Victoria Station Upgrade PAL 10. The challenges of mining an escalator barrel within an operational station

Size: px
Start display at page:

Download "Victoria Station Upgrade PAL 10. The challenges of mining an escalator barrel within an operational station"

Transcription

1 Victoria Station Upgrade PAL 10 The challenges of mining an escalator barrel within an operational station Ryan McCarron Harding Prize Submission Paper 2015

2 CONTENTS Table of Figures... 3 Acknowledgements... 3 Abbreviations... 3 Introduction... 1 Project Organisation... 1 Design Considerations... 2 Requirements... 2 Location... 2 Spatial Constraints... 3 Design... 3 Geometry... 4 Modelling... 4 Ground Conditions... 4 Sprayed Concrete Lining... 5 Construction... 5 Sequence... 5 Ground Treatment... 6 Upper Machine Chamber... 6 Preparatory Works... 7 Upper Barrel... 8 Cross Passage Construction... 9 Lower Barrel and Lower Machine Chamber Conclusion RYAN MCCARRON

3 TABLE OF FIGURES Figure 1: Congestion outside Victoria... 1 Figure 2: Upgraded Scheme... 1 Figure 3: Congestion on platform... 2 Figure 4: Victoria Line and Concourse Tunnel... 2 Figure 5: Existing Assets... 3 Figure 6: Elevation showing ground conditions and existing assets... 3 Figure 7: Proposed geometry... 4 Figure 8: 3D model showing advance sequence... 4 Figure 9: Elevation showing jet grout column layout... 4 Figure 10: Section through existing platforms and new escalator... 5 Figure 11: Sequence of Works... 6 Figure 12: Installation of inclined jet grout columns at the rear of the VPT... 6 Figure 13: Menzi Muck in operation... 7 Figure 14: Upper Machine Chamber under construction... 7 Figure 15: Temporary adit to facilitate preparatory works... 8 Figure 16: Construction of ramp within concourse tunnel... 8 Figure 17: Elephant's Foot Detail... 9 Figure 18: Completed UMC and upper barrel... 9 Figure 19: Concourse support frame Figure 20: Excavation between concourse and platform tunnels Figure 21: Location of IPI Figure 22: Steelwork encountered during existing cross passage breakout Figure 23: SCL Hood Figure 24: SCL Hood Constructed ACKNOWLEDGEMENTS Taylor Woodrow BAM Nuttall Joint Venture London Underground Ian Heath Taylor Woodrow BAM Nuttall JV Anmol Bedi Mott MacDonald ABBREVIATIONS VSU Victoria Station Upgrade TfL Transport for London TWBN Taylor Woodrow BAM Nuttall (JV) PAL Paid Area Link SCL Sprayed Concrete Lining SER Signal Equipment Room VPT Victoria Palace Theatre LU London Underground RIBA Royal Institute of British Architects UMC Upper Machine Chamber LMC Lower Machine Chamber CI Cast Iron IPI In Place Inclinometers RYAN MCCARRON

4 INTRODUCTION The Victoria Station Upgrade (VSU) project is part of Transport for London s (TfL s) multibillion pound Investment Programme to improve and expand the transport network. The Taylor Woodrow BAM Nuttall (TWBN) joint venture were awarded the contract in 2010 to upgrade Victoria Station. This entailed enlarging the Victoria Line ticket hall by fifty per cent, constructing an additional ticket hall leading to the northern end of the platforms, connecting the new and existing ticket halls via approximately four hundred metres of new passenger tunnels and providing step-free access to the station. These improvements will address the congestion problems (Figure 1) in the station, extending its life by approximately 75 years. The redevelopment of Victoria Station (Figure 2) is essential to facilitate the upgrade of the Victoria Line. The two together will result in quicker, easier, and less congested journeys for thousands of Londoners. This paper describes the design and construction of Paid Area Link 10 (PAL 10), a nine metre diameter, thirty metre long sprayed concrete lined (SCL) escalator barrel. The new tunnel descends at 30 degrees through an existing concourse tunnel and between the operational Victoria Line platform tunnels. In its completed form, the barrel will house a three-bank escalator providing the Figure 1: Congestion outside Victoria required access to the northern end of the Victoria Line platforms. The proximity of the escalator to existing assets, the ground conditions through which it is constructed, the complexities of the construction sequence and the client s requirement to maintain an operational station render this endeavour a unique tunnelling achievement. During this time I was the Sub Agent in charge of all the SCL works at Victoria Station Upgrade. PROJECT ORGANISATION Client London Underground Ltd Principal Contractor Taylor Woodrow BAM Nuttall Joint Venture Designer Mott MacDonald Sub-Designer Alan Auld Limited Specialist Sub- Keller Ground Engineering Contractor 2018 Figure 2: Upgraded Scheme RYAN MCCARRON PAGE 1

5 DESIGN CONSIDERATIONS REQUIREMENTS Two banks, each of three escalators currently serve the Victoria Line transporting passengers from street level to the Victoria Line platforms. However both of these provide access to the southern end of the Victoria Line platforms, naturally limiting the length of platform used by passengers. The congestion at the southern end of the platforms frequently results in platform overcrowding (Figure 3). To ensure safety, this requires closure of the whole station at street level causing disruption to many passenger journeys. between the two lines (Figure 4). These cross passages allow redistribution of passengers along the platform. It is this concourse tunnel where the new escalator is required to connect to the Victoria Line. Figure 4: Victoria Line and Concourse Tunnel The platforms tunnels at Victoria converge at the northern end to provide a crossing of the running tunnels just north of the station. Therefore the resulting clearance between the northbound and southbound platform is significantly compromised. Subsequently the concourse tunnel between the platform tunnels reduces in diameter. In reality, to achieve a three bank escalator the entire concourse tunnel would have to be demolished to provide sufficient space causing major disruption to the station. Figure 3: Congestion on platform Extensive passenger modelling of the existing station at Victoria was undertaken and it was identified that a significant proportion of journeys start and end on Victoria Street, at the northern end of the station. Modelling identified the requirement to provide access from street level to the northern end of the Victoria Line platforms to alleviate congestion. Construction of a new ticket hall which would be connected to the Victoria Line through the construction of an escalator barrel and additional cross passages. Further pedestrian modelling confirmed that a bank of three escalators would be required to carry the predicted passenger flow. LOCATION The Victoria Line platform tunnels are currently separated by a concourse tunnel that runs along the platform length. This tunnel is where the current escalators connect into the Victoria Line and forms part of the existing cross passages Further defining the precise location at which the concourse tunnel received the new escalator is one of the Victoria Line signal equipment rooms (SER) controlling a southern section of the Victoria Line. During a signal upgrade of the Victoria Line this was located to the northern end of the concourse and could not be relocated to facilitate the upgrade works. The available footprint within the station, the existing access and operational assets governed the location of the barrel; the passenger modelling governed the size of the barrel. At ground level the conditions were not favourable. Directly above the proposed location lies the Victoria Place Theatre (VPT) a grade II star listed building entertaining Londoners with six performances of Billy Elliot per week. The foundations of this building extend 4m below the ground level. RYAN MCCARRON PAGE 2

