Estimating in Disaster Recovery. Prof. Ralph V. Locurcio, PE Director, Construction Management Program Florida Institute of Technology

Size: px
Start display at page:

Download "Estimating in Disaster Recovery. Prof. Ralph V. Locurcio, PE Director, Construction Management Program Florida Institute of Technology"

Transcription

1 Estimating in Disaster Recovery Prof. Ralph V. Locurcio, PE Director, Construction Management Program Florida Institute of Technology

2

3 The 1991 Gulf War had just ended

4 Debris was everywhere

5 750 Oil Fires blackened the skies

6 The Scope of Work

7 Key Facilities 3 Major Power Plants partially destroyed

8

9

10 Electrical systems 750 Oil Fires blackened the skies 5000km of 300KV Power Lines

11

12 Water systems 2 Water Pumping stations & distribution lines

13

14 Debris Roads & Bridges to be cleared

15 Roads & Bridges Repave a major hiway

16

17 Ports & Harbors 2 Harbors mined & destroyed

18 Fire damage Major facilities were torched

19 Terrorist actions International Airport bombed & burned

20 Unknowns 300 Schools were severely damaged

21

22

23

24

25

26

27

28

29

30

31

32

33

34

35

36

37 Construction Methodology Hired 11 Contractors Based on conceptual estimates Used Cost Plus Contracts No time for design Pre-qualified Contractors Made selection based on quals Mobilized with contingency

38 The Estimating Process 1200 Damage Survey Reports Prep Govt Estimate Excel Data Base Prioritize DSRs Issue Work Order to Contractor Compare estimates Negotiate differences Issue NTP Inspect labor & materials Difinitize at 50%

39

40

41

42

43

44

45

46

47

48

49

50

51

52

53

54

55 Estimating Class at FIT 55 January 20, 2010

56 My Background Corps of Engineers 30yrs Hurricane Eloise - PA 1975 Hurricane Hugo - SC 1989 Kuwait Reconstruction Hurricane Iniki - HI 1993 Pinatubo Recovery Atlantic Hurricanes 1994 to 1996 Private sector engineering Florida Tech 2004 (4 Hurricanes)

57 Estimating defined A complex process involving the collection of available information on the scope of a project, the expected resource consumption, and future changes in resource costs. This information is synthesized in a visualization of the construction process and translated into an approximation of the final cost.

58 Qualifications of an estimator Extensive knowledge of: Construction processes & methods Materials & methods Contracts & work practices Construction documents & details Background business factors Design & code requirements Verbal & written communications Good common sense & judgment

59 Estimating & Bidding Establish Standards Lessons Learned Kickoff Meeting Work Plan Prepare Estimate Revise Update Database Document Estimate Reality Check Yes Review Estimate Adjust Estimate? No Submit Bid Project Execution Feedback to improve data base Project Completion

60 Key Estimating Activities Read the Plans, Specs & Contract Conduct Site Visit Decide Construction Method Prepare Schedule Material Take-Offs Plan for Equipment Plan for Subcontracts Estimate costs Analyze Risk Factors Determine contingency Finalize Bid

61 Components of an estimate Project components Equipment needed Construction methods Temporary work items Support activities Externalities

62 Two broad types of estimates Conceptual Used for early decisions & feasibility Rough estimate using minimal data Relies heavily on past data Level of accuracy about 70% Detailed Used for major decisions; i.e. bids & budgets Based on final design documents Level of accuracy up to 95%

63 Accuracy increases over time % Design % Accuracy

64 Conceptual types: Based on prior experience: Weight check weight of equipment Cost-capacity factor- ratio of Q/$ Comparative cost of structure $/unit Feasibility estimates Appropriations estimates Time & location adjustments

65 Comparative cost of structure Basis is cost per unit based on past experience with similar units. Compare structures of like construction, (e.g. school: steel, concrete, quality, local labor, weather) Develop cost per unit, e.g. A$/pupil = A Cost/A pupils Apply to new construction: B Cost = B pupils x A$/pupil

66 Examples: Schools: $/pupil Bridges: $/feet of span Stadium: $/seat Hospital: $/beds Offices: $/ft 2 Warehouses: $/ft 3

67 Variations of comparative cost Plant cost ratio process plant ratio differentiates machine ft 2 from admin ft 2 Floor area cost/ft 2 but Total horizontal area all floors equal Finished floor area $ based on type finish Cubic foot of volume floor height varies

68 Parametric estimates Used for capital budgeting Expect 80-90% accuracy Based on historical data base Methods: Panel hist data on typical panels Bay hist data on typical bays Plant component equip cost + other TPC = ET/(1-PT) Where ET=tot equip cost/(1-% all other cost items) ET = $$$ equip/(1-70%)

69 Time & Location adjustments Cost indexing Based on similar group of key items Compare group over time or location Final cost based on ratio x calculated cost: Est Cost = T 2 /T 1 x Calc Cost Est Cost = (T 2 /T 1 )(L 2 /L 1 ) x Calc Cost

70 Cost forecasting The future ain t what it used to be Yogi Berra Need to project costs to mid-point of the construction year for budgeting Generally average past 3-5 years cost data & project forward

71 Detailed estimates Based on three primary factors: A. Scope quantities B. Constructability methods C. Risk externalities

72 A. Scope factors Technology in project - complexity Milestone deadlines for work - timing Material & equipment - availability Staffing needed skill & availability Contract terms allocation of risk Amount of competition - markets

73 B. Constructability factors Construction quality skill required Allowable tolerances productivity Complexity of design learning curve Flexibility of methods special terms

74 C. Risk factors Unspecified material or workmanship Differing site conditions Error in bidding Changes in cost over time Subcontractor error or failures Weather & environmental issues Strikes & labor issues Utilities & support issues

