1 TO: All Potential Respondents RFB 1414 River Tower Shoreline Restoration and Water Quality Improvement Project FROM: Anita Hoover, Procurement Specialist 3 SUBJECT: QUESTION 1: QUESTION 2: Response to Questions Request the consultant prepare an additional drawing showing the required City tree barricade locations. The District is providing Figure B, Tree Barricade Location Map, which shows the tree barricade and potential root pruning and tree trimming locations as coordinated with the City of Tampa construction inspection personnel. Figure B is attached to Addendum 3. Request the consultant show trees to be removed on the plans? The trees to be removed per plan requirements are the four palms trees to be relocated as shown near the storm outfall to the river on Sheet 4, PAVING, GRADING AND DRAINAGE PLANS (2). Palm tree planting relocation area is shown on Sheet 31, PLANTING PLAN. There are four additional palm trees to be removed near the fence in the northeast corner of the park where the 72 storm pipe alignment enters the park site, shown in Figure B. These trees will be relocated to the same area for replanting as the other trees shown on the plans. QUESTION 3: QUESTION 4: Please provide City of Tampa s Landscape Ordinance more specifically regarding tree barricades. Figure C, Tree Barricade Detail, and Figure D City of Tampa Tree Ordinance are attached to Addendum No.3. During the Site Visit, Ms. Laurie Potier-Brown with the City of Tampa s Parks and Recreation Department, requested an existing conditions plan be provided to better reflect trees that will be impacted by construction, in order to better quantify how much tree barricade material will be needed. The estimated quantity of 170 LF on the bid form is low and Ms. Brown feels there should be more. The tree barricade quantity has been revised on the bid response form based on the information provided in Figure B.

2 Page 2 of 9 QUESTION 5: Reference specifications Section 01005, GENERAL REQUIREMENTS, page , par. E., Tree Relocation, there are four (4) cabbage palm trees to be relocated on site, but there is no bid item for this scope of work and no mention of what means to be taken to ensure their survival, please review. Any tree to be removed even if shown on the Plans still needs to go through City of Tampa Permit process. Sabal palms to be transplanted will be promptly prepared and transplanted to the approved on site location in the following manner: Palms will be extracted by excavator or other earth cutting equipment and lifted by straps or cushioned chains in such a manner as to avoid scarring the trunk. Frond boots do not need to be trimmed or removed. Roots will be cut to a confining root ball by a sharpened shovel or alternate cutting tool. All green fronds, except for the single emerging spear, will be cleanly cut with a hand saw or branch lopper shears. This specification should be amended to reflect Section Tree Transplanting, provided by the City of Tampa. Palm will be replanted in the approved location and supported with three 2 X4 bracing supports. Bracing supports will be constructed as to not scar the trunk. Braces to be removed after one growing season. Each palm will be watered with a minimum of 30 gallons of water. Additional dirt backfill will be provided following the initial watering if needed. A second watering of 30 gallons will be provided within 7 days. This is insufficient for establishment, refer watering specifications provided by City of Tampa. There will be no guarantee required for transplanted palms that are correctly planted and expire. QUESTION 6: During the Site Visit, the issue of cordoning off the buffer area around the Sulphur Springs Tower was raised, please confirm that the buffer area around the Tower is to be cordoned off and with what type of material. The City of Tampa has indicated that the buffer around the water tower as well as trees near the work area have to be protected in accordance with the City of Tampa tree barricade detail which has been provided in Addendum No. 3. Figure C. Figure B showing the approximate location of required tree barricades, has also been provided in Addendum No. 3. QUESTION 7: Plans do not show physical barrier around the tower suggest we add sufficient wooden tree barricade-type material, +/- 400 LF. See response to Question No. 1. QUESTION 8: Trees to be removed should be shown on Plans and X ed out. Grand Trees should be shown with suggested protection.

3 Page 3 of 9 QUESTION 9: QUESTION 10: There are four palm trees along the 72 storm pipe and maintenance access drive that will be removed or relocated. There are four palms along the storm outfall near the river top of bank that will be relocated. See response to Question No. 1. There are several large oaks and a large pine tree near some of the work areas, which are shown in Figure B. Treatment and identification of Grand Trees should follow Chapter 13 of the City of Tampa Land Development Code. What is the process to obtain the City Clearing permit? Sequence of Major Activities; install all erosion control devices and tree protection, tower protection and request inspection. The Site Clearing application needs to be made at 1400 N. Blvd. Once application made, inspection for compliance with stated activities will be made and permit issued to commence. Sheet 3, note 1 states this work may overlap with FDOT I-275 Rehab. Is this still a concern? The microtunnel equipment has tight availability schedules and high delay cost such that I don t think schedule accommodation is a simple matter. No. QUESTION 11: The Paving, Grading drawings show some work as by others, such as the Deltalok at the 72 MES at the river on sheet 5. This is the Interlocking Geo System. The specifications also specify Deltalok or equal. The CAD shows these retaining walls as Envirolock. Is Envirolock an approved equal? QUESTION 12: QUESTION 13: QUESTION 14: Envirolok is not an approved equivalent at this time. Would you please publish the milestone schedule dates required for the work? Proposed start, substantial completion, final completion. Isn t the overall duration to be 10 months? The overall duration for construction is twelve (12) months. The time period from Notice to Proceed to Substantial Completion for all work is ten (10) months. The time period from Substantial Completion for all work to Final Acceptance of all work is two (2) months. The Contractor can schedule work along the river bank, within the park, and within the Bird Street right of way to best accomplish the work per the plans, specifications and his workforces. The CAD file of proposed conditions does not include the finished grade spot between the recreation trail and the east-west silt fence by the new bollards. The bottom of the swale is there, though. Can you issue the CAD with these spot elevations included? Or are they not part of the design? An additional CAD zip file has been loaded to the District s FTP website regarding the grading plan with spot elevations. The CAD file is titled RIVER_TOWER_ACAD.zip. Are there any Category 1 and 2 nuisance species to be removed from along the river bank? If so, what methodology is acceptable (cut, and stump treated, etc.)?