6 Figure 5: Existing Assets SPATIAL CONSTRAINTS The geometry of the proposed escalator was heavily influenced by the proximity to existing London Underground (LU) assets (Figure 5). The main requirement was the escalator had to be of sufficient size to house three HD Metro escalators and their associated equipment. The end location within the existing concourse tunnel was dictated by the need to ensure there was sufficient run off between the end of the new escalators and the start of the existing escalators within the concourse tunnel. The detailed constraints in location and in particular the location of the SER (Figure 6) rendered a uniform profile impossible. The design team were required to model a number of significant changes in the geometry of the profile as the escalator descended to accommodate the requirements and fit within the various restrictions. The only way this was possible was to control the excavation profile as it exposed the crown of the concourse tunnel housing the SER and subsequently expose the back of the cast iron platform tunnels. Throughout the majority of the length of the proposed escalator, the clearance to existing structures was negligible. The construction sequence developed by the design and build contractor was integral in managing this risk. Figure 6: Elevation showing ground conditions and existing assets DESIGN The TWBN JV were engaged on a design and build contract at RIBA stage E allowing early involvement in the design. The design development phase commenced a year prior to the enabling works on site where the Designer and Contractor worked together to ensure efficiency in the design and construction. TWBN were committed to ensure the following principles were maintained throughout the design phase: Minimise the impact on the operational railway Simplicity in design and construction Provide programme certainty Provide cost certainty Minimise risk RYAN MCCARRON PAGE 3

7 GEOMETRY Following the development of the initial design the basic geometry of the permanent works was developed. The escalator would be split into three sections (Figure 7): Upper machine chamber - horizontal Barrel - Inclined 30 degrees Lower machine chamber horizontal Figure 7: Proposed geometry MODELLING Due to the complexity of the geometry and the construction sequence it was necessary to develop a sophisticated three dimensional numerical model to analyse the effects of the construction on the operational station and surrounding assets. The model developed a step by step analysis of the proposed advance sequence and a three dimensional representation of the existing assets which was used to finalise the advance sequence (Figure 8). Figure 8: 3D model showing advance sequence Following input of the defined constraints into the model, the advance sequence could be analysed. The initial assessments modelled a one metre heading and bench excavation and predicted unacceptably large deformations in the platform tunnels as the ground was removed between the tunnels. The predicted deformations would be large enough to cause significant damage to the platform tunnels. These would have to be closed during construction and possibly rebuilt. GROUND CONDITIONS The Upper Machine Chamber (UMC) of the escalator was to be constructed through water bearing gravels. Throughout the VSU project, the tunnels have all been constructed through this material and to allow this by pre-treating the ground using a method called jet grouting. Jet grouting is an erosion replacement process whereby the granular soils are mixed at high pressure with grout creating a composite stiff, dry medium. The resulting engineered columns are designed to provide a stable, impermeable medium for construction of tunnels (Figure 9). Figure 9: Elevation showing jet grout column layout The ground treatment was designed to provide a full face of treated material through which to excavate. This would additionally provide a two metre annulus around the excavation perimeter of the tunnel to provide stability to the saturated sands and gravels. It also provides a water cut-off between the excavation and the untreated ground. The works would be undertaken from ground level therefore the positioning of the rig and drill rod would be further constrained. With the Victoria Palace Theatre directly above the jet grout columns would need to be heavily inclined. The proximity of the theatre foundations meant it was necessary to install the jet grout columns through the foundations of the building whilst not disrupting the week s performances or rehearsals. RYAN MCCARRON PAGE 4

8 Jet grouting as a methodology was unproven on this scale. The critical nature of the escalator combined with the unfavourable ground conditions meant this treatment was the only viable solution. SPRAYED CONCRETE LINING The complex geometry associated with PAL 10 called for the tunnel to be constructed using a sprayed concrete lining. This provided flexibility in both lining thickness and profile. This allowed the tunnel to fit between existing assets with the profile varying as required to create sufficient space for the future escalators. The design premise was to provide a sequential excavation and support method, which utilises early strength gain in the sprayed concrete to minimise ground movements. In addition the sprayed concrete is fibre reinforced to provide flexural toughness and mesh can be introduced in areas of the lining under significant stress, which was required through the acute changes in geometry of the lining. CONSTRUCTION SEQUENCE Throughout the development of the design the concerns of the excessive movement predicted in the existing assets was reinforced. It became clear that whilst the design of the tunnel itself worked, it did not work within the strict movement limits on the existing assets (Figure 10). In order to safely construct PAL 10 the Contractor would have to combine the design with a novel construction sequence and the use of a number of different construction methodologies. The only solution was to develop a sequence whereby the existing tunnels could be stiffened prior to sinking the barrel past the axis of the existing platform tunnels. The traditional solution to this was through internal propping of the tunnel. This would not be viable as it would call for the closure of the Victoria Line platforms. The resulting proposal involved constructing a new pair of cross passages between the existing platform tunnels to provide the stiffness prior to the excavation of the lower section of the barrel and the lower machine chamber. The large deformations predicted by the numerical modelling demonstrated the locations at which the deformations would occur in the tunnel. It was suggested that by constructing the permanent cross passages first and therefore increasing the overall stiffness of the platform tunnels, construction of the barrel could be undertaken with manageable movements. In conjunction with this issue there was also a requirement identified to stabilise the concourse tunnel during construction. The sequence was modelled and whilst there were still significant deformations they fell within acceptable limits. The existing concourse tunnel was only accessible through the operational station, however due to the magnitude of preparatory works required a new access into the concourse would need to be formed. Assessing all the sequence issues the design produced adhered to the following sequence shown in Figure 11: A - Construct Upper Machine Chamber B - Drive temporary adit to closed section of concourse tunnel to carry out preparatory works C - Complete upper section of barrel to provide access to existing concourse D - Construct new cross passages from existing concourse tunnel to platform tunnels and backfill E - Construct lower section of barrel and lower machine chamber Figure 10: Section through existing platforms and new escalator RYAN MCCARRON PAGE 5

9 The construction of the new cross passages required to facilitate the closure of the concourse involved the sinking of a shaft between the Victoria Line running tunnels at the northern end and the construction of an access passageway between the Victoria Line platforms using traditional square works techniques to form the new cross passage. This was a significant phase of works not covered in this paper. The closure of the concourse tunnel and removal of all services within the area was also a key milestone for the commencement of the major tunnelling works. GROUND TREATMENT TWBN s specialist sub-contractor Keller installed the jet grout columns. Due to the proximity of the proposed columns to the foundations of the VPT it was necessary to drill an inclined core through the foundations of the VPT (Figure 12). This allowed the installation of the drill string through the core hole to reach the location of the inclined jet grout column. Figure 12: Installation of inclined jet grout columns at the rear of the VPT Figure 11: Sequence of Works To provide the required coverage of jet grout approximately two hundred columns were installed with varying diameters and inclination to provide the cut off of groundwater from the excavation. The installation of these columns was carried out in a very restricted worksite during adjacent piling works and sewer diversion. UPPER MACHINE CHAMBER In order to construct the escalator a series of specialist items of plant were required. RYAN MCCARRON PAGE 6

