Systems - MAP375 System SECTION FRAMED DECORATIVE PANEL SYSTEMS PART 1 - GENERAL 1.

Marlite Guide Specification 2/24/2017 Surface Systems - MAP375 System SECTION FRAMED DECORATIVE PANEL SYSTEMS PART 1 - GENERAL 1. Note: This document contains information and notes in hidden text. If you need assistance to view & hide text, instructions are at this link: http://www.marlite.com/hidden-notes-instructions.aspx Delete

More information

SECTION ARCHITECTURAL GLASS HANDRAIL AND RAILINGS

SECTION ARCHITECTURAL GLASS HANDRAIL AND RAILINGS SECTION 05720 ARCHITECTURAL GLASS HANDRAIL AND RAILINGS PART 1 GENERAL 1.01 WORK INCLUDED A. Furnish and install [aluminum] railings and components. 1.02 REFERENCE A. American Architectural Manufacturers

More information

Statement of Special Inspections

Statement of Special Inspections Statement of Special Inspections Project: Location: Owner: Design Professional in Responsible Charge: This Statement of Special Inspections is submitted as a condition for permit issuance in accordance

More information

SECTION The specification section is organized by placing information in three standard parts:

SECTION The specification section is organized by placing information in three standard parts: SECTION 14244 LIMITED USE HYDRAULIC ELEVATOR ***** Since 1982 Liftavator, Inc. has provided limited use/limited application (LU/LA) elevators, residential elevators, hydraulic vertical platform wheelchair

More information

SECTION BASIC ELECTRICAL REQUIREMENTS

SECTION BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions, apply to work of this section. 1.2 SUMMARY A. This section specifies

More information

Section Wood Veneer Ceiling Planks Linear

Section Wood Veneer Ceiling Planks Linear Section 095426 Wood Veneer Ceiling Planks Linear PART 1 GENERAL RELATED DOCUMENTS SUMMARY Drawings and general conditions of the Contract, including General and Supplementary Conditions and Division 1

More information

5 Concrete Placement

5 Concrete Placement 5 Concrete Placement Testing Entrained Air Slump Strength Water/Cementitious Ratio Mixing Placing Concrete Compressive Test Specimens Curing De-Tensioning Multiple Strand Release Single Strand Release

More information

SECTION MECHANICALLY ASSISTED MOBILE STORAGE SHELVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS

SECTION MECHANICALLY ASSISTED MOBILE STORAGE SHELVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS SECTION 10560 MECHANICALLY ASSISTED MOBILE STORAGE SHELVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

SECTION 2XXX TITLE OF SECTION

SECTION 2XXX TITLE OF SECTION APPROVED AND ADOPTED THIS xxth DAY OF month 20xx KANSAS CITY METROPOLITAN CHAPTER OF THE AMERICAN PUBLIC WORKS ASSOCIATION TABLE OF CONTENTS SECTION xx01 TITLE OF SECTION... 1 Definitions (optional)..

More information

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS PRODUCTION SPECIFICATIONS SECTION 03135 INSULATED CONCRETE FORMS PART 1 GENERAL 1.1 SECTION INCLUDES A. Insulated panel permanent concrete form system for: 1. Exterior structural wall panels. 2. Interior

More information

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS

PRODUCTION SPECIFICATIONS INSULATED CONCRETE FORMS PRODUCTION SPECIFICATIONS SECTION 03135 INSULATED CONCRETE FORMS PART 1 GENERAL 1.1 SECTION INCLUDES A. Insulated panel permanent concrete form system for: 1. Exterior structural wall panels. 2. Interior

More information

Project No: Pakenham Branch Library, Pakenham, Ontario Section DECEMBER, 2016 Page 1 of 5

Project No: Pakenham Branch Library, Pakenham, Ontario Section DECEMBER, 2016 Page 1 of 5 DECEMBER, 2016 Page 1 of 5 1 GENERAL 1.01 SUBMITTALS.1 Provide submittals in accordance with Section 01 33 00 - Submittal Procedures..2 Two weeks prior to Substantial Performance of the Work, submit to

More information

1. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces.