4 Page 4 of 9 There are Category 1 and 2 nuisance species existing on the river bank; these are to be controlled following the guidelines contained in the following documents (or latest edition): Control of Non-Native Plants in Natural Areas of Florida, K. A. Langeland and R. K. Stocker, Florida Cooperative Extensions Services, Institute of Food and Agricultural Sciences, University of Florida. Florida Pesticides Laws and Rules, Chapter 487, Florida Statutes, Florida Department of Agriculture and Consumer Services, June The principal species of concern is Brazilian pepper (Schinus terebinthifolius) which should be controlled by removal of the above ground biomass (stump cutting) and subsequent treatment of the stump with the approved herbicide. During exotic vegetation removal, care should be taken to avoid damage to existing native tree species. Due to the large trees along the riverbank, all protected and grand trees shall receive a 3 layer of Large Pine Bark mulch and a layer of plywood (3/4 thick) within a 10 diameter distance. No heavy machinery shall be used with the 10 distance. All digging shall be accomplished with hand tools. QUESTION 15: For the Concrete Spillway detailed on sheet 6. There are references to FDOT Index 281 which is for ditch paving, ditch paving is typically 3 or 4 with welded wire on fabric. This is calling for 6 with #5 rebar reinforcing. Does the owner want weepholes as per the FDOT Index 281? The weepholes are not required for the concrete spillway. QUESTION 16: The call out for the rip rap on the plans references the FDOT Index 281. It s understood that the install and rip rap will follow the 281 Index. Will the rip rap have to be FDOT certified. There is a considerable price difference between rip rap that follows FDOT specifications and FDOT certified rip rap. Please clarify. QUESTION 17: The riprap is not required to be FDOT certified. On the Work Category Specific Qualifications forms for the Microtunneling and Asphalt Paving/Road Construction it asks for experience in maintenance of traffic. Maintenance of traffic is usually the responsibility of the prime contractor. Will the subcontractors for the asphalt work and microtunneling be held to furnishing references pertaining to MOT? Please clarify. Addendum No. 2 provided revised Contractor or subcontractor experience reference sheets that delete the maintenance of traffic from the microtunneling contractor experience and allow the prime contractor to provide this service with its personnel or a separate subcontractor. QUESTION 18: The Paving, Grading drawings show some work as by others, such as the Deltalok at the 72 MES at the river on sheet 5. This is the Interlocking Geo System. The specifications also specifies Deltalok or equal. The CAD shows these retaining walls as Envirolock. Is Envirolock an approved equal? (32) Envirolok is not an approved equivalent at this time.

5 Page 5 of 9 QUESTION 19: In the Technical Specifications, section 13567, Temporary Bypass Pumping Provisions, Part 1, section 1.01, paragraph A, it states that The contractor shall design, furnish, install, startup, operate, maintain, and coordinate continuous bypass pumping facilities such that the work identified on the drawings and in the specifications for can be conducted. From what is depicted on the plans it appears that bypass pumping will have to occur where proposed structure S1 is connecting to the existing 78 RCP and where the existing 24 RCP ties into proposed structure S2. In order for the contractor to design, furnish, install, startup, operate, maintain, and coordinate continuous bypass pumping facilities for the work identified on the drawings there needs to be more information provided to design a proficient bypass system that meets this specification. What are the upstream facilities and conditions for what has to be bypassed? What are the flow rates through the pipe at peak conditions? The 78 RCP is a storm sewer trunk line that conveys approximately 700 acres of runoff through it. Based on the drainage modeling that was used for permitting, the peak flows for the mean annual, 25yr/24hr, and 100yr/24hr events are: Mean Annual (2.33yr/24hr): 270 cubic feet per second (cfs) 25yr/24hr: 390 cfs 100yr/24hr: 420 cfs The referenced 24 line that ties into structure S2 accepts approximately 15 acres. The flows associated with this line, based on the permitted drainage modeling are: Mean Annual (2.33yr/24hr): 27 cfs 25yr/24hr: 50 cfs 100yr/24hr: 65 cfs QUESTION 20: QUESTION 21: QUESTION 22: Can information be provided from the FDOT on the year the 78 RCP was installed, who the manufacturer of the pipe was and the length of the joints that were installed? The pipe was constructed with I-275 (formerly I-75) in Additional information is attached as Figure E SiteScope Report. Sheet 19 of the Traffic Control Plan drawings indicates a buffer area on E Bird Street west of the work zone, may this be used as an equipment/materials staging area as well as the indicated work zone? The buffer area must be free of all equipment and materials. The mast arm at the northwest corner of Bird St. and Lamar Ave. is in conflict with the location of the receiving shaft for the microtunnel, being close to traffic signal arm which prevents and/or greatly restricts the use of a crane safely. The current MOT plan does not address this issue. What is the plan to temporarily relocate the traffic signal at this location? The MOT plan included in the construction plans provides one approved method whereby the contractor can maintain traffic during construction. The use of temporary portable traffic signals would be an acceptable adjustment. The Engineer is willing to accommodate the minor revisions for this approach. The contractor may elect to develop an alternative plan that better serves their means and methods of construction. An

6 Page 6 of 9 alternative MOT plan would require the contractor to provide signed and sealed drawings to the appropriate agency and Engineer of Record for approval prior to implementation. QUESTION 23: QUESTION 24: QUESTION 25: QUESTION 26: Will an air test on the installed microtunnled RCP per FDOT be performed? Will a 13 psi (not 20 psi) pressure test be allowed for RCP? Gasketed RCP is designed and tested to 13 psi per ASTM C443. Standard RCP joints are not design to 20 psi. An individual joint test per ASTM C1103 may be more appropriate and safer. Based on coordination with FDOT, the inspection of the 72 pipe via visual inspection can performed in lieu of a pressure test. Class V RCP for a 12 deep micro-tunnel installation is well over designed. The circumferential steel required to carry live and dead loads at 12 depth for microtunnel installation is far less than class V. Only higher concrete strength to resist axial (jacking) forces is necessary specify 5,000 psi. Will the pipe manufacturer be allowed submit a more appropriate design? The 72 pipe must meet the minimum requirements of FDOT Section As specified in Section (b) the pipe may be Class III, IV, or V as required by load calculations, with a C-wall. The pipe manufacturer may substitute an alternative design. The contractor shall submit signed and sealed load calculations for the chosen pipe. A shop drawing submittal will be required for Engineer of Record approval. At the locations where the GEO-Modular Bag System is to be installed will the contractor be able to clear along the shoreline where installation is to be done to have access or does installation have to be done from the river side? Please clarify. The areas that will receive the Geo-Modular Bag System have been chosen with access from the land side in mind. There is either existing space between the native trees or locations where exotic vegetation is to be removed. Due to the large trees along the riverbank, all protected and grand trees are to remain and shall receive a 3 layer of Large Pine Bark mulch and a layer of plywood (3/4 thick) within a 10 diameter distance. No heavy machinery shall be used with the 10 distance. All digging shall be accomplished with hand tools. Where the 15 RCP gets installed from the existing inlet on Florida Ave. to the miter end section in the proposed retention area at the southeast corner of the project site, the existing grand oak tree will have to be trimmed to allow for the installation of the MES and to be able to do the required grading, as the branches are hanging and actually touching the ground at this location. A visit to the site and the aerial view on plan sheet 30 confirms this. Will the contractor be allowed to trim back the needed branches to enable this work to be performed? Please clarify. A permit will be required for trimming Grand Trees and any trimming must be performed by a certified arborist. Please refer to Chapter 13 of the City of Tampa Land Development Code for permitting requirements. QUESTION 27: In the Technical Specifications, section Pond Planting, sub-section 3.05 Maintenance, paragraph C, it states that Contractor shall supply and install signs posted a minimum of every 100 feet around the perimeter of all ponds stating Stormwater Treatment Pond No mowing or spraying of aquatic vegetation