10 TWBN purchased a Menzi Muck M540 to carry out the excavation of the tunnel, an excavator designed to work on inclines (Figure 13). Additionally TWBN modified a Putzmeister SPM300 spraying robot to work on the slope. The development of this specialised plant was key to the successful and safe construction of the escalator. Figure 13: Menzi Muck in operation The upper section of the escalator is known as the Upper Machine Chamber (UMC). Due to the relative size of the cut and cover structure and the escalator barrel the invert was significantly deeper than the slab from which the drive started. This defined the excavation and support sequence that was employed for the construction of the UMC. Figure 14: Upper Machine Chamber under construction The UMC was driven initially through a series of headings with a temporary invert. This facilitated the construction of approximately 7m of tunnels (Figure 14). At this point the invert was excavated from the face towards the tunnel eye. This allowed the full tunnel profile to be excavated for the UMC despite the relative difference in level from the cut and cover structure to the invert of the tunnel. Throughout the construction of the UMC the excavation was undertaken through the jet grouted sand and gravel. To provide assurance to the client and the construction team a series of Daily Review Meetings were employed to compare the as-built records to the 3D model showing the asbuilt positioning of the columns. This allowed the generation of the theoretical face logs identifying areas where the extent of ground treatment was reduced. Throughout the excavation in the jet grout a series of expected gaps were found within the tunnel profile. The associated ingress of the untreated sand and gravel was successfully managed during the construction phase. The UMC was excavated directly above the operational Signal Equipment Room. The average clearance from the crown the concourse tunnel housing the equipment room and the invert of the excavation was 400mm. The key control measure was to ensure there was no excessive vibration during the construction of the UMC as the signalling equipment within the room was extremely sensitive. TWBN commissioned the installation of real time vibration monitors with trigger levels set in conjunction with the LU signals team allowing the production team to understand the impact of each advance. PREPARATORY WORKS Ordinarily the only access to the concourse tunnel was from within the station. It would be impossible to carry all the required tools and equipment down through the station during engineering hours and carry out the works using this as an access. Further still, concrete construction was required on a large scale which could not be completed during LU Engineering Hours. To this end a temporary adit was driven from the headwall of the UMC (Figure 15). The adit was constructed as a traditional timber box heading large enough to facilitate an access route for labour and materials into the existing tunnel. This provided access from the UMC into the existing concourse tunnel. Once the access was created into the concourse tunnel, the existing cross passages were sealed with a reinforced concrete wall. The location in which the escalator barrel RYAN MCCARRON PAGE 7

11 entered the existing concourse tunnel required the construction of a permanent concrete ramp. Figure 15: Temporary adit to facilitate preparatory works This was to provide suitable support to the invert of the barrel as it descended into the concourse tunnel. Upon completion of the permanent concrete ramp (Figure 16) the remaining section of the concourse tunnel was backfilled with a low strength fill to allow it to be easily excavated. UPPER BARREL Once the preparatory works within the existing station were complete, the inclined barrel construction could commence. The upper barrel was constructed on a 24/7 shift pattern taking a total of 13,000 man hours. The escalator barrel was to be constructed through the remaining jet grout, London Clay and subsequently the existing station. Through these various mediums, no two advances were the same. The variability of materials, skilled labour and plant that was on site to deal with any inevitability was unprecedented. The initial pair of cross passages was encountered, these were constructed in the 1960 s and the excavation of these was undertaken from the top. This involved extensive breakout and removal of existing concrete and steelwork utilising low vibration tools and techniques. As the escalator barrel descended into the exiting station, the profile intersected the last cast iron ring in which the SER was housed. The geometrical requirements for the lining profile called for this to be sprayed within the profile. The proximity of the cross passages and their connections to the existing station made this phase of work extremely demanding. The barrel was to be excavated in a staggered heading and bench sequence. During the construction of the first phase of the barrel the profile descended through the jet grout, and fully into the London Clay, encountering and demolishing the existing station as it progressed. As the excavation profile descended fully into the clay the low clay cover became a primary concern. The crown of the barrel and subsequently the Lower Machine Chamber (LMC) had only two metres of clay cover with the saturated gravels overlying. In addition to this the saturated gravels formed the foundation material for the Victoria Palace Theatre. Figure 16: Construction of ramp within concourse tunnel Due to the critical nature of the clay cover and the relative size of the excavation the duration for which the crown of an advance was open posed a significant challenge. However as the excavation included sensitive demolition and existing of cast RYAN MCCARRON PAGE 8

12 iron (CI) tunnel rings and the breaking out of existing cross passages this required a change in the construction sequence. The design sequence for the barrel called for a staggered heading and bench sequence. This meant that the heading was hanging for the duration of the invert construction. As the time taken to removing the existing cross passages was significant, and the presence of the existing concourse tunnel meant that a temporary invert could not be installed it was decided to develop a Elephants Foot solution where the size of the top heading was increased and was footed onto the existing cross passage s (Figure 17). Figure 17: Elephant's Foot Detail This ensured full support to the vault of the excavation and subsequently reduced any potential impact of the low clay cover. This change in support sequence was developed onsite in conjunction with the designer s representative, the production team and the Client. It proved to be a key decision in the reduction in potential movements to the surrounding assets. Figure 18: Completed UMC and upper barrel The barrel was constructed down through the concourse tunnel to a point where suitable access could be gained for the construction of the cross passages (Figure 18). At this location a full-face headwall was sprayed to allow the commencement of the handworks require to construct the new cross passages. It was envisaged that the headwall and the barrel would remain in this temporary state throughout the cross passage construction. CROSS PASSAGE CONSTRUCTION At the bottom of the proposed escalator a pair of new cross passages had to be constructed. Traditionally a new tunnel is required through which the cross passages could be built, however in this case the concourse tunnel was already present. The cross passage construction required the formation of two new openings on the operational Victoria Line platforms. Historically the formation of a cross passage opening requires significant propping to be installed on the operational side of the asset. This was not feasible in Victoria as the existing platform width was small too small. This quandary led to the development of a propless cross passage construction. It called for a small hoarding to be installed on the platform side of the works (approx. three hundred millimetres into the passenger envelope) and all remaining work would be carried out from the new tunnels. To ensure the constructability, TWBN would need to gain sufficient access to the existing concourse tunnel to construct the new cross passages. The basic design premise of the cross passage construction was to limit deformation of the existing linings during construction. This was achieved through the use of two basic principles. Firstly excavation should be limited to small headings prior to the installation of support members, and secondly the additional support members should provide a significant increase in stiffness of the existing asset allowing further excavation and subsequent deformation to take place. The first activity associated with the cross passage construction was to mine out the remaining RYAN MCCARRON PAGE 9