75 Estimating process 1. Determine project characteristics: Scope, constructability, risk 2. Examine the project design & site 3. Structure the estimate 4. Determine elements of cost 5. Calculate estimate

76 Examine Project Design Technical specifications Referenced standards Project drawings Testing and performance Special methods or procedures Physical elements & site characteristics Errors & omissions

77 Structure the estimate Structure often follows specification template Ensure nothing left out Need a plan for completing the project Logical flow of resources & materials Productivity factors

78 Determine elements of cost Labor- craft & skill resources; sub-contractors; union labor; wage rates; training; effective labor rates; productivity factors (weather, complexity, experience, management) Material- price, shipping, availability, storage, relation to specifications Equipment- purchase vs. lease, single use, down time, cost of maintenance Capital- interest rates, payment flow, retainage Time- overhead costs, required completion date,

79 Calculate the estimate Material take-off from plans 1. Quantities of all construction materials 2. Compare with specifications Labor cost for construction or installation 1. Effective labor rates 2. Team composition & duration Construction equipment schedule 1. On hand vs. lease or purchase 2. Time on job Follow elements of cost 1. Ensure all items are covered

80 Some Example Problems Calculate the estimated cost Solution in class

81 Conceptual Estimates Based on historical data Accuracy = +30% Used for planning purposes when no design exists Used to check validity of detailed estimate

82 Cost of equipment method Assumes cost of equipment is dominant factor in plant cost Estimate based on % of cost allocated to equipment relative to total cost of facility Estimated cost is proportional to known cost Must adjust for time & location

83 Example 1 5 min. Assume that the equipment portion of a chemical processing plant constructed in 2006 cost $1.2M and the total plant cost was $2.5M. Therefore the equipment portion of the total cost was 46%. Estimate the cost of a new plant with the same processes if the equipment for the new plant has been determined to cost $2.7M. Assume time and location factors are negligible in this case. Solution:

84 Example 2 Assume that the equipment portion of a chemical processing plant constructed in 2006 cost $1.2M and the total plant cost was $2.5M. Therefore the equipment portion of the total cost was 46%. Estimate the cost of a new plant with the same process if the equipment for the new plant has been determined to cost $2.4M. Assume time and location factors are negligible in this case. Solution: C 2 /E 2 = C 1 /E 1 solve for C 2 C 2 = [C 1 /E 1 ] x E 2 C 2 = [$2.5M/$1.2M] x $2.4M C 2 = [2.08] x $2.7 = $5,625,000M

85 Volumetric unit measure Similar to comparison of $/sf unit measure Used when facility has differing ceiling heights Calculate the $/cf of known facility Determine $/cf of known facility Calculate total cf of new facility Using known $/cf calculate cost of new facility Adjust for time and location

86 Example 2 10 min. Determine the cost of a new warehouse which will have 3 distinct storage areas with differing ceiling heights. Area 1 = 12 ; Area 2=14 and Area 3 = 10. The floor area of all three areas is 4000sf. A similar warehouse was constructed earlier this year for $2.4M. In that building the floor area was 8000sf and the ceiling height was a uniform 14. Assume time and location factors are negligible in this case. Solution:

87 Example 2 Determine the cost of a new warehouse which will have 3 distinct storage areas with differing ceiling heights. Area 1 = 12 ; Area 2=14 and Area 3 = 10. The floor area of each area is 4000sf. A similar warehouse was constructed earlier this year for $2.4M. In that building the floor area was 8000sf and the ceiling height was a uniform 14. Assume time and location factors are negligible in this case. Solution: Existing Building A = 8000sf x 14 = 112,000 cf Cost/cf = $2,400,000 / 112,000 cf = $21.43/cf New Building A1 = 4000sf x 12 = 48,000 cf A2 = 4000sf x 14 = 56,000 cf A3 = 4000sf x 10 = 40,000 cf Total = 144,000 cf Cost = 144,000 cf x $21.43/cf = $3,085,714

88 Adjusting for time Prices escalate over time due to inflation Must adjust estimated cost to mid-point of construction. Determine period of construction Determine start date of construction Determine mid-point of construction = average cost Determine escalation rate = given index Multiply estimated cost by escalation rate Note: escalation is compounded, ie. increase is cumulative over number of years of escalation

89 Adjusting for location Prices differ by region of the country Must consult a reliable index to determine relative cost of construction between regions RS Means Cost Data or Engineering News Record are examples Adjustment is a simple ratio multiplied times the estimated construction cost. So C 2 /C 1 = L 2 /L 1 X Estimated Construction Cost and C 2 = C 1 x L 2 /L 1

90 Example 3 15 min. You have been asked to prepare a conceptual cost estimate for the construction of a new university dormitory at Florida Tech to open in You have 2005 RS Means data that provides a cost of $30,000/bed for similar dormitories in the northeast of the US, and a construction period of 2 years. The Means data states that construction costs escalate at 10% per year in the southeast. If the dorm is to house 200 students at Florida Tech and the Means Cost Comparison Index between the northeast and southeast is 0.80, what is the estimated cost for the new library at Florida Tech at the mid-point of construction? Estimated Florida Tech cost:

91 Solution to pop quiz 1. $30,000 per bed x 200 beds = $6,000,000 in the northeast in In the southeast in 2005 $6,000,000 x 0.80 = $4,800, Construction start is Occupancy 2 years = = Mid-point of construction is = = Years of escalation = 4 yrs

92 Solution to pop quiz 6. Escalation: $4,800,000 x 1.10 = $5,280,000 ( ) $5,280,000 x 1.10 = $5,808,000 ( ) $5,808,000 x 1.10 = $6,388,800 ( ) $6,388,800 x 1.10 = $7,027,680 ( )

93 Solution Therefore the estimated cost of the new dormitory for Florida Tech at the mid-point of construction in 2009 is: $7,027,680