7 Page 7 of 9 allowed unless authorized by FDEP. Call 813/ for more information. Signage shall be in accordance with specification and section Section pertains to the project identification sign and in section 2.01 Sign Materials, paragraph B of that section it states that Sign Surfaces 4 x 8 heavy duty 10mm colorplast. Does the District actually want 4 x 8 Stormwater Treatment Signs around the ponds? Please clarify and or provide size and template for said Stormwater Treatment Pond Signs. QUESTION 28: QUESTION 29: QUESTION 30: The signage size is not correct. A 12 X12 green sign with cream letters with the City of Tampa Parks & Recreation Department logo shall be created and installed low to the ground, about 24 to top of sign is desired. Along with signage please add short stakes with ribbon flagging to outline the new plantings until growth is established. Signs will be placed every 100 around the perimeter of the pond as stated in the specifications. On plan sheet 9, under the Proposed Pavement Section it calls out for Optional Base Group (O.B.G.) 8. On the bid form, bid item 53 has a description calling out for Optional Base Group 9. Please clarify what O.B.G. that is to be used for the proposed pavement section. Bid item 53 should be changed from OBG 9 to OBG 8 on the Bid Form. On plan sheet 3 at the construction entrance where the plans call out to install the Soil Tracking Prevention Device. Once the project is complete and the Soil Tracking Prevention Device is removed, will the new 12 Asphalt Maintenance Access Trail continue to the back of the concrete driveway? Please clarify. Yes. The Asphalt Maintenance Access Trail will continue to the back of the concrete driveway. I don t see on the plans any work taking place on the existing park entrance other than the removal of existing pavement at the south end and the installation of the wood bollards. Can clarification be made to the effect that no work is to take place on the remaining existing park entrance and will be left in the condition that it currently is in? No work will be completed on the northern portion of the existing driveway entrance. That portion of the entrance is to be left in its current condition or better. QUESTION 31: In the Technical Specifications, Section Temporary Bypass Pumping Provisions, Part 2 Bypass Pumping Systems, Sub-section 2.02 Capacity, paragraph A, it states The capacity of the bypass pumping system is described in Section When you go to Sub-Section 1.01 of Section 13567, I don t see anything covering the capacity of what the bypass pumping has to pump. Please provide the capacity of what the proposed bypass system will have to facilitate. See response to Question 19. QUESTION 32: Sheet 2: The COT root pruning standards need to be followed. Please add the following specification to the plan set. Root pruning should be shown, notes mention tunneling under root systems.

8 Page 8 of 9 Root Prune Specification Root Pruning may be necessary where there are existing trees according to the plans and notes, or documented in Figure B of Addendum #3. The Contractor is to verify site conditions and scope of work prior to submitting their bid. Root pruning shall be done by a certified, qualified arborist using a Dosko Root Pruner or the equivalent piece of machinery. The Contractor is to obtain approval from City of Tampa Project Manager for equivalent piece of machinery prior to conducting root pruning. Roots shall be cut even and smooth with soil and rootball intact beginning one inch offset from back of curb and continuing parallel to a depth not to exceed approximately nine inches. Following construction activity, the qualified arborist shall drench the perimeter of the rootball(s) with an approved systemic fungicide and root inducing hormone e.g. IBA. QUESTION 33: In the RFB under General Conditions, section 2.2 Terms. In the first sentence it states, The agreement will be effective upon execution by both parties and will remain in effect for eighteen months. But in the last sentence in this section it states The time period from the Notice to Proceed (NTP) to Substantial Completion shall be no more than ten (10) months. Final Completion shall be no more than two (2) months from Substantial Completion. The two sentences seem to contradict each other. What will be the actual term of the contract before liquidated damages go into effect? Please clarify. The additional six months of time added to the term beyond the expected total 12 months for project completion are included to avoid the need to amend the agreement in the event unforeseen circumstances, especially weather related issues, delaying the work from being completed within 12 months. The bidder s progress schedule is expected to be for a total of ten (10) months from NTP to Substantial Completion with an additional two (2) months for Final Completion. Liquidated damages could be assessed if the contractor delays the completion of the project without justifiable, documented and approved reasons. Section 2.22 in the RFB Specification provides information regarding the assessment of liquidated damages QUESTION 34: There is a call out on the plans to install dia. rip rap 24 thick at the 72 FES and there is a call out for 8 12 dia. Rip rap 18 thick at the spillway outfall and at the south east corner of the pond. There are two different types of rip rap but only one bid item for the rip rap. This bid item needs to be broke up into the two different sizes and provide a quantity for each, as the price to purchase for the two are different. QUESTION 35: The Bid Response Form, Attachment 1 to the RFB Specifications has been revised to account for the different sized riprap. Line number 33 on the Revised Bid Response Form was changed to 440 ton for the diameter (24 thick blanket) riprap and line number 63 was added for 720 ton for the 8-12 diameter (18 thick blanket) riprap. The Revised Bid Response Form is attached to Addendum 3. Please provide a detailed drawing with dimensions of the bridge support/footers in order to determine the exact locations, elevations and distance from the planned microtunnel.

9 Page 9 of 9 Drawings for the adjacent I-275 project that were provided by FDOT. These drawings are labeled Figure F and titled FDOT_Drawings. Figure F has been loaded to the District s FTP site.