13 temporary backfill in the concourse tunnel to provide access. At this time due to the extent of breakout required within the existing concourse tunnel to form the new cross passages a series of Y-frames (Figure 19) were installed to support the crown of the concourse tunnel. Figure 19: Concourse support frame The cross passages were excavated in the series of benches installing the permanent works as the excavation progressed. Initially the top bench was excavated, the upper strongback was installed and the permanent concrete for the cross passage was poured. This provided significant strengthening to the existing platform tunnels to prevent excessive deformation. The subsequent benches were excavated with a series of temporary props being installed to support the platform tunnel. This excavation was carried out by hand, and approximately three hundred millimetres away from passengers (Figure 20). The formed a six metre deep excavation between the operational platform tunnel and the concourse tunnel. Following completion of the excavation the lower strongback was installed along with the jamb frames allowing completion of the remaining permanent works concrete. The permanent works concrete was cast to the profile of the future LMC excavation. Due to the relative size of the concourse tunnel to the proposed LMC that would replace it, it was necessary to temporarily backfill the void left. This would allow the LMC chamber to be excavated through a weak backfill in contrast to a void which would not allow the formation of the full primary lining profile. LOWER BARREL AND LOWER MACHINE CHAMBER Following completion of the handworks this released the construction of the lower barrel and the lower machine chamber. Due to the significant durations required for the construction of the upper barrel there were additional concerns over the low clay cover through the LMC. To this end it was decided to install a horizontal In-Place- Inclinometer (IPI) through the crown of the LMC (Figure 20). This was completed prior to the restart of excavation works. The IPI would allow the deformation of the clay vault to be monitored during the excavation and would allow an assessment to be made on whether additional support measures would be required during the construction. This provided a key insight into the performance of the small layer of clay above the crown of the tunnel. Figure 20: Excavation between concourse and platform tunnels Figure 21: Location of IPI RYAN MCCARRON PAGE 10

14 As the excavation recommenced the barrel descended below the axis of the existing Victoria Line platforms. At this point the excavation profile exposed the back of the cast iron for the existing platforms. The barrel then levelled out to form the LMC. This involved the excavation of clay, breakout of cross passage concrete, removal of permanent and temporary steelwork, all with negligible clearance from the back of the cast iron platform tunnel and within three hundred millimetres of passengers. The successful completion of this phase of work hinged heavily on a collaborative relationship between London Underground and TWBN. TWBN identified the requirement to station an operative on the platform throughout all works. This provided eyes and ears on the platform and SER during the works. The face advanced further and encountered the second set of existing cross passages. This set of cross passages was constructed as part of the congestion relief scheme in the 1990 s. When the existing cross passages were exposed the quantity of temporary steelwork encountered was significantly larger than initially expected (Figure 22). This led to significant increase in the time taken to excavate and advance. the clay vault during the removal of the temporary work (Figure 24). Figure 23: SCL Hood Figure 24: SCL Hood Constructed Figure 22: Steelwork encountered during existing cross passage breakout Once again this duration posed a significant problem to the stability of the vault with the low clay cover. To this end the sequence for excavation of the advance was modified. This allowed the top of the vault excavation to be excavated over the existing concourse tunnel to form a SCL hood (Figure 23). The hood rested on the existing CI and provided temporary support to As the excavation of the lower machine chamber progressed through the existing cross passages and encountered the now redundant propping installed for the construction of the new cross passages, the excavation and dismantling of the propping was an intricate sequence to provide continuous support to the clay vault and existing platforms. The temporary fill installed following the cross passage construction was removed and the SCL lining was sprayed up against the permanent concrete installed during the construction of the new cross passages. The primary lining and permanent cross passages forming PAL 10 was completed in January 2015 with minimal disruption to the operational station. RYAN MCCARRON PAGE 11

15 CONCLUSION The construction of PAL 10 escalator was a critical element in the congestion relief scheme at Victoria Station Upgrade. Constraints above the ground and below the ground meant PAL 10 was challenging from the design phase right through to construction. The collaborative approach between TWBN and MM delivered a design solution in a very complex environment. The follow on construction phase demanded a robust approach to client assurance. The development of the propless solution for the cross passage construction resulted in a limited impact on the operational side of the platform satisfying both client and contractor requirements. An innovative design coupled with an adaptive construction sequence provided a solution to a seemingly insurmountable problem. The strong working relationship developed between contractor and client provided the client with the confidence that the risk associated with working in such close proximity to their asset was understood. Effective communication between the contractor and the operational staff on the station was key in ensuring the works could progress effectively and ultimately the successful delivery of PAL 10. RYAN MCCARRON PAGE 12

UK POWER NETWORKS BATTERSEA CABLE TUNNEL: POWERING A RENAISSANCE AT BATTERSEA S ICONIC POWER STATION

UK POWER NETWORKS BATTERSEA CABLE TUNNEL: POWERING A RENAISSANCE AT BATTERSEA S ICONIC POWER STATION UK POWER NETWORKS BATTERSEA CABLE TUNNEL: POWERING A RENAISSANCE AT BATTERSEA S ICONIC POWER STATION Gerard Quigg CEng MICE Senior Civil Engineer COWI UK Ltd. Table of Contents 1 Introduction... 1 2 Ground

More information

Learning Legacy Document Duration of data recorded (approx.) 1

Learning Legacy Document Duration of data recorded (approx.) 1 Table 1: Crossrail Water Consumption Data Contract C300/C410 - Crossrail Running Tunnels - West; Bond Street & Tottenham Court Road s - Early Access Shafts & SCL Works (JV: BAM Nuttall Ltd / Ferrovial

More information

Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro

Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro P. Kontothanassis, N. Koronakis, A. Karinas & S. Massinas Omikron Kappa

More information

Environmental Statement Non Technical Summary

Environmental Statement Non Technical Summary Crown copyright and database rights 2014 Ordnance Survey 100035971 Transport and Works Act 1992 London Underground (Bank Station Capacity Upgrade) Order Environmental Statement Non Technical Summary September

More information

SECANT PILE. Introduction:

SECANT PILE. Introduction: SECANT PILE Introduction: Over the last few decades construction of retaining walls in urban areas has grown significantly, as a result of territorial and economical development of the cities. In most

More information

Ground Freezing for Tunnel, Shafts, and Adits

Ground Freezing for Tunnel, Shafts, and Adits Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction

More information

GEOTECHNICAL SERVICES

GEOTECHNICAL SERVICES GEOTECHNICAL SERVICES Aarsleff Ground Engineering EXPERIENCE: Aarsleff s expertise as Ground Engineers is evidenced not only by its 25 years in UK construction and its dedicated staff, but in the decades

More information

Freezing techniques made a new tunnel possible

Freezing techniques made a new tunnel possible NGM 2016 Reykjavik Proceedings of the 17 th Nordic Geotechnical Meeting Challenges in Nordic Geotechnic 25 th 28 th of May Freezing techniques made a new tunnel possible Jens Kofod Nielsen Züblin A/S,

