1 5 pages TUFF-TAC TM BRIDGE MEMBRANE INSTALLATION GUIDE The following will describe the proper procedure to use when installing Tuff-Tac TM bridge deck membrane. The guide will cover recommended tools to use, deck preparation before membrane installation, the membrane installation and the procedures to follow when placing the asphalt-wearing surface on the membrane. TOOLS RECOMMENDED 1. Application tools or equipment to apply the 9. Tape Measure Adhesive/Primer. (See adhesive application 10. Gloves (solvent resistant) Section) Material can be applied with brooms, 11. Screw Driver squeegee s and rollers, or spraying equipment 12. Caulking gun. 2. Utility Knife 13. Garbage bags 3. Chalk Line 14. Rags 4. 6-foot Broom Handle or equivalent 15. Citrus cleaner 5. 20lb propane bottle 16. Tiger Torch 6. Stirring Paddle, or Jiffy mixer blade with 7. Drill 8. Soft Push Broom and/or Asphalt hand roller The above may not be all the tools that an individual installer could use, but these tools are enough to perform a proper installation. MATERIALS NEEDED 1. Tuff-Tac Bridge Deck Membrane 2. InfraPrimer S 3. SBS Mastic Edge Sealer All the above materials can be ordered through your Canadian Construction Products Representative, a Canadian Construction Products Distributor, or by calling Canadian Construction Products direct at (604) PACKAGING AND STORAGE Tuff-Tac TM membrane is packaged in a reflective, high optical density wrapper material that provides protection from ultra-violet light during storage. However, it is recommended that the product be stored in a cool, dry place away from direct sunlight. Storing the membrane in the sun on a hot day may make the membrane very sticky and hard to work with. On cooler days one may want to keep the membrane in the sun prior to placement to enhance the tackiness. Infraprimer should be stored at room temperature in a dry place until used. SBS Mastic edge sealer should be stored in a covered location and at room temperature prior to placement. DECK PREPARATION Tuff-Tac TM membranes can be placed over all types of new or old deck surfaces. The decks can be concrete, asphalt, wood, or steel. 1
2 DECK TYPES 1. New concrete decks must be properly cured before membrane is applied. That curing time will be a minimum of 14 days or otherwise specified by the engineer. The surface texture must be smooth enough to avoid tenting of the membrane. Prior to placement of the membrane, the deck should be lightly sandblasted or hydroblasted and compressed air cleaned to remove loose surface material. A. Old concrete decks must be in good structural shape. Remove all sharp projections, repair all broken concrete, and fill cracks and holes over 4mm using Stop-A-Drop liquid membrane. Use proper patching methods and materials to accomplish a long-term successful waterproofing job. B. Old concrete decks with a membrane and asphalt overlay, will require that systems removal before the Tuff-Tac TM system is applied. All of the old membrane must be removed exposing the concrete deck. If milling is used to remove the old asphalt and membrane, a smooth surface with less than 5mm grooves needs to be left so the membrane does not tent over the deck surface. CCP recommends a profilemilling drum be used, that has a 5mm spacing between teeth. If the milled surface is not smooth enough, a thin scratch/leveling course of asphalt using a maximum aggregate size that is one half the thickness of the overlay lift to provide a surface that is acceptable for membrane placement. 2. Old Asphalt bridge decks are not common not recommended for membranes. Canadian Construction Products recommends the use of Stop-A-Drop liquid membranes. Please contact your Canadian Construction Products distributor for more information. 3. Wooden bridge decks do, on occasion, require membrane waterproofing. Whether new or old the deck planks must be secured in such away to not allow individual planks to walk, which will cause reflective cracking and membrane failure. When possible a scratch/leveling course of asphalt should be placed on the wood deck to provide a smooth surface to place the membrane on. If the membrane is placed directly on the wooden deck, nailing using roofing nails is required to prevent slippage between the membrane and the wood. Contact your Canadian Construction Products distributor for more information on nailing procedures. 4. Steel bridge decks on a new surface will require a scratch/leveling course of asphalt applied to it. If the deck has an existing waterproofing system already installed, some or all of the old system needs to be removed, and a scratch/leveling course must be placed. It is not recommended to mill the old material to the steel as the cutters will gouge the steel causing sharp protrusions that can puncture the membrane. The scratch/leveling course will cover any fasteners that hold the steel deck in place, and/or provide a good surface for the membrane to bond too. GENERAL DECK PREPARATION PROCEDURES Once the deck type has its primary preparation done, the primer must be applied. The deck must be clean, dry, and free of all loose debris. Start by thoroughly sweeping or compressed air cleaning the surface to remove latent material, stones, and debris that will effect adhesion or puncture the membrane. 1. Treat oil/grease contaminates with a suitable detergent or solvent to prevent interference with adhesion. Make sure these areas are dry before continuing. 2. Use dry compressed air to remove any loose dirt, grit, sand, stones, pebbles, etc left after sweeping. 3. Apply the adhesive primer to fully coat the surface without pooling. Do not let the sealer stand overnight uncovered to minimize dust collection on the deck which would adversely affect adhesion of the membrane. 2
