1. Information Required

Size: px
Start display at page:

Download "1. Information Required"

Transcription

1 1. Information Required 1.1 Job Specification Job specification contains design criteria, agreed between Company and Client, affecting pipe rack design: Battery limit, valving and spade requirements. Catwalk, platform and ladder access to valves and relief valves in pipe rack. Minimum headroom and clearances under overhead piping or supporting steel within areas. Pipe ways and secondary access ways. Main access roads. Rail roads. Standard to be used for minimum spacing of lines in pipe racks. Handling and headroom requirements for equipment positioned under pipe racks. Operating and safety requirements affecting pipe rack and structure design. Location of cooling water lines underground or above ground. Trenched piping, if any. 1.2 Process Flow Diagrams Process flow diagrams show main process lines and lines interconnecting process equipment. 1.3 Engineering Flow Diagrams Engineering flow diagrams are developed from process flow diagrams and show: Pipe sizes. Pipe classes, and line number Valving. Mani folding. All instrumentation. Equipment and lines requiring services, i.e. water steam, air, nitrogen etc. 1.4 Utility Flow Diagrams Utility flow diagrams show the required services: Steam Condensate Water Air Gas Any additional services peculiar to the plant being worked on.

2 2. General The pipe way conveys all main process lines connecting distant pieces of equipment, relief and blow down headers, all lines leaving and entering the plant, utility lines supplying steam, air, cooling water and inert gas to the plant. Electrical and instrument cable trays are usually routed in the pipe way. Pipe ways are classified by their relative elevation to grade. 2.1 ABOVE GROUND:- a) Pipe rack:- Overhead piping supported on steel or concrete bents. b) Pipe track/pipe sleepers:- - Above ground piping supported on concrete sleepers at grade level. - This type of pipe way is generally associated with offsite areas where equipment is well spaced out, and land space is not a premium. - Wherever piping is laid on pipe sleepers, hard surfacing/gravel is provided below it, hard surfacing/gravel should be completed before start of pipe laying. Width of hard surfacing/gravel shall be about 1 meter more than the piping corridor on either side. This extra hard surfacing/gravel shall be for movement of operating personnel along the piping corridor. This movement area shall be approachable from the road at a distance of every 500 mtrs. Pipe track Width Pipe track width may be estimated using the method detailed for pipe rack. Spacing of Pipe track Sleepers Pipe track sleepers are relatively cheap thus piping economy is dictated by the recommended span of the smallest line in the track. Where small bore lines are few, sleeper spacing may be determined by the pipe span of large bore lines provided small bore lines are supported off the larger lines at adequate intervals. An angle with U bolts is sufficient (check with Pipe Support Section). For recommended pipe support spans, use Company standard. On an average minimum span = 3 meters Maximum span = 6 meters Depending on line size and substance carried in pipes, (i.e. gas or liquid). Pipe track Elevation Pipe track elevation is set by maintenance access to piping items located underneath the pipe track, i.e. drains and steam traps. A minimum of 12 /300 mm clearance between underneath of lines and grade is recommended; where necessary, this may be increased to 18 /450 mm. As pipe tracks are generally single tier, no change in elevation is necessary at changes of direction. This is affected by use of a flat turn.

3 Line Location Line location with reference to bore and weight is unnecessary, as all pipes are supported on sleepers which rest directly on the ground. Line routing is all important. All lines interconnecting process equipment and/or storage tanks located on left-hand side of pipe track are placed to the left-hand side. Similarly, all lines interconnecting equipment located on right-hand side of pipe track are placed to the right of pipe track. Lines interconnecting equipment located on either side of pipe track are placed near the centre of pipe track. Line Spacing Use Company job specification recommended pipe track spacing. Road Crossings The standard method is to provide culverts under access roads. Elevating piping on a cross-over rack is expensive and introduces unnecessary pockets in the lines thus routed. When determining width and height of culvert, care must be taken to allow sufficient room round the pipe work for maintenance, insulation and painting. Where only one or two lines cross a road, crossing may be by means of sleeves set under roadway. Access Ways In areas needing frequent access, platforms may be provided across pipe track. Valves Where possible, these should be grouped at the edge of an access platform for ease of operation. Drain valves where possible should be brought to outside of pipe track for ease of operation. The same applies to steam trap assemblies.

4 Expansion Loops Horizontally elevated expansion loops above pipetrack should be provided where necessary. Group all hot lines requiring expansion loops, hottest and largest line on the outside, on one side of pipetrack. (Generally, the side chosen is that side which has the highest number of take-offs serving equipment on that side). 2.2 UNDERGROUND:- The piping system is taken underground generally for the utility services like cooling water supply to various units and cooling water return to cooling tower for line sizes normally 18 inch NB and above, other water services with big pipeline sizes, big oil supply lines and various sewer systems in the process units of the chemical, petrochemical and refinery type of plants. The underground system consist of gravity flow drainage system carrying process waste, spillage, reclaimable hydrocarbons, sanitary and storm water, firewater and drinking water. a) Sewer Lines (1) Oily (2) Non Oily (3) Chemical (4) Sanitary Sewer b) Water Lines (1) Cooling Water (2) Potable Water (3) Sea Water (4) Industrial Water c) Fire Extinguishing Lines (1) Foam Extinguishing (at the time of Laying Piping) (2) Fire Fighting Water d) Trench (1) Electrical Cable (2) Piping for Process a) Trench Piping:- - Below ground piping laid in connection trenches. - Costly and usually undesirable; unless trenches are wide, shallow and well vented. - Heavy gases may settle and create a fire hazard through the length of the trench. For these reasons, only pump out lines, chemical sewers or chemical drain collection systems are sometimes placed in trenches and routed to a pit or underground collection tank.