More information

SHAFT CONSTRUCTION SECANT PILE

SHAFT CONSTRUCTION SECANT PILE by Rob jameson and eric lindquist feature story SECANT PILE SHAFT CONSTRUCTION Modern Tools and Techniques Allow Excavation to Depths Previously Considered Infeasible By Rob Jameson and Eric Lindquist

More information

1 Introduction Feasibility Concept Design Detailed Design (Pile Separation)... 13

1 Introduction Feasibility Concept Design Detailed Design (Pile Separation)... 13 TABLE OF CONTENTS 1 Introduction... 1 1.1 Personal History... 1 1.2 Project Backgrounds... 1 1.3 Alignment... 5 2 Feasibility... 6 2.1 Desktop Study... 6 2.2 Scope Definition... 8 3 Concept Design... 10

More information

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000 The Institution of Engineers of Ireland Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000 MODULE 4 RETAINING STRUCTURES DEEP EXCAVATIONS

More information

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

D7: TUNNEL CONSTRUCTION AND METHODOLOGY HIGH SPEED TWO INFORMATION PAPER D7: TUNNEL CONSTRUCTION AND METHODOLOGY This paper outlines the proposed tunnelling methodology. It will be of particular interest to those potentially affected by the

More information

BUILDING INFORMATION MODELLING Enabling Construction: Victoria Station Upgrade ICE 15 January 2013

BUILDING INFORMATION MODELLING Enabling Construction: Victoria Station Upgrade ICE 15 January 2013 BUILDING INFORMATION MODELLING Enabling Construction: Victoria Station Upgrade ICE 15 January 2013 Glenn Keelan LU Programme Manager Rob Dickson Mott MacDonald Project Director BIM Enabling Construction:

More information

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng. SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT Srdjan Brasic, M.Sc., P.Eng. UMA Engineering Ltd. Paper prepared for presentation at the Technical

More information

No. 1 SPINNINGFIELDS MANCHESTER

No. 1 SPINNINGFIELDS MANCHESTER No. 1 SPINNINGFIELDS MANCHESTER Client: Project Manager: Description: Allied London Gardiner & Theobald Asbestos Removal Demolition Enabling Works Date: October 2014 to July 2015 Duration: Location: 41

More information

The Effect of mixed foundations on the response of some buildings to excavation

The Effect of mixed foundations on the response of some buildings to excavation The Effect of mixed foundations on the response of some buildings to excavation J.N. Shirlaw Golder Associates (Singapore) Pte Ltd D. Wen Land Transport Authority of Singapore R.A. Algeo CJ Associates,

More information

Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines

Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines Design and Construction Issues of the Soft-Eye Headwall for Brisbane AirportlinkM7 s 12.48m Diameter Tunnel Boring Machines Joseph Donohue 1, R. Greg Eberhardt 2 and Ildiko Juhasz 3 1 Associate, Arup 2

More information

Doing things differently

Doing things differently Project Waterloo and Southwest upgrade Location London, UK Client Network Rail Expertise Rail systems, civil, structural, building services, geotechnical, environmental and fire engineering, security,

More information

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID TRANSIT SYSTEM Chi-Te Chang, Ming-Jung Wang, Chien-Tzen Chang, and Chieh-Wen Sun Central District Office, Department of Rapid Transit System, Taipei

More information

Construction of Access Shafts for Tunnels and Deep Pipelines in Urban New Zealand

Construction of Access Shafts for Tunnels and Deep Pipelines in Urban New Zealand Construction of Access Shafts for Tunnels and Deep Pipelines in Urban New Zealand N Wharmby 1 ABSTRACT In recent years in New Zealand there have been a number of tunnelling and deep directionally drilled

More information

The Institution of Structural Engineers Chartered Membership Examination

The Institution of Structural Engineers Chartered Membership Examination The Institution of Structural Engineers Chartered Membership Examination 16th APRIL 2004 Structural Engineering Design and Practice 9.30 a.m. - 1 p.m. and 1.30-5 p.m. (Discussion between individuals is

More information

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY

CROSSRAIL INFORMATION PAPER D8 TUNNEL CONSTRUCTON METHODOLOGY CROSSRAIL INFORMATION PAPER TUNNEL CONSTRUCTON METHODOLOGY This paper sets out the proposed Crossrail tunnel construction strategy and methodology. It will be of particular relevance to those in the vicinity

More information

Misan University - College of Engineering Civil Engineering Department

Misan University - College of Engineering Civil Engineering Department CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s

More information

Appendix C. Gallery Place Chinatown Station Structural Assessment

Appendix C. Gallery Place Chinatown Station Structural Assessment Appendix C Gallery Place Chinatown Station Structural Assessment Washington Metropolitan Area Transit Authority February 2018 Gallery Place Chinatown Station Passageway RFI Contents APPENDIX C 1.0 Introduction:

More information

London s sewerage system was designed by Sir Joseph Bazalgette in the 1850s, for a population of four million

London s sewerage system was designed by Sir Joseph Bazalgette in the 1850s, for a population of four million Thames Tideway Tunnel technical challenges of the Tideway East section Chambers Wharf to Abbey Mills Pumping Station London s sewerage system was designed by Sir Joseph Bazalgette in the 1850s, for a population

More information

The HKIE Structural Examination Written Examination

The HKIE Structural Examination Written Examination The HKIE Structural Examination Written Examination Section 2: Design Questions (80% of the Written Examination) Date: 28 November 2014 (Friday) Time: 12:00 nn - 06:00 pm Answer ONE question only Question

More information

Passage under Lövstavägen at Bypass Stockholm From Design to Realization

Passage under Lövstavägen at Bypass Stockholm From Design to Realization Passage under Lövstavägen at Bypass Stockholm From Design to Realization Roslin Mattias 1, Borio Luca 2 and Tomas Hellström 3 1 Swedish Transport Administration, Solna Strandväg 98, 171 54 Solna, mattias.roslin@trafikverket.se

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price)

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES. Granular Backfill (Wingwalls) (Set Price) SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

inspection, assessment

inspection, assessment CIRIA C671 London 2009 Tunnels: inspection, assessment and maintenance L McKibbins R Elmer K Roberts Mott MacDonald Ltd Golder Associates (UK) Ltd Atkins Classic House, 174-180 Old Street, London EC1V

More information

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000

Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000 The Institution of Engineers of Ireland Modular Course on Foundations and Earth retaining Structures for Building and Infrastructure Projects 9th March 2000 MODULE 4 RETAINING STRUCTURES DEEP EXCAVATIONS

More information

An Introduction to Keller in the UK COLCRETE EURODRILL GETEC PHI GROUP. Piling and Ground Improvement. Grouting, Soil Nails and Anchors

An Introduction to Keller in the UK COLCRETE EURODRILL GETEC PHI GROUP. Piling and Ground Improvement. Grouting, Soil Nails and Anchors An Introduction to Keller in the UK Piling and Ground Improvement Grouting, Soil Nails and Anchors Retaining Walls Equipment Manufacture Monitoring and Instrumentation PHI GROUP GETEC COLCRETE EURODRILL