3 DECK MOISTURE CONTENT Primarily on concrete decks that have received a high level of rain the moisture in the deck should be checked to help prevent membrane blistering. To see if the deck is dry enough for the membrane system application, use the plastic sheet method to determine moisture content. Place an 18-inch square piece of plastic or membrane on the deck. Put weight on the piece to hold it in place for one half-hour. Remove the plastic or membrane piece, turn it over to see if the surface that was against the deck is wet and look at the deck area for moisture. If either is moist or wet you cannot apply the membrane system. An artificial method, such as infrared heating can be used to accelerate the drying time. Once dry, the system installation can proceed. EDGE SEALER APPLICATION SBS Mastic should be applied as a generous continuous bead to all membrane system edges, cuts, and patchwork. Patches shall have a continuous bead of mastic on the cut out section, the patch is placed on top, and mastic is placed at the perimeter edge of the patch. As a preferred alternative, Stop-A-Drop rubberized liquid membrane can be substituted for the SBS Mastic. ADHESIVE/PRIMER INSTALLATION Canadian Construction Products Tuff-Tac TM is to be installed with Infratech Polymers Inc. Infraprimer TM S. Please read all data sheets pertaining to the Adhesive/ Primer being used. These products are solvent based and require the use of a respirator. 1. Open the container and thoroughly mix the Adhesive/Primer. The use of a jiffy mixer blade and drill is recommended for the 5- gallon containers. Always premix immediately prior to spray applications. 2. Application rate is 0.15 to 0.25 litres per sq.m. NOTE: AGAIN, THE DECK MUST BE CLEAN AND DRY BEFORE YOU APPLY 3. The primer after placing must dry to an almost tack free surface. This drying takes around 60 minutes on a 70 degree day. Moisture in the air and temperature will speed up or slow down the drying time. Do not apply membrane to Adhesive/Primer that is not dry. 4. Apply the Adhesive/Primer only to the deck area you intend to cover in a 24-hour period. Primed surface aged more than 24-hours or otherwise contaminated with dust or dirt should be re-primed with a very light coat of Adhesive/Primer. For enclosed areas or areas sensitive to solvents, Infraprimer TM E, a water carried primer is also available. 3
4 MEMBRANE APPLICATION 1. Application of the membrane can start once the Edge Sealer and Adhesive/Primer is in place and dry. On crowned deck surfaces place membrane sheets in a shingle fashion working from the curbside to the center crown. On flat deck surfaces start at one curb and proceed across to the other. Measure the width of the deck in at least three places and divide the widest number by 1.1m (the width of a roll minus the overlap) to get the number of sheets it will take to cover the deck width. You want to minimize the number of sheets, therefore having the fewest longitudinal seams. 2. Once you have decided the number of runs that it takes, put a chalk line 1.2m (48 inches) from the curb. You want the first sheet to be as straight as possible which allows the following rows to lay easily. Start the roll with the Zip Strip away from the curb, laying that edge on the chalk line. 3. The manual placement of the membrane requires 4 people. One person holds the beginning of the roll in place, at the beginning of the deck. Two men roll out the membrane using a broom handle or similar device guiding the edge so it follows the chalk line. The fourth person will remove the release film from the bottom. That person pulls the film off at a 45 degree angle, to the placing direction. This helps keep tension on the membrane as it lays down minimizing the wrinkles. Once the roll is down the first person needs to push the membrane into good contact with the deck using a push broom or a hand roller. 4. A second method can be used on a cooler day, when the Adhesive/Primer is not as tacky. Roll the membrane out on the deck, lining it with the chalk line. The first person holds the beginning of the in place. The second person holds the end the roll in place. The third person pulls the release film off in the same way as the first method except the membrane is on the deck. This method also minimizes wrinkles. It is important to not trap air under the membrane, and to work out all air that may be trapped. 5. If more than one roll is needed to cross the deck, start the second roll overlapping the first roll by 150mm (6 inches). This transverse joint will need to be heat sealed. We recommend heat sealing to be completed at the end of the working day. If you have an extra person, they can heat seal as the job progresses. Heat Sealing is the process of using a propane torch and heating the membrane area you want to seal. Look for the point when the top of the membrane shows signs of melting and apply even pressure along the seam. The technique should not take a long time to learn, but make sure you do not apply too much heat and melt through the membrane. Use a tiger torch or roofers torch to completed heat sealing. A unit that uses a 20 lb. propane bottle is sufficient. 6. Once the first row of membrane is completed, start the second, overlapping the leading edge of the first row, the width of the Zip Strip which is approximately 4 inches wide. Use the edge of the Zip Strip release film as your guide. Do not remove the Zip Strip release film until the complete roll is in place on the deck. Start at one end of the roll and pull the Zip Strip release film from between the overlapped rolls. 7. The transverse joints must be staggered. This can easily be done by using the piece of roll that was cut of on the first row to start the second. It is very rare to get a bridge that has equal length to the rolls. 8. Continue to place rows until the center of the bridge is reached. If the bridge is closed completely then start laying membrane from the opposite curb to the middle. Overlay the two sides with a center stripe as roof is overlapped at it peak. If the bridge must be opened to traffic on one side before the other side can be waterproofed, then leave a minimum of 8 inches of membrane exposed from the asphalt end on the first side. 4