1. Temperature Change: 120 deg F (67 deg C), ambient; 180 deg F (100 deg C), material surfaces. SECTION 05500- METAL FABRICATIONS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification

More information

Conditions of the Contract and Division 1 General Requirements are a part of this section.

Conditions of the Contract and Division 1 General Requirements are a part of this section. NOTES TO SPECIFIER General notes about the specifications and the reasons for them are listed here in general statements. Use this as a guide when choosing the correct selection of statements that apply

More information

FYPON, LLC. February 2014

FYPON, LLC. February 2014 Section 06 66 30 EXTERIOR PVC RAILINGS AND GUARDS PART 1 - GENERAL 1.1 RELATED SECTIONS: A. All contract documents apply to work of this section; this includes but is not limited to: Agreement; Drawings;

More information

1. High bay shelving units, fabrication and installation including leveling.

1. High bay shelving units, fabrication and installation including leveling. SECTION 10 56 13 - HIGH BAY SHELVING * ALL FIELDS IN [ ] MUST BE EDITED. PART 1 - GENERAL 1.1. RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary

More information

SECTION STEEL H PILES. A. Section includes steel H piles embedded into drilled concrete piers.

SECTION STEEL H PILES. A. Section includes steel H piles embedded into drilled concrete piers. SECTION 31 62 16 STEEL H PILES PART 1 - GENERAL 1.01 SCOPE OF WORK A. Section includes steel H piles embedded into drilled concrete piers. B. Furnish all labor, materials, equipment and incidentals required

More information

SECTION METAL WALL PANELS

SECTION METAL WALL PANELS Unience USA, Inc. 2115 Linwood Avenue, Suite 500 Fort Lee, NJ 07024 Phone: 201-676-2467 Fax: 201-944-3660 Email: alfrex@alfrexusa.com Web: www.alfrexusa.com SECTION 07 42 13 METAL WALL PANELS PART 1 GENERAL

More information

SPECIAL SPECIFICATION 4491 Type CAC Concrete

SPECIAL SPECIFICATION 4491 Type CAC Concrete 2004 Specifications SPECIAL SPECIFICATION 4491 Type CAC Concrete 1. Description. Remove unsound concrete and replace with Type CAC, calcium aluminate concrete for ultra high early strength concrete repairs.

More information

Façade Architectural Wall Panel System - Guide Specification 3/11/2017 SECTION FRAMED DECORATIVE PANEL SYSTEMS PART 1 - GENERAL 1.

Façade Architectural Wall Panel System - Guide Specification 3/11/2017 SECTION FRAMED DECORATIVE PANEL SYSTEMS PART 1 - GENERAL 1. SECTION 09 7710 FRAMED DECORATIVE PANEL SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: Decorative ½ / ¾ (13mm/19mm) thick prefinished panel with preengineered attachment clip along with hardware

More information

Report of Special Inspections

Report of Special Inspections Project: Project Location: Report of Special Inspections Central Carolina Technical College Advanced Manufacturing Technology Training Center Sumter, South Carolina Permit Number: Owner/Address: 853 Broad

More information

THRESHOLD INSPECTION SPECIAL INSPECTION PLAN. Evangel Temple Addition

THRESHOLD INSPECTION SPECIAL INSPECTION PLAN. Evangel Temple Addition Page 1 of 11 THRESHOLD INSPECTION SPECIAL INSPECTION PLAN PROJECT: Addition OWNER: ARCHITECT: Brennfoerder Architectural Services STRUCTURAL ENGR: Tappana Ondrick Structural Engineers DATE: Sept. 4, 2018

More information

LITHOCRETE ARCHITECTURAL CONCRETE PAVING

LITHOCRETE ARCHITECTURAL CONCRETE PAVING LITHOCRETE ARCHITECTURAL CONCRETE PAVING PART 1 GENERAL 1.1 GENERAL CONDITIONS A. Requirements of "General Conditions of the Contract" and of Division 1, "General Requirements," apply to work in this Section