More information

Hale Allen Jones The Institution of Structural Engineers East Anglian Branch Award for Structural Excellence Submission

Hale Allen Jones The Institution of Structural Engineers East Anglian Branch Award for Structural Excellence Submission The Institution of Structural Engineers East Anglian Branch Award for Structural Excellence - 2003 Submission Details of Project Location Jarrold Whitefriars Office Development Whitefriars, Norwich. Project

More information

Contents. Glossary 9. Foreword 10

Contents. Glossary 9. Foreword 10 Glossary 9 Foreword 10 1 Design considerations 11 1.1 Introduction 11 1.2 Client's general requirements 11 1.3 The ground 11 1.3.1 The concept of effective stress 11 1.3.2 Ground profile 13 1.3.3 Groundwater

More information

Bauer Jet Grouting. Process

Bauer Jet Grouting. Process Bauer Jet Grouting Process Advantages of the Jet Grouting Process During the jet grouting process, the soil surrounding the drill string is eroded by a high energy fluid jet and mixed with a self hardening

More information

Specialising in Ground Engineering & Slope Stabilisation

Specialising in Ground Engineering & Slope Stabilisation Specialising in Ground Engineering & Slope Stabilisation Ground Engineering & Slope Stabilisation for the Road, Rail, Construction & Mining Industries Company Profile Warner Company is proudly an Australian

More information

Singapore 11 November Uphill Excavator Peter Leyton and Peter Coppenhall

Singapore 11 November Uphill Excavator Peter Leyton and Peter Coppenhall Uphill Excavator Peter Leyton and Peter Coppenhall Client Stakeholders Supplier Designers Contractors What is the Project? C510 contract Liverpool Street Station Whitechapel Station What was the problem?

More information

The Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok

The Construction of the Langham Place. An Urban Renewal Project that re-shaped the urban landscape of Mong Kok The Construction of the Langham Place An Urban Renewal Project that re-shaped the urban landscape of Mong Kok Artist Impression of Langham Place Fast Fact The site located in the heart of the Mongkok District

More information

SPECIFICATIONS FOR STRUCTURAL EXCAVATION

SPECIFICATIONS FOR STRUCTURAL EXCAVATION SPECIFICATIONS FOR STRUCTURAL EXCAVATION 1.0 DESCRIPTION The Work shall consist of:.1 Excavation and removal of material for the placement of foundations, substructure units, approach slabs, transition

More information

The concept of statical determinacy

The concept of statical determinacy Appendix 3 The concept of statical determinacy 140 A3.1 Introduction It has been shown that the conditions for equilibrium of a set of coplanar forces can be summarised in the three equations of equilibrium

More information

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2

SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR. Robert Small 1, Rob Jameson 2 ABSTRACT SEISMIC RETROFIT OF AN UNDERGROUND RESERVOIR Robert Small 1, Rob Jameson 2 Seismic Upgrade of the University Mound Reservoir North Basin included 542 micropiles with 1335 KN (300 kip) design capacity

More information

Structural design and construction of the Carouge-Bachet underground railway station in Switzerland

Structural design and construction of the Carouge-Bachet underground railway station in Switzerland Structural design and construction of the Carouge-Bachet underground railway station in Switzerland Franco ROJAS Civil Engineer BG Consulting Engineers Lausanne, CH franco.rojashorna@bg-21.com Franco Rojas

More information

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel.

Rock Tunnel Engineering INTRODUCTION. Tunnel a hole in the ground to provide for desired movement or as mobility channel. Rock Tunnel Engineering INTRODUCTION Tunnel a hole in the ground to provide for desired movement or as mobility channel. Serves as highway, railroad, pedestrian passageway, water conveyance, waste water

More information

Contract No. NE/2016/01 Site Formation and Infrastructure Works for Development of Anderson Road Quarry Site

Contract No. NE/2016/01 Site Formation and Infrastructure Works for Development of Anderson Road Quarry Site Contract No. NE/2016/01 Site Formation and Infrastructure Works for Development of Anderson Road Quarry Site Award submission for Temporary Works Excellence Award 2017 PROJECT BACKGROUND This Contract

More information

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA)

Advantages / Disadvantages of Piling Methods. Continuous Flight Auger (CFA) Advantages / Disadvantages of Piling Methods In this Piling Advice Note we will explore the advantages and disadvantages of differing types of piling methods. Continuous Flight Auger (CFA) The pile is

More information

The HKIE Structural Examination Written Examination 2017

The HKIE Structural Examination Written Examination 2017 The HKIE Structural Examination Written Examination 2017 Section 2: Design Questions (80% of the Written Examination) Date: 5 December 2017 (Tuesday) Time: 12:00 nn 06:00 pm (Duration: 6 hours) Question

More information

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk

The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in Gdańsk dr inż. Marcin Blockus INGEO Sp. z o.o. Mobile: +48 505 24 38 37 E-mail: blockus@ingeo.com.pl The use of micropiles as a form of underpinning of existing commercial buildings development of IKEA hall in

More information

Lee Tunnel Flow Transfer System twin 2.4m diameter elevated steel gravity pipelines to transfer stormwater across Beckton STW

Lee Tunnel Flow Transfer System twin 2.4m diameter elevated steel gravity pipelines to transfer stormwater across Beckton STW www.waterprojectsonline.com Lee Tunnel Flow Transfer System twin 2.4m diameter elevated steel gravity pipelines to transfer stormwater across Beckton STW by Paul Furse CEng MICE T hames Water s Lee Tunnel

More information

Requirements for Measuring and Pricing of Structural Concrete

Requirements for Measuring and Pricing of Structural Concrete Requirements for Measuring and Pricing of Structural Concrete October 2016 TRANSPORT INFRASTRUCTURE IRELAND (TII) PUBLICATIONS About TII Transport Infrastructure Ireland (TII) is responsible for managing

More information

Structurally controlled instability in tunnels

Structurally controlled instability in tunnels 5 Structurally controlled instability in tunnels 5.1 Introduction In tunnels excavated in jointed rock masses at relatively shallow depth, the most common types of failure are those involving wedges falling

More information

4.0 CONSTRUCTION METHODS AND ACTIVITIES

4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.0 CONSTRUCTION METHODS AND ACTIVITIES 4.1 Introduction This chapter describes the construction methods and activities that are expected to occur during construction of the Proposed Action. The potential

More information

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division

More information

GEOTECHNICAL DESIGN AND CONSTRUCTION METHODOLOGY OF A DEEP BASEMENT CUT NEXT TO SENSITIVE BUILDINGS

GEOTECHNICAL DESIGN AND CONSTRUCTION METHODOLOGY OF A DEEP BASEMENT CUT NEXT TO SENSITIVE BUILDINGS GEOTECHNICAL DESIGN AND CONSTRUCTION METHODOLOGY OF A DEEP BASEMENT CUT NEXT TO SENSITIVE BUILDINGS James Livingston 1 Ching Dai 2 1 Geotechnical engineer at Coffey Services (NZ) 2 Chartered Senior Principal