5 When overlapping longitudinal seams that do not have a Zip Striped edge, you need to allow 6 inches of over lap to insure a good seal. All edges that are overlapped without a Zip Strip between the overlap, must be heat sealed. 9. At the end of each work day it is recommended that all transverse and longitudinal joints are heat sealed as stated in the previous item. Do not leave a partially complete job overnight without heat sealing. Exposed edges improperly set can allow unexpected rainfall to penetrate under the membrane system. Canadian Construction Products recommends the use of a Stop-A-Drop 100mm wide edge band on all daily edge terminations on incomplete membrane systems. 10. Patches: There is always a chance to trap a small stone under the membrane when placing it. The stones must be removed so they do not puncture through when the asphalt is placed. To remove the stone make a C shaped cut around the stone. Peel back the membrane, remove the stone then push the membrane back into place. Cut a 6 inch by 6 inch patch from a piece of membrane to cover the cut. Place it over the cut and then heat seal the patch. Similarly, cots, nicks, gouges, rips, tears, etc. are repaired using the same procedure. Refer to edge sealer procedure for mastic work. 11. Curb Strips: If required by specification, this detail strip is positioned so the curb strip edge is 12mm below the top of the proposed wearing surface. Adhesive primer needs to be applied on the vertical curb surface, to the height of the finished surface. Establish a reference by striking a chalk line. Curb Strips are installed before the deck membrane is installed, but it does not change the curb detail involving the SBS Mastic. Heat sealing the curb strip to the deck membrane and to the curb is required. Use a small trowel to press the vertical edge against the curb as you are heating it. Again make sure you are not over heating the membrane. 12. The Asphalt Overlay needs to be applied as soon as possible after the membrane installation to avoid damage to the membrane. The asphalt temperature needs to above 290 degrees F and all areas are compacted to specification to insure good bonding. Minimize equipment turning on the membrane, causing damage. This covers the entire general requirements for Tuff-Tac TM membrane installation, if you have any questions on this Guideline or on an issue not covered, please contact Canadian Construction Products technical department, or contact your local Canadian Construction Products Representative. Revised: 05/08/06 5
ITEM 458 WATERPROOFING FOR STRUCTURES
ITEM 458 WATERPROOFING FOR STRUCTURES 458.1. Description. This Item shall govern for the furnishing and placing of waterproofing on concrete and steel bridge decks of railroad structures and on other structures
More informationPROTECTING AMERICA S BRIDGES M-400, M-400A(R) AND M-400A(R) HD. Cold Applied Bridge Deck Waterproofing Membranes
PROTECTING AMERICA S BRIDGES M-400, M-400A(R) AND M-400A(R) HD Cold Applied Bridge Deck Waterproofing Membranes PROTECTO WRAP BRIDGE DECK WATERPROOFING SYSTEMS Since 1952, Protecto Wrap Company has been
More informationSection 710. WATERPROOFING AND PROTECTIVE COVERS Description. Furnish and place membrane waterproofing and protective covers.
Section 710. WATERPROOFING AND PROTECTIVE COVERS 710.01 710.01 Description. Furnish and place membrane waterproofing and protective covers. 710.02 Materials. Use materials meeting the following. Waterproofing
More informationApplication Guide GARAGE & COMMERCIAL FLOORS
Application Guide GARAGE & COMMERCIAL FLOORS REQUIRED TOOLS & MATERIALS - CHECKLIST Flexstone Coatings products (ensure you have enough) Flat Squeegee and Pole (Optional) Disposable brushes (3-4 ) Roller
More informationSection 710. WATERPROOFING AND PROTECTIVE COVERS
710.01 Section 710. WATERPROOFING AND PROTECTIVE COVERS 710.01. Description. This work consists of providing and placing membrane waterproofing and protective covers. 710.02. Materials. Provide materials
More informationColphene BSW Training and Application Guide. Colphene BSW Waterproofing Membrane. 1. Prepare substrate
Colphene BSW Training and Application Guide Colphene BSW Waterproofing Membrane. 1. Prepare substrate Substrate must be structurally sound. Surface must be free of voids, spalled areas, loose aggregate,
More informationARDEX GUIDE SPECIFICATION ARDEX CD Concrete Dressing and ARDEX CD FINE Concrete Dressing Polymer-Modified, Portland Cement-Based, Resurfacing Compound
ARDEX GUIDE SPECIFICATION ARDEX CD Concrete Dressing and ARDEX CD FINE Concrete Dressing Polymer-Modified, Portland Cement-Based, Resurfacing Compound SECTION 03 01 30 MAINTENANCE OF CAST-IN-PLACE CONCRETE
More informationGeneral Applications Before applying, mix the pre-measured catalyst* into Liquid Roof by following label directions.
General Applications Before applying, mix the pre-measured catalyst* into Liquid Roof by following label directions. Surface Preparation: Surface to be coated should be clean, dry and structurally sound.
More informationInstruction Guide APPLICATION OF CIM TO ASPHALT
23 Elm St., Peterborough, NH 03458 Tel: (800) 543-3458 (603) 924-9481 Fax: (603) 924-9482 Web site: Instruction Guide APPLICATION OF CIM TO ASPHALT 1.0 DESCRIPTION This guide covers the installation of
More informationJiffy Seal 140/60 Waterproofing System
TECHNICAL DATA SHEET Jiffy Seal 140/60 Waterproofing System TECHNICAL DATA Properties Test Method Test Results Color Black Thickness 60 mil Tensile Strength ASTM D412 1300 psi (reinforcement sheet) Tensile
More informationSECTION MODIFIED BITUMINOUS MEMBRANE ROOFING Peel & Seal
SECTION 07550 MODIFIED BITUMINOUS MEMBRANE ROOFING Peel & Seal This section is based on the products of MFM Building Products Corp., which is located at: 525 Orange St. P. O. Box 340 Coshocton, OH 43812
More informationAsphalt Maintenance PRODUCTS INFORMATION AND INSTALLATION GUIDE
Asphalt Maintenance PRODUCTS INFORMATION AND INSTALLATION GUIDE TABLE OF CONTENT About RESISTO 2 Asphalt Cleaner and Degreaser 3 Oil Spot Primer 3 Liquid Crack Filler 4 Rubberized Crack Filler 4 Levelling
More informationFully Adhered EPDM. Installation Instructions. Single-Ply Simplified
Fully Adhered EPDM Installation Instructions Single-Ply Simplified P.O. Box 251 Plainfield, PA 17081 866.471.5125 FAX: 717.960.4034 www.weatherbondroofing.com 2018 WeatherBond. 03.26.18 REPRINT REQUEST
More informationBRANZ Appraisal Certificate # 461 (2010) Internal wet areas.