More information

A. Meet at Project site <insert number> days before starting installation.

A. Meet at Project site <insert number> days before starting installation. SECTION 074643 - COMPOSITION SIDING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Engineered wood cladding. 2. Soffit panels. 3. Trim and fascia. 4. Sealant. 5. Weather barrier. 6. Flashing. 1.2

More information

SECTION (09800) - Suspended Acoustic Baffles. This Section is based on TECHLITE Accent Linear Ceiling Baffles.

SECTION (09800) - Suspended Acoustic Baffles. This Section is based on TECHLITE Accent Linear Ceiling Baffles. SECTION 09 53 00 (09800) - Suspended Acoustic Baffles This Section is based on TECHLITE Accent Linear Ceiling Baffles. PART 1 - GENERAL 1.1 SUMMARY A. Section includes TECHLITE S Accent Linear Ceiling

More information

SOUND & VIBRATION CONTROL FOR BUILDINGS. ISO-SEP 25HD High Dimple Rubber Isolation Mat Specification

SOUND & VIBRATION CONTROL FOR BUILDINGS. ISO-SEP 25HD High Dimple Rubber Isolation Mat Specification July, 2010 Fabricated Sound and Vibration Control Assemblies 13 48 23 [Project] SOUND & VIBRATION CONTROL FOR BUILDINGS ISO-SEP 25HD High Dimple Rubber Isolation Mat Specification This specification has

More information

SECTION DEMOUNTABLE WALLS SKY WALLS - STRATUS SYSTEM

SECTION DEMOUNTABLE WALLS SKY WALLS - STRATUS SYSTEM 1 SECTION 10.22.19 DEMOUNTABLE WALLS SKY WALLS - STRATUS SYSTEM PART 1 - GENERAL 1.01 SUMMARY A. This section includes: 1. Full height center-glazed, butt-jointed partition system. 2. Full height doors.

More information

DIVISION: CONCRETE SECTION: REINFORCING STEEL REPORT HOLDER: SPLICE SLEEVE JAPAN, LTD.

DIVISION: CONCRETE SECTION: REINFORCING STEEL REPORT HOLDER: SPLICE SLEEVE JAPAN, LTD. 0 Most Widely Accepted and Trusted ICC ES Evaluation Report ICC ES 000 (800) 423 6587 (562) 699 0543 www.icc es.org ESR 3141 Reissued 11/2017 This report is subject to renewal 11/2018. DIVISION: 03 00

More information

A. Section includes temporary excavation support and protection systems.

A. Section includes temporary excavation support and protection systems. SECTION 31 50 00 - EXCAVATION SUPPORT AND PROTECTION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

Statement of Special Inspections

Statement of Special Inspections Statement of Special Inspections Project: Location: Owner: Design Professional in Responsible Charge: This Statement of Special Inspections is submitted as a condition for permit issuance in accordance

More information

SECTION Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

SECTION Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces. PART 1 - GENERAL 1.1 SUMMARY A. Section includes the following: 1. Handrails and guardrails. 1.2 PERFORMANCE REQUIREMENTS A. General: In engineering railings to withstand structural loads indicated, determine

More information

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM ARCHITECTURAL SPECIFICATIONS MANUFACTURER: InterBlock LLC PO Box 1123, Sheboygan, WI 53082 Phone Number 920-207-7234 SECTION 03100 STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM PART 1 GENERAL 1.01 Summary

More information

SECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Glenlake Modular Railing System

SECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Glenlake Modular Railing System SECTION 05 5200 ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Glenlake Modular Railing System PART 1 GENERAL 1.01 WORK INCLUDED A. Furnish and/or install post supported stainless steel railings and components.