Tree Protection Policy

Tree Protection Policy Appendix F Tree Protection Policy The following is according to the City of Hamilton s special provision SP-97. General Tree Protection shall be in accordance with OPSS 801 as amended by this special provision.

More information

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following: CONSTRUCTION SURVEY PART 1 - GENERAL 1.01 SECTION INCLUDES Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following: A. Construction Survey: 1. Project

More information

DUKE UNIVERSITY DESIGN GUIDELINES

DUKE UNIVERSITY DESIGN GUIDELINES 1 Tree Protection Zones (TPZs) 1. Introduction A. Tree Protection Zones shall be established around all trees not slated for removal which are located within the construction envelope, or located within

More information

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587

CITY OF TROY CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 CITY OF TROY DESIGN STANDARDS AND CONSTRUCTION SPECIFICATIONS PREPARED BY: F-7587 JANUARY 2010 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 APPENDIX ROADWAY DESIGN DRAINAGE

More information

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012 PART FIVE DOCUMENTS FOR SITE AND INFRASTRUCTURE 31 00 00. EARTHWORK 31 10 00. SITE CLEARING.1 STRUCTURE REMOVAL: Include

More information

TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES

TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES TREE PRESERVATION AND PROTECTION SPECIFICATION FOR CONSTRUCTION NEAR TREES PART I GENERAL 1.02 The objective of this section is to reduce the negative impacts of construction on trees. Tree protection

More information

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000 610S.1 This item shall govern the proper care and treatment of all trees and other vegetation

More information

B. The purpose of the meeting shall be to establish the conditions of all existing trees upon receipt of the Project site by the Contractor. Failure t

B. The purpose of the meeting shall be to establish the conditions of all existing trees upon receipt of the Project site by the Contractor. Failure t Standard Specification SECTION 01 56 39 TREE AND PLANT PROTECTION PART 1 - GENERAL 1.1 WORK INCLUDED A. Perform all Work necessary and required to protect and maintain all trees, shrubs, groundcover and

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

Project Type: Drainage and Storm Systems

Project Type: Drainage and Storm Systems 580 Dakin Avenue Box Culvert & Utility Improvements Project $944,952 Improvements to approx. 3,000 lf of existing 4'x5' concrete box culvert; clean interior, patch surface, fill joints/cracks; install

More information

UTILITY NOTES GENERAL CONSTRUCTION NOTES PAVING AND GRADING NOTES: TREE PROTECTION NOTES

UTILITY NOTES GENERAL CONSTRUCTION NOTES PAVING AND GRADING NOTES: TREE PROTECTION NOTES GENERAL CONSTRUCTION NOTES PAVING AND GRADING NOTES: UTILITY NOTES PROPOSED LEGEND 66.50 66.50 GROUND SPOT ELEVATION GROUND SPOT ELEVATION (MATCH EXISTING GRADE) MATCH EXISTING GRADE MITERED END SECTION

More information

10:00 AM, Wednesday, April 8, 2015

10:00 AM, Wednesday, April 8, 2015 NOTICE OF MANDATORY PRE-BID CONFERENCE WILL BE HELD AT 10:00 AM, Wednesday, April 8, 2015 IN ROOM 16, CITY HALL BUILDING, 101 NORTH MAIN STREET WINSTON-SALEM, NORTH CAROLINA The purpose of this conference

More information

SECTION TRENCHING & BACKFILLING

SECTION TRENCHING & BACKFILLING SECTION 02225 - TRENCHING & BACKFILLING 1.0 GENERAL 1.1 Work included in this Section includes trenching and backfilling for underground pipelines and related structures only. 1.2 Reference Specifications

More information

CITY STANDARD DETAILS FOR CITY OF JACKSONVILLE FLORIDA DEPARTMENT OF PUBLIC WORKS

CITY STANDARD DETAILS FOR CITY OF JACKSONVILLE FLORIDA DEPARTMENT OF PUBLIC WORKS CITY STANDARD DETAILS FOR CITY OF JACKSONVILLE FLORIDA DEPARTMENT OF PUBLIC WORKS COMPLETE THROUGH REVISION #18 April 2009 CITY STANDARD DETAILS REVISIONS Revision No. Revision Date Effective Date 2 August

More information

CITY OF NAPERVILLE, ILLINOIS TREE REMOVAL PERMIT APPLICATION LOCATION: PROJECT CONTACT: VARIETY NUMBER SIZE CONDITION

CITY OF NAPERVILLE, ILLINOIS TREE REMOVAL PERMIT APPLICATION LOCATION: PROJECT CONTACT: VARIETY NUMBER SIZE CONDITION CITY OF NAPERVILLE, ILLINOIS TREE REMOVAL PERMIT APPLICATION NAME ADDRESS _ CITY ZIP PHONE Residence Business Fax Please indicate all trees to be removed: DATE PROJECT: LOCATION: PROJECT CONTACT: VARIETY

More information

CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application

CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application CITY OF HOMESTEAD Utility Rights-of-Way Use Permit Application Good for 90 days from the Date Issued This permit is only required if the work location is owned or controlled by the City of Homestead and

More information

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following: SEGMENTAL BLOCK RETAINING WALLS PART 1 - GENERAL 1.01 SECTION INCLUDES Segmental Block Retaining Walls 1.02 DESCRIPTION OF WORK Constructing segmental block retaining walls. 1.03 SUBMITTALS Comply with

More information

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION

DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION DESIGNING FOR MANDATORY TREE PROTECTION DURING CONSTRUC TION City of Santa Monica Community Maintenance Department Public Landscape Division 2600 Ocean Park Blvd. Santa Moni ca, CA 90405 (310) 458-8974

More information

ADDENDUM NO. 1 APRIL 24, 2017

ADDENDUM NO. 1 APRIL 24, 2017 DERBY DESTINATION DEVELOPMENT PUBLIC PROJECT NO. 1 EAST FREEDOM STREET PUBLIC PROJECT NO. 2 WEST FREEDOM STREET PUBLIC PROJECT NO. 3 WATERLINE IMPROVEMENTS PUBLIC PROJECT NO. 4 SANITARY SEWER IMPROVEMENTS

More information

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX

City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV (775) (775) FAX City of Reno Public Works 1 E. 1 st Street, 8 th Floor P.O. Box 1900 Reno, NV 89505 (775) 334-3304 (775) 334-1226 FAX SPECIAL CONDITIONS OF APPROVAL FOR Permit # EAE14-00XXX Applicant: Job Description:

More information

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum Page 1 of 6 DESIGN STANDARDS FOR: MEASUREMENT AND PAYMENT Where bids are utilities for construction, repair or alteration for Public Work park projects, the following bid item descriptions and units of

More information

JEFFERSON COUNTY STORM WATER MANAGEMENT

JEFFERSON COUNTY STORM WATER MANAGEMENT JEFFERSON COUNTY STORM WATER MANAGEMENT B-210 Courthouse, Birmingham, Alabama 35203 Telephone: (205) 325-8741 Erosion and Sedimentation Control Measures for Commercial Projects (Plans Requirements) -All

More information

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES Construction Best Management Practices Handbook www.montereysea.org BEST MANAGEMENT PRACTICES 26 www.montereysea.org Construction Best Management Practices Handbook VEHICLE TRACKING AND DUST CONTROL IN

More information

SITE DESIGN ENGINEER'S STATEMENT:

SITE DESIGN ENGINEER'S STATEMENT: SITE DESIGN ENGINEER'S STATEMENT: THESE DETAILED PLANS AND SPECIFICATIONS WERE PREPARED UNDER MY DIRECTION AND SUPERVISION. SAID PLANS AND SPECIFICATIONS HAVE BEEN PREPARED ACCORDING TO THE CRITERIA ESTABLISHED

More information

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

SECTION IV. PIPELINE EXCAVATION AND BACKFILL SECTION IV. PIPELINE EXCAVATION AND BACKFILL A. Description of Work B. Surface Types C. Backfill D. Surface Restoration A. DESCRIPTION OF WORK 1. Extent: Excavation of trenches for pipelines shall include

More information

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703)

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703) Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA 20155 Phone (703) 754-6750 Work Request # UNDERGROUND DISTRIBUTION FACILITIES AGREEMENT (FOR COMMERCIAL CUSTOMER) Developer/Builder/Owner

More information

SECTION A1 EXCAVATION AND BACKFILL GENERAL

SECTION A1 EXCAVATION AND BACKFILL GENERAL SECTION A1 EXCAVATION AND BACKFILL GENERAL The work under this section shall include all excavation to such width and depth as shown on the drawings, specified herein, or ordered by the Engineer. Such

More information

GILA RIVER INDIAN COMMUNITY GEORGE WEBB VILLAGE SUBDIVISION INFRASTRUCTURE IFB # ADDENDUM NO. 2 September 14, 2011

GILA RIVER INDIAN COMMUNITY GEORGE WEBB VILLAGE SUBDIVISION INFRASTRUCTURE IFB # ADDENDUM NO. 2 September 14, 2011 TO: All Bidders From: Gila River Indian Community, Property and Supply Department The following addendum to the George Webb Village Subdivision Infrastructure construction project is made. Acknowledgment

More information

CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION 7.1 TREE PROTECTION AREAS

CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION 7.1 TREE PROTECTION AREAS CHAPTER 7: TREE PROTECTION DURING CONSTRUCTION Urban trees need to be protected from damage to maximize their health, safety, benefits and functionality. Mature, young and newly transplanted trees need

More information

STANDARD TECHNICAL SPECIFICATIONS

STANDARD TECHNICAL SPECIFICATIONS CITY OF TARPON SPRINGS, FLORIDA STANDARD TECHNICAL SPECIFICATIONS FEBRUARY 2011 PUBLISHED BY: DEVELOPMENT SERVICES DEPARTMENT TABLE OF CONTENTS GENERAL CONSTRUCTION OPERATIONS...4 ACRONYMS & ABBREVIATIONS...5

More information

CITY OF ATLANTIC BEACH BID NUMBER PURCHASING DEPARTMENT 800 SEMINOLE ROAD ATLANTIC BEACH, FLORIDA (904)

CITY OF ATLANTIC BEACH BID NUMBER PURCHASING DEPARTMENT 800 SEMINOLE ROAD ATLANTIC BEACH, FLORIDA (904) CITY OF ATLANTIC BEACH BID NUMBER 1314-08 PURCHASING DEPARTMENT 800 SEMINOLE ROAD ATLANTIC BEACH, FLORIDA 32233 (904) 247-5880 REQUEST FOR BID CONTRACT - CONCRETE REPAIRS FOR THE PUBLIC WORKS/UTILITIES

More information

PERMEABLE INTERLOCKING PAVERS

PERMEABLE INTERLOCKING PAVERS PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement

More information

Storm Drain Inlet Protection for Construction Sites (1060)

Storm Drain Inlet Protection for Construction Sites (1060) Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain

More information

SECTION CONSTRUCTION SERVICES

SECTION CONSTRUCTION SERVICES SECTION 01100 CONSTRUCTION SERVICES PART 1 GENERAL 1.01 - Section Includes A. Mobilization. B. Construction Surveys. C. Record Documents. 1.02 Description Of Work A. Mobilization: includes the preparatory

More information

PART 1 GENERAL REQUIREMENTS

PART 1 GENERAL REQUIREMENTS PART 1 GENERAL REQUIREMENTS Contract Closeout Plan 110 Arrow diagram for project close-out...3 Erosion Control 121 Straw bale barrier... 5 122 Silt fence... 7 123 Diversion dike... 9 124 Inlet protection...

More information

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL 901.1 DESCRIPTION Install, maintain and remove temporary erosion and pollution control devices as required during the construction of the project. BID

More information

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements SECTION 3 DRAINAGE 3-1 General All Drainage plans for proposed development shall be prepared by a Professional Engineer registered in Virginia, except as noted below. Further, their seal and signature

More information

Attachment D-1: Civil/Structural Scope of Work

Attachment D-1: Civil/Structural Scope of Work Attachment D-1: Civil/Structural Scope of Work Project: Location: Targa Sound Renewable Fuels Project Tacoma, WA Prepared by: NORWEST ENGINEERING Consulting Engineers 4110 N.E. 122 nd Avenue, Portland,

More information

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES PART 1 GENERAL 1.01 SCOPE A. This work shall consist of the underground construction of a pipeline across the state right-ofway, or other facility as indicated on the plans and as

More information

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS) Definitions SWPPP: Storm Water Pollution Prevention Plan BMP: Best Management Practice(s) to control pollution IDNR: Iowa Department

More information

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual Prepared by: Mike Shaw Stormwater Program Manager City of Mountlake Terrace January 2010 Section I General Information This

