1 Lease-Leaseback Project Delivery Method ASBA Technical Meeting & Tradeshow Winter 2013 Presented by: Mark Baginski Principal Verde Design, Inc. James Moore V.P. of Pre-Construction Services Robert A. Bothman, Inc.

2 Agenda California Legal Authority What is Lease-Leaseback? Benefits of Lease-Leaseback Delivery Lease-Leaseback Process Lease-Leaseback Team L-LB Entity Selection The RFQ-RFP for L-LB Entity Reference Checks Interviews Contract Agreements Other Costs Lease-Leaseback A Landscape Architect s Perspective The Contractor s Role

3 Legal Authority California Education Code Section et. seq. the governing board of a school district, without advertising for bids, may let, for a minimum rental of one dollar ($1) a year, to any person, firm, or corporation any real property that belongs to the district if the instrument by which such property is let requires the lessee herein to construct on the demised premises, or provide for the construction thereon of, a building or buildings for the use of the school district during the term thereof, and provides that title to that building shall vest in the school district at the expiration of that term

4 What is Lease-Leaseback? A construction project delivery method A way to select a firm to build or modernize school facilities through a qualifications based process Can pick a firm that fits with District culture Value can be a factor of selection A possible financial mechanism

5 Lease-Leaseback Process District Elects to Pursue L-LB Delivery Receive Preliminary Board Approval Engage Legal Counsel to Develop Agreements Select Design Professional Through RFP/RFQ Conceptual Plan Development Based on Program & Available Budget Select L-LB Entity Through RFP/RFQ Enter into a L-LB agreement with L-LB Entity

6 Lease-Leaseback Team District Legal Counsel District CBO Architect Contractor Construction Manager (if Applicable)

7 L-LB Entity Selection RFP or RFQ Reference Checks Interviews Selection & Board Approval Contract Negotiations Board Approval of Contract

8 Contract Agreements Preliminary Services Agreement Site Lease Facilities Lease General Conditions

9 A Landscape Architect s Perspective

10 Lease-Leaseback: An LA s Perspective Why consider this alternative delivery method? What are the benefits of Lease-Leaseback? Thoughts on process Summary

11 Why Alternative Delivery? The traditional Design-Bid-Build delivery method for Public Contracts requires that the District accept the lowest bid. This process often does not consider the strength of a firm s qualifications. Designing to the lowest level versus the strengths of the contractor Opportunity to collaborate Everyone needs to do their homework GMP with contingency value added items

12 Benefits of L-LB from the Designer s Perspective Based on Clear Goals and Objectives More bang for your buck Collaborative environment Positive/Proactive communication Sharing knowledge This leads to a more successful project through a spirit of teamwork and cooperation and avoids adversarial relationships.

13 Benefits of L-LB from the Designer s Perspective Results: Reduced or Eliminated Change Orders Collaborative approach to the project Significant reduction in legal risks associated with design-bid-build Speedier project delivery

14 Thoughts on Process: An Architect s Perspective Need to embrace the process Need to think about things a bit differently Communication is essential for success Keep your options open Plan for contingencies Wish list items Possible scenarios Carry forward into next project on large multiple sites

15 Summary: An Architect s Perspective Private Sector process in the Public Sector Team atmosphere Better budget and schedule control Reduced risk of legal problems through partnerships established early in the project Easier Close Out process due to team relationships

16 Contractor s Role

17 L-LB Design Phase Services Preliminary Service Agreement Scope Site Assessment Budgeting Value Engineering Constructability Review Master Scheduling Bid Packaging & GMP Development Subcontractor input Construction Logistics Planning

18 What is a GMP? A Guaranteed Maximum Price (GMP) is the amount that the L-LB Entity guarantees (the sum of the cost of the work and the L-LB Entity s fee) it will not exceed. The maximum is subject to additions and deductions, due to changes in the scope of work. All costs which exceed the GMP and are not approved by change order are paid by the L-LB Entity.

19 GMP Preparation Pre-qualify Subcontractors Subcontractor Bid Solicitations Compliance with Local & Disadvantage Subcontractor Hiring Requirements Bidding Documents Plans and Specifications District Front End Documents Scope of Work Bid Packages OCIP or PLA Requirements Proposal Forms Master Subcontract Agreement Master Schedule

20 GMP Preparation Pre-Bid Meeting Evaluate and Level Bids Negotiate Prices Self-Perform Scope Estimates GMP Cost Breakdown General Conditions CSI Work Breakdown-Itemized Profit and Overhead Itemization Bonds & Insurance Contingencies GMP Written Proposal