SPECIFICATION FOR PROTECTO WRAP AFM-WM FOR INTERNAL WET AREAS BRANZ Appraisal Certificate # 461 (2010) Internal wet areas AFM/WM INTERNAL 0104 Page 1 AFM-WM INTERNAL SPECIFICATION PRODUCT DESCRIPTION Anti
More informationSECTION SELF-ADHERING SHEET WATERPROOFING CCW-711
MANUFACTURER S GUIDE SPECIFICATIONS SECTION 071326 SELF-ADHERING SHEET WATERPROOFING CCW-711 900 Hensley Lane Wylie TX 75098 800-527-7092 www.carlisleccw.com 605401 05.21.13 Carlisle, MiraDRAIN, MiraDRI
More informationThe following Supplemental Specification supersedes, in its entirety, the version contained in the Specifications for Bridge Construction
a. SUPPLEMENTAL SPECIFICATION SECTION 16, BRIDGE DECK WATERPROOFING The following Supplemental Specification supersedes, in its entirety, the version contained in the Specifications for Bridge Construction
More informationInstallation Instructions
Installation Instructions I. GENERAL INFORMATION KEY CHIP-100 FLOORING is a decorative resin flooring system consisting of clear, 100% solids epoxy resin and colored vinyl chips. KEY CHIP-100 FLOORING
More informationBITUTHENE Deck System
BITUTHENE Deck System Cold-applied, waterproofing system for inverted roofs, green roofs and elevated decks Product Description BITUTHENE Deck System combines BITUTHENE 4000 sheet membranes with BITUTHENE
More informationTHE BRITE THING TO DO
REDUCING ENERGY CONSUMPTION IMPROVING AIR QUALITY THE BRITE THING TO DO BRITE-n-EZ Enhanced Coating Application Process on Black EPDM Roof Membrane BRITE-n-EZ EPDM Application Instructions CLEANING Remove
More informationGUARANTEED ASPHALT LIMITED
GUARANTEED ASPHALT LIMITED GuaraTEC Installation Guide Installing our fully bonded hot melt system. 2016 Barratt Homes, Osiers Road Guaranteed Asphalt Limited 2 Mercury Way, London, SE14 5RR, 020 7277
More informationStudent Services & Classroom Addition
SECTION 071326 - SELF-ADHERING SHEET WATERPROOFING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division
More informationPacific Polymers Elasto-Deck 5000MR Guide Specification
1 071813-1 July 2018 Pacific Polymers Elasto-Deck 5000MR Guide Specification SECTION 071813 TRAFFIC COATINGS ELASTO-DECK 5000MR OVER CONCRETE 2 071813-2 July 2018 Pacific Polymers Elasto-Deck 5000MR Guide
More informationInstruction Guide APPLICATION OF CIM TO CONCRETE
23 Elm St., Peterborough, NH 03458 Tel: (800) 543-3458 (603) 924-9481 Fax: (603) 924-9482 Web site: Instruction Guide APPLICATION OF CIM TO CONCRETE 1.0 DESCRIPTION This guide covers the installation of
More informationPacific Polymers Elasto-Deck 5000X2 Guide Specification
1 071813-1 July 2018 Pacific Polymers Elasto-Deck 5000X2 Guide Specification SECTION 071813 TRAFFIC COATINGS ELASTO-DECK 5000X2 OVER CONCRETE 2 071813-2 July 2018 Pacific Polymers Elasto-Deck 5000X2 Guide
More informationDURA 500 THERMOPLASTIC FLAT ROOF COATING SYSTEM BY SUPERIOR POLYMERS INC.
SPECIFICATION GUIDELINE FOR SMOOTH ROOF SUBSTRATES INCLUDING MODIFIED BITUMEN, SMOOTH ASPHALT, EPDM, TPO, AND PLYWOOD. Part 1 General Information For the purpose of clarification in this document, the
More information.2 Flashings at grade to extents shown on the Drawings. .3 Membrane and polyethylene slip sheets at perimeter of walls.