94 Cost Engineering Class Intro problem garden shed Processes covered Conceptual estimating 3 classes Detailed Estimating 25 classes Materials covered steel, masonry, wood Topics foundations, walls, floors, roofing Industry professionals 4 classes

95 Semester Project Groups bid on actual project Lite commercial office = 3000sf Typical Residence = 2400sf Bids presented to panel of professional judges Mystery guest invited

96 Industry Participation at FIT 96 January 20, 2010

97 Harry Johnson explains BRPH estimating 97 January 21, 2011

98 Phillip Jarvis explains how estimating is done at Burgoon-Berger 98 January 21, 2011

99 The class bids on real projects 99 January 21, 2011

100 We appreciate industry support! 100 January 21, 2011

101 That s all folks!!!! Thank you.

Construction Estimating

Construction Estimating 1 Construction Estimating James E. Rowings, Jr. Peter Kiewit Sons, Inc. 1.1 Introduction 1.2 Estimating Defined 1.3 Estimating Terminology 1.4 Types of Estimates Conceptual Estimates Time and Location

More information

BCN 4612 Estimating II - Semester Course Outline Fall 2015

BCN 4612 Estimating II - Semester Course Outline Fall 2015 BCN 4612 Estimating II - Semester Course Outline Fall 2015 Prerequisites: BCN 3611, Senior Standing 3 Credits COURSE DESCRIPTION: Analysis of determination of the cost of construction operations including

More information

Section 5 - Project Logistics

Section 5 - Project Logistics Section 5 - Project Logistics The project schedule for the Pearland Recreation Center and Natatorium begins with commencement of design on March 1, 2007 and ends with substantial completion on May 12,

More information

Construction Summary

Construction Summary Construction Summary Project Name Item of Work Base Building Add-ons Total Cost Code Site Development $ 18,150.00 $ - $ 18,150.00 Landscaping $ 500.00 $ - $ 500.00 Cast-in-place Concrete $ 7,806.00 $ -

More information

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. FEMA 50% RULE - SUBSTANTIAL IMPROVEMENT SUBSTANTIAL IMPROVEMENT/DAMAGE Z101-0410 NOTICE TO PROPERTY OWNERS Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information

More information

CLB 029 Wrap Rate Projections

CLB 029 Wrap Rate Projections CLB 029 Wrap Rate Projections Lesson Defense Acquisition University Table of Contents Wrap Rate Projections... 3 Introduction... 3 Wrap Rate Projection Methods... 4 Wrap Rate Projections Applied... 6 Summary...

More information

Performance Information Procurement System. Developed By: Performance Based Studies Research Group

Performance Information Procurement System. Developed By: Performance Based Studies Research Group Performance Information Procurement System Developed By: Performance Based Studies Research Group www.pbsrg.com 1 High Vendor Performance III. Negotiated-Bid Owner selects vendor Negotiates with vendor

More information

RAPID STRUCTURAL ASSESSMENT REPORT

RAPID STRUCTURAL ASSESSMENT REPORT Structure Type: SUPERSTRUCTURE Work Order: 5540 Facility Name: Pier 68 Warehouse FIN: 1680036 Building- Bldg. # 36 Asset Number: 1680-BLDG36 Facility Code: 3490 Asset Activity: STRUCTURE TWO YR Port Engineer:

More information

ADDENDUM ADDENDUM NUMBER: One DATE: 30 October 2012

ADDENDUM ADDENDUM NUMBER: One DATE: 30 October 2012 ADDENDUM ADDENDUM NUMBER: One DATE: 30 October 2012 RE: Putnam County Emergency Services Disaster Response and Logistical Storage 410 S. State Road 19 Palatka, Florida Architect s Project No. 1132 FROM:

More information

ILC ASIAN DRAFT SCHEDULE

ILC ASIAN DRAFT SCHEDULE ILC ASIAN DRAFT SCHEDULE K Foraz, M Gastal & J Osborne Many thanks to all contributors Objectives and scope To provide a target baseline construction schedule for the 2 Asian sample sites Address remarks

More information

JMU Capital Projects SWaM Outreach Event Presentations

JMU Capital Projects SWaM Outreach Event Presentations JMU Capital Projects SWaM Outreach Event Presentations Kjellstrom + Lee Contact: Jessica Marcus jmarcus@kjellstromandlee.com Project: College of Business Renovation/Expansion Please contact Kjellstrom

More information

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc. Franklin County Septic & Zoning permit application: A septic and zoning permit is required for residential or commercial

More information

Cost Estimation Manual For Steel Structures READ ONLINE

Cost Estimation Manual For Steel Structures READ ONLINE Cost Estimation Manual For Steel Structures READ ONLINE If searched for the book Cost estimation manual for steel structures in pdf form, then you've come to faithful site. We furnish utter release of

More information

CONSTRUCTION MANAGEMENT

CONSTRUCTION MANAGEMENT CONSTRUCTION MANAGEMENT Construction Management is not a new idea. The function of the Construction Manager is to work on behalf of the owner to complete a project within the plans and specifications provided.