21 CM at Risk - GMP Contractor s Cost (GC s + Fee) + Contractor Self-Perform Scope + Subcontractors Bids + Contingency (% controlled by GC) + Contingency (% controlled by District) Changes to GMP: Errors & Omissions Change of Scope Unforeseen Conditions = GMP

22 L-LB Services: Construction Phase Team Management and Coordination Scheduling Cost Controls and Change Order Management Submittal Process Subcontracting

23 L-LB Services: Construction Phase Field Management Safety Program Quality Program Project Close Out Process Warranty Period Service

24 Acceptance of Risk Will Guarantee the Cost with a GMP We Cover the Gap in the GMP We Will Assure On-Time Completion We Will Furnish a Payment & Performance Bond if Requested We Will Comply with Owner Controlled Insurance Policy Requirements We function as the L-LB Developer/Contractor

25 L-LB vs. Hard Bid L-LB Hard Bid Owner receives competitive pricing X X Performance and payment bonds X X Ability to re-bid individual trades X No Prequalify all subcontractors X No Field coordination control X X Commissioning/warranty issues X X Price Guarantee * X X Contractor pays for scope gaps X X Contractor involved in design phase X No * Price Guarantee in Hard Bid is the floor but in L-LB it is the ceiling.

26 Summary: Advantages of L-LB Owner hand picks their designer and builder Project team works in a collaborative atmosphere Greater schedule control / flexibility Greater budget control including re-bid on individual trades if necessary Pre-qualify all trade contractors Competitive pricing in each trade Lowers potential for future change orders Perceived as more friendly contracting approach by designers and subcontractors Cost savings Open Book financial approach

27 Benefits to Architects A/E maintains contractual relationship to District Selection of contractor based on qualifications Contractor involvement during design phase Adversarial GC relationship eliminated GMP prior to construction

28 Benefits to Contractor Lower competition virtually eliminating unqualified contractors from selection process Final selection of contractor based on qualifications & team fit Contractor involvement during design phase helps eliminate design ambiguities prior to final pricing and through construction Much faster and more effective transition from pricing to construction Collaborative process eliminates traditional adversarial relationships

Alternative Delivery Methods in the Post-Davis World

Alternative Delivery Methods in the Post-Davis World CASBO 2017 Annual Conference April 2017 Alternative Delivery Methods in the Post-Davis World Alan Reising Long Beach Unified School District areising@lbschools.net Phil Henderson Orbach Huff Suarez & Henderson

More information

Publicly Bid: Negotiated, Non-Bid: Hybrid: 5/12/2017. Design-Bid-Build Multiple-Prime Contracting. Lease-Leaseback* Design-Build

Publicly Bid: Negotiated, Non-Bid: Hybrid: 5/12/2017. Design-Bid-Build Multiple-Prime Contracting. Lease-Leaseback* Design-Build 1 Leigh Sata, Santa Rosa Junior College Kelle Lynch McMahon, Peralta Community College Mark Kelley, Dannis Woliver Kelley Deidree Sakai, Dannis Woliver Kelley 2 1 Publicly Bid: Design-Bid-Build Multiple-Prime

More information

Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119

Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119 Clark County Department of Aviation Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119 Professional Service Contracts Construction Contracts Professional Service Contracts

More information

Lease-Leaseback in a Post-AB 2316 World

Lease-Leaseback in a Post-AB 2316 World CASBO 2018 Annual Conference Lease-Leaseback in a Post-AB 2316 World Alan Reising Long Beach Unified School District areising@lbschools.net Phil Henderson Orbach Huff Suarez & Henderson phenderson@ohshlaw.com

More information

FACILITY PROJECT BIDDING OPTIONS OVERVIEW

FACILITY PROJECT BIDDING OPTIONS OVERVIEW FACILITY PROJECT BIDDING OPTIONS OVERVIEW A Presentation to the Board of Education Galt Joint Union High School District February 14, 2017 January 10, 2017 GHSD Measure E Bidding Options Overview 2 Overview

More information

LB 889 The Political Subdivisions Construction Alternatives Act

LB 889 The Political Subdivisions Construction Alternatives Act 1 LB 889 The Political Subdivisions Construction Alternatives Act What cities, villages, counties, state colleges, community colleges, and school districts need to know about their construction options.