RWPS Foundations and Concrete Structures Page 1 of 8 1. GENERAL 1.1 Work Included.1 Supply and installation of ethylene propylene diene monomer (EPDM) membrane and insulation to extents shown on the Drawings
More informationCIM IG 13 11/06. Instruction Guide
23 Elm St., Peterborough, NH 03458 Tel: (800) 543-3458 (603) 924-9481 Fax: (603) 924-9482 Web site: Instruction Guide APPLICATION OF CIM 2000 TO CONCRETE 1.0 DESCRIPTION This guide covers the installation
More informationCARLISLE DECK COATING INSTALLATION OVER EXISTING POLYURETHANE COATINGS
CARLISLE DECK COATING INSTALLATION OVER EXISTING POLYURETHANE COATINGS 1. GENERAL A. When coating over existing coatings, Carlisle can not assume responsibility for the adhesion of the existing coating,
More information729 - MULTI-LAYER POLYMER CONCRETE OVERLAY SECTION 729 MULTI-LAYER POLYMER CONCRETE OVERLAY
SECTION 729 MULTI-LAYER POLYMER CONCRETE OVERLAY 729.1 DESCRIPTION Prepare the surface of the reinforced concrete bridge deck and construct a multi-layer polymer concrete overlay (overlay) as shown on
More informationSOLAR COATING SYSTEMS SYSTEM EMULSION /ACRYLIC. Specification for Built-Up Roofing MULSION/A 1.01 SUMMARY
SOLAR COATING SYSTEMS 2-PLY EMULSION MULSION/A /ACRYLIC SYSTEM Specification for Built-Up Roofing 07590 PART 1. GENERAL 1.01 SUMMARY Name Address City, State, zip A. Furnish and install a seamless, reinforced
More informationKU Medical Center 2018 PAVEMENT RESTORATION PROJECT Project No May 4, 2018
SECTION 321216 - ASPHALT PAVING PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and General Requirements of the Contract apply to this Section. 1.2 SUMMARY A. Section Includes: 1. Cold milling of existing
More informationERSYSTEM ONESTEP PLUS
1 DG0047-A 05/2017 AGED (EPDM, TPO, CSPE-HYPALON, PIB) SINGLE-PLY (THERMOSET) MEMBRANE RESTORATION SYSTEM APPLICATION SAMPLE DESIGN GUIDELINE ERSYSTEM ONESTEP PLUS ITW POLYMERS SEALANTS NORTH AMERICA,
More informationRubber Roofing Pocket Application Guide
Rubber Roofing Pocket Application Guide Table of Contents Page 2.......................... General Information Page 2........................ Cautions and Warnings Page 3.......................... Recommended
More informationBridge Preservation Product Advantages:
Specializing in the rail and highway markets, Bridge Preservation manufactures high performance membrane systems designed to permanently protect rail and highway structures. These rapid setting high build
More informationSECTION TW-60 Self-Adhering Sheet Waterproofing Membrane
This three-part specification is for design professionals for use as a guide and must be edited to delete information and instructions not required on a particular project. Delete the specifier notes in
More informationoptimum glue Preparation INSTALLATION INFORMATION We recommend to order all panels for the same commercial flooring project at the same time.
Preparation We recommend to order all panels for the same commercial flooring project at the same time. Always store and transport your vinyl floor carefully to prevent distortions. Store and transport
More information2007 FLORIDA BUILDING CODE TEST PROTOCOLS HVHZ (RAS)
ROOFING APPLICATION STANDARD (RAS) No. 117 STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES 1.. 3. Scope
More informationPLATON FOUNDATION WRAP
DRAINAGE SOLUTIONS SINCE 1908 PLATON FOUNDATION WRAP RUGGED, DIMPLED HIGH-DENSITY POLYETHYLENE (HDPE) MEMBRANE THAT KEEPS FOUNDATIONS DRY ADVANCED TECHNOLOGY EASY INSTALLATION PROVEN PERFORMANCE ARMTEC.COM
More informationAFM Anti-Fracture Membrane & AFM-WM Anti-Fracture Waterproofing Membrane Three-Part Specifications
AFM Anti-Fracture Membrane & AFM-WM Anti-Fracture Waterproofing Membrane Three-Part Specifications Protecto Wrap AFM Anti-Fracture Membrane and AFM - WM Anti-Fracture Waterproofing Membrane is a 40 mil
More informationInstallation Manual. Foundations. Version 4.3ᵠ
Installation Manual Foundations Version 4.3ᵠ (*) - Denotes Current Revisions throughout this Installation Manual Version 4 (ᵠ) - Denotes Current Revisions for Version 4.3 of this Manual Manual updated
More informationInstallation Instructions - Dry Method
Page 1 of 6 Installation Instructions - Dry Method There are two installation methods for GraniteCrete: Dry and Wet. The dry method is for installations up to 10,000 square feet (most home applications).
More informationE. Section Polymer Modified Cement Waterproofing. K. Section Sub drainage: Foundation perimeter drainage.
DELTA -MS CLEAR Section 07 10 00 Dampproofing and Waterproofing PART 1 GENERAL 1.1 SECTION INCLUDES A. Below grade waterproofing and dampproofing. 1.2 RELATED SECTIONS A. Section 07 11 13 - Bituminous
More informationInstallation Guide Wall Panels
Installation Guide Wall Panels Jointless or Dry-Stacked Installation (Read Prior to installation) The MStone system is a jointless / dry-stacked installation where panels and corners fit tightly together
More informationREBOUND ACE AIR CUSHION
This procedure is applicable to Rebound Ace Air Cushion using Rebound Air Cushion Mat NG- 7mm. PREPARATION Thoroughly clean or vacuum court surface before application, remove any dirt, stones, dust. Surface
More informationDO-IT-YOURSELF SELF ADHESIVE PLANK INSTALLATION
Woodland Creek Series Self-Adhesive Residential Vinyl Plank Pattern Numbers: Sku 725-6664 PLK1102 Sable Sku 725-6666 PLK1106 Gray Wolf DO-IT-YOURSELF SELF ADHESIVE PLANK INSTALLATION MATERIALS YOU MAY
More informationSLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu
INSTALLATION INSTRUCTIONS Note: The following installation instructions are based off of ASTM E 1643 (Standard Practice for Installation of Water Vapor Retarders Used in Contact with Earth or Granular
More informationA. The work of this section includes, but is not limited to, the following:
SECTION 07 14 00 FLUID APPLIED WATERPROOFING SYSTEM PART 1: GENERAL 1.1 RELATED DOCUMENTS A. All of the Contract Documents, including General and Supplementary Conditions and Division 01 General Requirements,
More informationUltraseal 3750 MTO Waterproofing Membrane Installation Instructions - Single Layer Application
Ultraseal 3750 MTO Waterproofing Membrane Installation Instructions - Single Layer Application MATERIALS Ultraseal 3750 MTO Waterproofing Membrane (Part No. 89020) Ultraseal 3750 MTO Waterproofing Membrane
More informationSelf Adhesive EPDM TRAINING MANUAL
Self Adhesive EPDM TRAINING MANUAL Rubber4Roofs Ltd, Unit 4 Kingswood Close Page 1 of 7 Copyright Rubber4Roofs Ltd GeneralHealth&Safety Extreme care must be exercised when working on ladders, roofs, below
More informationInstallation Instructions
Warning: Do not remove outer shrink wrapping from the Fire Rated Foam stick until you have read and understand the FULL instructions for proper installation. Failure to follow these directions may degrade
More informationPERM-FLEX ASSEMBLY DIRECT APPLICATION TO CEMENTITIOUS SUBSTRATES MANUFACTURERS SPECIFICATION / SECTION 09960
STUC-O-FLEX PERM-FLEX ASSEMBLY DIRECT APPLICATION TO CEMENTITIOUS SUBSTRATES MANUFACTURERS SPECIFICATION / SECTION 09960 PART 1 - GENERAL 1.01 DESCRIPTION Provide all labor, materials and equipment necessary
More informationINSTALLATION PROCEDURES FOR RUBBER FLOORING
! INSTALLATION PROCEDURES FOR RUBBER FLOORING Installation of rubber flooring will only mirror the characteristics of the existing substrate. Proper subfloor preparation is paramount to a successful installation.