5 In most plants, trenches are avoided due to problems associated with this type of pipe way: High initial cost. Fire hazard Trenchers are used to route lines such as: Pump out lines Chemical sewers Chemical drains Trenchers must be wide enough to allow sufficient clearance between trench wall and piping. 150 mm between outside of pipe and inside of wall is the minimum acceptable clearance. This will allow for installation of piping, painting and future maintenance. Total width of trench required may be determined by using method detailed above. Piping Department will advise Civil Department of requirements. Line Spacing Line location in a trench carrying a number of lines should be carefully chosen for maximum piping economy consistent with stress requirements, if any. Open trenches require drains to stop accumulation of surface water. Trench bottom should be sloped towards drain points. In this case, pipe supporting is by means of angle steel or I beams set into the walls, allowing bottom for free drainage to nearest drain point. This method allows drainage of a trench by a minimum of drain points between each pipe support as would be the case of solid concrete pipe supports built up from the trench. Before proceeding on trench drainage check with coordination procedure and Civil Department for water table level. Safety Precautions Most trenches have either a cover of concrete slabs or a grating. Where flammable liquids are carried in trenched lines, a fire break is provided at suitable intervals along a trench and at each intersection. This generally consists of two concrete walls 1 M M apart, with the space in between filled with sand. Where highly flammable gasses are carried, the whole trench, after installation of piping, is back filled with sand. Piping will advise Civil Department of requirements. Problems with Trenching Repairs generally require that a trench be opened for access. Many of these lines are far below grade and special precautions are required to ensure the safety of workers who enter these excavations. Sloping of trenches is usually only available on Greenfield sites. The trench slope is

6 laid back at an angle shallower than the angle of repose of the soil. This often requires a wide right-of-way. OSHA Standard for Trench pipe maintenance: (b) Employee safety and health training (a) Protect employees with shoring or sloping (b) Locate the utilities; contact the utilities (one-call system) (c) Provide egress from the trench or excavation (h) Protect employees from water accumulation in trench (j) Spoil pile or excavated material must be placed at least two feet from edge of excavation (k) Inspect trench or excavation on a daily or as-needed basis. b) Buried Piping:- - Piping direct buried below ground level. - Due to costly maintenance and the usually corrosive nature of soil, this method of routing is generally reserved for sewer and drain lines. - In some plants, especially in cold climates, cooling water lines are buried below the frostline. This should be determined at the beginning of a job, is generally a Client request. Keep buried piping to a minimum. Generally only sewer drain lines and fire mains are located below ground. In some cases due to Client or climate requirements, cooling water lines are also buried below the frost line. With future maintenance in mind, buried lines should be located well clear of foundations, and if running side by side, well spaced out. A minimum of 300 mm clearance is necessary between foundations and lines and between the lines themselves. Above ground safe drain-tails will enter below ground drain line via a tundish (concentric reducer normally) or if a sealed system and cooling water lines by a flanged stub raised above ground. Flanged connections should be a minimum of 300 mm above prevalent grade level. It is advantageous to set a common level for all these take offs at the outset of the job. When locating tie-in connections to underground systems, especially from elevated drain points, and adjacent to equipment plinths, ensure adequate clearance. All buried steel pipes should have applied a corrosion resistant coating and wrapping. Deep valve boxes for buried lines should be designed with ample room inside the box for a maintenance man to bend over and use wrenches for tightening flanges of re-packing valves. Consideration should be given to the use of concrete pipe in lieu of square boxes. The criteria for a good underground piping design should be ease of maintenance. Piping should be so spaced as to allow easy digging out and replacement of faulty sections; for this reason, never run underground piping under or through foundations. Pipe sleeves for underground piping Process facilities generally have pipe racks on which piping runs. These pipe racks allow the piping to be laid out over roads as well, leaving sufficient space for vehicles to pass below. But there are instances when pipe rack is not available at a particular location or it is not feasible to use pipe rack for piping. In such cases underground piping has to be done. In process plants cranes weighing up to more than 10 tons travel on roads. This load is born by the soil under roads. If we just dig a trench and lay the piping then every time when any heavy vehicle passes over that road, the pipe will also have to bear the load. In order to avoid any pipe leakage due to crushing load of the vehicle a pipe sleeve is used. Pipe sleeve is simply a pipe of heavy schedule

7 pipe and its size is approximately 2 to 3" larger. This sleeve is inserted such that load is now born by the sleeve and not the pipe itself. Under Ground Piping Basically the underground piping falls into one of two categories, process lines & drain lines. Process piping is probably the easiest routed enters the ground at point "A" and follows a routing that should be half way agreed on by the powers that be on the project by this time, and exits the ground at point "B" only issues are line spacing, burial depth, & corrosion protection on the pipe (if any). Drain piping is more complicated, this normally falls in two categories pressure drains, and gravity drains. Pressure drains are a "closed systems" that utilize pressure to push the commodity through the piping system. This piping is normally routed in the same trench with gravity drains. This is a "closed system" cleans out are not required in these lines, and this piping does not need to be sloped. Gravity drains are an "open system" that utilizes a sloped piping system so the commodity can get from point "A" to point "B" on its own utilizing the gravitational force acting on it. This "open system" means at points along this piping system there are branches to this piping that is open to the atmosphere to allow two things to happen, first and most important, this is where the waste commodity is introduced into the drain header. Secondly this is where the system is "vented" this allows the commodity to run down the system (kind of like putting a straw down into a container of liquid and putting your thumb over the end of the straw, with drawing the straw, the liquid will remain in the straw until you remove your thumb and the liquid is allowed to flow out of the straw, because the system (straw) was allowed to "vent", same thing on a gravity drain). Sloping drain headers - A gravity drain system is where the piping is sloped to utilize gravitational forces action upon it to get the waste commodity to where it can be properly taken care of or stored. Drain headers are normally run in there own trench with other drain headers. This is for a few reasons, first it is easier to slope the system if that has to occur with other sloped lines. Now pressure drains are routinely run with sloped gravity drains, normally because they end up in the same place (or close to it). Pressures drains don't require sloped piping, BUT it doesn't hurt that it is! Trying to slope some lines and not others in the same trench becomes a major construction headache so sloping the drains becomes the determining factor in the same trench, not only for engineering reasons, but only for a construction factor. This also dictates that any other buried lines that are routed with gravity drain will be configured using the 45 deg. ells. & a short spool piece between them, for any 90 Deg. change in direction (see this discussion in Clean-Outs) again because it is routed with gravity drains that do require this "unique" configuration. As I mention earlier sloped drain systems can get pretty deep over a long run, so it is advantageous to centrally locate the buried drain tank(s), ponds, or waste disposal area where the waste commodity eventually ends up, where-by shortening the drain system piping that enter this area. This does not mean dead in the middle of the facility! But off-set to the side, waste disposal is not normally the most important "system" in a facility, so it wouldn't occupy a prime spot in that facility.