More information

Construction Documents Education Program

Construction Documents Education Program PLANNING AND PRE-DESIGN THE CONSTRUCTION SPECIFICATIONS INSTITUTE 110 South Union Street, Suite 100 Alexandria, VA 22314-3351 www.csinet.org CDEP 1.0.1: 03-1 Copyright Materials This presentation is protected

More information

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO Time to Build! What to Expect On Your Upcoming and Journey PRESENTED TO Christopher is an award-winning architect with more than 20 years of diversified architectural experience in design of projects from

More information

Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011)

Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011) Ohio s Qualifications-Based Selection Law (as amended by Sub. H.B. 153, 129 th Ohio General Assembly, effective Sept. 28, 2011) Sec. 153.65. As used in sections 153.65 to 153.73 of the Revised Code: (A)(1)

More information

Chapter 4 State Requirements for Educational Facilities Section 4.1

Chapter 4 State Requirements for Educational Facilities Section 4.1 providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,

More information

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services REQUEST FOR PROPOSALS Construction Manager CM Services Pre-Construction and Construction Services Big Sky Fire Department Station 1 Project Big Sky Fire District OWNER Big Sky, Montana November 2016 Request

More information

Construction Family of Documents

Construction Family of Documents Construction Family of Documents The EJCDC Construction Family Documents (C-Series) is intended for engineered construction projects. The current edition (2013) is endorsed by both the Construction Specifications

More information

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN Introduction Becker County is issuing a RFQ for Construction Management at Risk Services

More information

ALTERNATE CONSTRUCTION PROJECT DELIVERY METHODS

ALTERNATE CONSTRUCTION PROJECT DELIVERY METHODS ATKINSON, ANDELSON, LOYA, RUUD & ROMO ALTERNATE CONSTRUCTION PROJECT DELIVERY METHODS 2017 ACBO Spring Conference Good Luck is the Residue of Good Design May 22-24, 2017 Lake Tahoe, California Cerritos

More information

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR February 5, 2018 SUMMARY OF CM/GC SELECTION PROCESS FOR DIMMIT II APARTMENT BUILDING The Town of Winter Park requests proposals from qualified Construction Manager / General Contractor (CM/GC) firms for

More information

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Project Delivery Methods January 30, 2012 Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing Terms Capital Project Capital Program Prioritized Capital Plan

More information

EXHIBIT A. 1) General:

EXHIBIT A. 1) General: 1) General: EXHIBIT A FINDINGS OF FACT FOR EXEMPTION FROM COMPETITIVE BIDDING AND USE OF THE CONSTRUCTION MANAGER/GENERAL CONTRACTOR (CM/GC) METHOD OF CONTRACTING FOR TILLAMOOK PUD OPERATIONS CENTER AND

More information

Facility Basics for Bond Project Communications

Facility Basics for Bond Project Communications Facility Basics for Bond Project Communications TSPRA Annual Conference February 19, 2013 Presented by: Cathy Brandewie O Connell Robertson Architectural Teams can help with Evaluating / Assessing Facilities

More information

Construction Project Delivery Methods

Construction Project Delivery Methods Construction Project Delivery Methods Purchasing Requirements and Applications 9/20/2012 1 General Purchasing Requirements 9/20/2012 2 Governmental Purchasing Requirements Law: Texas Education Code 44.031

More information

Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide

Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide array of design, construction, construction administration,

More information

Legal Issues Related to Design Build

Legal Issues Related to Design Build Legal Issues Related to Design Build Presented by Aaron O. Martin CLARK, MIZE & LINVILLE, CHARTERED 129 S. 8 th, St. Salina, KS 67401 Telephone: (785) 823 6325 Facsimile: (785) 823 1868 aomartin@cml law.com

More information

Construction Project Delivery Methods Overview and Comparison. Operations Division

Construction Project Delivery Methods Overview and Comparison. Operations Division Construction Project Delivery Methods Overview and Comparison Operations Division 1 Four Types of Delivery Methods Design/Bid/Build (CM Multi-Prime) CM at Risk Design/Build Lease/Leaseback 2 Considerations

More information

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents

Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Request for Qualifications (Design-Build Contract) State of Ohio Standard Forms and Documents Administration of Project: Local Agency Project Name Stadium Project Response Deadline 1/9/14 12 pm local time

More information

PROVING OUR PROFESSIONALISM

PROVING OUR PROFESSIONALISM PROVING OUR PROFESSIONALISM 49 TH ANNUAL CONFERENCE MAY 22-25, 2016 ORLANDO, FLORIDA DESIGN-BUILD 101 Joanne Flick, CPPO, CPPB TODAY S TOPICS Project Delivery Overview Comparing Project Delivery Methods

More information

PROJECT DELIVERY HANDBOOK

PROJECT DELIVERY HANDBOOK PROJECT DELIVERY HANDBOOK GuidetoCaliforniaSchooland CommunityCollege FacilityDelivery 2017 ThisversionincorporateschangesresultingfromlegislationincludingAB2316andSB693(2016). AssociationofCaliforniaConstructionManagersUpdatedJanuary17,2017