More informationInstallation Instructions Tuscan Field Applied Limestone Finish
Installation Instructions Tuscan Field Applied Limestone Finish TS-107 Recommended Tools for Installation of Tuscan StoneWorx Finishes Variable Speed Drill capable of producing 1000 RPM s MX1 Mixing Paddle
More informationbe installed while the adhesive is wet for better pattern matching capabilities. Concrete floors must be sealed if dusting or powdering exists. The fo
Installation of Commercial Broadloom Products lbs. per 1000 sq. ft. per 24 hours. Do not begin the installation if a higher moisture transmission rate is detected. Do not use other methods of moisture
More informationTufted and Woven Goods Direct Glue-Down
Tufted and Woven Goods Direct Glue-Down Installation Instructions Duraloc AIR Duraloc AIR Performance Unibond Flex Unibond Flex Bloc Unibond Laminate Unibond Plus Unibond Plus Bloc Weldlok Weldlok Bloc
More informationVulkem OC 810. One-Coat, Low-Odor, Low-VOC Deck Coating for Light Pedestrian Applications APPLICATION INSTRUCTIONS
One-Coat, Low-Odor, Low-VOC Deck Coating for Light Pedestrian Applications APPLICATION INSTRUCTIONS 1. Purpose 1.1 The purpose of this document is to establish uniform procedures for applying the Vulkem
More informationPol-E-Base Modified Bitumen Roof System
Pol-E-Base Modified Bitumen Roof System Specification Chemicals, Inc. produces the Pol-E-Base Built-up Roofing System as the ultimate in field applied reflective insulation roofing. It has the advantages
More informationPacific Polymers Elasto-Mat D&G Guide Specification
1 07141-1 August 2016 Pacific Polymers Elasto-Mat D&G Guide Specification SECTION 07141 FLUID APPLIED WATERPROOFING 2 07141-2 August 2016 Pacific Polymers Elasto-Mat D&G Guide Specification SECTION 07141
More informationApplication Specification:
Application Specification: MR-30-GF20 March 2014 Supersedes 10/11 PART 1 - GENERAL 1.1 SUMMARY DIVISION 07 01 50.61: GACO WESTERN GACOFLEX S-20 ELASTOMERIC SILICONE COATING FOR REHABILITATION OF AGED METAL
More informationA. Submit product data sheets and literature verifying fire ratings and physical properties of materials.
I. GENERAL ACRYSHIELD ROOF MANAGEMENT SYSTEM Installation Guide Specification For Preserving BUR & Mod Bit Roofs 07560 Saving Money, Safeguarding the Environment One Roof at a Time. 1.01 SUMMARY A. Provide
More informationPROTECTO DECK INSTALLATION INSTRUCTIONS
PROTECTO DECK INSTALLATION INSTRUCTIONS THE FOLLOWING MATERIALS ARE NEEDED TO COMPLETE THE PROTECTO DECK SYSTEM. Protecto Deck Protecto Deck is a cold applied, nominal 70 mil, self-adhering primary waterproofing
More informationSIDER-DECK / SIDER-SEALER Product Data
153 Regur Road Hawkinsville, GA 31036 USA 1.478.892.9800 888-743-3750 www.sider-crete.com SIDER-DECK / SIDER-SEALER Product Data Features and uses: Decorative textured concrete deck system. For interior
More informationApplication Specification:
Application Specification: MR-38-GF20 May 2014 Supersedes 10/11 PART 1 - GENERAL 1.1 SUMMARY DIVISION 07 01 50.61: GACO WESTERN GACOFLEX S-20 ELASTOMERIC SILICONE COATING FOR REHABILITATION OF AGED METAL
More informationSPECIAL SPECIFICATION 4429 Multiple-Layer Polymer Concrete Overlay
2004 Specifications SPECIAL SPECIFICATION 4429 Multiple-Layer Polymer Concrete Overlay 1. Description. Furnish and place a multi-layer polymer overlay consisting of a crack seal, polymer resin and aggregates.