More information

Soundmaster & Modernfold TECHNICAL DATA

Soundmaster & Modernfold TECHNICAL DATA This specification along with product information and model details can be downloaded from www.modernfold.com SPECIFICATION - SECTION 08 35 13 ACCORDION FOLDING DOORS PART 1 - GENERAL 1.1 RELATED DOCUMENTS

More information

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following: PART 1 GENERAL 1.01 SUMMARY SECTION 03460 TILT-UP PRECAST CONCRETE SANDWICH PANELS A. Work includes, but is not limited to, the following: 1. Architectural precast concrete sandwich wall panels. 2. Integral

More information

SECTION EMBEDDED CMU/SPLIT FACE ARCHITECTURAL PRECAST/SITECAST CONCRETE. A. Site Cast or Tilt-Up CMU/Split Face Concrete Panels.

SECTION EMBEDDED CMU/SPLIT FACE ARCHITECTURAL PRECAST/SITECAST CONCRETE. A. Site Cast or Tilt-Up CMU/Split Face Concrete Panels. SECTION 03460 EMBEDDED CMU/SPLIT FACE ARCHITECTURAL PRECAST/SITECAST CONCRETE PART 1 GENERAL 1.1 SECTION INCLUDES A. Site Cast or Tilt-Up CMU/Split Face Concrete Panels. B. Shop/Plant Cast CMU/Split Face

More information

GEOGRID CONNECTION DETAIL OLYMPIA RADIUS UNIT

GEOGRID CONNECTION DETAIL OLYMPIA RADIUS UNIT PLACE TWO STANDARD CONNECTORS IN EACH UNIT AS SHOWN (VERTICAL ORIENTATION) INSERT TWO CONNECTORS PER HORIZONTALLY ORIENTED BLOCK; INSERT ONE CONNECTOR PER VERTICALLY ORIENTED BLOCK SHIM BETWEEN BLOCK COURSES

More information

STATEMENT OF SPECIAL INSPECTION FORM

STATEMENT OF SPECIAL INSPECTION FORM Project Title: Permit #: Project Address: STATEMENT OF SPECIAL INSPECTION FORM This Statement of Special Inspections is submitted in fulfillment of the requirements of CBC Sections 1704 and 1705. Special

More information

SUPPLEMENTAL TECHNICAL SPECIFICATION

SUPPLEMENTAL TECHNICAL SPECIFICATION July 14, 2015 HIGH STRAIN DYNAMIC LOAD TESTING OF DRILLED SHAFTS 1.0 GENERAL This work shall consist of performing high-strain dynamic testing using a drop weight loading system on a test drilled shaft

More information

19 East Ave. Mullica Hill, N.J Phone: Fax: ARCHITECTURAL FOAM FABRICATORS, LLC.

19 East Ave. Mullica Hill, N.J Phone: Fax: ARCHITECTURAL FOAM FABRICATORS, LLC. Table of Contents Trims...1-17 Sills...18-21 Frieze Boards...22-23 Cornices...24-28 Bands...29-32 Keystones...33-35 Pilasters...36 Columns...37-39 Quoins...40 Arches & Circles...41-42 4 1/2 Trims 7 6 14

More information

Master Specifications for Microcotta November 2017

Master Specifications for Microcotta November 2017 SECTION 042130 - MICROCOTTA PART 1 - GENERAL 1.1 SUMMARY A. Provide Architectural Microcotta, cast architectural polymer resin units manufactured in accordance with the Contract Documents. 1.2 WORK INCLUDED

More information

CONCRETE SEGMENTAL FREESTANDING WALL SYSTEM

CONCRETE SEGMENTAL FREESTANDING WALL SYSTEM CONCRETE SEGMENTAL FREESTANDING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Lakeland TM unit segmental freestanding wall in accordance

More information

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts Supplemental Technical Specification for Bi-Directional Static Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 2, 2015 1.0 GENERAL This work shall consist of furnishing all

More information

Bi-Directional Static Load Testing of Drilled Shafts

Bi-Directional Static Load Testing of Drilled Shafts Supplemental Technical Specification for Bi-Directional Static Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (01/18) 1.0 GENERAL This work shall consist of furnishing all materials, equipment,