More information

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

A , Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum A101 2007, Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum AIA Document A101 2007 is a standard form of agreement between owner and contractor for

More information

FACILITIES CONFERENCE

FACILITIES CONFERENCE FACILITIES CONFERENCE April 24-26, 2013 Construction Manager at Risk Lessons Learned Minnesota State Colleges and Universities The Minnesota State Colleges and Universities system is an Equal Opportunity

More information

Rick Carr, Arcadis U.S., Inc. Tim O Malley, The O Malley Group Bill Brannen, Mohave Educational Services Cooperative

Rick Carr, Arcadis U.S., Inc. Tim O Malley, The O Malley Group Bill Brannen, Mohave Educational Services Cooperative Rick Carr, Arcadis U.S., Inc. Tim O Malley, The O Malley Group Bill Brannen, Mohave Educational Services Cooperative This presentation will cover: What is JOC? JOC contracting terms JOC experience Types

More information

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright Design Process 101 Michael Barnard, AIA, NCARB animalsheltering.org/expo #AnimalCareExpo Copyright 1 Design and Construction Process Needs Assessment Conceptual Design Schematic Design Design Development

More information

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES. For the renovation of existing apartment buildings. August 15, 2016

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES. For the renovation of existing apartment buildings. August 15, 2016 REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT SERVICES For the renovation of existing apartment buildings August 15, 2016 INVITATION Bath Housing Development Corporation is soliciting proposals for

More information

Design-Build Trifecta A joint presentation of DBIA WESTERN PACIFIC REGION

Design-Build Trifecta A joint presentation of DBIA WESTERN PACIFIC REGION Design-Build Trifecta A joint presentation of DBIA WESTERN PACIFIC REGION and AIA LOS ANGELES September 16, 2014 Design-Build Trifecta MODERATOR: SPEAKERS: Robert J, Hartung, Hon AIA, DBIA President, Alternative

More information

Document Synopses by Series

Document Synopses by Series Document Synopses by Series AIA Contract Documents are divided into six alphanumeric series by document use or purpose: A Series: Owner/Contractor Agreements B Series: Owner/Architect Agreements (p. 13)

More information

Construction Manager as Constructor (CMc) Manual

Construction Manager as Constructor (CMc) Manual Construction Manager as Constructor (CMc) Manual Manual Courtesy of Purdue University Presented By Table of Contents 1.0 Executive Summary 2.1 House Bill 1196 2.2 Analysis of House Bill 1196 and Requirements

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

AVIATION AUTHORITY POLICY

AVIATION AUTHORITY POLICY PURPOSE: To establish a policy for the selection of development related professional services firms, including design-build firms for professional services and the Consulting Engineer, pursuant to the

More information

WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES

WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES 1. Introduction WEST YELLOWSTONE SIEGEL LEARNING CENTER REQUEST FOR QUALIFICATIONS / PROPOSALS FOR CONSTRUCTION MANAGER AT RISK (CM-AR) SERVICES The Town of West Yellowstone (Town) is seeking a qualified

More information

ADDENDUM NO. 1. Date: January 11, for. RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College. BID No.

ADDENDUM NO. 1. Date: January 11, for. RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College. BID No. ADDENDUM NO. 1 Date: January 11, 2017 for RFQ for Design-Build Entity, Health Center/ Concession Project at Irvine Valley College BID No. 332 South Orange County Community College District General-All

More information

Pioneering Alternative Project Delivery in Ohio

Pioneering Alternative Project Delivery in Ohio Pioneering Alternative Project Delivery in Ohio Ali Bahar, PE Principal Engineer Metropolitan Sewer District of Greater Cincinnati Tim Koch, PE, Vice President, Brown and Caldwell 1 Agenda Construction

More information

REQUIREMENTS FOR PROCUREMENT BY THE COLORADO DEPARTMENT OF TRANSPORTATION OF DESIGN-BUILD CONTRACTS FOR TRANSPORTATION PROJECTS

REQUIREMENTS FOR PROCUREMENT BY THE COLORADO DEPARTMENT OF TRANSPORTATION OF DESIGN-BUILD CONTRACTS FOR TRANSPORTATION PROJECTS DEPARTMENT OF TRANSPORTATION Transportation Commission and Office of Transportation Safety REQUIREMENTS FOR PROCUREMENT BY THE COLORADO DEPARTMENT OF TRANSPORTATION OF DESIGN-BUILD CONTRACTS FOR TRANSPORTATION