8 Clean-outs these are the other branch connections on the main drain header. They are usually a 45 deg. lateral off the main header, & a 45 deg ell. in the vertical, and a threaded cap or a flange with a blind at the end. These clean-outs (C/O) are spaced approx. every 100 foot to provide a "port" so if the drain header becoming plugged maintenance people can go to this point, open up the port and introduces a "roto-router" (rotating blade at the end of a flexible cable) to be able to clear out the plug. This tool can normally reach about 100 ft., so positioning clean-outs ever 100 ft on the header is critical in case plugging does occurs deep in the drain header. This tool is very flexible and "could" make it through a couple 90 Deg ell., but the drain header needs to be designed to utilize this roto-router tool's flexible and not impede it, so all changes in direction on the drain header are done using 45 deg ell.s and not 90 Deg. ell.s (this helps the flow also). This configuration is also used in positioning/routing "drain funnels or drain hubs", this is because these points "could be" used to introduce this rooter-router tool as well, especially if the plug has occurred in that branch before the main header. A few design notes, as stated before, spacing for C/O's are approx. 100 ft., but there is another controlling issue, you don't want to try to push a roto-rooter through more then 5 fittings (this is a rule of thumb only) so a C/O would be required closer then the 100 ft. in this situation. One last clean-out location that needs to be discussed is the one on the very beginning of the main drain header. This is a configuration of 2 each 45 deg. ell.s in the vertical and a flange & blind (flg'd because of the larger size of the main header) could be a threaded cap on smaller drain headers. This is probably the most important one because it's the first entrance into the main drain header. It should be located where it can be easily accessed for maintenance equipment (all C/O's should be readily accessible!). An issue that can happen with all C/O's is "if" they could occur where there is vehicular traffic. Having a directly connected piping system exposed to traffic would cause stress/damage issues to that piping system. To eliminate this issue "covers" are fabricated to cover these C/O's. These covers have lids on them to be able to readily access these clean outs. These covers are basically a larger size section of pipe so you have 1" to 3" inches of clearance of any C/O flanges, this larger pipe would have 3 to 4 "lugs" welded to the inside and spaced roughly an 1" from the top edge so as a circular plate steel lid could be fashioned to just fit the inside bore of this "cover". A 1" diameter hole would be positioned into the center of this lid so the maintenance people could use a tool to remove this lid. Lid thickness to be able to with stand the traffic say around 3/8" to ½" thick. Design note - With the clean-out flange just fitting inside this cover, hex. headed bolts will have to be tackwelded to the underneath side of the flange so nuts are accessible from the top. Underground verses Overhead Piping:- The main criteria to be taken into account when deciding on the best design basis for pipe ways are economics, constructability, maintenance requirements and the process. Other aspects include the least interference to local or state amenities such as roads and railways, the minimum amount of interface and permit activities with local and state authorities and the protection of the local environment. The project will use overhead piping routes within the confines of the refinery to give ease of access for maintenance and fire fighting, to allow freedom of movement around the site without having to negotiate barriers created by low level pipeways and to give a more compact layout leading to economical piping design. Low level pipe ways will be used in offsite locations which in turn will reduce installation costs.

9 It is not considered good engineering practice to place hydrocarbon lines underground due to: * The detrimental effect to the environment in the event of a leak. * The widely differing effects on the piping stresses due to external forces. * Lack of maintenance access. Underground process piping is subjected to enormous external loads and material stresses due to thermal expansion, for example, a 12 sch 140 CS pipe operating at 100 deg.c would generate an anchor force of 500 tonnes over a distance of 1 km resulting in an anchor block, subject to soil conditions, of approximately 500 cu.m of concrete. Wall thickness usually has to be increased to compensate for the additional loads applied therefore increasing material costs. Additionally, piping would require external coating for protection against corrosion. It is not advisable to bury stainless steel lines close to shorelines due to the high risk of chloride attack from the saline conditions expected. External coating would be required but, this would be subject to damage during installation and friction due to thermal expansion. Cooling water and firewater piping are the only systems that are considered suitable to be buried due to the operating temperatures and very little or no thermal expansion.in the case of the cooling water system, the large sizes, due to their bulk, would take up a large amount of useful space. Large bore cooling water lines within the confines of the refinery complex will be buried but lines up to 30 may be located in the piperacks.generally, lines in the offsites and tankage areas will be above ground.however, it is essential that the extent of rock blasting is minimised and the philosophy regarding buried lines will be influenced by the results of terracing studies which will determine the cut & fill requirements. Firewater lines within the confines of the refinery will be buried but within the offsites and tankage areas these will above ground on sleepers. Effluent piping to the water treatment areas will be reviewed individually. Lines requiring a slope may be buried but lines being pumped will be placed overhead. Pipes should not be buried unless a clear-cut advantage can be gained. The main advantages of buried pipes are protection from freezing, fire, or accidental damage and these are valid reasons for burying fire mains or in exceptional cases, cooling water supplies if guaranteed flow under emergency conditions is essential. When pipes are buried, some general precautions should be taken Pipes should be below frost line or be buried to a minimum depth of 2 ft 6 in (0.75). Pipes passing under roads or access ways should be cased in concrete. If pipes run near roads or across cables, they must always be below cable level. Gas pipes should not be laid within 1 ft (0-3m) of plastic or asbestos potable water pipes. Provision must be made for valve chambers constructed in brick or concrete. Trench routes must be defined at an early stage in the job so that pipes clear foundations and the trenches can be dug during the main site civil works activity. Trench routes should not interfere with construction access. Full and accurate record drawings should be made of buried pipes for future use by the works.