More information

M $336M .73 S/L/A/M CONSTRUCTION SERVICES BY THE NUMBERS A BETTER WAY TO BUILD. YEARS OF CONSTRUCTION SERVICES DESIGN-BUILD PROJECTS

M $336M .73 S/L/A/M CONSTRUCTION SERVICES BY THE NUMBERS A BETTER WAY TO BUILD. YEARS OF CONSTRUCTION SERVICES DESIGN-BUILD PROJECTS A BETTER WAY TO BUILD. S/L/A/M CONSTRUCTION SERVICES BY THE NUMBERS Our team of construction professionals has more than 30 years of building experience in New England. We pride ourselves on the personal

More information

FOR SALE STATE-OF-THE-ART MANUFACTURING/WAREHOUSE STATE-OF-THE-ART MANUFACTURING/WAREHOUSE. 950 South Service Rd. Stoney Creek, ON

FOR SALE STATE-OF-THE-ART MANUFACTURING/WAREHOUSE STATE-OF-THE-ART MANUFACTURING/WAREHOUSE. 950 South Service Rd. Stoney Creek, ON STATE-OF-THE-ART MANUFACTURING/WAREHOUSE STATE-OF-THE-ART MANUFACTURING/WAREHOUSE FOR SALE 950 South Service Rd. Stoney Creek, ON For further details contact: Nick Holzinger Senior Vice President Sales

More information

EST Accuracy of FEL 2 Estimates in Process Plants

EST Accuracy of FEL 2 Estimates in Process Plants EST.2215 Accuracy of FEL 2 Estimates in Process Plants Melissa C. Matthews Abstract Estimators use a variety of practices to determine the cost of capital projects at the end of the select stage when only

More information

Totaling approximately 617,000

Totaling approximately 617,000 Totaling approximately 617,000 sq. ft, the mixed-use Embassy Suites hotel development is among the largest of several newly built hotels in the business district adjoining New York s bustling Wall Street

More information

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene January 19, 2018 Page 1 CURRENT CONSTRUCTION ACTIVITIES WEST ZONE Completed Carpet & Base in B6 Corridor. Completed 1 ST Coat of Paint in B4 Corridor. Completed 2 ND Coat of Paint in C3 Units Completed

More information

Invitation to Tender. Reference: IOSVSP4P-Metal

Invitation to Tender. Reference: IOSVSP4P-Metal 1 Invitation to Tender Metal fabrication / installation works at Plot 4, Porthmellon Industrial Estate, St Marys, Isles of Scilly Reference: IOSVSP4P-Metal 1 2 1 Background/Introduction Plot 4 Porthmellon

More information

Permit Fee Schedule from Fee Ordinance

Permit Fee Schedule from Fee Ordinance Permit Fee Schedule from Fee Ordinance SECTION II. A. PERMIT FEES At the department s discretion, 25% of fees may be required at the time plans are submitted for review. The permit fee plus the plan review

More information

RIDC Westmoreland. East Huntingdon Township 1001 Technology Drive Mt. Pleasant, PA 15666

RIDC Westmoreland. East Huntingdon Township 1001 Technology Drive Mt. Pleasant, PA 15666 East Huntingdon Township Table of Contents 1. Building Specifications 2. Site Layout 3. Rail Oriented Development Areas for New Construction 4. Floor Plans 5. Location Map 6. Map of Corporate Neighbors

More information

THE LEADER IN PREFABRICATED BATHROOM PODS

THE LEADER IN PREFABRICATED BATHROOM PODS THE LEADER IN PREFABRICATED BATHROOM PODS 2 why MODULAR SPEED SAFETY SIMPLICITY SUPERIOR QUALITY Bathroom pods have been in use across Europe and Asia for decades, and we are proud to have been the first

More information

THE VIRGINIA COMMONWEALTH UNIVERSITY SCHOOL OF BUSINESS AND ENGINEERING

THE VIRGINIA COMMONWEALTH UNIVERSITY SCHOOL OF BUSINESS AND ENGINEERING Thesis Proposal Lori E. Farley CONSTRUCTION MANAGEMENT Dr. J. Messner DECEMBER 18, 2007 THE VIRGINIA COMMONWEALTH UNIVERSITY SCHOOL OF BUSINESS AND ENGINEERING RICHMOND, VIRGINIA TABLE OF GUIDANCE EXECUTIVE

More information

The HOME Program and Multifamily Rehabilitation

The HOME Program and Multifamily Rehabilitation The HOME Program and Slide 1 Speakers Kevin Roddy, ICF International Joe Riddle, Arkansas Development Finance Authority Jonathan Stanley, Minnesota Housing Slide 2 Agenda Brief overview of HOME multi family

More information

Construction Manager at Risk Delivery Method

Construction Manager at Risk Delivery Method County of Alameda Board of Supervisors Transportation and Planning Committee May 4, 2015 Caroline Judy, Acting Director Construction Manager at Risk Delivery Method Briefing and Discussion Purpose Briefing

More information

SEMINOLE TRIBE OF FLORIDA INVITATION TO BID

SEMINOLE TRIBE OF FLORIDA INVITATION TO BID Solicitation #: ITB 151-2017 Title: Description: SEMINOLE TRIBE OF FLORIDA INVITATION TO BID General Home Repairs (Big Cypress Reservation) The Housing Department of the Seminole Tribe of Florida is requesting

More information

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower

DAG Architects, Inc. July South Walton Fire District Fleet Maintenance/Logistics Building & Training Tower DOCUMENT 001153 - REQUEST FOR QUALIFICATIONS 1.1 PURPOSE, LAWS, AND REGULATIONS A. The purpose of the Prequalification Procedure described in this Document is to provide Owner with a mechanism to evaluate

More information

NATIONAL SOCIETY OF INSURANCE PREMIUM AUDITORS & INSURANCE AUDITORS ASSOCIATION OF THE CENTRAL STATES APRIL 27, 2015 COMMONLY ABUSED CLASSIFICATIONS

NATIONAL SOCIETY OF INSURANCE PREMIUM AUDITORS & INSURANCE AUDITORS ASSOCIATION OF THE CENTRAL STATES APRIL 27, 2015 COMMONLY ABUSED CLASSIFICATIONS NATIONAL SOCIETY OF INSURANCE PREMIUM AUDITORS & INSURANCE AUDITORS ASSOCIATION OF THE CENTRAL STATES APRIL 27, 2015 1 The Winner Code 5606 Contractor Project Manager, Construction Executive, Construction