More information

SPECIAL NOTES FOR CONTRACT. Bidding Requirements and Conditions. Specifications Governing this Project

SPECIAL NOTES FOR CONTRACT. Bidding Requirements and Conditions. Specifications Governing this Project RES. NO. PROPOSAL FOR THE COMPLETION OF 2015-28 TO THE SATISFACTION OF THE BUTLER COUNTY COMMISSIONERS AND THE COUNTY ENGINEER: SAID WORK CONSISTING OF TYLERSVILLE ROAD IMPROVEMENTS, PHASE I TO THE COUNTY

More information

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT Adopted by City Council: May 21, 2007 X:\General Eng\DESIGN STANDARDS\Engineering Design Standards

More information

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL CHAPTER 3 EROSION AND SEDIMENT CONTROL Section 300 General Summary All projects constructed within the Town of Essex shall be constructed in strict accordance with

More information

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN

CHECKLIST FOR STREETS, INLETS, AND STORM SEWER DESIGN CHECKLIST FOR STREETS, INLETS, I. STREET CLASSIFICATION AND DESIGN CRITERIA A. Determine drainage classification for the roadway section using Table 7-1 or Table 7-2. B. Determine the allowable flow depth

More information

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS 8.1 INTRODUCTION To minimize the detrimental effects of erosion and sedimentation, Henrico County requires that those individuals responsible for

More information

I. General Information. A. Project Team & Contacts: Role Company Name Phone City of Johnson City Jeff Owner Water & Sewer Harmon, PE Department

I. General Information. A. Project Team & Contacts: Role Company Name Phone  City of Johnson City Jeff Owner Water & Sewer Harmon, PE Department I. General Information Civil Engineering Surveying Environmental Consulting Tysinger, Hampton & Partners, Inc. OPTIONAL PRE-BID MEETING MINUTES Austin Springs Road Water Line Replacement Project ITB #6190

More information

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017 SECTION 02630 - STORM DRAINAGE PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

NORTH OF THE PROPERTY ON BOYETTE ROAD, PUBLISHED ELEVATION 92.29' (NAVD88).

NORTH OF THE PROPERTY ON BOYETTE ROAD, PUBLISHED ELEVATION 92.29' (NAVD88). "REUSE OF THIS DOCUMENT: THE IDEAS & DESIGNS INCORPORATED INTO THIS DRAWING ARE PROVIDED AS A PROFESSIONAL SERVICE TO THIS CLIENT AND ARE THE PROPERTY OF MPH THESE IDEAS & DESIGNS ARE NOT TO BE USED FOR

More information

Addendum No. 1 Page 1 of 2

Addendum No. 1 Page 1 of 2 Addendum No. 1 Page 1 of 2 DATE: March 14, 2016 Joliet Junior College 1215 Houbolt Road Joliet, IL 60431 TO: Prospective Bidders SUBJECT: Addendum No. 1 PROJECT NAME: Parking Lot S7 Improvements JJC PROJECT

More information

STATE AID GUIDE FOR: Updated: December 16, 2005

STATE AID GUIDE FOR: Updated: December 16, 2005 STATE AID GUIDE FOR: Updated: December 16, 2005 1. AFTER THE FACT RIGHT OF WAY DEPARTMENT OF MINNESOTA TRANSPORTATION 2. MISCELLANEOUS AFTER THE FACT Traffic Signals, Lighting, Retaining Walls, Sidewalk,

More information

Erosion & Sedimentation Control Policy

Erosion & Sedimentation Control Policy Issue Date 10/22/2010 Page 1 of 8 Erosion & Sedimentation Control Policy Introduction: Soil erosion is the removal of soil by water, wind, ice or gravity and sediment deposition occurs when the rate of

More information

CITY OF FARGO SPECIFICATIONS EROSION AND SEDIMENT CONTROL

CITY OF FARGO SPECIFICATIONS EROSION AND SEDIMENT CONTROL EROSION AND SEDIMENT CONTROL PART 1 DESCRIPTION OF WORK The work to be completed under this section of the Specifications and the accompanying plans shall include all labor, materials, and equipment necessary

More information

Riverside County Transportation Department Summary of Bids

Riverside County Transportation Department Summary of Bids 1 COUNTY'S ESTIMATE Skanska USA Civil West CA Dist. Riverside, CA 92509 ITEM NO. ITEM CODE CONTRACT ITEM UNITS QUANTITY UNIT PRICE ENG ESTIMATE BID UNIT PRICE BID ESTIMATE 1 066100 DUST CONTROL LS 1 3,000.00

More information

ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number)

ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number) EXHIBIT A CONTRACTOR'S COMPENSATION SCHEDULE FOR ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / 50103-000-4150 (Budget Account Number) ITEM NO. P-S-F DESCRIPTION QTY

More information

SECTION EROSION AND SEDIMENTATION CONTROLS

SECTION EROSION AND SEDIMENTATION CONTROLS SECTION 312500 EROSION AND SEDIMENTATION CONTROLS PART 1 - GENERAL 1.01 GENERAL PROVISIONS A. Attention is directed to the CONTRACT AND GENERAL CONDITIONS and all Sections within DIVISION 01 - GENERAL

More information

C. Foundation stabilization for pipe and utility structures.

C. Foundation stabilization for pipe and utility structures. PART 1 - GENERAL 1.1 SECTION INCLUDES A. Excavating, backfilling, and compacting for utilities, including pipe, structures, and appurtenances. B. Control of water in trenches. C. Foundation stabilization

More information

Municipality of Waterville Public Sidewalk Repair Policy

Municipality of Waterville Public Sidewalk Repair Policy Municipality of Waterville Public Sidewalk Repair Policy Purpose - The purpose of this policy is to protect the public health, safety and welfare of the citizens and inhabitants of the Municipality by

More information

HILLSBOROUGH COUNTY UTILITY ACCOMMODATION GUIDE AND RIGHTS-OF-WAY USE PROCEDURES MANUAL APPROVED

HILLSBOROUGH COUNTY UTILITY ACCOMMODATION GUIDE AND RIGHTS-OF-WAY USE PROCEDURES MANUAL APPROVED HILLSBOROUGH COUNTY UTILITY ACCOMMODATION GUIDE AND RIGHTS-OF-WAY USE PROCEDURES MANUAL APPROVED APPROVED: Michael Williams, PE County Engineer Date Effective Date October 2017 Page i Utility Accommodation