More information

SPECIAL INSPECTION AND TESTING FORM

SPECIAL INSPECTION AND TESTING FORM Building Division SPECIAL INSPECTION AND TESTING FORM 4381 Broadway, Suite 201 American Canyon, CA 94503 Inquiries: (707) 647-4581 Inspection Request: (707) 551-4619 www.cityofamericancanyon.org Revision

More information

SECTION HANDRAILS AND RAILINGS. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION HANDRAILS AND RAILINGS. Display hidden notes to specifier. (Don't know how? Click Here) SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES Display hidden notes to specifier. (Don't know how? Click Here) A. Classic Railings (Picket). B. GridGuard Railings (Mesh). C. Invisirail

More information

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories.

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories. SECTION 02830 CHAIN LINK FENCES AND GATES (GALVANIZED) 1.0 GENERAL 1.1 Section Includes A. Fence framework, fabric, gates, and accessories. B. Excavation for post bases; concrete footing for posts. C.

More information

CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS

CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS CHAPTER 13 - MECHANICALLY STABILIZED EARTH WALLS AND PATENTED EARTH RETAINING SYSTEMS DS Temple 13.1 SCOPE This section covers the inspection of mechanically stabilized earth walls and other patented earth

More information

Section Wood Grille Ceiling Panels

Section Wood Grille Ceiling Panels Section 095426 Wood Grille Ceiling Panels PART 1 GENERAL RELATED DOCUMENTS Drawings and general conditions of the Contract, including General and Supplementary Conditions and Division 1 Specification sections

More information

Northpointe Renovation EPN #1701 F/A Prroject #17027 September 8, 2017

Northpointe Renovation EPN #1701 F/A Prroject #17027 September 8, 2017 SECTION 101423.16 - ROOM-IDENTIFICATION PANEL SIGNAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division

More information

SECTION TILT-UP PRECAST CONCRETE. A. Work includes, but is not limited to, the following:

SECTION TILT-UP PRECAST CONCRETE. A. Work includes, but is not limited to, the following: SECTION 03470 TILT-UP PRECAST CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Work includes, but is not limited to, the following: 1. Precast wall panels. 2. Forms and casting beds. 3. Concrete. 4. Reinforcing

More information

CONCRETE TILE PAVERS

CONCRETE TILE PAVERS Section 32 14 13 CONCRETE TILE PAVERS (1995 MasterFormat Section 02780) Note: This guide specification for the U.S. is for the installation of concrete tile paving units whose thickness are less than the

More information

Home Depot Page 1 of 5 HDPB Humacao, PR 10/19/09

Home Depot Page 1 of 5 HDPB Humacao, PR 10/19/09 PART 1 - GENERAL 1.01 SUMMARY A. Types of cold-formed metal framing units include the following: 1. C-shaped steel studs B. Related work specified elsewhere includes but may not be limited to: 1. Section

More information

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION ARDEX GUIDE SPECIFICATION ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) Cast-In-Place Concrete to Receive the ARDEX Concrete Management Systems including ARDEX Self-Leveling Underlayments SECTION 03 30 00

More information

CONCRETE REINFORCEMENT. 1. Supplementary Conditions, General Conditions, General Requirements, shall govern Work of this Section.

CONCRETE REINFORCEMENT. 1. Supplementary Conditions, General Conditions, General Requirements, shall govern Work of this Section. CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 03200-1 PART 1 GENERAL 1.1 General Requirements 1. Supplementary Conditions, General Conditions, General Requirements, shall govern Work of this Section.

More information

SUBSTITUTION REQUEST (After the Bidding/Negotiating Phase)

SUBSTITUTION REQUEST (After the Bidding/Negotiating Phase) SUBSTITUTION REQUEST (After the Bidding/Negotiating Phase) Project: Substitution Request Number: From: To: Date: A/E Project Number: Re: Contract For: Specification Title: Section: Page: Description: Article/Paragraph: