BANKABILITY OF SOLAR PROJECTS HOW TO MAKE YOUR PV PROJECT BANKABLE? HOW TO SELECT EPC CONTRATCOR? ROLE OF TECHNLOGY SELECTION

Size: px
Start display at page:

Download "BANKABILITY OF SOLAR PROJECTS HOW TO MAKE YOUR PV PROJECT BANKABLE? HOW TO SELECT EPC CONTRATCOR? ROLE OF TECHNLOGY SELECTION"

Transcription

1 0 HOW TO MAKE YOUR PV PROJECT BANKABLE? HOW TO SELECT EPC CONTRATCOR? ROLE OF TECHNLOGY SELECTION BANKABILITY OF SOLAR PROJECTS IMPACT OF O&M ON BANKABILITY SOLAR RESOURCE ASSESSMENT FIRSTGREEN CONSULTING U28A/3 FF DLF Phase III, GURGAON INDIA

2 Table of Contents I. Introduction... 2 II. Site and Solar Resource Assessment... 3 III. Design Optimisation... 4 IV. EPC Selection... 5 V. Installation and Commissioning... 6 VI. Operation and Maintenance... 7 VII. Other Issues... 7 VIII. Conclusion... 8 Firstgreen Consulting... 8 FIRSTGREEN WHITE PAPER BANKABILITY OF SOLAR PV PROJECTS - DECEMBER

3 Introduction While conventional power projects are facing the fuel availability challenges and fuel price uncertainty, investors are looking renewable as preferred options to remain in power sector. Especially solar PV projects are much more appealing to the investors due to their scalability and flexibility in nature. While Indian Government has withdrawn the accelerated depreciation from wind projects, solar provides a yet another tax aversion tool to the investors. The cash flow of solar present a much more stable and risk free cash flow as compared to the conventional power projects where you cannot predict the fuel prices. The higher cost of capital can significantly make projects unviable. Hence it is important for the project developers to take care of the factors which affects the bankability of solar projects. There are five major parameters which affects the bankability of solar projects which include The Banks and Financial institutions are concerned on the risk associated with the solar projects due to high capital cost requirements in these projects. The financing institutions in India do not have enough experience in these technologies and always concerned about the following issues: Is the yield assessment reliable? Are there any power evacuation risks? How about degradation? How about performance in the Indian dusty and high temperature conditions? What about skilled labour for maintenance? How about the reliability of the PPAs signed with the state utilities which are already under financial crunch? Are there any generation guarantee available? How about future policy framework? Is the technology proven? Has the EPC demonstrated the ability to deliver the projection-time and on-budget? What is the anticipated ROI? How quickly can the project start generating a return? Most of the solar projects face delays due to the reason of the financial closure and hence bankability of a solar project is a major issue. The degree of bankability is dependent on the reliability technology supplier, reliability of EPC contractor, Reliability of the yield assessment, and the financial health of the promoter company. FIRSTGREEN WHITE PAPER BANKABILITY OF SOLAR PV PROJECTS - DECEMBER

4 Site and Solar Resource Assessment Selecting a proper site is important aspect which may affect the bankability of solar project. While solar radiation do not change at a location within few kilometers, it is less risk in a selecting a project site as compared to wind power projects where the variability of wind is highly location specific. Developers should consider a project site with good solar insolation and near to the grid substation so that the transmission losses are lower. Selection of site should also consider the legal aspects of the land, clear title of land and position is required to make your project bankable. What level of confidence should be applied to historical solar data? What is known and what might not know of the site? What are the weather, Water, Geo-Technical and other infrastructure conditions? Does the project developer own the project Many times developer consider the solar radiation data for a single year, however long term solar radiance data should be collected for the proposed site in order to give comfort to the banker. This day s satellite based as well as ground based measurement data is available through which inter and annual variability in generation can be assessed. If developers have one year of major data, banks have to assume the minimum radiation levels observed at the site which will reduce the generation almost by 10% and project may become non bankable. Many times project developer take one year of solar radiation data, however it may note that there is a significant inter-annual variability in solar radiation data. Following example highlights that for a typical location in Rajasthan the solar radiation (GHI) has a variation from 1900 kwh/m 2 /year to 2100 kwh/m 2 /year. Typically banks expect P50, P75 and P90 level of confidence in solar radiation data. The P90 level of solar radiation of data is accepted globally by banks. It is not only important to assess the energy yield for a single year, there is a requirement to have the energy yield assessment on long-term basis for which you are required to have the historical solar radiation data at least for 10 years for the site location. The project developer should also consider the other factors such as historical flood data, seismic data, etc. which may save the developer the insurance cost and provide the lender significant comfort in terms of site location. FIRSTGREEN WHITE PAPER BANKABILITY OF SOLAR PV PROJECTS - DECEMBER

5 Design Optimisation Selecting an appropriate technology for your solar project plays a very important role in the bankability of a solar project. The major aspects in the technology selection are selection of PV module supplier which should be from the reputed manufacturer who provide the warranties for 5-10 year workmanship and performance guarantee for a period of 25 years. The guarantees and warranties of BOS also play an important role as PV module contributes only 50% of the project cost. Typically all the PV module manufacturers offer long term performance warrantee, however the question remains on the effectiveness of the warrantees. If a PV module manufacturer goes bankrupt, then there is no entity left to the developer for honoring the warrantees of the bankrupt of the manufacturer. Many developers take warrantee insurance to mitigate the risk associated with the bankruptcy of PV module supplier which help them in maintaining bankability of their solar projects. Apart from guarantees and warrantees most of the PV module suppliers conduct IEC and UL certification tests to justify their module degradation, performance and reliability. Selecting a PV module supplier with IEC and UL certification not only justifies the bankability of the selected modules, but also reduces risk of technology failure. It is important to optimize your system sizing while selecting PV technology and BOS. The major consideration should be given to levelized cost of energy to evaluate various design configurations. Are there any equipment warrantees? Are the manufacturers still able to service them? What are the components failure/reliability Risk? Is there adequate availability of spare parts? In state like Rajasthan the ambient temperature reaches as high as 50 C and modules surface temperature reach of the order of 75 C and accordingly the string voltage is of the order 560 V. It is equally important that we consider the minimum temperature of the site conditions while doing the array layout.during winters the temperature go as low as 0 C and the module surface temp is also reaching to C and hence the voltage of the string reach 770 V. It may be noted that the temperature has the greater impact on voltage,while the irradiance has greater impact on current.hence while selecting array size maximum irradiance and minimum irradiance will dictate cable size for interconnecting the modules in the string. FIRSTGREEN WHITE PAPER BANKABILITY OF SOLAR PV PROJECTS - DECEMBER

6 EPC Selection Selecting the right EPC is key to ensure the project commissioning as scheduled and as per the quality standards specified. Reputed EPCs offers significant advantage through their linkages for equipment procurement and standard installation practices. Many times the banks and financial institutes have their comfort for some of the empanelled EPC contractors who maintain certain quality standards and developers are required shortlist EPCs from the empanelled EPCs only. Some of the developers would like to reduce their upfront cost through fragmenting the single EPC into multiple EPC contractors, however this exposes the developer in terms of performance guarantee of the overall plant. If the EPC contractor is not reputed this increases the project risk ratings and in-turn increases the cost of capital available to the project. While selecting EPC the developer should consider not only experience and reliability but also the balance sheet of EPC should also take in to consideration so that the EPC can honor the guarantees and warrantees for the future. How strong is your EPC provider? Is the EPC Firm experienced?. Does it have strong balance sheet? Are the Risks allocated to various parties through contracts? Technology Selection We have personally seen that in years, many investors in India adopted only one criteria for the selection of EPC contractor. Yes, you are right, it was Money. At present many of those are not happy with their plant and for some of them, conditions are so bad that when they want to sell their solar plant to get rid of it, they didn t find any buyer. PV module supplier 5-10 year workmanship BOS DC/AC Ratio Banks/ financial institution are the major stakeholder in the solar plant investment. Selection of a reputed EPC contractor for your solar money plant can help you to get cheaper finance. Typically saying a 0.5% decrease in cost of debt can reduce the LCOE (Levelized cost of electricity) even by 30 paisa/ kwh. Performance Guarantee Corporate Sustainability Chances of meeting the promised time line for the commission of solar money plant are very high with a reputed EPC contractor. Take a case that this reputed EPC contractor commission plant one month before than the other one, and a typical 1 MW solar money plant generated around 1.3 Lac unit of electricity. This means you can enjoy this 1.3 lac of units which you cannot even think with another EPC contractor. FIRSTGREEN WHITE PAPER BANKABILITY OF SOLAR PV PROJECTS - DECEMBER

7 Installation and Commissioning The installation and commissioning can cut further if EPC is selected having experience in working in a specified region of the project. Selecting a local EPC also help in developer in resolving the local issues. An EPC with experience in the region is more likely to understand the regulatory and licensee requirement which may unnecessarily delay in project development. Many times project is to be commissioned with the specific timelines and delay in scheduled timelines may reduce the PPA price. Hence If the EPC contractor do not meet the specified timeline, the project developer may suffer significant losses because of reduced tariff beyond the agreed timeline. The installation and commissioning of project typically takes 6-8 months and if the EPC is not experienced it can prolong for a year.. Some Common Installation problems Many times the solar field terrain is uneven and requires variable leg length to achieve the level installation and avoid the shading of one table over another table. It becomes critical if the liner shading is not taken into consideration while designing the differential heights of the table. Selection of foundation is also one of the important factors for the structure design and layout. Where ever excavation/ drilling is possible, concrete structure are recommended, however, some of the project developer use ramming rather than concrete structure to save time and money. Rammed structures are more prone to corrosion and life expectancy for 20 years becomes critical. The structures vertical member should be designed in such a way that they can accommodate variability in height from one table to another table. Apart from the structure member clamping of module is also one of the critical consideration to mount the module on the structure, structure frame, there are various top down clams are available which can hold the with frame and frameless module efficiently. In case these considerations are not made during array installation the structure faces sagging and the tilt angle get disturbed. Are there any equipment warrantees? Are the manufacturers still able to service them? What are the components failure/reliability Risk? Is there adequate availability of spare parts? FIRSTGREEN WHITE PAPER BANKABILITY OF SOLAR PV PROJECTS - DECEMBER

8 Operation and Maintenance O&M of solar project becomes significant in maintaining the bankability of solar project, the banks and financial institutes typically wants to ensure the projected generation. Some of the insurance companies have also come up to cover the generation risk and started offering generation insurance. However the developer should consider the generation insurance is available at what cost. In recent installations the local site conditions were not taken in to consideration while deciding the inverter parameters which led tripping of inverter of solar plants this reduces generation. In order to cover the generation risk many financing institutions look for strong balance sheet of the developer in order to cover the generation short falls. Some of the financing institutions also create to a DSRA (Debt service reserve account) to mitigate the generation risk of the solar project. It is equally important to consider the adequate availability of spares so that equipment failures do not cause generation reduction in solar projects. The recent experiences in solar plants also highlight the reduced generation because of grid tripping. Solar project developers should take in to consideration the grid tripping data of their respective sub-station to estimate the project electricity generation estimates. The bankability of solar project is also affected by O&M cost and its expected escalation. Project developer should do sensitivity analysis of their LCOE with reference to their O&M cost escalation. Mwh Other Issues Apart from technical aspects the bank-ability of solar project is heavily dependent on power purchase agreement. The PPA should be on long-term basis on a clarity of cash flow at least for the long tenure. The lender assess PPA and the party s financial strength/pay ability, risk of the buyer. In this regard the PPAs with NVVN are considered bankable. The PPAs with state power utilities are also bankable, however some of the financial institutions have discomfort with regards to balance sheet (negative) of the state power utilities which increases the off taker payment risk in the project. Sometimes the PPA are signed with private parties as part of capital/ third part sale and the balance sheet of captive power buyer with third party becomes a critical factor in the bankability of the solar project. The technology selection and EPC also play an important role with the bankability of a solar project. For example if the modules and inverters are supplied from the reputed supplier. It is considered as a less risky proportion by the banker. Finally you should take care of permits, agreements, licenses, land papers and other statutory clearances available so that there is no compliance risk seen by the lender. If you structure your project with all above aspects the project can be bankable, will achieve financial closure. Many times people approach bank first and then start accumulating this information, however if all this information is compiled in advance with bank/financial institution then it will not take much time in releasing your loan Mwh Is the project developer balance sheet strong enough to cover this generation shortfall? Does the generation shortfall threaten the project debt service? FIRSTGREEN WHITE PAPER BANKABILITY OF SOLAR PV PROJECTS - DECEMBER

9 Conclusion Making solar projects bankable needs careful attention to the not only five key factors which are highlighted in this paper but also there are many other factors such as PPA, Local issues, curtailment which may affect the project economic viability. The project developer should strive in reducing the risk associated with solar radiation and collect local and satellite based data to attract more investors and lower the cost of capital in the project. In other words bankability of the solar projects is key for future capacity installations and developers have experienced this issues in recent installations. Structuring a project as a bankable project requires detailed consideration on the technical, legal and economic aspects of the project. Every bank and financial has its own set of criteria through which it assess the bankability of a project. However the basic requirement is that the project should have a stable and visible cash flow throughout the entire financing period of the project. The major aspect which any bank or financial institution assess for the bankability of a solar project is the local site conditions. The local site conditions are typically evaluated on the basis of solar radiation available at the site and expected yield (Annual Energy Generation) which dictates the cash flow of the project. It is not only important to assess the energy yield for a single year, there is a requirement to have the energy yield assessment on longterm basis for which you are required to have the historical solar radiation data at least for 10 years for the site location. So that the trend can be forecasted to give the expected future energy generation for the banker. Firstgreen Consulting Firstgreen provides consulting services in the area of Renewable Energy, Building Energy Efficiency, and Climate Change. We are one of the leading consulting firm in the field of Solar PV projects in India and have been involved in MW class grid connected as well as Rooftop Solar projects. We have provided Project Management consulting, Design and Engineering services for over 200 MW of solar projects since 2010 of which about 100 MW is already being commissioned and balance is under various stages of development. We provide various services to the client right from the inspection of project, Design and Engineering support, Policy and Regulatory support, financing support and strategic business advisory to our clients. Firstgreen has been conducting training and capacity building programs for solar, wind and building energy efficiency projects in India and abroad. Our training programs has been widely attended by senior management of various organizations which provide hands on experience and step by step approach to implement solar, wind, and building energy efficiency projects. We believe in sharing our knowledge through technical articles on our blog ( So far we have published around 680 articles which reflect our experience i policy, technology, financing, and project management. Our blog is visited by 64 countries in the world and having footfall over 1,40,000 people across the globe. We provide 360 degree turnkey solutions for solar projects and also provide EPC services. Some of the clients who believe in getting a quality installations (Grid connected/rooftop) through us. FIRSTGREEN WHITE PAPER BANKABILITY OF SOLAR PV PROJECTS - DECEMBER

Sun to Market Solutions. June 16 18, 2014 IFC Washington, DC

Sun to Market Solutions. June 16 18, 2014 IFC Washington, DC Sun to Market Solutions June 16 18, 2014 IFC Washington, DC Schedule 1 PV Technology Overview, Market Analysis, and Economics PV Project Development, Implementation, and Financing Case Study Schedule 2

More information

Solar Project Yield Assessment. Workshop on Solar Power Project Development, Sept 20-21, 2012

Solar Project Yield Assessment. Workshop on Solar Power Project Development, Sept 20-21, 2012 Solar Project Yield Assessment Workshop on Solar Power Project Development, Sept 20-21, 2012 Firstgreen Consulting Pvt Ltd. B 1202 Millennium Plaza, Sec 27 Gurgaon 122002 1 Solar Radiation Components 2

More information

SOLAR DUE DILIGENCE. Instructor: Peter Cockcroft March Jakarta

SOLAR DUE DILIGENCE. Instructor: Peter Cockcroft March Jakarta SOLAR DUE DILIGENCE Instructor: Peter Cockcroft 20 22 March 2017 Jakarta COURSE BENEFITS This 3-day course is essential for all players in the international solar power game, and you will walk away with

More information

REQUEST FOR BID (TURNKEY SOLUTION) 1MW GRID TIE SOLAR PV POWER PLANT. Location:

REQUEST FOR BID (TURNKEY SOLUTION) 1MW GRID TIE SOLAR PV POWER PLANT. Location: REQUEST FOR BID (TURNKEY SOLUTION) 1MW GRID TIE SOLAR PV POWER PLANT Location: Dist.: Jodhpur Rajasthan, INDIA Latitude 27.32 & Longitude 71.54 Elevation: 151 meter GENERAL INFORMATION AND TECHNICAL SPECIFICATION

More information

Subtask 1: Economic of PV System Performance and Reliability

Subtask 1: Economic of PV System Performance and Reliability TASK 13: PERFORMANCE AND RELIABILITY OF PV SYSTEMS Subtask 1: Economic of PV System Performance and Reliability Mauricio Richter (3E), Jan Vedde (SiCon) Mike Green (M.G.Lightning Electrical Engineering)

More information

HARTEK POWER PVT LTD SOLAR BUSINESS CATALOGUE (Formerly known as Amtek Energy & Power Pvt Ltd)

HARTEK POWER PVT LTD SOLAR BUSINESS CATALOGUE (Formerly known as Amtek Energy & Power Pvt Ltd) (Formerly known as Amtek Energy & Power Pvt Ltd) SOLAR BUSINESS CATALOGUE 2015-16 2 P a g e Contents 1. Introduction 2. Mission SOLAR 3. Why us? 4. Engineering Procurement Construction Services 4.1 Process

More information

NORTH COUNTRY LIBRARY SYSTEM County Route 190 Watertown, NY 13601

NORTH COUNTRY LIBRARY SYSTEM County Route 190 Watertown, NY 13601 22072 County Route 190 Watertown, NY 13601 REQUEST FOR PROPOSAL DESIGN/BUILD OF SOLAR PHOTOVOLTAIC ARRAY Solicitation The North Country Library System (NCLS), Watertown NY is soliciting proposals from

More information

TRAINING PROGRAM ON SOLAR POWER PROJECT DEVELOPMENT

TRAINING PROGRAM ON SOLAR POWER PROJECT DEVELOPMENT Duration : 5th Oct 2015 to 10th Oct 2015 TRAINING PROGRAM ON SOLAR POWER PROJECT DEVELOPMENT DAY 1 / 05.10.2015 (MONDAY): Welcome speech- and introduction of the training program FIRSTGREEN + MNIT + NISE

More information

TONGA POWER LIMITED REQUEST FOR PROPOSALS INDEPENDENT POWER PRODUCERS. for SOLAR PHOTOVOLTAIC GENERATION 5 APRIL, 2018 RFP - TPL SOLAR IPP

TONGA POWER LIMITED REQUEST FOR PROPOSALS INDEPENDENT POWER PRODUCERS. for SOLAR PHOTOVOLTAIC GENERATION 5 APRIL, 2018 RFP - TPL SOLAR IPP TONGA POWER LIMITED REQUEST FOR PROPOSALS INDEPENDENT POWER PRODUCERS for SOLAR PHOTOVOLTAIC GENERATION 5 APRIL, 2018 RFP - TPL SOLAR IPP RFP No. TPL SOLAR IPP 1 NOTICE TO OFFEROR REQUEST FOR PROPOSALS

More information

Ensuring bankability across the value chain, 30 th June 2015

Ensuring bankability across the value chain, 30 th June 2015 #1 Specialist Renewable and Cleantech Investment Banking and Consulting Boutique in Asia Pacific Solar Finance & Investment Asia 2015 Ensuring bankability across the value chain, 30 th June 2015 A Bankable

More information

100 MW CSP Project, Rajasthan, India

100 MW CSP Project, Rajasthan, India 100 MW CSP Project, Rajasthan, India CSP Location in India Nearest town: Pokaran (18 km) Nearest highway : NH 114(Jodhpur- Jaisalmer) Nearest airport : Jodhpur (170 km) Nearest rail station: Pokaran Rationale

More information

PV industry status and trends: Lessons learnt from Thailand's First Five Years of Utility-scale PV

PV industry status and trends: Lessons learnt from Thailand's First Five Years of Utility-scale PV PV industry status and trends: Lessons learnt from Thailand's First Five Years of Utility-scale PV Phil Napier-Moore, Project Director, Mott MacDonald 5th June 2013, Renewable Energy Asia 2013 Presentation

More information

7 Project Description

7 Project Description 7 Project Description 7.1 Project Promoter The CEB (Green energy) Co. Ltd. is a private company fully owned by the Central Electricity Board incorporated on 11 October 2016 to promote the generation of

More information

Risk Identification and Mitigation for Small Scale Renewable Energy Power Projects in Indonesia

Risk Identification and Mitigation for Small Scale Renewable Energy Power Projects in Indonesia Risk Identification and Mitigation for Small Scale Renewable Energy Power Projects in Indonesia Prepared by: Bill Meade Director, Tetra Tech (USA) CLEAN POWER ASIA 29-30 April 2013 Bangkok, Thailand Presentation

More information

Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India 347 NAGALAND ELECTRICITY REGULATORY COMMISSION Terms and Conditions for Determination of

More information

ECE 333 GREEN ELECTRIC ENERGY 15. PV ECONOMICS

ECE 333 GREEN ELECTRIC ENERGY 15. PV ECONOMICS ECE 333 GREEN ELECTRIC ENERGY 15. PV ECONOMICS George Gross Department of Electrical and Computer Engineering University of Illinois at Urbana-Champaign ECE 333 2002 2017 George Gross, University of Illinois

More information

Future Energy & Finance ASIA Risks and Returns in Solar Investments. 05 April 2017

Future Energy & Finance ASIA Risks and Returns in Solar Investments. 05 April 2017 Future Energy & Finance ASIA Risks and Returns in Solar Investments 05 April 2017 Introduction to Conergy Summary Overview Conergy is a leading global downstream solar company Develops, finances, installs

More information

SOLAR ENERGY ASSESSMENT REPORT. For 80.5 kwp. Meteorological Data Source NASA-SSE. Date 18 October, Name of Place Uttar Pradesh.

SOLAR ENERGY ASSESSMENT REPORT. For 80.5 kwp. Meteorological Data Source NASA-SSE. Date 18 October, Name of Place Uttar Pradesh. SOLAR ENERGY ASSESSMENT REPORT For 80.5 kwp Name of Place Uttar Pradesh Client abc Capacity 80 kw Meteorological Data Source NASA-SSE Email ezysolare@gmail.com Order No. #1410180006 Date 18 October, 2014

More information

RE Project Development, Risk Analysis and Financing

RE Project Development, Risk Analysis and Financing RE Project Development, Risk Analysis and Financing LEARNING OBJECTIVES Learn what are the challenges and trend in RE Project Development in the Philippine environment; who are the RE project stakeholders,

More information

Overview, Strengths, Service, Key Projects & Clients

Overview, Strengths, Service, Key Projects & Clients CENTER FOR SOLAR ENERGY [CSE] Overview, Strengths, Service, Key Projects & Clients Brief Overview Catalyzing growth of solar power in India since 2006 Objective is to facilitate holistic development of

More information

NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd

NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd Scatec Solar ASA NERSA Public Hearing Dyason s Klip 1 (Pty) Ltd Presented by Jan Fourie Business Development Manager September 2015 Project Company-General Information Dyason s Klip 1 (Pty) Ltd (formerly

More information

Cambodia s First Solar Park

Cambodia s First Solar Park Cambodia s First Solar Park Pradeep Tharakan Principal Energy Specialist Asian Development Bank Asia Solar Energy Forum 5 June 2018 1 Outline of Presentation Cambodia Power Sector Overview Solar PV Grid

More information

Procurement Australian Clean Energy Summit 2017

Procurement Australian Clean Energy Summit 2017 pwc.com.au Procurement Australian Clean Energy Summit 2017 July 2017 Contents 1 Procurement & Solar Market Snapshot 1 3 ECI / AWA 2 Free-issue Equipment 3 Procurement & Solar Market Snapshot Procurement

More information

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. SM/016/2014 (Suo Motu)

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. SM/016/2014 (Suo Motu) CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. SM/016/2014 (Suo Motu) Date of order: 30 th September, 2014 Coram: Shri Gireesh B. Pradhan, Chairperson Shri M. Deena Dayalan, Member Shri

More information

Solar power in action

Solar power in action Solar power in action Powering your business forward Product series September 2018 The Power of Solar Powering Performance Solar will help you cut your costs in a truly sustainable way by providing you

More information

Decentralized Commercial Systems

Decentralized Commercial Systems Decentralized Commercial Systems The Flexible Solution The challenge: Optimizing flexibility, cost, and time-to-market Cost. Energy production. ROI. When considering the design and layout of a commercial

More information

Solar Parks Concept, implementation and lessons learned. A Presentation by Agostinho Miguel Garcia SunBD Sun Business Development

Solar Parks Concept, implementation and lessons learned. A Presentation by Agostinho Miguel Garcia SunBD Sun Business Development Solar Parks Concept, implementation and lessons learned A Presentation by Agostinho Miguel Garcia SunBD Sun Business Development Solar park concept Solar park is not a fancy name for a solar plant. Solar

More information

V GL.E.PR.RSOEM

V GL.E.PR.RSOEM V1.1606.GL.E.PR.RSOEM Digital O&M: Optimising Management of Utility Scale Solar Plants Massimiliano Pili Country Manager Italy, Alectris Massimiliano.pili@alectris.com Contents About Alectris Brief history

More information

Accurately modeling and effectively maximising returns on large scale PV plants

Accurately modeling and effectively maximising returns on large scale PV plants Accurately modeling and effectively maximising returns on large scale PV plants Phil Napier-Moore, Project Director, Mott MacDonald 26 th November 2014, Solar Energy Southeast Asia Session Topics Key risks

More information

PV Investments Cost Benchmarking & Gap Analysis LCOE Simulation & Sensitivity Analysis

PV Investments Cost Benchmarking & Gap Analysis LCOE Simulation & Sensitivity Analysis Solar Bankability Webinar 22 November 2016 PV Investments Cost Benchmarking & Gap Analysis LCOE Simulation & Sensitivity Analysis Mauricio Richter, Caroline Tjengdrawira (3E) Funded by the Horizon 2020

More information

YAP RENEWABLE ENERGY DEVELOPMENT PROJECT Breaking the Reliance on Fossil Fuels

YAP RENEWABLE ENERGY DEVELOPMENT PROJECT Breaking the Reliance on Fossil Fuels YAP RENEWABLE ENERGY DEVELOPMENT PROJECT Breaking the Reliance on Fossil Fuels A photo montage of the wind farm at the proposed project site. GHD Pty Ltd. Electricity is expensive in Yap State in the Federated

More information

Energy Generation, Transmission and Distribution (GTD) Mr. André Luís Rodrigues

Energy Generation, Transmission and Distribution (GTD) Mr. André Luís Rodrigues Energy Generation, Transmission and Distribution (GTD) Mr. André Luís Rodrigues Business Area 2017 Net Operating Revenues Breakdown External Markets Domestic Market 17% 11% Energy Generation, Transmission

More information

SOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM

SOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM SOLARPVSYSTEM INFORMATIONPACK FIT PROGRAM (Thailand, July 2013) The Thai government has recently introduced a generous subsidy scheme involving Feed in Tariffs. This means that you get paid a premium rate

More information

Procurement of Renewable Energy Projects Hydropower, and the case of Ashta (Albania)

Procurement of Renewable Energy Projects Hydropower, and the case of Ashta (Albania) Procurement of Renewable Energy Projects Hydropower, and the case of Ashta (Albania) Nicola Saporiti, IFC PPP Advisory Creating Opportunity Where It s Needed Most Geneva, 31 March 2015 Hydropower plants

More information

SUCCESSFUL SOLAR POWER BUSINESS The Power and Renewable Energy Seminar 2016 Hosted by the Indonesian Gas Society

SUCCESSFUL SOLAR POWER BUSINESS The Power and Renewable Energy Seminar 2016 Hosted by the Indonesian Gas Society SUCCESSFUL SOLAR POWER BUSINESS The Power and Renewable Energy Seminar 2016 Hosted by the Indonesian Gas Society Jakarta 8 December 2016 www.canadiansolar.com Canadian Solar Corporate Overview Founded

More information

REPLIES TO QUERIES. Sr. Clause No Reference from RfQ cum RfP Queries Clarification. Developer. Bidder shall furnish the please.

REPLIES TO QUERIES. Sr. Clause No Reference from RfQ cum RfP Queries Clarification. Developer. Bidder shall furnish the please. REPLIES TO QUERIES ENGINEERING, PROCUREMENT AND CONSTRUCTION (EPC) SERVICES FOR 1.00MW MODEL SOLAR POWER PROJECT AT NEEMRANA INDUSTRIAL AREA ON TURNKEY BASIS AND OPERATION & MAINTENANCE OF 1.00MW SOLAR

More information

BRUNEI LNG SENDIRIAN BERHAD

BRUNEI LNG SENDIRIAN BERHAD BRUNEI LNG SENDIRIAN BERHAD 22 MWp LUMUT CAPTIVE SOLAR PV POWER PROJECT Draft Report BNERI 2014-04-RE/02 Company Brunei National Energy Research Institute Science and Technology Research Building UBD Tungku

More information

Solar (PV) Panel Installation and Maintenance With The Help Of PVSYST And PVSOL

Solar (PV) Panel Installation and Maintenance With The Help Of PVSYST And PVSOL Solar (PV) Panel Installation and Maintenance With The Help Of PVSYST And PVSOL Training Objective: This training program is designed for new Entrepreneurs, Prospective Entrepreneurs, working Professional

More information

Power Saver TM Program

Power Saver TM Program Power Saver TM Program COMMERCIAL SOLAR PHOTOVOLTAIC PERFORMANCE-BASED INCENTIVE PROGRAM GUIDELINES These guidelines govern the procedures and qualifications for incentives under the Austin Energy Commercial

More information

NABCEP PV Technical Sales Job Task Analysis

NABCEP PV Technical Sales Job Task Analysis NABCEP PV Technical Sales Job Task Analysis Introduction This document presents an in-depth Job Task Analysis for solar electric professionals who gather site specific information and analyze customer

More information

The Roofing Industry Alliance for Progress

The Roofing Industry Alliance for Progress The Roofing Industry Alliance for Progress Roofing & Solar- The Future Renewable Energy World magazine estimated commercial and residential roof top photovoltaic deployment after accounting for solar shading

More information

MAXIMIZING. Making Use of Existing Roofs

MAXIMIZING. Making Use of Existing Roofs MESSAGE MAXIMIZING Solar Power Generation Making Use of Existing Roofs In this article, Satish N Diwakar outlines various aspects of solar photovoltaic (SPV) systems on rooftops, including evaluation of

More information

Green Power Market Development Group - India. Tara Parthasarathy, Ashok Thanikonda Progress Review - Collaborative Rooftop PV Purchase Sept 30, 2013

Green Power Market Development Group - India. Tara Parthasarathy, Ashok Thanikonda Progress Review - Collaborative Rooftop PV Purchase Sept 30, 2013 Green Power Market Development Group - India Tara Parthasarathy, Ashok Thanikonda Progress Review - Collaborative Rooftop PV Purchase Sept 30, 2013 Overview Renewable Energy is expensive, unreliable and

More information

Appendix D Minimum Requirements For Developmental Resources For

Appendix D Minimum Requirements For Developmental Resources For Minimum For Developmental Resources For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy New Orleans, Inc. Entergy Services, Inc. July 13, 2016 MINIMUM REQUIREMENTS FOR

More information

Understanding bankability requirements for geothermal power projects with the IRENA Project Navigator

Understanding bankability requirements for geothermal power projects with the IRENA Project Navigator #ProjectNavigator Understanding bankability requirements for geothermal power projects with the IRENA Project Navigator Simon Benmarraze, IRENA sbenmarraze@irena.org Workshop Unlocking Geothermal Investments

More information

How Building Owners Save by Solar PV & SPF Roofing Systems. Presented by: Daryl A. Pilon, M.E. Director of Business Development Standard Solar, Inc.

How Building Owners Save by Solar PV & SPF Roofing Systems. Presented by: Daryl A. Pilon, M.E. Director of Business Development Standard Solar, Inc. How Building Owners Save by Solar PV & SPF Roofing Systems Presented by: Daryl A. Pilon, M.E. Director of Business Development Standard Solar, Inc. ANTITRUST POLICY STATEMENT FOR SPRAY POLYURETHANE FOAM

More information

Terms of Reference Shobak Wind Farm (Jordan) Lenders Engineer (Technical Due Diligence)

Terms of Reference Shobak Wind Farm (Jordan) Lenders Engineer (Technical Due Diligence) 1 Background Terms of Reference Shobak Wind Farm (Jordan) Lenders Engineer (Technical Due Diligence) The European Bank for Reconstruction and Development (EBRD) and other potential lenders (together, the

More information

WIND & SOLAR TECHNICAL EXPERT

WIND & SOLAR TECHNICAL EXPERT WIND & SOLAR TECHNICAL EXPERT Development phase An expert to secure investments Contract negotiation Management of the tender process and contracts negotiation through a set of best practices. Equipment:

More information

Jawaharlal Nehru National Solar Mission Building Solar India Ministry of New and Renewable Energy Government of India

Jawaharlal Nehru National Solar Mission Building Solar India Ministry of New and Renewable Energy Government of India Jawaharlal Nehru National Solar Mission Building Solar India Ministry of New and Renewable Energy Government of India 1 st Concentrated Solar Thermal Power Summit New Delhi, September 2010 Under the National

More information

Photovoltaic System Installation Request for Proposals. St. Mary s School, Boise, ID

Photovoltaic System Installation Request for Proposals. St. Mary s School, Boise, ID Photovoltaic System Installation Request for Proposals St. Mary s School, Boise, ID This Request for Proposals ( RFP ) is to solicit competitive quotes from photovoltaic (PV) system installers to design

More information

Wind Energy Basics & Project Cycle

Wind Energy Basics & Project Cycle Wind Energy Basics & Project Cycle Wind Energy Basics & Project Cycle 1.800.580.3765 WWW.TTECI.COM Pramod Jain, Ph.D. Presented to: DFCC Bank and RERED Consortia Members January 26 27, 2011 Colombo, Sri

More information

Reaching the lowest cost of electricity with a revolutionary new PV plant technology. PEG PV substructure The revolution in utility scale PV power

Reaching the lowest cost of electricity with a revolutionary new PV plant technology. PEG PV substructure The revolution in utility scale PV power Reaching the lowest cost of electricity with a revolutionary new PV plant technology PEG PV substructure The revolution in utility scale PV power 2 The PEG PV substructure The PEG PV substructure 3 Lower

More information

Renewable Energy: Changing the Energy Scenario and Achieving Sustainable Growth

Renewable Energy: Changing the Energy Scenario and Achieving Sustainable Growth Renewable Energy: Changing the Energy Scenario and Achieving Sustainable Growth Vivek Sharma Practice Leader & Director Energy & Natural Resources August 21, 2014 1 CRISIL Risk & Infrastructure Solutions

More information

INTERNATIONAL RENEWABLE ENERGY AGENCY

INTERNATIONAL RENEWABLE ENERGY AGENCY INTERNATIONAL RENEWABLE ENERGY AGENCY Extending the Frontier of PV Reliability: The Role of Quality Infrastructure Solar Bankability Workshop 8 February 2017 Brussels, Belgium Solar power investments 2015:

More information

Renewable Energy Integration Challenge MicroGrid Yu Chan, Canadian Solar Inc

Renewable Energy Integration Challenge MicroGrid Yu Chan, Canadian Solar Inc Renewable Energy Integration Challenge MicroGrid Yu Chan, Canadian Solar Inc June 07th 2016 CSIQ NASDAQ Listed Company Overview Founded in Ontario, 2001 Listed on NASDAQ (CSIQ) in 2006 Over 8,000 employees

More information

Photovoltaic Systems II. EE 446/646 Fall 2013

Photovoltaic Systems II. EE 446/646 Fall 2013 Photovoltaic Systems II EE 446/646 Fall 2013 Components of a grid-connected residential PV system (net meter) The inverter contains: Ground Fault Circuit Interrupter (GFCI) MPPT and Circuitry to disconnect

More information

Options to scale up solar PV in. Vietnam. - Introduction. Vietnam

Options to scale up solar PV in. Vietnam. - Introduction. Vietnam Options to scale up solar PV in Vietnam - Introduction Vietnam November 2015 Solar PV scale up in Vietnam INTRODUCTION Overall objectives To accelerate PV scale up in order to fulfill GoV target in a sustainable

More information

Thin Film TECHNOLOGY ADVANTAGE

Thin Film TECHNOLOGY ADVANTAGE TECHNOLOGY ADVANTAGE RECORD-SETTING PERFORMANCE Get superior efficiency, higher energy yield, and long-term reliability from an affordable, fieldproven module. Cadmium Telluride (CdTe) photovoltaic (PV)

More information

Wind Energy Basics & Project Cycle

Wind Energy Basics & Project Cycle Wind Energy Basics & Project Cycle WIND POWER PROJECT DEVELOPMENT PRACTICAL APPROACHES TO LAUNCHING SUSTAINABLE WIND PROJECTS October 18-19, 2011 1.800.580.3765 WWW.TTECI.COM Pramod Jain, Ph.D. Presented

More information

Reaching the lowest cost of electricity with a revolutionary new PV plant technology. PEG PV substructure The revolution in utility scale PV power

Reaching the lowest cost of electricity with a revolutionary new PV plant technology. PEG PV substructure The revolution in utility scale PV power Reaching the lowest cost of electricity with a revolutionary new PV plant technology PEG PV substructure The revolution in utility scale PV power 2 The PEG PV substructure The PEG Effect: Save CAPEX and

More information

Laura Genao Director of Regulatory Affairs Southern California Edison May 18, 2012

Laura Genao Director of Regulatory Affairs Southern California Edison May 18, 2012 Laura Genao Director of Regulatory Affairs Southern California Edison May 18, 2012 1 Overview of SCE One of the nation s largest electric utilities Nearly 14 million residents in service territory and

More information

Transmission Policy and Wind Energy

Transmission Policy and Wind Energy Transmission Policy and Wind Energy Grid Operational Challenges and Regulatory Measures V Subramanian, CEO and Secretary General Indian Wind Energy Association (InWEA) Present Status and Enabling Provisions/Framework

More information

RE Tariff Setting Approach

RE Tariff Setting Approach Satadru Chakraborty Sr Research Associate, WISE Training Programme on the Regulatory and Policy Framework for Market Development for Renewable Energy in India Presentation Outline Policy & Regulatory provisions

More information

TECHNICAL SPECIFICATION DESIGN, PROCUREMENT, INSTALLATION AND MAINTENANCE OF PHOTOVOLTAIC SOLAR POWER PLANT AT AZRAQ REFUGEE CAMP

TECHNICAL SPECIFICATION DESIGN, PROCUREMENT, INSTALLATION AND MAINTENANCE OF PHOTOVOLTAIC SOLAR POWER PLANT AT AZRAQ REFUGEE CAMP TECHNICAL SPECIFICATION DESIGN, PROCUREMENT, INSTALLATION AND MAINTENANCE OF PHOTOVOLTAIC SOLAR POWER PLANT AT AZRAQ REFUGEE CAMP July 2015 GENERAL SPECIFICATION 1. The contractor shall quote for the complete

More information

Appendix D. Minimum Requirements For Developmental Resources For

Appendix D. Minimum Requirements For Developmental Resources For Minimum For Developmental Resources For 2016 Request For Proposals For Long-Term Renewable Generation Resources For Entergy New Orleans, Inc. DRAFT Entergy Services, Inc. May 6July 13, 2016 MINIMUM REQUIREMENTS

More information

TENDER FOR COMMMUNITY ENERGY PROJECT

TENDER FOR COMMMUNITY ENERGY PROJECT TENDER FOR COMMMUNITY ENERGY PROJECT Background [Include your key messages and a description of where your project is up to] Business description

More information

GIZ Municipal Solar PV Training Solar Procurement For Local Government

GIZ Municipal Solar PV Training Solar Procurement For Local Government GIZ Municipal Solar PV Training Solar Procurement For Local Government 1 Agenda Solar Procurement For Local Section Government Heading 1. Existing Municipal project overview 2. Business models for RE Own

More information

PROJECT ALLOCATIONS UNDER THE NATIONAL SOLAR MISSION PHASE II BATCH I: AN OVERVIEW

PROJECT ALLOCATIONS UNDER THE NATIONAL SOLAR MISSION PHASE II BATCH I: AN OVERVIEW PROJECT ALLOCATIONS UNDER THE NATIONAL SOLAR MISSION PHASE II BATCH I: AN OVERVIEW Sunrise at Dal Lake, Srinagar March 2014 www.headwaysolar.com Abbreviations JNNSM SECI NVVN LCOE DCR VGF PV CSP MNRE Jawaharlal

More information

Solar Cell Optimization: Cutting Costs and Driving Performance

Solar Cell Optimization: Cutting Costs and Driving Performance Solar Cell Optimization: Cutting Costs and Driving Performance 1 Executive Summary Over the past several years, DC optimizers have become an important technological ingredient in many residential, commercial

More information

renewable energy services and applications

renewable energy services and applications renewable energy services and applications www.2en.com profile 2EN [Enallaktiki Energiaki SA], founded in 2001, is a dynamically developing company with extensive experience in the field of Renewable Energy.

More information

Renewable Energy Feasibility Study for Ione Band of Miwok Indians

Renewable Energy Feasibility Study for Ione Band of Miwok Indians Renewable Energy Feasibility Study for Ione Band of Miwok Indians By: Community Assessment of Renewable Energy and Sustainability & The Renewable and Appropriate Energy Laboratory Contents i. About CARES

More information

Table 1: Financial Analysis for without and with storage scenarios

Table 1: Financial Analysis for without and with storage scenarios Note on Preliminary Financial and Economic Analysis for Energy Storage Solutions and Floating Solar Photovoltaic for India: Innovation in Solar Power and Hybrid Technologies Project Energy Storage Solutions:

More information

We are pleased to quote our best price for 5 M W Solar Plant as appended. Annexure I : Price Schedule for 5 M W Solar Plant

We are pleased to quote our best price for 5 M W Solar Plant as appended. Annexure I : Price Schedule for 5 M W Solar Plant Dear Sir Greetings to you Subject: Offer for Supply of 5 M W Solar Plant Ref: Add posted on site Dear Sir, Greetings to you We are pleased to quote our best price for 5 M W Solar Plant as appended. Annexure

More information

TAKING ENERGY FORWARD enabling a world powered by reliable and affordable solar electricity.

TAKING ENERGY FORWARD enabling a world powered by reliable and affordable solar electricity. TAKING ENERGY FORWARD enabling a world powered by reliable and affordable solar electricity. First Solar Overview PV a Solution to Contemporary Energy Problems The Role of Utility-Scale PV Copyright 2013,

More information

The SUN is definitely rising, but will it shine?

The SUN is definitely rising, but will it shine? The SUN is definitely rising, but will it shine? Decoding the trend of falling solar tariffs in India Rahul Gaba Gurpreet Chugh Introduction Solar tariffs in India have continued to fall during the last

More information

Utility-scale PV challenges in the Australian market

Utility-scale PV challenges in the Australian market Utility-scale PV challenges in the Australian market All-Energy Conference 2016 October 4, 2016 Renzo Gaggioli Senior Project Manager, Energy Business www.canadiansolar.com Safe Harbor Statement This presentation

More information

PERFORMANCE VALIDATION AND PLANT

PERFORMANCE VALIDATION AND PLANT PERFORMANCE VALIDATION AND OPTIMIZATION OF UTILITY SCALE PV PLANT ASEF ASIA SOLAR ENERGY FORUM 2015 Manila 15 June 2015 M&P at a glance ABOUT US Moroni & Partners is a consultant engineering company specialized

More information

STATKRAFT BLP SOLAR SOLUTIONS. WORLD RENEWABLE ENERGY TECHNOLOGY CONGRESS, NEW DELHI

STATKRAFT BLP SOLAR SOLUTIONS. WORLD RENEWABLE ENERGY TECHNOLOGY CONGRESS, NEW DELHI STATKRAFT BLP SOLAR SOLUTIONS. WORLD RENEWABLE ENERGY TECHNOLOGY CONGRESS, NEW DELHI About SBSS: Statkraft BLP in India a confluence of global and local } Statkraft BLP Solar Solutions (SBSS) began its

More information

UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES

UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES UNDERGROUND COAL GASIFICATION - POWER OPPORTUNITIES Jay Govender - National Practice Head - Projects and Infrastructure Cliffe Dekker Hofmeyr South Africa STRUCTURE OF PRESENTATION Regulatory Overview

More information

Global Cumulative Capacity of Offshore Wind (MW)

Global Cumulative Capacity of Offshore Wind (MW) Offshore Wind Capacity (MW) EUROPEAN OFFSHORE WIND COST REDUCTIONS & IMPLICATIONS FOR NORTH AMERICA July 2017 www.poweradvisoryllc.com To: Clients and Colleagues From: John Dalton, President, James Takami

More information

Solar Mango s India MW Solar Advisor Sample Report INDIA MW SOLAR ADVISOR. Sample Report

Solar Mango s India MW Solar Advisor Sample Report INDIA MW SOLAR ADVISOR. Sample Report 2015 Solar Mango s India MW Solar Advisor INDIA MW SOLAR ADVISOR Why Do You Need An Expert Guide for MW Solar Power Plants? The solar power sector is still quite new in India, just about 5 years old. Unlike

More information

Renewable Energy Guidelines on. Solar PV Rooftop Implementation: Thailand. Version 1.0. E-Guidebook October 2017

Renewable Energy Guidelines on. Solar PV Rooftop Implementation: Thailand. Version 1.0. E-Guidebook October 2017 Renewable Energy Guidelines on Solar PV Rooftop Implementation: Thailand Version 1.0 E-Guidebook October 2017 Imprint Authors Tanai Potisat (GIZ) Thachatat Kuvarakul (GIZ) Boonrod Yaowapruek (USAID Clean

More information

Complete PV Power Plant Certification Technical Bankability

Complete PV Power Plant Certification Technical Bankability Complete PV Power Plant Certification Technical Bankability VDE, along with our partner Fraunhofer ISE are offering comprehensive quality assurance for solar photovoltaic (PV) power plant performance.