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS

DUKE UNIVERSITY CONSTRUCTION & DESIGN STANDARDS 1 33 63 00 - Underground Steam and Condensate Distribution System 1. Introduction A. Steam is distributed to University and Medical Center buildings through an underground piping system year-round at a

More information

Chapter 10. Pipeline Installation

Chapter 10. Pipeline Installation Chapter 10 CHAPTER 10 STOCKWATER PIPELINE INSTALLATION TABLE OF CONTENTS PART 10.1 TRENCHING 10-1 10.1.1 Backhoe Constructed Trench 10-1 10.1.2 Trencher Constructed Trench 10-1 10.1.3 Backfilling and Maintenance

More information

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED

Read Only Copy Not For Distribution. Chapter 17. Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.2 QUANTITY OF WATER REQUIRED Chapter 17 Private Potable Water Supply Systems 17.1 GENERAL REGULATIONS 17.1.1 Applicability The regulations in this chapter apply to any private potable water supply system where plumbing fixtures are

More information

SECTION SLUDGE HOLDING TANK DEWATERING

SECTION SLUDGE HOLDING TANK DEWATERING SECTION 13215 SLUDGE HOLDING TANK DEWATERING PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Dewatering and cleaning of sludge holding tank and sludge disposal. Contractor shall pay for all sludge removal,

More information

Excavation Safety Program

Excavation Safety Program Excavation Safety Program Excavation, Trenching & Shoring Safety I. Purpose The purpose of this policy is to establish safe operating procedures for any earthwork or underground work that is done on a

More information

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1

UNIVERSITY OF MISSOURI Hydronic Energy Distribution 2016 Q1 GENERAL: The scope of this document is to provide instruction for the installation and testing of chilled water piping installed for the University of Missouri. DESIGN GUIDELINES: 1. Materials 1.1. Pipe

More information

If a new residence s electrical service is not located within 200 feet of existing

If a new residence s electrical service is not located within 200 feet of existing Primary Line Extensions CHAPTER 4 If a new residence s electrical service is not located within 200 feet of existing primary electrical facilities, a primary line extension is required to place a close

More information

DUO-THERM 505 Specification Guide

DUO-THERM 505 Specification Guide STANDARD SPECIFICATION 3.101 7.01.08 Part 1 - General Duo - Therm 505 Steel Piping Systems suitable for Steam, High Temperature Hot Water, Gravity and Pumped Condensate. 1.1 Pre-insulated Piping - Furnish

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION

San Antonio Water System Standard Specifications for Construction ITEM NO. 812 WATER MAIN INSTALLATION ITEM NO. 812 WATER MAIN INSTALLATION 812.1 DESCRIPTION: This item shall consist of water main installation in accordance with these specifications and as directed by the Engineer. 812.2 MATERIALS: The

More information

Multicell. Vikimatic MultiCell Conduit Systems MULTICELL

Multicell. Vikimatic MultiCell Conduit Systems MULTICELL Multicell Vikimatic MultiCell Conduit Systems These guidelines should help you install MultiCell Conduit in the simplest way possible and should be read in their entirety before attempting to install the

More information

A. Codes and Standards that are Standard at the University: 1. AGA Compliance: LC 1-91 Interior Fuel Gas Piping Systems

A. Codes and Standards that are Standard at the University: 1. AGA Compliance: LC 1-91 Interior Fuel Gas Piping Systems PART 1: GENERAL 1.01 Purpose: This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is to

More information

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service.

Contact Clark Public Utilities Construction Services department at (360) to initiate a request for service. CHAPTER3 Clark Public Utilities Commercial Electric Service Handbook Commercial Underground Services Preparing for the installation The following checklist will assist in preparing a project for the installation

More information

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer

More information

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS

NORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS PART 1 GENERAL 1.01 SUMMARY Section 15140 PIPE HANGERS, This Section includes the furnishing and subsequent installation of: A. Pipe and equipment hangers, supports, and associated anchors B. Equipment

More information

THE SASKATCHEWAN CODES OF PRACTICE GAS INSTALLATION SUPPLEMENT CSA-B PROPANE STORAGE AND HANDLING CODE

THE SASKATCHEWAN CODES OF PRACTICE GAS INSTALLATION SUPPLEMENT CSA-B PROPANE STORAGE AND HANDLING CODE THE SASKATCHEWAN CODES OF PRACTICE GAS INSTALLATION SUPPLEMENT CSA-B149.2-15 PROPANE STORAGE AND HANDLING CODE Revision Date: CONTENTS The following clauses have been amended, noted, explained or added

More information

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure ArchCast Bridge 3-Sided Precast Concrete Bridge Structure Installation Manual Salem Location: 749 West Commercial Ave. Salem, IL 62881 (618) 548-1190 countymaterials.com Email: info@countymaterials.com

More information

CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD

CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD SPECIFICATIONS Establishing Minimum Standards for as Related To Fire Protection STANDARD # 103 REVISED 04/01/19 PAGES 7 SCOPE: These specifications shall

More information

On-Site Leaching Chamber Specifications & Features. Design & Installation Manual New York

On-Site Leaching Chamber Specifications & Features. Design & Installation Manual New York On-Site Leaching Chamber Specifications & Features Design & Installation Manual New York 1 This manual provides general design and installation information for use of Arc plastic leaching chambers in the

More information

INSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!

INSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING! DURA - TRENCH INSTALLATION GUIDE This guide is intended to aide in the installation of Dura-Trench systems. There are many different applications and situations for the use of this product and the installation

More information

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES

SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES SECTION 4 - DESIGN STANDARDS FOR WATER DISTRIBUTION FACILITIES 4.1 GENERAL REQUIREMENTS 4.1.1 Water and fire protection distribution facilities are to be provided solely for the purpose of supplying potable

More information

SECTION MEASUREMENT AND PAYMENT

SECTION MEASUREMENT AND PAYMENT SECTION 01026 PART 1 GENERAL 1.1 SECTION INCLUDES A. Explanation and Definitions B. Measurement C. Payment D. Schedule of Values E. Application for Payment 1.2 EXPLANATION AND DEFINITIONS A. The following

More information

T a b l e o f C o n t e n t s

T a b l e o f C o n t e n t s C i t y o f G l a d s t o n e P u b l i c W o r k s D e s i g n S t a n d a r d s T a b l e o f C o n t e n t s SECTION THREE SANITARY SEWER REQUIREMENTS... 1 3.0000 SANITARY SEWERS... 1 3.0010 General

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 02514 MANHOLES 1.0 GENERAL 1.1 SCOPE This section provides for construction of sewer manholes complete in place, including the furnishing and adjusting to grade of an existing

More information

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES

GUIDANCE MEMO NO : GUIDANCE CRITERIA FOR THE SEPARATION OF WATER MAINS AND NON-POTABLE PIPELINES State of California Memorandum Department of Health Services Date: April 4, 2003 To: From: Subject: Regional and District Engineers David P. Spath, Ph.D., Chief (Original signed by Dave) Drinking Water

More information

16. Design of Pipeline Structures.

16. Design of Pipeline Structures. 16. Design of Pipeline Structures. a. General. 1) The following guidelines are for the design of structures for water and sewer pipelines including structural concrete and miscellaneous metals design.

More information

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building... Contents 11. Construction processes and materials... 11-2 11.1 Power House... 11-2 11.2 Maintenance Building... 11-2 11.3 Fuel Treatment Building... 11-3 11.4 Roads & Paths... 11-3 11.5 Fencing... 11-3

More information

On-Site Leaching Chamber Specifications & Features. Design & Installation Manual Ohio

On-Site Leaching Chamber Specifications & Features. Design & Installation Manual Ohio On-Site Leaching Chamber Specifications & Features Design & Installation Manual Ohio 1 This manual provides general design and installation information for use of Arc plastic leaching chambers in the State

More information

Rockwood Water People s Utility District Cross Connection Implementation and Regulations

Rockwood Water People s Utility District Cross Connection Implementation and Regulations Rockwood Water People s Utility District Cross Connection Implementation and Regulations To ensure clean, safe, potable water, Rockwood Water People s Utility District (PUD) maintains a cross connection

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES

San Antonio Water System Standard Specifications for Construction ITEM NO. 813 WATER SERVICE FOR FIRELINES ITEM NO. 813 WATER SERVICE FOR FIRELINES 813.1 DESCRIPTION: This item shall consist of water service for fire line installations in accordance with these specifications and as directed by the Engineer.

More information

TYPICAL INSTALLATION INSTRUCTIONS

TYPICAL INSTALLATION INSTRUCTIONS TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect

More information

CONDUITS AND FITTINGS

CONDUITS AND FITTINGS CONDUIT AND FITTINGS Rigid Steel Conduit 3801 Rigid PVC Conduit 3803 HDPE Conduit 3803 Flexible Non Metallic Liquid Tight Conduit Type LFNC-B 3804 PVC Coated Urethane Lined Galvanized Rigid Steel Conduit

More information

Errata for the 2003 Uniform Plumbing Code Study Guide (5th Printing)

Errata for the 2003 Uniform Plumbing Code Study Guide (5th Printing) Errata for the 2003 Uniform Plumbing Code Study Guide (5th Printing) The following is a list of changes that we found after the fifth printing of the 2003 Uniform Plumbing Code Study Guide. These changes

More information

BACKFLOW PREVENTION ASSEMBLY INSTALLATION STANDARDS

BACKFLOW PREVENTION ASSEMBLY INSTALLATION STANDARDS Revised May 2014 BACKFLOW PREVENTION ASSEMBLY INSTALLATION STANDARDS All backflow prevention assembly installation shall be in accordance with the following Standards unless otherwise directed or approved

More information

A. This section is intended to provide design guidelines for Utility Direct Buried Piping and Conduit Systems.

A. This section is intended to provide design guidelines for Utility Direct Buried Piping and Conduit Systems. Date Description of Change Pages / Sections Modified ID 6/15/16 Entire document - mgl44 PART 1 - INTRODUCTION 1.1 PURPOSE A. This section is intended to provide design guidelines for Utility Direct Buried

More information

H. Underground Transmission System Design

H. Underground Transmission System Design H. Underground Transmission System Design In addition to analyzing potential routes, the Company considered several different design technologies for the proposed underground transmission supply lines,

More information

SECTION PLUMBING DRAINAGE AND CONTAINMENT. Copyright Specialloy Industries Inc. dba Slot Drain Systems - All rights reserved

SECTION PLUMBING DRAINAGE AND CONTAINMENT. Copyright Specialloy Industries Inc. dba Slot Drain Systems - All rights reserved SECTION 22 14 00 - PLUMBING DRAINAGE AND CONTAINMENT Copyright 1998-2017 Specialloy Industries Inc. dba Slot Drain Systems - All rights reserved PART 1 GENERAL 1.1 SECTION INCLUDES A. SLOT shaped, non-grated,

More information

GENERAL UTILITIES REQUIREMENTS

GENERAL UTILITIES REQUIREMENTS 33 00 00 GENERAL UTILITIES REQUIREMENTS i. 01 41 26.02 Local Utility Information & Locate ii. 23 05 19 Meters and Gages iii. 33 10 00 Water Utilities Public Water Distribution System iv. 33 12 13.13 Water

More information

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe

PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe Design and Installation Guide PVC Fittings & Laterals for Solid-Wall PVC Sewer Pipe TABLE OF CONTENTS Introduction 2 Products 3 Main-Line Fittings & Service-Line Fittings 3-4 Connections to Dissimilar

More information

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES SECTION 02221 EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 02200 - Earthwork. 2. 02660 - Water Systems. 3. 02720 - Storm Drainage System. 4.