More information

BUREAU Joe Iuviene, AIA January 20, 2017

BUREAU Joe Iuviene, AIA January 20, 2017 architectural BUREAU Joe Iuviene, AIA January 20, 2017 Alterations & Additions NEW TOWN HALL for TOWN OF AUSTERLITZ 816 State Route 203, Spencertown, New York 12165 ADDENDUM NO. 1 This addendum amends

More information

NATURAL RESOURCES PERMIT APPLICATION FOR NEW SINGLE FAMILY/DUPLEX CONSTRUCTION

NATURAL RESOURCES PERMIT APPLICATION FOR NEW SINGLE FAMILY/DUPLEX CONSTRUCTION NATURAL RESOURCES PERMIT APPLICATION FOR NEW SINGLE FAMILY/DUPLEX CONSTRUCTION The enclosed documentation contains information requiring completion prior to applying for a building permit to construct

More information

***************************************************************************************************************

*************************************************************************************************************** 02720 STORM DRAINAGE SYSTEM *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 33 40 00. ***************************************************************************************************************

More information

Sunnyside Valley Irrigation District Enclosed Lateral Improvements Projects Contract : Regions 011, 13 & 014

Sunnyside Valley Irrigation District Enclosed Lateral Improvements Projects Contract : Regions 011, 13 & 014 Sunnyside Valley Irrigation District Addendum No. 1 Enclosed Lateral Improvements Projects 2010-2011 Issued: 8/30/2010 Contract 10-003: Regions 011, 013 & 014 Page 1 of 7 Sunnyside Valley Irrigation District

More information

E. STORMWATER MANAGEMENT

E. STORMWATER MANAGEMENT E. STORMWATER MANAGEMENT 1. Existing Conditions The Project Site is located within the Lower Hudson Watershed. According to the New York State Department of Environmental Conservation (NYSDEC), Lower Hudson

More information

CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2

CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2 CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2 7.1. GENERAL.... 2 7.1.1. Inspection Restriction Dates.... 2 7.1.2. Complete Improvements.... 2 7.1.3. Public Improvements.... 2 7.1.4. Warranty

More information

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT SECTION 32 14 13 19 PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Permeable Articulating

More information

DRAFT TECHNICAL SPECIFICATIONS FOR

DRAFT TECHNICAL SPECIFICATIONS FOR DRAFT TECHNICAL SPECIFICATIONS FOR DETROIT RIVER AOC STONY ISLAND HABITAT RESTORATION PROJECT THE DETROIT RIVER, WAYNE COUNTY, MICHIGAN FOR INFORMATION JANUARY, 2016 Prepared for: FRIENDS OF THE DETROIT

More information

Specifications for SEEDING FOR EROSION CONTROL

Specifications for SEEDING FOR EROSION CONTROL Specifications for SEEDING FOR EROSION CONTROL 1. GENERAL 1.1. SCOPE Provide all supervision, labor, materials, tools, equipment and related items required for preparing ground, providing for sowing of

More information

Stormwater Quality Extended Detention Basin Operation and Maintenance (O&M) Manual. for: Located at: Prepared for: Prepared by:

Stormwater Quality Extended Detention Basin Operation and Maintenance (O&M) Manual. for: Located at: Prepared for: Prepared by: Stormwater Quality Extended Detention Basin Operation and Maintenance (O&M) Manual for: Insert Development Name Located at: Insert Address Prepared for: Insert Property Owner Name, Address, and Phone Number

More information

Sections:

Sections: DIVISION 15: NATURAL RESOURCES REGULATIONS CHAPTER 9-1500 NATURAL RESOURCES REGULATIONS: INTENT AND ORGANIZATION 9-1500.1 Title and Intent. 9-1500.2 Organization. 9-1500.1 TFlZE AND INTENT. Division 15

More information

Storm. Section. B. General Design and Drawing Standards Design

Storm. Section. B. General Design and Drawing Standards Design Section Storm 5 General Plans for the existing stormwater system are maintained in digital and printed form by the City. Copies may be obtained from the Utility Division of the Public Works Department.

More information

ANNE ARUNDEL COUNTY Department of Public Works DATE: 01/25/2017 FROM: Rich Osborn, P.E., Prof.L.S., Project Manager, Bureau of Engineering SUBJECT: Minutes for Pre-Bid Meeting January 19, 2017 South Shore

More information

Garage Construction. Permit Guide. Development Center. General Information. Zoning Ordinance Requirements. Building Code Requirements

Garage Construction. Permit Guide. Development Center. General Information. Zoning Ordinance Requirements. Building Code Requirements General Information Site Card. Before starting construction, post the site card (issued by the City) in a front window visible from the street. Miss Dig. Before you dig, call Miss Dig at 800.482.7171 This

More information

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) PART 1 - GENERAL TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING) 1.01 SECTION INCLUDES A. Trenchless Installation of Carrier Pipe with Casing Pipe B. Trenchless Installation of Carrier Pipe without

More information

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General DESIGN STANDARDS Division 02 Existing Conditions- Site Work General I. This Division includes: A. Demolition B. Clearing and Grubbing C. Excavation, Backfill and Compaction D. Pavement Base E. Paving and

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular

More information

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections.

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections. Village of Vernon Hills Community Development Department 290 Evergreen Drive, Vernon Hills, IL 60061 Phone 847-367-3704 - Fax 847-367-2541 - http:// www.vernonhills.org FENCES This hand out is for REFERENCE

More information

HAWTHORNE AND THAD WATER & WASTEWATER IMPROVEMENTS ITB #124D 16F CITY OF IRVING ADDENDUM # 1 MAY 10, 2016

HAWTHORNE AND THAD WATER & WASTEWATER IMPROVEMENTS ITB #124D 16F CITY OF IRVING ADDENDUM # 1 MAY 10, 2016 HAWTHORNE AND THAD WATER & WASTEWATER IMPROVEMENTS ITB #124D 16F CITY OF IRVING ADDENDUM # 1 MAY 10, 2016 1. THIS ADDENDUM IS HEREBY MADE AS PART OF THIS CONTRACT SPECIFICATION. THIS ADDENDUM IS ISSUED

More information

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1

SECTION STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 402 STORM DRAINAGE DESIGN CRITERIA 400-1 CITY OF THORNTON Standards and Specifications Revised: October 2012 SECTION 400 - STORM DRAINAGE DESIGN, GRADING, AND WATER QUALITY TECHNICAL CRITERIA TABLE OF CONTENTS PAGE 401 GENERAL PROVISIONS 400-1