More information

SECTION XXXXX STONE COLUMNS PART 1 - GENERAL

SECTION XXXXX STONE COLUMNS PART 1 - GENERAL SECTION XXXXX STONE COLUMNS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 00 and Division 01

More information

(Old examination format for reference only)

(Old examination format for reference only) The Institution of Structural Engineers Associate-Membership Examination 11 APRIL 2003 INSTRUCTIONS TO CANDIDATE 1. The examination comprises two sessions separated by a lunch break of 1 2 hour, during

More information

Tunnel waterproofing seamless waterproofing to create watertight tunnels

Tunnel waterproofing seamless waterproofing to create watertight tunnels www.tunnelwaterproofing.com Tunnel waterproofing seamless waterproofing to create watertight tunnels Passion that has preserved for over 40 years For over a quarter of a century, the development of new

More information

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS

4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS 4.5 GEOTECHNICAL, SUBSURFACE, AND SEISMIC HAZARDS This section discusses the geology, soils, seismicity, hazardous materials, and subsurface obstructions along Flower Street, and evaluates their potential

More information

ICD Brookfield Place, Dubai. Risk Management for a Deep Basement Excavation. Andrew Smith. Coffey Geotechnics Ltd.

ICD Brookfield Place, Dubai. Risk Management for a Deep Basement Excavation. Andrew Smith. Coffey Geotechnics Ltd. ICD Brookfield Place, Dubai Risk Management for a Deep Basement Excavation Andrew Smith Coffey Geotechnics Ltd. CONTENTS 1. Project description and site history 2. Ground Conditions 3. Assessment of risks

More information

West Brompton Village

West Brompton Village West Brompton Village Detailed Planning Application Royal Borough of Kensington & Chelsea Basement Construction Methodology November 2013 Prepared for EC Properties Ltd by ARUP To EC Properties Ltd Date

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

From Colonia Jardín to Cuatro Vientos

From Colonia Jardín to Cuatro Vientos 60 METROSUR Line 10, Section 1A Contractor: From Colonia Jardín to Cuatro Vientos The extension of Line 10 is underway, with two sections currently being built. The first, which is discussed here, was

More information

Preventing Water Leakage through Construction Joints using SYNKOFLEX Preformed Compressible Waterstop

Preventing Water Leakage through Construction Joints using SYNKOFLEX Preformed Compressible Waterstop Preventing Water Leakage through Construction Joints using SYNKOFLEX Preformed Compressible Waterstop Introduction A typical problem in most Water Retaining Structures is the leakage of water through Construction

More information

CASE STUDY SERIES #24

CASE STUDY SERIES #24 THE PROJECT TRAVELODGE NEW BUILD APPLICATION GABION CLADDING TO STEEL SHEET PILES SUPPLY INSTALLATION LOCATION GRAVESEND, KENT, UK DATE NOVEMBER 2017 CONTRACTOR CLIENT ARCHITECT BARNES CONSTRUCTION TRAVELODGE

More information

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program

ENTRY FORM. DVASE 2014 Excellence in Structural Engineering Awards Program ENTRY FORM DVASE 2014 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M Other Structures Under $5M Buildings

More information

Assalamualaikum & Good Morning (May All Of You Gain A Better Understanding)

Assalamualaikum & Good Morning (May All Of You Gain A Better Understanding) Assalamualaikum & Good Morning (May All Of You Gain A Better Understanding) Always Try To Do The Best In Your Life TYPES OF FOUNDATION TYPES OF FOUNDATION a) Shallow Foundation System i) Spread Foundation

More information

Brochure E. The Soilcrete Jet Grouting Process

Brochure E. The Soilcrete Jet Grouting Process Brochure 67-03 E The Soilcrete Jet Grouting Process Contents History...3 Soilcrete Jet Grouting Process... 4 Process Variations... 6 Construction Forms... 7 Construction Sequences... 8 Stabilisation...

More information

Technical Data Sheet NEC/GRAN/95:01

Technical Data Sheet NEC/GRAN/95:01 Technical Data Sheet NEC/GRAN/95:01 Installation Guidance Notes Granular Surround Note : These guidance notes refer only to the installation of Granular surround underground tanks. These guidance notes

More information

The Construction of the Langham Place in Mong Kok An Introduction

The Construction of the Langham Place in Mong Kok An Introduction The Construction of the Langham Place in Mong Kok An Introduction Artist Impression of Langham Place r o j e c t c o m p r i s i n g a i l / h o t e l c o m p a n o f f i c e / r e t Fast Fact The site

More information

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN

BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN BASEMENT CONSTRUCTION PREPARED BY PN NOOR AISYAH ASYIKIN BASEMENT CONSTRUCTION 01 content 1.DEFINITION 2. CONSTRUCTION CONSIDERATION 3. DESIGN REQUIREMENT 4.METHOD OF CONSTRUCTION a. Open Cut Construction

More information

Construction Technology B (CON4313)

Construction Technology B (CON4313) 3 - Basement 1 Quick Revision 1.1 Problems arising from basement construction a. Excavation method. b. Surface and ground water control c. Lateral stability of basement excavation. d. Stability of adjoining

More information

Sydney Metro Underground Corridor Protection

Sydney Metro Underground Corridor Protection Transport for NSW Sydney Metro Technical Services 16 October 2017 Document No: NWRLSRT-PBA-SRT-TU-REP-000008 Revision No: 1 Document information Client: Transport for NSW Title: Sydney Metro - Technical

More information

ROTARY DRILLING TECHNIQUES LARGE DIAMETER

ROTARY DRILLING TECHNIQUES LARGE DIAMETER INTRODUCTION This paper presents details about large diameter rotary drilling techniques typically employed in the civil engineering industry. These techniques have also been applied to the resources /

More information

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013 WATSON ROAD FACILITY PAGE 1 OF 6 PART 1 GENERAL 1.1 Description The work covered by this Section includes all labour, materials, equipment, and supervision necessary to complete the site services as shown

More information

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL

LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL Submission for Hulme Prize 2017 LARGE DIAMETER PIPE ROOF BOX EXCAVATION FOR PASSENGER LINKWAY TUNNEL F. Saffiyah BADURDEEN 1, G. T. SENTHILNATH 2, 1 Ed. Zublin AG Singapore 2 Geoconsult Asia Singapore

More information

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 602 MARCH 1993 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER 602.01 SCOPE 602.02 REFERENCES 602.05 MATERIALS TABLE OF CONTENTS

More information

Company Profile. projects, with values in excess of 500K, and technically complex projects.