More information

OUTLAW AUTOMATION INC. Safety Management System

OUTLAW AUTOMATION INC. Safety Management System Preparation: Safety Mgr Authority: President Issuing Dept: Safety Page: Page 1 of 6 Purpose The purpose of this program is to provide employees general information for working on owner client or other

More information

Underground System. Description

Underground System. Description Description Insapipe is a factory fabricated and insulated Underground piping system designed for direct burial into an unlined trench. The product is manufactured generally to British Standard 4508 for

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

CHAPTER 11 CONDUITS AND FITTINGS

CHAPTER 11 CONDUITS AND FITTINGS CONDUITS AND FITTINGS CHAPTER 11 CONDUITS AND FITTINGS The standards and requirements for conduits and fittings used for traffic control signal and lighting systems are presented in this chapter. 11.1

More information

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations.

To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 1.0 PURPOSE To establish the Panama Canal Authority (ACP) occupational safety requirements for excavations. 2.0 BACKGROUND Excavation activities are highly dangerous and thus require adequate planning

More information

PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!

PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING! INSTALLATION GUIDE This guide is intended to aide in the installation of Dura-Trench systems. There are many different applications and situations for the use of this product and the installation procedures

More information

GV 001 Equipment Bases and Enclosures General Information

GV 001 Equipment Bases and Enclosures General Information Eq u ip me n tba s e s a n d En c lo s u re s Ge n e ra lin fo rma tio n E n g in e e r :R.An th o n GV0 0 1 Ap p r o v e r :Jo s h u a Jo n e s Ap r 1 7 2 0 Ap r1 7 GV 001 Equipment Bases and Enclosures

More information

Weholite LIGHTWEIGHT PIPE SYSTEM

Weholite LIGHTWEIGHT PIPE SYSTEM Weholite LIGHTWEIGHT PIPE SYSTEM The lightweight pipe that takes a heavier load Weholite pipe is large diameter, profile wall pipe made from highdensity polyethylene (HDPE) resin, which is manufactured

More information

EFFECTIVE FEBRUARY note: drainage permit required to call for a dampproof inspection

EFFECTIVE FEBRUARY note: drainage permit required to call for a dampproof inspection EFFECTIVE FEBRUARY 2014 note: drainage permit required to call for a dampproof inspection PERMITS & INSPECTIONS 750 17th Street West Vancouver BC V7V 3T3 westvancouver.ca/permits t: 604-925-7040 f: 604-925-7234

More information

7. Allowable Fittings.

7. Allowable Fittings. 7. Allowable Fittings. a. General Requirements. 1) The fittings listed in this section are generally the allowable fittings for the design of DIP and PVC pipe. For steel pipe and fittings, see Part One,

More information

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES 3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In

More information

Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS

Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS Precast Concrete Trench Drain Systems INSTALLATION INSTRUCTIONS GENERAL INSTALLATION INSTRUCTIONS 1 Ensure that the trench where the channels are going to be installed has enough room for the appropriate

More information

FS-DUO. Wastewater Flow Distributor Technical Data. Submittal Special Precautions Specifications Installation. (62.2 cm) (62.2 cm)

FS-DUO. Wastewater Flow Distributor Technical Data. Submittal Special Precautions Specifications Installation. (62.2 cm) (62.2 cm) Wastewater Flow Distributor Technical Data Submittal Special Precautions Specifications Installation 24½" (62.2 cm) 12½" (31.8 cm) 24½" (62.2 cm) (30.5 cm) SUBMITTAL STANDARD: 4" plain end inlet/outlet

More information

SECTION GROUND WATER STORAGE TANKS

SECTION GROUND WATER STORAGE TANKS SECTION 33 16 13 GROUND WATER STORAGE TANKS PART 1: GENERAL 1.01 SCOPE A. Section includes requirements for designing, fabricating, and erecting a welded steel ground storage tank. 1.02 SYSTEM DESCRIPTION

More information

TABLE OF CONTENTS

TABLE OF CONTENTS DIVISION 33: SEWER AND SEPTIC SYSTEMS 33 3633 UTILITY SEPTIC TANK DRAINAGE FIELD TABLE OF CONTENTS 33 0000-1 SECTION 33 3633-- UTILITY SEPTIC TANK DRAINAGE FIELD PART 1 - GENERAL 1.1 SUMMARY A. Includes

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

Installation & maintenance instructions

Installation & maintenance instructions One piece, KD & 2 part cold water storage tanks Installation & maintenance instructions Nicholson Plastics Ltd. GRP Specialist since 1968 Table of contents 1. Guidelines for locating water tanks... 1 2.

More information

PIP PCEPA003 Process Analyzer System Field Installation Guidelines

PIP PCEPA003 Process Analyzer System Field Installation Guidelines January 2016 Process Control PIP PCEPA003 Process Analyzer System Field Installation Guidelines PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort to minimize the cost of process industry facilities,

More information

1. Required Minimum Flow:

1. Required Minimum Flow: SECTION 6 6. 6.01 General The City of Castle Rock Water System Minimum Standards and Specifications are minimum base level performance, design, and construction standards used to maintain uniformity of

More information

DOUBLE WALLED PIPING SYSTEMS

DOUBLE WALLED PIPING SYSTEMS DOUBLE WALLED PIPING SYSTEMS The design and construction of a double wall pipe is more complex than a single wall pipe because of the additional pipe, associated welds and tie in procedures. There are

More information

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction. Design Manual Chapter 3 - Sanitary Sewers 3C - Facility Design 3C-1 Facility Design A. Capacity of Pipe Pipe sizes 15 inches and smaller should carry the peak flow at a depth of no more than 0.67 of the

More information

SV24. Submittal Special Precautions Specifications Installation. 12½" (31.8 cm) 12½" (31.8 cm) 12" (30.5 cm) 12" (30.5 cm) 12" (30.