More information

How to Train Junior Estimators to Ensure They Develop the Instinct Earned with Experience & Don t Overly Rely on Imperfect Technology

How to Train Junior Estimators to Ensure They Develop the Instinct Earned with Experience & Don t Overly Rely on Imperfect Technology How to Train Junior Estimators to Ensure They Develop the Instinct Earned with Experience & Don t Overly Rely on Imperfect Technology Robert A. Nidzgorski, CPE, VMA, CCHM Preconstruction Director Skanska

More information

Chapter 1: Application and Administration

Chapter 1: Application and Administration Chapter 1: Application and Administration General Comments This chapter provides provisions regarding the purpose, scope, application, and administration of subsequent requirements of ICC 500. In addition

More information

Abington Memorial Hospital Abington, PA. Project Description

Abington Memorial Hospital Abington, PA. Project Description Project Description Project Description Project Background The expansion is a seven story, 360,000 SF addition with a total project cost of $98 million. Construction began in February 2003 and the project

More information

Extended Coverage Sprinklers

Extended Coverage Sprinklers Extended Coverage Sprinklers Agenda Why Extended Coverage History Extended Coverage Products Concept of Extended Coverage Sprinklers Summary 2 WHY EXTENDED COVERAGE? 3 Hazard / Occupancy Classification

More information

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider

FDA CDRH Laboratory Silver Spring, Maryland. Executive Summary: Timothy Mueller Structural Option Walter Schneider Executive Summary: The FDA-CDRH Laboratory is currently being built on the Food and Drug Administration s White Oak Consolidation Campus. It is a four story building with a full below grade ground floor

More information

Cashflow. Total price. Total cost. Contract completion. Predicted revenue (2) Total price. Total price. Total cost. Total cost. Contract completion

Cashflow. Total price. Total cost. Contract completion. Predicted revenue (2) Total price. Total price. Total cost. Total cost. Contract completion Cashflow The significance to the contractor s cashflow of different patterns of payment from the client and of delays is illustrated in the next figure showing a hypothetical contract of 2 years duration.

More information

1. SALIENT FEATURES OF DIPLOMA PROGRAMME IN CIVIL ENGINEERING (SPL. HIGHWAY ENGINEERING)

1. SALIENT FEATURES OF DIPLOMA PROGRAMME IN CIVIL ENGINEERING (SPL. HIGHWAY ENGINEERING) 1. SALIENT FEATURES OF DIPLOMA PROGRAMME IN CIVIL ENGINEERING (SPL. HIGHWAY ENGINEERING) 1) Name of the Programme : Diploma Programme in Civil Engineering (Spl. Highway Engineering) 2) Duration of the

More information

Devin Learn Construction Management AE Senior Thesis

Devin Learn Construction Management AE Senior Thesis Devin Learn Construction Management AE Senior Thesis 5 th and 6 th Floor Fit-Out & Cardiac Elevator Addition Introduction Vs. Retro- Pre-Cast Floor System s at ICRA Partitions and Conclusions Questions

More information

Storm Preparedness & Hazard Mitigation for Post-Sandy Red Hook, Brooklyn, NY Deborah Mills, CFM Dewberry Consultants, LLC.

Storm Preparedness & Hazard Mitigation for Post-Sandy Red Hook, Brooklyn, NY Deborah Mills, CFM Dewberry Consultants, LLC. Storm Preparedness & Hazard Mitigation for Post-Sandy Red Hook, Brooklyn, NY Deborah Mills, CFM Dewberry Consultants, LLC. Agenda Introduction to the Project Red Hook, Brooklyn Sandy s Impact Hazard Risks

More information

Cost Analysis and Estimating for Engineering and Management

Cost Analysis and Estimating for Engineering and Management Cost Analysis and Estimating for Engineering and Management Chapter 8 Product Estimating Ch 8-1 Overview Processes for Determining Price Bottom Up and Top Down Using Productive Hour Costs Learning in Product

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection

SECTION RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection SECTION 13090 RADIATION SHIELDING ENCLOSURE Low Intensity Radiation Protection Prepared by: 90 Dayton Avenue, Unit 4B, Suite 13 Passaic, NJ 07055 (973) 574-9077 13090-1 LOW INTENSITY RADIATION PROTECTION

More information

Questions and Answers for RFP No. 010 for the provision of prefabricated pharmacy storage units

Questions and Answers for RFP No. 010 for the provision of prefabricated pharmacy storage units December 6, 2017 Questions and Answers for RFP No. 010 for the provision of prefabricated pharmacy storage units 1. Question: In the site annex attachments mention is made of distance from the DHO What

More information

Construction Formwork Inventory Control Tracking System

Construction Formwork Inventory Control Tracking System Construction Formwork Inventory Control Tracking System 1 P age CASE STUDY OVERVIEW Supertech was first engaged by the subject formwork and concrete construction contractor to transition their planning,

More information

Manufacturing Facilities Proposal

Manufacturing Facilities Proposal Manufacturing Facilities Proposal Construction proposal To assist business owners with expansion projects, Wisconsin Public Service has compiled information and renderings of common building types in business

More information

SECTION NETWORK ANALYSIS SCHEDULES (NCA)

SECTION NETWORK ANALYSIS SCHEDULES (NCA) PART 1- GENERAL 1.1 DESCRIPTION: SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULES (NCA) SPEC WRITER NOTES: 1. Use this section only for NCA projects. 2. Coordinate this section with the paragraphs of FAR

More information

Ronald J. Rider, MBA

Ronald J. Rider, MBA Ronald J. Rider, MBA LONG INTERNATIONAL Long International, Inc. 5265 Skytrail Drive Littleton, Colorado 80123-1566 USA Telephone: (303) 972-2443 Fax: (303) 200-7180 www.long-intl.com Ronald J. Rider,