Company Profile. projects, with values in excess of 500K, and technically complex projects. Company Profile BAUER Technologies is the UK contracting arm of the BAUER Group. We perform deep foundation works on major projects in the UK. We specialise in the design and installation of large diameter

More information

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION INTRODUCTION By Dawn Tattle, P. Eng. Anchor Shoring & Caissons Ltd. TTC Yonge Station is the largest and most complicated of the

More information

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) SYSTEMS AND CAPABILITY TECHNICAL REQUIREMENT NO: MCE-SR-16 ISSUE: Initial DATE: 14-10-2009 PAGE: 1 of 19 REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES) ISSUE DATE DESCRIPTION /

More information

Chartered Membership Examination

Chartered Membership Examination CM Exam US 30/3/06 11:40 Page 1 The Institution of Structural Engineers Chartered Membership Examination Friday 21 APRIL 2006 Structural Engineering Design and Practice 9.30a.m. 1p.m. and 1.30 5p.m. (Discussion

More information

Jackson s Edge Service Reservoir - Compartment 1 innovative Design for Manufacture and Assembly (DfMA) approach to service reservoir construction

Jackson s Edge Service Reservoir - Compartment 1 innovative Design for Manufacture and Assembly (DfMA) approach to service reservoir construction www.waterprojectsonline.com Jackson s Edge Service Reservoir - Compartment 1 innovative Design for Manufacture and Assembly (DfMA) approach to service reservoir construction by Nathan Crabtree & Daniel

More information

Crossrail Environmental Statement Volume 1

Crossrail Environmental Statement Volume 1 Crossrail Environmental Statement Volume 1 Project description The environmental impact assessment process The need for Crossrail Planning policy context Route development and alternatives 1 If you would

More information

Surface Transport Master Plan Addendum 3 Transit Corridor Safeguarding Basis of Design. Revision A

Surface Transport Master Plan Addendum 3 Transit Corridor Safeguarding Basis of Design. Revision A Surface Transport Master Plan Addendum 3 Transit Corridor Safeguarding Basis of Design Revision A October 2008 Department of Transport PO Box 20 Abu Dhabi United Arab Emirates Surface Transport Master

More information

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10

EXECUTIVE SUMMARY. Figure 1 - Rail Deck Park Study Area. Executive Summary Rail Deck Park Engineering & Costing Study Report Page 1 of 10 EXECUTIVE SUMMARY Background The proposal for Rail Deck Park (RDP) comprises the construction of a decking structure over the rail corridor in downtown Toronto between Blue Jays Way and Bathurst Street

More information

BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know?

BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know? BRE Seminar Ground treatment - Getting the best from difficult sites A Reality Check What Does the Designer Need to Know? Chris Raison BEng MSc CEng MICE MASCE Raison Foster Associates Introduction A few

More information

concrete Precast car park The Avenue MSCP, Bracknell Sustainability by the sea Colwyn Bay seafront Clean water Treating hydro-demolition waste

concrete Precast car park The Avenue MSCP, Bracknell Sustainability by the sea Colwyn Bay seafront Clean water Treating hydro-demolition waste concrete THE MAGAZINE OF THE CONCRETE SOCIETY Volume 51 November 2017 Issue09 Visit: www.concrete.org.uk Precast car park The Avenue MSCP, Bracknell Clean water Treating hydro-demolition waste Sustainability

More information

SECTION 920 SANITARY AND STORM SEWER MANHOLES

SECTION 920 SANITARY AND STORM SEWER MANHOLES SECTION 920 SANITARY AND STORM SEWER MANHOLES 920.1 GENERAL This section contains items which are relative to the installation of sanitary and storm sewer manholes. 920.2 REFERENCES 920.2.1 ASTM C 43 C

More information

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe. MTS Jack and Bore Design Criteria Note: For the purposes of this Design Criteria and subsequent Construction Notes, the term Jack and Bore is used generically to refer to a number of trenchless construction

More information

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi STRUCTURAL NOTES MATERIAL STRENGTHS Structural Steel Reinforcing Steel Concrete Masonry Structural Lumber Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel

More information

VOTR Site Assessment Victoria on the River

VOTR Site Assessment Victoria on the River i Executive Summary A. Introduction AECOM New Zealand Limited (AECOM) was engaged by Hamilton City Council (HCC) to undertake a geotechnical assessment of the (VOTR) site in Hamilton s central business

More information

Preferred Elevated Tank Site

Preferred Elevated Tank Site Preferred Elevated Tank Site Preferred Site No. 3 is on private property owned by Hopewell Developments. Approximately 5 acres of land will be required, including lands required for a permanent access

More information

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES

CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 902 DECEMBER 1983 CONSTRUCTION SPECIFICATION FOR EXCAVATING AND BACKFILLING - STRUCTURES 902.01 SCOPE 902.02 REFERENCES 902.03 DEFINITIONS TABLE OF

More information

Compaction and Jet Grouting

Compaction and Jet Grouting Compaction and Jet Grouting Alan Ringen, PE Senior Vice President Breakthroughs in Tunneling Short Course August 16, 2017 Grouting Principles Geotechnical Grouting: The injection of pumpable fluid materials

More information

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil. H A Y W A R D B A K E R I N C. RIGID INCLUSIONS Rigid Inclusions offer an economical approach for building on sites underlain by soft soil. Above: HBI installed Rigid Inclusions on a congested downtown

More information

TRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT

TRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT P a g e 0 Prepared for: Trinity Development Group, Inc. TRUNK SEWER RELOCATIONS AT 900 ALBERT STREET SERVICING, CONSTRUCTABILITY AND MAINTENANCE REPORT OTTAWA, ON November 2016 P a g e 1 TABLE OF CONTENTS

More information

WARWICK TRIANGLE VIADUCT: OUTBOUND COMMENDATION Technical Excellence category Submitted by the SAICE Durban Branch

WARWICK TRIANGLE VIADUCT: OUTBOUND COMMENDATION Technical Excellence category Submitted by the SAICE Durban Branch Warwick Triangle Viaduct: Outbound INTRODUCTION The Warwick Triangle Precinct in Durban is one of the busiest trading and transport hubs in Africa. Major traffic conflict resulted from the movement of

More information

Monitoring of Sprayed Concrete Lined Tunnels Using Fibre Bragg Grating Sensors

Monitoring of Sprayed Concrete Lined Tunnels Using Fibre Bragg Grating Sensors Monitoring of Sprayed Concrete Lined Tunnels Using Fibre Bragg Grating Sensors M Brunton, J Preston, BE Whelan Monitor Optics Systems Pty. Ltd. ABSTRACT This paper outlines the use of Monitor Optics Systems

More information

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08 Table of Contents 1. Title 2. Designation 3. List of Figures 4. Scope 5. Referenced

More information

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc.

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. Roger Woodhead, PhD, P.Eng., SNC-Lavain Inc. Paper prepared for

More information

THOUGH STILL SUCCESSFUL, Keeping all of the stores open was critical during renovation and vertical expansion of the this 40-year-old mall

THOUGH STILL SUCCESSFUL, Keeping all of the stores open was critical during renovation and vertical expansion of the this 40-year-old mall Keeping all of the stores open was critical during renovation and vertical expansion of the this 40-year-old mall By Howell A. Gordy, R.A. THOUGH STILL SUCCESSFUL, THE 40-YEAR-OLD SOUTH SHORE PLAZA IN

More information