SV24. Submittal Special Precautions Specifications Installation. 12½ (31.8 cm) 12½ (31.8 cm) 12 (30.5 cm) 12 (30.5 cm) 12 (30. Wastewater Sampling Port Technical Data Submittal Special Precautions Specifications Installation 16½" (31.8 (41.9 cm) 8" (20.3 cm) -L -O SUBMITTAL STANDARD: 4" plain end inlet/outlet Highway traffic load

More information

APPA Institute, Dallas TX, February

APPA Institute, Dallas TX, February Heating System Distribution EU 332 Jay W. Becker, PE Key Points Take Aways Planning is vital Build for the future Know Campus layout Reliability meeting needs Economics / options / trade offs Good Design

More information

DARTMOUTH COLLEGE DESIGN January 3, 2012 & CONSTRUCTION GUIDELINES

DARTMOUTH COLLEGE DESIGN January 3, 2012 & CONSTRUCTION GUIDELINES SECTION 15420 DRAINAGE AND VENT SYSTEMS PART 1 DESIGN DIRECTIVES 1.1 DESIGN CRITERIA A. All cleanouts above finished (accessible and non-accessible) ceilings shall be extended to the floor above. B. Do

More information

TECHNICAL SPECIFICATION

TECHNICAL SPECIFICATION TECHNICAL SPECIFICATION ITEM 04821 TEMPORARY VEHICLE AND EQUIPMENT FUELING AREA PART 1 - GENERAL 1.01 Description Installation of erosion and sediment control for a temporary vehicle and equipment fueling

More information

Jobsite Layout Considerations

Jobsite Layout Considerations 1 Jobsite Layout Considerations The controlling contractor must consider many factors when laying out a site to support construction operations Site and building size and Equipment requirements configuration

More information

Excavation General Awareness Safety Training Presentation Red Willow Production Co.

Excavation General Awareness Safety Training Presentation Red Willow Production Co. Excavation General Awareness Safety Training Presentation Red Willow Production Co. Learning Objectives Understand the purpose of our Excavation SOP - to protect employees and contractors when working

More information

Section 403. DRAINAGE STRUCTURES

Section 403. DRAINAGE STRUCTURES 403.01 Section 403. DRAINAGE STRUCTURES 403.01. Description. This work consists of adjusting, constructing, or temporarily lowering drainage structures and cleaning existing drainage structures and leads

More information

SUPPLEMENTAL DRAWINGS

SUPPLEMENTAL DRAWINGS CITY OF GREATER SUDBURY SUPPLEMENTAL DRAWINGS TO THE ONTARIO PROVINCIAL STANDARD DRAWINGS Rev: February 2012 CITY OF GREATER SUDBURY STANDARD DRAWINGS TABLE OF CONTENTS Greater Sudbury Standard Drawings

More information

A. Codes and Standards that are standard at the University. C. Coordinate cleanout locations with Architect.

A. Codes and Standards that are standard at the University. C. Coordinate cleanout locations with Architect. PART 1: GENERAL 1.01 Purpose: A. This standard is intended to provide useful information to the Professional Service Provider (PSP) to establish a basis of design. The responsibility of the engineer is

More information

VALLECITOS WATER DISTRICT SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE

VALLECITOS WATER DISTRICT SECTION POLYVINYL CHLORIDE (PVC) PRESSURE PIPE PART 1 - GENERAL 1.1 DESCRIPTION A. This section designates the requirements for the manufacture and installation of polyvinyl chloride, abbreviated PVC, pressure pipe. 1.2 RELATED WORK SPECIFIED ELSEWHERE

More information

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets.

A. Product Data: For surface pathways, wireways and fittings, floor boxes, hinged-cover enclosures, and cabinets. ALLIANT ENERGY CENTER PAVILIONS Project No. 2013 027 SECTION 27 05 28 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions

More information

HAZOP Checklist for Sewage Treatment Plant

HAZOP Checklist for Sewage Treatment Plant HAZOP Checklist for Sewage Treatment Plant CHECKLIST 1.0 Overall Layout of Treatment Plant 1.1 General Layout Property are fenced and gated and the fence height. State where these problems/impacts occur

More information

Please check with your local inspection authority for any additional requirements before installation.

Please check with your local inspection authority for any additional requirements before installation. Specifications for Residential Underground Electric Service Installation This brochure addresses most typical residential underground service installations. Variances for the following specifications must

More information

Amendments to the January 2016 Design Criteria Manual & Supplementary Master Municipal Construction Documents

Amendments to the January 2016 Design Criteria Manual & Supplementary Master Municipal Construction Documents General Figure 2.3.1 16 Revise Revised Figure 2.3.1: New Development Areas where Secondary Suites Apply to include two new areas (#4 and 5). Water 3.3.2 Watermains 31 Add Added wording in Section 3.3.2.3

More information

Gas meter clearances and service installation requirements

Gas meter clearances and service installation requirements FEBRUARY 2018 Gas meter clearances and service installation requirements CALL PSE S CUSTOMER CONSTRUCTION SERVICES AT 1-888-321-7779 OR VISIT PSE.COM/CUSTOMERCONSTRUCTION FOR MORE INFORMATION. Builder/owner/developer

More information

Klickitat County. On-Site Sewage System. Construction Manual

Klickitat County. On-Site Sewage System. Construction Manual Homeowner OSS Design and Construction Guide Klickitat County On-Site Sewage System Construction Manual Minimum standards and recommendations expected for the construction of on-site wastewater treatment

More information

CITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS

CITY OF SCHERTZ TEXAS ENGINEERING AND PUBLIC WORKS TEXAS STANDARD CONSTRUCTION NOTES DRWN. BY: DSGN. BY: KJW 1 of 2 *Place geotextile fabric as a permeable seperator to prevent mixing of coarse aggregate and underlying soil. (as needed). 1. GEOTEXTILE

More information

Asphalt on Concrete Base with Waterproofing Membrane

Asphalt on Concrete Base with Waterproofing Membrane CABLES CANNOT BE IN DIRECT CONTACT WITH THE WATERPROOFING MEMBRANE! CABLES WILL BURNOUT, AND THE MEMBRANE WILL MELT. 7 5 4 6 1 2 3 NOTES: 1) CLEAN CONCRETE SURFACE 2) HOT MEMBRANE WATERPROOFING 3) ASPHALTIC