More information

INOVA Office Building I. Adolfson & Peterson Construction. Keri Burson:

INOVA Office Building I. Adolfson & Peterson Construction. Keri Burson: INOVA Office Building I Adolfson & Peterson Construction Keri Burson: kburson@a-p.com; 303-363-7101 Category #9 Best Building Project General Contractor ($10 - $40 Million) Why this project should win

More information

JOINT GUIDELINE #5. Temporary Job Utilities and Services. Construction Industry Survival Kit. The Second in a Series

JOINT GUIDELINE #5. Temporary Job Utilities and Services. Construction Industry Survival Kit. The Second in a Series The Second in a Series JOINT GUIDELINE #5 Temporary Job Utilities and Services tion between parties to the construc- tion contract. When adequate iden- tification of temporary services is pro- vided and

More information

Texas Health Resources, Methodist Alliance Hospital, Fort Worth, Texas. Hospital; 188,000 s.f. $46.5m 58 beds with growth potential of 300 beds

Texas Health Resources, Methodist Alliance Hospital, Fort Worth, Texas. Hospital; 188,000 s.f. $46.5m 58 beds with growth potential of 300 beds Seminar Objectives 1) IPD and its impact on team behavior 2) Lean and its role in a collaborative process. 3) Pre-Fabrication 4) How Lean, BIM and collaborative processes impact project value. The Project

More information

Subcontractor / Supplier Pre-Bid Qualification All fields must be filled out unless otherwise noted.

Subcontractor / Supplier Pre-Bid Qualification All fields must be filled out unless otherwise noted. GALLAGHER-KAISER CORPORATION Subcontractor / Supplier Pre-Bid Qualification All fields must be filled out unless otherwise noted. Supplier Name: Remit to Address: Contact: Email: City: Telephone: State:

More information

CH. 9 WOOD CONSTRUCTION

CH. 9 WOOD CONSTRUCTION CH. 9 WOOD CONSTRUCTION PROPERTIES OF STRUCTURAL LUMBER Grading Load carrying capacity effected by: - Size and number of knots, splits & other defects - Direction of grain - Specific gravity of wood Grading

More information

Suspended Metal lath and Cement Plaster. Coverings Rigid Insulation, 1/2 - in 0.75 psf. Floor Fill Lightweight Concrete, per inch 8 psf

Suspended Metal lath and Cement Plaster. Coverings Rigid Insulation, 1/2 - in 0.75 psf. Floor Fill Lightweight Concrete, per inch 8 psf Dead Loads Ceiling Suspended Metal lath and Cement Plaster 15 psf Coverings Rigid Insulation, 1/2 - in 0.75 psf Floor Fill Lightweight Concrete, per inch 8 psf Floor Finish Frame Partitions Ceramic or

More information

Principles of Schedule Contingency Management

Principles of Schedule Contingency Management Principles of Schedule Contingency Management Ted Douglas, CCC, PSP ACTPMA, LLC Consulting 2014 Construction CPM Conference Orlando, Florida Schedule Contingency Management Background Outline of Presentation

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

EMERGENCY MANAGEMENT PREPAREDNESS AND ASSISTANCE TRUST FUND ARC 4496 Evaluation Questionnaire

EMERGENCY MANAGEMENT PREPAREDNESS AND ASSISTANCE TRUST FUND ARC 4496 Evaluation Questionnaire EMERGENCY MANAGEMENT PREPAREDNESS AND ASSISTANCE TRUST FUND ARC 4496 Evaluation Questionnaire Additional Instructions and Clarifications 1. Please review ARC 4496 before beginning the project identification

More information

Cost Analysis and Estimating for Engineering and Management

Cost Analysis and Estimating for Engineering and Management Cost Analysis and Estimating for Engineering and Management Chapter 8 Product Estimating Ch 8-1 Overview Processes for Determining Price Bottom Up and Top Down Using Productive Hour Costs Learning in Product

More information

Independent Government Estimates A Fact Sheet

Independent Government Estimates A Fact Sheet 1. Introduction Independent Government Estimates A Fact Sheet An Independent Government Estimate (IGE) is an unbiased cost estimate based upon the specifications and without the influence of potential

More information

Cluster 2 Measure up. Construction, Plumbing and Services Integrated Framework CPC08 Certificate II in Construction Pathways (CPC20211)

Cluster 2 Measure up. Construction, Plumbing and Services Integrated Framework CPC08 Certificate II in Construction Pathways (CPC20211) Wagga Wagga RTO 90333 Instructions to Students Student Package Cluster 2 Measure up Units of competency covered by this assessment package CPCCCM1015A: Carry out measurements and calculations CPCCCA2002B:

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

VANDERBILT UNIVERSITY

VANDERBILT UNIVERSITY VANDERBILT UNIVERSITY CAMPUS PLANNING & CONSTRUCTION PROJECT MANUAL GUIDELINES INTRODUCTION These instructions are intended to guide the Architect in preparing the Project Manual for Vanderbilt University

More information

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows:

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows: UNION PACIFIC RAILROAD SCOPE OF HYDROLOGIC/HYDRAULIC DESIGN ENGINEERING AND PERMITTING SERVICES FOR SIZING WATERWAY OPENINGS AT NEW AND REPLACEMENT STRICTURES These flood passage criteria were developed

More information

PERMIT APPLICATION REQUIREMENTS NEW COMMERCIAL BUILDING/CONSTRUCTION CODES USED: CURRENT ADOPTED FLORIDA BUILDING CODE AND NEC

PERMIT APPLICATION REQUIREMENTS NEW COMMERCIAL BUILDING/CONSTRUCTION CODES USED: CURRENT ADOPTED FLORIDA BUILDING CODE AND NEC PERMIT APPLICATION REQUIREMENTS MANDATORY DOCUMENTS: NEW COMMERCIAL BUILDING/CONSTRUCTION CODES USED: CURRENT ADOPTED FLORIDA BUILDING CODE AND NEC 1. COMPLETED NEW COMMERCIAL or MULTIFAMILY PERMIT APPLICATION