More information

Bifacial PV and Tracking - The Simulation and Optimization of Yield Gain

Bifacial PV and Tracking - The Simulation and Optimization of Yield Gain Bifacial PV and Tracking - The Simulation and Optimization of Yield Gain October 25 th 2018 Andrea Viaro, JinkoSolar Co., Ltd. Global PV LCOE Sliding Down Source: Bloomberg 1H 2018 Solar LCOE Update 2

More information

STATKRAFT BLP SOLAR SOLUTIONS. CII GREEN POWER CONFERENCE, CHENNAI

STATKRAFT BLP SOLAR SOLUTIONS. CII GREEN POWER CONFERENCE, CHENNAI STATKRAFT BLP SOLAR SOLUTIONS. CII GREEN POWER CONFERENCE, CHENNAI About SBSS: Statkraft BLP in India a confluence of global and local Statkraft BLP Solar Solutions (SBSS) began its journey in November

More information

A World Bank Group solution to rapidly expand private investment in utility-scale solar PV

A World Bank Group solution to rapidly expand private investment in utility-scale solar PV A World Bank Group solution to rapidly expand private investment in utility-scale solar PV Rome Italy October 28, 2016 Stratos Tavoulareas Senior Energy Advisor Solar power generation has reached a tipping

More information

Market Requirements Document

Market Requirements Document Market Requirements Document Committee name: Prepared by: Deployment Working Group Joseph H. Cain, P.E. Modified Date: 1.05.17 Revision Number: 1 This work was created under the DOE Project Number EE-0007315

More information

(Draft Captive and Renewable Energy Generating Plants) Regulations

(Draft Captive and Renewable Energy Generating Plants) Regulations 307 Sl. No. UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION Description (Draft Captive and ) Regulations - 2014 1. Short title, extent and commencement. 2. Scope and extent of application Summary (i) Uttar

More information

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India 450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India WEST BENGAL ELECTRICITY REGULATORY COMMISSION Cogeneration and Generation of Electricity

More information

Cover Page for CTF Project/Program Approval Request 1

Cover Page for CTF Project/Program Approval Request 1 Cover Page for CTF Project/Program Approval Request 1 1. Country/Region Nigeria 2. CIF Project ID# 3. Investment Plan (IP) or 4. Public or X IP Dedicated Private Sector Private Program (DPSP) DPSP 5. Project/Program

More information

Reducing Solar Performance Uncertainty. Presented by: Gwendalyn Bender, Head of Solar Product Development

Reducing Solar Performance Uncertainty. Presented by: Gwendalyn Bender, Head of Solar Product Development Reducing Solar Performance Uncertainty Presented by: Gwendalyn Bender, Head of Solar Product Development Vaisala Measurement, Assessment, Forecasting Over 80 years helping industries manage the impact

More information

SUPPORT EXISTING FOR AND

SUPPORT EXISTING FOR AND Indian Biomass Power sector 1 FINANCIAL FRAMEWORK TO SUPPORT EXISTING FOR AND NEW BIOMASS POWER PLANTS MNRE Workshop on Biomass Sector - 9 th June 2014 Indian Biomass Power Association Why Biomass Power?

More information

Photovoltaic System Installation Request for Proposals. Notus Junior-Senior High School Notus, ID

Photovoltaic System Installation Request for Proposals. Notus Junior-Senior High School Notus, ID Photovoltaic System Installation Request for Proposals Notus Junior-Senior High School Notus, ID This Request for Proposals ( RFP ) is to solicit competitive quotes from photovoltaic (PV) system installers

More information

IEC Installation Guide for SERAPHIM Photovoltaic Module

IEC Installation Guide for SERAPHIM Photovoltaic Module SUSA [InstallationGuide] 2016.11_V1.0 IEC Installation Guide for SERAPHIM Photovoltaic Module Table of Contents 2 Purpose of this guide General safety Handling safety Installation safety Fire safety 5

More information

A holistic view of quality: building quality infrastructure for solar PV INTERSOLAR

A holistic view of quality: building quality infrastructure for solar PV INTERSOLAR A holistic view of quality: building quality infrastructure for solar PV INTERSOLAR Munich, Germany 1 June 2017 PV deployment Growth in PV deployment From 290 GW in 2016 (~100 GW/year) Source: IRENA Remap

More information

Gandhi Nagar 5 MW Solar Distributed/ Rooftop PPP Project

Gandhi Nagar 5 MW Solar Distributed/ Rooftop PPP Project Gandhi Nagar 5 MW Solar Distributed/ Rooftop PPP Project Sharing experience on doing an innovative Solar PPP Project Renewable Energy Workshop 1 st Feb. 2012 1 Agenda Overview of the Solar Programme in

More information

Ref. No.: SRMU/NDP-I/VBMPS-II/ INVITATION FOR QUOTATION FOR SUPPLY OF GOODS UNDER SHOPPING PROCEDURES

Ref. No.: SRMU/NDP-I/VBMPS-II/ INVITATION FOR QUOTATION FOR SUPPLY OF GOODS UNDER SHOPPING PROCEDURES Ref. No.: SRMU/NDP-I/VBMPS-II/ dt.22.09.2017 To INVITATION FOR QUOTATION FOR SUPPLY OF GOODS UNDER SHOPPING PROCEDURES P Dear Sir, Sub : INVITATION FOR QUOTATIONS FOR SUPPLY OF Rooftop Solar PV system

More information

PROJECT DEVELOPMENT. Spain India UK Egypt UAE

PROJECT DEVELOPMENT. Spain India UK Egypt UAE IPP & PROJECT DEVELOPMENT P.O.Box 301, Riyadh-11411, Kingdom of Saudi Arabia T: +966 92 000 6111 Ext.4003 / 4915 F: +966 11 275 2839 E: ae@alfanar.com www.alfanar.com Spain India UK Egypt UAE ALFANAR ENERGY

More information

Renewable Energy Resource Mapping of Pakistan. Anjum Ahmad Senior Energy Specialist WB. Nafees Ahmad Khan Project Coordinator AEDB

Renewable Energy Resource Mapping of Pakistan. Anjum Ahmad Senior Energy Specialist WB. Nafees Ahmad Khan Project Coordinator AEDB Renewable Energy Resource Mapping of Pakistan Anjum Ahmad Senior Energy Specialist WB Nafees Ahmad Khan Project Coordinator AEDB Sequence of Presentation... Brief Introduction of Alternative Energy Development

More information