More information

Progressive Design Build

Progressive Design Build Progressive Design Build July 19, 2018 Ash Dhingra P.E.,S.E TRADITIONAL PROCUREMENT Design-Bid-Build (DBB) Design to 100%, procurement (bid), and construction proceed sequentially Construction contract

More information

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013 Outline Alternative Delivery Options Oregon and Washington Legal Context Things an Owner Should

More information

LEVEL I PREQUALIFICATION DOCUMENTS

LEVEL I PREQUALIFICATION DOCUMENTS Project No. LEVEL I PREQUALIFICATION DOCUMENTS for MUIR BIOLOGY BUILDING 3RD FLOOR RENOVATION University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North Torrey Pines Road La Jolla,

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

AN OVERVIEW OF DESIGN-BUILD. Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014

AN OVERVIEW OF DESIGN-BUILD. Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014 AN OVERVIEW OF DESIGN-BUILD Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014 Design-Build Not a New Concept In California: Multiple statutes govern design-build

More information

Partnering for Alternative Delivery Projects

Partnering for Alternative Delivery Projects Partnering for Alternative Delivery Projects Presented by: Renee L. Hoekstra, CVS Managing Partner RHA, LLC Julie Kliewer, PhD, P.E. State Construction & Materials Engineer - ADOT Training Objectives Understanding

More information

Session THREE. Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: Self-directed (6 hours)

Session THREE. Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: Self-directed (6 hours) Session THREE Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: What type of tendering methods are there? What does qualification mean? Do you (the MC) bid for every job? Do you (the MC) price

More information

The Pros and Cons of Construction Delivery Methods Available to Community College Districts

The Pros and Cons of Construction Delivery Methods Available to Community College Districts The Pros and Cons of Construction Delivery Methods Available to Community College Districts Community College Facility Coalition 25 th Annual Conference September 11, 2018 Panel Alan Kroeker - Principal

More information

ALTERNATE FORMS OF PROJECT DELIVERY

ALTERNATE FORMS OF PROJECT DELIVERY ALTERNATE FORMS OF PROJECT DELIVERY 1 INTRODUCTION 1.1 BACKGROUND.1 In the building industry today, conventional methods of project delivery are being challenged by Clients, Consultants and Contractors

More information

Qualifications Based Selection of Contractors

Qualifications Based Selection of Contractors Qualifications Based Selection of Contractors AGC of America Project Delivery Committee QBS Working Group 1 Table of Contents QBS & The Industry: An Introduction Pages 3-4 Selection Criteria for QBS Page

More information

Figures, Examples and Lists

Figures, Examples and Lists Figures, Examples and Lists p. xiii Introduction p. xix The Fundamentals of the Root Form of CM (ACM) p. 1 The Six Essential Service Elements p. 1 Assignment of Responsibilities p. 2 Contracting Structures

More information

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build

Sounds good. What could possibly go wrong? 5/6/2014. Potential Benefits of Design Build. Potential Downsides of Design Build When Design Build Goes Wrong: Worst Practices to Avoid DBIA Edition for the O.N.E. Conference Blue Springs MO May 8, 2014 Dale Munhall, AIA Sounds good. What could possibly go wrong? Potential Benefits

More information

Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects

Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects Best Practices for Exceeding Project Goals and Reducing Risk on Construction Projects Presented by: Robyn Minter Smyers Alan S. Ritchie Heather A. Bartzi Erin Luke Presentation Team Robyn Minter Smyers

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION

ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION ADVERTISEMENT FOR DESIGN BUILDER PREQUALIFICATION Subject to conditions prescribed by the University of California, San Diego, responses to the University's prequalification documents for a Design Build

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

ICOC Procurement Briefing

ICOC Procurement Briefing ICOC Procurement Briefing How we acquire goods and services Overview Procurement of Professional Services Engineering, architecture, design build, construction manager Projects < $2 million use continuing

More information

1/12/2015. Collaborative IPD-ish Project Delivery using Design-Build, P3 or CM at-risk: the Einstein Approach

1/12/2015. Collaborative IPD-ish Project Delivery using Design-Build, P3 or CM at-risk: the Einstein Approach Collaborative IPD-ish Project Delivery using Design-Build, P3 or CM at-risk: the Einstein Approach DRAFT for AIA CCA Knowledge Community 2015 Dale Munhall, AIA not a sign of teamwork Director of Construction

More information

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement

Township of Severn REQUEST FOR PROPOSAL. Architectural & Professional Services Fire Station Replacement Township of Severn REQUEST FOR PROPOSAL Architectural & Professional Services Fire Station Replacement Deadline for proposal submission is June 15, 2017 at 2:00 p.m. Contact Person: Tim Cranney Director

More information

REQUEST FOR COMPETITIVE PROPOSALS FOR ARCHITECTURAL SERVICES CITY OF PERRIS

REQUEST FOR COMPETITIVE PROPOSALS FOR ARCHITECTURAL SERVICES CITY OF PERRIS REQUEST FOR COMPETITIVE PROPOSALS FOR ARCHITECTURAL SERVICES BY CITY OF PERRIS Perris, California December 4 th, 2018 City of Perris is requesting Competitive Proposals from licensed architectural firms

More information

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices

Seattle Public Schools Office of Internal Audit. Internal Audit Report Construction Management Practices Seattle Public Schools Office of Internal Audit Issue Date: December 5, 2017 Introduction and Background In accordance with the fiscal year 2018 capital audit plan, we have completed an audit of the district

More information

Choosing Delivery Method

Choosing Delivery Method Page 1 of 12 Advancing Professional Construction and Program Management Worldwide home contact us site map Search Find-A-CM/PM My Account Sign In Bookstore Career Center Home Choosing Delivery Method Choosing

More information

Construction 101. C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center

Construction 101. C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center Construction 101 C.A.S.H. 36 th Annual Conference February 23-25, 2015 Sacramento Convention Center This training is provided for educational, compliance and loss-prevention purposes only and, absent the

More information

A Primer Indianapolis, Indiana June 16, 2010

A Primer Indianapolis, Indiana June 16, 2010 Alternative Project Delivery Methods A Primer Indianapolis, Indiana June 16, 2010 Michael Kenig, Holder Construction Company, Past chair of AGC of America s s Project Delivery Committee Jayne O Donnell,

More information

JOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference

JOB ORDER CONTRACTING. United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference JOB ORDER CONTRACTING United Brotherhood of Carpenters and Joiners Interior-Exterior Systems Leadership Conference March, 2015 AGENDA Who is the Gordian Group Introduction to Job Order Contracting Explanation

More information

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications

More information

AIA Contract Documents

AIA Contract Documents AIA Contract Documents Contract Relationship Diagrams April 2017 Conventional (A201) Design-Bid-Build For use when the s project is divided into separate contracts for design () and construction (Contractor).

More information

LEVEL I PREQUALIFICATION DOCUMENTS OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA

LEVEL I PREQUALIFICATION DOCUMENTS OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA Project No. 4484/A4L-379/964840 LEVEL I PREQUALIFICATION DOCUMENTS for OUTPATIENT PAVILION UCSD MEDICAL CENTER LA JOLLA University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North

More information

DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD

DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD OWNER OWNER OWNER DESIGNER GC DESIGNER DESIGN CONSULTANTS TRADE SUBS DESIGN CONSULTANTS TRADE SUBS DESIGN CONSULTANTS TRADE SUBS DESIGN-BID-BUILD CONSTRUCTION MANAGER AT RISK DESIGN-BUILD Contracts Communications

More information

REQUEST FOR QUALIFICATIONS AND PROPOSALS

REQUEST FOR QUALIFICATIONS AND PROPOSALS REQUEST FOR QUALIFICATIONS AND PROPOSALS CONSTRUCTION MANAGER AT RISK SERVICES Preconstruction Phase Services and Construction Phase Services Sheridan Economic and Educational Development Authority Sheridan

More information

LEVEL I PREQUALIFICATION DOCUMENTS GEISEL RESTROOM RENOVATIONS

LEVEL I PREQUALIFICATION DOCUMENTS GEISEL RESTROOM RENOVATIONS Project No. 5005/A4L-424/ 962520 LEVEL I PREQUALIFICATION DOCUMENTS for GEISEL RESTROOM RENOVATIONS University of California, San Diego FACILITIES DESIGN & CONSTRUCTION 10280 North Torrey Pines Road La

More information

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II El Paso, Texas EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL for the BUILDING CONCRETE GLASS AND GLAZING FIRE SPRINKLER MECHANICAL

More information

REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS

REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS REQUEST FOR PROPOSALS (RFP) FOR ARCHITECTURAL SERVICES CLEARWATER PUBLIC SCHOOLS EWING PUBLIC SCHOOLS NELIGH-OAKDALE PUBLIC SCHOOLS 1. REQUEST FOR PROPOSALS. Clearwater Public Schools, Ewing Public Schools,

More information

WATERTOWN ELEMENTARY SCHOOLS SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018

WATERTOWN ELEMENTARY SCHOOLS SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018 SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018 Types of Public Construction Delivery Methods Available: Design-Bid-Build (DBB) under M.G.L Ch. 149 Overview Pros Cons Construction Management at Risk