More information

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8

Table of Contents.2. Introduction...3 Gravity Loading and Deflections..4. Existing Structural System..8 WISCONSIN PLACE RESIDENTIAL TECHNICAL ASSIGNMENT 2 OCTOBER 29, 2007 KURT KRASAVAGE THE PENNSYLVANIA STATE UNIVERSITY STRUCTURAL OPTION FACULTY ADVISOR: DR. ALI MEMARI 1 Table of Contents Table of Contents.2

More information

Covering the Pacific Northwest with QUALITY

Covering the Pacific Northwest with QUALITY 2 Covering the Pacific Northwest with QUALITY 3 Finding a reputable painting company that completes projects in a timely manner from the planning stages to completion can be a difficult task. Yet Long

More information

Managing Residential Properties Learning Objectives

Managing Residential Properties Learning Objectives Managing Residential Properties Learning Objectives PART I: INTRODUCTION 1. Course Overview The goal of this course is to provide residential managers with the tools and expertise necessary to professionally

More information

Report on Building Damage in Central Ibaraki Prefecture by The 2011 off the Pacific Coast of Tohoku Earthquake Released on April 3, 2011

Report on Building Damage in Central Ibaraki Prefecture by The 2011 off the Pacific Coast of Tohoku Earthquake Released on April 3, 2011 Report on Building Damage in Central Ibaraki Prefecture by The 2011 off the Pacific Coast of Tohoku Earthquake Released on April 3, 2011 Dr. Toshiyuki Kanakubo, Department of Engineering Mechanics and

More information

Lease-Leaseback Project Delivery Method

Lease-Leaseback Project Delivery Method Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman,

More information

Maintenance, Repair, and Operations JOC Program

Maintenance, Repair, and Operations JOC Program Maintenance, Repair, and Operations JOC Program Pre-Proposal Meeting CSP #16-11-07 Building Automation Systems CSP #16-11-08 Glass and Glazing Service CSP #16-11-09 HVAC / Mechanical CSP #16-11-10 Plumbing

More information

MANHATTAN COLLEGE STUDENT COMMONS

MANHATTAN COLLEGE STUDENT COMMONS MANHATTAN COLLEGE STUDENT COMMONS BUDGET CHECK USING GILBANE S COSTADVISOR MODEL OCTOBER 29, 2010 Introduction: Gilbane developed this CostAdvisor Model of the proposed new Manhattan College Student Commons

More information

Project Green House. Green Team. Making the world greener one house at a time

Project Green House. Green Team. Making the world greener one house at a time Project Green House Making the world greener one house at a time UC Berkeley Extension, Business and Management UCB X470 Project Management February 2008 Green Team Lori Plein Anne Cairney Ferdinand Bueno

More information

Cost Estimating Guideline February, 2017

Cost Estimating Guideline February, 2017 Cost Estimating Guideline February, 2017 Procedures are subject to change without notice. Check the Capital Project Delivery website to ensure this is the current version. Table of Contents Section 1 -

More information

PMP Sample Questions Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope?

PMP Sample Questions  Click here for PMP Questions. Question No : 1 Which of the following is an output of Define Scope? PMP Sample Questions www.techfaq360.com Click here for 1600+ PMP Questions Question No : 1 Which of the following is an output of Define Scope? A. Accepted deliverables B. Change Requests C. Project document

More information

REQUEST FOR QUALIFICATIONS (RFQ) For Engineering Services Institute for Marine Mammal Studies (IMMS)

REQUEST FOR QUALIFICATIONS (RFQ) For Engineering Services Institute for Marine Mammal Studies (IMMS) REQUEST FOR QUALIFICATIONS (RFQ) For Engineering Services Institute for Marine Mammal Studies (IMMS) The IMMS is soliciting qualification statements for engineering services to assist the IMMS with the

More information

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES T.M.S. Elhag and A.H. Boussabaine School of Architecture and Building Engineering, The University of Liverpool, Liverpool L69 3BX, UK Understanding the

More information

Financial Transfer Guide DBA Software Inc.

Financial Transfer Guide DBA Software Inc. Contents 3 Table of Contents 1 Introduction 4 2 Why You Need the Financial Transfer 6 3 Total Control Workflow 10 4 Financial Transfer Overview 12 5 Multiple Operating Entities Setup 15 6 General Ledger

More information

Fairfax County Government Construction Management At Risk (CMAR)

Fairfax County Government Construction Management At Risk (CMAR) Fairfax County Government Construction Management At Risk (CMAR) Presented for: CMAA - Owner s Committee Presented by: Matt Doyle Branch Chief, Wastewater Design and Construction Division Department of

More information

Understanding compact shelving

Understanding compact shelving Understanding compact shelving Introduction jdc - Spacemaster 2 In its essence, movable compact shelving is shelving that is mounted to a wheeled platform (carriage) that rides on tracks placed on or in

More information

Heavy Equipment Maintenance Building Project. Pre-Bid Meeting and Site Tour

Heavy Equipment Maintenance Building Project. Pre-Bid Meeting and Site Tour Heavy Equipment Maintenance Building Project Contract No. 4343 Pre-Bid Meeting and Site Tour February 22, 2017 Agenda Introduction of the HEMB Project Team EchoWater Project Overview Heavy Equipment Maintenance

More information

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT 1 East Franklin Street Phone: 301-790-4163 Third Floor Hagerstown, MD 21740 Fax: 301-791-2650 BUILDING PERMIT APPLICATION FOR RESIDENTIAL ACCESSORY