More informationTechnical Service. INSTALLATION INSTRUCTIONS FOR TARAFLEX SPORT PRODUCTS over Gypsum base Products. This document refers to the following products:
INSTALLATION INSTRUCTIONS FOR TARAFLEX SPORT PRODUCTS over Gypsum base Products This document refers to the following products: Product Width Width Ft. Installation direction Seams treatment Taraflex Surface
More informationInstruction Guide APPLICATION OF CIM TO EARTHEN PONDS AND RESERVOIRS (USING CIM SCRIM)
23 Elm St., Peterborough, NH 03458 Tel: (800) 543-3458 (603) 924-9481 Fax: (603) 924-9482 Web site: Instruction Guide APPLICATION OF CIM TO EARTHEN PONDS AND RESERVOIRS (USING CIM SCRIM) 1.0 DESCRIPTION
More informationACRYLIC Elastek #127 Solar One Plus
1 EL0017-L 01/2018 AGED (EPDM, TPO, CSPE-HYPALON, PIB) SINGLE-PLY (THERMOSET) MEMBRANE RESTORATION SYSTEM APPLICATION SAMPLE DESIGN GUIDELINE ACRYLIC Elastek #127 Solar One Plus ITW POLYMERS SEALANTS NORTH
More informationSECTION 20 INDEX PAVING FABRIC 1. SCOPE OF WORK MATERIAL REQUIREMENTS CONSTRUCTION AND INSTALLATION REQUIREMENTS...
SECTION 20 INDEX PAVING FABRIC 1. SCOPE OF WORK... 20-2 2. MATERIAL REQUIREMENTS... 20-2 3. CONSTRUCTION AND INSTALLATION REQUIREMENTS... 20-2 4. METHOD OF MEASUREMENT... 20-5 20-1 SECTION 20 PAVING FABRIC
More informationApplication Instructions for Keystone Kool Deck on Existing Concrete
Application Instructions for Keystone Kool Deck on Existing Concrete REQUIRED MATERIALS Keystone Kool Deck PTA Bonding Agent Water 20 Mesh Marble Sand White Portland Cement OPTIONAL TOOLS Mortex Pattern
More information1 PVC or ABS drain with strainer
Patents Pending ProBase II Single-Slope Shower Base and Kit CONTENTS 1. General Information...1 2. Materials...1 3. Planning...2 4. Preparation...3 5. Layout...3 6. Install Base and Shims...4 7. Install
More informationReflectiClean Acrylic/Urethane
1 DG0009-J 08/2015 Metal Roof Restoration Sample Design Guidelines ReflectiClean Acrylic/Urethane ITW POLYMERS SEALANTS NORTH AMERICA, INC. 111 S. Nursery Road. Irving, TX 75060 Tel: 972-438-9111 Fax:
More informationSECTION TEMPORARY ROOFING MEMBRANE INSTALLATION. A. Areas of the roof deck for asbestos abatement.
PART 1 GENERAL 1.01 APPLICATIONS SECTION 07500 TEMPORARY ROOFING MEMBRANE INSTALLATION A. Areas of the roof deck for asbestos abatement. B. Areas of the roof deck exposed to the structural roof deck substrate.
More informationSECTION CONCRETE PAVING
SECTION 32 13 13 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for providing portland cement concrete work and all other incidental concrete improvements for the project
More informationPERM-A-BARRIER NPS Detail Membrane
PERM-A-BARRIER NPS Detail Membrane Primerless self-adhered detail membrane for air and vapor barrier applications Product Description GCP Applied Technologies ( GCP ) PERM-A-BARRIER NPS Detail Membrane
More informationBid Opportunity Wilkes Reservoir North Cell Rehabilitation
Water and Waste MONOMER (EPDM) ROOFING Page 1 of 11 Part 1 General 1.1 REFERENCES.1 ASTM International Inc..1 ASTM D4637-14E1, Standard Specification for EPDM Sheet Used In Single-Ply Roof Membrane..2
More informationINSTALLATION INSTRUCTIONS
REPAIR SPALLING INSTALLATION INSTRUCTIONS A CSW Industrials Company BCSW Wall Compression Seals IMPORTANT The following instructions are very important. Read them carefully, and be sure you understand
More informationPERM-A-BARRIER VPS. Product Description. Product Data Sheets. Self-adhering vapor permeable air and water barrier membrane
PERM-A-BARRIER VPS Self-adhering vapor permeable air and water barrier membrane Product Description GCP Applied Technologies ( GCP ) PERM-A-BARRIER VPS (Vapor Permeable Sheet) membrane is a vapor permeable
More informationASPHALTIC CONCRETE PAVING SECTION
SECTION 31 50 00 PART 1: GENERAL 1-01 SECTION INCLUDES: A. Asphaltic concrete paving. B. Seal Coat. 1-02 RELATED SECTIONS: A. Division 31 Earthwork B. Section 31 60 00 Aggregate Base Course. C. Section
More informationAcrylic/Urethane. Metal Roof Restoration Sample Design Guideline
1 DG0009-I 04/2017 Metal Roof Restoration Sample Design Guideline Acrylic/Urethane ITW POLYMERS SEALANTS NORTH AMERICA, INC. 111 S. Nursery Road. Irving, TX 75060 Tel: 972-438-9111 Fax: 972-554-3939 www.itwsealants.com
More informationPacific Polymers Elasto-Deck BT Guide Specification
1 07141-1 August 2016 Pacific Polymers Elasto-Deck BT Guide Specification SECTION 07141 FLUID APPLIED WATERPROOFING 2 07141-2 August 2016 Pacific Polymers Elasto-Deck BT Guide Specification SECTION 07141
More informationFlex Shield EM ELASTOMERIC ROOF PRODUCTS & SYSTEMS.... for roofs with exceptional stress requirements
Flex Shield EM ELASTOMERIC ROOF PRODUCTS & SYSTEMS... for roofs with exceptional stress requirements Flex Shield EM Products & Systems When a roof structure has excessive movement due to unusual expansion
More informationINSTALLATION GUIDELINES - ECOWORX PERFORMANCE BROADLOOM