More information

DOCUMENT PROPOSAL FORM (Modified)

DOCUMENT PROPOSAL FORM (Modified) To be submitted by the time and date specified in Document RFI 01 (Request for Information), paragraph 5. TO THE HONORABLE BOARD OF TRUSTEES OF THE EAST SIDE UNION HIGH SCHOOL DISTRICT: THIS MODIFIED PROPOSAL

More information

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA PROGRESSIVE DESIGN-BUILD Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA ADVANTAGES/DISADVANTAGES DESIGN BID BUILD (HARD BID) The traditional project delivery method, which customarily

More information

Job Order Contracting (JOC) ITB JE Overview August 2016

Job Order Contracting (JOC) ITB JE Overview August 2016 Job Order Contracting (JOC) ITB 16-14204-JE Overview August 2016 Job Order Contracting (JOC) What is JOC? Using general and specialty trade contractors to perform a series of projects on an as-needed basis.

More information

School Construction: Contract Basics OSBA BONDS, BALLOTS AND BUILDINGS CONFERENCE FEBRUARY 09, 2018

School Construction: Contract Basics OSBA BONDS, BALLOTS AND BUILDINGS CONFERENCE FEBRUARY 09, 2018 School Construction: Contract Basics OSBA BONDS, BALLOTS AND BUILDINGS CONFERENCE FEBRUARY 09, 2018 Who we are Presenters Rob Wilkinson, Partner, Ball Janik LLP Scott Rogers, CPPB, Senior Project Manager,

More information

CONSTRUCTION CONTRACTING GUIDELINES Revised January 2017 I. GENERAL REQUIREMENTS AND PROCEDURES

CONSTRUCTION CONTRACTING GUIDELINES Revised January 2017 I. GENERAL REQUIREMENTS AND PROCEDURES THE UNIVERSITY OF TEXAS SYSTEM OFFICE OF GENERAL COUNSEL CONSTRUCTION CONTRACTING GUIDELINES Revised January 2017 The Rules and Regulations of the Board of Regents of The University of Texas System for

More information

UNIVERSITY OF CALIFORNIA, SAN DIEGO

UNIVERSITY OF CALIFORNIA, SAN DIEGO BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANT A BARBARA SANT A CRUZ OFFICE OF THE ASSOCIATE VICE CHANCELLOR CAPITAL PROGRAM MANAGEMENT TEL: (858) 534-2177 FAX: (858) 534-4363

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

Progressive Design-Build Discussion

Progressive Design-Build Discussion Presentation for: Progressive Discussion February 4, 2011 1 Project Delivery Options Design-Bid-Build Construction Management at Risk Lump Sum Progressive DESIGNER BUILDER DESIGNER CM TRADITIONAL DELIVERY

More information

EJCDC Contract Documents for America s Infrastructure Buy online at

EJCDC Contract Documents for America s Infrastructure Buy online at EJCDC Contract Documents for America s Infrastructure Buy online at www.booksforengineers.com N-122 Uniform Location of Subject Matter (2012) Published jointly with AIA and CSI. FREE DOWNLOAD Construction

More information

Committee Meeting. Procurement Processes for Professional Services and Contractors

Committee Meeting. Procurement Processes for Professional Services and Contractors Citizen s i Oversight Committee Meeting Procurement Processes for Professional Services and Contractors March 2, 2011 1 Procurement Process for Professional Services 2 Procurement Process for Professional

More information

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements

You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements You Passed Your Bond Now What? a Part 3: Multi-Prime and Design-Build Project Delivery Methods and Project Labor Agreements January 25, 2017 Presented By: Deidree Sakai Cameron Ward SAN FRANCISCO LONG

More information

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue

Bidding Conditions. March 22, (Project# 0192) at the. Fresno Chaffee Zoo. Project : Warthog Exhibit. Located at. 894 West Belmont Avenue Bidding Conditions March 22, 2018 (Project# 0192) at the Fresno Chaffee Zoo Project : Warthog Exhibit Located at 894 West Belmont Avenue Fresno, CA 93728 Page 1 of 8 DEFINITIONS Addendum - A document issued

More information

Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION

Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION Request for Proposals for: Construction Management Services For The ADDISON PUBLIC LIBRARY INTERIOR RENOVATION May 19, 2015 The Addison Public Library invites you to submit a reply to this Request for

More information

Understanding NC House Bill 857 Design Build and Public-Private Partnerships

Understanding NC House Bill 857 Design Build and Public-Private Partnerships Understanding NC House Bill 857 Design Build and Public-Private Partnerships Ted Edwards 434 Fayetteville Street, Suite 2800 Raleigh, NC 27601 T: 919.755.8764 E: ted.edwards@smithmoorelaw.com Elements

More information

making jump H E By S. S. Saucerman Official Publication of AWCI 25

making jump H E By S. S. Saucerman Official Publication of AWCI 25 making T jump H E By S. S. Saucerman Owners of wall and ceiling construction companies make scores of decisions every day, but none so pivotal as whether or not to expand their (historically) residential

More information

ADDENDUM #2. Design/Build Contractor RFP Bid # for the. Joint-Use 21 st Century Post-Century Education Center.