More information

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment & Convention Authority

More information

How to Estimate the Cost of Painting an Exterior Masonry Wall. December 2010 TABLE OF CONTENTS SECTION 1: INTRODUCTION... 3

How to Estimate the Cost of Painting an Exterior Masonry Wall. December 2010 TABLE OF CONTENTS SECTION 1: INTRODUCTION... 3 How to Estimate the Cost of Painting an Exterior Masonry Wall December 2010 TABLE OF CONTENTS SECTION 1: INTRODUCTION... 3 Main CSI Division... 3 Specific Sub-division... 3 Brief Description... 3 SECTION

More information

ATTACHMENT 13 NORTHEAST-POCONO RELIABILITY PROJECT PPL DESIGN CRITERIA AND SAFETY PRACTICES

ATTACHMENT 13 NORTHEAST-POCONO RELIABILITY PROJECT PPL DESIGN CRITERIA AND SAFETY PRACTICES ATTACHMENT 13 NORTHEAST-POCONO RELIABILITY PROJECT PPL DESIGN CRITERIA AND SAFETY PRACTICES The National Electrical Safety Code (NESC) is a set of rules to safeguard people during the installation, operation,

More information

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit: TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION 355-7575 Ext. 395 Needed to Obtain Permit: 1. Building Permit Application, and/or residential plumbing permit application, as applicable, to be

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER

More information

SECTION 14.0 CAPITAL COST ESTIMATES

SECTION 14.0 CAPITAL COST ESTIMATES SECTION 14.0 CAPITAL COST ESTIMATES 1 14.0 Capital Cost Estimates CONTENTS 14.0 CAPITAL COST ESTIMATES...4 14.1 Introduction...4 14.2 Overall Summary...4 14.3 Mining Capital Cost Estimate...5 14.3.1 Pre-Production

More information

PRODUCT SPECIFICATIONS

PRODUCT SPECIFICATIONS PART 1 GENERAL 1.01 SUMMARY A. Section Includes: High density cast resin architectural products, including columns, panels, caps, bases, trim elements and balustrade systems. Specifier Note: Article below

More information

CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures

CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE - 268-5161 Residential Accessory Structures This information has been compiled for the benefit of any person

More information

The economic impact of Blount Island Command

The economic impact of Blount Island Command ABSTRACT The economic impact of Blount Island Command Hassan Pordeli, Jacksonville University Peter Wynkoop The HPW Group, LLC This report provides a detailed analysis of the economic impact of the U.S.

More information

SUGGESTED COST-EFFECTIVE COLD-FORMED STEEL FIRE AND ACOUSTIC-RATED WALL AND FLOOR/ CEILING ASSEMBLIES FOR MULTI-UNIT STRUCTURES

SUGGESTED COST-EFFECTIVE COLD-FORMED STEEL FIRE AND ACOUSTIC-RATED WALL AND FLOOR/ CEILING ASSEMBLIES FOR MULTI-UNIT STRUCTURES TECHNICAL NOTE On Cold-Formed Steel Construction 1201 15th Street, NW, Suite 320 W ashington, DC 20005 (202) 785-2022 $5.00 SUGGESTED COST-EFFECTIVE COLD-FORMED STEEL FIRE AND ACOUSTIC-RATED WALL AND FLOOR/

More information

Project Manager- Park Operations

Project Manager- Park Operations Page 1 of 5 COSUMNES COMMUNITY SERVICES DISTRICT invites applications for the position of: Project Manager- Park Operations SALARY: $73,812.00 - $98,904.00 Annually OPENING DATE: 11/03/17 CLOSING DATE:

More information

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017 SECTION 01 4000 - QUALITY REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification

More information

Garage Construction. Permit Guide. Development Center. General Information. Zoning Ordinance Requirements. Building Code Requirements

Garage Construction. Permit Guide. Development Center. General Information. Zoning Ordinance Requirements. Building Code Requirements General Information Site Card. Before starting construction, post the site card (issued by the City) in a front window visible from the street. Miss Dig. Before you dig, call Miss Dig at 800.482.7171 This

More information

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department:

Permit Requirements: Building Codes: The City of Clanton has adopted the following codes which are enforced by the Building Department: Permit Requirements: Any owner, authorized agent, or contractor who desires to construct, enlarge, alter, repair, move, demolish, or change the occupancy of a building or structure, or to erect, install,

More information

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following: CONSTRUCTION SURVEY PART 1 - GENERAL 1.01 SECTION INCLUDES Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following: A. Construction Survey: 1. Project

More information

Michael Bologna. 665 Meadow Ln Rochester PA, State College, PA October 16, 2015

Michael Bologna. 665 Meadow Ln Rochester PA, State College, PA October 16, 2015 Michael Bologna State College, PA 16801 665 Meadow Ln Rochester PA, 15074 October 16, 2015 Linda M. Hanagan, PhD, P.E. The Pennsylvania State University Dear Dr. Hanagan, The attached technical reports

More information

Post Remediation Warranty

Post Remediation Warranty Post Remediation Warranty This warranty is provided by: Manufacturer: Anabec, Inc. 9393 Main Street PO Box 433 Clarence, NY 14031 716-759-1674 info@anabec.com & Qualified Contractor (Contractor): Presented

More information

Forecasting Construction Labor Demand: A Working Model?

Forecasting Construction Labor Demand: A Working Model? Construction Economics Research Network Washington, D.C. Forecasting Construction Labor Demand: A Working Model? Ralph Gentile McGraw-Hill Construction Research and Analytics December 6, 2007 1/24/2008

More information

Managing Schedule Change

Managing Schedule Change Managing Schedule Change Ted Douglas, CCP, PSP, FAACE CPM Construction Conference Orlando, Florida January 11, 2017 Managing Schedule Change Outline Change Drivers Contract Changes Clause Schedule Change

More information