More information

City of North Miami Beach, Florida COMMUNITY DEVELOPMENT DEPARTMENT

City of North Miami Beach, Florida COMMUNITY DEVELOPMENT DEPARTMENT City of North Miami Beach, Florida COMMUNITY DEVELOPMENT DEPARTMENT TO: Planning and Zoning Board FROM: Carlos M. Rivero, City Planner DATE: August 10, 2015 RE: Storage Facility P&Z ITEM # 15-010 OWNER

More information

Task Order Authorization

Task Order Authorization Task Order Authorization Task Order Number: 6 Task Order Name: 2017 Small Drainage Program Hourly Rate: See attached Exhibit B Budget Not To Exceed: $79,795.00 This Task Order pertains to the On-Call Agreement

More information

Richland County Department of Public Works Engineering (Land Development) Division

Richland County Department of Public Works Engineering (Land Development) Division Richland County Department of Public Works Engineering (Land Development) Division Commercial Projects What is a Commercial Project? Projects that are not related to residential single family homes and/or

More information

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION 820-1 SCOPE OF WORK: SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION a. Furnish all labor, materials, equipment, and incidentals required for demolition and/or removal and disposal of existing

More information

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Appendix A RFP No. 894-2014 Page 1 of 1 Template Version: SrC120131129 - Consulting Services RFP APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Revision: 2014-09-22 DEFINITION OF

More information

Curlex High Velocity EROSION CONTROL BLANKET SPECIFICATION

Curlex High Velocity EROSION CONTROL BLANKET SPECIFICATION Curlex High Velocity EROSION CONTROL BLANKET SPECIFICATION PART I - GENERAL 1.01 Summary A. The erosion control blanket contains excelsior wood fiber for the purpose of erosion control and revegetation

More information

Curlex II EROSION CONTROL BLANKET SPECIFICATION

Curlex II EROSION CONTROL BLANKET SPECIFICATION Curlex II EROSION CONTROL BLANKET SPECIFICATION PART I - GENERAL 1.01 Summary A. The erosion control blanket contains excelsior wood fiber for the purpose of erosion control and revegetation as described

More information

SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS

SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Building Inspections SWIMMING POOL PERMIT AND INSPECTION REQUIREMENTS Permit Applications Pool permit applications are now being accepted online at http://etrakit.flower-mound.com/. Starting November 1,

More information

Extended Detention Basin Maintenance Plan for [[== Insert Project Name ==]]

Extended Detention Basin Maintenance Plan for [[== Insert Project Name ==]] Extended Detention Basin Plan for [[== Insert Project Name ==]] [[== Insert Date =]] Project Address and Cross Streets Assessor s Parcel No.: Property Owner: Phone No.: Designated Contact: Phone No.: Extended

More information

PRELIMINARY DEVELOPMENT PLAN INFORMATION

PRELIMINARY DEVELOPMENT PLAN INFORMATION PRELIMINARY DEVELOPMENT PLAN INFORMATION SITE AREA =.0 AC. (,8,8 S.F.) BUILDING FOOTPRINT =,8 S.F. PAVEMENT/PARKING AREA = 0,98 S.F. BUILDING COVERAGE OF SITE = % SITE IMPROVEMENT PLAN NOTES. ALL UTILITY

More information

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL NEW CASTLE CONSERVATION DISTRICT through (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL Office use only: Received by Municipality: Received by

More information

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS SECTION 02620 PART 1 GENERAL 1.1 SCOPE OF WORK A. Furnish all labor, materials, equipment, and incidentals required to install High Density Polyethylene (HDPE) pressure pipe, fittings, and appurtenances

More information

Table of Contents for Guide Specifications

Table of Contents for Guide Specifications Table of Contents for Guide Specifications 01270A Measurement and Payment 01355A Environmental Protection 01356A Storm Water Pollution Prevention Measures 01421 Basic Storm Water Pollution Prevention Plan

More information

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions. SECTION 31 23 33 - TRENCHING, BACKFILLING AND COMPACTION PART 1 - GENERAL 1.1 SCOPE A. This Section specifies the requirements for excavating and backfilling for storm sewer, sanitary sewer, water distribution

More information

Alternative BMPs for Erosion Prevention & Sediment Control

Alternative BMPs for Erosion Prevention & Sediment Control Alternative BMPs for Erosion Prevention & Sediment Control J.P. Johns, PE - Woolpert March 11, 2011 Agenda + Traditional BMPs + Performance Specifications + Erosion Prevention + Sediment Control + The

More information

ROOF BALLAST MATERIALS ARCHITECTURAL CONCRETE PAVING SLABS SRS LEVELING BLOCK SYSTEM INSTALLATION PART GENERAL 1.

ROOF BALLAST MATERIALS ARCHITECTURAL CONCRETE PAVING SLABS SRS LEVELING BLOCK SYSTEM INSTALLATION PART GENERAL 1. 07555 - ROOF BALLAST MATERIALS ARCHITECTURAL CONCRETE PAVING SLABS SRS LEVELING BLOCK SYSTEM INSTALLATION PART 1.00 - GENERAL 1.01 SUMMARY: A. The work of this section consists of furnishing and installing

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

LANDSCAPE RETAINING WALLS

LANDSCAPE RETAINING WALLS SUDAS Standard Specifications Division 9 - Site Work and Landscaping Section 9070 - Landscape Retaining Walls LANDSCAPE RETAINING WALLS PART - GENERAL.0 SECTION INCLUDES A. Modular Block Retaining Walls

More information

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter. STANDARD SPECIFICATIONS SECTION 02420 TUNNELING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for constructing tunnels 48-inch and larger diameter. 1.2 DEFINITIONS A. Carrier Pipe: Sewer

More information

11 Ways to Avoid Storm Water Fines. No Exceptions!

11 Ways to Avoid Storm Water Fines. No Exceptions! 11 Ways to Avoid Storm Water Fines Do not start until you have gone over this with a SWPPP Rep. No Exceptions! 1. Contact Mark Atwood at 801-319-1331 or Jake Pettersson at 801-709-4463. 2. Submit a Notice

More information

Hydrodynamic Separation Product Calculator

Hydrodynamic Separation Product Calculator Hydrodynamic Separation Product Calculator Example Project BMP #1 CDS 2015-4 Project Information Project Name Example Project Option # A Country US State Kentucky City Covington Contact Information First

More information