ADDENDUM #2. Design/Build Contractor RFP Bid # for the. Joint-Use 21 st Century Post-Century Education Center. ADDENDUM #2 Design/Build Contractor RFP Bid #0606-14 for the Joint-Use 21 st Century Post-Century Education Center SJECCD California July 7, 2014 SAN JOSE EVERGREEN COMMUNITY COLLEGE DISTRICT 4750 San

More information

A D D E N D U M. REPLACE: Project Summary with attached revised Project Summary. 1 Specification Section Project Summary

A D D E N D U M. REPLACE: Project Summary with attached revised Project Summary. 1 Specification Section Project Summary A D D E N D U M 1 TO All Plan Holders ISSUE DATE 20 January 2017 PROJECT # 15-028 REGARDING Switchgear Replacement NARRATIVE PAGES 1 15-02812 KVa Switchgear Replacement Project SPECIFICATION PAGES 10 DRAWING

More information

Design and Content 2006 PSFEI.

Design and Content 2006 PSFEI. Guaranteed Energy Performance Contracting and The Pennsylvania Guaranteed Energy Savings Act TOPICS 1. What is a Project Delivery System? 2. Comparison of two types of Project Delivery Systems 3. Guaranteed

More information

PUBLIC CONTRACT CODE SECTION

PUBLIC CONTRACT CODE SECTION PUBLIC CONTRACT CODE SECTION 22160 22169 22160. (a) The Legislature finds and declares that the design build method of project delivery, using a best value procurement methodology, has been authorized

More information

Request for Proposal for Construction Management Services

Request for Proposal for Construction Management Services Request for Proposal for Construction Management Services Sauk Rapid-Rice Public Schools is soliciting Construction Management (CM) proposals for safety and security projects to be completed at each of

More information

Lake County School District s. Construction Audit for. Eustis Heights Elementary School. Executive Summary & Detailed Audit Report

Lake County School District s. Construction Audit for. Eustis Heights Elementary School. Executive Summary & Detailed Audit Report 1 Lake County School District s Construction Audit for Eustis Heights Elementary School Executive Summary & Detailed Audit Report Fiscal Year 2014 2015 Completed By: Thomas A. Mock, CIA Date: August 27,

More information

Professional Practice 544

Professional Practice 544 Spring Semester 2017 Professional Practice 544 Michael J. Hanahan Partner Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com Schiff Hardin LLP. All rights

More information

As a state agency, the College administration is required to develop procedures for Construction Manager selection.

As a state agency, the College administration is required to develop procedures for Construction Manager selection. COLLEGE of CENTRAL FLORIDA ADMINISTRATIVE PROCEDURE Title: Construction Management Selection Process Page 1 of 2 Implementing Procedure For F.S. 1013.45 Date Approved: 09/11/02 Division: Administration

More information

PURCHASING PROCEDURES: District Policies

PURCHASING PROCEDURES: District Policies PURCHASING PROCEDURES: District Policies 720 Selecting Professional Services 721 Purchasing Policies and Bidding 722 Bid Protest Resolution 723 School Construction and Facilities Operations Bid 724 Protest

More information

Professional Practice 544

Professional Practice 544 Spring Semester 2018 Professional Practice 544 Michael J. Hanahan Partner Schiff Hardin LLP 233 S. Wacker, Ste. 6600 Chicago, IL 60606 312-258-5701 mhanahan@schiffhardin.com Schiff Hardin LLP. All rights

More information

Architectural Services Consultant Exhibit A Scope of Services

Architectural Services Consultant Exhibit A Scope of Services Architectural Services Consultant Exhibit A Scope of Services I. Purpose The services to be provided under this Agreement will include a wide range of Architectural / Engineering services, including but

More information

ConsensusDocs. Catalog. Updated Docs Inside

ConsensusDocs. Catalog. Updated Docs Inside ConsensusDocs ConsensusDocs Contracts Catalog Updated Docs Inside ConsensusDocs Keeping You Ahead of the Cur ve ConsensusDocs... Building A Better Way! Whether working at the office, from the road or even

More information