INSTALLATION GUIDELINES - ECOWORX PERFORMANCE BROADLOOM Shaw is not responsible for any moisture related installation failures if these guidelines are not strictly followed. Notice Failure to follow these
More informationWabo FireShield Model: FSH
Wabo FireShield Model: FSH Horizontal Expansion Control Fire Barrier System The following installation procedure is very important and must be fully understood prior to beginning any work. To ensure proper
More informationADFORS PAVEMENT REINFORCEMENT SYSTEM GlasGrid GG
ADFORS PAVEMENT REINFORCEMENT SYSTEM GlasGrid GG Self-adhesive Crack mitigation Tensile strength Unique protective coating Installation Procedures Your Partner for Innovative Textiles The installation
More informationSECTION MODIFIED BITUMINOUS MEMBRANE ROOFING Peel & Roof
SECTION 07550 MODIFIED BITUMINOUS MEMBRANE ROOFING Peel & Roof This section is based on the products of MFM Building Products Corp., which is located at: 525 Orange St. P. O. Box 340 Coshocton, OH 43812
More informationARDEX GUIDE SPECIFICATION ARDEX FEATHER FINISH Self-Drying, Cement-Based Finish Underlayment
ARDEX GUIDE SPECIFICATION ARDEX FEATHER FINISH Self-Drying, Cement-Based Finish Underlayment SECTION 03 01 30 Maintenance of Cast-In-Place Concrete PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings, general
More informationInstallation Manual. Foundations. Version 2
Installation Manual Foundations Version 2 Contents Overview...1 Planning the Job... 2 Introducing DMX FlexSheet...2 Supplies Required...3 Tools Required...4 Preparing the Site...4 Where to Start?...5 Installing
More informationWATERPROOFING. MiraPLY Installation Instructions SCIENCE. SERVICE. SOLUTIONS. Introduction. Description. Substrate Preparation. Features and Benefits
Introduction Carlisle Coatings & Waterproofi ng Incorporated (CCW) has prepared this installation guide to assist applicators in the use of MiraPLY and accessories. Every project is different, and this
More information1.1 This procedure governs the installation of PENNTROWEL UT500 Polyurethane Mortar Flooring Systems CE-286, CE-287 and CE-288.
AN ERGONARMOR COMPANY TECHNICAL INFORMATION 05/10 Supersedes 12/09 SPECIFICATION FOR INSTALLATION PENNTROWEL UT500 SURFACER SYSTEMS 1. SCOPE 1.1 This procedure governs the installation of PENNTROWEL UT500
More informationEpoxy & Pebblestone Fax: We ship all over the USA U.V.
Epoxy & Pebblestone www.epoxyandpebblestone.com 623-688-6077 Fax: 623.594.7177 dave@epoxyandpebblestone.com We ship all over the USA U.V. EPOXY PHYSICAL PROPERTIES: Composition: Solids Content: Mix Ratio:
More informationApplication Specification:
Application Specification: MR-22-GF20 March 2014 Supersedes 10/11 PART 1 - GENERAL 1.1 SUMMARY DIVISION 07 01 50.61: GACO WESTERN GACOFLEX S-20 ELASTOMERIC SILICONE COATING FOR REHABILITATION OF AGED METAL
More information1. What is Millennium One Step / One Step Green Foamable Adhesive and how is it packaged?
Technical Bulletin Millennium One Step / One Step Green Foamable Adhesive Field Conditions and Field Questions This bulletin is intended as a summary of questions and answers regarding various field issues
More informationSECTION FLASHING AND SEALING FRAMING WITH NON-CHEMICAL TERMITE BARRIERS
SECTION 072800 FLASHING AND SEALING FRAMING WITH NON-CHEMICAL TERMITE BARRIERS This section includes editing notes to assist the user in editing the section to suit project requirements. These notes are
More informationARDEX GUIDE SPECIFICATION ARDEX GS-4 Self-Leveling Repair Underlayment for Distressed Gypsum and Wood Subfloors
ARDEX GUIDE SPECIFICATION ARDEX GS-4 Self-Leveling Repair Underlayment for Distressed Gypsum and Wood Subfloors SECTION 03 54 13 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings, general provisions of
More informationINDOOR RUBBER FLOORING INTERLOCKING INSTALLATION / MAINTENANCE GUIDELINES MARATHON SERIES. Four-Side Interlock Loose Lay Installation
INDOOR RUBBER FLOORING INTERLOCKING INSTALLATION / MAINTENANCE GUIDELINES MARATHON SERIES Four-Side Interlock Loose Lay Installation The following pages are guidelines only... please read this manual thoroughly
More informationGalaxy Fit & Ultra (tiles) Installation Manual
READ INSTALLATION INSTRUCTIONS IN ENTIRETY PRIOR TO BEGINNING INSTALLATION! Introduction Galaxy Fit & Ultra (tiles) Installation Manual Robbins Galaxy Fit and Ultra products are manufactured in a dual
More informationSection Pre-Applied Sheet Membrane Waterproofing
Section 071324 Pre-Applied Sheet Membrane Waterproofing PART 1 GENERAL 1.01 SUMMARY A. The Work of this Section includes, but is not limited to, pre-applied sheet membrane waterproofing that forms an integral
More informationTECHNICAL DATA SHEET
Dy-Mark EPOXY COAT WATER-BASED DIRECTIONS FOR USE Dy-Mark All-In-One Epoxy Coat Water-Based is a fast dry floor coating that gives a professional finish to interior bare concrete floors. Epoxy Coat resists
More information