More information

SECTION FIRE HYDRANTS

SECTION FIRE HYDRANTS SECTION 21 11 10 PART 1. GENERAL 1.1 SUMMARY: A. Work consists of furnishing and installing new fire hydrants, (boot with ductile iron retainer gland, standpipe and hydrant complete) plus constructing

More information

CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA

CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA CITY OF LA MARQUE, TEXAS CHAPTER 3 WATER SYSTEM DESIGN CRITERIA CHAPTER 3 WATER SYSTEM DESIGN 3.1 WATER SYSTEM DESIGN GENERAL 3.1.1 Criteria for the design of water service and water distribution lines

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

40'-0" PIPE SUPPORT (TYP.) (SEE DWG. NO. SK-2 OR DWG. NO. SK-4)

40'-0 PIPE SUPPORT (TYP.) (SEE DWG. NO. SK-2 OR DWG. NO. SK-4) SK-1 STANDARD LENGTH 4.301 40'-0" A 6" 2'-0" 9'-0" 9'-0" 9'-0" 9'-0" 2'-0" A 3" OF EXPOSED AT EACH END OF PIPE. PIPE SUPPORT (TYP.) (SEE DWG. NO. SK-2 OR DWG. NO. SK-4) EXPOSED PIPE MINIMUM GAUGE AND THICKNESS

More information

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

SECTION IV. PIPELINE EXCAVATION AND BACKFILL SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include

More information

Trench Safety & Qualified Person Presented by: Mike Ross National Training Director

Trench Safety & Qualified Person Presented by: Mike Ross National Training Director Trench Safety & Qualified Person Presented by: Mike Ross National Training Director Excavation Hazards Excavation has always been dangerous work. Workers in the underground industry have a 112% better

More information

Site Preparation... 2

Site Preparation... 2 TRUFIREWALLS INSTALLATION MANUAL This Installation Manual is intended to assist in the preparation and installation of TruFireWalls products manufactured by Oldcastle Enclosure Solutions. The TruFireWalls

More information

Flygt Advanced Low Pressure Sewer System Package

Flygt Advanced Low Pressure Sewer System Package PURPOSE Xylem The purpose of this document is to provide a brief reference to the recommended methods and procedures for installing Flygt's underground sump and sewage basins to ensure that damage or premature

More information

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-16 ISSUE: Initial DATE: 14-10-2009 PAGE: 1 of 19 REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) ISSUE DATE DESCRIPTION /

More information

Appendix 4. Bills of Quantities

Appendix 4. Bills of Quantities Appendix 4. Bills of Quantities 201 A4.1 Deep trench latrines Partitions of local materials 1m apart Timber foot rests and floor plates Lightweight timber frame Excavated soil (used for back-fill) Plastic

More information

ON-SITE SEWAGE CONTRACTOR EXAMINATION STUDY GUIDE

ON-SITE SEWAGE CONTRACTOR EXAMINATION STUDY GUIDE ON-SITE SEWAGE CONTRACTOR EXAMINATION STUDY GUIDE Table of Contents: Introduction...1 Application Process...2 Planning the Layout of the System...3 Setback Requirements...3 Septic Tank Specifications...4

More information

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller.

SECTION DUCTILE IRON FITTINGS. A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. PART 1 - GENERAL 1.1 DESCRIPTION A. This section includes materials, installation, and testing of ductile iron fittings 48 inches and smaller. 1.2 RELATED WORK SPECIFIED ELSEWHERE A. Section 01300 Record

More information

TABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM GENERAL SIZING LINES 115.

TABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM GENERAL SIZING LINES 115. TABLE OF CONTENTS PART III MINIMUM DESIGN STANDARDS Section 115 WATER DISTRIBUTION SYSTEM SECTION TITLE PAGE 115.1 GENERAL 115.1 115.2 SIZING LINES 115.1 115.3 DISTRIBUTION SYSTEM 115.2 115.3.1 Layout

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION Page 210500-1 SECTION 210500 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

SECTION PIPE INSTALLATION

SECTION PIPE INSTALLATION SECTION 02232 PIPE INSTALLATION A. General The pipe shall be Ductile Iron pipe with Tyton push-on joints and cement lined as described and manufactured in accordance with ANSI/AWWA C151/A21.51. Gaskets

More information

SECTION LAYING AND JOINTING BURIED PIPELINES

SECTION LAYING AND JOINTING BURIED PIPELINES SECTION 02650 LINES PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Installation of all underground pipelines. Provide pipeline materials, coatings and linings as specified and pipe of the types, sizes

More information

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK

1993 SPECIFICATIONS CSJ SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1993 SPECIFICATIONS CSJ 581-1-95 SPECIAL SPECIFICATION ITEM 4110 CONCRETE ENCASED DUCT BANK 1. DESCRIPTION. This Item shall govern for the furnishing and installation of all materials and equipment for

More information

Beacon Hill Water & Sewer District Standard Specifications

Beacon Hill Water & Sewer District Standard Specifications Beacon Hill Water & Sewer District Standard Specifications STEP Sewer Systems Including: Design Criteria Standard Construction Drawings REVISED JANUARY 2012 Alternative sewer systems must meet the requirements

More information

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES

SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES SENTINEL BARRIER - GENERAL INSTALLATION GUIDELINES Safety Precautions in the Excavation of a Sentinel Wedge take all necessary steps to make sure the pit is secured. Follow all OSHA requirements for digging

More information

TECHNICAL NOTE HDPE Pipe and Utility Crossings

TECHNICAL NOTE HDPE Pipe and Utility Crossings TECHNICAL NOTE HDPE Pipe and Utility Crossings TN 5.09 April 2008 Introduction Underground utilities include storm sewer, electric, sanitary sewer, gas, water, telephone and cable. Utility conflicts are

More information

GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS

GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS UTAH COUNTY HEALTH DEPARTMENT Div. of Environmental Health 151 South University Avenue, Provo 84601 (801) 851-7525 FAX 851-7521 GUIDELINES FOR INSTALLATION OF ON-SITE SEWAGE SYSTEMS This is intended to

More information